construct ceiling frames cpccca3005a€¦ · use the attached plan and the information above to...
TRANSCRIPT
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 1
Construct Ceiling
Frames
Trade Notes
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 2
Week 1:
INTRODUCTION TO CEILING FRAMING
The ceiling frame is the horizontal area between the top of walls and the roof, which
is designed to enclose the room by providing a dust barrier, insulation and security.
The frame consists of ceiling joists, ceiling trimmers, hanging beams and counter
beams. This system is designed to tie-in with a conventionally pitched skillion, gable
or hip roof.
Note: The ceiling frame of a trussed roof is made up of the bottom chords of the
individual trusses and does not require additional ceiling joists, hanging beams or
counter beams.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 3
Ceiling joists
These are the horizontal members with ends that rest on top of the wall plates. They carry
the ceiling sheets, and provide a lateral tie between the feet of opposing rafters to form a
strong, coupled frame. They may be nailed or bolted to the rafters.
They are spaced at maximum centres of 450 mm and 600 mm depending on their stress
grade, section size and thickness of ceiling lining being used. They may be joined in length
over a wall or under a hanging beam, where the join can be supported.
Refer to AS 1684 for sizes and stress grades.
Coupled roof Non-coupled roof
Stability under load
Failure under
load
Figure 1: Ceiling Joists
Vertical
Deflection
Ceiling Joists
under load
X1 + X2= Lateral Deflection
X1
Sta
bili
ty
un
der
loa
d
X2
St
ab
ilit
y
un
de
r
lo
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 4
Ceiling Frame member Identification and terminology.
Ceiling Ties
Ledger
20mm Packer
Counter Beam
Beam
Hanging Beam
Ceiling Trimmer
Beam
Top Plate
Ceiling Joist
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 5
Trimmer installed ‘on flat’
to allow rafter later
Ceiling trimmers
These are short lengths of framing material, fixed at right angles between ceiling joists and
at the same spacings as joists. See Figure 3. Normally trimmers are the same material as
ceiling joists.
Ceiling trimmers are· designed to:
Provide fixing for the top internal wall plates
Provide continuous lateral stability for the ceiling frame, in conjunction
with hanging beams.
Provide fixing for the ends of ceiling sheets and cornice.
Hanging Beams
Hanging beams are used to support ceiling joists, generally mid span. Hanging beams
intersect joists mostly at 90°. Metal connectors provide a secure load bearing connection
between a hanging beam and ceiling joist
intersection. Connectors are fixed on alternate
sides of the hanging beam to every second
joist. This technique assists in
preventing the hanging beam from
twisting to one side.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 6
Counter Beams
A counter beam, runs mostly at 90° to the line of hanging beams and underneath the
hanging beam. A counter beam required when the hanging beam's length ‘exceeds’ its
maximum allowable span. The hanging beam sits on a bearing ledger bolted on either side of
the counter beam. See Figure 7.
Student Notes:
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………
………………………………………..
Figure 7: Counter beam supporting hanging beams
Counter beam supporting Hanging beam
Hanging beam Hanging beam illustrated as
checked over Counter beam
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 7
Technical Information:
Timber Framing Code AS1684.2 Extract 7.2.4 Ceiling joists
7.2.4.1 General
Ceiling joists shall be at spacings to support ceiling linings.
For coupled roofs, ceiling joists shall be in single lengths or spliced in accordance with
Clause 7.2.4.2, and at the same spacing and in the same direction as the main rafters so that
they may be fixed to, and act as ties between, the feet of pairs of opposing rafters.
Intermediate ceiling joists may be required to support ceiling linings. End bearings of joists
shall be the full width of the supporting wall plate except as provided for in Clause 7.2.4.2.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 8
Fixing Requirements for ceiling Frame Members
9.5 NOMINAL FIXINGS (MINIMUM FIXINGS)
Unless otherwise specified, the minimum diameter of machine-driven nails shall be 3.05 mm
for hardwood and cypress and 3.33 mm for softwood framing. Machine-driven nails shall be
plastic polymer (glue) coated or annular or helical deformed shank nails.
Where the nail length is not specified in Table 5.2 or elsewhere, the minimum depth of
penetration into the final receiving member shall be I 0 times the nail diameter where driven
into side grain or 15 times the nail diameter where driven into end grain. Unless otherwise
specified herein, not less than two nails shall be provided at each joint.
Where plain shank hand-driven nails are used in lieu of machine-driven nails, they shall be a
minimum diameter of 3.15 mm for hardwood and cypress and 3.75 mm for softwood and
other low-density timber.
Nails used in joints that are continuously damp or exposed to the weather shall be hot-dip
galvanized, stainless steel or monel metal. The nominal (minimum) fixings for most joints are
given in Table 9.4.
`
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 9
Technical Detail cont
7.2.4.2 Splices and joints in coupled roof
Requirements for splices and joints in coupled roof are given in Clause 7.1.2.1.
7.1.2.1 General
Raftered roofs ('pitched' roofs) shall be either coupled or non-coupled (cathedral or skillion)
(see Clause 2.7.4). Where splices in rafters or ceiling joists are necessary, they shall be made
only at points of support. Splices shall be butt-joined with fishplates to both sides with
minimum length six times the joist depth. Fishplates shall be a minimum of 19 mm thick by
the full depth of rafters or ceiling joists. Alternatively, the rafters or ceiling joists may be
lapped over the support for a distance equivalent to at least three times their depth. Lapped
rafters or ceiling joists, or both ends of the butted rafters or ceiling joists to fishplates, shall
be secured with at least six hand-driven nails, or 8/3.05 mm diameter machine-driven nails,
or with an M12 bolt (see Section 9). Engineered nail plated rafters or ceiling joists shall be
spliced and supported in accordance with the manufacturer's recommendations.
7.2.4.3 Connection to hanging beams
Ceiling joists shall be fixed to hanging beams using 35 x 32 mm min. timber cleats, 25 x
1.6 mm galvanized steel strapping, steel ceiling joist hangers or equivalent approved
fasteners. Each alternate connection shall be fixed to opposite sides of the hanging beam
(see Figure 7.3).
Three Alternative methods to secure ceiling joist to hanging beams.
Fig 4: Fixing of joists to hanging beams with metal connectors
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 10
7.2.4.4 Trimming around openings
In a joisted ceiling, any opening (manholes, skylights, and similar openings) shall be
trimmed to provide full support for ceiling linings. Where no loads other than normal
ceiling loads will be carried, trimmers shall be as follows:
(a) Openings up to 1000 mm-same size as ceiling joist.
(b) Openings greater than 1000 mm and up to a maximum of 3000 mm-breadth of
(trimmer to be increased by 20% for each 300 mm in length greater than 1000 mm.
Members shall be connected by framing brackets.
Eg: Using 100 x 50 mm Ceiling joists and a opening of 1800mm
Therefore Say 1800 – 1000 = 800
800 ÷ 300 = round up to 3
Therefore 3 lots of (50 mm wide joist)
5
= 3 X 10
= 30
Therefore 50+30 = 80 nearest size for a 100 X 80=100 X 100
(c) Openings greater than 3000 mm-trimmer size as for hanging beams.
7.2.4.5 Platforms in roof spaces
Ceiling joists shall support ceiling loads only. Any platforms constructed in the roof space
above a ceiling for the support of a storage water heater, feed tank, flushing cistern, or
similar members, shall be designed for these loads.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 11
7.2.5 Hanging beams
7.2.5.1 General
Hanging beams shall support ceiling joists and the attached ceiling materials only. Hanging
beams are usually at right angles (or may be angled or placed off centre) to ceiling joists and
are located directly above them (see Figure 7.2). Requirements for beams supporting roof
and ceiling loads are given in Clauses 7.2.7 and 7.2.8.
Where hanging beams are used as lateral binders, the connection to the external
walls shall be equivalent to that shown in Figure 6.1 0.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 12
AS 1684.2 Extract Cont.
7 .2.5.2 End support of hanging beams
Hanging beams shall be held in a vertical position at both ends by nailing or bolting to an
available rafter, gable end struts or by means of angle strutting from internal walls. End-
bearings of hanging beams shall be the full width of the wall plate. Where hanging beams
span 3.0 m or more, they shall be located directly above a stud, or the plates shall be
stiffened (see Figure 6.8). Where the slope of rafters is such that the depth of a hanging
beam has to be reduced by more than two-thirds in order to avoid interference with roof
cladding, provision shall be made for additional support incorporating a jack ceiling joist
(trimmer) as shown in below figure
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 13
Alternative support for Gable end roofs
Hanging beam supported using gable
stud
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 14
Ceiling Frame Quantities
Calculations exercise No 1:
Calculate the quantities of materials required to construct the Ceiling Frame for
a Flush Gable Roof.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 15
Ceiling Frame Calculation specification.
The ceiling frame is to be suitable for a flush gable roof.
All timber to be MGP 10
Maximum length available 5100.
90 X 45, Ceiling Joists are to be placed flush with the inside face of the external
walls, all others not to exceed 450mm spacing
90 X 45 Ceiling trimmers are to be placed over the internal wall, not exceeding
450 spacing
Hanging beams to support a CLW of 3000
Hanging Beams section sizes
140 X 35 Max span 2200
240 X 45 Max span 4100
Counter beam not required
Materials Rates.
90 X 45 = $3.20/m
140 X35 = $4.20/m
240 X45 = $8.60/m
Ceiling ties & fixings
Allowance of $1.20 each
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 16
Use the attached plan and the information above to answer all questions on
the following pages and then complete the cost sheet supplied.
Question 1: Calculate the number of ceiling joists required.
No. of ceiling joists = ( Int Length of building) Rnd up + 1
Joist spacing
No. of ceiling joists =(5.800) 12.89 = 13 + 1 =14 joists
0.450
Question 2: Calculate the orderable length of ceiling Joists required
Orderable length of ceiling joists = The length of the ceiling joist rounded up to
the nearest orderable length, allow for cuts.
Order 90x45 MGP 10 Radiata Pine 14/5100 metre lengths
Question 3: Estimate the total number of ceiling joist trimmers required.
No. of ceiling trimmers = (Int Width of building) Rnd up + 1
Trimmer spacing
No. of trimmers =(4.600)Rnd up + 1= 10.22 =11 + 1
0.450
=12 trimmers
Question 4: Calculate the exact cut length of a ceiling joist trimmer.
Length of ceiling trimmers
= ceiling joist spacing – thickness of ceiling joist
Length of ceiling trimmers = 450mm – 45 mm = 405mm
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 17
Question 5: How many EXTRA ceilings joist lengths would be required if the
ceiling joist trimmers were to be cut from the ceiling joist order lengths.
Extra ceiling joists for trimmers
= Length of trimmers x No. of trimmers÷ (CJ Order Length)
= Extra ceiling joists for trimmer 0.405 x 12= 0.953 lengths
5.1
Therefore order 1 extra ceiling joist @ 5.100 metres
Question 6: What section Size and order length of hanging beam is
required for room A1.
Check :Clear Span of Room = 2200 – 100 = 2100
140 X 35 spans 2200 therefore can be used
Hanging beam for room A1 = 1/140 x 35 @ 2.400 metres long
Question 7: What section Size and order length of hanging beam is
required for room A2.
Check:Clear Span of Room = 6000–(2200 +100+100)
= 3600mm
Therefore 240 x 45 spans 4100 can be used.
Hanging beam for room A2 = 1/240 x 45 @ 3.900 metres long
Question 8: How many ceiling ties would be required?
No. of Ceiling ties required = 1 tie per ceiling joist/ per hanging beam
Therefore 14 ceiling ties
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 18
Co
st
$2
44
.80
$1
0.0
8
$3
3.5
4
$1
6.8
0
Tota
l Co
st =
$ 3
05
.22
Rat
e/
m
$3
.20
$4
.20
$8
.60
$1
.20
Tota
l
Lin
ear
76
.5
2.4
3.9
Lin
ear
71
.4
5.1
2.4
3.9
Ord
er
Len
gth
5.1
5.1
2.4
3.9
No
:
14
1 1 1 14
Mat
eria
l
MG
P 1
0
MG
P 1
0
MG
P 1
0
MG
P1
0
Size
90
x 4
5
90
X 4
5
14
0 X
35
24
0 X
45
ITEM
Cei
ling
Fram
e F
lush
Gab
le R
oo
f Ex
erc
ise
1
Cei
ling
Jois
t
Cei
ling
Trim
me
rs
Han
gin
g B
eam
s A
1
Han
gin
g B
eam
A2
Cei
ling
Ties
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 19
Ceiling Frame Quantities
Calculations exercise No 2: Using the following plan and specification calculate the quantities and costing of materials
required to construct the Ceiling Frame for a Flush Gable Roof.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 20
Ceiling Frame Calculation specification.
The ceiling frame is to be suitable for a flush gable roof.
All timber to be MGP 10
Maximum length available 6000.
90 X 45, Ceiling Joists are to be placed flush with the inside face of the external walls, all
others not to exceed 600mm spacing’s
90 X 45 Ceiling trimmers are to be placed over the internal wall, not exceeding 600 spacing’s
Hanging beams to support a CLW of 3000
Hanging Beams section sizes
140 X 35 Max span 2200
290 X 45 Max span 4500
Counter beam not required
Materials Rates.
90 X 45 = $3.20/m
140 X35 = $4.20/m
290 X45 = $9.60/m
Ceiling ties & fixings
Allowance of $1.20 each
Use the attached plan and the information above to answer all questions on the following
pages and then complete the cost sheet supplied
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 21
Question 1: Calculate the number of ceiling joists required.
Question 2: Calculate the orderable length of ceiling Joists required
Question 3: Estimate the total number of ceiling joist trimmers required.
Question 4: Calculate the exact cut length of a ceiling joist trimmer.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 22
Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist
trimmers were to be cut from the ceiling joist order lengths.
Question 6: What section Size and order length of hanging beam is required for room A1.
Question 7: What section Size and order length of hanging beam is required for room A2.
Question 8: How many ceiling ties would be required?
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 23
Co
st
Tota
l Co
st
Rat
e/ m
Tota
l Lin
ear
Lin
ear
Ord
er
Len
gth
No
:
Mat
eri
al
Size
ITEM
COST
SHEET
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 24
Week 2
Technical Information cont
7.2.6 Counter beams
7.2.6.1 General
Counter beams may be provided to support hanging beams (see Figures 7.2 and 7.4). End
support of counter beams shall be similar to that for hanging beams (see Clause 7.2.5.2).
Where roof loads are required to be supported on counter beams, they shall be designed as
combined strutting/counter beams (see Clause 7.2.8).
7.2.6.2 Intersection of hanging and counter beams
At intersections of hanging and counter beams, the hanging beam may be checked out over
the counter beam, or butted up to the counter beam. The hanging beams shall be supported
by 45 x 42 mm minimum ledgers fixed at each side of the counter beam with 5/3.05 mm
diameter nails or 2/No. 14 Type 17 screws, or by other proprietary connectors such as joist
hangers (see Figure 7.4).
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 25
Hanging beam
Figure 8: Fixing of hanging beam onto a plate
Counter
beam
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 26
Ceiling Joist placement and joining requirements Placement and positioning ceiling joists may require joining of ceiling joists. Below are
alternative methods of joining ceiling joists, over internal walls or points of support.
Lapping Ceiling Joist over
support wall
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 27
Alternative methods of Lapping or splicing Joints in Ceiling Joists
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 28
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 29
Drawing Exercise Detail ( Note:Portrait View)
Students to complete scaled drawing on A3
Birdsmouth
Drawing roof hanging beam detail scale 1:5
450
Note: 30mm
depth only
required
10mm
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 30
Ceiling Framing and Hip Roofing
The Introduction to Hip Roof and Ceiling Joists. Below is a diagram of a basic hip roof, the
position of ceiling Joists in a hip roof is critical and depends on the location of the roof
members illustrated below.
Plan View
Legend
1. Top Plate
2. Ridge
3. Centering Rafter
4. Crown End
5. Hip Rafter
6. Common Rafters
7. Creeper Rafters
8. Under purlin
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 31
Setting out position of Ceiling Joists for a Hip Roof When setting out for hip roofs, a number of calculations and measurements are required
first. Below sets out the process in marking out the top plates for the ceiling joists correctly.
Top Plates
Step 1 Determine the roof span and measure out from the comers marked "A" the distance
A-X This represents half span. Mark these positions on the top plates.
Step 2 Mark out the thickness of the. Crown end rafters and centering rafters. These are
located centrally over the half span "X" lines.
See fig 9·
Step 3 From these positions commence setting out rafter spacing’s towards the building
corners. Do not be concerned if the end spacing is shorter.
Step 4 Common rafter positions along the ridge board can be equally spaced but do not
exceed the maximum spacing specified in the plans.
Step 5 Mark the positions for the ceiling joists and ceiling trimmers by placing a J or T next to
each rafter.
Ridge To mark rafter positions on the ridge, lay the ridge across the ceiling joists or top
plates and transfer the applicable rafter positions directly across, Square these marks onto
both sides of the ridge.
Calculations
Ridge length Calculations
1. Centre line length of ridge = Length of building- Width of building
2. Cut length of ridge = (Length of building- Width of building) + Rafter thickness
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 32
Hip Roof Set Out
FIG 9: Set out crown end rafters and centring rafters first. These are all measured half span
from the comers.
NOTE:
Ridge length Calculations
1. Centre line length of ridge = Length of building- Width of building
2. Cut length of ridge = (Length of building- Width of building) + Rafter thickness
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 33
Marking out the wall plates to show the correct position of all rafters and ceiling frame
members to suit a hip roof pitched at 25 degrees.
Specification: Legend:
100 X 50 Rafters at 600centres CR = Centring Rafter
100 X 50 Ceiling Joists at 600 centres CE = Crown End
100 X 50 Ceiling Trimmers at 600 centres. R = Rafters
J = Ceiling Joists
SCALE 1:20 T = Ceiling Joist Trimmers
R T
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 34
400 tres
40 centres
Class exercise 2: Students to mark out the wall plates to show the correct position of all
rafters and ceiling frame members to suit a hip roof pitched at 25 degrees.
Specification: Legend:
100 X 50 Rafters at 400centres CR = Centring Rafter
100 X 50 Ceiling Joists at 400 centres CE = Crown End
100 X 50 Ceiling Trimmers at 400 centres. R = Rafters
J = Ceiling Joists
SCALE 1:20 T = Ceiling Joist Trimmers
Calculation exercise No 3:
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 35
Ceiling Frame Quantities
Calculations exercise No 3:
Using the following plan and specification calculate the quantities and costing of materials
required to construct the Ceiling Frame for a Hip Roof.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 36
Ceiling Frame Calculation specification.
The ceiling frame is to be suitable for a Hip roof.
All timber to be MGP 10
Maximum length available 5400.
90 X 45, Ceiling Joists not to exceed 600mm spacings
Note: No flush Joist (Formula change)
90 X 45 Ceiling trimmers are to be placed over the walls as required, not exceeding 600
spacing’s
Hanging beams to support a CLW of 3000
Hanging Beams section sizes
140 X 35 Max span 2200
240 X 45 Max span 4100
Counter beam not required
Materials Rates.
90 X 45 = $3.20/m
140 X35 = $4.20/m
240 X45 = $8.60/m
Ceiling ties & fixings
Allowance of $1.20 each
Use the attached plan and the information above to answer all questions on the following
pages and then complete the cost sheet supplied.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 37
Question 1: Calculate the number of ceiling joists required.
Question 2: Calculate the orderable length of ceiling Joists required
Question 3: Estimate the total number of ceiling joist trimmers required.
Question 4: Calculate the exact cut length of a ceiling joist trimmer.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 38
Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist
trimmers were to be cut from the ceiling joist order lengths.
Question 6: What section Size and order length of hanging beam is required for room
A1.
Question 7: What section Size and order length of hanging beam is required for room
A2.
Question 8: How many ceiling ties would be required?
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 39
Co
st
T
ota
l
Co
st
Rat
e/
m
Tota
l Lin
ear
Lin
ear
Ord
er
Len
gth
No
:
Mat
eri
al
Size
ITEM
C
OS
T
SH
EE
T
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 40
Week 3:
Ceiling Frame Quantities
Calculations exercise No 4:
Calculate the quantities of materials required to construct the Ceiling Frame for a Hip Roof.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 41
Ceiling Frame Calculation specification.
The ceiling frame is to be suitable for a Hip Roof.
All timber to be MGP 12
Maximum length available 6000.
90 X 45, Ceiling Joists are not to exceed 600mm spacing.
90 X 45 Ceiling trimmers are to be placed over the internal wall, not exceeding 600 spacing
90 X 45 Max Single span between supports. 2400
Allow extra 100mm on each joist where joists are lapped.
Hanging beams to support a CLW of 2400
Hanging Beams section sizes
240 X 45 Max span 4900
290 X 45 Max span 5200
Counter beam not required
Materials Rates.
90 X 45 = $4.00/m
120 X35 = $5.00/m
240 X45 = $10.00/m
290 x45 = $12.00/m
Ceiling ties & fixings
Allowance of $1.20 each
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 42
Use the attached plan and the information above to answer all questions on the following
pages and then complete the cost sheet supplied.
Question 1: Calculate the number of ceiling joists required.
Question 2: Calculate the orderable length of ceiling Joists required
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 43
Question 3: Estimate the total number of ceiling joist trimmers required.
Question 4: Calculate the exact cut length of a ceiling joist trimmer.
Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist
trimmers were to be cut from the ceiling joist order lengths.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 44
Question 6: What section Size and order length of hanging beam is required for room A2.
Question 7: What section Size and order length of hanging beam is required for room A3.
Question 8: What section Size and order length of hanging beam is required for room A4.
Question 9: How many ceiling ties would be required?
Extra working Space.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 45
Co
st
Rat
e/
m
Tota
l Lin
ear
Lin
ear
Ord
er
Len
gth
No
:
Mat
eri
al
Size
ITEM
C
OS
T
SH
EE
T
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 46
Understanding Basic Principals of the Span Tables
Additional Span Table Information
Determining which section size of Ceiling Joists, Hanging beam and Counter beams requires
an understanding of the specifications, span tables, and the load requirements placed on
individual members. To determine which Hanging Beam should be used the CLW needs to be
calculated. The Ceiling Load width (CLW) is the width of ceiling that contributes ceiling load
to a supporting member. (It is usually measured horizontally).
CLW = X ÷2
CLW is used as an input to span tables for
Hanging beams, and
Strutting beams/ hanging beams
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 47
Timber Framing Code Span Tables
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 48
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 49
Using the span tables determine the minimum section size which may be used for the ceiling
joists in the following examples. Leave grey areas blank.
TIMBER GRADE SINGLE SPAN
(Max CJ Span)
CONTINOUS
SPAN
(Max CJ Span)
JOIST SPACINGS SECTION SIZE
MGP10 3200 600 120 x 45
MGP12 2500 450 90 x 35
MGP12 2400 600 90 x 45
MGP10 2000 450 90 x 35
MGP12 2800 600 90 x 45
MGP10 2400 600 120 x 35
MGP10 3800 450 140 x 45
MGP12 3000 600 120 x 35
MGP10 2800 450 120 x 35
SEAS SW F7 3600 450 150 x 50
SEAS SW F7 2600 600 125 x 38
SEAS SW F7 2000 600 100 x 38
SEAS SW F7 2300 450 10 50
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 50
Week4:
Another type of ceiling that can be used in both residential and commercial projects is
known as a suspended ceiling, these can be constructed in a conventional method using
timber or by using a metal frame system eg Rondo system.
When determining what system would suit an understanding of loads requirements will
need to be determined, in addition ceiling joist or framework spacing and finish to ceiling
lining is required. Set out below is an example of standard lining material and required
support spacings, used in residential construction. For ceiling Joist spaced at 450 or 600
spacing’s include.
10 mm Plasterboard, Joists at 450mm centres
13mm Plasterboard at 600mm centres
10mm Reinforced Plasterboard at 600mm centres
4.5mm Fibre Cement (Hardiflex) at 600mm centres
6.5mm Fibre Cement (Villaboard) at 600 centres
140 x 12 mm Vjoint T&G Pine at 600 centres
The section size of ceiling joists can be determined from the correct 1684.2 Span table. The
span tables are designed allowing for conventional ceiling lining eg.1 layer 13mm
plasterboard. Large section sizes will be required for different ceiling loadings eg. Fire rating.
Technical Information AS168.24.2
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 51
Fire Rating Ceiling Systems Ceilings that are to be installed in areas that have potential fire threats for occupants, may
need to meet what is known as a fire resistance levels:
Fire Resistance is the ability of a building component to resist a fully developed
fire, while still performing its structural function. Fire resistance levels (FRL) are assigned
as performance criteria, in minutes, for structural adequacy, integrity and insulation. This important
parameter is defined by three numbers, e.g. 30/30/30 for which the:
first number relates to structural stability, i.e. the time to elapse before collapse;
second number is an integrity requirement, i.e. flames must not pass through the component for this
number of minutes;
third number is an insulation value, i.e. limits heat transfer through the component.
The examples below set out requirements for fire rating ceilings. There is more than 1 layer
of plasterboard, so consideration needs to be taken when selecting framework to use.
Information supplied from Boral Product Guide
Plasterboard Application for Systems using 1, 2 or 3 Layers of Plasterboard.
1. Fix Boral Firestop Plasterboard across the Furring Channel, Timber or Steel framing.
2. Butt (end) joints on the first layer (uppermost sheet) not formed on framing members should be back-
blocked as described under "Back-blocking".
3. The first layer (uppermost) of Firestop plasterboard sheets are fastened at 200mm max. centres in the field
of board and at 150mm max. centres on ends and edges (staggered).
4. Additional layers of Firestop plasterboard sheets are fixed in the same manner as the first layer but with
joints staggered between layers min. 200mm.
5. Additional layer butt joints not formed on a framing member are screw laminated to the previous layer at
200mm max. centres.
6. Tape and finish face sheet with preferred Boral Plasterboard jointing system.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 52
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 53
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 54
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 55
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 56
Small Cottage Quantities Calculations
Students to complete the Quantities for the cottage and upload into test and Quiz’s on completion of
the module.
Class Exercise
Step1.
Ceiling Joist set out and Hanging Beam Positioning Detail
Using the following Plan and Span Tables set out and mark suitable location of Ceiling Joists
to suit. Then calculate and identify the most suitable section size material required for the
job.
Specification
Rafter/ Trimmer Spacings @ 600centres
Hanging Beam CLW = 2800
Allow for 10mm Gyprock Ceiling.
Step 2.
Take off quantities to construct the ceiling frame, Calculate the quantity of Ceiling Joists ,
Trimmers, Hanging beams etc. Complete questions In Tasks & Quiz.
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 57
D 2
D 1
D 3
RW
P
RW
P
LIV
ING
BA
TH
RO
OM
BE
DR
OO
M
RW
P
10
00
0
6 0
20
90
3 7
10
90
60
02
40
06
91
0
7 20090
3 420
90
3 510
90
2 400 3 910890
6 2
00
90
6 0
20
90
1 3
00
3 6
00
1 3
00
3 8
00
90
0
2
3 600
90
3 420
90900 1800 900 1200
3 300
300
W 1
W 2
W 3
W 4
EL
EV
AT
ION
2
2400
2200
25
DE
G. R
OO
F P
ITC
H
WE
AT
HE
RT
EX
CL
AD
DIN
G
45
0
1F
LO
OR
PL
AN
U/S
HE
AD
FC
L
FF
L R
L.
87
.85
0
90
CO
LO
UR
BO
ND
RO
OF
SH
EE
TIN
G
CE
RT
3 C
AR
PE
NT
RY
ST
AG
E 1
TR
AD
E F
LO
OR
PL
AN
SC
AL
E 1
:10
0D
AT
E:
25
.5.0
5
14
0 X
45
F7
TR
P
SU
PP
OR
T R
AIL
90
X 9
0 F
7
TR
P P
OS
TS
DIR
EC
TIO
N
OF
FL
OO
R J
OIS
TS
DE
CK
90
X 2
0 T
RP
DE
CK
ING
90
X 9
0 F
7
TR
P P
OS
TS
24
0 X
45
F7
TR
P E
DG
E B
EA
M
24
0 X
45
F7
TR
P E
DG
E B
EA
M
FG
L
850
AM
EN
DE
D 2
0.6
.05
DE
CK
DE
TA
ILS
9
.8.0
5 F
FL
RA
ISE
D
Rafter Spacing
600 centres
CLW = 2800
CLW = 6020÷2
= 3010
Therefore 6020
÷3 = 2006
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 58
Small cottage: Calculations assessment sheet Workings
Question 1: Calculate the number of ceiling joists required.
C.Js Bedroom + Living Rm = 7020 ÷ 600 Rnd up – 1
= 11.7 Rnd up -1
=11 Joists
Bathroom Area
3710 ÷ 600 Rnd up – 1
= 6.183 Rnd up -1
= 6
Question 2: Calculate the orderable length of ceiling Joists required
CJ Order
= 90 X 35 MGP10 11/ 6300, 6/3900
Question 3: Estimate the total number of ceiling joist trimmers required.
Trimmers = Internal Wall length ÷ Spacing Rnd up + 1 X walls
= 6020÷ 600 rnd up + 1 X 3 Walls = 36
= 3420 ÷ 600 Rnd up + 1 x 1 = 7
Total Trimmers = 36 +7 = 43
Question 4: Calculate the exact cut length of a ceiling joist trimmer.
Spacing – Thickness = 600 – 35 =565
Question 5: How many EXTRA ceilings joist lengths would be required if the ceiling joist
trimmers were to be cut from the ceiling joist order lengths.
Total trimmers X Cut Length
CJ order length
= 43 X 565
6300
= 4 Lengths @ 6300
Carpentry & Construction Hornsby Construct ceiling Frames CPCCCA3005A
CERT III, Carpentry & Construction Hornsby TAFE Page 59
Question 6: What section Size and order length of hanging beam is required for room Living
Rm.
Step 1. Check CLW = 6020 ÷ 3 = 2007
Step 2. Select section Size CLW = 2400/ Span (3510) = 170 X 45 MGP10
Step 3. Calc order length = 90 + 3510+90= 3690
Order 170 x 45 MGP10 2/3900
Question 7: What section Size and order length of hanging beam is required for room
Bedroom.
Step 1. Check CLW = 6020 ÷ 3 = 2007
Step 2. Select section Size CLW=2400/ Span(3420) = 170 X 35 MGP10
Step 3. Calc order length = 90 + 3420+90= 3600
Order 170 x 35 MGP10 2/3900
Question 8: What section Size and order length of hanging beam is required for room
Bathroom.
Step 1. Check CLW = 3420 ÷ 2 = 1710
Step 2. Select section Size CLW=1800 Span(3710)= 170 X 35 MGP10
Step 3. Calc order length = 90 + 3710+90= 3890
Order 170 x 35 MGP10 1/3900
Question 9: How many ceiling ties would be required?
Number of ties = Number of CJs X Hang Beams
Living / Bedroom = 11 Joists X 2 = 22
Bathroom = 6 Joists
Total = 28 Ties