chiller retrofit case study hertz 600 vine center
TRANSCRIPT
Bill Balli Donny Knight DeBra-Kuempel Chiller Group
Chiller Retrofit Case Study
HERTZ 600 VINE CENTER
2021 ICE Group Meeting
Presentation Summary
Project Background 1 Demolition, Retrofit, & Startup 4
Bidding Process 2 Energy Savings & ROI 5
Design Considerations 3 Outcomes & Learnings 6
2021 ICE Group Meeting
Hertz Investment Group @ 600 Vine Center
Project Background
Walked into conversation at shop
– How to get chillers in penthouse of high-rise?
Hertz Investment Group in downtown Cincinnati, OH
Two 800-ton Carrier 19EB Chillers
– Located on 31st floor penthouse back of building
– Maintained since install by Carrier
2021 ICE Group Meeting
Bidding Process
DeBra Bid
Started out leveraging Turbocor TT400
– Need six total to reach tonnage req.
Contacted SMARDT
– Inquired utilizing VTT Compressor
– Similar to a parallel job, University of Cincinnati
Quoted
– Two VTT Compressors w/remote drives
– Kiltech control panel
2021 ICE Group Meeting
Bidding Process
Competition Competitive Bids
– Daikin McQuay w/four 400-ton WMCs
Complete Mechanical Changeout
– Pumps
– Chillers
– Controls
Space Limitations
Daikin contacted customer
– Warned that DeBra retrofit would not work (Due to Oil & Compressor size)
2021 ICE Group Meeting
Design Considerations
Approach Philosophy
– Lots of moving parts
– KEEP IT SIMPLE
Retrofit Considerations
– Cost of Rigging
– Cost of New Chillers
– Customer ROI
– Space of Mechanical Room
– Excessive Noise/Vibration
– Minimum tonnage turndown
– Condition of Tube sheets
– Factory Economizer / Floats Vs. EXV
Two Turbocor VTT compressors w/remote drives mounted on chiller near control panel
– New control panel
– Retube Cooler & Condenser
– Factory Economizer / Floats Vs. EXV
– Installed distribution panel in replacing Wye Delta starter
Interfaces with BAS
Large Energy Savings
Thought Process Actual Build
2021 ICE Group Meeting
Two Identical Chillers in Penthouse
Chiller No. 2 (behind No.1, Remains Stock) Chiller No. 1 (Full Retrofit)
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Started with:
Original Carrier 800 ton 19 EB
– 3600 lbs of R-12
– Subsequent field addition of Hot gas bypass
~35 years old
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
All condenser and chilled water piping to be removed
– Chiller was also going to be completely retubed
Small 3-foot walkway between Housekeeping Pad & Tower
Notice that it sat on airbags to mitigate noise/vibrations
3 Feet
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Starting Point
Overhead rigging had to be fabricated.
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Tear Down
View after the motor and most of the compressor has been removed
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Tear Down
Oil pump was removed
Traced all oil lines out of the shell
– Some of the oil/refrigerant lines go through the uni-shell
Note:
– Still on airbags
– Original Tubes
– No economizer work yet
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Tubes Removed
Added access windows
– Every condenser support sheet broke during tube removal
Dropped machine down
– Easier access to control panel
– Lowered overall height
Dropped
machine down
Added
windows
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
These are the holes we cut to gain access to the tube sheets.
As it turns out, the shell was one-inch thick.
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Welded support sheets
These are the condenser tube sheets after they were welded in
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Inside the Economizer
Keeping it simple…
Rebuilt original floats as opposed to installing electronic expansion valves
Float had worked for 35 years. Not broken – don’t fix it
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Start of Fabrication
Fabricated the suction, discharge, and economizer headers
Notice that we re-welded the condenser covers
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Test Fit of Compressors & Headers
Rigging used to set compressors
– Fabricated spreader bars for the compressors
Spreader Bar
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Both compressors Fabbed
Note the tubes are installed and the tube sheets have been coated with Belzona
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Wiring & Ancillary Piping
Electricians installing main power
– Sensor cabling
Liquid injection and economizer lines
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Compressor Table
Pipefitters fabbed a plate for the compressor to sit
– Bolted the suction and discharge flange prior to drilling the compressor feet
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Hot Gas Bypass
Incorporated hot gas bypass into overall controls strategy
Installed all new electronic flow switches
Removed the original DP switches – Installed thermal
displacement switches
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Both economizer and liquid feed for the motor cooling were built from fabricated headers
Liquid injection header
Added Caps to shell (orig. refrig./oil circuitry through shells)
Liquid
Header
Economizer
Header
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
The discharge 90’s off the compressor were back-ordered
Had to set the distance of the headers which made the center-to-center on the headers off.
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Close to Complete
Used Kiltech Panel
Original design had VFD’s next to Kiltech Panel to keep refrigerant piping and wiring nearby – Customer wanted drives
relocated to wall behind for spacing
2021 ICE Group Meeting
Demolition, Retrofit, & Startup
Relocated the VFD’s on the wall behind the chiller instead of the original location
2021 ICE Group Meeting
Energy Savings & ROI
Estimating cost savings:
– Original flow meters not functioning
– Chiller No. 2 “building’s best running machine”
– Measured old Machine…
Unit Operation Design (GPM) Actual (GPM)
Condenser 2400 2897
Evaporator 1200 1837
2021 ICE Group Meeting
Savings Estimate
Retrofit running at design conditions yields estimated $60k-$80k annual savings
Accounting for Condenser Relief, savings increase further
Design Carrier
(100%)
Retrofit
(100%)
Carrier
(50%)
Retrofit
(50%)
Retrofit
Condenser Relief
@ 65 degrees
Motor Amps 797 800 632 412 294 105
kW/Ton 0.7172 0.8690 0.5772 1.1745 0.4558 0.2363
Evaporator Tons 795 689 810 283 480 275
2021 ICE Group Meeting
Lessons Learned – What went WRONG?
COVID-19 – Virtually all parts had extended lead-times shipping internationally
Drive Location Challenges – Customer wanted panels installed in different location than design
– Had to absorb cost of change within budget
– BE SPECIFIC. Outline all inclusion/exclusion assumptions
Every condenser tube support sheet broke – Had to cut windows for access
Underestimated spacing constraints in Penthouse – Needed to stage all equipment in lower floors – significant hours spent in the elevators
2021 ICE Group Meeting
Lessons Learned – What went WELL?
Every condenser tube support sheet broke
Utilized similar job at UC for reference – Startup was extremely smooth
Performance exceeds expectations
Won maintenance contract – Previously performed by Carrier past ~35 yrs
High likelihood of second machine win – Design work can be mirrored for second machine