TRANSCRIPT
- Feasibility Study in 2014 showed needs in Christiansburg schools
-Expansion of Falling Branch was the top priority to address overcrowding in elementary schools
-Need to address other elementary schools and high school with limited funds
-Current plan requires no tax increase
Why Now?
-Presentation on the current plan
- Public Input Opportunity -Use sticky notes to write down questions, comments or things we need to consider for each phase -Six stations, first station number is on agenda -As you move through stations, leave your sticky note and participate in dialogue -10 min at each station -Public Address following input session (3 minutes per speaker)
- We will compile every response and present them to the School Board on September 19.
Public Input Process
Phase 2
New NW/Belview Area Elementary (possibly using previous design at EMES/PFES) 2022-2024
Station 5
Phase 2
New Academic Building at CHS New Gym at CHS 2022-2024
Phase 3
Upgrade/Renovate Current CHS Building 2024-2025
Station 6