chris wieberg, mdnr, central office permitting update, missouri water seminar, september 10-11,...
TRANSCRIPT
Water Protection Program, Water
Pollution Control Branch, Central
Office Permitting Update
Chris Wieberg
Permitting Staffing Changes
New Unit Chiefs
– Tim Bull – Domestic Permits
– Jake Faulkner – Industrial
Permits
– Stacia Bax – MS4, MGP, LD,
401, ePermitting
Permitting Staffing Changes
New Staff
401 Coordinator - Mike Irwin
MS4 Coordinator - Mike Abbott
Industrial Permit Writer – Amberly Schulz
Domestic Permit Writer – Shawn Massey
Domestic Permit Writer – Adam Paige
Each unit as 1 vacant position currently
Permitting Totals
January 1, 2015-September 3, 2015
• Domestic Site-Specific: Non-municipal/POTW
permits - 225
• Industrial Site-Specific - 59
• ePermitting (Land Disturbance) - 720
• Priority Permits Candidates – 80%
• 401 Certifications – 43
• Subdivision Approvals - 25
CAFCOM (Affordability) 2015
• Cost Analysis For Compliance
– 30 effective permits with CAFCOM analysis
– All effective permits had a compliance
alternatives resulting in a MHI percentage
less than 2%.
– CAFCOM template has seen no changes in
2015
S.B. 642 merged with S.B. 664 2014
• created Section 644.058 RSMo
– require 66 unique environmental and
economic need studies prior to modifying
water quality standards and document these
evaluations and use them in making
individual site specific permit decision
– Also included a reporting requirement to the
Legislature on affordability
SS HB 2015
• Modified Section 644.145
– Now requires affordability analysis for water
and sewer treatment works and not just
POTWs.
– Clarified that the measurement of affordability
against the specific communities MHI or the
States MHI
Missouri Sustainability Assessment
Tool (MoSAT) • The Department contracted with Wichita State University to
complete an assessment tool that would allow for predictions on
rural Missouri community populations and future sustainability.
• A stepwise regression model was applied to 19 factors which were
determined as predictors of rural population change in Missouri.
• The weighted values for each town / village were then added
together to determine an overall decision score. The overall decision
scores were then divided into five categories
• Permit Writers reference MoSAT category when determining an
appropriate Schedule of Compliance.
Voluntary Early Nutrient Monitoring Program
for Point Sources
• According to the Nutrient Loss Reduction
Strategy
• Differs from the monitoring requirement
established for N and P in 10 CSR 20-
7.015
Nutrient Monitoring 10 CSR 20-7.015
• Discharges greater than 100,000 gallons
per day shall monitor once per quarter for
total N and P.
Voluntary Early Nutrient Monitoring
Program for Point Sources • The reduction strategy suggested slightly
different monitoring than 7.015.
– 0.1 to 1 MGD discharges to sample quarterly
for total nitrogen must included TKN, NH3,
NO3, and NO2 and Total P
– Greater than 1 MGD discharges to sample
monthly for total nitrogen must included TKN,
NH3, NO3, and NO2 and Total P
Voluntary Early Nutrient Monitoring
Program for Point Sources • The reduction strategy suggested slightly
different monitoring than 7.015.
– Additionally the strategy suggest that
receiving stream monitoring also occur at a
similar frequency for the same parameters.
– It is suggested that flow also be monitored in
order to establish loading
Voluntary Early Nutrient Monitoring
Program for Point Sources • The program procedure is currently draft
and we are accepting comments through
October 1st, 2015
• Comments and Questions can be directed
to Cameron Eisterhold at
(573) 751-7326
Electronic Discharge Monitoring
Reporting • Currently 7% of the states discharge
permittees are reporting via eDMR.
• Sign up by filling out a Facility Participation
Packet.
• eDMR training is held in Jefferson City
around 5 times a year
• eDMR is the first phase of eReporting
Compliance
Multiple-Discharger Variance • Currently working on the variance framework which is
available now at
http://dnr.mo.gov/env/wpp/cwc/docs/variance-draft-
20150715.pdf
• Applicability would include Municipal Publicly Owned
Treatment Works with a functional lagoon system
• Each municipality will need to justify that in order to meet
the water quality standards for total ammonia nitrogen
the municipality would be required to raise residential
user rates to an amount that would cause a substantial
and widespread economic and social impact.
Integrated Planning
• Can consider all environmental obligations
and requirements (Drinking water, MS4, I&I,
etc…)
• Identify highest public health and
environmental risks
• Work on highest risks first
• Formally recognize priorities
• Could support a modification of a Schedule of
Compliance
Industrial Stormwater Permitting
• Stormwater Pollution Prevention Plans
• Limits vs. Benchmarks
• BMPs
– Structural vs. Operational
• You should be letting your permit writer know what
BMPs are being implemented
Power Plant Permitting
• 316a Thermal Discharges
– BTU limits will be changed
to ̊F limits
– Schedules of Compliance will
be established where
appropriate
– Some will want to conduct a
316a variance study. Meet
with the department to
discuss work plan and QAPP
Power Plant Permitting
• 316b Intakes
– Studies are being conducted focused on
impingement and entrainment.
– Regardless of permit status you should be
working on this since the rule is effective and
self implementing.
– Information will be submitted to the
department at renewal or otherwise as
dictated by the rule.
Power Plant Permitting • Groundwater monitoring around ash ponds
– This requirement is for compliance with RSMO 644,
not the RCRA CCR rule
– Site Characterization to determine geology and
hydrology and initially indicate if discharges are
potentially occurring from the ash ponds.
– Establish well locations to monitor the discharge
condition, or lack there of
– May lead to limits in future permits if reasonable
potential exists to exceed standard
– Working to get a factsheet on this topic out by Spring
Keep an eye on the Ameren Labadie appeal.
http://168.166.15.111/Clients/MOAHC/Public/Case_Details.aspx?&EntityID=10059797
CAFO Permitting • Documents related to
permits of interest are
posted to the Departments
CAFO webpage
• Non NPDES CAFO
permits must maintain no
discharge status
regardless of weather
event
MS4 Permitting
• Mike Abbott is the new MS4 Coordinator
• General Permit will be public noticed again
• General Permit draft is currently under
MDNR General Council Review
• If you have questions please call or email
Mike Abbott at
(573) 526-1139
POTW Permitting
• CAFCOM
• Stormwater for those over 1 MGD
• No exposure or SWPPP
• Blending
Private Domestic Permitting
• Some private sewer companies have
negotiated longer schedules of compliance
for NH3 by expressing rate payer impact
as compared to the state MHI
• Not a CAFCOM but can lengthen a SOC
where appropriate.
Questions???
Thank You