change management 11-5-14

50
1 CONTRACT CHANGE MANAGEMENT Mark Adams PE Facility Services Supervisor Nov. 5, 2014

Upload: others

Post on 08-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Change Management 11-5-14

1

CONTRACT CHANGE MANAGEMENT

Mark Adams PEFacility Services SupervisorNov. 5, 2014

Page 2: Change Management 11-5-14

2

Fight

Page 3: Change Management 11-5-14

3

Bigger Fight

Page 4: Change Management 11-5-14

4

Paperwork

Page 5: Change Management 11-5-14

5

Confusion

Page 6: Change Management 11-5-14

6

Stress and Frustration

Page 7: Change Management 11-5-14

7

Where to Go

Page 8: Change Management 11-5-14

8

What to Do

Page 9: Change Management 11-5-14

9

Page 10: Change Management 11-5-14

10

Meet the Experts

Page 11: Change Management 11-5-14

11

-Jim Dreier – Contract Administrator (CA) Facility [email protected] 303-342-2674

-Annette Kimble – Contract Administrator (CA) Infrastructure [email protected] 303-342-4681

-Neal Swift – Project Controls Estimator – AIM [email protected] 303-342-4550

-David Mashburn – Director of Facility Services – AIM [email protected] 303-342-2610

-Glenn Frieler – Director of Infrastructure Management – AIM [email protected] 303-342-2933

-Jen Stein – Project Controls Scheduler – AIM Development [email protected] 303-342-2324

-Mark H Adams – Manager of Facility Services – AIM [email protected] 303-342-2762

Meet The Experts

Page 12: Change Management 11-5-14

12

Alphabet Soup

RFI – Request for Information

CN – Change Notice

CCR – Contractor Change Request

COD – Change Order Directive

TCOD – Task Change Order Directive

CO – Change Order

TCO – Task Change Order

BMS – Business Management Services

Unifier – New DIA Project Management Software produced by

Oracle (Primavera)

Page 13: Change Management 11-5-14

13

Common Contract Types

− Unit Cost− Hard Bid− On-Call Task Order− Mainly used with our Civil Infrastructure Projects

− Lump Sum− Hard Bid− On-Call Task Order− Negotiated/Best Value/Design Build− Mainly used with our Building/Facility Projects

Page 14: Change Management 11-5-14

14

How does a Change get Started?

− RFI’s− Design Initiated Change (CR)− Owner Initiated Change (CR or CN)− Contractor Initiated Change (CCR)− Deficiency or NCR

How Does a Change Order Get Issued?

− Change Notice (CN)− Change Order Directive (COD)

Page 15: Change Management 11-5-14

15

Page 16: Change Management 11-5-14

16

CHANGE MANAGEMENT

Annette Kimble & Jim DreierContract AdministratorsNov. 5, 2014

Page 17: Change Management 11-5-14

17

Page 18: Change Management 11-5-14

18

Page 19: Change Management 11-5-14

19

Page 20: Change Management 11-5-14

20

Page 21: Change Management 11-5-14

21

Page 22: Change Management 11-5-14

22

Page 23: Change Management 11-5-14

23

Page 24: Change Management 11-5-14

24

Page 25: Change Management 11-5-14

25

NEGOTIATION REQUIREMENTS

Neal SwiftProject Controls - EstimatorNov. 5, 2014

Page 26: Change Management 11-5-14

- Change Order Submission and Pricing Requests– Explain concisely, accurately and with appropriate detail

– Why added scope and / or time is required

– Include pictures to illustrate issues difficult to explain

– How or what caused potential change

– Provide basis for determination of time required and other

constraints that may include additional cost and time

– Understand that reviewer will already have comprehensive

knowledge of your contracted scope of work and be familiar

with project - outline major points26

Page 27: Change Management 11-5-14

– Negotiation Meetings

– When level of complexity requires face-to-face meeting

– Come prepared with logs, reports, project docs, photographs

– Receipts and invoices for materials and equipment

– Cost of labor to be fair and reasonable, verified with LMT

– General Info

– Follow contract & general condition before starting added work

– Weather – understand what is considered Adverse Weather

– Mark-up’s, Staff & OH costs and pass-thru costs27

Page 28: Change Management 11-5-14

28

What’s the difference between a Change Order Directive (COD) and a Change Order (CO)?

− Change Order Directive (COD)− Directs the contractor to

immediately proceed with the work

− Only used when time does not allow the standard Change Notice (CN) process to be used

− 90% of DIA’s Cost Estimate or T&M with a Not-To-Exceed (NTE)

− A change order (CO) will be issued when final amounts are agreed to

− Change Order (CO)− Proposed work is negotiated

first and then completed− Final amounts to be agreed to

in negotiations− Only mechanism to completely

revise contract terms, dollars or durations

− References Change Notices (CN) and Change Order Directives (COD)

COD vs. CO

Page 29: Change Management 11-5-14

29

Page 30: Change Management 11-5-14

30

Page 31: Change Management 11-5-14

31

Page 32: Change Management 11-5-14

32

Page 33: Change Management 11-5-14

33

Page 34: Change Management 11-5-14

34

Page 35: Change Management 11-5-14

35

REDUCING AND AVOIDING CHANGE ORDERS

Glenn FrielerDirector of Infrastructure and QANov. 5, 2014

Page 36: Change Management 11-5-14

Change Orders

36

Page 37: Change Management 11-5-14

Misinterpretation of the Plans

37

Page 38: Change Management 11-5-14

Unclear Plans and Specifications

38

Page 39: Change Management 11-5-14

Working at an Airport

39

Page 40: Change Management 11-5-14

Things DIA is Doing to Limit Change Orders

40

- Work on improving the quality of our plans

- Involving contractors during the design process

- Limiting additional work that is added to a contract

- Working with the contractor when a change condition occurs

- Using “Common Sense” as we interpret our specifications

- Set realistic timelines for the completion of our projects

Page 41: Change Management 11-5-14

Change Condition

41

Page 42: Change Management 11-5-14

Plan Error

42

Page 43: Change Management 11-5-14

Missing Items

43

Page 44: Change Management 11-5-14

Working Together

44

Page 45: Change Management 11-5-14

45

REDUCING AND AVOIDING CHANGE ORDERS

David MashburnDirector of Facility ServicesNov. 5, 2014

Page 46: Change Management 11-5-14

46

Avoiding Change Orders

The best defense is a good offense

One of our Key Performance Indicators (KPI) is to be below 15% on change orders now. In the future, we want to be below 5%. Currently, on all our projects we are at 4%. Going to BIM and a stronger plan review process will reduce further.

Page 47: Change Management 11-5-14

47

Reviewing models with designers leads to stronger coordination. With BIM, the plans are prints of the model, with eSpec, the keynotes in the plans are tied to the specifications.

Plan and Model Review Process

Contractors review models with sub-contractors because it is more cost effective to virtually build first.

Page 48: Change Management 11-5-14

48

Reviewing plans with more people in less time.

A 2015 KPI is: turning around plan reviews in under 17 days.

Plan Review Process

Page 49: Change Management 11-5-14

49

Improved Planning for projects allows more time for project teams and reviews = reduced changes due to rushing emergency projects

Project Planning Process

Page 50: Change Management 11-5-14

50

REDUCING AND AVOIDING CHANGE ORDERS

David MashburnDirector of Facility ServicesNov. 5, 2014