chapter ix studies on multiple funicular shell...
TRANSCRIPT
CHAPTER IX
STUDIES ON MULTIPLE FUNICULAR SHELL RAFT IN THE FIELD
9.1 General
There are vast areas of soft compressible soil
deposits which pose serious foundation problems. A
feasibility study of using multiple funicular shell rafts
for providing efficient and economical foundations in place
of conventional ones in such sites was considered
worthwhile. With this end in view, a study was made by
building a raft using 110cm x 110cm size funicular shells.
A single room structure was built over this type of
foundation and its performance was monitored for more than
eight years and ten months since 1978.
9.2 Site of the Experimental Study
The study was conducted at Mankompu in Kuttanad,
Kerala State, India. Originally the entire area was below
mean sea level. The typical soil profile at the site
consisted of very soft to soft marine clay deposits of 8 to
10 metres thick underlain by slightly stiffer clays upto 30
to 35m depth. As the entire area is water-logged,
construction of buildings is carried out on reclamations.
Even single storeyed residential buildings on conventional
spread foundation in the area have shown distress by
excessive settlements and cracking. Typical cases of large
deformations on walls and floors of structures due to
foundation problems, are illustrated in Figs. 9.1a to 9.ld.
The piers and abutments of bridges constructed in the region
126
are fouI;ded on piles and wells. Buildings with more than
two floors are nearly absent in this area due to the serious
foundation problems encountered. Raft foundation is one of
the types of foundations which can be resorted to under such
conditions. It is proposed to examine whether funicular
shells in the form of multiple units is a suitable and
economical alternative to conventional raft foundations.
For this purpose. a prototype structure on a raft foundation
using four funicular shells with suitable connecting beams
was built and its performance monitored. The soil profile
at the site is given in Fig.6.6.
9.3 Details of the MUltiple Funicular Shell Raft and the
Superstructure
The raft was constructed 60 m below the existing
ground level on the reclaimed soil of sandy loam of grain
size distribution shown in Fig.6.B. A pit of 3m x 3m size
and 60cm deep was excavated at the site for the experimental
structure. A layer of river sand of 10 cm thickness was
spread and compacted. The position of funicular shells were
marked and the sand bed was shaped to receive the conve~
face of the funicular shells. The distance between the
adjacent shells was kept at 20cm to ensure proper filling in
of sand below the shells and between the shells before the
connecting beams are cast. After placing the shells in
position. sand and water were poured in between the shells
and on their sides and properly compacted to ensure perfect
support for the shells. Then the formwork for the
connecting beams and edge beams was made and erected in
127
position. The arrangement of shells in position and the
shuttering work with reinforcement for the beams were as
shown in Fig.9.2. The connecting beams were designed to
take up the hogging moments due to the soil reaction. The
edge beams were cast directly on the edge beam of the shell
and were given nominal reinforcements only. Since the
purpose of the experiment was to study the behaviour of the
multiple shell raft units on soft soils, the connecting
beams were slightly over-designed so that they would act
more or less rigidly when the structure built over the raft
was test loaded. The connecting and. edge beams were
concreted with a nominal concrete mix of 1:2:4. After
curing for 28 days, the super structure was constructed on
the edge beams with country burnt bricks of size 20cm x
10cm x 6.5cm in cement mortar 1:4 mix. Four scales
graduated to an accuracy of O.lcm were fitted vertically at
the corners of the structure while the masonry work was in
progress. The walls were constructed to a height of 255cm
above which a reinforced concrete slab of 1Scm thickness
was cast to enable further loading of the structure. A
parapet wall 20cm thick and 90cm high was constructed above"
the roof slab with cement mortar 1:3 mix. The sectional
elevation and plan of the structure are ahown in Fig.9.3.
The inside faces of the parapet walls and the top of the
roof slab were plastered with fine cement mortar so that
the structur~ could be loaded with saturated sand above the
roof. The structure was completed in March 1978 and its
general view is shown in Fig.9.4.
128
9.4 Performance of the Foundation
Measurements of soil pressures were attempted but
were not successful over a period of time, presumably due to
entry of some air in the measurement system. Hence the long
term pressure measurements had to be discontinued.
The settlements at the four corners and the centre
of the structure were measured using a precision level with
which readings up to O.Olcm can be read on a scale and upto
O.001cm by estimation, with scales held on to the structure
and a permanent bench mark established 15m away from the
structure. On 15 th August 1978, the structure was test
loaded by pumping in water on to the roof top in stages of
1Scm height of water at a time. The maximum load on the
foundation with the tank full of water was estimated to be
19.5t. This load was maintained till 1st of llovember 1978
when the water was emptied and river sand was refilled with
an average density of 1.75t/m3 and water pumped upto the top
of the fill. Then the load was estimated to be 23t. This
load was 1.44 times the ultimate combined capacity of the
four shells in the unit. The unit had almost uniform
settlement. The settlements of the structure since th~
start of its construction are given in Fig.9.S. The shells
are intact even today after nearly nin~ years since the
completion of the structure. The performance of the
structure had been very satisfactory from the point of view
of settlements and structural stability. The load of 23t
corresponds to an average contact pressure of 4t/m 2• For a
three or four storeyed building with room· dimensions in the
129
range of 3 to 4 metres, the mUltiple funicular shell raft
may prove to be an economical and efficient foundati.on as
in the case of mUltiple funicular shell footing units. By
properly designing the connecting and edge beams, the shells
may be put to its optimum use.
9.5 Special Features of Multiple Funicular Shell Rafts
The self weight of the multiple funicular shell
raft is less than that of a conventional raft, designed to
transmit the same pressures to the soil.
If there are some minor loca\ised settlements in
the foundation, the readjustments of the shells can take
place without necessarily producing undesirable
defortnations.
The multiple funicular shell raft foundation may
prove to be more economical and efficient than the
conventional raft or pile foundations for three or four
storeyed buildings with room dimensions of 3 to 4 metres.
Incidentally, this study has shown that rafts using
funicular shells can be a suitable proposition in
prefabricated constructions for large housing projects and
townships on soft soils. However, there is need for
practical construction of large sized structures and their
monitoring since the size effects can lead to larger total
settlements and consequently the differential settlements
may become higher.
130
FIG.9 .1a. CRACKS ON A WALL DUE TODIFF ERENTIAL SETTLEMENT OFFOUNDATIONS
131
FlG.9.1b. HORIZONTAL CRACK ON WALL ATWINDOW SILL LEVEL
132
FIG.9 .le. CRACKS ON A VERANDAH PARAPETWALL NEAR THE CENTRE OF THESPAN BETWEEN TWO COLUMNS.
133
FIG. 9 .ld. CRACKS ON THE FLOOR DUE TODIFFERENTIAL SETTLEMENTS OFFOUNDATION SOILS UNDERBASEMENT FILL
134
FIG. 9·2. DETAILS OF REINFORCEMENT FORCONNECTING BEAMS AND EDGE BEAMSOF MULTIPLE FUNICULAR SHELL RAFTUSED IN FI ELD TEST.
135
SOIL
FUNICULAR
Scale
dge beam
Pressure cell
RCC Roof slab20cm thick brick
wall
Connecting beam
..,.Scale
1""""-20cm thick parapetof brickwork
ScaleftC---t-----~-.lH-Funicular shell
G.L.
-
"" E
/,-,<-
I~('rl7"-"\ I'-' -"
i- -
1Eu
aen
] 1'"i:.-.
IIEu
Lf1Lf1
61~ '. ij
- ..··:·f ..... ~ ,.4, b:~~-:.
E l·Wi\<,:,........••..........:...'.?•.., ~, :".'" ,; •. :<i: SOF Tu 1 Sectional Elevationa~
fEu
Lf1N
E~
~lM
.~
TEu
Lf1Na
glN
vr~---------255cm ~
Plan(Foundation leve I)FIG9.3TEST STRUCTURE ON MULTIPLE
SHELL RAFT IN THE FIELD
136
FIG. 9.4. STRUCTURE BUILT ON MULTIPLE FUNICULARSHELL RAFT IN FIELD.
137
y
)' N~MBER OF YE~RS SINCE START OF CONSTRUCTION6/ - 8 91 2 3 4 5 6 7
~1\~\
~
~ ---
~~-~
~~
------ ----r---.
---"w00
..t,4Q
°30«320
10
o1
2
3
E 4u
1-' SZw 6:2:w 7--J
:= 8wIf) 9
)101112
FIG.9.S GRAPHS OF LOAD vs NUMBER OF YEARS AND NUMBER OF YEARS
vs SETTLEMENT OF THE STRUCTURE BUILT ON MULTIPLE FUNICULARSHELL RAFT