    Planning Tools and Techniques

    Part 2

    1

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    2/39

    2

    Planning Tools and Techniques

    Planning tools

    Network diagrams

    Critical path method

    PERT analysis

    Gantt charts

    Resource histogram

    Containment of risk

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    3/39

    3

    PERT analysis

    PERT stands for:Program Evaluation & Review Technique

    A way of modelling uncertainty when scheduling

    If used properly will lead to more stable schedules

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    4/39

    4

    PERT analysis

    Expected timecalculated from 3 estimates

    for the duration of each activity

    optimistic time(o)if things go well

    most likely time(m)this is usually the original estimate

    pessimistic time(p)if it can go wrong, it will...

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    5/39

    5

    PERT analysis

    Based on distribution, the expected time teis calculated as:

    te

    = [o + 4m + p] / 6

    Our activity B has estimate of 4. Let us say:

    o = 3, m = 4, p = 11

    te = [3 + 16 + 11] / 6

    Expected time te is 5, longer than the most likely time

    This could change the critical path in the network diagram

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    6/39

    6

    PERT analysis

    try out the tasks past exam questions

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    7/397

    Gantt charts

    Devised by Henry Gantt (early 1900s)

    Block representation of tasks

    Length of task bar proportional to duration

    Each start/end time represented by task bar Graphical representation of project

    Can translate network diagram into Gantt chart

    Easy to read

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    8/39

    8

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Can set questions while requesting and reviewing papers

    Might not need two full weeks

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    9/399

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Might be able to start this task early

    ...and finish early

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    10/3910

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Might not haveto start this task straight away

    Might want to delaywhile doing other things

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    11/39

    11

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Might be able to set questions in the middle of the time slot

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    12/39

    12

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Questionnaire must be prepared before it can be issued

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    13/39

    13

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Questionnaire must be issued & returned before results can be analysed

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    14/39

    14

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Analyse data before interviewing subjects

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    15/39

    15

    Gantt charts

    Time line:week1

    week2

    week3

    week4

    week5

    week6

    week7

    week8

    week9

    week10

    Activities:

    Request Jones paper

    Request Smith paper

    Review Jones paper

    review Smith paper

    Interview subjects

    set q's for questionnaire

    issue questionnaire

    Analyse data from

    q'naire

    have report proof read

    Write report

    Submit report

    Interview subjects before writing report

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    16/39

    16

    Gantt charts in MS Project

    ID Task Name Duration

    1 Task 1 3 days

    2 Task 2 2 days

    3 Task 3 5 days

    4 Task 4 3 days

    5 Task 5 6 days

    6 Task 6 3 days

    7 Task 7 4 days

    8 Task 8 1 day

    T F S S M T W T F S S M T W T F

    12 Mar '00 19 Mar '00

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    17/39

    17

    Gantt charts

    In their basic form Gantt charts: Do not explicitly show logical dependencies

    Do not optimise resources and costs Do not display current progress

    But...They are simple to read

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    18/39

    1818

    Gantt charts in MS Project

    ID Task Name

    1 Activity 1

    2 task 1.1

    3 task 1.2

    4 task 1.3

    5 Activity 2

    6 task 2.1

    7 task 2.2

    8 task 2.3

    9 task 2.4

    10 deliver

    AB

    AB[50%],CD[50%]

    EF

    AB

    CD

    AB,CD

    EF

    20/03

    W T F S S M T W T F S S M T W T F

    12 Mar '00 19 Mar '00

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    19/39

    19

    Gantt charts

    In more advanced forms Gantt charts:

    Soon become cluttered

    Become more difficult to read

    Become more difficult to update

    Still cannot easily show all task dependencies

    Require computer software to keep up to date

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    20/39

    20

    Gantt charts

    try out the tasks including past exam papers

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    21/39

    21

    Resource histogram

    Identifies resource requirements over time Helps to identify peak resource requirements

    Helps to identify unnecessary peaks and troughs(resource smoothing: keep within limits)

    Commonly used to analyse staff resource levels

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    22/39

    22

    Resource histogram

    02

    4

    6

    8

    10

    1214

    16

    18

    20

    1 2 3 4 5 6 7 8 9 10

    Week number

    Staff required

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    23/39

    23

    Resource histogram

    upper limit of

    staff resources

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    24/39

    24

    Resource histogram

    upper limit of

    staff resources

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    25/39

    25

    Staff resources

    try out the tasks including past exam papers

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    26/39

    26

    Risk: Isolate the Baseline Plan

    Risksmust be associated with a planbefore

    they can be handled

    As risks could prevent the achievement of

    objectives, plans for achieving objectives must

    be in place before risks can be considered

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    27/39

    27

    Risk revisited

    Identify: Whatare the potential risks?

    Assess: What is the impactof each risk? What is the likelihoodof the risk occurring?

    How can the risk be preventedoridentified early?

    What needs to be doneif the risk does occur? Allocate:

    To whom can I assignthe risk?

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    28/39

    28

    Containment

    A new MS Access/Visual Basic system

    for a retail company

    Duration:requirements capture: 2 weeks

    development: 8 weeksacceptance testing: 2 weeks

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    29/39

    29

    Sequence of Activities

    Requirements

    Capture

    Development Acceptance

    2 Weeks 8 Weeks 2 Weeks

    Project will last 12 weeks (i.e. 2 + 8 + 2)

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    30/39

    30

    What is the risk?

    There is an 90% chancethat this length of time is insufficient

    because the MS Access specialist may be required to support a

    project of higher priority.

    If this were to happen, the 8 weeks scheduled for development

    would then extend to 10 weeks

    i.e. a 2 week delay

    with 7 person-weeksfurther effort

    Consider a containment action

    investigate whether this is a cost-effective solution

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    31/39

    31

    Including the element of risk

    RC Development Acceptance

    Risk: 2 week over-run

    2 Weeks 8 Weeks (10%) 2 Weeks

    90%

    10%

    2 Weeks

    7 Person Weeks

    Project will last 12 weeks (10%) or14 weeks (90%)

    10 Weeks (90%)

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    32/39

    32

    Containment Calculation

    Expected value of additional duration

    = 0.9 * 2

    = 1.8 weeks

    This evaluates the 90% chanceof a 2 week delay

    Expected value of additional effort

    = 0.9 * 7

    = 6.3 person-weeksThis evaluates the 90% chanceof a further7 person-weeks

    This calculation is without a containment action

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    33/39

    33

    Containment

    A 3-week training course in parallel(i.e. 1 extra week) with

    the requirements capture would reduce the risk to 25%

    with an additional 2 person-weekseffort

    Draw a diagram to show the containment actionand

    recalculate the revised impact on effort and duration

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    34/39

    34

    Containing the risk

    RC Development Acceptance

    2 Weeks 2 Weeks

    25%

    75%

    2 Weeks

    7 Person-weeks

    Course

    3 Week course1 extraWeek

    2 Person-weeks

    Risk: 2 week over-run

    Project will last 13 weeks (75%) or15 weeks (25%)

    8 Weeks (75%)10 Weeks (25%)

    Using a training course as

    a containment action

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    35/39

    3535

    Containment Calculation

    Expected value of additional duration

    = 1 + (0.25 * 2)

    = 1.5 weeks

    This evaluates the extra weekon the course, plus the reducedrisk of 25%of a 2 week delay

    Expected value of additional effort

    = 2 + (0.25 * 7)

    = 3.75 person-weeks

    This evaluates extra 2 person-weekson the course, plus the

    reduced risk of 25%of a further7 person-weeks

    This calculation includes a containment action

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    36/39

    3636

    Dealing with risk

    Would you book the course?

    What other factors need to be considered?

    How would the diagram look if the course is beforeRequirements Capture?

    is betweenRequirements Capture and Development?

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    37/39

    3737

    Risk analysis

    try out the tasks - including past exam papers

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    38/39

    38

  • 7/30/2019 CC5001 Planning Tools Part 2 2012

    39/39

    Further reading

    Bentley C (1997) PRINCE 2: A Practical Handbook Oxford:

    Butterworth-Heinemann

    Brooks F. (1995) The Mythical Man-Month (Anniversary Edition),

    Harlow: Addison-Wesley Burke R (1999). Project Management: Planning and Control

    Techniques, Chichester: Wiley

    Central Computer & Telecommunications Agency (1997)

    PRINCE 2: An Outline, London: The Stationery Office

    Field M & Keller L (1998) Project Management, Oxford:International Thomson Business Press