class 7 - project cost control and ev

Upload: rumimallick

Post on 06-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Class 7 - Project Cost Control and EV

    1/50

    Monitoring your ProjectMonitoring your ProjectProject Cost ControlProject Cost Control

    InstructorInstructor

    Roger deRoger de PeizaPeiza

  • 8/3/2019 Class 7 - Project Cost Control and EV

    2/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Learning Goals

    1. Cost Control

    2. Earned Value Management

  • 8/3/2019 Class 7 - Project Cost Control and EV

    3/50

    Attendance

  • 8/3/2019 Class 7 - Project Cost Control and EV

    4/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control Cost Control

  • 8/3/2019 Class 7 - Project Cost Control and EV

    5/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Cost Control

    Cost control is concerned with:

    Influencing the factors that create changesto the cost baseline to ensure that changesare agreed upon

    Determining that the cost baseline haschanged

    Managing the actual change when and asthey occur

  • 8/3/2019 Class 7 - Project Cost Control and EV

    6/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    What does Cost Control include?

    1. Monitoring cost performance to detectand understand variances from the plan

    2. Ensuring that all appropriate changes arerecorded accurately in the cost baseline

    3. Preventing incorrect, inappropriate orunauthorized changes from beingincluded in the cost baseline

    4. Informing appropriate stakeholders of

    authorized changes5. Acting to bring expressed cost within

    acceptable limits

  • 8/3/2019 Class 7 - Project Cost Control and EV

    7/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Cost Control Processes

    Inputs

    Cost baseline

    Project funding

    requirements

    Performancereports

    Work performance

    information

    Approved change

    requests

    Project

    management plan

    Tools and Techniques

    Cost change control

    system

    Performance

    measurement

    analysis

    Forecasting

    Project performance

    reviews

    Project management

    software

    Variance

    management

    Outputs

    Cost estimates

    updates

    Cost baseline update

    Performance

    measurement

    Forecasted

    completion

    Requested changes

    Recommended

    corrected actions

    Organizational

    process assets

    (updates)

    Project management

    plan (updates)

  • 8/3/2019 Class 7 - Project Cost Control and EV

    8/50

  • 8/3/2019 Class 7 - Project Cost Control and EV

    9/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Work completion

    In order to have effective project controls, itis imperative that the project team haveaccurate measurements of the workperformed for each scheduled task.

    If this information is not available, no oneknows if there is over or under spending onthe project's budget.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    10/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Examples ofWork Completion Rules

    0/100 Rule

    20/80 Rule

    50/50 Rule

  • 8/3/2019 Class 7 - Project Cost Control and EV

    11/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    0/100 Rule

    Assume that 0 percent of the taskis complete until the entire task isfinished

    Using the 0/100 Rule requires avery conservative approach.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    12/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    20/80 Rule

    Once the task is started, the projectoffice assumes that 20 percent ofthe task is complete

    When the task is finished, theremaining 80 percent is added tothe amount completed

    This method is very cautious, but isless conservative than the 0/100Rule

  • 8/3/2019 Class 7 - Project Cost Control and EV

    13/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    50/50 Rule

    Probably the most popular methodof showing a task's progress is the50/50 Rule.

    This assumes that once the task hasbegun, 50 percent of the task iscompleted

    When the task is completed, theremaining 50 percent is added tothe amount completed

  • 8/3/2019 Class 7 - Project Cost Control and EV

    14/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Cost Control InputChange requests

    Request for changes in the scope ofwork

    May occur in many forms:

    Oral or written

    Direct or indirect

    External or internally initiated

    Legally mandated or optional

    Changes may increase or decreasethe budget

  • 8/3/2019 Class 7 - Project Cost Control and EV

    15/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Cost Control ToolsCost Change Control System

    A system that defines procedures by whichthe cost baseline may be changed

    Includes:

    Paperwork

    Tracking systems

    Approval levels needed for authorizingchanges

  • 8/3/2019 Class 7 - Project Cost Control and EV

    16/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Cost Control ToolsPerformance measurements

    Helps access the magnitude of any variationsthat do occur

    An important part of cost control is to

    Determine what is causing the variance

    Decide if the variance needs corrective action

    Earned ValueAnalysis is useful important to costcontrol

  • 8/3/2019 Class 7 - Project Cost Control and EV

    17/50

    Break

  • 8/3/2019 Class 7 - Project Cost Control and EV

    18/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    What is Earned Value?

    The PMBOK defines earned value asa method of reporting project statusin terms of both cost and time.

    It is the Budgeted Cost ofWorkPerformed (BCWP) regardless of theactual cost incurred.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    19/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Another definition of Earned Value?

    According to Dr. David Frame, theearned value approach allows theproject to examine cost andschedule variances concurrently,enabling them to take a holisticview of project progress.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    20/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The 3 fundamental building blocks of theEarned Value technique

    PV

    Planned Value

    or

    Budget Cost of Work Scheduled (BCWS)

    AC

    Actual Cost

    or

    Actual Cost of Work Performed (ACWP)

    EV

    Earned Value

    orBudgeted Cost of Work Performed (BCWP)

  • 8/3/2019 Class 7 - Project Cost Control and EV

    21/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Planned Value (PV)

    The Planned Value (PV) is the budgetedcost for the work scheduled to becompleted on an activity

    It is the same as the planned budget orhow much was budgeted to perform acertain function

    PV is also called the Budgeted Cost ofWork Scheduled (BCWS)

  • 8/3/2019 Class 7 - Project Cost Control and EV

    22/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The Cost PerformanceMeasurement Baseline

    The BCWS may also be referred to asthe Cost Performance MeasurementBaseline.

    The BCWS shows budget costs relativeto time and quantities for the purposeof comparison, analysis and forecasts ofcosts

    The BCWS is typically shown graphicallycomparing budget costs relative to time

  • 8/3/2019 Class 7 - Project Cost Control and EV

    23/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Actual cost (AC)

    AC is the amount it actually costs toperform the task.

    AC is also called the Actual Cost ofWork Performed (ACWP).

  • 8/3/2019 Class 7 - Project Cost Control and EV

    24/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Establishing a variance

    The concepts of PV and AC offerplanned and actual measurements

    When actual is subtracted fromplanned, a variance is established.

    With the third element, EV orBCWP, the concept of earned valueis introduced.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    25/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Earned Value (EV)

    EV is the amount of money that was budgetedfor the work that has been completed so far

    EV is also called the Budgeted Cost ofWorkPerformed (BCWP)

  • 8/3/2019 Class 7 - Project Cost Control and EV

    26/50

    Cumulative Cost Curve

    Cost

    Duration

    Totalproject

    Planned

    Cost

    Measured

    Period

    SV = EV - PV

    CV = EV - AC

    PV

    EV

    AC

  • 8/3/2019 Class 7 - Project Cost Control and EV

    27/50

    Exercise

    The Fence Part 1Determine the PV, AC and EV

  • 8/3/2019 Class 7 - Project Cost Control and EV

    28/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The Cost Variance

    To calculate the Cost Variance (EV-AC) in the example above, supposethat the AC was $6,000.

    The EV is the value of the work todate, and the AC is the cost toperform the work.

    Using these figures and applying theabove variance formula, there is apositive variance of $2,000.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    29/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    What does this mean?

    The positive variance indicates acost under-run when it is shown byitself.

    However, variance must take intoaccount the schedule of thecompletion of the project, which atthis point in time is behindschedule.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    30/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The schedule variance

    The schedule variance is calculatedas follows:

    SV = EV - PV

    Therefore in our example:

    SV = $8,000 - $10,000 = -$2,000

  • 8/3/2019 Class 7 - Project Cost Control and EV

    31/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Interpreting SV

    One must compare the work that wasplanned to what was actuallyaccomplished.

    Since the project's PV was $10,000 andits earned value is now $8,000, or acompletion of only 80 percent duringthe planned time frame, the value ofthe time schedule slippage is $2,000.

    This variance is a negative value,therefore it implies that the project isbehind schedule.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    32/50

    What does it all mean?

    +Schedule

    Variance

    -Schedule

    Variance

    + Cost Variance

    - Cost Variance

    The project is within budget

    but behind schedule

    Either the task has

    not started or it has

    started and not

    enough resources

    have been applied.

    The project is over budgetand behind schedule

    The project is within budget

    and ahead of schedule

    The project is over budget

    but ahead of schedule

    Money may have been

    spent to crash the

    project.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    33/50

    The Interpretation

    CostVariance

    ScheduleVariance

    Interpretation

    + -The project is within budget but behindschedule

    Either the task has not started or it has

    started and not enough resources have beenapplied.

    - -The project has overrun its budget and isbehind schedule.

    - +The project is ahead of schedule but is over

    budget. Money was probably spent to crash the

    schedule

    + +The project is within budget and ahead ofschedule

  • 8/3/2019 Class 7 - Project Cost Control and EV

    34/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The SV and CV percent

    100*100*%PV

    PVEV

    PV

    SVSV

    !!

    Provide an idea of how much the project isdeviating from the plan.

    To calculate the SV and CV percent use theseformulas:

    100*100*%EV

    ACEV

    AC

    CVCV

    !!

  • 8/3/2019 Class 7 - Project Cost Control and EV

    35/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Cost and Schedule Performance Index

    Another important concept is that ofCost andSchedule Performance Index.

    These two formulas explain how efficiently thework has been accomplished.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    36/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The Cost Performance Index (CPI)

    The Cost Performance Index (CPI) is the ratioof Earned Value to Actual Cost (EV/AC).

    Cost Performance Index (CPI) = EV/AC

    The cumulative CPI (the sum of all individualEVs divided by the sum of all individual ACs) iswidely used to forecast project cost atcompletion

  • 8/3/2019 Class 7 - Project Cost Control and EV

    37/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The magnitude of a possible cost overrun

    To predict the magnitude of apossible cost overrun, the followingformula is used:

    Projected Cost At Completion =

    Original Cost Estimate / CPI

  • 8/3/2019 Class 7 - Project Cost Control and EV

    38/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    CPI explained

    Suppose the value of the work is worth $750(EV).

    It cost $800 to perform the work (AC).

    This means that every dollar spent will provide93.73 cents worth of work.

    This ratio can then be applied to project thepossible costs overrun.

    If the original project cost estimate was $10,000,divided by the calculated CPI of .9373 =$10,669, or a possible $669 overrun.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    39/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The Schedule Performance Index (SPI)

    The Schedule Performance Index (SPI) is theratio of budgeted cost work performed tobudgeted cost of work scheduled (BCWP/BCWS)

    Schedule Performance Index (SPI) =EV/PV

    In some applications areas, the SchedulePerformance Index is used to forecast the projectcompletion date.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    40/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    SPI interpreted

    An interpretation of the SPI is that if $500 worthof work (EV) is performed, and the value ofwork schedule is $400 (PV), each dollar ofscheduled work generated $1.25 worth of work,or a ratio of 25.

    This ratio tells us that for every day of workscheduled, the project is .25 days ahead ofschedule at the point the analysis wascompleted.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    41/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    What does CPI and SPI say about projectperformance

    If the CPI is equal to 1.0, there is perfectperformance.

    If CPI > 1.0, means cost under run, there isexceptional performance.

    If CPI is < 1.0, means cost overrun, theperformance is poor.

    This same generalization is true for the SPI.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    42/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Budgeted at Completion (BAC)

    Budgeted at Completion (BAC) is the sum of allthe budgets (PV) allocated to the project or theproject baseline, i.e. this is what the total effortof the project should cost.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    43/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Estimated at completion (EAC)

    The EAC [(AC/EV) X BAC] or [BAC/CPI] isdefined as either the hour or dollar amount thatprovides a realistic appraisal of the workperformed.

    According to Dr. Kerzner, it is the sum of alldirect and indirect costs to date plus theestimate of all authorized work remaining.

    In other words, the EAC is what the totalproject is expected to cost.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    44/50

    3 Ways of Calculating EAC

    EAC = Actuals to date

    plus a new estimate forall remaining work.

    This approach is most oftenused when past performanceshows that the originalestimating assumptions were

    fundamentally flawed, or thatthey are no longer relevantdue to a change inconditions.

    EAC = Actuals to dateplus remaining budget.

    This approach is most oftenused when current variancesare seen as atypical and theproject management team'sexpectation is that similarvariances will not occur in thefuture.

    EAC = Actuals to date plusthe remaining projectbudget modified by aperformance factor, oftenthe CPI.

    This approach is most oftenused when current variancesare seen as typical of futurevariances.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    45/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The Variance at Completion (VAC)

    Using the EAC, the Variance at Completion(VAC) can be calculated.

    VAC = BAC - EAC

    The VAC provides the best estimate of the

    total cost at the completion of the project.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    46/50

    How to remember all of this

    Question Answer Acronym

    How much work shouldbe done?

    Planned Value orBudgeted cost of work

    scheduled

    PV or BCWS

    How much work is

    done?

    Earned Value or

    Budgeted cost of workperformed

    PV or BCWP

    How much did the workcost?

    Actual Cost or

    Actual cost of workperformed

    AC or ACWP

    What was the total jobsupposed to cost?

    Budget at completion BAC

    What do we now expectthe total job to cost

    Estimate at completionor latest revised

    estimate

    EAC

  • 8/3/2019 Class 7 - Project Cost Control and EV

    47/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    Class Exercise

    The Fence Part 2

    Complete the rest

  • 8/3/2019 Class 7 - Project Cost Control and EV

    48/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The Cumulative Cost Curve

    The Cumulative Cost Curve or S curve is anothereffective monitoring tool in controlling the budget

    This chart provides the cumulative expendituresof the project.

    The cost curves for the planned and actual resultsare graphically shown.

  • 8/3/2019 Class 7 - Project Cost Control and EV

    49/50

    Cumulative Cost Curve

    Cost

    Duration

    Totalproject

    Planned

    Cost

    MeasuredPeriod

    SV = BCWP -

    BCWS

    CV = BCWP -

    ACWP

    BCWS

    BCWP

    ACWP

  • 8/3/2019 Class 7 - Project Cost Control and EV

    50/50

    Agenda

    CostManagement

    Cost Budgeting

    Cost Control

    The End

    Thank youThank you