cesrta e-cloud activities (jan. 2009)
DESCRIPTION
CesrTA E-cloud Activities (Jan. 2009). J.W. Flanagan, KEK. Organization. CesrTA meeting slides from 2009.2.11 WebEx, provided by Mark Palmer Have tried to attribute original authors correctly. Supplemental slides on some contributions from KEK. M. Palmer (CesrTA Mtg.). - PowerPoint PPT PresentationTRANSCRIPT
CesrTA E-cloud Activities(Jan. 2009)
J.W. Flanagan, KEK
Organization
• CesrTA meeting slides from 2009.2.11 WebEx, provided by Mark Palmer– Have tried to attribute original authors correctly.
• Supplemental slides on some contributions from KEK
February 11, 2009 CesrTA-KEK Update 3
CesrTA Run & Down Recap• Completed experimental run 2/2/2009
– Low emittance correction in 2.085 GeV baseline optics– X-ray Beam Size Monitor (xBSM) commissioning– EC Measurements
• RFA & TE wave measurements• Dynamics
– General instrumentation/feedback tests/commissioning• 13 visitors
– LET - J. Jones, A. Wolski – xBSM – J. Flanagan, H. Sakai– EC – S. De Santis, R. Holtzapple, K. Shibata, L. Wang– Feedback – D. Teytelman, M. Tobiyama– CLIC – H. Schmickler– Instrumentation – A. DellaPenna, I. Pinayev
• 2nd upgrade down is underway…– Installation of PEP-II experimental hardware– Installation of photon stop chamber for 5GeV operation of the CesrTA L0 wiggler straight– Replacement of SRF cavity that failed during summer 2008– Installation of xBSM beam line front end for electron beam– Continue with instrumentation upgrade for 4ns bunch train operation– Contingency item: Repair of 15BW dipole coils
M. Palmer (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 4
Optics and LET• Low emittance 2.085 GeV optics loaded and corrected
– Correction methods tested– Beam-based alignment measurements– Coupling and dispersion bumps created for tuning
• Emittance measurements begun…– Touschek lifetime measurements initially used to characterize
beam size– xBSM measurements as detector and optics were characterized
• Ongoing program of magnet alignment to improve emittance– Alignment work continued throughout the run– 2 anomalous locations in the ring have been identified which
are being scrutinized.
D. Rubin (CesrTA Mtg)
February 11, 2009 CesrTA-KEK Update 5
Measured energy acceptance = 0.7% v ~ 32pmFrom xBSM v ~ 155 m v ~ 38pmAppear to be within a factor of 2 of the 20pm target
First Detailed Optics Correction Touschek Study xBSM Measurement (Preliminary)
Wolski
A. Wolski (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 6
xBSM Snapshots (Preliminary)
• Scan of coupling knob• Coded aperture measurements• Smallest recorded size:
~15 m (but further calibrationwork needed)
Simulations
Measurement
Fresnel Zone Plate
CodedAperture
<20mbeam size
J. Alexander (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 7
EC Data-Simulation Updates• Simulations of tune shifts in POSINST at Cornell and LBNL, using a new option in
POSINST for offseting the bunches, have shown that the tune shifts of a single bunch are different if the whole train is oscillating coherently, than if just the single bunch is oscillating. – Horizontal tune shifts in a dipole are much smaller when the whole train is oscillating
coherently. This is particularly relevant for the tune shift measurements at CesrTA, since we kick the whole train coherently to do the measurement.
– Tune shifts calculated for a coherently oscillating beam give better agreement with measurements: see following three slides.
• January run– Studies of systematic effects in the tune shift measurements were carried out.– Measurements of tune shift vs. current for long trains (10, 20, 45 and 116 and 145
bunches) were carried out (evidence of instability developing at the end of the 116 and 145 bunch trains)
– RFA and TE wave measurements to characterize EC density in drifts, dipoles and wigglers
– Work on comparisons between RFA and TE wave measurements as well as systematics checks for both
G. Dougan(CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 8
10 Bunch Train with Trailing Witness Bunch(es) Data-POSINST Comparison (Preliminary)
Positron Beam
Blue Vertical QRed Horizontal QSquares SimulationCircles Data
G. Dougan(CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 9
Electron Beam
10 Bunch Train with Trailing Witness Bunch(es) Data-POSINST Comparison (Preliminary)
Blue Vertical QRed Horizontal QSquares SimulationCircles Data
G. Dougan (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 10
Drift vs Dipole Contributions• Comparison of drift (red) and dipole (blue)
contributions to tune shifts in each dimension
Horizontal Vertical
G. Dougan (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 11
Positron Beam
45 Bunch Train: Data-POSINST Comparison (Preliminary)
Blue Vertical QRed Horizontal QSquares SimulationCircles Data
G. Dougan (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 12
L0 RFA Data
2/3/08
Wiggler with RFAsand uncoated Cu VC
Wiggler with RFAsand TiN-coated VC
e+
e-
2E Segmented RFA
2W Segmented RFA
G. Dougan (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 13
Electron-Positron Comparisons (1x45 Current Scans)Segmented driftCu wiggler (pole center)
Positrons
Electrons
2W detectordownstream of
wigglers for e+ beam
2E detectordownstream of
wigglers for e- beam
Cu wiggler (pole center)Segmented drift
G. Dougan (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 14
Cu wiggler, pole center
Drift (Cu VC)
Dipole (Al VC)
Long Train Data• 1x145 e+
– 14 ns spacing 79% of ring filled– Multipacting stripe
• Strongly visible in dipole• Weaker in L0 wiggler and
drift regions
G. Dougan (CesrTA Mtg.)
February 11, 2009 CesrTA-KEK Update 15
Plans
15E/W testchamber design for coating tests
Segmented RFA
Shielded Pickups
• CESR layout modifications to be completed by March 1– 4 Experimental areas for EC build-up and mitigation studies
• L0 wiggler straight– Configured for RFA and TE Wave measurements of EC build-up– 4 wiggler comparisons planned (CU-KEK-LBNL-SLAC collab.)
» Cu vacuum chamber (installed)» TiN coated vacuum chamber (installed)» Grooved vacuum chamber ( summer ’09 installation)» Clearing electrode vacuum chamber ( fall ’09 installation)
• L3 straight w/PEP-II chicane and SEY sample station– Sample station tests (CU-FNAL-SLAC collab.)– Grooved chamber tests (CU-SLAC collab.)
• 15E/W – Flexible location for testing chambers with dipole synchrotron radiation– Presently planned comparisons (summer/fall ’09)
» Al vacuum chamber» carbon coated VC (CERN-CU collab.)» Enamel chamber with electrode
(Project X collab.)» TiN-coated Al vacuum chamber
– Detailed beam dynamics studies at ultralow emittance
• Mid-2009 end of program• Characterize instability thresholds• High resolution bunch-by-bunch beam size
measurements to characterize incoherent emittance growth
• Witness bunch studies for flexible control of EC interaction with beam
M. Palmer (CesrTA Mtg.)
KEK Participation in CesrTA• Several members of KEKB are participating in CesrTA:
– K. Ohmi (electron cloud instability dynamics studies and simulation)– M. Tobiyama (instrumentation and feedback)– K. Kanazawa, Y. Suetsugu, K. Shibata (vacuum group: electron cloud
mitigation measures)– J. Flanagan (e-cloud studies and diagnostics, x-ray beam size monitor)– +H. Fukuma, N. Ohuchi, …– Note: Funding provided by US-Japan Cooperation Program (Nichibei)
• ATF members also participating:– H. Sakai (U. Tokyo): X-ray beam size monitor– K. Kubo: Low emittance tuning
– Reverse direction (from Cornell):– Jim Alexander -> KEK for x-ray monitor readout tests– Jim Shanks -> ATF for low emittance tuning
– Others likely not listed
Bunch-by-bunch Feedback
• Longitudinal feedback at 4 ns successfully demonstrated in January 2009 by Dmitry Teytelman (Dimtel, formerly SLAC) using iGp– iGp: Next generation digital feedback system
developed by collaboration of SLAC (J. Fox, D. Teytelman), KEK (M. Tobiyama), INFN (A. Drago), Dimtel
– Transverse feedback also demonstrated.
Mitigation methods:PRELIMINARY results from KEKB
• Techniques also being tested at CesrTA– Clearing Electrode (Suetsugu, Fukuma et al.
design)• Design being worked on for CesrTA
– Grooved Chamber (Pivi et al. design)• Being installed at CesrTA for testing in summer run
Clearing Electrode 1Study on clearing electrode also started for mitigation of electron cloud in magnets.
Clearing electrode and electron detector were installed in wiggler magnet of LER. (placed at the center of pole)
To demonstrate the effect of electrode, the electron density was measured by the electron detector with 7 strips.
Sustainability for high beam current was also tested.
19The 14th KEKB Review on 9-11 February 2009 at KEK
Very thin electrode (0.1 mm, Tungsten) and insulator (0.2 mm, Al2O3) were developed. (Thermal Spray)
7 strips can measure the horizontal spatial distribution of the electron cloud.
440 mm
Stainless steel
Tungsten
Al2O3
40 m
m
Feed-through
Y. Suetsugu et al., NIM-PR-A, 598 (2008)
372
K. Shibata (KEKB Review)
Clearing Electrode 2
20The 14th KEKB Review on 9-11 February 2009 at KEK
Electrode [W] (~ +1 kV)
Collector (7 strips, w5 mm)
Cooling channel
Insulator [Al2O3](t~0.2 mm)
Grid (~ 1 kV)
Vacuum seal by metal O-ring
Cooling Water paths
Shield
MonitorBlock
ElectrodeBlock
2 mm holesR47
Limited by magnet aperture
(w40, l440, t~0.1)
Beam
Cross-section
Test chamber
Wiggler magnet Magnetic filed : 0.77 TEffective length : 346 mmAperture (height) : 110 mm
Electron detector
Clearing electrode
Y. Suetsugu et al., NIM-PR-A, 598 (2008)
372
K. Shibata (KEKB Review)
Clearing Electrode 3Drastic decrease in electron density was demonstrated by applying positive voltage.
21
[8ns]
[6ns]
[4ns]
[16ns]I e [
A]
Velec [V]
Number of electrons was reduced to 1/10 1/100 if applied voltage of clearing electrode was more than 300 V for any bunch spacing.
The 14th KEKB Review on 9-11 February 2009 at KEK
Vr = 1.0 kVB = 0.77 T
I e [A] V el
ec [V
]
Collectors
1 x 10-5
1 x 10-6
1 x 10-7
1 x 10-8
1 x 10-9
1585 bunches(Bs ~ 6 ns)~1600 mA
Collector : #4
Velec = 0
posit
ive
nega
tive
Y. Suetsugu et al., NIM-PR-A, 598 (2008)
372
K. Shibata (KEKB Review)
Clearing Electrode 5Electrode was very effective, but modification of the feed-through connection part is required for high beam current.
Insulation resistivity decreased from 2 M to several 10 k during the trial period due to discharge at feed-through connection part.
Connection part
Improved clearing electrode will be installed this winter.
22
electrodeinsulator
The 14th KEKB Review on 9-11 February 2009 at KEK
Y. Suetsugu
K. Shibata (KEKB Review)
Clearing electrode for CesrTA
Groove Surface 1Effect of groove surface was also studied last autumn. (collaboration with SLAC)
Electrode was replaced by groove surface.Same setup for clearing electrode was utilized.Groove structure was designed and manufactured in SLAC.
TiN~200 nm
Flat surface with TiN coating was also tested for reference.
R47
Beam
[Groove]
[Monitor]
Mag
neti
c field
Y. Suetsugu, ILCDR2008
Groove surface [SUS + TiN]
Flat surface [SUS + TiN]
TiN~200 nm
24The 14th KEKB Review on 9-11 February 2009 at KEK
K. Shibata (KEKB Review)
Groove Surface 2Electrons for groove surface was reduced to 1/5 1/10 the number for flat surface (3 buckets spacing).
1x10-61x10-6
Flat surface Groove surface
25
Y. Suetsugu
Preliminary result
Further R&D will be carried out toward the practical use of groove surface.
The 14th KEKB Review on 9-11 February 2009 at KEK
K. Shibata (KEKB Review)
Mitigation Performance Comparison
~1x1012 e-/m3
~1x101 1
~1x1010
~1x109
Vr = -1 kV(1/1585/3.06)
Ranking of estimated performance in magnet is ;
Clearing electrode is much more effective than groove surface and TiN coating.
Electrode >> TiN+Groove >> TiN(Flat) > Cu(Flat)10 510 23
26
Preliminaryresult
1x10-9
1x10-8
1x10-7
1x10-6
1x10-5
0 2x105 4x105 6x105 8x105 1x106 1.2x106
Ele
ctro
n C
urr
en
t [A
]
Beam Dose [mA Hours]
TiN
Groove+TiN
W electrode(V
elec = 0 V)
W electrode(V
elec > 300 V)
Ib = 1450 - 1550 mAV
r = 1 kV,
1/1585/3.06
The 14th KEKB Review on 9-11 February 2009 at KEK
Electrode and groove surface are very promising, but more studies are required to achieve the practical use of them.
K. Shibata (KEKB Review)
X-ray monitor: Coded Aperture Imaging
Simulated detector response for various beam sizes
Example of beam size measurement at CesrTA (y =~
45 m)
Uniformly Redundant Array (URA) mask being tested at CesrTA
•Technique developed by x-ray astronomers using a mask to modulate incoming light.
•Resulting image must be de-convolved through mask response (including diffraction and spectral width effects) to reconstruct object.
•Open aperture of 50% gives high flux throughput for bunch-by-bunch measurements.
•A heat-sensitive monochromator not needed.
red : datagreen : simulation
preliminary
A*G : system point-spread function ~ function
ˆ O P *G O*(A *G)P=O*A
A : mask or aperture, G: post processing array
ˆ O : reconstructed object, P: picture, O: object,
* : convolution
Coded Aperture.1/28/2009CESR condition same as for the 18um case on previous page
X-ray Beam Size Monitor
• X-ray beam size monitor results:– Beam size = 15-20 um (using both Fresnel Zone
Plate and Coded Aperture Mask)• Corresponds to emittance of ~38 pm.
• Touschek lifetime measurements indicate an emittance of ~30 pm.