BIM Implementation For Megaproject

In Malaysia

Transforming Built Asset Economy through

Open BIM standards

Oct 19, 2016

by

Mohd Harris Ismail Deputy Chairman of BuildingSMART Malaysia Chapter Corresponding Member of BuildingSMART International PAM’s CPD (Professional Practice) Speaker for BIM Former HOD, Construction IT Dept. CIDB Member of RICS ASEAN BIM Working Group 2015 Member of APEC BIM STANDARD DEV COMMITTEE 2012 - 2014 Patron for Draftermal Association Malaysia Trainer and Panel for Curriculum Development (BIM) for MOHE, Malaysia PhD Researchers on Build Environment, UKM

BACKGROUND

BIM Building Information Modelling

❖ Why BIM In Malaysia

❖ Mega Project

❖ Introduction to BIM

❖ BIM Implementation In Mega Project

❖ buildingSMART Participation

Content

BIM Building Information Modelling

• Four Strategic Thrusts in CITP are shown below

• BIM adoption is crucial in ensuring the construction productivity is more than doubled by 2020

• 120 industries are depending on construction industry, hence efficient methodology in

construction is inevitable

Why BIM in Malaysia

BIM Building Information Modelling

Introduction to BIM

BIM can be thought of as a set of database of the

building project. The information in this database

spans the full range of data as an integrated data set

As such, BIM integrates the information created by

many industry domains

Planning Information

Building Information

Design Information

Management Information

Data-rich

database

with all required

building

information

Virtual Design

Analyze

Communication

Estimates

Submittals

RFI’s

As-Built

Facilities

Management

Schedules

Promotes efficiency and high productivity

P E O P L E

Human Activity +

Computer Software

(Technology)

Digital Representation of a

Building and to fulfil BIM

Methodology

Integrated Approach

Co-existence of human activity and computer software is inevitable

P R O C E S S The co-existence, will ultimately induce broad process changes in the delivery of construction projects

Coordination

Trades Subcon

Consultants etc

Submission

KM BP

DO

CONSTRUCTION LIFECYCLE

Inception

Review

PROCUREMENT

Monitoring

Risk Study

Contract Admin

PLAN

CLOSURE

Troubleshooting

Facility Management Concept

DESIGN

Simulation Discrepancies Check

Planning (WP)

CPC CCC

CONSTRUCTION

Asset Management

DLP

Tender

Estimates

Submittals

RFI’s

As-Built

Facilities

Management

Schedules

Better Construction Management

Susta

inabili

ty

Issues in conventional construction phase

Design Pre-

Construction Construction

Commissioning

& Handover Facility

Management

1 2 3 4 5

Planning Design Procurement Construction Handover Acceptance

Ma

inte

nan

ce

Asse

ssm

en

t Problems with

detailed design

Lack of detailed

information on design

Slow correction of

design issues

Delay in

dissemination of new

design

Delay in decision

making by client

Inaccurate project

estimation i.e

Cost & duration

Incomplete clash

detection

Out-of-sync

collaboration due to

information silos

Inefficiency in

procurement

process

Misinterpretation of

design intent

Delay due to rework

Logistics problems

Difficulty in project

monitoring &

controlling

Inaccurate as-built

plans & drawings

Inaccurate &

incomplete

inventory

Need to re-inspect

as-built & inventory

Delay in tests &

inspections

Delay in certificates

issuance

Delay in payment

disbursement

Difficulty in asset and

facility management

Problems in managing

preventive & corrective

maintenance

procedures

Not optimizing use of

resources i.e power &

water

Less than desirable

management of energy,

water & waste

LEED

Malaysia

GBI

MyCrest

Design Management Project Management Facility Management

Reduction of productivity & Leads to Additional cost at every phase

Issues: Cost

Overrun Fragmented Inaccurate

As-built Delays

Uncoordinated

Fragmented

Isolated

Coordinated

Collaborated

BIG ROOM MEETING

COORDINATION MEETING

BIM Building Information Modelling

Contact information

For any enquiries and clarification kindly contact:

MY buildingSMART Berhad

No 21A Jalan Kristal K7/K, Seksyen 7

40000 Shah Alam, Selangor Darul Ehsan

Tel: 03-7731 4850

Fax: 03-7725 1229

Hp: 012-304 3899

Email:

[email protected]

[email protected]