Cat Power Finance
1
Cat Power Finance
Biogas Projects –
A Lender’s Perspective
Cat Power Finance
2
Agenda:
1. Krabi Waste to Energy
2. Typical biogas commercial structures
3. Key financing questions
4. Bank due diligence – Process and
Requirements
Cat Power Finance
3
Krabi Waste to Energy – CPF’s 1st
project financed biogas project
Cat Power Finance
4
Case Study – Krabi Waste to Energy
CPF signed loan documents with project company May 2014
Palm oil mill that generates 500 cbm/day of POME wastewater
In-ground biodigester reactor
2.4MW gross of Cat engines
Total capital cost: About US$5MM / 150 MTHB
Financing Terms:
56% project financed loan facility US$2.8M / 84 MTHB
8 year term, Thai fixed rate
First priority security position in all project assets and pledge of shares
Assignment of contracts to lender
No corporate guarantee from shareholders
Cat Power Finance
5
Case Study – Krabi Waste to Energy
Project took 3.5 years to reach financial close
CPF was in the deal throughout; providing financial advisory and
supporting developer in stakeholder discussions
Review of key project agreements for project financeability
Review of financial model; finalizing bank base case
Drafting of project finance loan agreements, assignment agreements,
pledge of shares – CPF now has a reference list of documents
Cat Power Finance
6
Case Study – Krabi Waste to Energy
Project Financing Terms Explanation
56% project financed loan facility
US$2.8M / 84MTHB
Lender financed 56% of the total project cost, including soft costs,
civil works, Cat engines, biodigester and scrubber
8 year term, Thai fixed rate Lender offered Thai Baht fixed rate loan over 8 years
First priority security position in all
project assets and pledge of shares
Lenders loan is senior debt; If required, CPF can exercise the
pledge of shares to sell the shares of the project company to
realize value, or to take over shareholder responsibilities
Assignment of contracts to lender
CPF can “step-into” any of the key project agreements to become
the counterparty in that specific agreement
No corporate guarantee from
shareholders
The shareholders are not required to put up corporate guarantees
during the term of the loan; the loan will be paid purely from the
cashflows of the project
Cat Power Finance
7
Typical biogas commercial
structures
Cat Power Finance
8
COMMON KEY CONTRACTUAL
RELATIONSHIPS: TYPE 1
Assets: Biogas Digester, Mill Assets and
Power Plant
Government
Utility
Power Purchase Agreement
Govt approvals,
environmental permits
Power
Plant
O&M Co
Power Plant
O&M
Agreement
EPC Contractor
Project Company
EPC
Contract
Cat Power Finance
9
COMMON KEY CONTRACTUAL
RELATIONSHIPS: TYPE 2
Assets: Biogas Digester and Power Plant
Government
Utility
Power Purchase Agreement
Govt approvals,
environmental permits
Power
Plant
O&M Co
Power Plant
O&M
Agreement
Palm Oil Mill
Host
Agreement
EPC Contractor
Project Company
EPC
Contract
Cat Power Finance
10
COMMON KEY CONTRACTUAL
RELATIONSHIPS: TYPE 3
PowerCo
Government
Utility
Power Purchase Agreement
Assets:
*Power Plant
Biogas
Supply
Agreement
WasteCo
Assets:
Biogas Digester
Govt approvals,
environmental permits
Power
Plant
O&M Co
Power Plant
O&M
Agreement
Palm Oil Mill
Host
Agreement
EPC Contractor
Project Company
*Power plant will include any significant grid interconnect
EPC
Contract
Cat Power Finance
11
Key Financing Questions
Cat Power Finance
12
Key Financing Questions Host /
Feedstock
supplier
Electricity
Tariff
Biodigester
Technology
Generator EPC Contractor Shareholders Operators
Economic
incentive to
supplier
High enough
return to
incentivize
investors?
Operating and
financing
precedents
Reliability Full "Wrap" (Full
performance
guarantee based
on plant output)
Strong balance
sheet
(Development
spend &
equity)
Able to
mobilize
local labor
Alternate
sources of
supply for
project
Known
history of
tariff
Feedstock
matching
technology?
Type of
maintenace
contract
signed
Installation /
Integration
experience
Technical /
Operating
Experience
Technical /
Operating
Experience
Seasonal
variability of
feedstock
Offtaker
motivation /
alternatives
Safety record? Operating
precedents
with biogas
Strong balance
sheet (managing
sub-contractors /
posting bonds)
Development
experience
(Financial,
regulatory etc)
Able to
access
parts and
equipment
supplyAvailability Known
performance
parameters of
technology?
Willing to put up
performance
guarantees on
entire plant
Relationships
with other
parts of project
Cat Power Finance
13
Bank Due Diligence –
Biogas Projects
Cat Power Finance
14
Documents Required & Why
Document Reason
Information Memorandum Summary document for project commercial and economic concept
Financial Model Provides cashflow forecast of project; key in understanding financeability
of project for lender
Shareholder Structure Allows lenders to understand shareholder composition of project
Project Technical Concept
Report
Sets out technical parameters of biodigester
Reference List of projects Builds out developer and EPC contractor experience with technologies
Key Project Agreements Especially required in Project Finance; lenders need to review key project
agreements before execution to ensure project is financeable
Project Closing List Agreement between lender and developer of all documents to be delivered
before first draw; Helps set expectations on timeline and deliverables
Loan Agreement and
Assignment Docs
Form and content to be agreed between lender and developer
Cat Power Finance
15
Documentation – What’s needed at which point
Development
begins
Screening
Project Info Memo
Financial Model
Project Structure
Shareholder Structure
Docs Closing List
Project Schedule
Credit
Approval
Finalized Financial
Model
Updates from A
90% finalized Docs
Closing List
Project Agreements
A B Loan Agmt
Assignment
Agmt
Bonds
Shareholder
Resolutions
Indicative offer Commitment Letter
First Draw on
loan facility
C
Equity
Invested
Cat Power Finance
16
Sample Closing List
Item Ok? Expected
Completion
EPC Contract √
Power Purchase Agreement 31-Dec-14
Insurance Policies √
Wastewater characterization √
BOOT Agreement √
Generation Licence √
Factory Licence √
Public Hearing 30-Sep-14
Construction Permit 15-Aug-14
Key Project Agreements
Permits and Environmental Clearances
Cat Power Finance
17
Sample Closing List Item Ok? Expected
Completion
Secured Rights of Way √
Land Title √
Shareholder resolutions √
SPV resolutions 30-Jun-14
Deed of subordination for shareholder
loans
√
SPV articles of association √
Loan Agreement √
Pledge of Shares √
Assignment of various crts √
Land Use
Corporate Documents
Financing Documents
Cat Power Finance
18