gantry analysis

Upload: marco-bourdon

Post on 06-Apr-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Gantry Analysis

    1/22Winter 2010 |PCI Journal

    Editors quick points

    n Precast concrete bridges are frequently built with self-launching

    erection machines.

    n Little has been written about these machines despite their cost,

    complexity, and sophistication.

    n This paper illustrates the main features of self-launching erec-

    tion machines and presents some lessons learned.

    Self-launching

    erection

    machinesfor precast

    concrete

    bridgesMarco Rosignoli

    The technological aspects of construction influence the

    modern bridge industry from the very first steps of design.

    Entire families of prestressed concrete bridges, such as

    launched bridges, span-by-span bridges, and balanced-can-

    tilever bridges, take their names straight from the construc-

    tion method.

    Construction of precast concrete bridges with spans rang-

    ing from 100 ft (30 m) to more than 600 ft (180 m) is

    mostly based on the use of self-launching machines. The

    launching units are complex and delicate structures. They

    resist high loads on long spans under the same constraints

    that the obstruction to overpass exerts on the final struc-ture. They are adaptable for reuse on different projects.

    They must be as light as possible, which involves design-

    ing for high stress levels in different load and support

    conditions, and they are assembled and dismantled many

    times and reused by different crews.

    Little has been written on these machines in spite of their

    cost, complexity, and sophistication. The present work

    illustrates the main features of self-launching bridge erec-

    tion machines and some lessons learned during 27 years

    of the authors practice in the bridge industry and as an

    independent design-checker of launching units.

    Every construction method for precast concrete bridges

    has its own advantages and challenges. In the absence of

    particular requirements that make one solution immedi-

    ately preferable to the others, the evaluation of the possible

    alternatives is a difficult task. Comparisons based on the

    quantities of materials consider only one of the compo-

    nents of the construction cost of a bridge. In industrialized

    countries, the cost of a bridge is more and more influenced

    by the processing costs of the materials, such as labor, in-

    vestments for specialty equipment, delivery and assembly

    costs for the equipment, and energy.

  • 8/3/2019 Gantry Analysis

    2/22 3PCI Journal|Winter 2010

    may be exposed to impacts and strong wind. The support

    reactions are often applied eccentrically, the support sec-

    tions are often devoid of diaphragms, and most units are

    supported on deformable brackets or cross beams.

    Mechanical and hydraulic components interact with the

    structural components and often govern the stress distri-

    bution. The safety of the unit itself depends on complexinteractions among mechanical, electrical, hydraulic, and

    structural components. Indeed, such design conditions are

    almost inconceivable in a permanent structure subjected to

    such loads.

    Types and featuresof launching units

    The industry of self-launching machines is a specialty

    niche. Every unit is originally conceived for a scope, every

    manufacturer has its own technological habits, every con-

    tractor has preferences and reuse expectations, and every

    bridge has its own technical requirements. The length of

    the bridge dictates the automation level of the equipment,

    and even the construction country of the unit affects some

    aspects of design. Nevertheless, there are not many con-

    ceptual schemes.

    The launching gantries for precast concrete girders com-

    prise two parallel 3-D trusses. Two winch trolleys run

    along the top chords with the girder suspended under-

    neath, so no cross braces are typically installed between

    the trusses. The span is relatively short; 150 ft (45 m)

    spans are rarely exceeded in precast concretegirder

    bridges, the design load of the unit is relatively low asthe girder is just a small portion of the span, and the

    winch trolleys operate far from each other as the girder

    is suspended at the ends. Therefore, these units are light,

    deformable, and often comprise transportable modules

    with tubular diagonals welded to the chords and through

    pins at the field splices.

    A launching gantry for span-by-span erection of precast

    concrete segmental box girders operates on similar spans,

    130 ft to 170 ft (40 m to 50 m), but the design load is much

    higher because the unit supports the entire span during

    segment assembly and the application of prestress.

    The most versatile overhead units comprise two parallel

    girders that suspend the deck segments and support the

    runways for one or two winch trolleys. The girders are

    supported by cross beams and are equipped with truss

    extensions that control overturning during launching. The

    winch trolleys operate along the entire unit so the main

    girders are braced to each other only at the ends. The

    girders comprise modules joined by pins or bolts, and the

    modular nature of design often permits different assembly

    configurations of chords and diagonals. These heavy work-

    horse units are expensive on long bridges because of their

    Savings in materials lower the construction cost of a bridge

    only when they are not achieved with higher technological

    costs. In other words, greater quantities of materials do not

    necessarily make a solution uneconomical, provided that

    the construction process is able to generate low labor costs

    and to facilitate the amortization of specialty equipment.

    A good balance of material costs and technological costsis the reason for the success of the incremental launching

    method in industrialized countries.1 Compared with the use

    of ground falsework, bridge launching diminishes the cost

    of labor with similar investments in equipment. Compared

    with the use of self-launching erection machines, bridge

    launching diminishes the investments in equipment with

    similar labor costs. In both cases bridge launching di-

    minishes the technological costs, and even if the launch

    stresses increase the cost of prestressing, the balance is

    positive and the solution is financially effective.

    The construction method that comes closest to bridge

    launching is segmental precasting.2 Hundreds of bridges

    have been built by segmental precasting even though the

    need for avoiding joint decompression increases the cost of

    prestressing. However, the investments in specialty equip-

    ment are also high, so segmental precasting is typically

    used for long bridges that allow amortization of precasting

    facilities and erection machines. On shorter bridges, pre-

    fabrication is limited to the concrete girders and the deck

    slab is cast in place.

    Precast concrete segments or girders can be erected with

    ground cranes if the piers are not tall and the area under the

    bridge is accessible. Sensitive environments, valleys withsteep slopes, tall piers, and inhabited areas often require

    assembly by launching gantry, and in this case the techno-

    logical costs increase significantly.

    Self-launching erection machines are complex and delicate

    machines. They resist huge loads on long spans, often the

    weight of an entire span. Deck erection and self-launching

    must be compatible with plan and vertical curvatures of the

    bridge, and the most advanced units are also able to trans-

    fer their support systems to avoid the use of ground cranes.

    In spite of such complexity, the launching units mustalso be light. The weight governs the cost of the unit,

    the delivery and assembly costs, and the launch stresses.

    Weight limitation dictates the use of high-strength steel

    and designing for high stress levels under different load

    and support conditions.

    The launching units are reused several times in different

    conditions and by different crews. The units are modified

    and adapted to new work conditions, field splices are as-

    sembled and dismantled many times, and structural nodes

    and splices are subjected to hundreds of load reversals.

    The nature of loading is often highly dynamic and the units

  • 8/3/2019 Gantry Analysis

    3/22Winter 2010 |PCI Journal 3

    The bridge itself may support lifting frames for precast

    concrete segmental erection of balanced-cantilever bridg-

    es. These light units are cost-effective for short bridges and

    long spans, though they typically involve longer construc-

    tion duration. Compared with a launching gantry, these

    units also permit contemporaneous erection of several

    hammers and erection sequences that do not require con-

    struction from abutment to abutment.

    Purpose-designed, multiwheel carriers with self-launching

    support girders are used for transporting entire precast

    concrete spans from the casting yard to the assembly loca-

    tion along the completed bridge. The span length rarely

    exceeds 130 ft (40 m) because of the prohibitive design

    load for both the carrier and the bridge. Much longer

    precast concrete spans can be handled with floating cranes

    when the bridge dimensions permit amortization of such

    investments.

    Launching gantries forprecast concrete girders

    The most common method for erecting precast concrete

    girders is with ground cranes. Cranes usually entail the

    simplest and most rapid erection procedures with the mini-

    mum of investment, and the deck may be built in several

    places at the same time. Good access is necessary along

    the entire length of the bridge to allow the cranes to be

    positioned and the girders to be transported and lifted into

    place, and the bridge should be low to the ground. In the

    presence of rivers, railroads, highways, or tall piers, crane

    erection may not be possible. Ground transportation and

    crane erection of precast concrete girders are often impos-sible in urban areas.

    Ground gantries on tires or rails have been used to lift

    the girders where level access is available and the deck is

    very low to the ground. Less versatile than cranes, ground

    gantries are typically used for erecting long urban viaducts

    along existing roads. Paired gantries may be necessary

    for the longest girders to limit the negative moment from

    long-end cantilevers.

    The use of a launching gantry often solves erection dif-

    ficulties. A launching gantry for precast concrete girdersis a light modular structure comprising two parallel trusses

    with triangular cross sections. The truss length is about

    2.3 times the standard bridge span (Fig. 1). Light braced

    frames support the trusses at the piers and allow the longi-

    tudinal and transverse movements necessary to place the

    girders with the due eccentricity and to launch the gantry

    along curved alignments. The gantry operates without any

    contact with the deck so the girders for many spans can be

    placed before casting the deck slab.

    Two winch trolleys run along the upper chords of the gan-

    try and lodge two winches each. The main winch suspends

    weight, the high labor demand, the complexity of opera-

    tions, and the need for specific support structures.

    Lighter and more automated, custom-designed, single-

    beam units are often preferred on long bridges. These units

    are based on one central beam; a light front extension

    controls overturning during launching, and a rear portal

    frame is supported by the new span. The front end of themain girder may also be supported by a self-launching

    beam, and the connection may be pivoted to fit tight plan

    curvatures. These units are lighter than the twin-upper-

    beam units and do not require cross beams at the piers;

    however, they are less versatile and adaptable. These units

    are also more stable and compact and typically have full

    self-launch capability.

    Two parallel girders are also used in the underslung units.

    The girders are typically equipped with front and rear ex-

    tensions that control overturning and are supported on pier

    brackets. The most advanced units are able to move the

    brackets to the new pier. Struts from foundations are also

    used to support the unit in bridges not very high above the

    ground. In this case, the bridge span can be longer.

    A cross beam running along the new span may suspend

    the rear end of the unit. This diminishes the number of pier

    brackets needed and shortens the unit. The front ends of

    the main girders may also be connected with a cross beam

    sliding along a central self-launching support beam. These

    units are short and able to operate on tight plan curvatures.

    Although the depth of the main girders may cause clear-

    ance problems at the abutments or when overpassinghighways or railroads and their length is often a problem in

    curved bridges, the twin-lower-beam gantries for span-by-

    span precast concrete segmental erection are typically less

    expensive than the twin-upper-beam units.

    The upper-beam units for precast concrete segmental

    balanced-cantilever erection can be operated on spans that

    often exceed 350 ft (100 m). Compared with the launching

    units for span-by-span construction, the design load is less

    because the segments are handled individually or in pairs

    and no entire span is suspended from the unit. Top-slab

    tendons in the deck resist the negative moment generatedby the segment weight, and temporary pier locks resist the

    load imbalance when the deck is not continuous with the

    pier.

    The design-governing load condition for the unit is typi-

    cally the negative moment from the long front cantilever,

    so varying-depth trusses are sometimes preferred. Stay

    cables deviated by an extension tower of the main support

    frame solve the most critical cases. The load deflections

    are significant, but this is rarely a problem.

  • 8/3/2019 Gantry Analysis

    4/22 3PCI Journal|Winter 2010

    The typical support block for the main trusses comprises a

    lower group of rolls or skids that move transversely along

    the support cross beam and an upper group of rolls that

    support the bottom chord of the truss. A transverse pin

    connects the two groups of rolls and allows the upper rolls

    to follow the rotations of the main trusses and the gradi-

    ent of the launch plane. Some support blocks are equipped

    with lock systems for the main trusses to avoid involuntary

    movements of the unit. Most bridges have a longitudi-

    nal grade and the gantries are supported on low-friction

    inclined planes, so the lock systems are critical for the

    stability of the unit and safety of operations.

    Launching gantriesfor span-by-span erectionof precast concretesegmental box girders

    Three different techniques can be used for erecting a pre-

    cast segmental box girder:

    span-by-span assembly

    balanced-cantilever assembly

    progressive placement with the help of temporary

    stays or props

    With the span-by-span method, all of the segments for a

    span are positioned before the prestressing tendons are

    installed, and the complete span is lowered onto the bear-

    ings. The balanced-cantilever method involves erecting

    the segments as a pair of cantilevers about each pier, and

    the segments are prestressed with deck slab tendons that

    cross the entire hammer. With the progressive placement, a

    lifting frame or ground crane raises and places the seg-

    the girder, and a smaller translation winch acting on an

    endless ring cable moves the trolley longitudinally along

    the gantry. The endless ring cable is anchored to the oppo-

    site ends of the unit and is kept in tension by lever counter-

    weights. A third trolley often carries an electric generator

    that feeds gantry operations. Motorized wheels can also

    be used for translation. Vertical hydraulic cylinders may

    replace the main winches when the girders are deliveredalong the completed deck.

    The gantry operates in one of two ways depending on how

    the girders are delivered. If the girders are delivered at the

    ground level, the gantry raises them to the deck level and

    places them onto the bearings. If the girders are delivered

    at the abutment, the gantry is moved back to the abutment

    and the winch trolleys are placed at the rear end of the unit.

    The front trolley lifts the front end of the girder and moves

    it forward along the unit with the rear end supported on

    the ground transportation unit. When the rear end of the

    girder reaches the rear winch trolley, the latter picks it up

    to release the ground transportation unit.

    The longitudinal movement of the gantry is a two-phase

    process. Initially, the gantry is anchored to a pier and the

    winch trolleys move the girder one span ahead. Then the

    winch trolleys are anchored to the pier and their translation

    systems launch the trusses to the next span. This sequence

    can be repeated many times so that when the girders are

    delivered at the abutment, the gantry can place them sever-

    al spans ahead. When the bridge is long, moving the gantry

    over many spans slows down the erection and it may be

    faster to cast the deck slab as soon as the girders are placed

    and to deliver the next girders along the completed bridge.

    The launching gantries for precast concrete girders are

    relatively inexpensive and easily adaptable in both length

    and spacing of the main trusses. They are flexible, so

    wedge sledges are necessary at the ends of the trusses to

    recover the elastic deflection during launching. These units

    are able to cope with variations in span length and deck

    geometry, and because they are located above the deck,

    they are generally unaffected by ground-level constraints

    and the plan curvature of the bridge.

    Support frames anchored to the pier caps hold a rail forthe lateral movements of the unit. The cross beam of the

    support frames typically comprises two I shapes connected

    by horizontal bracing and diaphragms. Box girders are also

    used in light applications. The cross beams have lateral

    overhangs to shift the gantry laterally for the placement of

    the edge girders and to launch the unit when the bridge is

    curved in plan (Fig. 2). The support legs of the pier frames

    are located so as not to interfere with the girders (Fig. 1).

    They are adjustable (typically, hydraulic cylinders for

    geometry adjustment and screw legs for the structural sup-

    port) to set the transverse rail horizontal when the pier cap

    is inclined.

    Figure 1. This light gantry is used or precast concrete girders. Photograph

    courtesy o Comtec.

  • 8/3/2019 Gantry Analysis

    5/22Winter 2010 |PCI Journal

    ments in one direction from the starting point, passing over

    the piers in the process. The balanced-cantilever method

    is mostly used on long spans while long viaducts with

    shorter spans are better suited to the span-by-span method.

    Progressive placement is rarely adopted.

    Span-by-span erection is used for both simply supported

    spans and continuous superstructures. The adjacent spansof continuous bridges are joined together with in-place

    stitches that avoid propagation of the geometry tolerances of

    short-line segmental match-casting. After the closure pour

    has hardened, continuity prestressing tendons are installed

    and tensioned. With span-by-span erection and epoxy joints,

    a typical 130 ft (40 m) span is usually erected every two or

    three days. With a twin-lower-beam gantry and dry joints, an

    erection rate of up to one span per day is achievable.

    Span-by-span erection is typically used for spans shorter

    than 160 ft (48 m). For longer spans, balanced-cantilever

    erection is often more cost-effective because of the lowercost of the gantry. Progressive placement is usually the

    most time-consuming erection technique because of the

    single work location; however, the specialty equipment can

    be particularly inexpensive, especially when ground cranes

    can erect the segments along the entire length of the bridge.

    Upper- or lower-beam gantries are used in the span-by-

    span erection to support a complete span of segments,

    which are pulled together by prestressing bars during

    gluing of the joints and then by the permanent tendons.

    The gantry then releases the span onto the bearings and

    launches itself forward to erect the next span.

    A typical twin-upper-beam gantry comprises two paral-

    lel trusses or box girders supported on cross beams. The

    truss units are preferred in high-wind regions and are

    often lighter, while the box-girder units are more stable

    and solid. The twin-upper-beam units are easily adaptable

    to different span lengths, and they are able to cope with

    variations in deck geometry. Because the main girders are

    located above the deck, these units are less affected byground constraints; however, they are more complex to

    design, assemble, and operate and the units are slower in

    erecting the segments than an underslung gantry.

    Overturning during launching is typically controlled with

    extension trusses applied to the main girders. The total

    length of the unit thus becomes about 2.3 times the stan-

    dard span of the bridge, but this is rarely a problem with

    overhead units. Cross beams anchored to the piers sup-

    port the main girders with saddles that permit longitudinal

    launching and lateral movements of the unit. The support

    legs of the cross beams are adjustable to ensure that theframe is level. Hydraulic cylinders are used to adjust the

    elevation, and safety ring nuts lock the cylinders during

    operation and launching. The cross beams are anchored to

    the pier cap with prestressing bars that resist uplift forces.

    The cross beams have lateral overhangs to set the gantry

    with the appropriate eccentricity (Fig. 3) and to launch the

    unit on curved spans, so significant uplift forces may arise

    in the anchor systems.

    The support rollers comprise a lower group of transverse

    rolls, which are supported on the cross beam, and an

    upper group of longitudinal rolls that support the bottom

    Figure 2. The edge girder is being placed. Photograph courtesy o Comtec.

  • 8/3/2019 Gantry Analysis

    6/22 4PCI Journal|Winter 2010

    chord. A transverse pin between the two roll assemblies

    makes the support adaptable to rotations in the main gird-

    ers and to launching onto grades. Some support blocks

    lodge longitudinal lock systems for the unit, and all thesupport cross beams are typically equipped with trans-

    verse lock systems.

    The overhead gantries operate in one of two ways depend-

    ing on how the deck segments are delivered. If the seg-

    ments are delivered along the completed deck, a winch

    trolley picks them up at the rear end of the gantry, moves

    them over the span until reaching the assembly location,

    and lowers them down to the deck level. If the segments

    are delivered at the ground level, the winch trolley raises

    them up to the deck level. Hangers are used to align and

    hold the segments in position during assembly. Afterreaching the assembly location, the segments are hung

    from the main girders and the winch trolley is released for

    a new cycle. To avoid interference with the hangers of the

    previously placed segments, the segments are moved out

    with the long side in the longitudinal plane of the bridge.

    The segments are rotated 90 deg just before suspension

    with a special hook that is able to hydraulically turn the

    segment.

    Typically, all of the segments for the span are suspended

    from the gantry before the joints are glued so that no ad-

    ditional truss deflections can occur. Epoxy is applied to

    groups of segments that are then pressed together with

    temporary clamping bars. The permanent tendons are

    usually tensioned from a stressing platform attached to the

    front segment.

    The lightest gantries may be launched with winches, such

    as those units for precast concrete girders. Typically, how-

    ever, long-stroke hydraulic cylinders lodged into the sup-

    port saddles and acting against racks anchored to the main

    girders are used to push the unit forward. Twin cylinders

    are often used so that one cylinder anchors the unit during

    repositioning of the adjacent cylinder. Figure 4 shows the

    launch cylinders of a twin-lower-beam gantry in the raised

    configuration for segment assembly. Lowering the support

    jacks releases the span onto the launch bearings in one

    operation.

    Single-upper-beam gantries may also be used for span-by-

    span precast concrete segmental erection. In these units,

    the carrying structure is a longitudinal girder that is sup-

    ported at the front pier of the span to be erected and at the

    rear pier (in the case of simply supported spans) or on the

    front overhang of the completed deck (in the case of a con-

    tinuous bridge). The main girder may comprise two braced

    trusses or plate girders, or it may be a triangular truss with

    one upper chord and two bottom chords. A winch trolley

    runs along the unit and moves the deck segments to the

    assembly locations.

    Figure 3. This shows a twin-upper-beam gantry with support cross beams. Photograph courtesy o NRS.

  • 8/3/2019 Gantry Analysis

    7/22Winter 2010 |PCI Journal

    A light front extension typically controls overturning dur-

    ing launching. The rear end of the unit is supported by the

    completed span. No rear nose is necessary, so these units

    are shorter than a typical twin-upper-beam gantry and are

    more adaptable to curvatures in the bridge. The main girder

    is stiffer than two parallel trusses, and its support systems

    are also stiffer.

    Lateral bracing connects the trusses or plate girders

    along their entire length (Fig. 5). Lateral bracing typi-

    cally includes cross beams between the flanges or chords,

    connections designed to minimize displacement-induced

    fatigue, and sufficient flexural stiffness to resist vibration

    stresses. Cross frames connected to the flanges or chords at

    the same locations of lateral bracing distribute torsion and

    provide transverse rigidity. Connections are often designed

    to develop member strength.

    The gantry supports an entire span, so the main girder is

    heavily stressed. The units for the heaviest spans are some-

    times equipped with prestressing or stay cables, though

    this complicates and slows the operations and increases

    labor demand. Truss gantries are preferred in this case for

    better control of buckling and simpler structural nodes at

    the anchor points of stay cables.

    Special support devices are necessary to launch the unit

    when the front support frame is integral with the maingirder. Launching is typically achieved by friction, taking

    advantage of the support reaction that the main girder

    applies to the launcher. Figure 6 shows a typical friction

    launcher assembled onto a support tower. A support box

    is located underneath each bottom flange or chord of the

    main girder. A hydraulic cylinder moves the box longitu-

    dinally along the low-friction surface of a pivoted arm, and

    two jacks at the opposite ends of the arm lift and lower the

    main girder. The working sequence is as follows:

    The vertical jacks lower the unit onto the support1.

    boxes.

    The thrust cylinders push the support boxes forward,2.

    and the thrust force is transferred to the main girder by

    friction.

    When the launch cylinders reach the limit stop, the3.

    jacks lift the unit and the support boxes may return

    idle to the initial position to start this cycle again.

    The friction launchers are typically pinned to the support

    towers to allow rotations when launching along curved

    alignments. Low-friction surfaces between the support

    tower and the base frame also allow lateral shifting (Fig. 6).These geometry-control systems are equipped with sliding

    clamps so that the entire assembly can be suspended from

    the main girder (Fig. 7). Figure 7 shows the two friction

    launchers of the unit suspended from the front overhang.

    The rear support of the gantry is an adjustable frame that

    runs along the completed span. Horizontal hydraulic cyl-

    inders control the transverse alignment of the frame when

    launching along curved spans, and vertical cylinders con-

    trol the support reaction that the frame transfers to the deck.

    Upon completion of span erection, the rear launcher is

    moved backward to the front pier or overhang. In the firstphase of launching, the unit is typically supported at the

    rear launcher and at the rear support frame. When the front

    end of the unit reaches the next pier, the pier-cap segment

    and the front launcher are positioned for launch comple-

    tion. A front support leg typically controls overturning

    during this operation. At the end of launching, the two

    launchers are suspended from the front overhang and a

    new span can be erected with the unit supported at the

    main frame and the rear portal frame.

    Refined single-upper-beam machines have been designed

    for erecting precast concrete segmental box girders with

    Figure 4. The launch cylinders o a twin-lower-beam gantry are shown in the

    raised conguration or segment assembly.

    Figure 5. Lateral bracing o a single-upper-beam gantry in a movable scaoldingsystem conguration connects the plate girders along their entire length.

  • 8/3/2019 Gantry Analysis

    8/22 4PCI Journal|Winter 2010

    ing noses after erecting the first span and launching the

    unit to the second span. The front nose is also dismantled

    before launching the unit to the last span. The abutment

    walls must also be taller than the total depth of the unit so

    as not to prevent operations in the first and last span.

    The length and weight of the precast concrete segments for

    box-girder bridges are usually governed by handling and

    transportation requirements. Lengths up to 12 ft (3.6 m)

    are often transportable on public roads without excessive

    restrictions. If the precasting plant is close to the erection

    site and no transportation restrictions exist, the segments

    are made as long as practical, but they rarely exceed

    lengths of about 14 ft (4.3 m).

    To further increase the segment dimensions, a box girder

    may be divided transversely into two halves to be joined

    with in-place stitches in the two slabs. The girder may also

    be divided into a pier-cap segment and a midspan segment

    tight plan curvatures. In the unit ofFig. 8, the winch trolley

    is suspended from the bottom flanges and the deck seg-

    ments are delivered on the ground or along the completed

    deck through the rear support frame. To accommodate

    tight plan curvatures, the gantry comprises two elements:

    a rear main girder and a front support beam. A turntable

    with hydraulic controls for translation and vertical and

    horizontal rotations connects the main girder to the supportbeam. During launching, the turntable pulls the main girder

    along the support beam. When the front support frame has

    reached the front pier, the support beam is launched for-

    ward to clear the area under the main girder for assembly

    of the new span.

    Many precast concrete segmental bridges have also been

    erected with underslung gantries. These units are posi-

    tioned beneath the deck with the two trusses or box girders

    on opposite sides of the pier, and the gantry supports the

    segments under the lateral overhangs. The unit is typically

    supported on pier brackets or props from foundations.

    When the deck is low to the ground, midspan props may be

    used to increase the operating span of the unit.

    When overturning is controlled with front and rear exten-

    sions, the length of the unit is more than twice the typical

    span length. A central front launching beam may be used

    in curved bridges to support the main girders in combina-

    tion with a rear support frame running on the completed

    deck. This type of gantry is a telescopic assembly of a

    central support beam and two lateral girders that support

    the segments. This solution requires a particular design of

    the pier head to create the launch clearance for the support

    beam.

    The segments are placed onto the gantry with a crane or

    lifting frame. When the segments are delivered through the

    completed deck, the lifter is placed at the rear end of the

    gantry. When the segments are delivered on the ground, the

    crane is placed at the front end of the gantry. The segments

    are placed onto the gantry close to the lifter and are moved

    along the gantry to the assembly position with rollers.

    Upon completion of assembly and application of prestress,

    the gantry lowers the span onto the bearings.

    Underslung gantries are simple to design, assemble, andoperate. Segment erection is fast, and props can be used to

    extend the operating span when working low to the ground.

    However, these units are not suitable for decks on a tight

    horizontal curve. Vertical hinges in the main girders have

    been used though the joints are heavily stressed and the

    units are more complex to operate.

    The underslung gantries also project beneath the deck,

    which may cause clearance problems when passing over

    existing roads or railroads and difficulties in the end spans

    because the abutment walls are broader than the piers. This

    problem is typically solved by assembling the rear launch-

    Figure 6. A riction launcher is assembled onto a support tower.

    Figure 7. The riction launchers are suspended rom the main girder.

  • 8/3/2019 Gantry Analysis

    9/22Winter 2010 |PCI Journal

    The design-governing loading condition typically occurs

    during handling of the pier-cap segment. This segment

    is heavier and it is suspended at the center because it is

    designed for negative moment, so the two winch trol-

    leys work closely to each other and loading of the main

    trusses is localized (Fig. 9). The segment weight is also

    unevenly distributed between the winch trolleys to con-

    trol overturning during insertion under the front support

    cross beam. The lighter midspan segments are suspended

    at the ends so that the winch trolleys work far from each

    other, and the load displacement along the gantry is also

    shorter.

    The main trusses and the support cross beams are heavy,

    so the launch stresses are also demanding on such long

    spans. The weight of cross beams discourages crane

    erection, and the gantry is typically able to reposition itssupporting systems. In this case, the unit has four support

    points:

    two main cross beams

    a front arm used during transfer of the front cross

    beam to the next pier

    the pivoted rear leg, which is lowered behind the mac-

    rosegment after its insertion under the gantry

    The cross beams are moved forward with the winch trol-leys. Both cross beams usually lodge hydraulic cylinders

    for the launch of the main trusses. The launch of a twin-

    upper-beam gantry for macrosegmental construction is a

    complex operation because these units are heaviest and the

    load that they transfer to the bridge requires precise sup-

    port locations. Control of overturning may require placing

    the winch trolleys at the rear end of the unit and suspend-

    ing counterweights, which further increases the launch

    stresses and generates specific conditions of out-of-plane

    buckling.

    with in-place stitches at the span quarters. A macroseg-

    mental span thus typically comprises four precast concrete

    segments.

    The macrosegments are transported longitudinally. The

    segment length rarely exceeds 150 ft (45 m), so the maxi-

    mum span length of the span-by-span macrosegmental

    bridges is about 300 ft (90 m). In this case, the deck typi-

    cally has varying depth. The segment weight is excessive

    for ground cranes and also for most gantries for balanced-

    cantilever construction, so special twin-upper-beam units

    are used for macrosegmental erection (Fig. 9).

    The segments are transported along the completed deck.

    The length and weight of the segments are such that the

    gantry cannot rotate them, so the segments are delivered

    with their final alignment. The complexity of the opera-

    tions and the cost of gantry are such that macrosegmentalconstruction is typically used for long parallel bridges low

    to the ground. The four macrosegments for a span can thus

    be supported on temporary towers at the front span quarter

    before stitching and completion of prestressing. The rear

    ends of the midspan segments are typically suspended from

    the front overhang of the completed deck.

    The launching gantries for macrosegmental construction

    are subjected to specific design constraints. The segments

    are very heavy, with the pier-cap segment typically heavier

    than the midspan segment, and their weight may exceed

    1500 kip (6.5 MN). The length and weight of segmentsprevent their being picked up from cantilever sections of

    the gantry. Therefore, a rear pivoted leg is necessary. Com-

    pared with a gantry for balanced-cantilever construction,

    however, the front cantilever is shorter, so the total length

    of the unit is similar. The pier-cap segments are inserted

    longitudinally between the pier and the front support cross

    beam, so the latter is supported on tall braced columns

    (Fig. 9). The segments are also moved laterally, which

    requires shifting the gantry along the support cross beams

    and also shifting the winch blocks along the winch-trolley

    cross beams to reach the maximum eccentricity. Overload-

    ing the main trusses is increased further in curved bridges.

    Figure 8. This is the pivoted single-upper-beam gantry or curved precast concrete

    segmental bridges. Photograph courtesy o Deal.Figure 9. This heavy twin-upper-truss unit is or precast concrete macrosegmental

    erection.

  • 8/3/2019 Gantry Analysis

    10/22 4PCI Journal|Winter 2010

    In a precast concrete segmental bridge, the pier-head seg-

    ment should have the same weight as the other segments

    so as not to require special lifting devices. The segment

    contains a thick support diaphragm (the bearings are usually

    eccentric with respect to the webs because of their dimen-sions) and the bottom slab is also thick because of the

    longitudinal compression forces from the cantilevers, so the

    pier-head segment is usually very short. This also facilitates

    its placement because the gantry also must be supported at

    the pier. Sometimes it is necessary to transfer some bending

    to the piers by means of two parallel lines of bearings. Full

    continuity can also be achieved by casting the pier-head seg-

    ment in-place with through reinforcement from the pier.

    The most common methods for precast concrete segmen-

    tal balanced-cantilever erection are with ground cranes

    or launching gantries. Ground cranes require access tothe deck along the entire length of the bridge. Ground

    improvement may also be necessary. Cranes usually give

    the simplest and most rapid erection procedures with the

    minimum of temporary works. Cranes are also readily

    available, and multiple cantilevers can be erected at once.

    The main constraint on crane erection is access because

    balanced-cantilever bridges are often selected in response

    to inaccessible terrain.

    Lifting frames operating on the deck are sometimes used

    on tall piers or cable-stayed bridges. They are also selected

    to use over water, where a custom-built system can accom-

    Launching gantriesfor balanced-cantileverconstruction

    Balanced-cantilever erection is a construction method wellsuited to precast concrete segmental bridges. The deck is

    erected from each side of the pier in a balanced sequence

    to minimize the load imbalance on the pier. This method is

    particularly advantageous on long spans and where access

    beneath the deck is difficult.

    Segment assembly with ground cranes or lifting frames

    permits free erection sequences, while the use of a launch-

    ing gantry requires that the deck be erected from one

    abutment toward the opposite one; however, this permits

    delivering the segments along the completed deck and does

    not require having access to the area under the bridge.

    Balanced-cantilever bridges usually have box-girder

    sections.3 Ribbed slabs have also been built in the past;

    nowadays they are used almost only for cable-stayed

    bridges, where most of the negative moment is resisted

    by the stay cables. The deck can have constant or varying

    depth. Constant-depth decks are easier to build, but they

    are competitive in a narrower range of spans, 200 ft to

    230 ft (60 m to 70 m). It is possible to erect a 130 ft (40 m)

    precast concrete segmental span with epoxy joints in 3

    days, while spans of 330 ft (100 m) typically take from 7 to

    12 days to erect.

    Figure 10. This long twin-upper-beam gantry is used or balanced-cantilever erection. Photograph courtesy o HNTB archive.

  • 8/3/2019 Gantry Analysis

    11/22Winter 2010 |PCI Journal

    modate heavier segments. The pier-head segment is cast

    in place to establish a platform on which one or two lifting

    frames are secured. An auxiliary frame may also be used to

    lift the pier-head segment and then the main lifting frame.

    When a single lifting frame is used, the unit is moved from

    one side of the pier to the other to lift the segments in turn.

    Some lifting frames are able to pick up the segment at the

    base of the pier and to move it along the cantilever. Usinga pair of lifting frames, one on each cantilever, simplifies

    the erection process. Unless the bridge is very high off the

    ground, lifting frames are used less than ground cranes

    because of their cost and relative slowness and the disrup-

    tion when moving to the next pier.

    Launching gantries can speed erection rates, and when

    the segments are delivered along the deck, site disruption

    beneath the deck is minimized. They are suited to building

    over rivers or other obstructions, though they are limited to

    erecting the deck in a sequential manner and are delayed if

    problems occur at any pier or span. Both single- and twin-

    upper-beam units can be used. The gantry takes support

    at the front pier of the span to be erected and on the front

    overhang of the completed deck (Fig. 10).

    The earliest gantries were slightly longer than the span to

    be erected. The length was sufficient to span between the

    front overhang of the completed deck and the next pier,

    and minimizing the distance between the supports resulted

    in a lighter gantry. Disadvantages of short gantries include

    overloading the front deck overhang and the complexity

    of placement of the pier-head segment and of the launch-

    ing operations. The length of the most recent gantries is

    typically twice the span length. These units take support

    onto the piers, and the higher cost of the gantry is offset byless reinforcement and prestressing along the entire length

    of the bridge. Placement of the pier-head segment and

    launching are also simplified.

    One or two winch trolleys transport the segments to the

    assembly location. If the segments are delivered along the

    completed deck, the winch trolley picks them up at the rear

    end of the gantry and moves them out over the span. If the

    segments are delivered at the ground level or on barges,

    the winch trolley raises them up to the deck level.

    A typical sequence for gantry erection is as follows:

    The gantry places the pier-head segment onto the next1.

    pier. At this stage, the front support frame of the gan-

    try is on the pier and the central and rear support cross

    beams are on the completed deck.

    Figure 11. This single-upper-truss gantry is equipped with a deviation tower. Photograph courtesy o HNTB archive.

  • 8/3/2019 Gantry Analysis

    12/22 4PCI Journal|Winter 2010

    flange. The field splices in the chords are arranged with lon-

    gitudinal bolts above the upper flange and below the bottom

    flange to permit the wheels to pass through.

    Macrosegmental construction is also compatible with

    balanced-cantilever erection of long deck segments de-

    livered on the ground. The weight of segments suggests

    strand jacking for lifting as in Fig. 12. The segments are

    connected with in-place stitches with through reinforce-

    ment, and after application of prestressing the two seg-ments are released and the unit is ready for lifting another

    pair of segments. This type of launching units can easily

    be adapted to in-place casting (the lifting platforms are

    replaced with shifting casting cells) and vice-versa.

    The use of these heavy lifting units is suitable for spans

    up to 350 ft to 400 ft (100 m to 120 m) and rectilinear or

    slightly curved bridges of adequate length. The length of

    the girders is about 1.3 times the maximum span length.

    Despite their cost, these units offer many advantages. The

    girder provides easy access to the work locations from the

    completed deck for workers and materials. If the deck issupported onto bearings, the girder balances the cantilevers

    without the deck being temporarily anchored to the pier.

    This balancing action is also useful when the deck is con-

    tinuous with the piers and the piers are tall and slender.

    Wheeled carriersfor full-span precasting

    Several major bridges have been built with concrete spans en-

    tirely cast off-site and transported into place. Box girders are

    well suited to highway and railroad bridges, while U-girders

    are used only for railroad bridges, where they meet structural

    The gantry moves its central support cross beam for-2.

    ward onto the pier-cap segment.

    The gantry is launched forward until it is sitting sym-3.

    metrically above the pier.

    After the gantry is anchored, the deck segments are4.

    picked up and moved into position. New segments areplaced on either side of the pier and fixed with epoxy,

    temporary joint clamping bars, and top-slab tendons.

    When the two cantilevers are completed, aligned, and5.

    locked to each other, a 1 ft to 2 ft (0.3 m to 0.6 m) in-

    place closure segment is cast at midspan. Bottom-slab

    tendons are installed across the joint to complete the

    connection.

    The pier-head segment is typically placed on temporary

    supports while it is set to the correct alignment. When the

    deck is supported on one line of bearings, the cantilevers

    are stabilized with temporary lock systems. Props and

    tie-downs from foundations are used with short piers. For

    taller piers, stability is achieved with brackets or tie-down

    arrangements comprising hydraulic jacks and vertical

    prestressing bars. The temporary pier-head lock systems

    are typically designed for a maximum of one segment out

    of balance. Sometimes two segments are erected simul-

    taneously on either side of the pier to reduce the load

    imbalance, though this requires gantries equipped with two

    winch trolleys. In some cases the gantry itself has been

    used to stabilize the cantilevers.

    Single-upper-truss gantries are sometimes equipped witha deviation tower at the central support and symmetrical

    stays that relieve the stresses in the truss (Fig. 11). The rear

    support leg is typically close to the rear pier to diminish

    the stresses in the front deck overhang. This solution is

    sometimes also adopted for span-by-span erection. In this

    case, the deviation tower is placed at the rear pier and the

    cable-stayed truss suspends the entire span.

    The deviation tower is integral to the main support legs and

    the truss. In the transverse plane, the tower is an A-frame

    with the anchor section of stay cables at the top, the truss

    at the middle, and two support legs that allow the precastconcrete segments to pass through. A base cross beam often

    resists the horizontal forces generated by the leg inclination.

    Truss towers and legs may be used to enhance rigidity.

    A single plane of cables is generally preferred. The use of

    numerous small cables facilitates their anchoring, and a fan

    layout simplifies pull adjustment from a work platform. A

    single support plane results in high torsion in the main truss,

    however, so a few cables may be anchored to the bottom

    chords to provide a torsional restraint. The winch trolleys

    are typically suspended from the bottom chords; H-shapes

    are used for the chords, and the wheels run onto the bottom

    Figure 12. Strand-jack liting o macrosegments is used or balanced-cantilever

    construction. Photograph courtesy o Thyssenkrupp.

  • 8/3/2019 Gantry Analysis

    13/22Winter 2010 |PCI Journal

    and noise-containment requirements. Truss box girders with

    one or two railroad tracks on the bottom slab and a roadway

    on the top slab have also been entirely precast.

    Full-span precasting results in rapid bridge construction

    and repetitive casting processes in factory conditions. The

    precast concrete units may be longer than 330 ft (100 m)

    when floating cranes are used for placement. Groundtransportation is rarely adopted for spans longer than 170 ft

    (50 m).

    The precasting plant is usually located near the bridge site

    to facilitate the transfer of the units. The units are removed

    from the forms as soon as the concrete has reached the

    required strength and are stored on temporary foundations

    for completion of prestressing, application of bearings, and

    finishing. The units are moved around the precasting plant

    and storage areas with heavy gantries or wheeled carriers.

    Rail-mounted gantries are often simpler to operate, while

    wheeled carriers provide more flexibility. The reinforce-

    ment cage is typically prefabricated complete with bulk-

    heads and inserted into the casting cell by the heavy lifters

    (Fig. 13).

    For viaducts over land, the spans are transported along the

    completed deck with special multiwheel carriers. The car-

    rier ofFig. 14 was custom designed for erecting 755 spans.

    After transporting the 1660 kip (7.4 MN), 103 ft (31.5 m)

    span to the front end of the bridge, the front trolley of the

    carrier moves forward along the 250 ft (76 m) support

    beam until reaching the lowering position. The support

    beam is then launched forward to the next span to clear the

    area under the carrier for lowering the span.

    The precast concrete spans are usually placed on bearings

    to simplify the erection process, but they may be made

    integral with the piers with in-place concrete connections.

    The units can also be joined together with in-place con-

    crete stitches to form a continuous structure.

    Design loads

    The load combinations used in the design of self-launching

    bridge erection machines are complex because of the dy-

    namic nature of loading. Because most units are designed

    in Europe, the discussion that follows is based on the

    FEM-1.001 standard for heavy lifters.4 The load classifica-

    tions and combinations can easily be adapted to different

    standards.

    The heavy lifters are grouped into classes in relation to the

    tasks they perform during their service life. The classifica-

    Figure 13. The preabricated cage or the entire span is being inserted into the casting cell.

  • 8/3/2019 Gantry Analysis

    14/22 4PCI Journal|Winter 2010

    tion determines the load-amplification factor to be used

    for the design of the structural components, which varies

    from C= 1.00 for A1-class units to C= 1.20 for A8-class

    units. The class of a unit is determined by the expected

    number of load cycles and the loading level. A load spec-

    trum relates the entity of loading to the number of cycles,

    and since most load cycles of these units take place at or

    near the load capacity, the spectral factor is typically high.

    However, the number of cycles is low, so these machines

    are often designed as A2-class units with load factor C=1.02.

    A similar classification applies for the mechanical compo-

    nents. The load-amplification factor varies from M= 1.00

    for M1-class units to M= 1.30 for M8-class units, and

    the bridge erection machines are often designed as M2- or

    M3-class units with M= 1.04 and M= 1.08, respectively.

    In both cases, the amplification factors are applied to the

    individual loads, and the results are then processed with

    the load factors for limit-state assessment prescribed by the

    design standard.

    The structural components are designed for static stresses

    in the least favorable load conditions, inertial forces gener-

    ated by vertical and horizontal movements of the load or

    the unit, and meteorological loads. The design loads are

    divided into four groups:

    forces that act regularly during the normal operations

    of the unit

    forces that arise occasionally in the unit in service

    exceptional forces in service and out-of-service condi-

    tions

    forces that arise during assembly and dismantling

    The regular forces include self-weight, service load, and

    inertial forces generated by load movements. The structural

    weight resulting from cross-sectional areas is typically in-

    creased by 30% to 40% to account for attached components,

    such as stiffeners and connections. The accuracy of correc-

    tion may be checked by weighting modules of the machine

    Figure 14. This wheeled span carrier has a sel-launching support beam or high-speed railway projects.

  • 8/3/2019 Gantry Analysis

    15/22Winter 2010 |PCI Journal

    during assembly. Concentrated loads represent specific

    components, such as rollers and electric generators.

    Service load includes lifted accessories, such as a gin

    block, hook, positioning transoms, and suspension bars.

    Vertical inertial forces derive from the sudden application

    or removal of the load and from the positive or negative

    accelerations during the vertical movements. The interven-tion of the emergency brakes in the case of an electrical

    blackout may be analyzed with dynamic analysis and

    assessed like any other service-limit-state (SLS) condition,

    though the elasticity of such demultiplied ropes diminishes

    the dynamic response significantly. The longitudinal iner-

    tial forces derive from the accelerations or decelerations of

    the winch trolleys along the runways.

    The occasional forces are impacts of the wheels of the

    winch trolleys against the runways, wind, snow, ice, and

    thermal differences. The impacts along the runways are

    often disregarded when the field splices in the rails are

    welded and grinded away at dismantling. Snow and ice are

    often disregarded in ordinary weather. FEM-1.001 requires

    designing the erection machines for temperatures from

    -4 F to 113 F (-20 C to 45 C).4

    The exceptional forces are out-of-service wind, load test-

    ing, impacts against end-of-stroke buffers or fixed obsta-

    cles, and the design earthquake. Impacts against buffers at

    the ends of the winch-trolley runways are often disregarded

    for translation velocity lower than 2.3 ft/sec (0.7 m/sec),

    provided that the runways are equipped with end-of-stroke

    switches. The effects are computed in relation to the de-

    celeration imposed on the winch trolley. The static stressesare often increased 25% for linear-spring buffers and 60%

    for constant-force hydraulic buffers.

    The design loads are grouped into three load conditions.

    Load condition 1 is the normal operational condition,

    which combines self-weight, superimposed dead load,

    service load inclusive of vertical dynamic amplification,

    and service load plus weight of winch trolley multiplied by

    the longitudinal-dynamic-amplification factor. All of these

    loads are then multiplied by the load-amplification factor

    resulting from the classification of the unit. Load condition

    2 is the operational condition in the presence of occasionalforces. It combines the actions of condition 1 with wind in

    service, snow and ice, and thermal differences. In the case

    of strong design wind, the longitudinal dynamic amplifica-

    tion can be different from the value for condition 1 because

    the action of wind can affect the starting and braking times

    of the winch trolleys. Load condition 3 is the action of

    exceptional loads. It considers the following combinations:

    self-weight, superimposed dead load and out-of-

    service wind

    self-weight, superimposed dead load, service load, and

    impacts against the end-of-stroke buffers

    self-weight, superimposed dead load, service load and

    design earthquake

    self-weight, superimposed dead load, wind in service,

    and assembly and dismantling operations

    Although conceptually similar to assembly and disman-

    tling, self-launching is typically assessed in the more

    demanding condition 2 because of the higher frequency of

    these operations. Load testing typically requires specific

    checks when the static test load is greater than 140% of the

    design load or the dynamic test load is greater than 120%.

    Both SLSs and ultimate limit states (ULSs) are assessed.

    SLSs correspond to the loss of functionality of the unit

    and are related to internal displacements of components or

    rotations of slip-critical connections. Unit load factors are

    applied to the three load conditions, and the resistance fac-

    tors are prescribed by the steel design standard. The ULSs

    correspond to critical conditions, such as rigid equilibrium,

    rupture of connections, yielding of structural elements,

    and local buckling. The three load conditions are handled

    with progressively lower load factors. According to CNR-

    10021,5 for example, it is LC - 1 = 1.50, LC - 2 = 1.34, and

    LC - 3 = 1.20.

    Most design standards do not distinguish between local

    and global (out-of-plane) buckling, and both conditions

    may be assessed like any other ULS condition. However,

    out-of-plane buckling of long sections of compressionchords is a riskier event than local buckling of a web panel

    or a secondary compression member. No post-critical

    domain exists in most cases, and the critical load is influ-

    enced by geometry imperfections that are difficult to de-

    tect. It is therefore common practice to assess out-of-plane

    buckling with higher load factors, LC-1 = LC-3 2.5.

    Modeling and analysis

    The optimum level of detail for the finite-element (FE)

    model of a launching unit is always a major concern. The

    more refined the model, the more accurate the results ofanalysis. Alternatively, the number of load and support

    conditions to analyze suggests using simple models to

    rapidly investigate all of the possible combinations. Simple

    beam models facilitate the research of the design-gov-

    erning load conditions and provide the stress magnitude

    to be expected from more refined analyses as well as the

    boundary conditions to assign to local models. Afterward,

    however, the different types of bridge erection machines

    require specific approaches to FE modeling and analysis.

    The twin-lower-girder units are typically supported on

    stiff pier brackets, and simple beam models often suffice.

  • 8/3/2019 Gantry Analysis

    16/22 5PCI Journal|Winter 2010

    cross beams and P-delta effects in the support towers. It is

    therefore necessary to check that the longitudinal stiffness

    of the support points of the main girders is higher than the

    breakaway friction of sliding bearings.

    Instability of main trusses

    Among the factors influencing the stability of a freestand-ing truss are the degree of fixity at the supports, a support

    condition prompting the truss to twist as it deflects later-

    ally, the lateral restraint exerted by the inclined diagonals

    on the compression chords, the location of concentrated

    loads, and the level of imperfections in the initial geometry

    of the truss.

    In the twin-truss units, these factors coexist and coalesce.

    The degree of fixity at the supports is low, the truss being

    supported at the bottom chords on flexible brackets or

    cross beams with out-of-node eccentricity and without

    cross diaphragms. The truss bends laterally and twists

    because of the deflections in the support cross beams, and

    the height of the truss amplifies the lateral displacements

    of the upper chord. The truss is typically high and narrow,

    so the lateral restraint that the inclined diagonals exert

    onto the upper chord is poor. The winch trolleys run along

    the upper chord, so the load is applied above the center of

    shear. Finally, the geometric imperfections may be signifi-

    cant because of the high number of field splices and the

    tolerances accumulated in second-hand equipment.

    The design standards normally recognize two types of

    instability; the first type is related to the overall sway of

    the structure (out-of-plane buckling) and the second type isrelated to deformations of a compression member between

    its end nodes (local buckling). Out-of-plane buckling can

    rarely be assessed with bibliographic values of the critical

    elastic moment in such complex structures. Investigating

    many buckling modes with complex numerical models in-

    volves long computational times, so only the first modes of

    out-of-plane buckling are typically analyzed numerically,

    and the local modes are checked with the load-magnifica-

    tion factors prescribed by the design standard.6

    Linear buckling analysis investigates the stability of a

    structure under a specified set of loads. The buckling modesdepend on the load, and instability must therefore be as-

    sessed for different load conditionsthat is, by reproducing

    the placement of the design-governing deck segments. The

    inertial load amplification also affects the buckling factor

    during the vertical and lateral movements of load.

    Excessive confidence with a launching gantry as a result

    of having already handled similar loads in the past may be

    a serious mistake. The stability of a gantry does not only

    depend on the entity of the load but also on how the load is

    applied to the unit. When a gantry handles a long precast

    concrete girder, the winch trolleys are at the girder ends

    Twin-lower-truss units are more complex, and 3-D models

    are recommended when the pier brackets are flexible or

    only some of the trusses support the deck segments. Mod-

    eling the support structures is also necessary when the unit

    is supported onto permanent piers and temporary props

    from foundations as the different flexibility and thermal

    inertia of supports affect load distribution and buckling

    factors.

    In a single-upper-beam gantry, the front support legs are

    close to each other to be supported by the pier while the

    rear legs are distant to feed the assembly area with precast

    concrete segments through the completed deck. In the pres-

    ence of so many technological requirements, the structural

    nodes are so complex (Fig. 15) that local 3-D solid models

    are often necessary. Simple beam models are used to

    analyze span erection, the deck-gantry interaction at the

    application of prestress, and self-launching.

    When a twin-upper-truss unit is supported by deformable

    cross beams, analyzing the unit as a single 3-D truss on

    rigid supports leads to imprecise results. Modeling the en-

    tire unit allows for evaluation of the effects of cross-beam

    deflections.

    An ideal truss should fulfill three basic conditions. The

    members of diagonals and chords are perfectly hinged

    at the truss nodes. This condition is never respected in a

    launching unit. The truss nodes are continuous, and when

    the unit is provided with assembly pins, these are typically

    located far from the nodes. The loads are applied at the

    truss nodes. Also this condition is never respected. Techno-

    logical requirements dictate the location of the suspensionpoints of segments, and the load applied by winch trolleys

    and support rollers migrates along the chords. The grav-

    ity axes of all members converging into a node cross at

    the geometric panel node. This condition could actually

    be met, though in most cases the convergence points of

    the diagonals onto the chords are eccentric to simplify the

    design of nodes.

    Depicting the stresses resulting from these geometry im-

    perfections requires accurate modeling. The model should

    describe the entire unit3-D trusses, support cross beams,

    and support towers. Out-of-node eccentricities and steps inthe bending plane at the changes of cross section should be

    considered, and end offsets should be used to account for

    the finite size of diagonal and chord intersections.

    The reliability of internal releases of degrees of freedom

    should be critically reviewed. The twin-upper-beam units

    are often supported on cross beams that are held up by

    steel towers. The main tower provides the longitudinal

    restraint, and the secondary tower may be equipped with

    sliding bearings. Before overcoming breakaway friction,

    the sliding bearings do not slide at all and thermal expan-

    sion of the main girders generates horizontal bending in the

  • 8/3/2019 Gantry Analysis

    17/22Winter 2010 |PCI Journal

    Figure 15. This shows the main structural node o an overhead gantry.

  • 8/3/2019 Gantry Analysis

    18/22 5PCI Journal|Winter 2010

    to reduce the risk of progressive collapse is to require

    insensitivity to local failure. In other words, local buckling

    of a primary load-carrying member must not cause col-

    lapse of the gantry or of a major part of it.

    Although the structural damage induced by local buckling

    is limited, the sudden stress redistribution generated by the

    loss of carrying capacity of a member is a highly dynamic

    process that requires analysis in the time domain.6 The

    resulting stresses can be assessed like any other ULS con-

    dition. Dynamic amplification is often low thanks to theflexibility of these units, and because the support rollers

    are long, several pairs of diagonals are typically involved

    in the load path at supports.

    Local buckling in the compression flange can trigger

    critical situations in the box-girder units because during

    launching the support sections are devoid of stiffeners and

    diaphragms. In the unit in Fig. 16, the left girder (on the

    right side in the photograph) was slightly misaligned left-

    ward so that when the front overhang was already 157 ft

    (48 m) long, the operator of the unit decided to realign it.

    A cross beam was placed near the front support saddle to

    and the load that they apply is one-half of the total weight.

    When the winch trolleys operate near each other (for ex-

    ample, in a heavy pier-cap segment), the total load may be

    similar but the stresses in the compression diagonals may

    be much higher.

    Overloaded members may buckle suddenly, so careful

    inspections are necessary during assembly and at regular

    intervals during the use of a launching unit. Damaged

    diagonals must be reinforced or replaced even when they

    apparently are in noncritical locations because the loadconditions are so varying that they might become the criti-

    cal element of the structure. The cross diaphragms should

    also be inspected frequently.

    The stability of a launching gantry depends on the stability

    of members against local failure and on the unit response

    to local failure. Local buckling of a primary load-carrying

    member is often critical in the support towers, while stable

    alternate load paths often exist in such redundant trusses;

    however, local buckling may trigger a chain reaction of

    failures causing progressive collapse. The simplest ap-

    proach to ensure the robustness of a launching gantry and

    Figure 16. The buckling o the compression fange at the supports is due to the wrong operation.

  • 8/3/2019 Gantry Analysis

    19/22Winter 2010 |PCI Journal

    alignment required lateral shifting of the base hydraulic

    cylinders of the support frame to align them with the

    bridge webs, so the cross beam was windowed in its end

    sections. As a result, the torsion constant in the two 12 ft

    (3.6 m) windowed portions of the cross beam became

    about one-thousandth of the original box-section constant.

    When the support cylinders are at the ends of the crossbeam, the two vertical load paths are three-aligned-hinge

    schemes where the central cylindrical hinge has minimal

    rotational stiffness because of the low torsion constant of

    the windowed section (Fig. 17). The scheme is more stable

    when the support cylinders are under the inclined legs

    of the W-frame, so buckling was likely to occur only in

    curved bridges. The buckling factor was as low as LC - 1 =

    0.6, and triangular box stiffeners were applied to increase

    the torsional constant and stabilize the frame.

    The design of connections has a fundamental influence

    on the strength and stability of the support towers. When

    the legs are always compressed and the contact between

    column and end plate is machined, the welds at the ends of

    the module are subjected to minimal stresses. In the case

    of load reversal, therefore, the end welds are often de-

    signed for tension and the much higher compression force

    is resisted by the machined contact. In the case of roughly

    machined contacts, however, the weld can break under the

    compression force, and at load reversal, the column can

    detach from the end plate.

    Launch and lock systems

    In light units such as lifting frames, the launch stresses arerelatively low and the operations are simple and intuitive.

    In heavy units such as long gantries, the launch stresses

    are so great that they often govern the design of primary

    components of the unit. The launch stresses depend on the

    launch procedures, and launching heavy units involves

    sequences of operations that are typically more complex

    the heavier the unit is.

    Light gantries for erection of precast concrete girders and

    many heavy units use assemblies of cast-iron rolls on

    rocking arms for the launch bearings. The number of rolls

    depends on the load and the diameter. It is usually two,four, or eight, with progressively higher costs. Lateral

    guide may be ensured with rolls acting against the bottom

    flange or a steel rail welded under the web.

    The use of cable bearings is less frequent. The support

    reaction is distributed by a tensioned ring cable that

    directly supports the rolls, so these bearings are thinner

    and more stable than the roll bearings with rocking arm.

    When the launch occurs along a curve, cable bearings

    may be combined with orientation ball-plate bearings and

    shifting bearings, which respectively orient and align the

    rolls under the webs. Cable bearings may also be placed

    support two flat jacks on PTFE plates. The jacks were to

    be inserted under the box-girder webs to then pull the jacks

    and box girder rightward along the low-friction contact.

    However, the procedure was misunderstood and after rais-

    ing the box girder with the flat jacks, the PTFE plates were

    inserted between the box girder and the main support jacks.

    In the initial stage of realignment, the box girder resisted

    the transverse bending generated by the increasing ec-

    centricity in the support reactions. Eventually, the outer

    flange and the central flange panel buckled upward. This

    generated two low-friction inclined planes that gave rise

    to uncontrolled rightward sliding of the box girder. Flange

    buckling further increased, and both webs also buckled.

    Collapse was avoided because the end block of the cross

    beam stopped the box-girder stroke when the left jack (on

    the right in the photograph) was already almost disengaged.

    Support member instability

    The weight of the gantry and the service load are trans-

    ferred to the bridge foundations through complex load

    paths that typically include adjustable components, hy-

    draulic systems, and pivoted legs. These support systems

    are affected by specific forms of instability. The pivoted

    support legs, in particular, are among the most delicate

    components of a launching gantry.

    A gantry had a pivoted W-shaped rear support frame,

    where the base cross beam originally had a box section

    over the entire width. Reusing the gantry on a curved

    Figure 17. This gure shows a rear portal rame with shiting support pistons.

  • 8/3/2019 Gantry Analysis

    20/22 5PCI Journal|Winter 2010

    the launch. Therefore, the equipment can be designed for

    the launch loads and overloaded without excessive worries

    if necessary. The electronic control of the hydraulic plant

    permits synchronization of launchers and the ability to set

    limit pressures avoids overloading. Launch-cycle automa-

    tion with end-of-stroke switches facilitates the operations

    and increases the launch speed.

    When approaching the pier, the front end of the gantry

    is deflected downward. In the lightest gantries, the front

    deflection is recovered by inclining the bottom flanges

    to force progressive realignment (Fig. 2). The alignment

    force rarely overloads the support cross beams, but the

    launch bearings must be anchored to avoid displacement

    or overturning. The launch bearings must also be articu-

    lated to accommodate large rotations. Realignment may

    also be achieved with long-stroke hydraulic cylinders that

    move steel arms hinged to the nose tip. When the lifting

    arm reaches the pier, it is lowered down and forced until

    recovery of the elastic deflection. Hybrid solutions are also

    possible where the bottom chords are rounded and a front

    hydraulic cylinder recovers only a portion of the cantilever

    deflection.

    Several overhead gantries are designed for launching their

    own support systems. In this case, the front tip is often

    equipped with a vertical arm that during launching takes

    support at the front pier to stabilize overturning. After

    forcing the front arm, the winch trolley places the pier cap

    segment and then advances the front support cross beam

    and places it onto the segment, and the launch can restart.

    Load testing

    Bridge erection machines are typically load tested upon

    completion of the first assembly. New load tests and

    comparisons with previous tests should also follow every

    major reassembly of the unit.

    Launching gantries are subjected to static and dynamic

    tests. The static test load is 10% to 40% higher than the

    design load of the unit. Load testing takes place in the ab-

    sence of wind and consists of slowly lifting a progressively

    increasing load until reaching the full test load. The load

    is lifted at different locations to reach full design stressesin the critical components of the unit, the deflections are

    compared with the theoretical values, and deflection re-

    covery is also checked. The dynamic test load is typically

    10% to 20% higher than the design load. The movements

    of the gantry are tested individually at increasing velocities

    until they reach the maximum values. Blackout tests can

    also be performed to measure the dynamic response to the

    intervention of the emergency brakes.

    onto hydraulic jacks for accurate distribution of the support

    reactions and the creation of torsional hinges.

    Sliding bearings may also be based on polytetrafluoroethyl-

    ene (PTFE) skids. The bottom flange typically slides along

    lubricated PTFE surfaces without interposition of stainless-

    steel sheets. Dispersal of the support reaction into the webs

    may be facilitated with multilayered elastomeric blockscovered with a dimpled PTFE plate. These blocks are

    aligned in rocking frames on ball-and-socket articulations or

    transverse pins. At the current state of practice, roll bearings

    and sliding bearings are complementary. Sliding bearings

    are fit for slow launching of high loads, while roll bearings

    are fit for medium loads and high launch velocities.

    The launch and lock systems have a substantial impact

    on the stability and safety of a launching gantry. Launch-

    ing is achieved with one of three methods. In the simplest

    and oldest units, a winch trolley is anchored to a pier and

    its translation winch moves the main trusses to the next

    span. In more recent units, long-stroke hydraulic cylinders

    lodged into the support saddles push the unit forward by

    acting against racks fixed to the bottom flanges. In the

    most advanced units, the thrust force is transferred by

    friction using hydraulic launchers that directly support the

    girders.

    The light gantries for precast concrete girders are usually

    moved with winches, though this solution presents some

    disadvantages, especially when launching along inclined

    planes. The longitudinal grade of many bridges is close to

    the friction coefficient of the rollers, so when launching

    occurs with new or well-greased rollers it can be necessaryto brake the unit to prevent uncontrolled sliding. Braking

    of any component of the tow system also leaves the unit

    unrestrained on low-friction supports. This requires design

    precautions and the adoption of higher safety factors,

    which involves oversizing equipment and operating more

    slowly.

    Higher thrust forces require mechanical transmission by

    means of launch cylinders acting against racks fixed to the

    bottom chords, as in Fig. 4. These launch systems are very

    efficient in the case of horizontal launching, and they also

    permit backward pulling of the unit. When launching upgrade, the unit must be locked during the return stroke of

    the launch cylinders to avoid uncontrolled backward slid-

    ing. Two adjacent launch cylinders are used in this case.

    In the more refined units, the launch force is transferred

    by friction (Fig. 6). For the unit to be trailed, it is neces-

    sary that the ratio of the thrust force to the support reaction

    onto the launcher be smaller than the friction coefficient

    between the two steel surfaces. The support reaction varies

    during launching, so two synchronized launchers are gen-

    erally used. Friction launchers offer high intrinsic safety

    because the worst consequence of hydraulic faults is halt of

  • 8/3/2019 Gantry Analysis

    21/22Winter 2010 |PCI Journal

    Conclusion

    The bridge industry has seen unbelievable progress in the

    past decades. New means of analysis and a better knowl-

    edge of mechanics of materials have permitted new struc-

    tural solutions and are at the basis of architectural wonders

    that will represent our legacy, as a bridge community, to

    the next generations. Such progress, however, is also theresult of the technological advance in the erection methods

    for precast concrete bridges.

    The technological aspects of erection will have a more and

    more marked influence on the modern bridge industry, and

    construction of precast concrete bridges is mostly based on

    the use of self-launching machines. In spite of the technical

    skill and the quality-assurance and quality-control pro-

    cesses of many manufacturers of launching units, accurate

    custom-written technical specifications and independent

    checking of design may be precious tools in making better

    and more circumstantiated decisions and dodging avoid-

    able mistakes.

    References

    Rosignoli, M. 2002.1. Bridge Launching. London, UK:

    Thomas Telford.

    American Segmental Bridge Institute (ASBI). 2008.2.

    Construction Practices Handbook for Concrete Seg-

    mental and Cable-Supported Bridges. Phoenix, AZ:

    ASBI.

    Hewson, N. 2003.3. Prestressed Concrete Bridges:Design and Construction. London, U.K.: Thomas

    Telford.

    Federation Europeenne de la Manutention FEM 1.001.4.

    1987.Rgles pour le Calcul des Appareils de Levage.

    [In French.]

    CNR 10021. 1985.5. Strutture di Acciaio per Apparec-

    chi di Sollevamento. Istruzioni per il Calcolo, lEsecu-

    zione, il Collaudo e la Manutenzione. [In Italian.]

    Rosignoli, M. 2007. Robustness and Stability of Lau-6.nching Gantries and Movable Shuttering Systems

    Lessons Learned. Structural Engineering Internatio-

    nal, 02/2007: pp. 133140.

  • 8/3/2019 Gantry Analysis

    22/22

    About the author

    Marco Rosignoli, Dr.Ing., P.E.,

    has 27 years of experience inbridge design and construction.

    For 15 years he has served as

    construction manager, project

    manager, and bridge-department

    lead for prime European bridge

    contractors. After assisting contractors on complex

    bridge projects in 19 countries and 4 continents for 9

    additional years, he has served as chief bridge

    engineer at HNTB Corp. since 2006.

    Rosignoli has been the independent design checker of

    many self-launching bridge-erection machines. Expert

    in bridge construction technologies, he has written two

    books and more than 60 publications. He is currently

    chairing the working group WG-6, Bridge Construc-

    tion Equipment, of the International Association for

    Bridge and Structural Engineering.

    Synopsis

    Launching units are complex and delicate structures.

    They resist high loads on long spans under the same

    constraints that the obstruction to overpass exerts

    onto the final structure. They are adaptable for reuse

    on different projects. They must be as light as pos-sible, which involves designing for high stress levels

    in different load and support conditions, and they are

    assembled and dismantled many times and reused by

    different crews.

    For all of these reasons, self-launching bridge erection

    machines are typically purchased or leased based on

    purpose-written technical specifications, their design

    is subjected to independent checking, load testing isfrequent at the end of assembly, and the operations are

    ruled by written procedures.

    Little has been written on these machines in spite of

    their cost, complexity, and sophistication. This article

    illustrates the main features of self-launching bridge

    erection machines and includes some lessons learned.

    Keywords

    Bridge, girder, launching gantry.

    Review policy

    This paper was reviewed in accordance with the

    Precast/Prestressed Concrete Institutes peer-review

    process.

    Reader comments

    Please address any reader comments to PCI Journal

    editor-in-chief Emily Lorenz at [email protected]

    or Precast/Prestressed Concrete Institute, c/o PCI

    Journal, 209 W. Jackson Blvd., Suite 500, Chicago,

    IL 60606. J