construction activity o3 significant projects | … · south garage to mcmahon residence hall •...
TRANSCRIPT
NorthGarage
StudentUnion
CentralWarehouse
RomeCommons
NathanHale Inn
MirrorLake
EO SmithHigh School
PublicSafety
GampelPavilion
McMahonResidence
Hall
SouthGarage
Fine ArtsComplex
VisitorCenter
Library
BentonMuseum
DRAFT April 13, 2018Subject to change
Building / Site Project
Infrastructure Project
NORTH CAMPUS
N1 North Eagleville Road Infrastructure Repairs & UpgradesN2 Northwest Science Quad Infrastructure Phase IN3 Gant Science Complex RenovationsN4 Central Utility Plant Equipment Replacements & Upgrades
HERITAGE DISTRICT
H1 Wilbur Cross Reading Room RenovationsH2 Beach Hall Interior RenovationsH3 Infrastructure Repairs at Koons, Family Studies & ManchesterH4 Hawley Office Renovations
CORE CAMPUS
C1 Central Campus Infrastructure UpgradesC2 Student Recreation CenterC3 Jim Calhoun Way UtilitiesC4 Central Campus ParkingC5 Gampel Security BollardsC6 Fairfield Circle ReconstructionC7 Babbidge Library Electrical UpgradesC8 History Museum Renovations (May)C9 Steam Vault Repairs
SOUTH CAMPUS
S1 Alumni Residence Halls RenovationsS2 Fine Arts Production FacilityS3 Southeast Campus Infrastructure
OTHERS
O1 Mansfield Road Sealcoating (Aug)O2 Alumni Drive ResurfacingO3 Interior LED Retrofitting---- IT Backbone Cable Pulls---- Wayfinding Implementation
CONSTRUCTION ACTIVITYSignificant Projects | Summer 2018
GreatLawn
SOUTH CAMPUS
CORE CAMPUS
DoddCenter
North Campus & Northwest Residence
Halls
WB Young Building
HERITAGE DISTRICT
S Lot
X Lot
Lot 8
Y Lot
JorgensenCenter
Bookstore
Admissions
Werth Residence
Tower
NORTH CAMPUS
N1
N2N3N4
N1
O3O3
O3
O3
H2
H3
C4
H1
C2
O2 C6O3
C7
H4
O1
H3C9
S2S3
S1
C3
C8
C1
C5C5C2
NO NORTH-SOUTH ROUTE THROUGH CORE CAMPUS• SOUTH GARAGE IS A “DEAD END”• RTE 195 IS PREFERRED ROUTE TO SOUTH CAMPUS FROM NORTH, AND TO NORTH CAMPUS FROM SOUTH• DELIVERIES BY EXTERNAL VENDORS TO BUILDINGS IN RESTRICTED AREAS SHOULD DELIVER TO CENTRAL WAREHOUSE• EVENTS & PROGRAMS MAY CONTACT TRANSPORTATION SERVICES FOR ARRANGING SHUTTLES AND SPECIAL ACCOMMODATIONS
Approaching CampusFROM POINTS NORTH AND WEST Use Discovery Drive via SR44 from SR195FROM POINTS SOUTH AND EAST Use Bolton Road via SR195TOWN (LOCAL) ROADS Construction Vehicles Not Permitted; Event Traffic Discouraged
Summary of Road Closures & Vehicular RestrictionsALUMNI DRIVE Alternating Direction between Hillside Road and Husky Circle, 7-10 days May-July (TBD)
AUDITORIUM ROAD & EXTENSION Closed; Access to Gant loading dock coordinated with project upon request
BENTON SERVICE DRIVE Service, Emergency & Special Permit Vehicles Only
COVENTRY ROAD Closed at Maple Lane
FAIRFIELD WAY Emergency or Special Permit Access Only
GAMPEL SERVICE DRIVE Closed between Jim Calhoun Way and Temporary Administrative Building (May)Restricted to Local Traffic & Trucks Only, Regular Delays
GLENBROOK ROAD Right turn only at North Eagleville Road
SUMMER CONSTRUCTION AND TRAFFIC UPDATEUPDATED April 13, 2018 | Subject to Change
Summary of Road Closures & Vehicular Restrictions (cont’d)HILLSIDE ROAD Closed between Glenbrook Road and Gilbert Road
Restricted Access to Fieldhouse (May-Aug) and McMahon Residence Hall North Side (May)Accessible Drop-Off at McMahon Residence Hall South SideRestricted Access to Bookstore Loading Dock (Jun-Aug)Emergency Vehicle Access – Coordinated with Projects, Staging Apparatus as Necessary
JIM CALHOUN WAY Closed between Gampel Service Drive & Hillside Road (No Access to Hillside Road)Turnaround at Temporary Administrative Building (May)Loop around Champions Center (June-Aug)Through Trucks use Gampel Service Drive to Glenbrook Road
JORGENSEN ROAD No Truck Access or Through Traffic to Auditorium RoadAccessible Drop-Off & Turnaround for Events
MANSFIELD ROAD Alternating Direction & Partial Closure 3 days or nights in August for sealcoating (TBD)
MANSFIELD WAY Open to Emergency Vehicles Only
MAPLE LANE Alternating direction during utility work
NORTH EAGLEVILLE ROAD Open One-Way (Eastbound) between Discovery Drive and Glenbrook RoadOpen Two-Way between SR195 and Glenbrook Road to All Traffic
WHITNEY ROAD & EXTENSION No Through Traffic to Gilbert RoadTurnaround at Dodd Center
SUMMER CONSTRUCTION AND TRAFFIC UPDATEUPDATED April 13, 2018 | Subject to Change
TRAFFIC PATTERNSProbable Impacts | May 2018
NORTH CAMPUS
1. North Eagleville Road One-Way Eastbound
2. Auditorium Road & Extension Closed3. North Garage Access
HERITAGE DISTRICT
1. Mansfield Way Restrictions2. Benton Service Drive Restrictions
CORE CAMPUS
1. Hillside Road Partial Closure and Restrictions
2. Fairfield Way Restrictions3. Jim Calhoun Way Partial Closure and
Restrictions4. Gampel Service Drive Restrictions5. South Garage Access6. Turnaround behind Champions Center7. Whitney Road Restrictions8. Alumni Drive Alternating Direction
(TBD)
SOUTH CAMPUS
1. Coventry Road Partial Closure2. Maple Lane Restrictions3. Loop around Lot 8
NorthGarage
StudentUnion
DoddCenter
CentralWarehouse
JorgensenCenter
RomeCommons
NathanHale Inn
MirrorLake
EO SmithHigh School
PublicSafety
GampelPavilion
McMahonResidence
Hall
Bookstore
VisitorCenter
Library
BentonMuseum
Fine ArtsComplex
WB Young Building
North Campus Residence Halls
NorthwestResidence Halls
UPDATED APRIL 13, 2018Subject to change
S Lot
X Lot
Occasional Delays
Frequent Delays
Restricted Access
Road Closed
Traffic Control Point
SouthGarage
Lot 8
Y Lot
Admissions
Werth Residence
Tower
WilburCross
McHugh (Laurel)
Hall
TRAFFIC PATTERNSProbable Impacts | June – August 2018
NORTH CAMPUS
1. North Eagleville Road One-Way Eastbound
2. Auditorium Road & Extension Closed3. North Garage Access
HERITAGE DISTRICT
1. Mansfield Way Restrictions2. Benton Service Drive Restrictions3. Mansfield Road Partial Closure and
Alternating Direction (TBD)
CORE CAMPUS
1. Hillside Road Partial Closure and Restrictions
2. Fairfield Way Restrictions3. Jim Calhoun Way Partial Closure and
Restrictions4. Gampel Service Drive Restrictions5. South Garage Access6. Turnaround at Champions Center7. Whitney Road Restrictions8. Alumni Drive Alternating Direction
(TBD)
SOUTH CAMPUS
1. Coventry Road Partial Closure2. Maple Lane Restrictions3. Loop around Lot 8
NorthGarage
StudentUnion
DoddCenter
CentralWarehouse
JorgensenCenter
RomeCommons
NathanHale Inn
MirrorLake
EO SmithHigh School
PublicSafety
GampelPavilion
McMahonResidence
Hall
Bookstore
VisitorCenter
Library
BentonMuseum
Fine ArtsComplex
North Campus Residence Halls
WB Young Building
NorthwestResidence Halls
UPDATED APRIL 13, 2018Subject to change
S Lot
X Lot
Y Lot
Lot 8
SouthGarage
Admissions
Werth Residence
Tower
Occasional Delays
Frequent Delays
Restricted Access
Road Closed
Traffic Control Point
WilburCross
McHugh (Laurel)
Hall
NorthGarage
CentralWarehouse
RomeCommons
NathanHale Inn
MirrorLake
EO SmithHigh School
PublicSafety
GampelPavilion
SouthGarage
Fine ArtsComplex
VisitorCenter
Library
BentonMuseum
UPDATED April 13, 2018Subject to change
McMahon Residence Hall to Bookstore• Follow sidewalk along same side of Hillside Rd• Enter Bookstore on left
Bookstore to Student Union• Cross Jim Calhoun Way at designated crossing• Cross Hillside Rd to School of Business side• Follow sidewalk to Student Union on right
Hilltop Residences to Bookstore• Follow ramp to Sherman Field• Along Sherman Field to breezeway at Natatorium• Through breezeway to Hillside Rd• Turn right to Bookstore
Bookstore to Library• Exit Bookstore on Hillside Rd and turn left• Cross Jim Calhoun Way at designated crossing• Cross Hillside Road to School of Business• Continue straight through quad behind School of
Business to Library
South Garage to Dodd Center• Exit stair tower, follow Jim Calhoun Way to Hillside Rd• Cross Hillside Rd to School of Business• Continue straight behind School of Business, through
quadrangle to Whetten Center• Turn right to Dodd Center
South Garage to Rome Commons• Exit stair tower, follow Jim Calhoun Way to Hillside Rd• Turn right on Hilliside Rd and follow to Gilbert Rd• Cross onto Gilbert Rd and follow to Rome Commons
South Garage to McMahon Residence Hall• Exit stair tower, follow Jim Calhoun Way to Hillside Rd• Turn right and follow Hillside Rd to McMahon
Residence Hall on right
North Garage to Jorgensen Center• Exit stair tower and turn right• Follow signs to Hillside Rd
Admissions
DoddCenter
North Campus & Northwest Residence
Halls
WB Young Building
Lot 8
S Lot
X Lot
PEDESTRIAN PATTERNSPreferred Routes | May 2018
• BE SAFE, STAY ALERT AT ALL TIMES• FOLLOW SIGNS & OBEY CROSSING GUARDS• CROSS ROADS ONLY AT CROSSWALKS
JorgensenCenter
StudentUnion
WilburCross
Bookstore
Y Lot
McMahonResidence
Hall
Engineering II
Werth Residence
Tower
McHugh (Laurel)
Hall
School of Business
SUMMER CONSTRUCTION AND TRAFFIC UPDATEUPDATED April 13, 2018 | Subject to Change
MEMBERS
University Planning, Design and ConstructionConstruction sites and activitiesSean Vasington, Ian Dann, Ed Cotter, Lou Gaedt, Heather Schlink
Logistics AdministrationParking, transit, signage, warehouseDwight Atherton, Charlie Grab, Alex Karr
University CommunicationsCampus communication/outreachStephanie Reitz, Tom Breen
Public SafetyTraffic control, pedestrian safety, emergency managementChris Casa, Darren Cook, Chris Renshaw, Steve Garvin
Facilities Operations & Building ServicesTemporary facilities and controlsAris Ristau, Eric Kruger
University Events & Conference ServicesPrograms/Event coordinationCara Workman
FOR MORE INFORMATION ON CONSTRUCTION IMPACTS, PLEASE CONTACT SEAN VASINGTON AT [email protected]
RESOURCE GROUPCurrently coordinating implementation of traffic control points and bridging any communication gaps between campus stakeholders and project representatives. Convening weekly meetings throughout the summer to report activities/observations, monitor campus impacts and coordinate special accommodations
COMMUNICATIONCheck for regular updates at uconn.edu/construction, Daily Digest and UConn Today