CITY GATE Phase 1: Project assessment and functional analysis (3 weeks) - Functions and Operations – identify business functions of each building, and its essential operations - Access – define the access requirements and restrictions – by day, times and location – of authorized users necessary to enable the intended function of the building - Interdependence – identify interdependencies and access requirements of authorized and revenue to the common areas, restricted areas and secure/prohibited areas. - Shared risks – define the shared risks and single points of failure created by business functions and building infrastructure together with the access requirements of authorized users. 1 st week 2- day meeting with the Design team Tabletop discussion regarding the findings (with the internals) Clarificatory meetings 2 nd week Report writing and analysis Wednesday: Consultation (initial report) 3 rd week Monday: Submission of final report Revisions Final report (Wednesday - morning) Phase 2: Risk assessment (6 weeks) - Asset characterization - Risk classification - Threat characterization External ( political, socio economic, terrorism and extremism, criminal, natural disasters) Internal ( safety hazards, stakeholders) - Profiling of protective forces and support groups - Risk exposure and vulnerability assessment - Risk matrix 1 st week Field observation/ ocular/ interview Data gathering

Upload: kaatevi

Post on 12-Jan-2016

4 views

Category:

Documents


0 download

DESCRIPTION

city

TRANSCRIPT

Page 1: CITY GATE

CITY GATE

Phase 1: Project assessment and functional analysis (3 weeks)

- Functions and Operations – identify business functions of each building, and its essential operations

- Access – define the access requirements and restrictions – by day, times and location – of authorized users necessary to enable the intended function of the building

- Interdependence – identify interdependencies and access requirements of authorized and revenue to the common areas, restricted areas and secure/prohibited areas.

- Shared risks – define the shared risks and single points of failure created by business functions and building infrastructure together with the access requirements of authorized users.

1st week 2- day meeting with the Design teamTabletop discussion regarding the findings (with the internals) Clarificatory meetings

2nd week Report writing and analysisWednesday: Consultation (initial report)

3rd week Monday: Submission of final report RevisionsFinal report (Wednesday - morning)

Phase 2: Risk assessment (6 weeks)

- Asset characterization- Risk classification- Threat characterization

External ( political, socio economic, terrorism and extremism, criminal, natural disasters) Internal ( safety hazards, stakeholders)

- Profiling of protective forces and support groups- Risk exposure and vulnerability assessment- Risk matrix

1st week Field observation/ ocular/ interviewData gatheringMeeting (re: findings)

2nd week Data gathering (desktop/field)3rd week Risk analysis (risk matrix)

Threat analysis4th week Report writing

Initial report deadline (Saturday)5th week Report writing

Submission of final report (Wednesday)Revisions

6th week Final report (Monday)

Page 2: CITY GATE

Phase 3: Design documents and Workshop for the final approval of design studies (8 weeks)

- Physical security- Access control and integration- Building requirements

1st week Ocular/ documentation

2nd week Table top discussion3rd week Planning

Market researchDesign concept and guidelines

4th week Design of detailed project security systemSaturday: Initial reportMeeting with the team (initial presentation for approval)

5th week PolishingFinal reportPresentation and discussion

6th Revisions

Phase 4: Security Management Plan (6 – 8 weeks)

1st week Discussion/ brainstormAnalysis

2nd week BrainstormSecurity plan development

3rd week Security plan development4th week Presentation/ report (status)5th week Security plan and development6th week Report writing

Friday (Initial report)7th week Revisions

Final report

Phase 5: Consultation fine tuning and adjustments of designs (1 week)