construct ceiling frames cpccca3005a€¦ · use the attached plan and the information above to...

59
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A CERT III, Carpentry & Construction Hornsby TAFE Page 1 Construct Ceiling Frames Trade Notes

Upload: others

Post on 13-Jun-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 1

Construct Ceiling

Frames

Trade Notes

Page 2: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 2

Week 1:

INTRODUCTION TO CEILING FRAMING

The ceiling frame is the horizontal area between the top of walls and the roof, which

is designed to enclose the room by providing a dust barrier, insulation and security.

The frame consists of ceiling joists, ceiling trimmers, hanging beams and counter

beams. This system is designed to tie-in with a conventionally pitched skillion, gable

or hip roof.

Note: The ceiling frame of a trussed roof is made up of the bottom chords of the

individual trusses and does not require additional ceiling joists, hanging beams or

counter beams.

Page 3: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 3

Ceiling joists

These are the horizontal members with ends that rest on top of the wall plates. They carry

the ceiling sheets, and provide a lateral tie between the feet of opposing rafters to form a

strong, coupled frame. They may be nailed or bolted to the rafters.

They are spaced at maximum centres of 450 mm and 600 mm depending on their stress

grade, section size and thickness of ceiling lining being used. They may be joined in length

over a wall or under a hanging beam, where the join can be supported.

Refer to AS 1684 for sizes and stress grades.

Coupled roof Non-coupled roof

Stability under load

Failure under

load

Figure 1: Ceiling Joists

Vertical

Deflection

Ceiling Joists

under load

X1 + X2= Lateral Deflection

X1

Sta

bili

ty

un

der

loa

d

X2

St

ab

ilit

y

un

de

r

lo

Page 4: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 4

Ceiling Frame member Identification and terminology.

Ceiling Ties

Ledger

20mm Packer

Counter Beam

Beam

Hanging Beam

Ceiling Trimmer

Beam

Top Plate

Ceiling Joist

Page 5: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 5

Trimmer installed ‘on flat’

to allow rafter later

Ceiling trimmers

These are short lengths of framing material, fixed at right angles between ceiling joists and

at the same spacings as joists. See Figure 3. Normally trimmers are the same material as

ceiling joists.

Ceiling trimmers are· designed to:

Provide fixing for the top internal wall plates

Provide continuous lateral stability for the ceiling frame, in conjunction

with hanging beams.

Provide fixing for the ends of ceiling sheets and cornice.

Hanging Beams

Hanging beams are used to support ceiling joists, generally mid span. Hanging beams

intersect joists mostly at 90°. Metal connectors provide a secure load bearing connection

between a hanging beam and ceiling joist

intersection. Connectors are fixed on alternate

sides of the hanging beam to every second

joist. This technique assists in

preventing the hanging beam from

twisting to one side.

Page 6: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 6

Counter Beams

A counter beam, runs mostly at 90° to the line of hanging beams and underneath the

hanging beam. A counter beam required when the hanging beam's length ‘exceeds’ its

maximum allowable span. The hanging beam sits on a bearing ledger bolted on either side of

the counter beam. See Figure 7.

Student Notes:

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………

………………………………………..

Figure 7: Counter beam supporting hanging beams

Counter beam supporting Hanging beam

Hanging beam Hanging beam illustrated as

checked over Counter beam

Page 7: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 7

Technical Information:

Timber Framing Code AS1684.2 Extract 7.2.4 Ceiling joists

7.2.4.1 General

Ceiling joists shall be at spacings to support ceiling linings.

For coupled roofs, ceiling joists shall be in single lengths or spliced in accordance with

Clause 7.2.4.2, and at the same spacing and in the same direction as the main rafters so that

they may be fixed to, and act as ties between, the feet of pairs of opposing rafters.

Intermediate ceiling joists may be required to support ceiling linings. End bearings of joists

shall be the full width of the supporting wall plate except as provided for in Clause 7.2.4.2.

Page 8: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 8

Fixing Requirements for ceiling Frame Members

9.5 NOMINAL FIXINGS (MINIMUM FIXINGS)

Unless otherwise specified, the minimum diameter of machine-driven nails shall be 3.05 mm

for hardwood and cypress and 3.33 mm for softwood framing. Machine-driven nails shall be

plastic polymer (glue) coated or annular or helical deformed shank nails.

Where the nail length is not specified in Table 5.2 or elsewhere, the minimum depth of

penetration into the final receiving member shall be I 0 times the nail diameter where driven

into side grain or 15 times the nail diameter where driven into end grain. Unless otherwise

specified herein, not less than two nails shall be provided at each joint.

Where plain shank hand-driven nails are used in lieu of machine-driven nails, they shall be a

minimum diameter of 3.15 mm for hardwood and cypress and 3.75 mm for softwood and

other low-density timber.

Nails used in joints that are continuously damp or exposed to the weather shall be hot-dip

galvanized, stainless steel or monel metal. The nominal (minimum) fixings for most joints are

given in Table 9.4.

`

Page 9: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 9

Technical Detail cont

7.2.4.2 Splices and joints in coupled roof

Requirements for splices and joints in coupled roof are given in Clause 7.1.2.1.

7.1.2.1 General

Raftered roofs ('pitched' roofs) shall be either coupled or non-coupled (cathedral or skillion)

(see Clause 2.7.4). Where splices in rafters or ceiling joists are necessary, they shall be made

only at points of support. Splices shall be butt-joined with fishplates to both sides with

minimum length six times the joist depth. Fishplates shall be a minimum of 19 mm thick by

the full depth of rafters or ceiling joists. Alternatively, the rafters or ceiling joists may be

lapped over the support for a distance equivalent to at least three times their depth. Lapped

rafters or ceiling joists, or both ends of the butted rafters or ceiling joists to fishplates, shall

be secured with at least six hand-driven nails, or 8/3.05 mm diameter machine-driven nails,

or with an M12 bolt (see Section 9). Engineered nail plated rafters or ceiling joists shall be

spliced and supported in accordance with the manufacturer's recommendations.

7.2.4.3 Connection to hanging beams

Ceiling joists shall be fixed to hanging beams using 35 x 32 mm min. timber cleats, 25 x

1.6 mm galvanized steel strapping, steel ceiling joist hangers or equivalent approved

fasteners. Each alternate connection shall be fixed to opposite sides of the hanging beam

(see Figure 7.3).

Three Alternative methods to secure ceiling joist to hanging beams.

Fig 4: Fixing of joists to hanging beams with metal connectors

Page 10: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 10

7.2.4.4 Trimming around openings

In a joisted ceiling, any opening (manholes, skylights, and similar openings) shall be

trimmed to provide full support for ceiling linings. Where no loads other than normal

ceiling loads will be carried, trimmers shall be as follows:

(a) Openings up to 1000 mm-same size as ceiling joist.

(b) Openings greater than 1000 mm and up to a maximum of 3000 mm-breadth of

(trimmer to be increased by 20% for each 300 mm in length greater than 1000 mm.

Members shall be connected by framing brackets.

Eg: Using 100 x 50 mm Ceiling joists and a opening of 1800mm

Therefore Say 1800 – 1000 = 800

800 ÷ 300 = round up to 3

Therefore 3 lots of (50 mm wide joist)

5

= 3 X 10

= 30

Therefore 50+30 = 80 nearest size for a 100 X 80=100 X 100

(c) Openings greater than 3000 mm-trimmer size as for hanging beams.

7.2.4.5 Platforms in roof spaces

Ceiling joists shall support ceiling loads only. Any platforms constructed in the roof space

above a ceiling for the support of a storage water heater, feed tank, flushing cistern, or

similar members, shall be designed for these loads.

Page 11: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 11

7.2.5 Hanging beams

7.2.5.1 General

Hanging beams shall support ceiling joists and the attached ceiling materials only. Hanging

beams are usually at right angles (or may be angled or placed off centre) to ceiling joists and

are located directly above them (see Figure 7.2). Requirements for beams supporting roof

and ceiling loads are given in Clauses 7.2.7 and 7.2.8.

Where hanging beams are used as lateral binders, the connection to the external

walls shall be equivalent to that shown in Figure 6.1 0.

Page 12: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 12

AS 1684.2 Extract Cont.

7 .2.5.2 End support of hanging beams

Hanging beams shall be held in a vertical position at both ends by nailing or bolting to an

available rafter, gable end struts or by means of angle strutting from internal walls. End-

bearings of hanging beams shall be the full width of the wall plate. Where hanging beams

span 3.0 m or more, they shall be located directly above a stud, or the plates shall be

stiffened (see Figure 6.8). Where the slope of rafters is such that the depth of a hanging

beam has to be reduced by more than two-thirds in order to avoid interference with roof

cladding, provision shall be made for additional support incorporating a jack ceiling joist

(trimmer) as shown in below figure

Page 13: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 13

Alternative support for Gable end roofs

Hanging beam supported using gable

stud

Page 14: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 14

Ceiling Frame Quantities

Calculations exercise No 1:

Calculate the quantities of materials required to construct the Ceiling Frame for

a Flush Gable Roof.

Page 15: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 15

Ceiling Frame Calculation specification.

The ceiling frame is to be suitable for a flush gable roof.

All timber to be MGP 10

Maximum length available 5100.

90 X 45, Ceiling Joists are to be placed flush with the inside face of the external

walls, all others not to exceed 450mm spacing

90 X 45 Ceiling trimmers are to be placed over the internal wall, not exceeding

450 spacing

Hanging beams to support a CLW of 3000

Hanging Beams section sizes

140 X 35 Max span 2200

240 X 45 Max span 4100

Counter beam not required

Materials Rates.

90 X 45 = $3.20/m

140 X35 = $4.20/m

240 X45 = $8.60/m

Ceiling ties & fixings

Allowance of $1.20 each

Page 16: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 16

Use the attached plan and the information above to answer all questions on

the following pages and then complete the cost sheet supplied.

Question 1: Calculate the number of ceiling joists required.

No. of ceiling joists = ( Int Length of building) Rnd up + 1

Joist spacing

No. of ceiling joists =(5.800) 12.89 = 13 + 1 =14 joists

0.450

Question 2: Calculate the orderable length of ceiling Joists required

Orderable length of ceiling joists = The length of the ceiling joist rounded up to

the nearest orderable length, allow for cuts.

Order 90x45 MGP 10 Radiata Pine 14/5100 metre lengths

Question 3: Estimate the total number of ceiling joist trimmers required.

No. of ceiling trimmers = (Int Width of building) Rnd up + 1

Trimmer spacing

No. of trimmers =(4.600)Rnd up + 1= 10.22 =11 + 1

0.450

=12 trimmers

Question 4: Calculate the exact cut length of a ceiling joist trimmer.

Length of ceiling trimmers

= ceiling joist spacing – thickness of ceiling joist

Length of ceiling trimmers = 450mm – 45 mm = 405mm

Page 17: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 17

Question 5: How many EXTRA ceilings joist lengths would be required if the

ceiling joist trimmers were to be cut from the ceiling joist order lengths.

Extra ceiling joists for trimmers

= Length of trimmers x No. of trimmers÷ (CJ Order Length)

= Extra ceiling joists for trimmer 0.405 x 12= 0.953 lengths

5.1

Therefore order 1 extra ceiling joist @ 5.100 metres

Question 6: What section Size and order length of hanging beam is

required for room A1.

Check :Clear Span of Room = 2200 – 100 = 2100

140 X 35 spans 2200 therefore can be used

Hanging beam for room A1 = 1/140 x 35 @ 2.400 metres long

Question 7: What section Size and order length of hanging beam is

required for room A2.

Check:Clear Span of Room = 6000–(2200 +100+100)

= 3600mm

Therefore 240 x 45 spans 4100 can be used.

Hanging beam for room A2 = 1/240 x 45 @ 3.900 metres long

Question 8: How many ceiling ties would be required?

No. of Ceiling ties required = 1 tie per ceiling joist/ per hanging beam

Therefore 14 ceiling ties

Page 18: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 18

Co

st

$2

44

.80

$1

0.0

8

$3

3.5

4

$1

6.8

0

Tota

l Co

st =

$ 3

05

.22

Rat

e/

m

$3

.20

$4

.20

$8

.60

$1

.20

Tota

l

Lin

ear

76

.5

2.4

3.9

Lin

ear

71

.4

5.1

2.4

3.9

Ord

er

Len

gth

5.1

5.1

2.4

3.9

No

:

14

1 1 1 14

Mat

eria

l

MG

P 1

0

MG

P 1

0

MG

P 1

0

MG

P1

0

Size

90

x 4

5

90

X 4

5

14

0 X

35

24

0 X

45

ITEM

Cei

ling

Fram

e F

lush

Gab

le R

oo

f Ex

erc

ise

1

Cei

ling

Jois

t

Cei

ling

Trim

me

rs

Han

gin

g B

eam

s A

1

Han

gin

g B

eam

A2

Cei

ling

Ties

Page 19: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 19

Ceiling Frame Quantities

Calculations exercise No 2: Using the following plan and specification calculate the quantities and costing of materials

required to construct the Ceiling Frame for a Flush Gable Roof.

Page 20: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 20

Ceiling Frame Calculation specification.

The ceiling frame is to be suitable for a flush gable roof.

All timber to be MGP 10

Maximum length available 6000.

90 X 45, Ceiling Joists are to be placed flush with the inside face of the external walls, all

others not to exceed 600mm spacing’s

90 X 45 Ceiling trimmers are to be placed over the internal wall, not exceeding 600 spacing’s

Hanging beams to support a CLW of 3000

Hanging Beams section sizes

140 X 35 Max span 2200

290 X 45 Max span 4500

Counter beam not required

Materials Rates.

90 X 45 = $3.20/m

140 X35 = $4.20/m

290 X45 = $9.60/m

Ceiling ties & fixings

Allowance of $1.20 each

Use the attached plan and the information above to answer all questions on the following

pages and then complete the cost sheet supplied

Page 21: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 21

Question 1: Calculate the number of ceiling joists required.

Question 2: Calculate the orderable length of ceiling Joists required

Question 3: Estimate the total number of ceiling joist trimmers required.

Question 4: Calculate the exact cut length of a ceiling joist trimmer.

Page 22: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 22

Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist

trimmers were to be cut from the ceiling joist order lengths.

Question 6: What section Size and order length of hanging beam is required for room A1.

Question 7: What section Size and order length of hanging beam is required for room A2.

Question 8: How many ceiling ties would be required?

Page 23: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 23

Co

st

Tota

l Co

st

Rat

e/ m

Tota

l Lin

ear

Lin

ear

Ord

er

Len

gth

No

:

Mat

eri

al

Size

ITEM

COST

SHEET

Page 24: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 24

Week 2

Technical Information cont

7.2.6 Counter beams

7.2.6.1 General

Counter beams may be provided to support hanging beams (see Figures 7.2 and 7.4). End

support of counter beams shall be similar to that for hanging beams (see Clause 7.2.5.2).

Where roof loads are required to be supported on counter beams, they shall be designed as

combined strutting/counter beams (see Clause 7.2.8).

7.2.6.2 Intersection of hanging and counter beams

At intersections of hanging and counter beams, the hanging beam may be checked out over

the counter beam, or butted up to the counter beam. The hanging beams shall be supported

by 45 x 42 mm minimum ledgers fixed at each side of the counter beam with 5/3.05 mm

diameter nails or 2/No. 14 Type 17 screws, or by other proprietary connectors such as joist

hangers (see Figure 7.4).

Page 25: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 25

Hanging beam

Figure 8: Fixing of hanging beam onto a plate

Counter

beam

Page 26: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 26

Ceiling Joist placement and joining requirements Placement and positioning ceiling joists may require joining of ceiling joists. Below are

alternative methods of joining ceiling joists, over internal walls or points of support.

Lapping Ceiling Joist over

support wall

Page 27: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 27

Alternative methods of Lapping or splicing Joints in Ceiling Joists

Page 28: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 28

Page 29: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 29

Drawing Exercise Detail ( Note:Portrait View)

Students to complete scaled drawing on A3

Birdsmouth

Drawing roof hanging beam detail scale 1:5

450

Note: 30mm

depth only

required

10mm

Page 30: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 30

Ceiling Framing and Hip Roofing

The Introduction to Hip Roof and Ceiling Joists. Below is a diagram of a basic hip roof, the

position of ceiling Joists in a hip roof is critical and depends on the location of the roof

members illustrated below.

Plan View

Legend

1. Top Plate

2. Ridge

3. Centering Rafter

4. Crown End

5. Hip Rafter

6. Common Rafters

7. Creeper Rafters

8. Under purlin

Page 31: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 31

Setting out position of Ceiling Joists for a Hip Roof When setting out for hip roofs, a number of calculations and measurements are required

first. Below sets out the process in marking out the top plates for the ceiling joists correctly.

Top Plates

Step 1 Determine the roof span and measure out from the comers marked "A" the distance

A-X This represents half span. Mark these positions on the top plates.

Step 2 Mark out the thickness of the. Crown end rafters and centering rafters. These are

located centrally over the half span "X" lines.

See fig 9·

Step 3 From these positions commence setting out rafter spacing’s towards the building

corners. Do not be concerned if the end spacing is shorter.

Step 4 Common rafter positions along the ridge board can be equally spaced but do not

exceed the maximum spacing specified in the plans.

Step 5 Mark the positions for the ceiling joists and ceiling trimmers by placing a J or T next to

each rafter.

Ridge To mark rafter positions on the ridge, lay the ridge across the ceiling joists or top

plates and transfer the applicable rafter positions directly across, Square these marks onto

both sides of the ridge.

Calculations

Ridge length Calculations

1. Centre line length of ridge = Length of building- Width of building

2. Cut length of ridge = (Length of building- Width of building) + Rafter thickness

Page 32: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 32

Hip Roof Set Out

FIG 9: Set out crown end rafters and centring rafters first. These are all measured half span

from the comers.

NOTE:

Ridge length Calculations

1. Centre line length of ridge = Length of building- Width of building

2. Cut length of ridge = (Length of building- Width of building) + Rafter thickness

Page 33: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 33

Marking out the wall plates to show the correct position of all rafters and ceiling frame

members to suit a hip roof pitched at 25 degrees.

Specification: Legend:

100 X 50 Rafters at 600centres CR = Centring Rafter

100 X 50 Ceiling Joists at 600 centres CE = Crown End

100 X 50 Ceiling Trimmers at 600 centres. R = Rafters

J = Ceiling Joists

SCALE 1:20 T = Ceiling Joist Trimmers

R T

Page 34: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 34

400 tres

40 centres

Class exercise 2: Students to mark out the wall plates to show the correct position of all

rafters and ceiling frame members to suit a hip roof pitched at 25 degrees.

Specification: Legend:

100 X 50 Rafters at 400centres CR = Centring Rafter

100 X 50 Ceiling Joists at 400 centres CE = Crown End

100 X 50 Ceiling Trimmers at 400 centres. R = Rafters

J = Ceiling Joists

SCALE 1:20 T = Ceiling Joist Trimmers

Calculation exercise No 3:

Page 35: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 35

Ceiling Frame Quantities

Calculations exercise No 3:

Using the following plan and specification calculate the quantities and costing of materials

required to construct the Ceiling Frame for a Hip Roof.

Page 36: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 36

Ceiling Frame Calculation specification.

The ceiling frame is to be suitable for a Hip roof.

All timber to be MGP 10

Maximum length available 5400.

90 X 45, Ceiling Joists not to exceed 600mm spacings

Note: No flush Joist (Formula change)

90 X 45 Ceiling trimmers are to be placed over the walls as required, not exceeding 600

spacing’s

Hanging beams to support a CLW of 3000

Hanging Beams section sizes

140 X 35 Max span 2200

240 X 45 Max span 4100

Counter beam not required

Materials Rates.

90 X 45 = $3.20/m

140 X35 = $4.20/m

240 X45 = $8.60/m

Ceiling ties & fixings

Allowance of $1.20 each

Use the attached plan and the information above to answer all questions on the following

pages and then complete the cost sheet supplied.

Page 37: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 37

Question 1: Calculate the number of ceiling joists required.

Question 2: Calculate the orderable length of ceiling Joists required

Question 3: Estimate the total number of ceiling joist trimmers required.

Question 4: Calculate the exact cut length of a ceiling joist trimmer.

Page 38: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 38

Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist

trimmers were to be cut from the ceiling joist order lengths.

Question 6: What section Size and order length of hanging beam is required for room

A1.

Question 7: What section Size and order length of hanging beam is required for room

A2.

Question 8: How many ceiling ties would be required?

Page 39: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 39

Co

st

T

ota

l

Co

st

Rat

e/

m

Tota

l Lin

ear

Lin

ear

Ord

er

Len

gth

No

:

Mat

eri

al

Size

ITEM

C

OS

T

SH

EE

T

Page 40: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 40

Week 3:

Ceiling Frame Quantities

Calculations exercise No 4:

Calculate the quantities of materials required to construct the Ceiling Frame for a Hip Roof.

Page 41: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 41

Ceiling Frame Calculation specification.

The ceiling frame is to be suitable for a Hip Roof.

All timber to be MGP 12

Maximum length available 6000.

90 X 45, Ceiling Joists are not to exceed 600mm spacing.

90 X 45 Ceiling trimmers are to be placed over the internal wall, not exceeding 600 spacing

90 X 45 Max Single span between supports. 2400

Allow extra 100mm on each joist where joists are lapped.

Hanging beams to support a CLW of 2400

Hanging Beams section sizes

240 X 45 Max span 4900

290 X 45 Max span 5200

Counter beam not required

Materials Rates.

90 X 45 = $4.00/m

120 X35 = $5.00/m

240 X45 = $10.00/m

290 x45 = $12.00/m

Ceiling ties & fixings

Allowance of $1.20 each

Page 42: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 42

Use the attached plan and the information above to answer all questions on the following

pages and then complete the cost sheet supplied.

Question 1: Calculate the number of ceiling joists required.

Question 2: Calculate the orderable length of ceiling Joists required

Page 43: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 43

Question 3: Estimate the total number of ceiling joist trimmers required.

Question 4: Calculate the exact cut length of a ceiling joist trimmer.

Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist

trimmers were to be cut from the ceiling joist order lengths.

Page 44: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 44

Question 6: What section Size and order length of hanging beam is required for room A2.

Question 7: What section Size and order length of hanging beam is required for room A3.

Question 8: What section Size and order length of hanging beam is required for room A4.

Question 9: How many ceiling ties would be required?

Extra working Space.

Page 45: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 45

Co

st

Rat

e/

m

Tota

l Lin

ear

Lin

ear

Ord

er

Len

gth

No

:

Mat

eri

al

Size

ITEM

C

OS

T

SH

EE

T

Page 46: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 46

Understanding Basic Principals of the Span Tables

Additional Span Table Information

Determining which section size of Ceiling Joists, Hanging beam and Counter beams requires

an understanding of the specifications, span tables, and the load requirements placed on

individual members. To determine which Hanging Beam should be used the CLW needs to be

calculated. The Ceiling Load width (CLW) is the width of ceiling that contributes ceiling load

to a supporting member. (It is usually measured horizontally).

CLW = X ÷2

CLW is used as an input to span tables for

Hanging beams, and

Strutting beams/ hanging beams

Page 47: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 47

Timber Framing Code Span Tables

Page 48: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 48

Page 49: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 49

Using the span tables determine the minimum section size which may be used for the ceiling

joists in the following examples. Leave grey areas blank.

TIMBER GRADE SINGLE SPAN

(Max CJ Span)

CONTINOUS

SPAN

(Max CJ Span)

JOIST SPACINGS SECTION SIZE

MGP10 3200 600 120 x 45

MGP12 2500 450 90 x 35

MGP12 2400 600 90 x 45

MGP10 2000 450 90 x 35

MGP12 2800 600 90 x 45

MGP10 2400 600 120 x 35

MGP10 3800 450 140 x 45

MGP12 3000 600 120 x 35

MGP10 2800 450 120 x 35

SEAS SW F7 3600 450 150 x 50

SEAS SW F7 2600 600 125 x 38

SEAS SW F7 2000 600 100 x 38

SEAS SW F7 2300 450 10 50

Page 50: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 50

Week4:

Another type of ceiling that can be used in both residential and commercial projects is

known as a suspended ceiling, these can be constructed in a conventional method using

timber or by using a metal frame system eg Rondo system.

When determining what system would suit an understanding of loads requirements will

need to be determined, in addition ceiling joist or framework spacing and finish to ceiling

lining is required. Set out below is an example of standard lining material and required

support spacings, used in residential construction. For ceiling Joist spaced at 450 or 600

spacing’s include.

10 mm Plasterboard, Joists at 450mm centres

13mm Plasterboard at 600mm centres

10mm Reinforced Plasterboard at 600mm centres

4.5mm Fibre Cement (Hardiflex) at 600mm centres

6.5mm Fibre Cement (Villaboard) at 600 centres

140 x 12 mm Vjoint T&G Pine at 600 centres

The section size of ceiling joists can be determined from the correct 1684.2 Span table. The

span tables are designed allowing for conventional ceiling lining eg.1 layer 13mm

plasterboard. Large section sizes will be required for different ceiling loadings eg. Fire rating.

Technical Information AS168.24.2

Page 51: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 51

Fire Rating Ceiling Systems Ceilings that are to be installed in areas that have potential fire threats for occupants, may

need to meet what is known as a fire resistance levels:

Fire Resistance is the ability of a building component to resist a fully developed

fire, while still performing its structural function. Fire resistance levels (FRL) are assigned

as performance criteria, in minutes, for structural adequacy, integrity and insulation. This important

parameter is defined by three numbers, e.g. 30/30/30 for which the:

first number relates to structural stability, i.e. the time to elapse before collapse;

second number is an integrity requirement, i.e. flames must not pass through the component for this

number of minutes;

third number is an insulation value, i.e. limits heat transfer through the component.

The examples below set out requirements for fire rating ceilings. There is more than 1 layer

of plasterboard, so consideration needs to be taken when selecting framework to use.

Information supplied from Boral Product Guide

Plasterboard Application for Systems using 1, 2 or 3 Layers of Plasterboard.

1. Fix Boral Firestop Plasterboard across the Furring Channel, Timber or Steel framing.

2. Butt (end) joints on the first layer (uppermost sheet) not formed on framing members should be back-

blocked as described under "Back-blocking".

3. The first layer (uppermost) of Firestop plasterboard sheets are fastened at 200mm max. centres in the field

of board and at 150mm max. centres on ends and edges (staggered).

4. Additional layers of Firestop plasterboard sheets are fixed in the same manner as the first layer but with

joints staggered between layers min. 200mm.

5. Additional layer butt joints not formed on a framing member are screw laminated to the previous layer at

200mm max. centres.

6. Tape and finish face sheet with preferred Boral Plasterboard jointing system.

Page 52: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 52

Page 53: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 53

Page 54: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 54

Page 55: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 55

Page 56: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 56

Small Cottage Quantities Calculations

Students to complete the Quantities for the cottage and upload into test and Quiz’s on completion of

the module.

Class Exercise

Step1.

Ceiling Joist set out and Hanging Beam Positioning Detail

Using the following Plan and Span Tables set out and mark suitable location of Ceiling Joists

to suit. Then calculate and identify the most suitable section size material required for the

job.

Specification

Rafter/ Trimmer Spacings @ 600centres

Hanging Beam CLW = 2800

Allow for 10mm Gyprock Ceiling.

Step 2.

Take off quantities to construct the ceiling frame, Calculate the quantity of Ceiling Joists ,

Trimmers, Hanging beams etc. Complete questions In Tasks & Quiz.

Page 57: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 57

D 2

D 1

D 3

RW

P

RW

P

LIV

ING

BA

TH

RO

OM

BE

DR

OO

M

RW

P

10

00

0

6 0

20

90

3 7

10

90

60

02

40

06

91

0

7 20090

3 420

90

3 510

90

2 400 3 910890

6 2

00

90

6 0

20

90

1 3

00

3 6

00

1 3

00

3 8

00

90

0

2

3 600

90

3 420

90900 1800 900 1200

3 300

300

W 1

W 2

W 3

W 4

EL

EV

AT

ION

2

2400

2200

25

DE

G. R

OO

F P

ITC

H

WE

AT

HE

RT

EX

CL

AD

DIN

G

45

0

1F

LO

OR

PL

AN

U/S

HE

AD

FC

L

FF

L R

L.

87

.85

0

90

CO

LO

UR

BO

ND

RO

OF

SH

EE

TIN

G

CE

RT

3 C

AR

PE

NT

RY

ST

AG

E 1

TR

AD

E F

LO

OR

PL

AN

SC

AL

E 1

:10

0D

AT

E:

25

.5.0

5

14

0 X

45

F7

TR

P

SU

PP

OR

T R

AIL

90

X 9

0 F

7

TR

P P

OS

TS

DIR

EC

TIO

N

OF

FL

OO

R J

OIS

TS

DE

CK

90

X 2

0 T

RP

DE

CK

ING

90

X 9

0 F

7

TR

P P

OS

TS

24

0 X

45

F7

TR

P E

DG

E B

EA

M

24

0 X

45

F7

TR

P E

DG

E B

EA

M

FG

L

850

AM

EN

DE

D 2

0.6

.05

DE

CK

DE

TA

ILS

9

.8.0

5 F

FL

RA

ISE

D

Rafter Spacing

600 centres

CLW = 2800

CLW = 6020÷2

= 3010

Therefore 6020

÷3 = 2006

Page 58: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 58

Small cottage: Calculations assessment sheet Workings

Question 1: Calculate the number of ceiling joists required.

C.Js Bedroom + Living Rm = 7020 ÷ 600 Rnd up – 1

= 11.7 Rnd up -1

=11 Joists

Bathroom Area

3710 ÷ 600 Rnd up – 1

= 6.183 Rnd up -1

= 6

Question 2: Calculate the orderable length of ceiling Joists required

CJ Order

= 90 X 35 MGP10 11/ 6300, 6/3900

Question 3: Estimate the total number of ceiling joist trimmers required.

Trimmers = Internal Wall length ÷ Spacing Rnd up + 1 X walls

= 6020÷ 600 rnd up + 1 X 3 Walls = 36

= 3420 ÷ 600 Rnd up + 1 x 1 = 7

Total Trimmers = 36 +7 = 43

Question 4: Calculate the exact cut length of a ceiling joist trimmer.

Spacing – Thickness = 600 – 35 =565

Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist

trimmers were to be cut from the ceiling joist order lengths.

Total trimmers X Cut Length

CJ order length

= 43 X 565

6300

= 4 Lengths @ 6300

Page 59: Construct Ceiling Frames CPCCCA3005A€¦ · Use the attached plan and the information above to answer all questions on the following pages and then complete the cost sheet supplied

Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A

CERT III, Carpentry & Construction Hornsby TAFE Page 59

Question 6: What section Size and order length of hanging beam is required for room Living

Rm.

Step 1. Check CLW = 6020 ÷ 3 = 2007

Step 2. Select section Size CLW = 2400/ Span (3510) = 170 X 45 MGP10

Step 3. Calc order length = 90 + 3510+90= 3690

Order 170 x 45 MGP10 2/3900

Question 7: What section Size and order length of hanging beam is required for room

Bedroom.

Step 1. Check CLW = 6020 ÷ 3 = 2007

Step 2. Select section Size CLW=2400/ Span(3420) = 170 X 35 MGP10

Step 3. Calc order length = 90 + 3420+90= 3600

Order 170 x 35 MGP10 2/3900

Question 8: What section Size and order length of hanging beam is required for room

Bathroom.

Step 1. Check CLW = 3420 ÷ 2 = 1710

Step 2. Select section Size CLW=1800 Span(3710)= 170 X 35 MGP10

Step 3. Calc order length = 90 + 3710+90= 3890

Order 170 x 35 MGP10 1/3900

Question 9: How many ceiling ties would be required?

Number of ties = Number of CJs X Hang Beams

Living / Bedroom = 11 Joists X 2 = 22

Bathroom = 6 Joists

Total = 28 Ties