chapter 8 - iee - draft

Upload: ram-p-mony

Post on 05-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Chapter 8 - Iee - Draft

    1/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    8.0 INITIAL ENVIRONMENTAL EXAMINATION (IEE)

    8.1 INTRODUCTION

    The Ministry of Energy and Water (MEW) of the Islamic Republic of Afghanistan is

    intending to utilise resources available under the World Bank-funded Emergency

    Irrigation Rehabilitation Project (EIRP) The water resources schemes being targeted

    under the project are small to medium dams, supplying nearby irrigable areas and

    provision of other water resources infrastructure such as micro or mini-hydro

    facilities. The government strategies behind such activities are to develop long termstrategy to manage water resources which will in turn help in increasing availability

    and reliability of water supplies, improving water use efficiency, eliminating

    unsustainable land use practices, expanding the irrigated command area and

    increasing sustainable agricultural production in Afghanistan.

    This IEE has been prepared as part of Pre-Feasibility Studies &Priority Ranking of

    22 Small/Medium Dam Sites in Faryab, Jawzjan, Saripul, Balkh and SamanganProvinces. The IEE at this pre-feasibility stage addresses the subjective

    environmental impacts due to construction of the proposed project and also the

    environmental management and monitoring aspects relating to project

    implementation. The project proponent is Ministry of Energy and Water (MEW).

    8.2 PROJECT LOCATION

    The proposed project,sites are located in the northern part of the Afghanistan

    covering five provinces namely, Faryab, Jawzjan, Saripul, Balkh and Samangan

    province.. The list of the site along with other details such as province, latitude,

    longitude, village name and district are given in the table 8.1.. It can be seen that out

    of 22 project sites 10 sites lie in Samangan province, five sites in Faryab province,

    two in Balkh province, three in Saripul province and two in Jawzjan province. The

    elevation of the project sites range from less than 500 m to more than 2500 m aMSL

    Chapter-8 : IEE 8-1 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    2/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Table 81: Location Details of 22 identified dam sites for PFR and/or FR study

    Chapter-8 : IEE 8-2 WRD, WAPCOS LimitedMarch-2012

    S.N. Name ofProposed Dam

    Province District Village Latitude Longtitude

    1 Shamar Samangan Aybeek center Shalaktu 36 14' 5.7" 68 13' 19"

    2 Quran dara Samangan Hazrat Sultan Sharik yar 36 25' 21" 68 9' 34.5"

    3 BatoBaba(Quchandara )

    Samangan Dar-e- Yousif Mahadun Tur 36 13' 42.8" 68 4' 36.8"

    4 Chashma Dara Samangan Firoz Naghjir 36 29' 39.5" 67 40' 26"

    5 Shiraba Dam Sar-e-Pul Center 36 08' 33" 66 09' 5"

    6 Masjet Sabz Sar-e-Pul Sang charak Masjet Sabz 35 50' 49" 66 19' 30"

    7 Gudara Dam Sar-e-Pul Center 35 49' 43.8" 66 22' 57.3"

    8 Pascha Dam Balkh Char Kant 36 20' 37.9" 67 26' 19.9"

    9 Shakrak Faryab Kohistanat Bandar 35 19' 38" 64 34' 45.1"

    10 Yati Quluq Faryab Qaisar Nareen 35 47' 23"' "

    64 20' 38"' "

    11 Toi Mast Dam Faryab Qaisar 35 35' 20.5" 64 15' 17.1"

    12 Darz Aab Dam Jozjan Darz Ab 36 0' 13.8" 65 21' 52.5"

    13 Fayz Abad Dam Jozjan Fayz Abad 36 29' 33" 66 20' 42"14 Shah Abdullah Samangan Dar-e- Yousif Mahadun Tur 36 0' 26" 67 35' 7.4"

    15 Anbar Samangan Royia dow AabNawaz ah waroyai

    35 43' 50" 68 2' 5.24"

    16 Jahil Kala Samangan Upper Dar-e- 35 36' 53" 67 7' 54.6"

    17 Tangi Shadyan Balkh Mazar Shadyan 36 34' 6.3" 67 8' 31"

    18 Pasha Dara Faryab Pashtoon Kot Pasha Dara 35 53' 09" 64 48' 30"

    19 Dahane Dara Faryab Pashtoon Kot Daraghzi 35 49' 34" 64 51' 54"

    20 Kol e Rehmat Samangan Royee Doad Qarghana 35 33' 0" 68 0' 24"

    21 Dara e Negaar Samangan Royee Doad Royee 35 45' 08" 67 53' 0"

    22 Ab e Keli SamanganKhuram &Sarbagh

    Cloor e Baala 35 52' 22" 67 56' 48"

  • 7/31/2019 Chapter 8 - Iee - Draft

    3/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    8.3 OBJECTIVES

    The Phase 1 of assignment is aimed to formulate 22 water resources schemes

    comprising small to medium dams, diversion works based on pre-feasibility grading

    studies and investigations. These schemes are to be evaluated on a common basis

    using criteria that are to be evolved by the Consultant in consultation with water

    management department, Islamic Republic of Afghanistan (IRA) and with approval of

    the Ministry of Energy and Water (MEW), IRA. This preliminary assessment will

    target schemes which are superior technically and easy to implement, which give

    better returns and have minimal environmental and social impacts. In the second

    phase, at the feasibility level, Environmental and Social Assessment (ESA) will be

    carried out for the 10 most technically suited schemes. The brief scope of work is

    given below:

    Review of available reports, maps and other existing literature

    Undertake an Initial Environmental Examination and an Initial Social

    Assessment to rank the 22 potential sites, at prefeasibility level

    Carry out the Environmental and Social Assessment, at the

    feasibility stage, for the 10 most technically suited sites

    The main objective of the IEE is to identify the likely impacts, both positive and

    negative on the environment caused due to implementation of the proposed

    schemes. The basic objective is to minimize the negative environmental and social

    impacts of such development. In order to achieve this objective, all negative impacts

    have to be mitigated and the costs of doing so should be included in the economic

    analysis of the project.

    Chapter-8 : IEE 8-3 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    4/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    8.4 METHODOLOGY FOR IEE

    The IEE has been prepared following the methodology laid down in the

    Environmental and Social Management Framework (ESMF) prepared for the

    Irrigation Restoration and Development (IRD) Project of the Islamic Republic of

    Afghanistan, WB Guidelines, Law on the Protection of Nature of the Government of

    Afghanistan, and discussions with the National Environmental Protection Agency

    (NEPA) and MEW, IRA. The experiences of other studies in preparing IEEdocumentation have also been reviewed.

    This IEE was prepared based on reconnaissance field visit and review of secondary

    data. This report covers the description of existing environmental conditions,

    subjective assessment of impacts caused by the project, recommended mitigation

    measures and monitoring plan for the Important Environmental Components (IECs).

    The environmental impacts were considered for activities that are expected to take

    place during pre-construction, construction and operation phases of the project.

    This IEE Study is the result of an intensive inter-disciplinary effort. The data from the

    following disciplines were reviewed and incorporated into this study.

    - Climate

    - Geology

    -Seismology

    -Hydrology

    -Sociology

    Chapter-8 : IEE 8-4 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    5/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    8.4 POLICY, LEGAL AND REGULATORY FRAMEWORK

    The National Environmental Protection Agency (NEPA) is the prime environmental

    regulatory and approval authority in Afghanistan .It was constituted in 2005. The Act

    under which NEPA was established specifies that the proponents of any project,

    plan, policy or activity must submit to NEPA a preliminary Environmental

    Assessment, in order to allow NEPA to determine the associated potential adverse

    effects and possible impacts. After reviewing the preliminary assessment, NEPA can

    either authorize - with or without conditions the project, plan, policy or activity,

    provided that the potential adverse effects of the proposed activities on the

    environment are unlikely to be significant. Otherwise, NEPA may require the

    proponents to submit a detailed environmental impact statement including a

    comprehensive mitigation plan for its review and approval.

    8.4.1 The Environment Law and the EIA Regulation for IRDP project

    It is envisaged that all subprojects and activities of the IRD project fall under

    Category 2, which comprises activities with potentially adverse, site specific impacts,

    primarily of non-irreversible nature.

    The Afghan EIA Regulation requires for Category 2 that the project proponent and

    owner should submit an application form and a screening report to NEPA. The

    documents should be meeting the agency is required technical guidelines for thescreening report, i.e., description of the activities, completion of Rapid Environmental

    Assessment (REA) to identify potential impacts and their sources and the relevant

    mitigation measures, public participation in the assessment process and etc.

    Once the application form and other relevant documents are submitted to NEPA

    according to the agency EIA regulation NEPA would: (i) issue a Certificate of

    Compliance, with or without conditions, (ii) advise the applicant in writing to review

    Chapter-8 : IEE 8-5 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    6/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    the technical reports and address the concern of NEPA. According to the EIA

    regulation NEPA would grant a Certificate of Compliance or would refuse to do so

    and provide written reasons for the refusal to the applicant. The EIA regulations are

    silent on NEPA rules during implementation of the activities and projects.

    The NEPA of Afghanistan is the responsible agency to give environmental clearance

    for various development projects. The Project components shall be in accordance

    with the environmental requirements of the Government of Afghanistan & World

    Bank Guidelines This IEE is prepared in accordance with the guidelines laid down in

    the ESMF prepared for the IRD Project of the Islamic Republic of Afghanistan, The

    National Environmental Impact Assessment Policy of the Islamic Republic of

    Afghanistan and WB Guidelines.

    8.4.2 Environmental Policies, Laws and Regulations:

    The National Environmental Impact Assessment Policy 2007 of IRA indicates that a

    project is classified Category 1 if it is likely to have significant adverse environmental

    impacts that are sensitive, diverse, or unprecedented, and affects an area broader

    than the sites or facilities subject to physical works.

    A project is classified as Category 2 if its potential adverse environmental impacts

    on human populations or environmentally sensitive areas (e.g. wetlands, forests,

    grasslands and other natural habitats) are less adverse than those of Category 1

    projects. These impacts are site specific, and few are irreversible.

    Relevant Government environmental legislative documents are as follows:

    -Water Law 2009

    -Environmental Law 2007

    -National EnvironmentalImpact Assessment Policy 2007

    -The Law on Land Expropriation 2005

    Chapter-8 : IEE 8-6 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    7/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    -Law on the Preservation of Afghanistans Historical and Cultural Heritage, 2004 The

    -Law on Pasture and Public Land 2000

    The IEE have been prepared considering these policies, rules and guidelines.

    8.4.3 World Bank Guidelines

    The World Banks OD 4.01 Environmental Assessment of January 1999 indicatesthe kind of projects which are categorized as A projects and for which a full

    environmental assessment (EA) is required. These projects include most of those

    having large population displacement impacts. Category B projects do not require a

    full EA but do require some environmental analysis. As the present study is a pre-

    feasibility level investigation, an IEE is prepared. The sections most relevant to

    Environmental Assessment have been reviewed for the present study:

    OP/BP 4.01 Environmental Assessment

    OP/BP 4.04 Natural Habitats

    OP 4.07 Water Resources Management

    OP/BP 4.36 Forestry

    OP 4.37 Dam Safety

    8.5. PROJECT BENEFITS-ENVIRONMENTAL CONSIDERATIONS

    The major benefit associated with the construction of The Proposed Project is the

    availability of a more reliable water supply for irrigation,hydropower and domestic

    uses in the project area. The dam will create a reservoir which may be used for

    fishery and enhance the potential for increased agricultural production in the area

    Chapter-8 : IEE 8-7 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    8/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    downstream of the reservoir. The Project will improve terrestrial and aquatic

    ecology, and overall biodiversity in the project impact area; stabilize irrigation

    systems in these district. In addition, the objectives are to improve living conditions

    and quality of life and to reduce poverty among people living in rural areas where

    water availability and access to water are matter of serious concerns. The Project

    will help the district to develop effective and sustainable management of irrigation

    and to ensure reliable distribution of water. The project will result in reduced risk of

    water-borne diseases with the better access to adequate potable water supply in the

    area.

    8.6 DESCRIPTION OF THE ENVIRONMENT

    8.6.1 Physical Environment

    Topography

    Mountains dominate in the project area. The topography is characterized by valleys,

    mountains, valley margins which are insignificantly vegetative with alluvial deposits

    draining from the river.

    Soil and Geological Characteristics

    The river valley is covered with flood plain deposit of thickness 1 m. The deposit consists ofsub-rounded to rounded cobbles, pebbles and gravel of various igneous and sedimentary rocksin the matrix of sand and silt. Some boulders are deposited along the flood plain (photo 3.1).

    The hill slopes are stable and free of any major geological disturbances.

    Seismology

    The northern, northeastern and southeastern parts of the country are characterized

    to have a high to very high seismic risk, while the western and central parts have a

    low to moderate seismic risk.

    The Machalgho dam site is located in the high hazard zone to the very high hazard

    zone according to the seismic hazard map of the country.

    Climate

    The climate of the project area is dry and temperate. Winter temperatures are low

    Chapter-8 : IEE 8-8 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    9/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    and the temperature can go below -15C for many weeks during winter. In the project

    area, annual maximum monthly mean temperature is 10.9 C and the minimum is

    -1.1C. Climate profile of the nearby Gardez meteorological station is given in Table

    8.2

    Table 8.2: Climatic Condition of the Gardesh (Average of 2004-07)

    Month T max T min T mean Relative

    Humidity

    Rainfall

    oC oC oC % mm

    Jan -0.7 -24.5 -12.6 77.05 22.5

    Feb 3.8 -9 -2.6 80.63 57.3

    Mar 6.6 -2.6 2 58.5 71.4

    Apr 11 -2.4 4.3 39.64 42.1May 16.6 8.7 12.65 24.4 16.8

    Jun 17.6 9 13.3 24.26 52.2

    Jul 22.9 12.4 17.65 30.51 1.8

    Aug 19 13.2 16.1 42.53 26.7

    Sep 14.4 5.8 10.1 28.37 2.6

    Oct 12.8 2.2 7.5 33.87 0.8

    Nov 6.2 -5 0.6 62.5 33.1

    Dec 0 -20.4 -10.2 76.27 46.2

    Mean\Total 10.9 -1.1 4.9 48.2 362.4

    Annual rainfall of the project area is observed to be 362 mm. Three-fourth rainfall of

    the annual rainfall is occurred in the first half of the year (January to June)

    Hydrology

    The main source of water in the project area is Mechalghu River. The average

    dependable flows are 13.13 M cu m. The level of water in the rivers oscillates

    greatly. 70% of the flow is observed in the month of March July. The highest flow

    is in April and May (3.3-5.6 cumec) and the lowest flow is observed in January (1.25

    cumec). To facilitate the augmentation of water, a dam has been proposed across

    the Mechalghu River near Wach Sakh Kala village. The catchment area of the river

    at the point of diversion is about 66.85 km2.

    3.4 Noise

    No noise monitoring data is available in the project area and it is expected that noise

    quality will conform to international noise standards with low background noise level.

    Chapter-8 : IEE 8-9 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    10/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    The field visit also reveals that vehicular traffic, which is low in volume, is the main

    source of noise level.

    High noise levels can interfere with communication, damage hearing, cause

    sleep deprivation, and disrupt concentration. Noise is measured logarithmically in

    decibels (dB). Due to its logarithmic scale, if a noise increases by 10 dB, it

    sounds as if the noise level has doubled. If a noise increases by 3 dB, the

    increase is just barely perceptible to humans. Often sound is measured as

    "Aweighted;"

    this filters out low frequency sounds which humans are unable to hear

    and is more indicative of the noise people actually hear. In general, the Sound

    Pressure Level from an outdoor noise source radiates out from the source,

    decreasing 6 dB per doubling of distance. Thus, a noise measured at 80 dB 50

    feet away from the source will be 74 dB at 100 feet, 68 dB at 200 feet, and 62 dB

    at 400 feet.

    Mazar-e-Sharif Environmental AssessmentMarch 29, 2007

    Due to the potential for sleep disruption, loud noises between 10 p.m. and 7 a.m.

    are normally considered more annoying than loud noises during the day.

    Therefore, community noise levels are often measured by the Day-Night Average

    Sound Level (Ldn), which is an average of noise in a 24-hour period; however, a

    10 dB penalty is added to noise between 10 p.m. and 7 a.m. In the United States,

    there is a goal of 55 dB for Ldn in outdoor spaces.

    3.4.1 Affected Environment

    The area surrounding the site is rural.

    3.4.2 Environmental Consequences

    3.4.2.1 Construction lmpacts

    Dam construction would require equipment for excavation, such as backhoes,

    front loaders, bulldozers, and dump trucks; materials-handling equipment, such

    as cement mixers and cranes; and, compressors, generators, and pumps. Noise

    Chapter-8 : IEE 8-10 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    11/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    generated from this type of equipment would range from 87 to 99 dBA at 30 feet

    (Cowan, 1994), which would be equivalent to 57 to 69 dBA at 1,000 feet.

    Construction is expected to temporarily increase noise levels in the vicinity.

    Given the distance to the nearest homes, construction noise from the dam is of no

    concern.

    Construction activities would also increase traffic on local roads. Large trucks

    would produce noise levels around 89 dBA at 30 feet (Cowan, 1994), which is

    equivalent to 77 dBA at 120 feet.

    3.4.2.2 Operational lmpacts

    Dam construction and development would generally increase noise levels. In

    addition, generator use and increased traffic will contribute to noise levels. This

    increase would depend on many factors, including size of the park, types of

    facilities, use of noise control devices, number of employees, and the amount of

    increased traffic. However, given the distance to the nearest homes, operational

    noise from the dam is of no concern.

    Mitigation Measure:

    Project engineers will examine several approaches to cutting generator noise.

    Noise barriers and air intake silencers can provide significant noise reduction.

    Noise also can be cut through modifications to a generator's exhaust, intake,

    ventilation, enclosure and mounting. Sound attenuation baffles can be installed

    on the cooling air inlet and outlet.

    Another possible approach to reducing noise is limiting the hours of operation.

    When power demands drop, generator operation also may decrease.

    3.5 Cultural and Historical Resources

    3.5.1 Affected Environment

    Mazar-e-Sharif and Balkh Province have a long history of human occupation.

    There is, however, no record of the site hosting cultural or historical resources.

    3.5.2 Environmental Consequences

    Chapter-8 : IEE 8-11 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    12/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Cultural and historical resources should not be affected by construction of the

    proposed dam.

    .

    3.6 Air Quality

    Afghanistan has not yet established its ambient air quality standard. There were no

    data available on ambient air quality of this area. However, air pollution does not

    constitute a major problem in the study area but its reliance on inexpensive energy

    has created some issues. Most vehicles run on diesel fuel, and household energy

    often relies on burning wood and other materials. As a result, air pollution in urban

    areas is visible and may pose health issues.

    Apart from wind borne dust during dust storms, ambient air quality in the project area

    is likely to be good based on the following characteristics: (i) all the dam sites will be

    situated in the rural areas or barren lands (ii) there are no industrial activities existing

    in the project area. In the absence of site specific air quality data, the only reliable

    means to assess the air quality in the project area is the clear visibility of thesurrounding area. As all the dams will be situated in the rural areas having no major

    industry and other air polluting object in the surroundings, it can be concluded that

    the air quality in the project area is generally good and does not contain any

    materials harmful to the environment.

    The major factors affecting the air quality in the Project area are dust emissions from

    fuel combustion and brick kilns. Dust from the unpaved roads is the major source of

    air pollution in rural areas.

    Presently, unleaded petrol is sold in Afghanistan. There is hardly movement of 1 or 2

    vehicle in a day on this project road because it is cart road and this is situated in

    rural area, so that possibility of lead pollution along the road is negligible.

    The project area is not characterized by any formal or informal industrial activities to

    Chapter-8 : IEE 8-12 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    13/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    create considerable air pollution, but smog and heavy concentrations of airborne

    particulates are common phenomenon in the project influence area due to dust.

    Within the project areas there are no industries, so air quality is considered relatively

    clean.

    Climate factors can affect air quality. In the project area, March and April are the

    wettest months at roughly 40 millimeters/month.

    The month of August is the driest, averaging 0 millimeters/month. The average

    monthly air temperature ranges from 39F in January to 90F in July.

    3.6.1 Affected Environment

    A 2004 article highlighted some of the growing air pollution problems affecting

    Afghanistan (Saba, D., April 2004). Earlier, the January 2003 UNEP Post-

    Conflict Environment Assessment Report carried out air sampling at Mazar-e-

    Sharif and other sites in Afghanistan. At all sites, results indicate high amounts

    of dust and concentrations of polyaromatic hydrocarbons (PAHs). Benzo-apyrene

    is one of the pollutants detected and is believed to increase risk of lung

    cancer. The highest concentrations were detected in Mazar-e-Sharif, where

    analyses show 13.6 Nglm3. The World Health Organization (WHO) average

    values for urban areas range from 1 to 10 Nglm3.

    3.6.2 Environmental Consequences

    Temporary and intermittent air quality impacts would be associated with site

    preparation and construction activities. Air pollution from construction equipment,fugitive dust emissions from operation of this equipment during dry conditions,

    and increased traffic during construction would cause some minor and temporary

    air quality issues. However, the project team can use reasonable precautions to

    prevent fugitive dust emissions.

    3.7 Water Quality

    Chapter-8 : IEE 8-13 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    14/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    There is no water quality data is available in project area. Any site work on

    infrastructure will be consistent with applicable codes and standards. When codes

    and standards are in conflict, the most stringent shall apply. Further, all work shall be

    designed and constructed to meet all Afghanistan codes, standards and laws. In the

    absence of Afghanistan codes, standards and laws, internationally recognized

    codes, standards, and laws shall be used.

    3.7.1 Affected Environment

    3.7.1 .I Surface Water

    Mazar-e-Sharif is located in between the Rud Khana-e Shahi (Shahi River) and

    the Balkh River. The Balkh river, with its 18 tributaries, makes it independent of

    other water sources of the region.

    Balkh province consists of Balkh, Charbulak, Sholagra, Daulatabad, Nahri Shahi,

    Chimtal Shoortipa, Charkent and Mazar-e-Sharif districts. Most of the population

    in these districts uses water from irrigation canals as a drinking water supply. In

    some areas, water is supplied through shallow and deep groundwater wells.

    UNEP has reported that there is a considerable need to extend the city's supplynetwork. A World Bank project is expected to reconstruct and rehabilitate the

    existing network only. Extending the network will require identifying groundwater

    resources of proper quality and quantity.

    3.7.1.2 Groundwater

    There is a general lack of understanding about the underlying geologic conditions

    in the Mazar-e-Sharif region, which complicates groundwater resource

    management. While available information is limited, ongoing studies by several

    international organizations should increase the knowledge of geology and

    groundwater resources throughout Mazar-e-Sharif and Afghanistan.

    3.7.2 Environmental Consequences

    Air Quality

    Chapter-8 : IEE 8-14 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    15/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    8.6.2 Ecological Resources in Project Area

    Terrestrial Flora

    Project province - Paktia is one of the forest rich zones of the Afghanistan. The

    project area is characterized by coniferous forest, sub alpine and alpine vegetation

    etc. Other species are Pistachio and Archa. The following vegetation is common in

    project influence area

    Above 1,300 m there are evergreen oaks, the eastern varieties of Mediterranean

    forms: quercus baloot (up to 2,000-2,300 m); quercus dilatata (ca. 2,000-2,400 m);

    quercus semicarpifolia (up to about 2,900m).

    The level of coniferous forests, covering the westernmost part of the Himalayan

    forests, starts with pinus gerardiana, which from a height of 2,000 m, among the

    driest exposures, mixes with the Q. baloot, which grows in the wettest exposures.

    Between 2,400 and 2,700 m, when annual precipitations exceed 800 mm, the main

    trees are cedars (cedrus deodora) mixed with Q. semicarpifolia.

    Between 2,900 and 3,300 m, there are nothing but conifers, forming a mixed forestof spruce (picea smithiana), fir (abies webbiana) and pine (pinus wallichiana).

    formation of pistachio and almond trees (here pistacia atlanticao between ca. 1,200

    and 1,800 meters)

    Aquatic Species and Fisheries

    Aquatic species in the river are mainly crab, frog, water snake etc. In the project

    area, no fish species are identified during the reconnaissance visit; however, detail

    survey will be needed at feasibility level to assess the fishery resources in the river.

    Wildlife

    Wildlife of the area identified during the reconnaissance survey may be summarized

    as below

    Reptiles: Snake, Scorpion, Spider, Pincer and Lizard

    Amphibians: From, Turtle, Water Snakes

    Chapter-8 : IEE 8-15 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    16/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Mammals: Wolf, Rabbit, Dear, Foxes, mouse,

    Birds: Crow, pigeon, Falcon, Hawk, Nightingale, Duck, Wild Hen, Sicken, Swallow,

    Lark, Andalif.

    Wolf, some rabbit species, foxes, falcon, hawk, sicken, turtle species, and pincer are

    among rare species, and the condition of these rare species will be assessed during

    feasibility stage for required mitigation measures, if needed.

    Protected Areas

    Afghanistans biodiversity is similar to that of Middle East and Central Asia.

    Conservation of genetic resources in the country was matter of high priority beforethe war. In 1977 the Afghan Government established a Germ Plasm Unit in the

    Darul-Aman Research Station, Kabul. However, the entire establishment was

    destroyed during the conflict era from 1992 to 1995. 1978)

    Zadaran National Reserved is one of the proposed protected areas located in the

    south-east part of the Paktia but it is not under the project influence zone but at a

    distance of around 40 km from the project dam site.

    In the Project area there are no protected, sensitive or designated sites as such from

    the point of view of protected areas.

    Historical \ Archeological Sites

    There is no any monument or archeological \ historical sites in the project influence

    area of the Mechalghu Dam Project.

    3.9 Ecology

    3.9.1 Affected Environment

    Afghanistan is home to a wide variety of plant and animal life. A more detailed

    discussion can be found in Appendix B.

    Over 120 mammal species are found in Afghanistan. Some species have been

    categorized as threatened by the World Conservation Union (IUCN). The most

    seriously endangered are the goitered gazelle, leopard, snow leopard, markor

    goat, the Asiatic black bear, and Bactrian deer.

    Chapter-8 : IEE 8-16 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    17/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    The endangered salamander Batrachuperus mustersi does not occur near this

    proposed site. This amphibian is found only in streams in the Hindu Kush of

    Kabul Province.

    Over 450 bird species are found in Afghanistan. Species identified as globally

    threatened are the Siberian crane, white-headed duck, marbled teal, Pallas's

    sea-eagle, greater spotted eagle, imperial eagle, lesser kestrel, corncrake,

    sociable lapwing and the pale-backed pigeon. The IUCN has categorized the

    Siberian crane as Critically Endangered. It faces an extremely high risk of

    extinction in the wild. The global population, estimated to contain 2,500-3,000

    birds, is divided into three groups. Only a single breeding pair may remain in the

    central group, which formerly used wetlands in Afghanistan (and Iran) as

    stopover points during migration between breeding grounds in Russia and the

    Mazar-e-Sharif Environmental Assessment

    March 29, 2007

    wintering area in India. In Afghanistan, the key resting site is Ab-e-Estada in

    Gazni Province.

    No aquatic species occur on the proposed industrial park site.3.9.2 Environmental Consequences

    No known threatened or endangered plants have been observed or reported in

    the area of the proposed site. No occurrences of or suitable habitat for

    threatened or endangered plant species were identified during field inspections of

    the proposed site. Therefore, none of the proposed alternatives are expected to

    have impacts on threatened or endangered plant species or their habitats. The

    plant communities that occur on the site are common to, and representative of,

    Balkh Province.

    Although construction of the proposed facility would affect some plants, the loss

    is expected to be insignificant. Field surveys indicate that these vegetation

    communities are characterized by common and widespread species in Balkh

    Province that would not be adversely affected by the loss of these populations.

    No endangered or threatened species were identified on the site. Wildlife

    habitats that occur on the site are common throughout the region. Site

    Chapter-8 : IEE 8-17 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    18/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    development would remove some plant habitat and displace wildlife populations

    that favor these habitats. Most species would find refuge in similar habitats

    adjacent to the site. Following development, many of these species would likely

    re-colonize in areas surrounding the proposed industrial park. Thus, the

    proposed project is not expected to result in significant adverse impacts to

    terrestrial animal populations of the site. Further, implementing BMPs will

    mitigate any potential concerns.

    Site development may result in an increase in populations of animals that favor

    recently modified habitats. Some might become a "nuisance" in the area.

    The proposed development of the park will not affect any aquatic habitats.

    3.10 Prime Farmland, Wetlands, and Managed Areas and Recreation

    3.10.1 Affected Environment

    Neither wetlands, prime farmland, managed areas nor recreation opportunities

    were identified on or in the vicinity of the proposed industrial park site.

    3.10.2 Environmental Consequences

    There are no potential environmental consequences associated with prime

    farmlands, wetlands, managed areas or recreation areas.Mazar-e-Sharif Environmental Assessment

    March 29, 2007

    3.1 1

    Biological Environment

    The project site is occupied by a very sparse cover of low perennial shrubs

    (predominantly

    Artemesia and Acacia species) and scattered annual forbs and grasses. Currently

    the village

    members harvest shrubs and grass in the area to use as fuel wood and fodder. This

    practice is in

    Chapter-8 : IEE 8-18 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    19/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    some cases their only livelihood, and has resulted in a severely denuded landscape.

    Wildlife

    mainly consists of smaller animals, including upland songbirds and rodents. Rodents

    are in fact a

    problem for many farmers as they destroy the walls of the irrigation canals and

    structures.

    3.3.1 Biodiversity and Threatened or Endangered Species

    Biological (and socio-biological) modification of any environment tends to change

    the species

    composition of an ecological community. Afghanistan has prepared a comprehensive

    draft policy

    on conservation of species and is embodied in the Environment Act. The Act has

    been submitted

    to the Cabinet for approval.

    Based on conversations with local villager, there were, at one time, many types of

    wild animals

    and birds in the remote areas of Khulm District including deer, dogs, foxes, horses,jackasl,

    leopards, nanny (wild goat), rabbit, rams, wolves, and snakes. Wild birds such as

    cuckoo (fakhta),

    hoopoe (hototak), pigeon, quail (Budana), owl, nightingale (Bulbul), hawk (Baz),

    goose (Qaaz),

    falcon, crow, crane (kolang), and canary were also common. However, a significant

    decrease in

    the biodiversity of the area has been noted as a result of many factors including

    prolonged

    drought, conflict, increased population, poor land management, and lack of

    conservation

    mechanisms enforced by the government

    Wildlife and/or Rare/Endangered Species

    Chapter-8 : IEE 8-19 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    20/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Although Afghanistan mandates conservation of endangered species in their

    Environmental Law,

    the government has not established a national list of threatened and endangered

    species. As

    previously noted, Afghanistan adopted the policies of the Convention on International

    Trade in

    Endangered Species of Wild Fauna and Flora (CITES) in 1985. No protected or

    endangered

    species listed by CITES are known to occur or have been reported in the area. Many

    migratory

    bird species may pass through the region. As such, creation or degradation of any

    habitat features

    (e.g., wetland features associated with Khoja Alghar Spring, or created wetland

    nutrient filters),

    may impact beneficially or adversely on some bird species. Siberian Cranes,

    traditionally

    migrated 5000 km southeast from Western Siberian over Afghanistan to theirwintering grounds

    in northeast India. The wetlands used by Siberian Cranes is vital to the survival of

    cranes. Dasht-e

    Nawar and Ab-i-Estada in southern Afghanistan are among the key sites where

    Siberian Cranes

    have been reported to consistently rest during their migration. The project site does

    not provide a

    resting habitat for Siberian Cranes.

    The project site has traditionally provided pasture land for sheep. Grazing commonly

    affects plant

    communities through desertification and introduction of weed species when not

    carefully

    managed. Under such circumstances, biological concerns can be socioeconomically

    important.

    Chapter-8 : IEE 8-20 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    21/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Possible biological issues at the site include:

    Protection of wetland resources

    Changes in land use from grazing to agricultural use

    Introduction of weeds and/or insect pests

    Draft 04Feb08

    61

    In general, the project is not likely to adversely affect endangered species.

    Forests/Protected Areas

    There are no forests or protected areas in the vicinity of the canal area. There are

    wetlands

    associated with the Chashma-e-Hayat and Khoja Alghar Springs and riverine

    ecosystems

    upstream of the project. A detailed analysis of the project site for wetlands has not

    been

    undertaken. The project has a slight potential to affect the hydrology of wetlands

    upstream, within,

    and downstream (if any) of the project site. However, it is anticipated that wetlandswill not be

    significantly affected and will ultimately be eliminated from further detailed study.

    3.3.2 Proximity to Protected Areas and Forest Resources or Unique or

    Sensitive Natural Habitat

    There are no protected areas or sensitive natural habitats in proximity of the project

    site. As noted,

    there are wetlands associated with the Khoja Alghar and Chashma-e-Hayat springs

    and riverine

    ecosystems upstream of the project. Based on our field visits to date and

    conversations with local

    farmers and government organizations, there are no wetlands within the proposed

    Mazar Foods

    project area. Therefore it is not anticipated that the project will have direct impacts on

    wetland

    Chapter-8 : IEE 8-21 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    22/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    systems. However, analysis of hydrologic regimes will need to be conducted to

    ensure that

    upstream riparian areas are not affected by massive surface water usage and

    drainage. A

    monitoring program should be implemented to ensure that no adverse indirect

    impacts occur to

    wetland systems in the project area.

    3.3.3 Proximity to Sensitive Cultural or Archeological Sites

    During preliminary site visits, ancient ruins was identified outside the village of Deh

    Hassan,

    north of the proposed project boundary. Although this resource is well north of the

    current project

    boundary, the proximity of the project warrants discussion in the event that project

    boundaries are

    modified.

    Khulm is commonly identified with the ancient town of Aornos on Alexander the

    Greats line ofmarch (330-329 B.C.). Later known as Khulm, it was destroyed in the mid-16th

    century, the ruins

    of which are to the north of present day Khulm.

    3.3.4

    8.7 SCREENING ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

    In this section, potential environmental impacts have been assessed according to the

    magnitude on different environmental resources to project location, as related to

    design, during construction and regular operation. Mitigation measures have also

    been recommended for induced impacts. The impacts describes as, I- for

    insignificant, M- for moderate or S- for significant and impact duration such as, T-

    temporary or P-permanent and are presented in a manner that shows magnitude

    and duration of a particular impact, e.g., I/T means the impact is insignificant and is

    Chapter-8 : IEE 8-22 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    23/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    temporary in nature. The summary of findings is presented in Table 8.3:

    Table 8.3

    i. Environmental and Social Parameters for Tangi Shadiyan (site no. 17)

    Actions (IECs)AffectingEnvironmentalResourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    IEE Matrix

    NoNegativeImpact

    Rating of Impact

    Small

    Moderate Major

    -

    _ ++-

    -+

    +-

    -+

    +

    A. Environmental Issues related to Project Location

    Areasubmergeddue tocreation ofDam

    I/P NoneX

    Submergence

    of humansettlements

    0Nil X

    Submergenceof roadsinfrastructure

    M/P (around 1km)

    Adequatecompensationto concernedDept., andrealignment ofroad

    XX

    Loss ofagriculturalland fromflooding

    0 NIL X x

    Loss ofhistoric,cultural oraestheticfeatures byinundations

    0 None X

    Land

    acquisition

    0 None X x

    Chapter-8 : IEE 8-23 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    24/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Resettlementofhouseholds

    0 None X x

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bank erosion I/T Provision of toe protection,gabions andboulderplacement

    x X

    Risk ofbreakage ofembankment

    0 None X

    Seismic effect I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwithinternationallyacceptedstandards

    related to theseismic risk ofthe area tominimize orpreventdamage to thestructuresduringearthquakes

    x

    C. Environmental Issues during Construction

    Air and waterpollution fromconstruction andwaste disposal

    I/T(Temporarylocalizeddustpollution)

    Constructionmobilize insummerseason, selectappropriatesite forlocation ofcamps,provide masksto workers,disposewastes in a

    x

    Chapter-8 : IEE 8-24 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    25/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    designatedsite

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    X

    Disposal of oiland grease

    I/T(Machinerysuch as,excavators,

    bulldozers,scrapers,tractors)

    Propermaintenanceof machineryand plant,

    followconstructionimpactmonitoringandmanagementprogramchecklist

    X

    Fisheriesresources

    I/T None x

    Sedimentation ofdam and loss ofstorage capacity

    M/P Follow landuseregulations,control of landuse inwatershed,prevention ofconversion offorest /pasture toagriculture

    X

    Safety ofworkers fromaccidents

    I/T(Construction relatedhazards,health andsite safety)

    Providehelmets,gloves, dress,and otherappropriatesafetydevices toworkers,arrangeperiodicmedical checkup of workers,

    X X

    Chapter-8 : IEE 8-25 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    26/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    provision ofdecenthousing,standard food,drinking waterand sanitation

    Social issues 0 None x

    Gender issue 0 None x

    Physical impactson culturalheritage

    0 None x

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusheroperation)

    Maintenanceof equipment,commissioning of cyclone incrusher

    x

    Pollution ofwater resources

    I/T Provision of settling pond

    x

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision ofroutinemaintenance;Ensurerequiredbudget forO&M

    X x

    Flora and fauna I/P Regeneration

    of indigenousspecies thatsupportwildlife andbirds

    x

    Soil Pollutionfrom fertilizer andpesticide

    I/P Awareness of IPM and IPNM

    X

    Downstreamimpacts

    I/P Release of optimum water

    x

    Chapter-8 : IEE 8-26 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    27/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    flow forecosystemmanagementanddownstreamusers

    Movement ofwildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting andinflow of glaciers 0 None x

    Gender issue 0 None x

    ii. Environmental and Social Parameters for Chasma Dara (Site No. 4)

    Actions (IECs)AffectingEnvironmental

    Resourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    IEE Matrix

    No

    NegativeImpact

    Rating of Impact

    Small

    Moderate Major

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Areasubmergeddue to

    creation ofDam

    I/P NoneX

    Submergenceof humansettlements

    M/P (around 2houses)

    Adequatecompensationto PAFs, forhouses andalternativesites

    X

    Submergenceof roads

    infrastructure

    M/P (about200 m of road)

    Adequatecompensation

    to concerned

    X

    Chapter-8 : IEE 8-27 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    28/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Dept., andrealignment ofroad

    Loss ofagriculturalland and treesfrom flooding

    M/P (around 1ha)

    Adequatecompensationto PAFs

    X x

    Loss ofhistoric,cultural oraestheticfeatures by

    inundations

    0 None X

    Landacquisition

    M/P (about 1ha)

    Adequatecompensationto PAFs

    X x

    Resettlement ofhouseholds

    M/P (about 2houses)

    Adequatecompensationto PAFs andalternativehouses

    Xx

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bankerosion

    I/T Nil X x

    Risk ofbreakage ofembankment

    0 Nil X

    Seismic effect

    I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwithinternationallyacceptedstandardsrelated to theseismic risk ofthe area tominimize orprevent

    x

    Chapter-8 : IEE 8-28 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    29/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    damage to thestructuresduringearthquakes

    C. Environmental Issues during Construction

    Air and waterpollution fromconstruction andwaste disposal

    I/T(Temporarylocalizeddustpollution)

    Constructionmobilize insummerseason, selectappropriatesite for

    location ofcamps,provide masksto workers,disposewastes in adesignatedsite

    x

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquatic

    plants andother woodyvegetation

    X

    Disposal of oiland grease

    I/T(Machinerysuch as,excavators,bulldozers,scrapers,tractors)

    Propermaintenanceof machineryand plant,followconstructionimpactmonitoring

    andmanagementprogramchecklist

    X

    Fisheriesresources duringsummer

    I/T None x

    Sedimentation ofdam and loss ofstorage capacity

    M/P Follow landuseregulations,

    X

    Chapter-8 : IEE 8-29 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    30/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    control of landuse inwatershed,prevention ofconversion offorest /pasture toagriculture

    Safety ofworkers fromaccidents

    I/T(Construction relatedhazards,health and

    site safety)

    Providehelmets,gloves, dress,and otherappropriate

    safetydevices toworkers,arrangeperiodicmedical checkup of workers,provision ofdecenthousing,standard food,drinking water

    and sanitation

    X X

    Socialissues

    0 None x

    Genderissue

    0 None x

    Physical impactson culturalheritage

    0 None x

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusheroperation)

    Maintenanceof equipment,commissioning of cyclone incrusher

    x

    Pollution ofwater resources

    I/T Provision of settling pond

    x

    Chapter-8 : IEE 8-30 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    31/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision ofroutinemaintenance;Ensurerequiredbudget forO&M

    X x

    Flora and fauna I/P Regenerationof indigenousspecies thatsupport

    wildlife andbirds

    x

    Soil Pollutionfrom fertilizer andpesticide

    I/P Awareness of IPM and IPNM

    X

    Downstreamimpacts

    I/P Release of optimum waterflow forecosystemmanagement

    anddownstreamusers

    x

    Movement ofwildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting and

    inflow of glaciers

    0 None x

    Gender issue 0 None x

    iii. Environmental and Social Parameters for Bato Baba / Qachan Dara(Site No. 3)

    Actions (IECs)AffectingEnvironmental

    IEE Matrix

    Rating of Impact

    Chapter-8 : IEE 8-31 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    32/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Resourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    NoNegativeImpact

    Small

    Moderate Major

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Areasubmergeddue tocreation ofDam

    I/P None X

    Submergenceof humansettlements

    0

    Nil X

    Submergenceof roadsinfrastructure

    M/P (about500 m)

    Adequatecompensationto concernedDept.

    XX

    Loss ofagriculturalland from

    flooding

    M/P (about 1ha on rightbank)

    Adequatecompensationto PAFs

    x X

    Loss ofhistoric,cultural oraestheticfeatures byinundations

    0 None X

    Landacquisition

    M/P (About 1ha)

    Adequatecompensationto PAPs

    x

    Resettlementofhouseholds

    0 None X x

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bank erosion I/T None X x

    Chapter-8 : IEE 8-32 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    33/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Risk ofbreakage ofembankment

    0 None X

    Seismic effect I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwithinternationallyacceptedstandardsrelated to theseismic risk ofthe area to

    minimize orpreventdamage to thestructuresduringearthquakes

    x

    C. Environmental Issues during Construction

    Air and waterpollution fromconstruction and

    waste disposal

    I/T(Temporarylocalized

    dustpollution)

    Constructionmobilize insummer

    season, selectappropriatesite forlocation ofcamps,provide masksto workers,disposewastes in adesignatedsite

    x

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    X

    Disposal of oiland grease

    I/T(Machinerysuch as,excavators,bulldozers,

    Propermaintenanceof machineryand plant,follow

    X

    Chapter-8 : IEE 8-33 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    34/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    scrapers,tractors)

    constructionimpactmonitoringandmanagementprogramchecklist

    Impact onFisheriesresources

    I/T None x

    Sedimentation ofdam and loss of

    storage capacity

    M/P Follow landuse

    regulations,control of landuse inwatershed,prevention ofconversion offorest /pasture toagriculture

    X

    Safety ofworkers from

    accidents

    I/T(Constructio

    n relatedhazards,health andsite safety)

    Providehelmets,

    gloves, dress,and otherappropriatesafetydevices toworkers,arrangeperiodicmedical checkup of workers,provision ofdecent

    housing,standard food,drinking waterand sanitation

    X X

    Social issues 0 None x

    Gender issue 0 None x

    Physical impactson culturalheritage

    0 None x

    Chapter-8 : IEE 8-34 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    35/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusheroperation)

    Maintenanceof equipment,commissioning of cyclone incrusher

    x

    Pollution ofwater resources

    I/T Provision of settling pond

    x

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision ofroutinemaintenance;Ensurerequiredbudget forO&M

    X x

    Flora and fauna I/P Regenerationof indigenousspecies thatsupport

    wildlife andbirds

    x

    Soil Pollutionfrom fertilizer andpesticide

    I/M Awareness of IPM and IPNM

    X

    Downstreamimpacts

    I/P Release of optimum waterflow forecosystemmanagement

    anddownstreamusers

    X

    Movement ofwildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting and 0 None x

    Chapter-8 : IEE 8-35 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    36/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    inflow of glaciers

    Gender issue 0 None x

    iv. Environmental and Social Parameters for Shamar (Site No.1)

    Actions (IECs)AffectingEnvironmentalResourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    IEE Matrix

    NoNegativeImpact

    Rating of Impact

    Small

    Moderate Major

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Areasubmergeddue tocreation ofDam

    I/P NoneX

    Submergenceof humansettlements

    0

    Nil X

    Submergenceof roadsinfrastructure

    M/P(about 500 m)

    Adequatecompensationto concernedDept.

    X

    Loss ofagriculturalland from

    flooding

    M/P Adequatecompensationwould be

    provided toPAFs

    x X

    Loss ofhistoric,cultural oraestheticfeatures byinundations

    0 None X

    Landacquisition

    M/P(About 1 ha)

    Adequatecompensation

    would be

    x

    Chapter-8 : IEE 8-36 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    37/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    provided toPAFs

    Resettlementofhouseholds

    0 None X x

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bank erosion I/T Nil X

    Risk ofbreakage ofembankment

    0 Nil X

    Seismic effect I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwithinternationallyacceptedstandardsrelated to the

    seismic risk ofthe area tominimize orpreventdamage to thestructuresduringearthquakes

    x

    C. Environmental Issues during Construction

    Air and water

    pollution fromconstruction andwaste disposal

    I/T

    (Temporarylocalizeddustpollution)

    Construction

    mobilize insummerseason, selectappropriatesite for locationof camps,provide masksto workers,dispose wastesin a designatedsite

    x

    Chapter-8 : IEE 8-37 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    38/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    X

    Disposal of oiland grease

    I/T(Machinerysuch as,excavators,bulldozers,scrapers,tractors)

    Propermaintenance ofmachinery andplant, followconstructionimpactmonitoring and

    managementprogramchecklist

    X

    Fisheriesresources

    I/T None x

    Sedimentation ofdam and loss ofstorage capacity

    M/P Follow landuseregulations,control of landuse in

    watershed,prevention ofconversion offorest / pastureto agriculture

    X

    Safety ofworkers fromaccidents

    I/T(Construction relatedhazards,health andsite safety)

    Providehelmets,gloves, dress,and otherappropriatesafety devices

    to workers,arrangeperiodicmedical checkup of workers,provision ofdecenthousing,standard food,drinking waterand sanitation

    X X

    Chapter-8 : IEE 8-38 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    39/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Social issues 0 None x

    Gender issue 0 None x

    Physical impactson culturalheritage

    0 None x

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue to

    crusheroperation)

    Maintenance ofequipment,commissioning

    of cyclone incrusher

    x

    Pollution ofwater resources

    I/T Provision of settling pond

    x

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision of routinemaintenance;Ensure

    requiredbudget forO&M

    X x

    Flora and fauna I/P Regenerationof indigenousspecies thatsupportwildlife andbirds

    x

    Soil Pollution

    from fertilizer andpesticide

    I/P Awareness of

    IPM and IPNM

    X

    Downstreamimpacts

    I/P Release of optimum waterflow forecosystemmanagementanddownstreamusers

    x

    Chapter-8 : IEE 8-39 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    40/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Movement ofwildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting andinflow of glaciers

    0 None x

    Gender issue 0 None x

    v. Environmental and Social Parameters for Anbar / Chali Duzda (Site No.15)

    Actions (IECs)AffectingEnvironmentalResourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    IEE Matrix

    NoNegativeImpact

    Rating of Impact

    Small

    Moderate Major

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Areasubmergeddue tocreation ofDam

    I/P None X

    Submergenceof humansettlements

    0Nil X

    Submergenceof roadsinfrastructure

    0 Nil X X

    Loss ofagriculturalland fromflooding

    0 Nil X x

    Loss ofhistoric,

    cultural or

    0 None X

    Chapter-8 : IEE 8-40 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    41/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    aestheticfeatures byinundations

    Landacquisition

    0 X

    Resettlementofhouseholds

    0 None X x

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bank erosion I/T None X x

    Risk ofbreakage ofembankment

    0 None X

    Seismic effect I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwith

    internationallyacceptedstandardsrelated to theseismic risk ofthe area tominimize orpreventdamage to thestructuresduringearthquakes

    x

    C. Environmental Issues during Construction

    Air and waterpollution fromconstruction andwaste disposal

    I/T(Temporarylocalizeddustpollution)

    Constructionmobilize insummerseason, selectappropriatesite forlocation ofcamps,provide masks

    x

    Chapter-8 : IEE 8-41 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    42/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    to workers,disposewastes in adesignatedsite

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    X

    X

    Disposal of oil

    and grease

    I/T

    (Machinerysuch as,excavators,bulldozers,scrapers,tractors)

    Proper

    maintenanceof machineryand plant,followconstructionimpactmonitoringandmanagementprogramchecklist

    X

    Impact onFisheriesresources

    I/T None x

    Sedimentation ofdam and loss ofstorage capacity

    M/P Follow landuseregulations,control of landuse inwatershed,prevention ofconversion of

    forest /pasture toagriculture

    X

    Safety ofworkers fromaccidents

    I/T(Construction relatedhazards,health andsite safety)

    Providehelmets,gloves, dress,and otherappropriatesafetydevices toworkers,

    X X

    Chapter-8 : IEE 8-42 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    43/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    arrangeperiodicmedical checkup of workers,provision ofdecenthousing,standard food,drinking waterand sanitation

    Social issues 0 None x

    Gender issue 0 None x

    Physical impactson culturalheritage

    0 None x

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusher

    operation)

    Maintenanceof equipment,commissioning of cyclone in

    crusher

    x

    Pollution ofwater resources

    I/T Provision of settling pond

    x

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision of routinemaintenance;Ensurerequired

    budget forO&M

    X x

    Flora and fauna I/P Regenerationof indigenousspecies thatsupportwildlife andbirds

    x

    Soil Pollutionfrom fertilizer and

    I/M Awareness of IPM and IPNM

    X

    Chapter-8 : IEE 8-43 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    44/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    pesticide

    Downstreamimpacts

    I/P Release of optimum waterflow forecosystemmanagementanddownstreamuser

    x

    Movement ofwildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting andinflow of glaciers

    0 None x

    Genderissue

    0 None x

    vi. Environmental and Social Parameters for Dar e Negaar (Site No. 21)

    Actions (IECs)AffectingEnvironmentalResourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    IEE Matrix

    NoNegativeImpact

    Rating of Impact

    Small

    Moderate Major

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Areasubmergeddue tocreation ofDam

    I/T NoneX

    Submergenceof humansettlements

    0Nil X

    Chapter-8 : IEE 8-44 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    45/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Submergenceof roads andotherinfrastructure

    0 Nil X

    Loss ofagriculturalland fromflooding

    I/T Nil X x

    Loss ofhistoric,cultural oraesthetic

    features byinundations

    0 None X

    Landacquisition

    0 None X x

    Resettlementofhouseholds

    0 None X x

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bank erosion I/T Nil X

    Risk ofbreakage ofembankment

    0 Nil X

    Seismic effect I/M or?(Unknowneffects within

    Project life)

    The dam willbe designedconsistent

    withinternationallyacceptedstandardsrelated to theseismic risk ofthe area tominimize orpreventdamage to thestructuresduring

    x

    Chapter-8 : IEE 8-45 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    46/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    earthquakes

    C. Environmental Issues during Construction

    Air and waterpollution fromconstruction andwaste disposal

    I/T(Temporarylocalizeddustpollution)

    Constructionmobilize insummerseason, selectappropriatesite forlocation ofcamps,provide masksto workers,

    disposewastes in adesignatedsite

    x

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    X

    Disposal of oiland grease

    I/T(Machinerysuch as,excavators,bulldozers,scrapers,tractors)

    Propermaintenanceof machineryand plant,followconstructionimpactmonitoringandmanagementprogramchecklist

    X

    Fisheriesresources

    I/T None x

    Sedimentation ofdam and loss ofstorage capacity

    M/P Follow landuseregulations,control of landuse inwatershed,prevention ofconversion of

    X

    Chapter-8 : IEE 8-46 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    47/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    forest/pastureto agriculture

    Safety ofworkers fromaccidents

    I/T(Construction relatedhazards,health andsite safety)

    Providehelmets,gloves, dress,and otherappropriatesafetydevices toworkers,arrangeperiodicmedical check

    up of workers,provision ofdecenthousing,standard food,drinking waterand sanitation

    X X

    Social issues 0 None x

    Gender issue 0 None x

    Physical impactson culturalheritage

    0 None x

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusheroperation)

    Maintenanceof equipment,commissioning of cyclone incrusher

    x

    Pollution ofwater resources

    I/T Provision of settling pond

    x

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision of routinemaintenance;Ensurerequiredbudget for

    X x

    Chapter-8 : IEE 8-47 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    48/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    O&M

    Flora and fauna I/P Regenerationof indigenousspecies thatsupportwildlife andbirds

    x

    Soil Pollutionfrom fertilizer andpesticide

    I/P Awareness of IPM and IPNM

    X

    Downstream

    impacts

    I/P Release of

    optimum waterflow forecosystemmanagementand adequatecompensationfor existingmini-hydropowerplant of PAFs

    X

    Movement of

    wildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting andinflow of glaciers

    0 None x

    Gender issue 0 None x

    vii. Environmental and Social Parameters for Ab e Keli (Site No. 22)

    Actions (IECs)AffectingEnvironmentalResourcesand Values

    EnvironmentalImpacts of oron the Project

    RecommendedMitigationMeasures

    IEE Matrix

    NoNegativeImpact

    Rating of Impact

    Small

    Moderate Major

    Chapter-8 : IEE 8-48 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    49/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Areasubmergeddue tocreation ofDam

    I/P None X

    Submergenceof humansettlements

    P3 houses X

    Submergenceof roadsinfrastructure

    I/P Adequatecompensationfor roadrealignmentdue toconstructionof powerhouse

    XX

    Loss ofagriculturalland and trees

    from flooding

    P Adequatecompensationto PAPs

    x X

    Loss ofhistoric,cultural oraestheticfeatures byinundations

    0 None X

    Landacquisition

    M/P Adequatecompensationto PAPs

    x

    Resettlementofhouseholds

    P Adequatecompensationfor 3householdsand alternativehouses forPAFs

    X x

    Loss ofwildlife habitat

    0 None x

    Chapter-8 : IEE 8-49 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    50/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    B. Environmental Issues related to Project Design

    Bank erosion I/T None X x

    Risk ofbreakage ofembankment

    0 None X

    Seismic effect I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwithinternationallyaccepted

    standardsrelated to theseismic risk ofthe area tominimize orpreventdamage to thestructuresduringearthquakes

    x

    C. Environmental Issues during Construction

    Air andwater pollutionfromconstruction andwaste disposal

    I/T(Temporarylocalizeddustpollution)

    Constructionmobilize insummerseason, selectappropriatesite forlocation ofcamps,provide masksto workers,dispose

    wastes in adesignatedsite

    x

    Deterioration ofwater quality indam

    M/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    X

    Disposal of oil I/T Proper X

    Chapter-8 : IEE 8-50 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    51/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    and grease (Machinerysuch as,excavators,bulldozers,scrapers,tractors)

    maintenanceof machineryand plant,followconstructionimpactmonitoringandmanagementprogramchecklist

    Impact onFisheries

    resources

    I/T None x

    Sedimentation ofdam and loss ofstorage capacity

    M/P Follow landuseregulations,control of landuse inwatershed,prevention ofconversion offorest /pasture to

    agriculture

    X

    Safety ofworkers fromaccidents

    I/T(Construction relatedhazards,health andsite safety)

    Providehelmets,gloves, dress,and otherappropriatesafetydevices toworkers,arrangeperiodic

    medical checkup of workers,provision ofdecenthousing,standard food,drinking waterand sanitation

    X X

    Social issues 0 None x

    Gender issue 0 None x

    Chapter-8 : IEE 8-51 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    52/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Physical impactson culturalheritage

    0 None x

    Noise andvibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusheroperation)

    Maintenanceof equipment,commissioning of cyclone incrusher

    x

    Pollution of

    water resources

    I/T Provision of

    settling pondx

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision ofroutinemaintenance;Ensurerequiredbudget forO&M

    X x

    Flora and fauna I/P Regenerationof indigenousspecies thatsupportwildlife andbirds

    x

    Soil Pollutionfrom fertilizer andpesticide

    I/M Awareness of IPM and IPNM

    X

    Downstream

    impacts

    I/P Release of

    optimum waterflow forecosystemmanagementand fordownstreamusers

    x

    Movement ofwildlife

    0 None x

    Croplands I/P Monitor x

    Chapter-8 : IEE 8-52 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    53/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    ing of cropdiversification

    Rapid melting andinflow of glaciers

    0 None x

    Gender issue 0 None x

    viii. Environmental and Social Parameters for Quran Dara (Site No.2)

    Actions (IECs)

    AffectingEnvironmentalResourcesand Values

    Environmental

    Impacts of oron the Project

    Recommended

    MitigationMeasures

    IEE Matrix

    NoNegativeImpact

    Rating of Impact

    Small

    Moderate Major

    -

    _

    ++

    --

    ++

    --

    ++

    A. Environmental Issues related to Project Location

    Area

    submergeddue tocreation ofDam

    I/T None

    X

    Submergenceof humansettlements

    0Nil X

    Submergenceof roadsinfrastructure

    0 Nil X

    Loss ofagriculturalland fromflooding

    0 Nil X x

    Loss ofhistoric,cultural oraestheticfeatures byinundations

    0 None X

    Chapter-8 : IEE 8-53 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    54/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    Landacquisition

    0 None X x

    Resettlement ofhouseholds

    0 None X x

    Loss ofwildlife habitat

    0 None x

    B. Environmental Issues related to Project Design

    Bank erosion I/T Nil X

    Risk ofbreakage ofembankment

    0 Nil X

    Seismic effect I/M or?(Unknowneffects withinProject life)

    The dam willbe designedconsistentwithinternationallyacceptedstandardsrelated to the

    seismic risk ofthe area tominimize orpreventdamage to thestructuresduringearthquakes

    x

    C. Environmental Issues during Construction

    Air and water

    pollution fromconstruction andwaste disposal

    I/T

    (Temporarylocalizeddustpollution)

    Construction

    mobilize insummerseason, selectappropriatesite forlocation ofcamps,provide masksto workers,disposewastes in adesignated

    x

    Chapter-8 : IEE 8-54 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    55/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    site

    Deterioration ofwater quality indam

    I/T Periodicclearance ofleaf, aquaticplants andother woodyvegetation

    XX

    Disposal of oiland grease

    I/T(Machinerysuch as,excavators,bulldozers,

    scrapers,tractors)

    Propermaintenanceof machineryand plant,follow

    constructionimpactmonitoringandmanagementprogramchecklist

    X

    Fisheriesresources

    I/T None x

    Sedimentation of

    dam and loss ofstorage capacity

    M/P Follow land

    useregulations,control of landuse inwatershed,prevention ofconversion offorest/pastureto agriculture

    X

    Safety ofworkers from

    accidents

    I/T(Constructio

    n relatedhazards,health andsite safety)

    Providehelmets,

    gloves, dress,and otherappropriatesafetydevices toworkers,arrangeperiodicmedical checkup of workers,provision ofdecent

    X X

    Chapter-8 : IEE 8-55 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    56/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    housing,standard food,drinking waterand sanitation

    Social issues 0 None x

    Gender issue 0 None x

    Physical impactson culturalheritage

    0 None x

    Noise and

    vibration

    0 None x

    Dust, odors andfumes

    I/T (Fugitiveemissionsdue tocrusheroperation)

    Maintenanceof equipment,commissioning of cyclone incrusher

    x

    Pollution ofwater resources

    I/T Provision of

    settling pondx

    C. Environmental Issues during Operation

    Operation andmaintenance(O&M)

    M/P Provision ofroutinemaintenance;Ensurerequiredbudget forO&M

    X x

    Flora and fauna I/P Regenerationof indigenousspecies that

    supportwildlife andbirds

    x

    Soil Pollutionfrom fertilizer andpesticide

    I/P Awareness of IPM and IPNM

    X

    Downstreamimpacts

    I/P Release of optimum waterflow forecosystem

    x

    Chapter-8 : IEE 8-56 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    57/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    managementanddownstreamusers

    Movement ofwildlife

    0 None x

    Croplands I/P Monitoring of cropdiversification

    x

    Rapid melting andinflow of glaciers

    0 None x

    Gender issue 0 None x

    Chapter-8 : IEE 8-57 WRD, WAPCOS LimitedMarch-2012

  • 7/31/2019 Chapter 8 - Iee - Draft

    58/61

    Project:Pre-Feasibility Studies & Priority Ranking of 22 Small/MediumDam Sites and Feasibility Study of 10 Small/Medium Dams and Related Structures

    in Faryab, Jawzjan, Saripul, Balkh and Samangan Provinces

    8.8 INSTITUTIONAL REQUIREMENT, ENVIRONMENTAL MANAGEMENT AND

    MONITORING PLAN

    8.8.1 Environmental Mitigation

    Institutions responsible for executing and monitoring the environmental aspects of

    this project are:

    MEW is responsible for planning, constructing, operating and maintaining EIRP in

    Afghanistan. The PCU in MEW is in charge of project management to ensure that

    the contract provisions are adhered to. PCU is responsible for environmental

    monitoring and management Plan also. The MEW and its provincial authorities will

    also undertake routine and random monitoring of specific environmental p