CONSTRUCTION UPDATE West Allis - West Milwaukee PROGRESS THIS WEEK: GOALS NEXT 2 WEEKS: MILESTONE DATES: CONSTRAINTS: None Building Start installation of audio/visual wiring Start site concrete Continue flooring installation Continue walking track flooring Continue wood gym flooring Testing of fire alarm system Building Kitchen coiling door installation complete Fire protection system is substantially complete Bathroom specialties are complete Door and hardware installation is progressing Gym subfloor started Site grading for sidewalks is underway HVAC testing and balancing underway Occupancy June 2020 RECREATION & COMMUNITY SERVICES CENTER April 3, 2020 Site Grading for Sidewalks Early Childhood Millwork Installation Kitchen Coiling Doors Office Door Installation

Upload: others

Post on 10-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION UPDATE...• Gym flooring is progressing • Installation of Cubbies for Early Childhood • Occupancy June 2020 RECREATION & COMMUNITY SERVICES CENTER April 17, 2020

CONSTRUCTION UPDATE

West Allis - West Milwaukee

PROGRESS THIS WEEK: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Start installation of audio/visual wiring

• Start site concrete

• Continue flooring installation

• Continue walking track flooring

• Continue wood gym flooring

• Testing of fire alarm system

Building

• Kitchen coiling door installation complete

• Fire protection system is substantially complete

• Bathroom specialties are complete

• Door and hardware installation is progressing

• Gym subfloor started

• Site grading for sidewalks is underway

• HVAC testing and balancing underway

• Occupancy June 2020

RECREATION & COMMUNITY SERVICES CENTER

April 3, 2020

Site Grading for Sidewalks

Early Childhood Millwork Installation Kitchen Coiling Doors

Office Door Installation

Page 2: CONSTRUCTION UPDATE...• Gym flooring is progressing • Installation of Cubbies for Early Childhood • Occupancy June 2020 RECREATION & COMMUNITY SERVICES CENTER April 17, 2020

CONSTRUCTION UPDATE

West Allis - West Milwaukee

PROGRESS THIS WEEK: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete installation of audio/visual wiring

• Complete site concrete

• Continue flooring installation

• Start walking track flooring

• Continue wood gym flooring

• Tie fire alarm and fire protection systems together

Building

• Site sidewalks and approaches are progressing

• Door and hardware installation is progressing

• Gym subfloor is progressing

• Fire alarm testing is near completion

• HVAC testing and balancing underway

• Occupancy June 2020

RECREATION & COMMUNITY SERVICES CENTER

April 10, 2020

Multi-Purpose Room Door Installation

Gym Subflooring Installation Sidewalks on North side of building

Sidewalks on East side of Gym

Page 3: CONSTRUCTION UPDATE...• Gym flooring is progressing • Installation of Cubbies for Early Childhood • Occupancy June 2020 RECREATION & COMMUNITY SERVICES CENTER April 17, 2020

CONSTRUCTION UPDATE

Building

• Complete installation of audio/visual wiring

• Complete the install of the wood flooring

• Start sanding the wood flooring

• Start walking track flooring

• Start spreading topsoil

• Start asphalting playground area

West Allis - West Milwaukee

PROGRESS THIS WEEK: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Site concrete is complete

• Door and hardware installation is progressing

• Installation of plumbing fixtures is progressing

• Gym flooring is progressing

• Installation of Cubbies for Early Childhood

• Occupancy June 2020

RECREATION & COMMUNITY SERVICES CENTER

April 17, 2020

Bathroom Sinks & Countertops

Installation of wood flooring in the Gym Cubbies by Early Childhood entrance

New approach for parking lot

Page 4: CONSTRUCTION UPDATE...• Gym flooring is progressing • Installation of Cubbies for Early Childhood • Occupancy June 2020 RECREATION & COMMUNITY SERVICES CENTER April 17, 2020

CONSTRUCTION UPDATE

Building

• Start installing audio/visual equipment

• Start sealing the gym floor and paint the game lines

• Complete walking track flooring

• Start landscaping

• Start asphalting playground area

West Allis - West Milwaukee

PROGRESS THIS WEEK: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Door hardware installation is near completion

• Spreading of topsoil around the North side of the building

• Sanding of the gym floor is near completion

• Walking track flooring is progressing

• Elevator install has started

• Occupancy June 2020

RECREATION & COMMUNITY SERVICES CENTER

April 24, 2020

Start of Elevator Installation

Sanding of Wood Flooring in the Gym Spreading of topsoil on the North side

Floor Prep on Walking Track