clic schedule issues

20
CLIC Schedule issues K. Foraz CLIC09 Workshop 12-16 October 2009

Upload: midori

Post on 05-Feb-2016

26 views

Category:

Documents


0 download

DESCRIPTION

CLIC Schedule issues. K. Foraz CLIC09 Workshop 12-16 October 2009. Outline. CLIC-ILC comparisons : From CLIC workshop 2008 to ALCPG09 in Albuquerque CLIC workshop 2008 ILC - GDE in Tsukuba in 2009 ILC - ALCPG09 in Albuquerque in 2009 CLIC schedule progress and issues - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CLIC Schedule issues

CLIC Schedule issues

K. ForazCLIC09 Workshop 12-16 October 2009

Page 2: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

Outline

• CLIC-ILC comparisons : From CLIC workshop 2008 to ALCPG09 in Albuquerque– CLIC workshop 2008– ILC - GDE in Tsukuba in 2009– ILC - ALCPG09 in Albuquerque in 2009

• CLIC schedule progress and issues– Main LINAC: from module production to installation

schedule– Injectors: very first drafts

October, 15een 2009

Page 3: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC workshop 2008From CLIC workshop 2008 to ALCPG09 in Albuquerque

• First draft for the main LINAC was presented:– Phase 1: ~ 7 years– Phase 2: ~ 10 years

• Actions were:– Compare CLIC and ILC assumptions– Review ILC schedule with same CLIC assumptions

October, 15een 2009

Page 4: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

From CLIC workshop 2008 to ALCPG09 in Albuquerque

ILC-GDE Tsukububa 09: ILC schedule – 2 tunnels

• 2 versions were presented:– Unlimited resources total duration = 6 years

– Resource « leveled total duration = 9 years

October, 15een 2009

Page 5: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

From CLIC workshop 2008 to ALCPG09 in Albuquerque

Tsukuba 09: ILC and CLIC Schedule comparison

CLIC ILC

500GeV 3 TeV Unlim. Resour.

Leveled resources

Nb of TBM 2 9 4Nb of teams for elec. general services 4 24 8Nb of teams for cooling and ventilation 4 12 4Nb of teams for cabling 4 24 8Nb of teams for machine installation 2 12 2

(years) 7,2 10,5 6 9,5

2 tunnels

October, 15een 2009

Page 6: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

ALCPG09 in Albuquerque– ILC schedule 1 tunnel

Question raised:• Number of fronts for the machine • Number of TBM

From CLIC workshop 2008 to ALCPG09 in Albuquerque

October, 15een 2009

Page 7: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues

• Main Linac– The schedule of the production of modules has been

checked with respect to the installation schedule (see next slides)

– Since last year, the cross section evolved (ventilation ducts, pipes in “radier”, and the system are becoming more matures (for instance the survey); the progress rates will be reviewed with the project engineers (to be done)

• Injectors– First draft for 500 GeV

October, 15een 2009

Page 8: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues

Modules production and installation• Production

– Tendering process ends t0+1.5 year– Module comp. reception starts t0+3 years– Module assembly starts t0+4 years– Module ready for inst. starts t0+5years– Last module ready for inst t0+10 years– 3 lines of production– 60 months of production

• Installation– Transport : up to 40 modules /day with 6 vehicles (1 shift, 5d/wk) (K.

Kershaw)

Courtesy G. Riddone

October, 15een 2009

Page 9: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues

Schedule of the main LINAC – Machine * Case 1• What is the t0 (for module production) ?

– With the hypothesis that the contracts for modules will be signed 6 months after the start of civil engineering works:► t0(modules)=to(c.e. start)-2 years• modules will have to be stored before installation (see next slides)• but the installation of modules can end at t0(c.e. start)+9 years !!!

-3 -2 -1 0 1 2 3 4 5 6 7 8 9 (years)

Component procurement

Tendering

process

Component receptionModule assembly

Courtesy G. Riddone

500 GeV 3TeV

C.E start of works

October, 15een 2009

Page 10: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

0

5000

10000

15000

20000

Modules production and installationif modules contracts are signed 6 months after the civil engineering starts

StockProductionInstallation

Months

Nb

of m

odul

es

CLIC schedule progress and issues

Schedule of the main LINAC – Machine * Case 1

• 500GeV modules in place at to+6 years• 3TeV modules in place at to+9 years

6-8 & 8-10

4-6 & 5-7

To+4 years

2-4 & 3-5

1-2 & 1-3

October, 15een 2009

Page 11: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

1

2

3

4

5

6

7

8

9

10

11-9(4.39 km)

9-7(4.39 km)

7-5(4.39 km)

5-3(4.39 km)

3-1(6.26 km)

1-2(6.26 km)

2-4(4.39 km)

4-6(4.39 km)

6-8(4.39 km)

8-10(4.39 km)

CLIC schedule progress and issuesFrom module prod. to installation schedule * Case 1

The reverse schedule shows that:2 TBM, 4 teams of each guild and 4 transport vehicles are sufficient to stick with the production of modules

Time for construction and installation of general services for 500 GeV : 5.2 years

Commissioning

October, 15een 2009

Page 12: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

1

2

3

4

5

6

7

8

9

10

11-9(4.39 km)

9-7(4.39 km)

7-5(4.39 km)

5-3(4.39 km)

3-1(6.26 km)

1-2(6.26 km)

2-4(4.39 km)

4-6(4.39 km)

6-8(4.39 km)

8-10(4.39 km)

CLIC schedule progress and issues

With 4 TBM * Case 1

4 TBM gives more margins, and can correspond to 3 CE contracts

Commissioning

October, 15een 2009

Page 13: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues

Schedule of the main LINAC – Machine * Case 2• What is the t0 (for module production) ?

– With the hypothesis that the contracts for modules will be signed 6 months before the start of civil engineering works:► t0(modules)=to(c.e. start)-3 years• modules will have to be stored before installation (see next slides)• but the installation of modules can end at t0(c.e. start)+8 years !!!

-3 -2 -1 0 1 2 3 4 5 6 7 8 9 (years)

Component procurement

Tendering process

Component receptionModule assembly

Courtesy G. Riddone

500 GeV 3TeV

C.E start of works

October, 15een 2009

Page 14: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

0

5000

10000

15000

20000

Modules production and installationif modules contracts are signed when the civil engineering starts

StockProductionInstallation (1.5 years)

Months

Nb

of m

odul

es

CLIC schedule progress and issues

Schedule of the main LINAC – Machine * Case 2

• 500GeV modules in place at to+6 years• 3TeV modules in place at to+8 years

6-8 & 8-10

4-6 & 5-7

To+3 years

2-4 & 3-5

1-2 & 1-3

October, 15een 2009

Page 15: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

1

2

3

4

5

6

7

8

9

10

11-9(4.39 km)

9-7(4.39 km)

7-5(4.39 km)

5-3(4.39 km)

3-1(6.26 km)

1-2(6.26 km)

2-4(4.39 km)

4-6(4.39 km)

6-8(4.39 km)

8-10(4.39 km)

CLIC schedule progress and issuesSchedule of the main LINAC – Machine * Case 2

Just in time schedule ; a 4 TBM version will be more appropriate (see next slide)6 transport vehicles needed

Commissioning

October, 15een 2009

Page 16: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

1

2

3

4

5

6

7

8

9

10

11-9(4.39 km)

9-7(4.39 km)

7-5(4.39 km)

5-3(4.39 km)

3-1(6.26 km)

1-2(6.26 km)

2-4(4.39 km)

4-6(4.39 km)

6-8(4.39 km)

8-10(4.39 km)

CLIC schedule progress and issues

With 4 TBM * Case 2

Commissioning

October, 15een 2009

Page 17: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issuesStart of Module production versus end of installation

October, 15een 2009

-1 -0.5 0 0.5 1 1.55

6

7

8

9

10

500GeV3TEV

Contracts for modules (w.r.t civil eng. start) in years

End

of m

odul

e in

stal

latio

n (f

orm

t0 in

yea

rs)

Page 18: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

CLIC main LINAC - Summary

• The start of the process for the production of modules has an impact on the end dates.

• The next step is to schedule the delivery and tendering process for the other components, as well as the integration milestones.

• Since October the typical cross section changed, and each system is more mature (for instance survey); progress rates need to be reviewed with the groups.

October, 15een 2009

Page 19: CLIC Schedule issues

K. Foraz, CLIC Worshop 2009

1

2

3

4

5

6

7

8

9

10

11-9(4.39 km)

9-7(4.39 km)

7-5(4.39 km)

5-3(4.39 km)

3-1(6.26 km)

1-2(6.26 km)

2-4(4.39 km)

4-6(4.39 km)

6-8(4.39 km)

8-10(4.39 km)

Commissioning

CLIC schedule progress and issuesInjectors 500GeV – first draft for civil engineering

Drive beam + Main beam + curves = 3 years slopes down to points 3 and 2 with a road header (15m/wk), i.e. t0+4 years slopes excavated, in line with the construction of the main LINAC.~ 3 years for the installation and commissioning of the injectors (schedule to be studied)

Injectors & curves3 years

October, 15een 2009

Page 20: CLIC Schedule issues

Conclusions / homeworks (!!)

• Main LINAC– Schedule the delivery and tendering process for the

other components– Review of the progress rates w.r.t the evolution of

the project.• Injectors– Schedule the installation and commissioning– Schedule the injectors for 3TeV

• Technical note on schedule– Started

October, 15een 2009 K. Foraz, CLIC Worshop 2009