chap 5 schmtds
TRANSCRIPT
-
7/29/2019 Chap 5 Schmtds
1/13Construction Project Management Page 1
Chapter - V Scheduling Methods
Work Breakdown Structure
Bar Chart Basic Networks
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
-
7/29/2019 Chap 5 Schmtds
2/13
Construction Project Management Page 2
Work Breakdown Structure
The construction process starts with the construction planning which is the prime activity
in Construction Project Management (CPM). Planning is the identification of the tasks which need to be
done for the completion of the work (project). It is achieved by the technique known as Work Breakdown
Structure (WBS).
The various steps involved in WBS are as follows :-
a) Breaking the project into recognizable systems or units.
b) Dividing each system or unit into functional sub systems.
c) Detailing the various tasks involved in completion of each sub system.
d) Listing the activities in a task in hierarchical order.
e) Each activity is so chosen that it can be planned, scheduled and executed.
Scheduling
It is the process of fitting the work plan to a time frame. The activities are sometimes
interdependent or independent. For example, Roof slab casting can't take place unless the reinforcement has
been placed in position and reinforcement can't be placed in position until the shuttering has been completed
Like this the various inter-related activities of the project need to be studied and scheduled accordingly for the
efficient functioning.
The independent activities takes place irrespective of the completion or delay of the other
activities. For example, reinforcement and erection of shuttering can be done independently and simultaneously
Some of the conventional methods for Scheduling explained below.
Bar Chart (Gantt Chart)
Henry Gantt developed this specialized chart around the years 1910 - 1915 and
popularized in West. The early application of this was tracking the progress of ship building.
A Bar chart is a linear calendar of project activities for planning of a project. The chart is two - dimensional
with Time along the X-axis and Activities along the Y-axis.
The Start of the horizontal bar indicates the start of an Activity. The activities which can
run concurrently i.e. which are independent of other activities are depicted by parallel bars. The sequential
activities which can happen only after the completion of the previous, are depicted by bars starting from the
time when the first activity ends. ( shown in fig. )
Let us take the following example of construction of column footings in a building :-
Activity Duration
A Layout and excavation of column footings. 2 days
B Laying of lean concrete and curing. 3 days
C Fabrication of foundation reinforcement. 2 days
D Erection of shuttering and placing of reinforcement. 2 days
E Casting of column foundations. 2 days
-
7/29/2019 Chap 5 Schmtds
3/13
Construction Project Management Page 3
Bar Chart
Monitoring
Coloring and Hatching bars technique was associated with the Bar charts to check out the
progress of different activities. As shown in the bar chart, the darkened (black) part of bars indicate the level of
completion of the particular activity against time (in days). Let us take a particular day, say day 8 and try to find
the progress of the activities. If we see, at the end of day 7 only 50 % of work is completed against the planned70%.
This review of progress would indicate an Urgency to expedite the laying of foundation concrete by including
more resources to avoid delay of subsequent activities. But without this additional impovement on Bar Chart
site engineers would not know the extent of delay in planned schedule and may fail to take timely corrective
measures.
Limitations of Bar Charts
a) Interdependency of activities - The bar chart fails to clarify the interdependency of an activity on one
or more of other activities explicitly.
b) Monitoring of progress - The bar chart has no provision to indicate the progress of work at any given
time and hence cannot be used as a monitoring tool.
c) Critical activities - The are no such indications in the bar charts, which can help us in finding the
critical activity of the project cycle, as the delay of this critical activity could affect the completion of
project.
-
7/29/2019 Chap 5 Schmtds
4/13
Construction Project Management Page 4
d) Quantum of work- The quantity of work to be carried out in each activity is not indicated, thus it is not
easy to work out the requirement of resources for execution.
Advantages of Bar Chart
a) In case of small projects having limited number of activities, the application of bar chart is very much
successful.
b) ven in the case of a large project, Bar chart cn be used as an excellent tool at the foreman level, where it
becomes easy in understanding the split sub-activities of a main activity.
Basic Networks
Networks are logical and chronological graphic representation of the activities that
constitutes a project (events composing a project). basically the networks are of two types, Arrow network and
the Node network. In an arrow network the activity is mentioned over the arrow and so it is also called as
Activity On Arrow (AOA) networks. In case of the node network, the activity is mentioned inside the node and
so it is called AON i.e. Activity On Node.The representation of a simple AOA and AON network below gives the idea of basic
networks in construction management.
The circles in the AOA and the squares in the AON network represents the nodes, the activities are represented
by the alphabets and the arrow heads indicate the hierarchy of activities.
The nodes represent events ; as an event is the point of time when an activity starts or ends. Each arrow connect
two nodes, the fr om nodeand the to node(depicted by circles and squares in AOA and AON respectively). The
basic difference between AOA and AON networks is that, in AON or node networks the dummy activities are
not depicted separately.
-
7/29/2019 Chap 5 Schmtds
5/13
Construction Project Management Page 5
Logic : In the above network we have, the activities B and C following after A. This means B and C can't
happen when A is not completed. But in reality B and C may occur consecutively or concurrently depending
upon the resources availability, site conditions etc. And once both B and C are done, activity D can start.
Dummy activities : These are fictitious activities which are inserted into arrow (AOA) networks to make it
logically correct and to distinguish between identities of activities. The AOA network below will explain about
the dummy activities or dummies.
Redundancies: An important thing to note that while building a arrow network you can have not only a
logically improper network but also a proper one with redundant dummy activities. This fact is especially true
for complicated networks. Redundant dummy activities are not logically improper: they are just redundant ( ).
Critical Path Method
The Critical Path Method is the extension of the basic networks in which the activities are
grouped into two groups i.e. Non critical and Critical activities. This identification of criticality of the activities
involves the understanding of the following terms :-
Earliest event time
Forward pass
Latest event time
Backward pass Float and its calculation.
-
7/29/2019 Chap 5 Schmtds
6/13
Construction Project Management Page 6
Earliest event time
It is the earliest time by which all activities leading to an event are completed. In practice
it is represented by TE and is written in a triangle above the event node. The iniitial node in a network is alloted
TE=0.
The Rule for evaluating TE- Add duration of activity to earliest event time of the immediately preceding event
if there are more than one activities for which this event is the end event, then repeat the same process for each
activity and the highest of the time so calculated would be the earliest event time for that event.
The network below explains the TE calculation,Forward pass
In forward pass we move from left to right in forward direction and calculate the TE of
all events starting from initial event till the end event. Earliest event time of initial event is taken equal to Zero.
T of event 10 = 0 and earliest event 20 can occur only after the completion of activtiy A i.e T for event
20=0+5= 5 days
T of 30 = 5+10 = 15 days and T of 40 = 5+8 = 13 days
T of 50 will be largest of earliest completion of activtiy 30-50 and T of 40
earliest completion of 30-50 = 15+7 = 22 days.
T of 40 = 13 days therefore T of 50 = 22 days.
Similarly T of 60 will be largest of earliest completion of activity 40-60 and 50-60.
Earliest completion of activity 40-60 = 13+12 = 25 days.
Earliest completion of activity 50-60 = 22+6 = 28 days.
Therefore T of 60 = 28 days and T of 70 = 28+4 = 32 days.
Fig. AOA network (Activity duration in days)
-
7/29/2019 Chap 5 Schmtds
7/13
Construction Project Management Page 7
Latest event time for an event
The latest time by which an event should occur to keep the project on schedule is called
the Latest event time of that event. It is denoted by TL and we consider the latest event time of last event equal
to its earliest event time and then move backward. It is written below the node in square.
The Rule for evaluating TL - Deduct duration of activity from latest event time of immediately succeeding
event, if there are more than one activities (paths) to reach immediate successor event, then repeat the process of
deducting activity duration from latest event time of immediately succeeding activity for all paths and choose
the lowest of the times so calculated and that would be the latest event time of event under consideration
Backward pass
In case of backward pass we assume the latest event time of the end event equal to its
earliest event time and then move from right to left reaching the first event and on the way we work out the
latest time for each event and note the same below the event node. If calculation is error free the Initial event
will have the latest event time equal to Zero. Let us consider the above network, in that for event 70 to occur on
32 days event 60 must occur on 28 days as activity 60-70 needs 4 days for completion. And for event 60 to
occur in 28 days the event 50 should occur in 28-6 = 22 days. Activity 40-60 duration is 12 days so event 40
should occur not later than 28-12 = 16 days but considering backwards path via dummy activity 40-50 event 40
should occur not later than 22-0 = 22 days, choosing the least value of 16 days, we can say that events 50 and
60 can on their latest time when event 40 occurs in 16 days.
TL of 30 = 22-7 = 15 days
TL of 20 = 15-10 = 5 days via activity 20-30
= 16-8 = 8 days via activity 20-40
Therefore TL of 20 = 5 days (choosing least of 8 and 5 days)
Float
Float is the extra time available for an activity over and above the activity duration. There
are three types of floats namely Total Float (TF), Free Float (FF) and Independent Float (IF).
(a) Total Float (TF) :- It is the maximum time by which an activity can be delayed without delaying the
completion time of Project. Total Float of an activity is related to all other activities and use of Total float will
affect the floats of both preceding and succeeding activities.
Total Float (TF) = Total time available to execute activity - duration of activity.
TF = (TLh - TEt) - d
(b)Free Float (FF) :- If we don't wish to interfere with the floats of succeeding activities the activity must
finish at the earliest event time of head event so that succeeding activity can start at its EST (Earliest Start Time
of an activity), therefore
FF = (TEh - TEt) - d
-
7/29/2019 Chap 5 Schmtds
8/13
Construction Project Management Page 8
(c) Independent Float (IF) :- This is the real reserve of the activity because by using IF we will not be
interfering either with the preeding or succeeding activity and for this to happen activity should start at latest
start time of tail event and finish at the earliest event time of head event.
IF = (TEh - TLt - d)
Critical Activities
The activities of a project can be grouped into two groups i.e. Non Critical activities and
Critical activities. Non Critical activities are those activities for which Total float is not zero and Critical
activities are those for which the Total float is zero. As there is zero Total float in Critical activities, any delay
in their completion will cause corresponding delay in the project completion time.
Critical Path
The path joining the critical activities in a network is known as Critical Path. It is the
longest path in the network and the time taken on this path determines the completion time of project.
To locate critical path total float in respect of all activities is worked out and critical
activities (TF = 0) are identified and joined together to identify the critical path. Double or Bold lines are used
to mark the critical path in network so that it is prominently visible. A network may have more than one critical
path. The network below will explain the Critical path method of Scheduling.
Consider the activity table and the corresponding AON network.
Activity Immediately Preceding
Activity (IPA)
Duration (in
days)
A - 5
B A 8
C A 6
D B 9
E B,C 6
F C 3
G D,E,F 1
The Forward Pass
The project starts with activity A, which starts at the beginning of day 1 (end of day 0). It
takes 5 days to finish activity A: it finishes on day 5 (end of the day). At this point, activities B and C can start.
Activity B takes 8 days: it can start on day 5 (directly after activity A finishes), so it can finish as early as day
13. Similarly, activity C can finish on day 11 (5 + 6). Activity D follows activity B. It can start on day 13 (end
of B) and end on day 22. Activity E must wait till both activities B and C are finished. Activity C finishes on
day 11, but activity B does not finish till day 13. Thus, activity E cannot start till day 13. with 6 days' duration,
activity E can then finish on day 19. Activity F depends on activity C only. Thus, it can start on day 11 and
finish on day 14. The last activity, G, cannot start till activities D, E, and F are finished. Through simple
-
7/29/2019 Chap 5 Schmtds
9/13
Construction Project Management Page 9
observation, we can see that activity G cannot start till day 22 (when the last activity of D, E, and F finishes).
Activity G takes 1 day, so it can finish on day 23. The Completed network is shown below
For this example, we have calculated two types of dates: 1. The expected completion date of the project: day 23
2. The earliest date when each activity can start and finishThese dates are called the early start (ES) and theearly finish (EF) dates for each activity. As you will soon learn, an activity cannot start earlier than its ES date
and cannot finish earlier than its EF date, but it may start or finish later than these dates. In mathematical terms
the ES time for activityj (ESj)is as follows:
ESj=max(EFj)
where (EF1)represents the EF times for all immediately preceding activities. Likewise, the EF time for activity
j (E15)is as follows:
EF=ESj+Durj
where Dur is the duration of activity j. The forward pass is defined as the process of navigating through a
network from start to finish and calculating the early dates for each activity and the completion date of the
project. See Figure \
The Backward Pass
Now let us start from the end of the project and work our way back to the start. we
already know the end-of-project date5: day 23. Activity G must finish by day 23. Its duration is only 1 day, so it
must start no later than day 22(23 - 1) so that it does not delay the project. Similarly, activities D, E, and F must
finish no later than day 22 so that they will not delay activity G. Through simple computations, we can find
their late start dates: activity F: 22-3 =19; activity E: 22 - 6 = 16: and activity D: 22- 9 =13. Activity C must
-
7/29/2019 Chap 5 Schmtds
10/13
Construction Project Management Page 10
finish before activities E and F can start. Their late start dates are 16 and 19, respectively. Clearly, activity C
must finish by the earlier of the two dates, day 16, so that it will not delay the start of activity E. Thus, its late
start date is day 10 (16 - 6). Similarly, activity B must finish by the earlier of its successors' late start dates: day
13 for D and day 16 for E. Therefore, the late finish date for activity B is day 13 and its late start date is day
5(13 - 8). The last activity (from the start) is A: It must finish by the earlier of the late start dates for activities B
and C, which are day 5 for B and day 10 for C. Consequently, the late finish date for activity A is day 5, and its
late start date is day 0 (5 - 5). In mathematical terms, the late finish (LF)time foractivity j(LSj)is as follows
LF=min(LSk)
where (LSk) represents the late start times for all succeeding activities. Likewise, the late start (LS) time for
activityj (LSj) is as follows:
LSj=LFjDurj
The backward pass is defined as the process of navigating through a network from finish
to start and calculating the late dates for all activities. This pass, along with the forward-pass calculations, helps
identify the critical path and the float for all activities. If you refer to Figure , you can see that for some
activities (light lines), the late dates (shown under the boxes) are larger (i.e., later) than their early dates (shown
above the boxes). For other activities (thick lines) late and early dates are the same. For the second group, we
can tell that these activities have strict start and finish dates. Any delay in them will result in a delay in theentire project. We call these activities critical activities. We call the continuous chain of critical activities from
the start to the end of the project the critical path. Other activities have some leeway. For example, activity C
can start on day 5, 6, 7, 8, 9, or 10 without delaying the entire project. As mentioned previously, we call this
leeway float
There are several types of float. The simplest and most important type of float is total float (TF):TF = LS - ES (or) TF = LF - EF (or) TF = LF - Dur - ES
With the completion of the backward pass, we have calculated the late dates for all activities. With both passes
completed, the critical path is now defined and the amount of float for each activity is calculated.
Activity Duration ES EF LS LF TF
A 5 0 5 0 5 0
B 8 5 13 5 13 0C 6 5 11 10 16 5
D 9 13 22 13 22 0
E 6 13 19 16 22 3
F 3 11 14 19 22 8
G 1 22 23 22 23 0
-
7/29/2019 Chap 5 Schmtds
11/13
Construction Project Management Page 11
PERT (Program Evaluation and Review Technique)
The program evaluation and review technique (PERT) is an event-oriented network
analysis technique used to estimate project duration when individual activity duration estimates are highly
uncertain. PERT applies the CPM to a weighted-average duration estimate. PERT is considered a probabilistic
method.
Concept of PERT
Like the regular (deterministic) CPM, PERT uses logic networks to calculate the
completion date of a project or the date of any other event in the schedule. In PERT, a probability (likelihood) is
associated with any event date. This probability depends on uncertainty in the durations of the activities that
lead to the desired event (e.g., project completion). PERT realizes that actual durations vary from those
assigned, so it attempts to compensate for this variation with a time range during which activity durationsmay realistically occur. This topic is discussed in more detail after the details of PERT are covered.
Working Of PERT
PERT uses a probabilistic approach, which requires a duration frequency distribution for
each activity. In most cases, such distributions are unknown or unavailable. Because of this, PERT requires the
user to set three durations that constitute the practical range of the duration for each activity. These three
-
7/29/2019 Chap 5 Schmtds
12/13
Construction Project Management Page 12
durations give a distribution for the activity, and we can produce the statistical mean and variance for the
duration of the activity. When we need to compute the probability that a certain event, such as Substantial
Completion of a building, will occur by a certain date, we need to take into account all preceding events,
starting at the beginning of the project and including the continuous chain of activities till Substantial
Completion. Using the central limit theorem, PERT treats the means of the durations of these activities as a
normal distribution, no matter what distributions these durations followed. PERT then uses simple statistics to
calculate the mean and variance (or standard deviation) of the time required to complete the chain of events
leading to Substantial Completion. It calculates the probability that Substantial Completion will occur by a
particular date, or, conversely, it calculates the date that the Substantial Completion event will happen with a
certain level of confidence (probability).
PERT Calculations
As mentioned previously, the path (chain of activities or events) leading to the examined
event (e.g., Substantial Completion) must be chosen. For each activity on that path, three durations must be
estimated:
To: Optimistic Duration
Tm: Most Likely Duration
Tp: Pessimistic Duration
The preceding values are estimated by the scheduler or project manager, who uses his or
her experience and good judgment to do so. The optimistic duration is the amount of time the activity will take
if everything goes smoothly and efficiently. The pessimistic duration is the duration under the worst-case
scenario. Both values must be within the realistic, although perhaps unlikely, realm of expectations. The mean
weighted value for these three durations is called the expected duration (Te). It is calculated as follows:
Te = To + 4Tm + Tp
6
The weights assigned to these times (coefficients of To, Tm, and Tp) may be adjusted, but the denominator
must equal the sum of all weights. The weights in equation above represent a population of durations made up
of 16.7% (one-sixth) optimistic (To); 66.7% (four-sixths) most likely (Tm); and 16.7% (one-sixth) pessimistic
(Tp). Most likely Duration (Tp) is the time for completion of an activity under normal conditions i.e.
conditions are not ideal, minor mishaps may happen.
Applications of PERT
PERT is used for works which are first of its kind, where time estimates for various
activities are neither known nor can be estimated with any certainty. The emphasis is given on reducing project
completion time without cost constraints.
-
7/29/2019 Chap 5 Schmtds
13/13