chapter 9 project managament subjet

48
Chapter 9 Reducing Project Duration 175 Chapter 9 REDUCING PROJECT DURATION Chapter Outline 1. Rationale for Reducing Project Duration 2. Options for Accelerating Project Completion A. Options When Resources Are Not Constrained i. Adding Resources ii. Outsourcing Project Work iii. Scheduling Overtime iv. Establish a Core Project Team v. Do It TwiceFast and Correctly B. Options When Resources Are Constrained i. Fast-Tracking ii. Critical-Chain iii. Reducing Project Scope iv. Compromise Quality 3. Project Cost-Duration Graph 4. Constructing a Project Cost-Duration Graph A. Determining the Activities to Shorten B. A Simplified Example 5. Practical Considerations A. Using the Project Cost-Duration Graph B. Crash Times C. Linearity Assumption D. Choice of Activities to Crash Revisited E. Time Reduction Decisions and Sensitivity 6. What if Cost, Not Time, Is the Issue? A. Reduce Project Scope B. Have Owner Take on More Responsibility

Upload: hajimusan5817

Post on 28-Apr-2015

6.652 views

Category:

Documents


456 download

DESCRIPTION

Project Management

TRANSCRIPT

Page 1: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 175

Chapter 9

REDUCING PROJECT DURATION

Chapter Outline

1. Rationale for Reducing Project Duration

2. Options for Accelerating Project Completion

A. Options When Resources Are Not Constrained

i. Adding Resources

ii. Outsourcing Project Work

iii. Scheduling Overtime

iv. Establish a Core Project Team

v. Do It Twice—Fast and Correctly

B. Options When Resources Are Constrained

i. Fast-Tracking

ii. Critical-Chain

iii. Reducing Project Scope

iv. Compromise Quality

3. Project Cost-Duration Graph

4. Constructing a Project Cost-Duration Graph

A. Determining the Activities to Shorten

B. A Simplified Example

5. Practical Considerations

A. Using the Project Cost-Duration Graph

B. Crash Times

C. Linearity Assumption

D. Choice of Activities to Crash Revisited

E. Time Reduction Decisions and Sensitivity

6. What if Cost, Not Time, Is the Issue?

A. Reduce Project Scope

B. Have Owner Take on More Responsibility

Page 2: Chapter 9 Project Managament Subjet

176 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

C. Outsourcing Project Activities or Even the Entire Project

D. Brainstorming Cost Savings Options

7. Summary

8. Key Terms

9. Review Questions

10. Exercises

11. Case: International Capital, Inc.—Part B

12. Case: Whitbread World Sailboat Race

13. Case: Nightingale Project—A

14. Case: Nightingale Project—B

15. Case: The “Now” Wedding—Part A

16. Case: The “Now” Wedding—Part B

Chapter Objectives

To understand how to use the critical path to reduce project duration

To explain alternative methods for crashing activities

To explain the risks associated with compressing or crashing a project

To recognize when a project manager should try for the optimum cost-duration.

Review Questions

1. What are five common reasons for crashing a project?

Reasons given could include:

Imposed deadline in which disfavor will be earned by not meeting superior’s

deadline

Time to market competitive advantage

Realize benefits from incentive contracts

To make up for lost time and avoid contract penalties

Save extensive overhead costs

Free up resources to work on other projects

Exceed customer expectations.

2. What are the advantages and disadvantages of reducing project scope to

accelerate a project? What can be done to reduce the disadvantages?

Reducing the scope of the project can lead to big savings both in time and costs. It

typically means the elimination of certain tasks. At the same time scaling down the

scope may reduce the value of the project such that it is no longer worthwhile or fails

to meet critical success parameters. The key is reassessing the project requirements

to determine which are essential and which are optional. This requires the active

involvement of all key stakeholders. More intense re-examination of requirements

Page 3: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 177

may actually improve the value of the project by getting it done more quickly and for

a lower cost.

3. Why is scheduling overtime a popular choice for getting projects back on

schedule? What are the potential problems for relying on this option?

Scheduling overtime is popular because if it involves salary workers and no direct

costs are added to the project. Even if it involves additional costs, you avoid Brook’s

law and minimize additional coordination and training costs. The disadvantages are

the additional time and half costs associated with hourly overtime and stress and

fatigue that come with working long hours which can lead to accidents, inferior

performance, and turnover.

4. Identify four indirect costs you might find on a moderately complex project.

Why are these costs classified as indirect?

Indirect (overhead) costs are costs that cannot be attributed to a specific activity or

work package. Examples of indirect costs are supervision, consultants, debt interest

charges, machinery common to several activities, accounting and information

processing, public relations, penalties or incentives for early or late completion. In

practice it is amazing how many project compression decisions are made without

serious consideration of indirect costs.

5. How can a cost-duration graph be used by the project manager? Explain.

A cost-duration graph is useful to the project manager for comparing alternatives.

Any alternative that moves the project duration away from the optimum cost-duration

point will increase costs. Additionally, incentives and penalties can be evaluated

against the total, low cost point.

6. Reducing the project duration increases the risk of being late. Explain.

Compressing the project duration means slack (float) on noncritical activities will be

reduced. When slack of noncritical activities is reduced, the chance of new critical

paths occurring increases; hence, the risk of the project becoming late increases. In

addition, compressing will have the following other impacts on managing the project:

Reduces flexibility by using slack

Can increase number of critical activities

Can increase interdependencies of paths

Makes resource scheduling tighter (critical)

May increase costs.

Page 4: Chapter 9 Project Managament Subjet

178 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

7. It is possible to shorten the critical path and save money. Explain how.

The only way to shorten the critical path and save money is to have indirect costs

which are greater than the additional direct costs of shortening the critical path one

unit of time. The difference is a savings.

Exercises

Note: Use the procedure presented in the chapter example to compute exercises; that is,

compress one time unit per move using the least-cost method.

1. Draw a project network from the following information.

Activity Predecessor Duration

A None 2

B A 4

C A 3

D A 2

E B 3

F C 6

G C, D 5

H E, F 6

I G 5

J H, I 5

Activities B and H can be shortened to a minimum of 2 weeks. Which activity

would you shorten to reduce the project duration by 2 weeks? Why?

Page 5: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 179

2. Assume the network and data that follow. Compute the total direct cost for each

project duration. If the indirect costs for each project duration are $400 (19

time units), $350 (18), $300 (17), and $250 (16), compute the total project cost for

each duration. Plot the total direct, indirect, and project costs for each of these

durations on a cost-time graph. What is the optimum cost-time schedule for the

project? What is this cost?

Page 6: Chapter 9 Project Managament Subjet

180 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 7: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 181

The optimum duration is 17 time units at a cost of $840.

Page 8: Chapter 9 Project Managament Subjet

182 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

3. Given the data and information that follow, compute the total direct cost for

each project duration. If the indirect costs for each project duration are $90 (15

time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project

cost for each duration. What is the optimum cost-time schedule for the project?

What is this cost?

Page 9: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 183

Page 10: Chapter 9 Project Managament Subjet

184 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 11: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 185

4. If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15

weeks, $1,000 for 14 weeks, $900 for 13 weeks, $860 for 12 weeks, $820 for 11

weeks and $790 for 10 weeks, compute the total costs for each duration. Plot

these costs on a graph. What is the optimum cost-time schedule?

Note: The duration for this schedule is weeks and students should be told only to

crash the network one week at a time (not days).

Page 12: Chapter 9 Project Managament Subjet

186 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

For duration 14, B is chosen over D & E because it is the earliest task. If problems

occur, you can crash D or E.

Page 13: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 187

Page 14: Chapter 9 Project Managament Subjet

188 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 15: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 189

5. If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks,

$180 for 25 weeks, $120 for 24 weeks, $60 for 23 weeks, and $50 for 22 weeks,

compute the direct, indirect and total costs for each duration. What is the

optimum cost-time schedule? The customer offers you $10 dollars for every

week you shorten the project from your original network. Would you take it? If

so for how many weeks?

Note: The duration for this schedule is weeks. Students should be reminded that they

crash the schedule one week at a time (not divide the week into days).

Page 16: Chapter 9 Project Managament Subjet

190 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 17: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 191

Page 18: Chapter 9 Project Managament Subjet

192 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 19: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 193

6. Use the information contained below to compress one time unit per move using

the least cost method. Reduce the schedule until you reach the crash point of the

network. For each move identify what activity(s) was crashed, the adjusted total

cost, and explain your choice if you have to choose between activities that cost

the same.

Note: Crash point of the network is the point in which the duration cannot

be reduced any further.

Activity ID Slope

Maximum Crash Time

Direct Costs Normal Crash

Time Cost Time Cost

A - 0 4 $50 0 -

B $40 3 5 70 2 $190

C 40 1 5 80 4 120

D 40 2 4 40 2 120

E 40 2 5 60 3 140

F 40 1 5 50 4 90

G 30 1 4 70 3 160

H 30 1 4 80 3 110

I - 0 3 50 0 -

Total direct normal costs— $550

Caution: There is an error in the text – the “crash” cost for Activity C should be 120,

not 40. This should not be a problem for most students since the slope is correctly

listed as $40, but we encourage you to point this out before assigning this exercise.

Page 20: Chapter 9 Project Managament Subjet

194 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 21: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 195

Page 22: Chapter 9 Project Managament Subjet

196 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Case

International Capital, Inc.—Part B

See Teacher’s Manual, Chapter 7

Appendix Case for Part A of problem.

Part A suggests that the project would have to be compressed down to 61 days to reach

the 95% chance of meeting the average. Compressing follows the steps listed below.

Start at 73 workdays

Cut A 3 days $1,500 70 days

Cut K 6 days 6,000 64 days

Cut J 1 day 1,000 63 days

Cut H 1 day 2,000 62 days

Cut D 1 day 3,000 61 days

TOTAL $13,500

However, when these data are plotted with the indirect costs, the picture changes slightly.

The optimum time/cost tradeoff is 70 days. See chart below. Clearly, the risk of being

late has increased. Activities A&B are parallel and have added a critical path.

Compressing D one day reduces slack for Activities E&F to one day. Brown and the

project review committee have a trade off decision themselves. To get to 61 days will

cost $5,700 ($159,200 – 153,500).

Duration Project Normal Direct Total Total

Overhead Direct Costs Crash Costs Direct Costs Costs

60

61 42,700 103,000 13,500 116,500 159,200

62 43,400 103,000 10,500 113,500 156,900

63 44,100 103,000 8,500 111,500 155,600

64 44,800 103,000 7,500 110,500 155,300

65 45,500 103,000 6,500 109,500 155,000

66 46,200 103,000 5,500 108,500 154,700

67 46,900 103,000 4,500 107,500 154,400

68 47,600 103,000 3,500 106,500 154,100

69 48,300 103,000 2,500 105,500 153,800

70* 49,000 103,000 1,500 104,500 153,500

71 49,700 103,000 1,000 104,000 153,700

72 50,400 103,000 500 103,500 153,900

73 51,100 103,000 - 103,000 154,100

74 51,800 103,000 - 103,000 154,800

Page 23: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 197

Case

Whitbread World Sailboat Race

This is a fairly difficult case in which students have to create a project schedule and then

use the time-cost method to determine whether it is possible to meet the 45 week deadline

and $3.2 million budget limit. Students also have to factor in indirect costs in the form of

a hammock for the additional cost of keeping vessels in service.

Whitbread Project

(Costs in $000)

Activity Normal

Time

Normal

Cost

Crash

Time

Crash

Cost

Slope

A Design 6 $ 40 4 $ 160 60

B Build hull 12 1,000 10 1,400 200

C Install ballast tanks 2 100 2 100 -

D Order mast 8 100 7 140 40

E Order sails 6 40 6 40 -

F Order accessories 15 600 13 800 100

G Build deck 5 200 5 200 -

H Coat hull 3 40 3 40 -

I Install accessories 6 300 5 400 100

J Install mast and sails 2 40 1 80 40

K Test 5 60 4 100 40

L Sea trials 8 200 7 450 250

M Select crew 6 10 5 20 10

N Secure housing 3 30 3 30 -

O Select crew equipment 2 10 2 10 -

P Order crew equipment 5 30 5 30 -

Q Routine sail/maintenance 15 40 12 130 30

R Crew maintenance Train 10 100 9 340 240

S Initial sail training 7 50 5 350 150

Total direct cost $2,990

Hammock (Indirect costs):

Costs for keeping old vessel in service = $4,000/week for 25 weeks = $100,000

Cost for keeping new vessel in service for training = $6,000/week for 19 weeks = $114,000

Total hammock indirect costs = $214,000

Normal costs for 50-week plan:

Normal direct costs $2,990,000

Indirect costs (hammock) 214,000

Total costs $3,204,000

Page 24: Chapter 9 Project Managament Subjet

198 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Compressed to 45 Weeks:

Costs for keeping old vessel in service = $4,000/ week for 21 weeks = $84,000

Cost for keeping new vessel in service for training = $6,000/week for 19 weeks = $114,000

Total hammock indirect costs = $198,000

Compressed Activities:

A 2 weeks = 60,000+60,000 = $120,000

B 2 weeks = 200,000+200,000 = 400,000 (Reduce hammock 2 weeks)

R 1 week = 240,000 = 240,000

$760,000

Normal direct costs 2,990,000

Indirect costs (hammocks) 198,000 (21x4,000=84,000) + (19x6,000=114,000)

Total costs $3,948,000

Page 25: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 199

Upon working the problem, students should advise Bjorn that yes it is possible to

complete the project in 45 weeks but that the cost is estimated to be $3.948 million. This

is $748,000 more than Bjorn’s $3.2 million. This begs the question of priorities. When

asked what the priorities of the project are most students will rightly indicate:

Whitbread Project Priority Matrix

TIME PERFORMANCE COST

Constrain X X

Enhance X

Accept

Students will point out that both time (45 weeks) and budget ($3.2 million) are

constrained. However, based on their analysis it is impossible to meet both constraints.

Given that performance (victory) is the primary goal, one should argue that Bjorn should

seek additional funding and accept cost over-run. This is an important lesson. Often

projects begin with similar constraints but are forced to make a trade off in the final

analysis.

Page 26: Chapter 9 Project Managament Subjet

200 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Case

Nightingale Project—Part A

This case, along with Part B, is designed to have the students use the tools and concepts

introduced in Chapters 6 and 9 to answer some basic questions concerning the schedule

of the Nightingale Project. It is an excellent vehicle for training students to use project

management software to create a network and assess alternative courses of action. At our

college the students have access to MS Project and we have found that students are

capable of completing this assignment by simply following the Tutorial contained within

the program and on the CD-Rom.

Note: The answers provided are based on a January 1, 2010 start date which due to

holidays means the project begins on January 4, 2010. We suggest you tell students to

use this start date to insure consistency in answers.

Students should submit a project schedule similar to the one presented in computer output

below to support their answers.

1. Will the project as planned meet the October 25th deadline?

No, the scheduled completion date is 12/21/10.

2. What activities lie on the critical path?

Architectural decisions Feature specifications Database Review design

Integration Procure prototype components Assemble prototypes Lab test

Page 27: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 201

prototype Field test prototypes Adjust design Order stock parts Assemble

first production unit Test unit Produce 30 units Train sales representatives.

3. How sensitive is the network?

The text defines sensitivity as the likelihood that the critical path may change during

the course of the project. Sensitivity results from the number of critical paths and the

amount of slack available to non-critical activities.

Based on the information provided, this project is a fairly insensitive network. Most

non-critical activities have between 20-37 days of slack, exceeding their estimated

duration times. The lone exceptions are Price components which has only 5 days of

slack and Order custom parts which has 8 days of slack. However, given the nature

of these tasks it is unlikely that they will take more than 5 days beyond their

estimated duration time to complete. It should also be noted that, after an initial burst

of activities, there are only two non-critical activities (Document design and Order

custom parts) during the second half of the project.

Case

Nightingale Project—Part B

Students should assess the suggestions presented in Part B and prepare a short memo to

respond to the questions presented at the end of the case.

Page 28: Chapter 9 Project Managament Subjet

202 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

1. Is it possible to meet the deadline?

Yes, it is possible. The revised schedule has a projected completion date of October

25th, right before MedCON.

2. If so, how would you recommend changing the original schedule (Part A) and

why? Assess the relative impact of crashing activities versus introducing lags to

shorten project duration.

While crashing activities will reduce project duration, introducing the suggested start-

to-start lags has the biggest impact on schedule with the added bonus of no additional

costs. The completion date was 11/10/10 after introducing all of the start-to-start

lags.

Implement:

Document design could begin 5 days after the start of the review design.

Adjust design could begin 15 days after the start of field test prototypes.

Order stock parts could begin 5 days after the start of adjust design.

Order custom could begin 5 days after start of adjust design.

Training sales representatives could begin 5 days after the start of test unit and

completed 5 days after the production of 30 units.

To meet the October 25 deadline, three critical activities need to be crashed.

Crash activities:

Creation of database from 40 days to 35 days at a cost of $35,000.

Procure prototype components from 20 days to 15 days at a cost of $30,000.

Order stock parts from 15 days to 10 days at a cost of $20,000.

These three activities are on the critical path and would reduce the project duration by

15 working days at a cost of $85,000.

Neither External specifications, Document design, nor Voice recognition are on the

critical path so, crashing these activities would have no impact on project duration.

3. What would the new schedule look like?

Students should present a revised schedule similar to the table above.

4. What other factors should be considered before finalizing the schedule?

The team needs to review the suggested revisions and make sure they are feasible.

When crashing activities, there is always the danger that quality may be

compromised; they need to take steps so that this doesn’t happen. The team needs to

Page 29: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 203

assess the impact of these changes on the sensitivity of the network. A quick

assessment of the slack available to noncritical activities suggests that the sensitivity

of the network has not changed significantly, which enhances the chances of the

project meeting the deadline. Introducing start-to-start lags may create resource

conflicts if the same people are working on both activities. The team needs to check

and make sure there are adequate resources available to avoid this problem. Finally,

there is no slack between the estimated completion date and MedCON. The team

should consider contingency plans if critical activities slip. One plan would be to

have funds ready if it is necessary to crash production of the prototypes which occurs

at the tail end of the project.

Assignment Variation

Part A could be assigned after completing Chapter 6 and Part B could be assigned for

Chapter 9.

Case

The “Now” Wedding—Part A

This is a great case for a class exercise. Students enthusiastically enter into the case and

have fun.

The case can be used several ways. First, the case can be used as a small team/group

assignment. Second, the case can be used as suggested in the text—as an in-class

exercise.

Starting with the yellow sticky approach will get you past the many differences of

opinion on how the network is developed. Careful reading of the case should bring the

group around to the network suggested in the attached exhibits.

Development of the original network suggests that the wedding cannot make the January

21 deadline. It would take until January 26 and be too late for Connor’s ship out date of

January 30.

Page 30: Chapter 9 Project Managament Subjet

204 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

However, two tasks can be shortened at an additional cost and the deadline reached.

Activity 8, Order material, can be cut from 8 days to 5 days at a cost of only $20.

Activity 11, Sew dress, can be cut from 11 days to 9 days at a cost of $96 ($48x2).

Activity 16, Mail invitations, must go out 10 days before the wedding.

Reduce Activity 12, Order and receive invitations, from 7 days to 6 days. The cost is

$20.

Reduce Activity 13, Address invitations, from 3 days to 1 day. The cost is $80

($40x2).

Total costs = $216

The deadlines are met. The wedding can take place January 21 and have a seven-day

honeymoon. Connor can leave on January 30.

Case

The “Now” Wedding—Part B

Part B presents some unknown risk events. Given these events, students will attempt to

shorten Activity 11 and revise durations for Activity 7 and 12.

Activity 11, Sew dress. Cut from 9 to 6 days at a cost of $144 ($48 x 3).

Activity 7, Guest list. Add 3 days for the flu. Now duration is 7 days.

Activity 12, Order and receive invitations. Add 1 day for press breakdown; now the

duration is 7 days.

Page 31: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 205

Conclusion: Deadlines cannot be reached! The notice of the loss of dress material

(Activity 8) in transit received January 10 kills the January 21 deadline. Reordering on

January 11 won't do it!

Although students are disappointed, give them an opportunity to suggest some

alternatives. We find two suggestions almost always come up quickly.

1. Buy the material locally and pay the price.

2. Buy a ready-made wedding dress.

Page 32: Chapter 9 Project Managament Subjet

206 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

TRANSPARENCIES (for exercises)

Page 33: Chapter 9 Project Managament Subjet

207 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Page 34: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 208

Exercise 2 (a)

Page 35: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 209

Exercise 2 (b)

Page 36: Chapter 9 Project Managament Subjet

210 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 2 (c)

Page 37: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 211

Exercise 3 (a)

Page 38: Chapter 9 Project Managament Subjet

212 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 3 (b)

Page 39: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 213

Exercise 3 (c)

Page 40: Chapter 9 Project Managament Subjet

214 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 4 (a)

Page 41: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 215

Exercise 4 (b)

Page 42: Chapter 9 Project Managament Subjet

216 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 4 (c)

Page 43: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 217

Exercise 4 (d)

Page 44: Chapter 9 Project Managament Subjet

218 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 5 (a)

Page 45: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 219

Exercise 5 (b)

Page 46: Chapter 9 Project Managament Subjet

220 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 5 (c)

Page 47: Chapter 9 Project Managament Subjet

Chapter 9 Reducing Project Duration 221

Exercise 5 (d) with graph

Page 48: Chapter 9 Project Managament Subjet

222 PROJECT MANAGEMENT: THE MANAGERIAL PROCESS

Exercise 6