chapter 6 launching gantry distribute · g option d: overhead gantry with single main girder for...

4
Bridge Deck Erection Equipment ISBN 978-0-7277-6193-4 ICE Publishing: All rights reserved https://doi.org/10.1680/bdee.61934.063 Chapter 6 Precast segmental span-by-span erection by launching gantry 6.1. Introduction Decks that are made self-supporting for self-weight span by span are by far the most common struc- tural systems used for precast segmental viaducts. Unlike other systems, the contractor has little choice than to use overhead or underslung Launching Gantries (LG) when erecting such viaducts, unless it is possible to utilise ground-supported falsework. Decks are built span by span by stressing all segments of a span together with longitudinal prestressing cables, which run the full span length (refer to Section III, Chapter 15 for explanations about prestressing). Since such launching gantries need to be able to support the weight of an entire span, they are among the heaviest erection equipment used for bridge construction. The method by which segments are joined and stressed together to make self-supporting spans has a direct impact on the LG’s performance criteria and configuration. The permanent work designer should understand the detail of how such bridges are built, since many design and detailing aspects are governed by construction considerations and not by in-service requirements. The contractor, when ordering a launching gantry, needs a good understanding of how the bridge they have to build works structurally, to enable them to order the right erection equipment (for details, refer to Section III, Chapter 15). The content of this chapter is an extended version of a piece written for Structural Engineering Inter- national (Meyer, 2011). 6.2. Application range Precast segmental bridge decks, which are built span by span, are used for spans from 20 to 60 m, deck widths from 5 to 24 m and span weights from 2000 to more than 20 000 kN. Typical range of appli- cation is between 30 and 50 m, with span weights between 2000 and 10 000 kN and segment weights between 300 and 1500 kN. These bridges can be classified according to how they are made self- supporting. As explained in Section III, Chapter 15, we can differentiate between three systems (Ganz and Meyer, 1997). The three systems are shown in Figure 6.1 with segmentation of the deck, the sequence of construction, the location of the construction joints and the layout of the longitudinal prestressing (in red). 6.3. General arrangement of the BDE For erection of span-by-span precast segmental viaducts, a contractor has four options (A to D), as shown in Figure 6.2. 63 COPYRIGHTED MATERIAL. DO NOT DISTRIBUTE

Upload: others

Post on 25-Mar-2020

27 views

Category:

Documents


1 download

TRANSCRIPT

Bridge Deck Erection Equipment

ISBN 978-0-7277-6193-4

ICE Publishing: All rights reserved

https://doi.org/10.1680/bdee.61934.063

Chapter 6

Precast segmental span-by-span erection bylaunching gantry

6.1. IntroductionDecks that are made self-supporting for self-weight span by span are by far the most common struc-tural systems used for precast segmental viaducts. Unlike other systems, the contractor has little choicethan to use overhead or underslung Launching Gantries (LG) when erecting such viaducts, unless it ispossible to utilise ground-supported falsework. Decks are built span by span by stressing all segmentsof a span together with longitudinal prestressing cables, which run the full span length (refer toSection III, Chapter 15 for explanations about prestressing). Since such launching gantries need tobe able to support the weight of an entire span, they are among the heaviest erection equipment usedfor bridge construction.

The method by which segments are joined and stressed together to make self-supporting spans has adirect impact on the LG’s performance criteria and configuration. The permanent work designershould understand the detail of how such bridges are built, since many design and detailing aspectsare governed by construction considerations and not by in-service requirements. The contractor, whenordering a launching gantry, needs a good understanding of how the bridge they have to build worksstructurally, to enable them to order the right erection equipment (for details, refer to Section III,Chapter 15).

The content of this chapter is an extended version of a piece written for Structural Engineering Inter-national (Meyer, 2011).

6.2. Application rangePrecast segmental bridge decks, which are built span by span, are used for spans from 20 to 60 m, deckwidths from 5 to 24 m and span weights from 2000 to more than 20 000 kN. Typical range of appli-cation is between 30 and 50 m, with span weights between 2000 and 10 000 kN and segment weightsbetween 300 and 1500 kN. These bridges can be classified according to how they are made self-supporting. As explained in Section III, Chapter 15, we can differentiate between three systems(Ganz and Meyer, 1997). The three systems are shown in Figure 6.1 with segmentation of the deck,the sequence of construction, the location of the construction joints and the layout of the longitudinalprestressing (in red).

6.3. General arrangement of the BDEFor erection of span-by-span precast segmental viaducts, a contractor has four options (A to D), asshown in Figure 6.2.

63

COPYRIGHTED M

ATERIAL. DO N

OT DISTRIBUTE

Fig

ure

6.1

The

thre

ebasi

csy

stem

sfo

rco

nst

ruct

ion

of

pre

cast

segm

enta

lbridge

deck

s(V

SL

Inte

rnat

ional)

N –

1N

+ 1

N +

2N

N –

1N

+ 1

N +

2N

N –

1N

+ 1

N +

2N

64

Bridge Deck Erection Equipment

COPYRIGHTED M

ATERIAL. DO N

OT DISTRIBUTE

g Option A: ground-based falsework supporting segments underneath bottom slab and crane forhandling of segments.

g Option B: underslung gantry with pair of main girders supporting segments underneath theirwings and segment loader or crane for handling of segments.

g Option C: overhead gantry with pair of main girders for suspension of segments and forsupport of winch trolley for handling of segments.

g Option D: overhead gantry with single main girder for suspension of segments and winchtrolley for handling of segments.

Since the subject of this book is Bridge Deck Erection Equipment (BDE), the following explanationsfocus on underslung and overhead launching gantries and only a few comments are given aboutground-based falsework. Ground-based falsework may be a valuable option for very small projectsand for starting, end and odd spans on projects where the majority of spans are erected by gantries.Often such falsework systems need to be equipped with a pair of sliding beams to allow longitudinalmovement of segments along the span to get segments into their final position, or at least for fineadjustment during joining.

Figure 6.2 The four options for construction of precast segmental viaducts (VSL International)

Segment loader

Main girder

Main girder

Main girder

Main girdersupport

Main girdersupport

BracketFalsework

Winch trolleySuspension

frame

Winch trolley

Connectionbeam

At mid span At support

Option A

At mid span At support

Option C

At mid span At support

Option D

At mid span At support

Option B

Connectionbeam

Precast segmental span-by-span erection by launching gantry

65

COPYRIGHTED M

ATERIAL. DO N

OT DISTRIBUTE

The rest of this subsection describes the main components of underslung and overhead launchinggantries. The typical kinematics for these types of LGs are presented in subsection 6.4, ‘Kinematics’.

6.3.1 Underslung launching gantriesUnderslung LGs were originally developed for the erection of series of spans made up of box-girdersegments with distinctive wing slabs, which are supported on single pier shafts with reasonably straightalignment in plan.

A typical underslung gantry is made up of the following main components (for illustration, refer toFigure 6.3).

A. Brackets: Pairs of brackets are attached laterally to the piers supporting the span to be erected.Normally a minimum of three sets are required per gantry. They are generally relocated by acrane. They are clamped against the pier shafts with high-tensile bars for transfer of bendingmoments and preferably transfer shear to pier by bearing and not by friction. Therefore oftena pair of small recesses is needed at the pier top to enable such shear transfer.Brackets have mechanical components, which allow vertical, transverse, longitudinal translationsand rotation about horizontal and vertical axes between the main girders and brackets.

B. Pair of main girders: They support precast segments of a span underneath their wings untilthey are stressed together to create a span. Main girders have a centre part, on which segmentsare moved along and then supported by, and a nose at each end, used for launching. Noses aretapered at the front to allow launching onto pre-placed brackets. The rear nose is sometimesomitted by provision of a pair of C-frames at the rear of the main girder. They run on thecompleted deck N when launching the gantry into span N + 1. In this case, the bridge deckhas to be checked for the corresponding moving point loads and there is the need for running

Figure 6.3 Isometric view of a typical underslung launching gantry (VSL International)

A. BracketsB. Pair of main girders with segment trolleys and

segment support jacks or screw jacks

C. Segment loader with winch trolley and lifting beam

D. Stressing platform

66

Bridge Deck Erection Equipment

COPYRIGHTED M

ATERIAL. DO N

OT DISTRIBUTE