con 2001-cve 4070 construction engineering project organization & stakeholders prof. ralph v....

21
CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Upload: octavia-williamson

Post on 03-Jan-2016

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

CON 2001-CVE 4070

Construction EngineeringProject Organization & StakeholdersProf. Ralph V. Locurcio, PE

Page 2: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Part 1 – The Basics

Day Class Topic and Section Homework Due / Reading

8/18 1 Introduction, course requirements --------------------

8/20 2 Project Organization & Stakeholders Kerzner Ch-11

8/25 3 Contract Types & Controls Kerzner Ch-19

8/27 4 Work Breakdown Structure; HW #1-WBS Handout Kerzner Ch-1

9/1 -- Labor Day Holiday (no class) --------------------

9/3 5 Construction Contract Documents; Kerzner Ch-3

9/8 6 Preconstruction & Bidding; HW#2-Write Resume Class notes

9/10 7 WBS critique; Shop Drawings & Inspections WBS due; Kerzner Ch-21

9/15 8 Tour Construction Project / HW#3-Construction Report Handout

9/17 9 Project Organ & Responsibilities & Study Guide Resume due/Class notes

9/22 10 Test #1 & Critique

Page 3: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Organization…

Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Project Manager

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Design Manager

ProjectArchitect

StructuralEngineer

CivilEngineer

MechEngineer

ElectricalEngineer

A

B

C

Quality Assure

OfficeEngineer

TechnicalInspectors

A/E Const Staff

Resident Engineer

UsingAgency

Contractor or

Construction Manager

Page 4: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Participants & Responsibilities…

The Owner The Designer The Builder The Project Manager (PM) The Construction Manager (CM)

Class exercise: define responsibilities

Page 5: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

The Owner… Pays for the project Accepts the project on completion Sets criteria for design Sets cost parameters Establishes time line for completion Determines contract type Hires the designer & builder Appoints the construction manager Makes decisions when needed

Page 6: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

The Designer… Oversees planning & advises owner Evaluates siting options Develops concept design Prepares contract plans Prepares contract specifications Prepares cost estimates Prepares bid package Assists in selection of builder Assists during construction

Page 7: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

The Builder or Contractor… Prepares and submits bid documents Organizes project team Hires & pays subcontractors Obtains permits and licenses Mobilizes contract work force on NTP Builds IAW plans & specifications Controls quality & cost Manages construction site & safety Turns over completed project on time

Page 8: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

The Project Manager (PM) Represents the Owner in all matters Serves as technical assistant to owner Controls project budget, schedule, quality & timing Makes recommendations on budget, schedule,

changes, & quality changes Makes recommendations on payments Recommends acceptance of project

Page 9: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Construction Manager (CM)… Represents the contractor in all matters Oversees construction operations Monitors schedule & costs Provides interface with client operations Follows all contract provisions Makes recommendations on changes or claims Submits progress payments Responsible for quality control Ensures all work is completed

Page 10: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

One-to-One Relationship…

Single point of contact One person is official rep Locus of authority Makes all decisions Prevents misunderstandings

One person represents each firm Usually the PM & CM

Page 11: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

One-to-One authority…

Organization Organization Organization Organization Organization Organization

One to One

PM CM

Page 12: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

One-to-One authority…

Org

an

iza

tion

Org

an

iza

tion

Org

an

iza

tion O

rga

niz

atio

nO

rga

niz

atio

nO

rga

niz

atio

n

One to One

Page 13: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Constructon Organizations…

Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Project Manager

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Design Manager

ProjectArchitect

StructuralEngineer

CivilEngineer

MechEngineer

ElectricalEngineer

A

B

C

Quality Assure

OfficeEngineer

TechnicalInspectors

A/E Const Staff

Resident Engineer

UsingAgency

Contractor or

Construction Manager

Page 14: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Organization-designOwner

ProjectArchitect

StructuralEngineer

CivilEngineer

MechanicalEngineer

Design Manager

Corporate Management

Project Manager

ConstructionContract

UsingAgency

ElectricalEngineer

Design Staff Design Staff Design Staff Design Staff Design Staff

Consultant A Consultant B Consultant C

Page 15: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Organization-const mgt…

Owner

Quality Assurance

OfficeEngineer

TechnicalInspectors

A/E Const Staff

ResidentEngineer

Corporate Management

Corporate staff

Field site

FoundationElectrical

Mechanical

Shop DrawingsRFI controlMaterialsSamples

SchedulesPayments

RFI responsesClarification of drawings

Monitor compliance

Monitor QC processPrepare QA reports

Monitor corrective actionsDocument QA/QC

Project Manager

ConstructionContract

Responsibility

Page 16: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Organization-const opns

Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Corporate Management

Corporate staff

Field site

Interpret Drawings & SpecsShop Drawings

RFI controlMaterialsSamples

Construction operationsCoordination of trades

SchedulesPayments

Safety-OSHAChanges

RFI responsesClarification of drawings

Monitor compliance

Monitor QC processPrepare QC reportsMake inspections

Take corrective actionDocument QC checks

Project Manager

ConstructionContract

Subcontractor A Subcontractor B Subcontractor C Subcontractor D Subcontractor E

Sub-contracts

Contractor orConstruction

Manager

Page 17: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Organization…

Owner

Quality Control

Superintendent Project Engineer

Project Engineer

Project Manager

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Subcontractor

Design Manager

ProjectArchitect

StructuralEngineer

CivilEngineer

MechEngineer

ElectricalEngineer

A

B

C

Quality Assure

OfficeEngineer

TechnicalInspectors

A/E Const Staff

Resident Engineer

UsingAgency

Contractor or

Construction Manager

Page 18: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

That’s all folks!

Next class… contract types

Page 19: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Contract Homework Do research in your text, on the internet or in the library to describe the

attributes listed below for each of the 7 types of construction contracts (  letter contracts, cost plus contracts, unit price contracts, indefinite quantity contracts, design-build contracts, design contracts and fixed price contracts ).

Turn in this assignment on September 5th. We'll go over the answers in class. Advantages Disadvantages Risks taken by the owner Risks taken by the contractor When should this contract be used

D. The Pyramid assignment will not be due until September 7th.

Page 20: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Tour… Before:

1. Meet at parking lot @ 5:00pm (Eau Gallee & Pineapple)2. Sign Waiver Form(?) and give to me.3. Get hard hat and adjust band.4. Pick up construction tour homework sheet.5. Ask questions during the tour to get info you need.

After:1. Return to parking lot @ 6:00pm.2. Return hard hat to me.3. Tour homework sheet is due Thursday 9/8.4. Next class 9/6 at regular time & place. 6. Don’t forget Quiz #1 on 9/8 7. Blackboard for class notes and powerpoint.8. Have a safe & happy Labor Day

Page 21: CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE

Project Tour Site

P

MH WilliamsCondo Const