CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 www.kirklandwa.gov
MEMORANDUM
To: Kurt Triplett, City Manager
From: George Minassian, P.E., Sr. Project Engineer Rod Steitzer, P.E., Capital Projects Manager Julie Underwood, Interim Public Works Director
Date: June 25, 2020
Subject: ANNUAL STREET PRESERVATION PROGRAM 2020 STREET OVERLAY PROJECT—AWARD CONTRACT
RECOMMENDATION:
City Council to award a construction contract for the Annual Street Preservation Program (SPP), 2020 Street Overlay Project (Project), to Lakeside Industries of Issaquah, Washington, in the amount of $1,543,365.15.
By taking action on this item under the Consent Calendar, the City Council is awarding a construction contract for the subject project.
BACKGROUND DISCUSSION:
The City uses a Pavement Management System to manage and prioritize preservation treatments throughout the City’s street network. The Pavement Management System considers all City streets in terms of existing pavement conditions (Pavement Condition Index, or PCI), prior maintenance history, the City’s annual budget for street preservation, and other factors to determine the most cost-effective treatment. Once selected for treatment, candidate streets are then reviewed for potential conflicts with other construction projects (e.g., other CIP projects, private development, Washington State Department of Transportation projects, and private utility work). High priority street segments that do not have construction conflicts are added to the current year’s program list. For the 2020 Street Overlay Project, the highest-ranking streets will receive subgrade preparation and repair, pavement milling, and the application of a new wearing surface layer of asphalt.
For several years, the Annual Street Preservation Program included three construction phases, concrete and ADA ramp repairs, the overlay, and an annual Slurry Seal project. This year, SPP consists of the 2020 Street Overlay Project. The concrete work needed for 2020 overlay program was completed in advance as part of the 2018 Program and the federally funded Lake Front Project. The 2020 program will not include a Slurry Seal phase, as the amount of slurry seal street candidates was not big enough to make it economically viable to justify a project.
Council Meeting: 07/07/2020 Agenda: Awards of Bids Item #: 8. e. (1)
Memorandum to Kurt Triplett June 25, 2020
Page 2
As such, there is only one phase in this year’s program, but staff anticipates that the 2021 Street Preservation Program will resume having three phases of work. This year’s Project originally included 4 streets:
• NE 132nd Street from Juanita Dr to 80th Avenue NE, • 84th Ave NE from NE 132nd Street to NE 124th Street, • Market Street from 16th Ave to Central Way, and • 3rd Street from Central Way to 7th Ave.
However, the construction progress of the developer at 312 Central Way (old Wendy’s location) is behind schedule due to delays caused by COVID-19, and as such, 3rd Street will not be ready to be resurfaced as part of this year’s program and it will be added to next year’s program. This year’s project was bid with three schedules of work for a total of 5.4 lane miles (see Attachment A, “Project Vicinity Map”). With an engineer’s estimate of $1,858,821 for construction of all schedules, the Project was first advertised on May 7, 2020. Three bids were received on May 21, 2020, with Lakeside Industries, being the lowest responsive bidder. The bid results are as follows:
Table 1 – 2020 Street Overlay Bid Results Contractor Total Bid
Lakeside Industries $1,543,365.15 Cadman Materials, Inc. $1,582,523.15 Engineer’s Estimate $1,858,181.50 Watson Asphalt $1,873,237.56
Staff checked the references of the lowest bidder Lakeside Industries and they were very satisfactory. A comparison of the unit prices shows that the average cost of asphalt for overlay in 2020 decreased to $82.50/ton from $95.58/ton in 2019 (Attachment B). Funding The total budget for the Annual Street Preservation Program (SPP) for 2020 is a combination of two revenue sources (Attachment C), including base CIP funding and Proposition 1 Levy funds: Table 2– Street Preservation Program (SPP) Funding (2020 only)
Funding Source City 2020 Street Preservation CIP Funding $1,432,400 2020 Street Preservation Prop 1 Levy $1,870,200
Total 2020 SPP $3,302,600 As shown above on Table 2, the subject project award has an available budget of $3,302,600. Based on the available funding and staff’s recommendation for a contract award for the 2020
Memorandum to Kurt Triplett June 25, 2020
Page 3
Street Overlay Project, the anticipated expenses for the Annual Street Preservation Program for 2020 are shown on Table 3 below: Table 3 – 2020 Street Preservation Project Funding vs. Expenses
Items Funding Available Funding for 2020 SPP $3,302,600
Estimated Expenses Design/Insp./CM/Staff ($750,000) Construction Overlay (this memo) ($1,543,365) Contingency ($231,505)
ESTIMATED TOTAL EXPENSES ($2,524,870) Estimated Funding Balance $777,730
Conclusion The Project will start this summer and is estimated to be complete this fall. With City Council’s approval of award of the construction contract at its July 7 meeting, staff will begin the pre-construction public outreach process by notifying adjacent property owners with an informational mailer describing the Annual Street Preservation Program. This information, along with a regularly updated construction schedule, will also be posted on the City’s website. Construction notice signs will be installed on higher volume streets in advance of the overlay. Door hangers describing the work will also be distributed to all adjacent homes and businesses at least 24 hours prior to construction. Attachment A: Project Vicinity Map Attachment B: Kirkland Annual Street Overlay Program: Cost Comparison Attachment C: Project Budget Report
6th St
S
State
St
6th St W
Kirkland Way
18th Ave
Central Way
I-405
Frwy
LakeWashington
93rd
Ave N
E
NE 132nd St
NE 124th St
NE 85th St
84th
Ave N
E
Holmes Point Dr NE
108th
Ave N
E
NE 120th Pl
NE 131st Way
NE Juanita Dr
Juanita Dr NE
116th
Ave N
E
98th Ave NE
76th
Pl NE
5th Pl
7th Ave
3rd St
116th
Ave N
E
112th
Ave N
E
NE 124th St
Marke
t St
NE 112th St
NE 116th St
Forbes Creek Dr
Waverly Way
6th St
Kirkland Ave
8th St
S
NE 141st St
NE 132nd St
NE 123rd St
84th
Ave N
E
90th
Ave N
E
Holmes Point Dr NE
100th
Ave N
E10
0th Av
e NE
Juanita
-Wood
inville
Way
NE
I-405
Frwy
I-405 Frwy
Lake
St S
Seattle
Kenmore
M:\PW\Staff\GeorgeM\2020 Overlay Streets.mxd Produced by the City of Kirkland. © 2020, the City of Kirkland, all rights reserved. No warranties of any sort, including but not limited to accuracy, fitness or merchantability, accompany this product.
0 2,040Feet
0 0.4Miles
©
2020 Street Overlay Project
Author: Name In Map Doc PropertiesName: 2020 Overlay Streets
Date Saved: 6/3/2020 12:28:21 PM
I5 I1J1
I7 I3 I2I4J5
I6J2J7 J6 J3J8 J4
L1
J0
L6 L2
I8
La
F1
J9
L0
F5
L5 L4
F2
L7 L3L9 L8
E5F3F4
KaK1
E2 E1
C4
K6
E3
C2
K2
C3
N1
C5
K7K9 K8 K0
E4
K4 K3
B4
K5
B3A4
B5C1
B2
H5
N5
A5
H1
O2
D2
N2
D1
N4M1
D0
N7N8
H2
D4D5
G5H4 H3
D3
G1
N3
G4 G3
N6
G2H6
O3
M2 MaM4M9 M5 M0M7M8 M3M6
H7
Overlay StreetParks / Open SpacesSchoolsCross Kirkland CorridorRegional Rail CorridorCity Limits
Schedule C:84th Ave NE
&NE 132nd St
Schedule B:Market St
ATTACHMENT A
Street from to 84th Ave NE NE 124th St NE 132nd StNE 132nd St 80th Ave NE Juanita DrMarket St Central Way 16th Ave
Project Vicinity Map
Schedule Aincludes
project-wide bid l -=-========----_J ' ; I ........ ..._ __ ,/
-
$0
$20
$40
$60
$80
$100
$120
$140
Cost
per
Ton
of A
spha
lt
Year
Kirkland Annual Street Overlay Program Cost Comparison
Kirkland Average Bid $/ton
State Average Price
Bellevue Average Bid Price $/ton
Redmond Average Bid Price $/ton
Linear (Kirkland Average Bid $/ton)
KIRKLAND cost per ton
WSDOT cost per ton
BELLEVUE cost per ton
REDMOND cost per ton
ATTACHMENT B
---
$750,000
$750,000
$1,543,365
$2,226,043
$1,432,400 1,870,200
$777,730
$0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000
FUNDING SOURCES
ACCEPT WORK
AWARD CONTRACT
APPROVED BUDGET
ESTIMATED COST
PHAS
E
Project Budget Report
ENGINEERING CONSTRUCTION CONTINGENCY FUND BALANCE CIP PROP 1 LEVY
Annual Street Preservation - 2020 Street Overlay Project(STC0060000/STC0060300)
(this Memo)
$3,302,600
(2019-2024 CIP UPDATE)
Attachment C
(Fall 2020)
■ ■ ■ ■ ■ ■