cigre b2-305

Upload: jorge-pinto-rocha

Post on 10-Feb-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/22/2019 CIGRE b2-305

    1/8

    New type of Tower for Overhead Lines

    Preferential Subject PS 3 for Study Committee B2

    Henning Oebro1

    Eltra2

    Erik Bystrup

    Bystrup Architects

    and Industrial Designers

    K. Krogh and

    M. H. Foder

    RAMBOLL

    DENMARK

    Summary

    The paper presents a new type of tower for a 400 kV overhead line.

    The type is new in several respects:

    - Layout of route: The route for this line is composed of shallow bendings resulting in a route

    following the contours of the landscape better than a conventional line composed of straight

    lines.

    - Design of tower: The tower design consists of two elements; a shaft and a lattice structure

    tower top with very few members, all tubular profiles.- Materials: The tower top is made of stainless steel tubes connected by cast joints in

    stainless steel, and the tower shaft of hot dip galvanised steel.

    - Foundation: The foundations are produced as 7 to11m long steel tubes with a diameter of

    1,5 m driven into the ground by a large pile driver.

    Table of Contents for the Paper

    1. Introduction and background.

    2. Design of tower.

    3. Construction and technical experiences.4. Economy.

    5. Future development

    1Member of SC B2

    2 Eltra amba, Fjordvejen 1-11, DK-7000 Fredericia, Denmark, e-mail: [email protected]

    21, rue d'Artois, F-75008 Parishttp://www.cigre.org CIGR

    Session 2004B2-305

  • 7/22/2019 CIGRE b2-305

    2/8

    2

    1.1.1. Introduction and Background

    Eltra is system operator for the western part of Denmark and owner the 400 kV grid.

    In March 2001, Eltra received a license to construct a new 400 kV connection between the

    cities of Aarhus and Aalborg, finalising a major 400 kV ring.

    This connection consists of overhead lines (117 km) with intermediate sections of underground

    cables (14 km).

    A minor part of the connection (27 km, shown on the map below in green) is placed going

    through a rural area with few technical installations. For this part the Danish Minister for Energy

    decided to demand a new type of tower based on a design competition.

    The wining entry, selected from among 48 entries, was based on a tower with a cylindrical

    shaft of weathering steel and a tower top constructed as a lattice structure built of very few

    tubular members, all in stainless steel.

    Wining entry New 400kV line Transition from Donau- to design-towers

    2. Design of Tower

    The overall design strategy for the new 400kV tower was to design a tower which, unlike the

    existing Donau towers, did not add visual noise or interference to the landscape. A tower

    consisting of few elements and simplicity in the design. A tower that would be read as aesthetic

    calm and repetitive elements strolling through the landscape contours.

    To achieve this a hierarchy on how a technical installation are perceived in the landscape was

    developed:

    -At a distance, only the body of the poles is visible, standing quietly measuring out the

    landscape

    -A little closer the insulators, the high voltage strings and the lattice top become visible

    -Close on the tower the details of the lattice top, the joints, the connections and the electrical

    components become visible

  • 7/22/2019 CIGRE b2-305

    3/8

    3

    Shafts in the landscape The lattice top

    To support this hierarchy a choice of materials for the different elements was suggested:Weathering steel for the shaft and Stainless Steel for the lattice top.

    Thus in colour and texture the weathering steel becoming to the soil and the Stainless Steel

    lattice top becoming part of the sky.

    Together these materials would strengthen each other giving character to both elements and

    underline the design strategy.

    Due to local public opposition the weathering steel for the shaft was abandoned and replaced

    with hot dip galvanised steel.

    The new 400 kV tower accomplishes a variety of assignments in one unique design:

    - Creating a continuous visual appearance, thus

    - Minimising the visual impact on the landscape

    - Angle tower capabilities allow a harmonious, bent alignment of overhead line and

    landscape

    - Due to a straight-forward and inexpensive foundation method, the tower leaves a minimal

    footprint

    - Fitting lattice tubes with cast stainless steel joints allows faster in situ assembling

    - The overall design allows a reduction of the magnetic fields

    One of the main adjustments of the wining entry was to change the vertical strings to V-strings

    in order to be able to use the same tower as a suspension tower and as a running angle tower

    for minor angles, to lower magnetic fields and to achieve a narrow right of way.

    The tower head is constructed as a lattice structure of stainless steel tubes welded together.

    The joints of the tubes are cast in stainless steel. Developing the moulds for the castings and

    execution of the castings were a difficult task due to the complicated geometry.

  • 7/22/2019 CIGRE b2-305

    4/8

    4

    A prototype of the suspension tower was constructed and tested mechanically to 105% of the

    maximum design loads.

    Prototype V-string Angle tower

    A tower family with 3 types of towers was developed:

    - Suspension tower

    - Running angle tower for max. 5o bending

    - Angle tension tower for 5 to 45o line angle

    3. Construction work and Technical Experiences

    The line was erected during 2003. The main part of the foundation work was made in

    April-August, the erection of towers took place in J une-August, and the stringing of conductors

    took place in J uly- September.

    Steel pile Connection Ready for pole

    3.1 Foundation

    The foundation is a large steel pile (a pipe 1,5 m in diameter, 22 mm thickness, 7 to11 m long)

    driven into the ground by using a hydro hammer (9,2 tons). This method was suitable for soil

    with the actual occurrence of sand and clay on this line. The working time for this operation isapproximately 30 minutes per pile.

  • 7/22/2019 CIGRE b2-305

    5/8

    5

    A 2 m base section of the shaft is overlapping the upper part of the pile on a length of 1,5 m.

    The necessary strength connection between shaft and pile is established by concreting this

    volume with concrete with a compressive strength of min. 60 MPa. Together with the ribs in

    both the base and the pile it forms a shear lock, which is able to transfer the forces between the

    elements.

    This connection principle allows rather big tolerance between pile and shaft. Finaly a concrete

    plinth is concreted outside the base section.

    This process includes correct alignment of the shaft as well as a fine corrosion protection of the

    vulnerable steel part through terrain surface. The corrosion protection of the pile itself is based

    on extra wall thickness as corrosion allowance.

    3.2 Erection of Towers

    The new concept for design of shaft and foundation was very advantageous concerning

    erection of tower systems. Each section of the shaft is supplied with heavy flanges for boltingshaft sections together.

    Therefore each shaft section is put on top of the adjacent section and on top of the base sec-

    tion at the foundation by a mobile crane and the flanges are bolted together.

    After that the assembled tower top together with insulators and stringing accessories are lifted

    up by the mobile crane and connected to the shaft by flange bolting. This whole operation is

    done in a few hours.

    Erection of shaft Stringing Lifting lattice top

    3.3 Technical Experiences

    During the design and construction process many issues had to be addressed.

    A few examples are given below.

    3.3.1 Overhead Line with " Bendings"

    The route of the line was designed with many small bendings in order to adapt the route to thelandscape and the farms in the area. Towers influenced by these bendings (angles up to 5o)

  • 7/22/2019 CIGRE b2-305

    6/8

    6

    will have increased forces in tower top, shaft and foundation and the shafts and foundations for

    these towers were strengthened compared to the normal suspension towers. This was judged

    beneficial for the line expression in spite of the increased weight of the structures.

    As V-chains were used everywhere, the appearance from tower to tower did not change even

    if the line angle varied from tower to tower.

    Overhead line with bendings The line in the landscape

    3.4.2 Materials Used

    Structural steel used for shafts is of the type S 355 J 2G3 (EN 10025). This was because of

    strength, but also because of chemical composition of this steel. As the whole shaft is hot

    dipgalvanised, and the zinc thickness should be at least 200 m for 50 years service time

    without any maintenance, this steel is the most suitable.

    The tubular stainless steel in the tower head is of quality 1.4307 (EN 10088). This is the

    cheapest type, which is enough for corrosion stability, and a low carbon type because of easy

    welding qualities.

    Stainless steel castings are of quality 1.4308 (prEN 10213), which is a proper compromise

    between cheap steel, but with reasonably strength, corrosion stability and easy welding.

    All bolts are of type 8.8, hot dip galvanised, which is sufficient because all bolt are placed inside

    the tower.

    3.4.3 Casting of Stainless Steel Joints

    The moulds for the castings were manufactured as part of the development project and used

    for the prototype as well as for the production of the remaining tower tops.

    For the final delivery tenders were invited on basis of the Directives of the Europe Union and

    the moulds were sent to the chosen producer. It was difficult to deliver castings in the required

    quality, but repairs by welding were rather easy and were done to the extent necessary.

  • 7/22/2019 CIGRE b2-305

    7/8

    7

    Moulds Casting Stainless steel joints

    3.4.4 Vibration of Tower Head Elements

    Vortex shedding around the tubular members in the tower head was foreseen as a potentialproblem and theoretical analyses showed that some members were exposed more than could

    be accepted. They might be damaged by fatigue due to the vortex-induced vibrations. The

    problem was overcome in different ways.

    The outside diameter of one member was reduced in order to change its dynamic properties

    and behaviour.

    After the prototype of the tower head was produced structural damping of the tubular members

    was measured, and the result was as expected very low values: logarithmic decrement below

    1%.

    The most susceptible members were cured for vortex shedding by making holes at the front

    and back of the central part of the members. The favourable effect of the introduced air

    leakage from the pressure side to the suction side of the members was confirmed by wind

    tunnel tests as well as subsequent measurements on the erected prototype. By using the

    results of the measurements in the theoretical analysis the improvement in design lifetime for

    fatigue was shown to be increased by a factor of more than 30, which was fully satisfactory.

    4. EconomyThe costs of the line with the new towers (excl. development costs) are compared to the

    estimated costs of a conventional line with lattice towers placed in the same right of way.

    Costs in EUR 1.000 per km of line

    New line Conventional line

    Conductors: 38 38

    Towers 215 70

    Foundation 76 120

    Insulators, hardware 28 20

    Assembly of towers 14 31Stringing of conductors: 31 31

  • 7/22/2019 CIGRE b2-305

    8/8

    8

    Compensations, etc. 144 144

    Planning, etc. 16 16

    Total: 562 470

    Development costs, incl. full- scale tests: EUR 2 million.

    5. Future Development

    In the current design there is still potential for improvements. A further optimisation of the

    construction may result in a reduction of the tower price and a better logistic work process both

    at the factory and in the field.

    The successful design signal has resulted in a proposal for a new 2x400 kV tower,

    based on the same design principle and using the experiences obtained in the development of

    the 1x400 kV tower.

    The illustrations below exemplify designs that are investigated for the time being.

    dragonfly eagle