East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 1 of 24 East Brunswick Village: Stage 1 CONSTRUCTION MANAGEMENT PLAN East Brunswick Village: Stage 1 127-137, 139 & Part 149 Nicholson Street, Brunswick East Prepared by: Hacer Group Pty Ltd, 87 High Street, Kew, VIC 3101 26th of April 2018 Revision A

Upload: others

Post on 08-Oct-2020

17 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 1 of 24 East Brunswick Village: Stage 1

CONSTRUCTION MANAGEMENT PLAN

East Brunswick Village: Stage 1 127-137, 139 & Part 149 Nicholson Street, Brunswick East

Prepared by: Hacer Group Pty Ltd, 87 High Street, Kew, VIC 3101

26th of April 2018

Revision A

Page 2: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 2 of 24 East Brunswick Village: Stage 1

CONTENTS

1.0 Introduction 2.0 Project Description 3.0 Project Location 4.0 Sequence of Works 5.0 Project Documentation 6.0 Traffic Management Plan / Site Access 7.0 Normal Working Hours and Parking Facilities 8.0 Construction Waste 9.0 Storage of Materials 10.0 Temporary Buildings 11.0 Hoardings 12.0 Storm Water Management Plan 13.0 Dust, Noise, Odour Control & Vehicle Wash Down Facility 14.0 Hazard & Risk Management 15.0 Occupational Health and Safety 16.0 Anticipated Road Closures, Road Occupation and Footpath Closures 17.0 Measures to Protect Council Infrastructure and Surrounding Properties 18.0 Monitoring and Inspection Programme 19.0 Construction Methodology

Appendices Appendix A Preliminary Programme of Works Appendix B Project Document Register Appendix C Traffic Management Plan Appendix D Site Establishment and Hoarding Plan Appendix E Hacer Group Personnel and Emergency Contact

Page 3: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 3 of 24 East Brunswick Village: Stage 1

1.0 INTRODUCTION

This document outlines the Construction Management Plan for the construction of the East Brunswick Village mix use development located at 127-137, 139 & part 149 Nicholson Street, Brunswick East to be undertaken by Hacer Group. The contents of this document includes:

A brief description of the project

Planned project sequencing

Traffic Management Plan

Details of a stormwater management system during construction

Dust, noise and odour control measures

On-site risk management

On-site occupational health and safety

Project team contact details This plan has been prepared to address the construction works that will be carried out on the project and also those outlined in the current approved Town Planning permit requirements.

2.0 PROJECT DESCRIPTION

East Brunswick Village is due to commence onsite works on the 30th of April 2018 following the completion of excavation works on site. Stage 1 development is comprised of 2 levels of basement and two separate building structures (lot 1 & 2). Lot 1 (building A) is 4 levels high, housing 66 apartments and 4 retail tenancies. Lot 2 (building B & C) is comprised of a Coles Supermarket including Liquorland and 157 apartments within levels 1-5. A Coles temporary car park is also located on ground floor.

Page 4: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 4 of 24 East Brunswick Village: Stage 1

3.0 PROJECT LOCATION

The site is located at 127-137, 139 & part 149 Nicholson Street, Brunswick East. The site is located on the west side of Nicholson Street, between Glenlyon Road and Albert Street.

Source: Map Data – 2018 Google

4.0 SEQUENCE OF WORKS

1. Site establishment including the erection of the site amenities on basement 1 level of the east boundary of the site, parallel to John Street (Refer to Appendix D – Site Establishment and Hoarding Plan).

2. Structure works including installation of precast concrete panels and columns, insitu concrete works to floor slabs and the core with the aid of two tower cranes

3. Fit out works (i.e. carpentry, plastering, windows, carpet, joinery and the like) 4. Project handover

Refer to Appendix A - Hacer Group preliminary programme of works.

5.0 PROJECT DOCUMENTATION Refer to Appendix B – Document Register for a list of architectural, structural and service drawings for the projects overall design.

6.0 TRAFFIC MANAGEMENT PLAN / SITE ACCESS Hacer Group has prepared a traffic management plan appropriate for the duration of the project – (Refer to Appendix C – Traffic Management Plan) and shall commence implementation of this plan immediately upon mobilisation on site and council approval.

Page 5: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 5 of 24 East Brunswick Village: Stage 1

If required due to works and site logistics, a request to amend the traffic management plan will be made to the Responsible Authority. The attached traffic management plan completed by Cardno and issued by Hacer Group outlines general traffic flow, site access, construction zones and signage. A traffic management company will be employed by Hacer Group to handle all major traffic management issues including general day to day management of all site access gates and footpaths. The site will have means of access for the duration of the project from Nicholson St and Rickard St. During the structure and fit out stages the use of trucks to complete these works are indicative as per below:

Precast Concrete delivery truck (approx. 17m in length)

Concrete Boom Pump truck (approx. 10m in length)

Concrete Delivery truck (approx. 10m in length)

Flatbed truck (approx. 8m in length)

All deliveries will enter the site via the allocated entry gates and offload onsite to restrict any disturbance to the road/pedestrian traffic on the outskirting roads/footpaths. Entry into the site will only take place via an existing vehicle crossing. A vehicle crossing permit from council will need to be obtained prior to altering an existing and or constructing a temporary vehicle crossing. If required, Work Zones can be applied for by the developer to assist with access in Nicholson Street or Rickard Street. The staging of vehicles should be provided on site where possible. Discussions on appropriate locations away from the site can be discussed at a later date if number of deliveries effect resident amenities. Relevant permits are required for temporary road occupation of any road reserve where pedestrians and vehicle movements will be affected.

LOADING ZONES Hacer Group will be proposing to establish 4 loading bays, all within the site boundaries, subject to VicRoads/council approval of the proposed access gates to site from Nicholson St & Rickard St. The loading zones will be used to facilitate daily deliveries, general site logistics and concrete trucks when concrete pours are being completed onsite.

7.0 NORMAL WORKING HOURS

Construction activity will follow the EPA Noise Guidelines ‘normal working hours’ (as defined in the Environmental Protection Authority Noise Control Guidelines, Publication 1254, October 2008), (or any future version of this document) being:

o 7 am — 6 pm Monday to Friday; and o 7 am — 1 pm Saturdays

A permit must be granted under the Council General Local Law 2018 (Section 10.6) (or any future version of this document) for construction activity outside of ‘normal working hours’.

Requests for construction activity to occur outside ‘normal working hours’ must be submitted to Moreland City Council in writing and must contain justification for the request. Written requests for construction activity outside of ‘normal working hours’ should be submitted to Moreland City Council at least two weeks prior to the scheduled construction activity. In approving any request for construction activity outside of

Page 6: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 6 of 24 East Brunswick Village: Stage 1

‘normal working hours’ Council may direct that notification be provided to nearby neighbours.

TYPICAL ENTRY AND EXIT TIMETABLE

Workers will arrive on site between 6:45am – 7:00am Monday – Saturday

Workers will exit site between 4:00pm – 5.30pm Monday – Friday and Saturday until 1:00pm.

Deliveries will arrive on site between 7:00 am – 5:00 pm Monday – Friday and 7:00am – 12:30pm Saturday.

All workers will minimise noise during the time between arrival and commencing work.

CONTRACTOR PARKING

The 2 main stages of construction and approximated contractors / cars noted below:

Structure Works: Approximately 60 contractors; Approximately 40 cars; Approximate duration of 6 months

Fit out Works: Approximately 150-200 contractors; Approximately 100 cars; Approximate duration of 9 months

Contractors must adhere to road rules and parking restrictions in the local area. The use of public transport as a means of accessing the site will be encouraged to all contractors as part of site induction to minimise the impact of parking on the surrounding area.

8.0 CONSTRUCTION WASTE Recyclability of Common Building Materials

Although most common building materials are easily recycled, this is dependent on the cost effectiveness of the operation. The following table indicates the relative difficulties of recycling common building materials.

Easy to Recycle Difficult to Recycle

Concrete and bricks;

Plasterboard (if in sufficient quantity);

Steel/metal (reinforcing);

Cardboard

Timber;

Glass;

Plastic packaging;

Ceiling tiles; and

Carpet/underlay.

Waste Minimisation Program Measures to Aim to Achieve Diversion from Landfill

The following is an outline of the activities to be undertaken:

Ordering materials to size or required quantities;

Aiming not to over order;

Ordering pre-cut or pre-fabricated materials;

Reducing packaging at source, buying materials with less packaging where possible.

Page 7: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 7 of 24 East Brunswick Village: Stage 1

Training site workers not to damage or contaminate materials or off-cuts so they can be reused on site where possible.

Developing a waste minimisation plan and to reduce, reuse, and recycle materials where practical and economically viable.

Conducting training for all relevant employees as part of site inductions.

Reuse of Infrastructure Waste A waste management contractor will be used to recycle and sort material onsite by way of mixed waste bins. The bins will be collected and transported to a materials recovery facility where waste will be sorted and separated into target materials, e.g. concrete/bricks, timber products, metals. Other materials that are recovered, where viable, at such facilities include large quantities of plasterboard and intact pallets.

Packaging Waste

Packaging waste particularly plastics, by volume, is a significant proportion of construction solid waste streams. Packaging waste clutters building sites posing safety risks, complicates other site recycling efforts by contaminating sorted waste and takes up unnecessary space in bins. For these reasons it is recommended that packaging waste is also targeted as part of the construction waste minimisation plan. Hacer Group minimises packaging as part of base waste minimisation commitments by means of reducing packaging prior to coming on site.

Minimising Packaging Waste

Waste Stream Current Practice

Avoid Reduce Reuse Recycle

Timber pallets Many returned

Return By collection

Plastic packaging strips

Landfill Through purchasing choice

Return By collection

HDPE plastic film Landfill Through purchasing choice

Return By collection

Metal straps Most to Landfill

Reuse By collection

Corrugated cardboard boxes

Landfill Reuse By collection

Paint tins Landfill Ask for plastic tin liners

Buy bulk Return/Reuse tins

Plastic trigger pack tubes

Landfill Buy bulk

Source: Resource Efficient Builder, 1999

9.0 STORAGE OF MATERIALS All storage of materials will be contained within the site perimeters. Hazardous and dangerous materials will be stored and locked on site and recorded on material safety data sheets.

Page 8: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 8 of 24 East Brunswick Village: Stage 1

10.0 TEMPORARY BUILDINGS

The location for the site amenities during construction will be located along the east boundary of the site, running parallel to John St, on basement 1 level. The site amenities will be dismantled at project completion.

11.0 HOARDINGS

As per the Public Protection – 604 of the Building Commission Victoria, a hoarding will maintained around the perimeter of the site. Refer to Appendix D – Site Establishment and Hoarding Plan.

12.0 STORM WATER MANAGEMENT PLAN

Storm Water Management Plan

These procedures describe how water pollution prevention and storm water management should be undertaken to protect environmental quality. Please note that Hacer Group shall undertake required maintenance and upkeep of any temporary storm water or drainage modifications it undertakes.

Objectives Wastewater discharged offsite to be kept to a minimum.

No impact on offsite surface or ground water(s) due to construction activities.

Site storm water will be managed such that there will be no contaminated water discharged off-site.

Targets

Sediment content of storm water minimised.

No impact on surface waters.

Wastewater management to incorporate the principles of reduce, re-use and recycling prior to disposal.

Issue Procedures

General Storage of materials and waste is to be located at least 2 m away from drainage lines.

Oils, fuel and other chemicals are to be located on spill trays or on a sufficiently sized bunded area.

All chemical spills will be contained and cleaned up immediately.

Storm Water Prevent storm water from adjacent sites from entering the development site.

Install hay bales or geotechnical fabric socks around storm water drains to minimise sediment entering storm water.

Remove sediment and rubbish from sediment fences and storm water inlet filters after storm events.

Check sediment traps after storm events.

Undertake inspections of surface runoff during or immediately after storm events.

Apply crushed rock to other frequently used tracks and haul roads that may produce sediment.

Page 9: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 9 of 24 East Brunswick Village: Stage 1

Issue Procedures

Stockpiles or treatment piles of contaminated soils to be capped and bunded.

Storm water discharge quality needs to comply with the SEPP (Waters of Victoria).

Regular inspections of the effectiveness of sediment control measures will be undertaken, with necessary improvements made where required. An inspection will be undertaken after every storm event.

In circumstances where there is a large downpour of rain or when there is large amounts of water pooling onsite, dewatering of the site will occur through a trade waste agreement with Yarra Valley Water, which will deposit through a sediment/filtration tank and then finally deposited into the sewer system. This trade waste agreement will be arranged with Yarra Valley Water if required onsite.

13.0 DUST, NOISE, ODOUR CONTROL & VEHICLE WASHDOWN FACILITY The Dust, Noise and Odour Management Plan outlines the following objectives with respect to control:

• Reduce the effect of construction on nearby residents and employees • Comply with EPA Victoria and Council guidelines with respect to construction noise

and airborne pollutants (i.e. dust). The following outlines the proposed measures to manage dust, noise and odour during construction:

AIR/DUST

These procedures describe how dust control and air quality management should be undertaken to protect air quality.

Objectives

To ensure that air pollution and dust are within acceptable limits and do not pose a health risk or threat to the environment.

To comply with the SEPP (Air Quality Management).

Targets

Air exhausts within acceptable limits.

Dust kept to a minimum.

No complaints received in relation to air emissions or dust.

Issue Procedures

Dust control Water exposed areas when visible dust is observed. Dust observations are to be undertaken on a daily basis.

Stockpiles are to be observed for dust issues every day and will be watered to restrict any dust issues. If watering does not solve the issue, a tarpaulin will be used to completely cover the stockpiles and will be fixed into the ground to eliminate the chance of dust exiting the area.

Stockpiles that are likely to exist on site for a period greater than 1 month must have their surfaces stabilized by a tarpaulin

All truckloads are to be covered during transport.

Page 10: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 10 of 24 East Brunswick Village: Stage 1

Street sweeping will be carried out weekly or more frequently as required to ensure that the adjacent roads and footpaths are kept clean from mud debris and sediment build up. Unscheduled cleansing of affected roads and footpaths will be completed at Councils request.

Air Quality Smoke from the internal combustion engines of construction vehicles should not be visible for more than ten seconds.

Fit vehicles and machinery with emission control devices where design specifications allow.

Service and maintain site construction equipment and vehicles regularly. Maintain a record of servicing and maintenance.

Turn off vehicles when not in use, particularly during loading and unloading.

No burning or incineration of wastes is to occur on-site.

Minimize exposure of soil and groundwater contaminated with hydrocarbons and other volatiles. Cap contaminated stockpiles.

NOISE

These procedures describe how noise emissions will be minimized

Objectives To ensure that the generation of noise from construction activities is kept to a level low

enough to not significantly affect the amenity of neighboring residents, contractors and surrounding land users.

Comply with the SEPP (Control of Noise from Commerce, Industry and Trade).

Targets No complaints received in regards to noise emissions during the construction phase.

No violation of noise regulations.

Issue Procedures

Noise Emissions Limit the speed of vehicles particularly in the vicinity of nearby residents.

Fit all pneumatic tools, vehicles and plant with silencers where specifications allow.

Ensure noise labels are affixed to new mobile air compressors and pavement breakers.

Maintain noise suppression devices to the manufacturer’s specifications.

Regularly maintain equipment and machinery.

Maintain a record of maintenance activities.

Noisy construction and remediation activities will be conducted between the hours of 7.00am to 6.00pm Monday to Friday and 7.00am to 1.00pm Saturday, where such works would cause a nuisance to noise sensitive areas such as neighboring residents. These type of works are not to occur outside normal working hours. Refer to the State Environment Protection Policy (Control of Noise from Commerce, Industry and Trade).

No noise emissions from construction activities will be discernible from a habitable room of a sensitive area between the hours of 6pm and 7am Monday to Friday.

For activities outside scheduled normal working hours obtain prior written approval from the Local Council and notify neighbors of any noisy activities during these hours. The notification to neighbors must include the name and phone number of a contact person.

Page 11: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 11 of 24 East Brunswick Village: Stage 1

No amplified music will be discernible from a habitable room of a neighboring residence

NOISE ATENUATION MEASURES

An acoustic engineer will be engaged at the start of the project to install a noise logger on the south boundary of the site where neighbouring buildings will be most sensitive to construction noise.

A letter drop will be completed to all neighbouring resident properties (as described within the complaints section on page 16) informing them of increased noise works for the first month of works due to excavation of rock to pour the pad footings of the building.

fronting John Street and Nicholson Street between Albert and Glenlyon Road, all properties on Rickard Street and Gamble Street north of Glenlyon Road, all properties on the south side of Albert

Construction activity noise levels will be programmed and monitored, so as to conform to the Code of Practice for noise and E.P.A regulations

Council regulations shall be followed with regard to start times and finish times for noisy works (i.e. use of Power Tools, Plant, etc). Hours for noisy work are 7.00am – 6.00pm Monday to Friday, 7.00am – 1.00pm Saturday, noisy works by permit only on Sundays or Public Holidays

Plant engines shall be turned off whilst not in use

Waiting trucks shall not be left idling

Construction plant and machinery shall be fitted with noise suppressors where necessary

Works being conducted between 7.00am – 9.00am on Saturdays and will conform to the Code of Practice for Nose and E.P.A. Regulations

EROSION

These procedures describe how erosion will be minimized.

Objectives To ensure all erosion is minimized.

Targets No impact on surrounding environment from sediment runoff.

Issue Procedures

Construction Phase Stabilize the site, install and maintain erosion controls so that they remain effective during any pause in construction.

Keep vehicles to well-defined haul roads.

Keep haul roads off sloping terrain wherever practicable.

Design the slope of a cut to minimize the angle of incline.

Cultivate the cut surface to increase infiltration of rainfall and decrease the velocity of water across the slope during rain and therefore reduce erosion.

Vehicles to be washed down in a designated area, which will capture all wash down water. Vehicles are to be washed down on a daily basis to minimize dust and dirt being carried off site.

Page 12: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 12 of 24 East Brunswick Village: Stage 1

VEHICLE WASHDOWN FACILITY

To ensure minimal site debris is carried beyond the site boundary via vehicles travelling out of site, a concrete hardstand will be built inside the entrance into the site from Nicholson Street to allow vehicles to be washed down prior to exiting the site (as shown in the below image). A cattle grid will also be set up on the west side of the concrete hardstand for the assistance of this dirt/sediment removal. All trucks exiting the site will be assessed with the cleanliness of wheels and body of the truck and will be hosed down with a pressure washer gerny to ensure that there will be no dirt depositing on the footpaths/roads outside the site boundary.

The concrete agitator trucks which will be entering the site from Rickard Street once ground floor has been poured, will be set up on a concrete slab with falls to a catchment sump also and will be hosed down with a pressure washer gerny prior to leaving the site.

SITE CONTAMINATION

Any soil or surface rubble that is disposed of from the site in the future should be assessed to determine its contamination status and managed in accordance with EPA requirements. These procedures describe how soil contamination should be managed to protect environmental quality.

Objectives To minimize the disturbance of soil during construction works and therefore

minimize potential impacts from arising.

To comply with the EPA appointed Environmental Auditor’s requirements.

Targets Dust minimized during construction works.

Volume of spoil kept to a minimum.

Sediment runoff controlled.

Issue Procedures

Stockpiles Stockpiles to be removed / used as soon as possible or covered if they are non-working stockpiles in storage. Stockpiles undergoing hydrocarbon remediation are to be covered and emissions controlled.

Stockpiles are to be located away from drainage lines.

Keep topsoil separate from under burden when stockpiling soil.

NICHOLSON STREET

CATTLE GRID

CATCHMENT SUMP

CONCRETE HARDSTAND

Page 13: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 13 of 24 East Brunswick Village: Stage 1

Issue Procedures

Construct stockpiles with no slope greater than 2:1 (horizontal to vertical).

Circle stockpiles with silt fences (e.g. hay bales) or a drainage system that will collect and correctly dispose of contaminated water.

Hand water stockpiles to suppress dust. Dust observations to be undertaken on a daily basis.

Onsite Fill Material Excavations will be examined for signs of contamination within any fill (e.g. staining, rubble).

Imported soil or fill Any soil or fill imported to the site will be required to be tested by the supplier for contamination. No contaminated soil or fill will be imported to the site. Any imported material used onsite must be classified as suitable for commercial land use.

Asbestos in soil Asbestos to be handled packaged and removed in accordance with the Occupational Health and Safety (Asbestos) Regulations 1992, EPA Publication 364c The Transport and Disposal of waste asbestos October 2002, and the WorkSafe Australia Asbestos Code of Practice.

14.0 HAZARD AND RISK MANAGEMENT

The following Risk Management Plan outlines the following objectives with respect to risk control:

• Minimise potential risk involved in the project construction on site workers, nearby

property owners and the community at large. • Implement design changes and better construction methodologies to mitigate the

potential for risk causing injury and harm.

The following outlines the proposed measures to manage risk during the construction process:

Objectives Throughout the project our objective will be to prevent and control chemical spillage and comply with:

Dangerous Goods Act 1985

Australian Standard AS1940-1993 Storage and Handling of Flammable and Combustible Liquids

Storage & Handling of Dangerous Goods Regulations

Targets No spillage of stored fuels and chemicals.

Issue Procedures

General Wastes identified to be Regulated Wastes will be disposed and transported as per the Regulations.

Only store the required volumes of fuel and/or chemicals.

Where more than 1200 liters of chemicals is stored within a defined working area, provide bunds in accordance with EPA bunding requirements.

Chemical and oil containers are to be kept on spill control pallets.

Maintain the integrity of any storage tanks.

Label storage tanks appropriately in accordance with the Dangerous Goods Act and Australian Standards.

Fit automatic cut-offs on fuel dispensers.

Store an appropriately stocked spill kit on site, for use in the event of fuel or chemical spills.

Page 14: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 14 of 24 East Brunswick Village: Stage 1

Issue Procedures

Conduct a risk assessment to identify the potential risks to persons, property or the environment posed by the development and use of the site. The risk assessment is to include but not be limited to the storage of dangerous goods.

15.0 OCCUPATIONAL HEALTH AND SAFETY Objectives

Maintain a safe working environment for all staff and visitors.

Targets

No incidents reported.

Issue Procedures

General Wear / use protective equipment appropriate to tasks being undertaken.

Wear gloves when handling soil.

Wash hands before eating.

Conduct induction training in respect of OH&S for all staff.

Maintain records for all employees who have undergone OH&S induction training.

Provide sufficient OH&S equipment (e.g. First Aid Kits, emergency showers in appropriate locations).

Maintain records of any incidents that have occurred, including management actions taken to prevent the incident from occurring again.

Ensure there is sufficient signage regarding first aid locations.

Ensure all equipment is logged and regularly rested. Ensure all drivers of particular equipment have current tickets.

Prepare a site occupational health and safety plan for demolition and construction works.

HAZARD IDENTIFICATION AND RISK ASSESSMENT

Occupational Health and Safety Legislation requires the identification of potential workplace hazards, the assessment of the risk of the hazard and the development of controls to eliminate, or minimise the risk. To assist to identify potential hazards the work to be undertaken will be, where practicable, broken into activities reflecting the sequence of construction. For building and construction these activities are provided in a Safe Working Method Statement which is made up of a list of job procedures and other work related practices which inform the Principal Contractor how the Scope of Work will be carried out. For each of the work activities and associated job steps identified in a Safe Working Method Statement, potential hazards must be identified. These hazards will be identified using available resources including:

WorkCover Codes of Practice and other publications, e.g. safety alerts;

Hazard Profiles for specific trade groups;

Workplace experience; and

Consultation (e.g. Toolbox Talks) with workers experienced in the task.

For each potential workplace hazard identified a Risk Class will be determined. A Risk Class is a measure of how badly a person may be injured from a potential hazard. A Risk Class will be

Page 15: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 15 of 24 East Brunswick Village: Stage 1

calculated by reference to the following classifications. The attached Risk Management chart will determine the requirement for management of the risks identified.

Class 1: (High Risk): Does the hazard have the potential to kill, or permanently disable you? Class 2: (Medium Risk): Does the hazard have the potential to cause a serious

injury, or illness, which will temporarily disable you? Class 3: (Low Risk): Does the hazard have the potential to cause a minor injury

which would not disable you? Selection and Use:

The Risk Class will determine the level of Controls required, eliminating, or minimizing the potential hazard.

The higher the Risk Class the more extensive the controls to be provided

HAZARDOUS SUBSTANCES

Before any substance of a hazardous nature is brought on to site, a Material Safety Data Sheet (MSDS) is to be supplied to the Site Manager. MSDS can be obtained from the supplier or manufacture of the product. The Site Manager will maintain a register of Hazardous Substances to be used on the project.

INSPECTION AND MAINTENANCE PROCEDURES Objectives

No impact on the surrounding environment, staff or nearby residents Targets

Minimum “down time” for machinery undergoing maintenance.

Issue Procedures

General Keep a record of all inspections and maintenance.

TRAINING PROCEDURES

Objectives

Maintain a safe working environment for all staff and visitors. Targets

All staff receiving appropriate training.

Issue Procedures

General Ensure all staff receives induction training before working onsite.

Maintain records for all employees who have undergone training. Provide ongoing training for all staff.

EMERGENCY AND INCIDENT REPORTS

Objectives No impact on the surrounding environment, staff or nearby residents

Targets

All incidents will be managed and resolved as quickly as possible.

Page 16: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 16 of 24 East Brunswick Village: Stage 1

Issue Procedures

General All staff will report every emergency incident to the site manager as soon as practicable.

Ensure incident is resolved and recorded.

Direct staff to control the discharge and supervise the operation.

Stop any spill at the source if possible.

Report incidents to the EPA where offsite impacts to air or waters occur.

Report all incidents on site or ones that impact on neighboring properties.

Review incidents and response actions with a view to minimizing reoccurrence of incidents.

COMPLAINTS

Objectives All complaints will be managed directly by the Project Manager and resolved as

quickly and efficiently as possible.

Targets No complaints received.

All complaints resolved in accordance with the complaints procedure to the satisfaction of all parties involved.

Issue Procedures

General A letter drop will be conducted at the commencement of Hacer Group works onsite to all residential properties fronting John Street and Nicholson Street between Albert and Glenlyon Road, all properties on Rickard Street and Gamble Street north of Glenlyon Road, all properties on the south side of Albert Street between Nicholson and John Street. This letter will outline the timing of works to be completed by Hacer and list the Project Managers name and contact number to speak to regarding any complaints throughout the project.

Establish nature of complaint and record details of complaint in the incident register.

Coordinate complaint response and ensure problem is resolved.

Note details of complainant, time, date of incident, nature of problem, outcome of resulting investigation and solution to problem.

MONITORING

Objectives No impact on the surrounding environment due to construction activities.

Targets Air, water and soil pollution below accepted limits.

Noise levels below excessive noise guidelines.

Issue Procedures

General Routine inspections of the storm water system are to be conducted, in particular after a rainfall event.

Noise monitoring will be conducted via observations and the review of any complaints received.

Page 17: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 17 of 24 East Brunswick Village: Stage 1

Dust emissions will be monitored via personal observations and the review of any complaints received from surrounding residential areas or regulatory authorities.

Groundwater will be monitored in accordance with the ground water management plan detailed in the environmental audit

16.0 ANTICIPATED ROAD CLOSURES, ROAD OCCUPATION & FOOTPATH CLOSURES

Future works to install an additional tram stop on Nicholson St, East of the site, along with the proposed intersection into the site from Nicholson St have been loosely planned to be completed in the first week of January 2019. These works will require a full road closure, so by completing both works at the same time, it will dramatically reduce the impact on the public and traffic.

Partial road closures will also be required for the sewer, water & gas tap in connection into the main lines on Nicholson St. Further details and dates will be confirmed after the relevant services subcontractor has been appointed for the project.

All appropriate and statutory signage will be clearly displayed and all necessary permits and notifications to relevant authorities will be initiated prior to work commencing. Once approved, all documentation pertaining to this will be kept on site and filed for reference as required.

17.0 MEASURES TO PROTECT COUNCIL INFRASTRUCTURE AND SURROUNDING

PROPERTIES

In the case of any accidental damage, immediate temporary rectification will be implemented by way of ‘cold mix asphalt’. Permanent rectification will be carried out at the completion of works at East Brunswick Village.

As part of Hacer Group works, any kerbs, footpaths or nature strips that may be damaged during construction will be rectified as per the requirements of the Moreland City Council.

18.0 MONITORING AND INSPECTIONS PROGRAMME

Prior to any construction works Hacer Group will engage an independent contractor to conduct a dilapidation report of council and adjoining properties. This has been arranged to be completed at the end of April 2018, just prior to Hacer Group’s commencement date onsite.

All subcontractors prior to arrival on site, are to submit all appropriate documentation including Hazard Identification and Risk Assessment followed by a comprehensive list of control measures to eliminate (if possible) or at least minimise potential harm / damage caused from identified hazards.

The on-site health and safety representative monitors compliance of all identified and potential hazards on a daily basis.

The on-site health and safety committee carries out a comprehensive safety walk on a weekly basis identifying any risks or hazards to the workers, the public and the environment. Any issues found are documented onto safety walk minutes and immediate rectification works are implemented.

Page 18: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 18 of 24 East Brunswick Village: Stage 1

Upon their first arrival on site, workers shall be inducted into the site’s working procedures. Relevant information from this Construction Management plan shall be provided to them at this time.

Site Management shall monitor compliance of workers with all aspects of this Construction Management plan.

19.0 CONSTRUCTION METHODOLOGY

All construction works will take into consideration local planning regulations and be constructed as per BCA Codes and Practices, and as per Building Permit requirements.

Tower cranes will be utilised on site to facilitate the construction of the structure. They will be used to install precast concrete panels and columns, structural steel elements, roof sheeting and the loading and unloading of construction materials.

Traffic management personnel shall be present on site to coordinate and manage vehicular access into site and pedestrian traffic.

The majority of the works will be undertaken within the site boundaries and will have little impact on the surrounding area.

Page 19: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 19 of 24 East Brunswick Village: Stage 1

APPENDIX A: PRELIMINARY PROGRAMME OF WORKS The estimated construction work durations as per the preliminary programme are as follows:

Structure Works: 11 months

Fit-out Works: 12 months

Page 20: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

0 EAST BRUNSWICK VILLAGE - STAGE 1 Thu 14/12/17Wed 18/12/1 441 d1 KEY PROJECT MILESTONES Fri 15/12/17 Wed 18/12/19 440 d2 Engage Preferred Contractor Fri 15/12/17 Fri 15/12/17 0 d3 Construction Commence / Commence On Site Tue 1/05/18 Tue 1/05/18 0 d4 Colour Schemes For Building A Apartments Finalised Mon 16/07/18 Mon 16/07/18 0 d5 Colour Schemes For Buildings B & C Joinery 2 Pac Thu 2/08/18 Thu 2/08/18 0 d6 Colour Schemes For Buildings B & C Timber Floors / Tiles / Stone Bench Tops / Carpet Fri 21/09/18 Fri 21/09/18 0 d7 Colour Schemes For Buildings B & C Loose Timber Veneer Panels Finalised Mon 12/11/18 Mon 12/11/18 0 d8 Area Stripped Commence Coles Tue 26/02/19 Tue 26/02/19 0 d9 Building A Prototype Apartment Complete Ready For Inspection Wed 13/03/19 Wed 13/03/19 0 d

10 Building C Prototype Apartment Complete Ready For Inspection Thu 23/05/19 Thu 23/05/19 0 d11 Permanent Power Available Switch Room Mon 25/03/19 Mon 25/03/19 0 d12 Lot 1 Fit Out & Finishes Complete Thu 11/07/19 Thu 11/07/19 0 d13 External Works Complete Wed 11/09/19 Wed 11/09/19 0 d14 Lot 2 Fit Out & Finishes Complete Wed 9/10/19 Wed 9/10/19 0 d15 Certificate of Occupancy Thu 24/10/19 Thu 24/10/19 0 d16 SEPARABLE PORTIONS Wed 7/08/19 Wed 18/12/19 86 d17 Separable Portion 1 Base Build Work Complete Hand Over Coles (Net) Wed 7/08/19 Wed 7/08/19 0 d18 Separable Portion 1 Base Build Work Complete Hand Over Coles (Gross) Fri 20/09/19 Fri 20/09/19 0 d19 Separable Portion 2 Coles Open & Trading Wed 18/12/19 Wed 18/12/19 0 d20 Separable Portion 3 Practical Completion (Net) Thu 31/10/19 Thu 31/10/19 0 d21 Separable Portion 3 Practical Completion (Gross) Wed 18/12/19 Wed 18/12/19 0 d22 OFFSITE WORKS Thu 14/12/17 Fri 26/04/19 408 d23 TENDER PERIOD Thu 14/12/17 Sat 6/01/18 18 d24 Engage Preferred Contractor Fri 15/12/17 Fri 15/12/17 0 d25 Finalise Building Contract Thu 14/12/17 Sat 6/01/18 18 d26 DESIGN Mon 8/01/18 Tue 20/03/18 60 d27 Value Management/Cost Saving Review Process Mon 8/01/18 Mon 29/01/18 18 d28 Coles Final Design For Coles Review Tue 30/01/18 Mon 19/02/18 18 d29 Final Coles Documentation Review and Approval (By Coles) Tue 20/02/18 Tue 20/03/18 24 d30 Final Design and Documentation Tue 30/01/18 Tue 20/03/18 42 d31 CONSTRUCTION DOCUMENTATION Mon 29/01/18 Fri 18/05/18 75 d32 IFT DOCUMENTS Mon 29/01/18 Tue 20/03/18 35 d33 Substructure, In-ground Services up to GL slab Mon 29/01/18 Mon 29/01/18 0 d34 Building Services including VT Mon 19/02/18 Mon 19/02/18 0 d35 Above Ground Structure (Insitu Concrete, PT Slabs, Precast, Structural Steel) Mon 5/03/18 Mon 5/03/18 0 d36 Architectural Finishes (Internal & External) and External Works/Landscaping Tue 20/03/18 Tue 20/03/18 0 d37 CLIENT SIGN OFF OF IFT DOCUMENTATION Mon 5/02/18 Thu 5/04/18 40 d38 Substructure, In-ground Services up to GL slab Mon 5/02/18 Mon 5/02/18 0 d39 Building Services including VT Mon 5/03/18 Mon 5/03/18 0 d40 Above Ground Structure (Insitu Concrete, PT Slabs, Precast, Structural Steel) Tue 20/03/18 Tue 20/03/18 0 d41 Architectural Finishes (Internal & External) and External Works/Landscaping Thu 5/04/18 Thu 5/04/18 0 d42 IFC DOCUMENTS Mon 12/02/18 Fri 4/05/18 55 d43 Substructure, In-ground Services up to GL slab Mon 12/02/18 Mon 12/02/18 0 d44 Building Services including VT Tue 20/03/18 Tue 20/03/18 0 d45 Above Ground Structure (Insitu Concrete, PT Slabs, Precast, Structural Steel) Thu 19/04/18 Thu 19/04/18 0 d46 Architectural Finishes (Internal & External) and External Works/Landscaping Fri 4/05/18 Fri 4/05/18 0 d47 CLIENT SIGN OFF OF IFC DOCUMENTATION Mon 19/02/18 Fri 18/05/18 60 d48 Substructure, In-ground Services up to GL slab Mon 19/02/18 Mon 19/02/18 0 d49 Building Services including VT Tue 27/03/18 Tue 27/03/18 0 d50 Above Ground Structure (Insitu Concrete, PT Slabs, Precast, Structural Steel) Fri 4/05/18 Fri 4/05/18 0 d51 Architectural Finishes (Internal & External) and External Works/Landscaping Fri 18/05/18 Fri 18/05/18 0 d52 WORKS PROTECTION NOTICES Thu 1/02/18 Fri 23/02/18 17 d53 Prepare & Issue Works Protection Notices Thu 1/02/18 Wed 7/02/18 5 d54 Works Protection Notice Response Period (2 weeks) Thu 8/02/18 Fri 23/02/18 12 d55 Works Protection Notices Complete Fri 23/02/18 Fri 23/02/18 0 d56 CONSTRUCTION MANAGEMENT PLANS Thu 1/02/18 Thu 29/03/18 40 d57 Prepare Construction Management Plans Thu 1/02/18 Wed 7/02/18 5 d58 Issue For Approval Wed 7/02/18 Wed 7/02/18 0 d59 Construction Management Plans Approved & Signed Off Thu 8/02/18 Thu 29/03/18 35 d60 BUILDING PERMITS Tue 30/01/18 Mon 1/10/18 169 d61 LOT 2 Tue 30/01/18 Mon 20/08/18 127 d62 Substructure - Prepare & Lodge Application Tue 30/01/18 Wed 14/02/18 12 d63 Review Period Thu 15/02/18 Thu 22/03/18 25 d64 Substructure Building Permit Obtained Wed 4/04/18 Wed 4/04/18 0 d65 Super Structure - Prepare & Lodge Application Fri 20/04/18 Fri 4/05/18 10 d66 Review Period Mon 7/05/18 Mon 18/06/18 30 d67 Super Structure Building Permit Obtained Mon 18/06/18 Mon 18/06/18 0 d68 Remaining Works - Prepare & Lodge Application Tue 19/06/18 Mon 9/07/18 15 d69 Review Period Tue 10/07/18 Mon 20/08/18 30 d70 Remaining Works Building Permit Obtained Mon 20/08/18 Mon 20/08/18 0 d71 LOT 1 Thu 15/02/18 Mon 1/10/18 142 d72 Substructure - Prepare & Lodge Application Thu 15/02/18 Fri 2/03/18 12 d73 Review Period Mon 5/03/18 Wed 11/04/18 25 d74 Substructure Building Permit Obtained Wed 11/04/18 Wed 11/04/18 0 d75 Super Structure - Prepare & Lodge Application Fri 4/05/18 Thu 17/05/18 10 d76 Review Period Fri 18/05/18 Fri 29/06/18 30 d77 Super Structure Building Permit Obtained Fri 29/06/18 Fri 29/06/18 0 d78 Remaining Works - Prepare & Lodge Application Mon 30/07/18 Fri 17/08/18 15 d79 Review Period Mon 20/08/18 Mon 1/10/18 30 d80 Remaining Works Building Permit Obtained Mon 1/10/18 Mon 1/10/18 0 d

Y PROJECT MILESTONES15/12/2017

1/05/201816/07/2018

2/08/201821/09/2018

12/11/201826/02/2019

13/03/201923/05/2019

25/03/201911/07/2019

11/09/20199/10/2019

24/10/2019SEPARABLE PORTIONS

7/08/201920/09/2019

18/12/201931/10/2019

18/12/2019OFFSITE WORKSTENDER PERIOD

15/12/2017Finalise Building Contract

DESIGNValue Management/Cost Saving Review Process

Coles Final Design For Coles ReviewFinal Coles Documentation Review and Approval (By Coles)Final Design and Documentation

ONSTRUCTION DOCUMENTATIONIFT DOCUMENTS

29/01/201819/02/2018

5/03/201820/03/2018

SIGN OFF OF IFT DOCUMENTATION5/02/2018

5/03/201820/03/2018

5/04/2018IFC DOCUMENTS

12/02/201820/03/2018

19/04/20184/05/2018

T SIGN OFF OF IFC DOCUMENTATION19/02/2018

27/03/20184/05/2018

18/05/2018WORKS PROTECTION NOTICES

Prepare & Issue Works Protection NoticesWorks Protection Notice Response Period (2 weeks)23/02/2018

STRUCTION MANAGEMENT PLANSPrepare Construction Management Plans7/02/2018

Construction Management Plans Approved & Signed OffBUILDING PERMITS

LOT 2Substructure - Prepare & Lodge Application

Review Period4/04/2018

Super Structure - Prepare & Lodge ApplicationReview Period18/06/2018

Remaining Works - Prepare & Lodge ApplicationReview Period20/08/2018

LOT 1Substructure - Prepare & Lodge Application

Review Period11/04/2018

Super Structure - Prepare & Lodge ApplicationReview Period29/06/2018

Remaining Works - Prepare & Lodge ApplicationReview Period1/10/2018

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 1 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 21: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

81 SITE SPECIFIC PLANS Tue 20/02/18 Tue 1/05/18 47 d82 Prepare Hoarding & Site Traffic Management Plans Tue 20/02/18 Thu 1/03/18 8 d83 Prepare Site OHS Management & Emergency Plans Mon 26/02/18 Wed 7/03/18 8 d84 Prepare Site Environmental Management Plans Fri 2/03/18 Tue 13/03/18 7 d85 Review & Sign Off Wed 14/03/18 Tue 27/03/18 10 d86 Remaining Permits & Approvals Obtained Thu 29/03/18 Thu 29/03/18 0 d87 Builder Mobilisation Tue 27/03/18 Tue 1/05/18 21 d88 KEY SUBCONTRACT LETTING Tue 6/03/18 Fri 26/04/19 279 d89 LOT 1 (BUILDING A) Tue 6/03/18 Wed 19/12/18 181 d90 Lifts - Tender, Evaluate & Award Tue 6/03/18 Thu 5/04/18 20 d91 Lifts - Shop Drawings / Review Period / Approvals Fri 6/04/18 Fri 1/06/18 40 d92 Lifts - Lead Time Mon 4/06/18 Wed 7/11/18 110 d93 Main Services - Tender, Evaluate & Award Tue 6/03/18 Thu 12/04/18 25 d94 Main Services - Shop Drawings / Review Period / Approvals Fri 13/04/18 Fri 8/06/18 40 d95 Main Services - Lead Time Tue 12/06/18 Tue 16/10/18 90 d96 Façade, Windows & Cladding - Tender, Evaluate & Award Fri 6/04/18 Fri 4/05/18 20 d97 Façade, Windows & Cladding - Shop Drawings / Review Period Mon 7/05/18 Mon 2/07/18 40 d98 Façade, Windows & Cladding - Approvals Tue 3/07/18 Mon 13/08/18 30 d99 Façade, Windows & Cladding - Manufacture & Lead-In Time Tue 14/08/18 Wed 19/12/18 90 d100 Façade First Required Onsite Tue 11/12/18 Tue 11/12/18 0 d101 Floor Finishes - Tender, Evaluate & Award Fri 20/04/18 Fri 18/05/18 20 d102 Floor Finishes - Obtain Samples Mon 21/05/18 Mon 2/07/18 30 d103 Floor Finishes - Review & Approval Period Tue 3/07/18 Mon 16/07/18 10 d104 Floor Finishes (Timber/Tiles/Carpet) - Approved Mon 16/07/18 Mon 16/07/18 0 d105 Floor Finishes - Procurement Tue 17/07/18 Wed 7/11/18 80 d106 Floor Finishes - Delivery Thu 8/11/18 Wed 19/12/18 30 d107 Joinery - Issue Of Achitectural IFC Drawings Mon 23/04/18 Mon 23/04/18 0 d108 Joinery - Tender, Evaluate & Award Tue 24/04/18 Tue 22/05/18 20 d109 Joinery - Finalise Drawings, Establish Shop Drawings Wed 23/05/18 Wed 1/08/18 50 d110 Joinery - Obtain Samples Build Prototypes Wed 23/05/18 Mon 2/07/18 28 d111 Joinery - Review & Approval, Colour Scheme Sign Off Tue 3/07/18 Mon 16/07/18 10 d112 Colour Schemes For Apartments Finalised Mon 16/07/18 Mon 16/07/18 0 d113 Colour Schemes - Achitectural IFC Drawings Tue 24/07/18 Tue 24/07/18 0 d114 Joinery - Manufacture Period Thu 2/08/18 Thu 11/10/18 50 d115 Joinery - Delivery Fri 12/10/18 Fri 7/12/18 40 d116 LOT 2 (BUILDINGS B & C) Tue 6/03/18 Fri 26/04/19 279 d117 Lifts - Tender, Evaluate & Award Tue 6/03/18 Thu 5/04/18 20 d118 Lifts - Shop Drawings / Review Period / Approvals Fri 6/04/18 Fri 1/06/18 40 d119 Lifts - Lead Time Mon 4/06/18 Wed 7/11/18 110 d120 Travelators - Tender, Evaluate & Award Tue 6/03/18 Thu 5/04/18 20 d121 Travelators - Shop Drawings / Review Period / Approvals Fri 6/04/18 Fri 1/06/18 40 d122 Travelators - Lead Time Mon 4/06/18 Wed 7/11/18 110 d123 Main Services - Tender, Evaluate & Award Tue 6/03/18 Thu 12/04/18 25 d124 Main Services - Shop Drawings / Review Period / Approvals Fri 13/04/18 Fri 8/06/18 40 d125 Main Services - Lead Time Tue 12/06/18 Tue 16/10/18 90 d126 Façade, Windows & Cladding - Tender, Evaluate & Award Tue 19/06/18 Mon 16/07/18 20 d127 Façade, Windows & Cladding - Shop Drawings / Review Period Tue 17/07/18 Mon 10/09/18 40 d128 Façade, Windows & Cladding - Approvals Tue 11/09/18 Tue 23/10/18 30 d129 Façade, Windows & Cladding - Manufacture & Lead-In Time Wed 24/10/18 Wed 13/03/19 90 d130 Façade First Required Onsite Wed 27/02/19 Wed 27/02/19 0 d131 Floor Finishes - Tender, Evaluate & Award Thu 10/05/18 Wed 6/06/18 20 d132 Floor Finishes - Obtain Samples Thu 7/06/18 Thu 26/07/18 35 d133 Floor Finishes - Review & Approval Period Fri 27/07/18 Thu 20/09/18 40 d134 Floor Colour Scheme Finishes - Approved Thu 20/09/18 Thu 20/09/18 0 d135 Floor Finishes - Procurement Fri 21/09/18 Thu 24/01/19 80 d136 Floor Finishes - Delivery Thu 24/01/19 Thu 24/01/19 0 d137 Joinery - Issue Of Achitectural IFC Drawings Mon 23/04/18 Mon 23/04/18 0 d138 Joinery - Tender, Evaluate & Award Thu 10/05/18 Wed 6/06/18 20 d139 Joinery - Finalise Drawings, Establish Shop Drawings Thu 7/06/18 Thu 9/08/18 40 d140 Joinery - Obtain Samples Build Prototypes Thu 7/06/18 Thu 19/07/18 30 d141 Joinery - Review & Approval, Colour Scheme Fri 20/07/18 Thu 2/08/18 10 d142 Colour Schemes For 2 pac Thu 2/08/18 Thu 2/08/18 0 d143 Colour Scheme For 2 Pac - Issue Of Achitectural IFC Drawings Fri 10/08/18 Fri 10/08/18 0 d144 Joinery - Manufacture Period Mon 13/08/18 Mon 10/12/18 75 d145 Joinery - Delivery Tue 11/12/18 Fri 8/02/19 30 d146 Loose Timber Veneer Panels - Tender, Evaluate & Award Fri 17/08/18 Thu 13/09/18 20 d147 Loose Timber Veneer Panels - Obtain Prototye Samples Fri 14/09/18 Fri 26/10/18 30 d148 Loose Timber Veneer Panels - Review & Approval of Prototye, Colour Scheme Sign Off Mon 29/10/18 Mon 12/11/18 10 d149 Colour Schemes For Loose Timber Vaneer Panels Finalised Mon 12/11/18 Mon 12/11/18 0 d150 Loose Timber Vaneer Panels - Issue Of Achitectural IFC Drawings Tue 20/11/18 Tue 20/11/18 0 d151 Loose Timber Veneer Panels - Finalise Drawings, Establish Shop Drawings Wed 21/11/18 Fri 11/01/19 30 d152 Loose Timber Veneer Panels - Manufacture Period Mon 14/01/19 Tue 12/03/19 40 d153 Loose Timber Veneer Panels - Delivery Wed 13/03/19 Fri 26/04/19 30 d154 MATERIALS HANDLING Mon 4/06/18 Mon 15/07/19 243 d155 TOWER CRANES Mon 4/06/18 Tue 2/07/19 235 d156 CRANE 1 (EAST - LOT 1) Mon 4/06/18 Thu 21/03/19 174 d157 FRP Crane Base & Cure Period Mon 4/06/18 Sun 10/06/18 7 d158 Erect Tower Crane (Weekend Work) Wed 13/06/18 Thu 14/06/18 2 d159 Remove Tower Crane (Weekend Work) Wed 20/03/19 Thu 21/03/19 2 d160 CRANE 2 (WEST - LOT 2) Sat 23/06/18 Tue 2/07/19 222 d161 FRP Crane Base & Cure Period Sat 23/06/18 Fri 29/06/18 7 d162 Erect Tower Crane (Weekend Work) Mon 2/07/18 Tue 3/07/18 2 d

SITE SPECIFIC PLANSPrepare Hoarding & Site Traffic Management Plans

Prepare Site OHS Management & Emergency PlansPrepare Site Environmental Management Plans

Review & Sign Off29/03/2018

Builder MobilisationKEY SUBCONTRACT LETTING

LOT 1 (BUILDING A)Lifts - Tender, Evaluate & Award

Lifts - Shop Drawings / Review Period / ApprovalsLifts - Lead Time

Main Services - Tender, Evaluate & AwardMain Services - Shop Drawings / Review Period / Approvals

Main Services - Lead TimeFaçade, Windows & Cladding - Tender, Evaluate & Award

Façade, Windows & Cladding - Shop Drawings / Review PeriodFaçade, Windows & Cladding - Approvals

Façade, Windows & Cladding - Manufacture & Lead-In Time11/12/2018

Floor Finishes - Tender, Evaluate & AwardFloor Finishes - Obtain Samples

Floor Finishes - Review & Approval Period16/07/2018

Floor Finishes - Procurement Floor Finishes - Delivery

23/04/2018Joinery - Tender, Evaluate & Award

Joinery - Finalise Drawings, Establish Shop DrawingsJoinery - Obtain Samples Build Prototypes

Joinery - Review & Approval, Colour Scheme Sign Off16/07/2018

24/07/2018Joinery - Manufacture Period

Joinery - DeliveryLOT 2 (BUILDINGS B & C)

Lifts - Tender, Evaluate & AwardLifts - Shop Drawings / Review Period / Approvals

Lifts - Lead TimeTravelators - Tender, Evaluate & Award

Travelators - Shop Drawings / Review Period / ApprovalsTravelators - Lead Time

Main Services - Tender, Evaluate & AwardMain Services - Shop Drawings / Review Period / Approvals

Main Services - Lead TimeFaçade, Windows & Cladding - Tender, Evaluate & Award

Façade, Windows & Cladding - Shop Drawings / Review PeriodFaçade, Windows & Cladding - Approvals

Façade, Windows & Cladding - Manufacture & Lead-In Time27/02/2019

Floor Finishes - Tender, Evaluate & AwardFloor Finishes - Obtain Samples

Floor Finishes - Review & Approval Period20/09/2018

Floor Finishes - Procurement 24/01/2019

23/04/2018Joinery - Tender, Evaluate & Award

Joinery - Finalise Drawings, Establish Shop DrawingsJoinery - Obtain Samples Build Prototypes

Joinery - Review & Approval, Colour Scheme2/08/2018

10/08/2018Joinery - Manufacture Period

Joinery - DeliveryLoose Timber Veneer Panels - Tender, Evaluate & Award

Loose Timber Veneer Panels - Obtain Prototye Samples Loose Timber Veneer Panels - Review & Approval of Prototye, Colour Scheme Sign Off12/11/2018

20/11/2018Loose Timber Veneer Panels - Finalise Drawings, Establish Shop Drawings

Loose Timber Veneer Panels - Manufacture PeriodLoose Timber Veneer Panels - Delivery

MATERIALS HANDLINGTOWER CRANES

CRANE 1 (EAST - LOT 1)FRP Crane Base & Cure PeriodErect Tower Crane (Weekend Work)

Remove Tower Crane (Weekend Work)CRANE 2 (WEST - LOT 2)

FRP Crane Base & Cure PeriodErect Tower Crane (Weekend Work)

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 2 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 22: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

163 Remove Tower Crane (Weekend Work) Mon 1/07/19 Tue 2/07/19 2 d164 MAN / MATERIALS HOISTS Wed 31/10/18 Mon 15/07/19 147 d165 LOT 1 Wed 31/10/18 Tue 26/03/19 81 d166 Man / Materials Hoists - Level 3 Slab Poured Wed 31/10/18 Wed 31/10/18 0 d167 Man / Materials Hoists - Erect Hoist Thu 1/11/18 Fri 2/11/18 2 d168 Man / Materials Hoists - Builder's Lift Available Tue 26/03/19 Tue 26/03/19 0 d169 LOT 2 Tue 11/12/18 Mon 15/07/19 123 d170 Man / Materials Hoists - Level 3 Slab Poured Tue 11/12/18 Tue 11/12/18 0 d171 Man / Materials Hoists - Erect Hoist Wed 12/12/18 Thu 13/12/18 2 d172 Man / Materials Hoists - Builder's Lift Available Mon 15/07/19 Mon 15/07/19 0 d173 ONSITE WORKS Tue 1/05/18 Wed 18/12/19 365 d174 WORK ZONE 1 A Tue 1/05/18 Wed 4/09/19 298 d175 SITE ESTABLISHMENT Tue 1/05/18 Wed 30/05/18 19 d176 Construction Commence / Commence On Site Tue 1/05/18 Tue 1/05/18 0 d177 Confirm Location of Terminated Services Wed 2/05/18 Wed 2/05/18 1 d178 Adjust Hoarding & Barriers For Construction Wed 2/05/18 Thu 3/05/18 2 d179 Site Access Point, Traffic Management Fri 4/05/18 Mon 7/05/18 2 d180 Install Environmental Controls Tue 8/05/18 Wed 9/05/18 2 d181 Install Pedestrian Protection Fri 4/05/18 Tue 15/05/18 7 d182 Establish Site Amenities Tue 8/05/18 Wed 30/05/18 15 d183 SUB STRUCTURE Thu 10/05/18 Thu 2/08/18 54 d184 Final Trim & Detail To Required Levels Thu 10/05/18 Thu 24/05/18 10 d185 Detail Excavate FRP Pad Footings Mon 21/05/18 Tue 17/07/18 37 d186 Detail Excavate FRP Strip Footings Fri 25/05/18 Fri 22/06/18 18 d187 Detail FRP Raft Slabs Fri 8/06/18 Wed 4/07/18 16 d188 FRP Overruns Strip & Cure Mon 18/06/18 Tue 17/07/18 20 d189 Under Slab Service Fri 8/06/18 Thu 2/08/18 35 d190 SLABS ON GROUND (LOWER BASEMENT) Tue 26/06/18 Tue 28/08/18 42 d191 AREA 1 (SOUTH GRIDS 2-16 to 2-5) Tue 26/06/18 Tue 28/08/18 42 d192 LOT 2 Tue 26/06/18 Mon 13/08/18 32 d193 Prepare Sub Base FRP Slab On Ground (Pour 1) Tue 26/06/18 Mon 2/07/18 5 d194 Prepare Sub Base FRP Slab On Ground (Pour 2) Tue 3/07/18 Tue 10/07/18 5 d195 Prepare Sub Base FRP Slab On Ground (Pour 3) Wed 11/07/18 Tue 17/07/18 5 d196 Prepare Sub Base FRP Slab On Ground (Pour 4) Fri 20/07/18 Fri 27/07/18 5 d197 Prepare Sub Base FRP Slab On Ground (Pour 5) Mon 30/07/18 Fri 3/08/18 5 d198 Prepare Sub Base FRP Slab On Ground (Pour 6) Tue 7/08/18 Mon 13/08/18 5 d199 LOT 1 Fri 13/07/18 Tue 28/08/18 30 d200 Prepare Sub Base FRP Slab On Ground (Pour 7) Fri 13/07/18 Thu 19/07/18 5 d201 Prepare Sub Base FRP Slab On Ground (Pour 8) Fri 20/07/18 Fri 27/07/18 5 d202 Prepare Sub Base FRP Slab On Ground (Pour 9) Mon 30/07/18 Fri 3/08/18 5 d203 Prepare Sub Base FRP Slab On Ground (Pour 10) Tue 7/08/18 Mon 13/08/18 5 d204 Prepare Sub Base FRP Slab On Ground (Pour 11) Tue 14/08/18 Tue 21/08/18 5 d205 Prepare Sub Base FRP Slab On Ground (Pour 12) Wed 22/08/18 Tue 28/08/18 5 d206 STRUCTURE Mon 30/07/18 Mon 18/03/19 136 d207 LOT 2 Mon 30/07/18 Mon 18/03/19 136 d208 UPPER BASEMENT (GRIDS 1-A to 1-K, 2-16 to 1-6) Mon 30/07/18 Thu 20/09/18 35 d209 Verticals FRP Suspended Slab (Pour 1) Mon 30/07/18 Wed 8/08/18 7 d210 Verticals FRP Suspended Slab (Pour 2) Fri 3/08/18 Tue 14/08/18 7 d211 Verticals FRP Suspended Slab (Pour 3) Fri 10/08/18 Tue 21/08/18 7 d212 Verticals FRP Suspended Slab (Pour 4) Thu 16/08/18 Mon 27/08/18 7 d213 Verticals FRP Suspended Slab (Pour 5) Thu 23/08/18 Fri 31/08/18 7 d214 Verticals FRP Suspended Slab (Pour 6) Wed 29/08/18 Fri 7/09/18 7 d215 Verticals FRP Suspended Slab (Pour 7) Wed 5/09/18 Thu 13/09/18 7 d216 Verticals FRP Suspended Slab (Pour 8) Tue 11/09/18 Thu 20/09/18 7 d217 MEZZANINES Tue 4/09/18 Tue 18/09/18 10 d218 Verticals FRP Suspended Slabs Tue 4/09/18 Tue 18/09/18 10 d219 GROUND LEVEL (GRIDS 1-A to 1-K, 2-16 to 1-6) Thu 20/09/18 Wed 28/11/18 43 d220 Verticals FRP Suspended Slab (Pour 1) Thu 20/09/18 Wed 3/10/18 8 d221 Verticals FRP Suspended Slab (Pour 2) Thu 27/09/18 Wed 10/10/18 8 d222 Verticals FRP Suspended Slab (Pour 3) Mon 8/10/18 Thu 18/10/18 8 d223 Verticals FRP Suspended Slab (Pour 4) Tue 16/10/18 Thu 25/10/18 8 d224 Verticals FRP Suspended Slab (Pour 5) Tue 23/10/18 Thu 1/11/18 8 d225 Verticals FRP Suspended Slab (Pour 6) Tue 30/10/18 Tue 13/11/18 8 d226 Verticals FRP Suspended Slab (Pour 7) Fri 9/11/18 Wed 21/11/18 8 d227 Verticals FRP Suspended Slab (Pour 8) Fri 16/11/18 Wed 28/11/18 8 d228 LEVEL 1 EXTRA HEIGHT & TRANSFER Thu 11/10/18 Mon 14/01/19 50 d229 Verticals FRP Suspended Slab (Pour 1) Thu 11/10/18 Mon 29/10/18 12 d230 Verticals FRP Suspended Slab (Pour 2) Wed 24/10/18 Tue 13/11/18 12 d231 Verticals FRP Suspended Slab (Pour 3) Thu 8/11/18 Mon 26/11/18 12 d232 Verticals FRP Suspended Slab (Pour 4) Thu 29/11/18 Mon 17/12/18 12 d233 Verticals FRP Suspended Slab (Pour 5) Wed 12/12/18 Mon 14/01/19 12 d234 EAST TOWER Wed 14/11/18 Fri 25/01/19 39 d235 LEVEL 2 Wed 14/11/18 Thu 29/11/18 11 d236 Verticals FRP Suspended Slab (Pour 1) Wed 14/11/18 Fri 23/11/18 7 d237 Verticals FRP Suspended Slab (Pour 2) Wed 21/11/18 Thu 29/11/18 7 d238 LEVEL 3 Mon 26/11/18 Tue 11/12/18 11 d239 Verticals FRP Suspended Slab (Pour 1) Mon 26/11/18 Wed 5/12/18 7 d240 Verticals FRP Suspended Slab (Pour 2) Fri 30/11/18 Tue 11/12/18 7 d241 LEVEL 4 Thu 6/12/18 Thu 20/12/18 11 d242 Verticals FRP Suspended Slab (Pour 1) Thu 6/12/18 Fri 14/12/18 7 d

Remove Tower Crane (Weekend Work)MAN / MATERIALS HOISTS

LOT 131/10/2018Man / Materials Hoists - Erect Hoist

26/03/2019LOT 2

11/12/2018Man / Materials Hoists - Erect Hoist

15/07/2019ONSITE WORKSWORK ZONE 1 A

SITE ESTABLISHMENT1/05/2018Confirm Location of Terminated ServicesAdjust Hoarding & Barriers For ConstructionSite Access Point, Traffic ManagementInstall Environmental Controls

Install Pedestrian ProtectionEstablish Site Amenities

SUB STRUCTUREFinal Trim & Detail To Required Levels

Detail Excavate FRP Pad Footings Detail Excavate FRP Strip Footings

Detail FRP Raft SlabsFRP Overruns Strip & Cure

Under Slab ServiceSLABS ON GROUND (LOWER BASEMENT)

AREA 1 (SOUTH GRIDS 2-16 to 2-5)LOT 2

Prepare Sub Base FRP Slab On Ground (Pour 1)Prepare Sub Base FRP Slab On Ground (Pour 2)

Prepare Sub Base FRP Slab On Ground (Pour 3)Prepare Sub Base FRP Slab On Ground (Pour 4)

Prepare Sub Base FRP Slab On Ground (Pour 5)Prepare Sub Base FRP Slab On Ground (Pour 6)

LOT 1Prepare Sub Base FRP Slab On Ground (Pour 7)

Prepare Sub Base FRP Slab On Ground (Pour 8)Prepare Sub Base FRP Slab On Ground (Pour 9)

Prepare Sub Base FRP Slab On Ground (Pour 10)Prepare Sub Base FRP Slab On Ground (Pour 11)

Prepare Sub Base FRP Slab On Ground (Pour 12)STRUCTURE

LOT 2UPPER BASEMENT (GRIDS 1-A to 1-K, 2-16 to 1-6)

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

Verticals FRP Suspended Slab (Pour 3)Verticals FRP Suspended Slab (Pour 4)Verticals FRP Suspended Slab (Pour 5)

Verticals FRP Suspended Slab (Pour 6)Verticals FRP Suspended Slab (Pour 7)

Verticals FRP Suspended Slab (Pour 8)MEZZANINES

Verticals FRP Suspended SlabsGROUND LEVEL (GRIDS 1-A to 1-K, 2-16 to 1-6)

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

Verticals FRP Suspended Slab (Pour 3)Verticals FRP Suspended Slab (Pour 4)

Verticals FRP Suspended Slab (Pour 5)Verticals FRP Suspended Slab (Pour 6)

Verticals FRP Suspended Slab (Pour 7)Verticals FRP Suspended Slab (Pour 8)

LEVEL 1 EXTRA HEIGHT & TRANSFERVerticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)Verticals FRP Suspended Slab (Pour 3)

Verticals FRP Suspended Slab (Pour 4)Verticals FRP Suspended Slab (Pour 5)

EAST TOWERLEVEL 2

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

LEVEL 3Verticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)LEVEL 4

Verticals FRP Suspended Slab (Pour 1)

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 3 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 23: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

243 Verticals FRP Suspended Slab (Pour 2) Wed 12/12/18 Thu 20/12/18 7 d244 LEVEL 5 Mon 17/12/18 Wed 16/01/19 11 d245 Verticals FRP Suspended Slab (Pour 1) Mon 17/12/18 Thu 10/01/19 7 d246 Verticals FRP Suspended Slab (Pour 2) Fri 21/12/18 Wed 16/01/19 7 d247 ROOF LEVEL Fri 11/01/19 Fri 25/01/19 11 d248 Verticals FRP Suspended Slab (Pour 1) Fri 11/01/19 Mon 21/01/19 7 d249 Verticals FRP Suspended Slab (Pour 2) Thu 17/01/19 Fri 25/01/19 7 d250 WEST TOWER Tue 15/01/19 Mon 18/03/19 39 d251 LEVEL 2 Tue 15/01/19 Thu 31/01/19 11 d252 Verticals FRP Suspended Slab (Pour 1) Tue 15/01/19 Wed 23/01/19 7 d253 Verticals FRP Suspended Slab (Pour 2) Mon 21/01/19 Thu 31/01/19 7 d254 LEVEL 3 Thu 24/01/19 Tue 12/02/19 11 d255 Verticals FRP Suspended Slab (Pour 1) Thu 24/01/19 Tue 5/02/19 7 d256 Verticals FRP Suspended Slab (Pour 2) Fri 1/02/19 Tue 12/02/19 7 d257 LEVEL 4 Wed 6/02/19 Thu 21/02/19 11 d258 Verticals FRP Suspended Slab (Pour 1) Wed 6/02/19 Fri 15/02/19 7 d259 Verticals FRP Suspended Slab (Pour 2) Wed 13/02/19 Thu 21/02/19 7 d260 LEVEL 5 Mon 18/02/19 Tue 5/03/19 11 d261 Verticals FRP Suspended Slab (Pour 1) Mon 18/02/19 Wed 27/02/19 7 d262 Verticals FRP Suspended Slab (Pour 2) Fri 22/02/19 Tue 5/03/19 7 d263 ROOF LEVEL Thu 28/02/19 Mon 18/03/19 11 d264 Verticals FRP Suspended Slab (Pour 1) Thu 28/02/19 Fri 8/03/19 7 d265 Verticals FRP Suspended Slab (Pour 2) Wed 6/03/19 Mon 18/03/19 7 d266 LOT 1 Tue 14/08/18 Mon 26/11/18 65 d267 UPPER BASEMENT (GRIDS 1-K to 1-Q, 1-12.2 to 1-9) Tue 14/08/18 Tue 11/09/18 19 d268 Verticals FRP Suspended Slab (Pour 1) Tue 14/08/18 Thu 23/08/18 7 d269 Verticals FRP Suspended Slab (Pour 2) Tue 21/08/18 Wed 29/08/18 7 d270 Verticals FRP Suspended Slab (Pour 3) Mon 27/08/18 Wed 5/09/18 7 d271 Verticals FRP Suspended Slab (Pour 4) Fri 31/08/18 Tue 11/09/18 7 d272 GROUND LEVEL (GRIDS 1-K to 1-Q, 1-12.2 to 1-9) Fri 24/08/18 Thu 27/09/18 23 d273 Verticals FRP Suspended Slab (Pour 1) Fri 24/08/18 Wed 5/09/18 8 d274 Verticals FRP Suspended Slab (Pour 2) Fri 31/08/18 Wed 12/09/18 8 d275 Verticals FRP Suspended Slab (Pour 3) Mon 10/09/18 Thu 20/09/18 8 d276 Verticals FRP Suspended Slab (Pour 4) Tue 18/09/18 Thu 27/09/18 8 d277 LEVEL 1 EXTRA HEIGHT Thu 13/09/18 Wed 10/10/18 17 d278 Verticals FRP Suspended Slab (Pour 1) Thu 13/09/18 Mon 24/09/18 7 d279 Verticals FRP Suspended Slab (Pour 2) Thu 20/09/18 Tue 2/10/18 7 d280 Verticals FRP Suspended Slab (Pour 3) Tue 2/10/18 Wed 10/10/18 7 d281 LEVEL 2 Wed 3/10/18 Mon 22/10/18 13 d282 Verticals FRP Suspended Slab (Pour 1) Wed 3/10/18 Thu 11/10/18 7 d283 Verticals FRP Suspended Slab (Pour 2) Thu 11/10/18 Mon 22/10/18 7 d284 LEVEL 3 Fri 12/10/18 Wed 31/10/18 13 d285 Verticals FRP Suspended Slab (Pour 1) Fri 12/10/18 Tue 23/10/18 7 d286 Verticals FRP Suspended Slab (Pour 2) Tue 23/10/18 Wed 31/10/18 7 d287 LEVEL 4 Wed 24/10/18 Wed 14/11/18 13 d288 Verticals FRP Suspended Slab (Pour 1) Wed 24/10/18 Thu 1/11/18 7 d289 Verticals FRP Suspended Slab (Pour 2) Thu 1/11/18 Wed 14/11/18 7 d290 ROOF LEVEL Fri 2/11/18 Mon 26/11/18 13 d291 Verticals FRP Suspended Slab (Pour 1) Fri 2/11/18 Thu 15/11/18 7 d292 Verticals FRP Suspended Slab (Pour 2) Thu 15/11/18 Mon 26/11/18 7 d293 ROOF LEVEL WORKS Fri 16/11/18 Wed 7/08/19 154 d294 LOT 1 Fri 16/11/18 Wed 17/04/19 88 d295 Complete Precast Core Lids Tue 27/11/18 Thu 6/12/18 7 d296 EAST Fri 16/11/18 Wed 10/04/19 83 d297 Install Drainage Fri 16/11/18 Thu 29/11/18 9 d298 Screeds & Ballast Fri 30/11/18 Wed 12/12/18 8 d299 Apply Water Proof Membrane Thu 13/12/18 Fri 18/01/19 15 d300 ROOF PLANT ENCLOSURE Fri 30/11/18 Wed 6/02/19 34 d301 Construct Plinths & Grillage Fri 30/11/18 Tue 11/12/18 7 d302 Install Plant & Connect Wed 12/12/18 Mon 14/01/19 12 d303 Construct Plant Screens Tue 15/01/19 Wed 30/01/19 10 d304 Test & Commission Mechanical Plant Tue 15/01/19 Wed 6/02/19 15 d305 ROOF COMMON AREA Thu 31/01/19 Wed 10/04/19 45 d306 Install Steel Structures Thu 31/01/19 Fri 8/02/19 7 d307 Install Roof Decking Tue 12/02/19 Wed 20/02/19 7 d308 Construct Lightweight Walls Thu 21/02/19 Wed 6/03/19 9 d309 Install Balustrades Thu 7/03/19 Tue 26/03/19 12 d310 Paving & Tiling Works Wed 20/03/19 Wed 10/04/19 15 d311 WEST Tue 27/11/18 Wed 17/04/19 82 d312 Install Drainage Tue 27/11/18 Mon 10/12/18 9 d313 Screeds & Ballast Tue 11/12/18 Thu 20/12/18 8 d314 Apply Water Proof Membrane Fri 21/12/18 Fri 25/01/19 14 d315 ROOF PLANT Fri 21/12/18 Wed 17/04/19 65 d316 Construct Plinths Fri 21/12/18 Mon 14/01/19 5 d317 Install Roof Plant & Equipment Tue 15/01/19 Thu 14/02/19 20 d318 Testing & Commissioning Services Thu 7/02/19 Wed 17/04/19 45 d319 ROOF / ROOF TOP POOL & TERRACE Fri 7/12/18 Wed 3/04/19 65 d320 Construct Lightweight Structures & Pergola's Fri 7/12/18 Wed 9/01/19 12 d321 Install Balustrades Thu 10/01/19 Thu 31/01/19 14 d

Verticals FRP Suspended Slab (Pour 2)LEVEL 5

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

ROOF LEVELVerticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

WEST TOWERLEVEL 2

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

LEVEL 3Verticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)LEVEL 4

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

LEVEL 5Verticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)ROOF LEVEL

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

LOT 1UPPER BASEMENT (GRIDS 1-K to 1-Q, 1-12.2 to 1-9)

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

Verticals FRP Suspended Slab (Pour 3)Verticals FRP Suspended Slab (Pour 4)

GROUND LEVEL (GRIDS 1-K to 1-Q, 1-12.2 to 1-9)Verticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)Verticals FRP Suspended Slab (Pour 3)

Verticals FRP Suspended Slab (Pour 4)LEVEL 1 EXTRA HEIGHT

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

Verticals FRP Suspended Slab (Pour 3)LEVEL 2

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

LEVEL 3Verticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)LEVEL 4

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

ROOF LEVELVerticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)ROOF LEVEL WORKS

LOT 1Complete Precast Core Lids

EAST Install Drainage

Screeds & BallastApply Water Proof Membrane

ROOF PLANT ENCLOSUREConstruct Plinths & Grillage

Install Plant & ConnectConstruct Plant Screens

Test & Commission Mechanical PlantROOF COMMON AREA

Install Steel StructuresInstall Roof Decking

Construct Lightweight WallsInstall Balustrades

Paving & Tiling WorksWEST

Install DrainageScreeds & Ballast

Apply Water Proof MembraneROOF PLANT

Construct PlinthsInstall Roof Plant & Equipment

Testing & Commissioning ServicesROOF / ROOF TOP POOL & TERRACE

Construct Lightweight Structures & Pergola'sInstall Balustrades

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 4 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 24: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

322 Paving & Tiling Works Wed 23/01/19 Thu 7/02/19 10 d323 Finishes to Planter Boxes Fri 8/02/19 Fri 22/02/19 10 d324 Construct Seating Areas Mon 18/02/19 Mon 4/03/19 10 d325 Install BBQ & Seating Thu 28/02/19 Thu 14/03/19 9 d326 Install Irrigation Systems Fri 15/03/19 Thu 21/03/19 5 d327 Landscaping & Planting Works Mon 18/03/19 Wed 3/04/19 12 d328 LOT 2 Wed 30/01/19 Wed 7/08/19 117 d329 EAST Wed 30/01/19 Thu 4/07/19 96 d330 Complete Precast Core Lids Wed 30/01/19 Thu 7/02/19 7 d331 Install Drainage Wed 30/01/19 Tue 12/02/19 9 d332 Screeds & Ballast Wed 13/02/19 Fri 22/02/19 8 d333 Apply Water Proof Membrane Tue 26/02/19 Wed 20/03/19 15 d334 COLES ROOF PLANT ROOM Wed 6/02/19 Thu 14/03/19 23 d335 Construct Plinths & Grillage Wed 6/02/19 Wed 13/02/19 5 d336 Construct Plan Building Structure Thu 14/02/19 Thu 21/02/19 6 d337 Plant Room Sheeting & Cladding Fri 22/02/19 Thu 14/03/19 12 d338 ROOF TERRACE AREA Fri 22/02/19 Thu 4/07/19 80 d339 Install Steel Structures Fri 22/02/19 Tue 5/03/19 7 d340 Install Roof Decking Wed 6/03/19 Mon 18/03/19 7 d341 Construct Lightweight Walls Tue 19/03/19 Fri 29/03/19 9 d342 Install Balustrades Tue 2/04/19 Wed 17/04/19 12 d343 Paving & Tiling Works Thu 11/04/19 Thu 9/05/19 15 d344 Finishes to Planter Boxes Fri 10/05/19 Fri 24/05/19 10 d345 Construct Seating Areas Mon 20/05/19 Mon 3/06/19 10 d346 Install Seating Thu 30/05/19 Thu 13/06/19 9 d347 Install Irrigation Systems Fri 14/06/19 Tue 25/06/19 7 d348 Landscaping & Planting Works Wed 19/06/19 Thu 4/07/19 11 d349 WEST Tue 19/03/19 Wed 7/08/19 87 d350 Complete Precast Core Lids Tue 19/03/19 Wed 27/03/19 7 d351 Install Drainage Tue 19/03/19 Fri 29/03/19 9 d352 Screeds & Ballast Tue 2/04/19 Thu 11/04/19 8 d353 Apply Water Proof Membrane Fri 12/04/19 Thu 9/05/19 14 d354 ROOF PLANT Fri 12/04/19 Tue 30/07/19 65 d355 Construct Plinths Fri 12/04/19 Thu 18/04/19 5 d356 Install Roof Plant & Equipment Mon 29/04/19 Tue 28/05/19 20 d357 Testing & Commissioning Services Tue 21/05/19 Tue 30/07/19 45 d358 ROOF / ROOF TOP POOL & TERRACE Thu 28/03/19 Wed 7/08/19 80 d359 Install Steel Structure Thu 28/03/19 Mon 8/04/19 7 d360 Install Roof Decking Tue 9/04/19 Wed 17/04/19 7 d361 Construct Lightweight Walls & Pergola's Thu 18/04/19 Tue 14/05/19 12 d362 Install Balustrades Wed 15/05/19 Tue 4/06/19 14 d363 Paving & Tiling Works Wed 29/05/19 Thu 13/06/19 10 d364 Finishes to Planter Boxes Fri 14/06/19 Fri 28/06/19 10 d365 Construct Seating Areas Fri 21/06/19 Fri 5/07/19 10 d366 Install Seating Wed 3/07/19 Tue 16/07/19 9 d367 Install Irrigation Systems Wed 17/07/19 Fri 26/07/19 7 d368 Landscaping & Planting Works Tue 23/07/19 Wed 7/08/19 11 d369 TEMPORARY ROOFING WORKS TO STAGE 2 UPPER BASEMENT Wed 27/02/19 Thu 2/05/19 38 d370 Set Out, Drill & Fix Stub Columns Wed 27/02/19 Thu 7/03/19 7 d371 Install Primary Roof Structure Fri 8/03/19 Mon 18/03/19 5 d372 Install Secondary Structure Tue 19/03/19 Wed 27/03/19 7 d373 Install Gutters & Drainage Thu 28/03/19 Mon 8/04/19 7 d374 Lay Roof Sheeting Tue 9/04/19 Mon 15/04/19 5 d375 Capping & Flashing Tue 16/04/19 Thu 2/05/19 7 d376 STRIP CURE & BACK PROP Thu 13/09/18 Wed 10/04/19 122 d377 LOT 1 Thu 13/09/18 Wed 19/12/18 61 d378 UPPER BASEMENT Thu 13/09/18 Mon 8/10/18 15 d379 Initial Stress Thu 13/09/18 Thu 13/09/18 1 d380 Final Stress Fri 21/09/18 Fri 21/09/18 1 d381 Strip & Back Prop Wed 26/09/18 Tue 2/10/18 3 d382 Completion of Cure Wed 3/10/18 Mon 8/10/18 4 d383 GROUND Wed 3/10/18 Wed 24/10/18 15 d384 LEVEL 1 Fri 12/10/18 Fri 2/11/18 15 d385 LEVEL 2 Wed 24/10/18 Fri 16/11/18 15 d386 LEVEL 3 Fri 2/11/18 Wed 28/11/18 15 d387 LEVEL 4 Fri 16/11/18 Mon 10/12/18 15 d388 ROOF LEVEL Wed 28/11/18 Wed 19/12/18 15 d389 LOT 2 Mon 24/09/18 Wed 10/04/19 116 d390 UPPER BASEMENT Mon 24/09/18 Wed 17/10/18 15 d391 Initial Stress Mon 24/09/18 Mon 24/09/18 1 d392 Final Stress Wed 3/10/18 Wed 3/10/18 1 d393 Strip & Back Prop Mon 8/10/18 Wed 10/10/18 3 d394 Completion of Cure Thu 11/10/18 Wed 17/10/18 4 d395 GROUND LEVEL Fri 30/11/18 Fri 21/12/18 15 d396 LEVEL 1 Wed 16/01/19 Thu 7/02/19 15 d397 EAST TOWER Tue 4/12/18 Thu 21/02/19 43 d398 LEVEL 2 Tue 4/12/18 Wed 9/01/19 15 d399 LEVEL 3 Thu 13/12/18 Fri 18/01/19 15 d400 LEVEL 4 Wed 9/01/19 Thu 31/01/19 15 d401 LEVEL 5 Fri 18/01/19 Tue 12/02/19 15 d402 ROOF LEVEL Thu 31/01/19 Thu 21/02/19 15 d

Paving & Tiling WorksFinishes to Planter Boxes

Construct Seating AreasInstall BBQ & Seating

Install Irrigation SystemsLandscaping & Planting Works

LOT 2EAST

Complete Precast Core LidsInstall Drainage

Screeds & BallastApply Water Proof Membrane

COLES ROOF PLANT ROOMConstruct Plinths & Grillage

Construct Plan Building StructurePlant Room Sheeting & Cladding

ROOF TERRACE AREAInstall Steel Structures

Install Roof DeckingConstruct Lightweight Walls

Install BalustradesPaving & Tiling Works

Finishes to Planter BoxesConstruct Seating Areas

Install SeatingInstall Irrigation Systems

Landscaping & Planting WorksWEST

Complete Precast Core LidsInstall Drainage

Screeds & BallastApply Water Proof Membrane

ROOF PLANTConstruct Plinths

Install Roof Plant & EquipmentTesting & Commissioning Services

ROOF / ROOF TOP POOL & TERRACEInstall Steel Structure

Install Roof DeckingConstruct Lightweight Walls & Pergola's

Install BalustradesPaving & Tiling Works

Finishes to Planter BoxesConstruct Seating Areas

Install SeatingInstall Irrigation Systems

Landscaping & Planting WorksTEMPORARY ROOFING WORKS TO STAGE 2 UPPER BASEMENT

Set Out, Drill & Fix Stub ColumnsInstall Primary Roof Structure

Install Secondary StructureInstall Gutters & Drainage

Lay Roof SheetingCapping & Flashing

STRIP CURE & BACK PROPLOT 1

UPPER BASEMENTInitial Stress

Final StressStrip & Back Prop

Completion of CureGROUND

LEVEL 1LEVEL 2

LEVEL 3LEVEL 4

ROOF LEVELLOT 2

UPPER BASEMENTInitial Stress

Final StressStrip & Back Prop

Completion of CureGROUND LEVEL

LEVEL 1EAST TOWER

LEVEL 2LEVEL 3

LEVEL 4LEVEL 5

ROOF LEVEL

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 5 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 25: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

403 WEST TOWER Mon 4/02/19 Wed 10/04/19 43 d404 LEVEL 2 Mon 4/02/19 Tue 26/02/19 15 d405 LEVEL 3 Thu 14/02/19 Thu 7/03/19 15 d406 LEVEL 4 Tue 26/02/19 Wed 20/03/19 15 d407 LEVEL 5 Thu 7/03/19 Fri 29/03/19 15 d408 ROOF LEVEL Wed 20/03/19 Wed 10/04/19 15 d409 STRIPPING & CLEARING Mon 22/10/18 Thu 9/05/19 114 d410 LOT 1 Mon 22/10/18 Thu 31/01/19 55 d411 BASEMENT B2 Mon 22/10/18 Mon 29/10/18 6 d412 UPPER BASEMENT Wed 31/10/18 Mon 12/11/18 6 d413 GROUND LEVEL Wed 14/11/18 Tue 27/11/18 9 d414 LEVEL 1 Mon 26/11/18 Fri 7/12/18 9 d415 LEVEL 2 Thu 6/12/18 Tue 18/12/18 9 d416 LEVEL 3 Wed 19/12/18 Wed 16/01/19 9 d417 LEVEL 4 Thu 17/01/19 Thu 31/01/19 9 d418 LOT 2 Mon 21/01/19 Thu 9/05/19 66 d419 BASEMENT B2 Mon 21/01/19 Wed 30/01/19 6 d420 UPPER BASEMENT Thu 7/02/19 Mon 18/02/19 7 d421 GROUND Tue 19/02/19 Tue 26/02/19 5 d422 LEVEL 1 Fri 1/03/19 Thu 14/03/19 8 d423 EAST TOWER Fri 1/03/19 Thu 18/04/19 32 d424 LEVEL 2 Fri 1/03/19 Thu 14/03/19 8 d425 LEVEL 3 Fri 15/03/19 Tue 26/03/19 8 d426 LEVEL 4 Wed 27/03/19 Mon 8/04/19 8 d427 LEVEL 5 Tue 9/04/19 Thu 18/04/19 8 d428 WEST TOWER Mon 18/03/19 Thu 9/05/19 32 d429 LEVEL 2 Mon 18/03/19 Wed 27/03/19 8 d430 LEVEL 3 Thu 28/03/19 Tue 9/04/19 8 d431 LEVEL 4 Wed 10/04/19 Mon 29/04/19 8 d432 LEVEL 5 Tue 30/04/19 Thu 9/05/19 8 d433 MAIN SERVICES Wed 10/10/18 Wed 14/08/19 181 d434 SUBSTATION Wed 10/10/18 Wed 20/03/19 91 d435 Ground Level Fully Stressed Wed 10/10/18 Wed 10/10/18 0 d436 Strip & Clear Services Area Thu 11/10/18 Tue 16/10/18 3 d437 Complete Conduits & Cable Racking To Room Wed 17/10/18 Fri 16/11/18 20 d438 Block Work Walls Wed 17/10/18 Thu 25/10/18 7 d439 Install Door Frames & Doors Fri 26/10/18 Thu 1/11/18 5 d440 Services Fit Out & Paint Room Fri 2/11/18 Mon 12/11/18 4 d441 Install Mono Rail, Floor Plates & Grates, Complete Services Fit Off Tue 13/11/18 Thu 22/11/18 7 d442 BWIC Prior to Handover Fri 23/11/18 Thu 29/11/18 5 d443 Handover to Supply Authority Thu 29/11/18 Thu 29/11/18 0 d444 Supply Authority Works Fri 30/11/18 Wed 20/03/19 60 d445 Substation Live & Certified Wed 20/03/19 Wed 20/03/19 0 d446 MAIN SWITCH ROOM Fri 30/11/18 Mon 25/03/19 63 d447 Complete Builder's Work Fri 30/11/18 Fri 14/12/18 10 d448 Install Switchboard & Fit Out Room Mon 17/12/18 Tue 15/01/19 10 d449 Install Cable Racking & Supply Extension to New Switch Room Wed 9/01/19 Thu 31/01/19 15 d450 Initial Connection to New Panels, Test Fri 1/02/19 Fri 15/02/19 10 d451 Test & Commission Thu 21/03/19 Mon 25/03/19 3 d452 Permanent Power Available Switch Room Mon 25/03/19 Mon 25/03/19 0 d453 TRAVELATORS Tue 26/03/19 Wed 3/07/19 60 d454 Builder's Work Prior to Handover Tue 26/03/19 Tue 2/04/19 5 d455 Install Travelator Frames Wed 3/04/19 Wed 8/05/19 20 d456 Fit Off Frames Thu 9/05/19 Tue 18/06/19 25 d457 Final Commission & Commissioning Wed 19/06/19 Wed 3/07/19 10 d458 LIFTS Fri 7/12/18 Wed 14/08/19 146 d459 COLES BOH & RETAIL Fri 8/02/19 Fri 3/05/19 50 d460 Builder's Work Prior to Handover Fri 8/02/19 Mon 4/03/19 15 d461 Install Lift Rails & Lift Equipment Tue 5/03/19 Thu 11/04/19 25 d462 Test & Commissioning Fri 12/04/19 Fri 3/05/19 10 d463 Lifts Operational Fri 3/05/19 Fri 3/05/19 0 d464 LOT 1 Fri 7/12/18 Thu 2/05/19 80 d465 Builder's Work Prior to Handover Fri 7/12/18 Thu 20/12/18 10 d466 Install Lift Rails & Lift Cars Fri 21/12/18 Tue 19/03/19 45 d467 Test & Commissioning Wed 20/03/19 Tue 26/03/19 5 d468 Builder Lift Available Tue 26/03/19 Tue 26/03/19 0 d469 Completion Of Lift Installation & Commissioning Thu 11/04/19 Wed 17/04/19 5 d470 Final Commission & Lift Tuning Thu 18/04/19 Thu 2/05/19 5 d471 LOT 2 Fri 8/02/19 Wed 14/08/19 115 d472 EAST BUILDING Fri 8/02/19 Fri 28/06/19 85 d473 Builder's Work Prior to Handover Fri 8/02/19 Fri 22/02/19 10 d474 Install Lift Rails & Lift Equipment Tue 26/02/19 Fri 10/05/19 45 d475 Test & Commissioning Tue 14/05/19 Tue 28/05/19 10 d476 Builder Lift Available Tue 28/05/19 Tue 28/05/19 0 d477 Complete Fit Out of Builders Lift Fri 14/06/19 Thu 20/06/19 5 d478 Final Commission & Lift Tuning Fri 21/06/19 Fri 28/06/19 5 d479 WEST BUILDING Thu 28/03/19 Wed 14/08/19 85 d480 Builder's Work Prior to Handover Thu 28/03/19 Thu 11/04/19 10 d481 Install Lift Rails & Lift Equipment Fri 12/04/19 Fri 28/06/19 45 d482 Test & Commissioning Mon 1/07/19 Mon 15/07/19 10 d483 Builder Lift Available Mon 15/07/19 Mon 15/07/19 0 d

WEST TOWERLEVEL 2

LEVEL 3LEVEL 4

LEVEL 5ROOF LEVEL

STRIPPING & CLEARINGLOT 1

BASEMENT B2UPPER BASEMENT

GROUND LEVELLEVEL 1

LEVEL 2LEVEL 3

LEVEL 4LOT 2

BASEMENT B2UPPER BASEMENT

GROUNDLEVEL 1

EAST TOWERLEVEL 2

LEVEL 3LEVEL 4

LEVEL 5WEST TOWER

LEVEL 2LEVEL 3

LEVEL 4LEVEL 5

MAIN SERVICESSUBSTATION

10/10/2018Strip & Clear Services Area

Complete Conduits & Cable Racking To RoomBlock Work Walls

Install Door Frames & DoorsServices Fit Out & Paint Room

Install Mono Rail, Floor Plates & Grates, Complete Services Fit OffBWIC Prior to Handover29/11/2018

Supply Authority Works20/03/2019

MAIN SWITCH ROOM Complete Builder's Work

Install Switchboard & Fit Out RoomInstall Cable Racking & Supply Extension to New Switch Room

Initial Connection to New Panels, TestTest & Commission25/03/2019

TRAVELATORSBuilder's Work Prior to Handover

Install Travelator FramesFit Off Frames

Final Commission & CommissioningLIFTS

COLES BOH & RETAILBuilder's Work Prior to Handover

Install Lift Rails & Lift EquipmentTest & Commissioning3/05/2019

LOT 1Builder's Work Prior to Handover

Install Lift Rails & Lift CarsTest & Commissioning26/03/2019

Completion Of Lift Installation & CommissioningFinal Commission & Lift Tuning

LOT 2EAST BUILDING

Builder's Work Prior to HandoverInstall Lift Rails & Lift Equipment

Test & Commissioning28/05/2019

Complete Fit Out of Builders LiftFinal Commission & Lift Tuning

WEST BUILDINGBuilder's Work Prior to Handover

Install Lift Rails & Lift EquipmentTest & Commissioning15/07/2019

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 6 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 26: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

484 Complete Fit Out of Builders Lift Wed 31/07/19 Wed 7/08/19 5 d485 Final Commission & Lift Tuning Thu 8/08/19 Wed 14/08/19 5 d486 FIRE PUMPS & TANKS Thu 13/12/18 Fri 15/03/19 49 d487 BWIC Prior to Handover Thu 13/12/18 Fri 11/01/19 10 d488 Construct Tanks Mon 14/01/19 Thu 31/01/19 12 d489 Install Pumps Fri 1/02/19 Fri 15/02/19 10 d490 Connect & Fill Tanks Mon 18/02/19 Wed 27/02/19 7 d491 Preliminary Test & Commission Thu 28/02/19 Fri 15/03/19 10 d492 REMAINING FAÇADE WORKS Fri 18/01/19 Wed 4/09/19 142 d493 LOT 1 Fri 18/01/19 Fri 7/06/19 86 d494 GROUND FLOOR Thu 28/03/19 Fri 7/06/19 43 d495 Install Façade Support Brackets Thu 28/03/19 Wed 10/04/19 9 d496 Install Frames & Mullions Thu 11/04/19 Thu 2/05/19 10 d497 Install Shop Fronts & Glazing Fri 3/05/19 Fri 17/05/19 10 d498 Prepare & Install Awning Mounting Brackets & Awnings Fri 10/05/19 Wed 29/05/19 12 d499 Services Fit-Off & Cladding Finishes to Awnings Wed 22/05/19 Fri 7/06/19 12 d500 LEVEL 1 Thu 31/01/19 Tue 9/04/19 43 d501 Commence Scaffolding Thu 31/01/19 Thu 31/01/19 0 d502 Install Façade Support Brackets Thu 7/02/19 Tue 26/02/19 12 d503 Install Frames, Transoms & Mullions Wed 27/02/19 Mon 18/03/19 12 d504 Install Feature Cladding & Wall Glazing & Caulk Tue 19/03/19 Tue 9/04/19 15 d505 LEVEL 2 Fri 18/01/19 Wed 27/03/19 43 d506 LEVEL 3 Tue 5/02/19 Thu 11/04/19 43 d507 LEVEL 4 Wed 20/02/19 Fri 3/05/19 43 d508 LOT 2 Thu 28/03/19 Wed 4/09/19 98 d509 GROUND FLOOR Fri 5/07/19 Wed 4/09/19 40 d510 Install Façade Support Brackets Fri 5/07/19 Fri 19/07/19 10 d511 Prepare & Install Awning Mounting Brackets & Awnings Tue 23/07/19 Thu 15/08/19 17 d512 Services Fit-Off & Cladding Finishes to Awnings Fri 9/08/19 Wed 4/09/19 18 d513 LEVEL 1 Wed 10/04/19 Fri 7/06/19 35 d514 Install Façade Support Brackets Wed 10/04/19 Wed 1/05/19 10 d515 Install Frames, Transoms & Mullions Thu 2/05/19 Thu 16/05/19 10 d516 Install Feature Cladding & Wall Glazing & Caulk Fri 17/05/19 Fri 7/06/19 15 d517 EAST Thu 28/03/19 Fri 2/08/19 77 d518 Commence Scaffolding Thu 28/03/19 Thu 28/03/19 0 d519 LEVEL 2 Thu 4/04/19 Mon 3/06/19 35 d520 LEVEL 3 Thu 18/04/19 Wed 19/06/19 35 d521 LEVEL 4 Fri 10/05/19 Thu 4/07/19 35 d522 LEVEL 5 Wed 12/06/19 Fri 2/08/19 35 d523 WEST Thu 11/04/19 Fri 2/08/19 68 d524 Commence Scaffolding Thu 11/04/19 Thu 11/04/19 0 d525 LEVEL 2 Wed 17/04/19 Tue 18/06/19 35 d526 LEVEL 3 Thu 9/05/19 Wed 3/07/19 35 d527 LEVEL 4 Fri 24/05/19 Thu 18/07/19 35 d528 LEVEL 5 Wed 12/06/19 Fri 2/08/19 35 d529 WORK ZONE 1 B Tue 4/09/18 Thu 7/03/19 108 d530 SUB STRUCTURE Tue 4/09/18 Thu 11/10/18 25 d531 Final Trim & Detail To Required Levels Tue 4/09/18 Mon 10/09/18 5 d532 Detail Excavate FRP Pad Footings Tue 11/09/18 Thu 27/09/18 12 d533 Detail Excavate FRP Strip Footings Mon 24/09/18 Thu 11/10/18 12 d534 Detail FRP Raft Slabs Mon 24/09/18 Tue 2/10/18 5 d535 FRP Overruns Strip & Cure Wed 3/10/18 Thu 11/10/18 7 d536 Under Slab Service Tue 11/09/18 Thu 4/10/18 15 d537 SLABS ON GROUND (LOWER BASEMENT) Fri 12/10/18 Thu 22/11/18 25 d538 Prepare Sub Base FRP Slab On Ground (Pour 1) Fri 12/10/18 Fri 19/10/18 5 d539 Prepare Sub Base FRP Slab On Ground (Pour 2) Mon 22/10/18 Fri 26/10/18 5 d540 Prepare Sub Base FRP Slab On Ground (Pour 3) Mon 29/10/18 Fri 2/11/18 5 d541 Prepare Sub Base FRP Slab On Ground (Pour 4) Thu 8/11/18 Wed 14/11/18 5 d542 Prepare Sub Base FRP Slab On Ground (Pour 5) Thu 15/11/18 Thu 22/11/18 5 d543 UPPER BASEMENT Fri 23/11/18 Tue 26/02/19 51 d544 Verticals FRP Suspended Slab (Pour 1) Fri 23/11/18 Thu 6/12/18 9 d545 Verticals FRP Suspended Slab (Pour 2) Tue 4/12/18 Fri 14/12/18 9 d546 Verticals FRP Suspended Slab (Pour 3) Wed 12/12/18 Wed 9/01/19 9 d547 Verticals FRP Suspended Slab (Pour 4) Thu 20/12/18 Thu 17/01/19 9 d548 Verticals FRP Suspended Slab (Pour 5) Tue 15/01/19 Fri 25/01/19 9 d549 Verticals FRP Suspended Slab (Pour 6) Wed 23/01/19 Wed 6/02/19 9 d550 Verticals FRP Suspended Slab (Pour 7) Mon 4/02/19 Fri 15/02/19 9 d551 Verticals FRP Suspended Slab (Pour 8) Wed 13/02/19 Tue 26/02/19 9 d552 GROUND Fri 7/12/18 Thu 7/03/19 49 d553 Verticals FRP Suspended Slab (Pour 1) Fri 7/12/18 Tue 18/12/18 8 d554 Verticals FRP Suspended Slab (Pour 2) Fri 14/12/18 Thu 10/01/19 8 d555 Verticals FRP Suspended Slab (Pour 3) Fri 21/12/18 Fri 18/01/19 9 d556 Verticals FRP Suspended Slab (Pour 4) Wed 16/01/19 Wed 30/01/19 9 d557 Verticals FRP Suspended Slab (Pour 5) Thu 24/01/19 Thu 7/02/19 9 d558 Verticals FRP Suspended Slab (Pour 6) Tue 5/02/19 Mon 18/02/19 9 d559 Verticals FRP Suspended Slab (Pour 7) Thu 14/02/19 Wed 27/02/19 9 d560 Verticals FRP Suspended Slab (Pour 8) Fri 22/02/19 Thu 7/03/19 9 d561 FIT OUT & FINISHES Wed 28/11/18 Wed 18/12/19 233 d562 BASEMENTS UNDER LOTS 1 & 2 Thu 31/01/19 Fri 21/06/19 87 d563 BASEMENT B 2 Thu 31/01/19 Mon 3/06/19 75 d

Complete Fit Out of Builders LiftFinal Commission & Lift Tuning

FIRE PUMPS & TANKSBWIC Prior to Handover

Construct Tanks Install Pumps

Connect & Fill TanksPreliminary Test & Commission

REMAINING FAÇADE WORKSLOT 1

GROUND FLOORInstall Façade Support Brackets

Install Frames & MullionsInstall Shop Fronts & Glazing

Prepare & Install Awning Mounting Brackets & AwningsServices Fit-Off & Cladding Finishes to Awnings

LEVEL 131/01/2019

Install Façade Support BracketsInstall Frames, Transoms & Mullions

Install Feature Cladding & Wall Glazing & CaulkLEVEL 2

LEVEL 3LEVEL 4

LOT 2GROUND FLOOR

Install Façade Support BracketsPrepare & Install Awning Mounting Brackets & Awnings

Services Fit-Off & Cladding Finishes to AwningsLEVEL 1

Install Façade Support BracketsInstall Frames, Transoms & Mullions

Install Feature Cladding & Wall Glazing & CaulkEAST

28/03/2019LEVEL 2

LEVEL 3LEVEL 4

LEVEL 5WEST

11/04/2019LEVEL 2

LEVEL 3LEVEL 4

LEVEL 5WORK ZONE 1 B

SUB STRUCTUREFinal Trim & Detail To Required Levels

Detail Excavate FRP Pad Footings Detail Excavate FRP Strip Footings

Detail FRP Raft SlabsFRP Overruns Strip & Cure

Under Slab ServiceSLABS ON GROUND (LOWER BASEMENT)

Prepare Sub Base FRP Slab On Ground (Pour 1)Prepare Sub Base FRP Slab On Ground (Pour 2)

Prepare Sub Base FRP Slab On Ground (Pour 3)Prepare Sub Base FRP Slab On Ground (Pour 4)

Prepare Sub Base FRP Slab On Ground (Pour 5)UPPER BASEMENT

Verticals FRP Suspended Slab (Pour 1)Verticals FRP Suspended Slab (Pour 2)

Verticals FRP Suspended Slab (Pour 3)Verticals FRP Suspended Slab (Pour 4)

Verticals FRP Suspended Slab (Pour 5)Verticals FRP Suspended Slab (Pour 6)

Verticals FRP Suspended Slab (Pour 7)Verticals FRP Suspended Slab (Pour 8)

GROUNDVerticals FRP Suspended Slab (Pour 1)

Verticals FRP Suspended Slab (Pour 2)Verticals FRP Suspended Slab (Pour 3)

Verticals FRP Suspended Slab (Pour 4)Verticals FRP Suspended Slab (Pour 5)

Verticals FRP Suspended Slab (Pour 6)Verticals FRP Suspended Slab (Pour 7)

Verticals FRP Suspended Slab (Pour 8)FIT OUT & FINISHESBASEMENTS UNDER LOTS 1 & 2

BASEMENT B 2

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 7 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 27: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

564 BASEMENT B 1 Tue 19/02/19 Fri 21/06/19 75 d565 REMAINING BASEMENT AREAS Fri 22/03/19 Tue 16/07/19 70 d566 BASEMENT B 2 Fri 22/03/19 Mon 1/07/19 60 d567 BASEMENT B 1 Tue 30/04/19 Tue 16/07/19 50 d568 LOT 2 GROUND FLOOR - COLES Tue 26/02/19 Wed 18/12/19 185 d569 Area Stripped Commence Coles Tue 26/02/19 Tue 26/02/19 0 d570 COLES MAIN SERVICES Wed 27/02/19 Fri 24/05/19 53 d571 PLANT BASEMENT Wed 27/02/19 Tue 14/05/19 45 d572 Construct Plant Room Blockwork Walls Wed 27/02/19 Thu 14/03/19 10 d573 Plant & Equipment Fri 15/03/19 Fri 5/04/19 15 d574 Preliminary Test & Commission Main Services Mon 8/04/19 Mon 29/04/19 10 d575 Final Services Fitoff / Clean / Defects Rectification Tue 30/04/19 Tue 14/05/19 10 d576 PLANT ROOM MEZZANINE Wed 6/03/19 Fri 24/05/19 48 d577 Construct Plant Room Blockwork Walls Wed 6/03/19 Tue 19/03/19 8 d578 Install & Hook up MSB / Sub-mains Mon 18/03/19 Fri 22/03/19 5 d579 Comms - Install Panel & Connect Mon 25/03/19 Mon 8/04/19 10 d580 Install Remaining Plant & Equipment Tue 2/04/19 Wed 17/04/19 12 d581 Preliminary Test & Commission Main Services Thu 18/04/19 Thu 9/05/19 10 d582 Final Services Fitoff / Clean / Defects Rectification Fri 10/05/19 Fri 24/05/19 10 d583 ROOF PLANT Wed 20/03/19 Fri 17/05/19 35 d584 Builders Work Prior to Handover Wed 20/03/19 Tue 26/03/19 5 d585 Install Condensers Wed 27/03/19 Thu 2/05/19 20 d586 Testing & Commissioning Thu 18/04/19 Fri 17/05/19 15 d587 GROUND LEVEL Wed 27/02/19 Fri 20/09/19 129 d588 Remove Back Propping & Clear Floor Wed 27/02/19 Fri 15/03/19 11 d589 FAÇADE Wed 27/02/19 Fri 29/03/19 21 d590 Install Wall Framing / Window Sub Sills & Frames Wed 27/02/19 Wed 13/03/19 9 d591 Top Hats Install Wall Cladding Mon 4/03/19 Mon 18/03/19 9 d592 Install Glazing Sections and External Shop Fronts Wed 13/03/19 Mon 25/03/19 9 d593 Install Entry Doors Thu 21/03/19 Fri 29/03/19 7 d594 Building Mostly Watertight Fri 29/03/19 Fri 29/03/19 0 d595 TRADING AREA Mon 18/03/19 Wed 7/08/19 88 d596 HL Services Rough-In Mon 18/03/19 Fri 5/04/19 14 d597 Paint Exposed HL Services Tue 2/04/19 Mon 15/04/19 10 d598 Topping Screed to Trading Floor & Cure Period Tue 16/04/19 Tue 7/05/19 10 d599 Internal Walls / Wall Rough-in & Linings Wed 8/05/19 Fri 24/05/19 12 d600 Bulkheads / Susp. Ceiling Grid / PB Lining Tue 21/05/19 Wed 5/06/19 11 d601 Joinery & Services Rough-in Fri 24/05/19 Thu 13/06/19 12 d602 Services Fit-off / Paint / Builders Fit-off Wed 29/05/19 Mon 17/06/19 12 d603 Install Floor Finishes (Including Polished Concrete Floor) Tue 4/06/19 Fri 12/07/19 25 d604 Final Paint & Clean / FF & E Tue 9/07/19 Thu 25/07/19 12 d605 Fitout - Signage, Hardware, etc. Fri 26/07/19 Wed 31/07/19 4 d606 Builders Clean & Touch up / Defecting Thu 1/08/19 Wed 7/08/19 4 d607 BACK OF HOUSE & STORAGE AREA Mon 8/04/19 Wed 7/08/19 74 d608 Blockwork Walls Mon 8/04/19 Wed 17/04/19 8 d609 HL Services Rough-in Thu 18/04/19 Fri 10/05/19 11 d610 Internal Walls / Wall Panels, etc. Thu 2/05/19 Thu 16/05/19 10 d611 Wall Rough-in & Linings Fri 10/05/19 Fri 24/05/19 10 d612 Suspended Ceiling Grid / PB Ceilings Wed 22/05/19 Mon 3/06/19 8 d613 Fitout Transfer Room Tue 28/05/19 Wed 5/06/19 7 d614 Joinery & Services Rough-in Wed 29/05/19 Fri 7/06/19 8 d615 Cool Rooms, Freezers, Complete Floor Finishes In Area Fri 17/05/19 Fri 14/06/19 18 d616 Services Fit-off / Paint / Builders Fit-off Thu 13/06/19 Thu 27/06/19 10 d617 Floor Finishes Wed 26/06/19 Wed 17/07/19 15 d618 Fitout - Signage, Hardware, etc. Fri 12/07/19 Wed 24/07/19 8 d619 Final Paint & Clean / FF & E Tue 23/07/19 Tue 30/07/19 6 d620 Builders Clean & Touch up / Defecting Wed 31/07/19 Wed 7/08/19 5 d621 OFFICE & STAFF AREAS Tue 14/05/19 Wed 7/08/19 55 d622 HL Services Rough-in Tue 14/05/19 Tue 28/05/19 10 d623 Construct Internal Walls Mon 20/05/19 Mon 3/06/19 10 d624 Services Rough-In Walls Wed 29/05/19 Thu 13/06/19 10 d625 PB Wall Lining / Set & Sand Thu 6/06/19 Fri 21/06/19 10 d626 Install Susp. Ceilings & Bulkheads / Linings Thu 6/06/19 Thu 20/06/19 9 d627 Amenities - WP Membranes & Cure Tue 4/06/19 Thu 13/06/19 6 d628 Amenities - Screeds & Tiling Wed 12/06/19 Fri 21/06/19 8 d629 Amenities - Partitions, Joinery & Hydr Fitout Thu 20/06/19 Tue 2/07/19 8 d630 Amenities - Fit-Off & Final Finishes Tue 2/07/19 Fri 12/07/19 8 d631 Offices - Fitout & Finishes Fri 21/06/19 Fri 5/07/19 10 d632 Hang Doors & Hardware / Fixtures / Fitout Tue 9/07/19 Tue 16/07/19 6 d633 Lay Carpet & Other Floor Finishes Wed 17/07/19 Tue 23/07/19 4 d634 Services Fit-Off / Final Paint / FF & E Tue 23/07/19 Tue 30/07/19 6 d635 Builders Clean & Touch up / Defecting Wed 31/07/19 Wed 7/08/19 5 d636 LOADING DOCK AREA Wed 29/05/19 Wed 7/08/19 45 d637 Install Dock Levellers, Roller Doors Wed 29/05/19 Thu 6/06/19 7 d638 HL Services Rough-in Tue 4/06/19 Fri 14/06/19 7 d639 Construct Internal Walls, Panels, etc. Wed 12/06/19 Wed 19/06/19 6 d640 Wall Rough-in & Linings Mon 17/06/19 Tue 25/06/19 6 d641 Ceiling Panels Thu 20/06/19 Mon 1/07/19 7 d642 Install Loading Dock Equipment Tue 2/07/19 Thu 18/07/19 12 d643 Joinery & Services Rough-in Thu 27/06/19 Tue 2/07/19 4 d644 Services Fit-off / Paint / Builders Fit-off Tue 25/06/19 Tue 9/07/19 10 d

BASEMENT B 1REMAINING BASEMENT AREAS

BASEMENT B 2BASEMENT B 1

LOT 2 GROUND FLOOR - COLES26/02/2019

COLES MAIN SERVICESPLANT BASEMENT

Construct Plant Room Blockwork WallsPlant & Equipment

Preliminary Test & Commission Main Services Final Services Fitoff / Clean / Defects Rectification

PLANT ROOM MEZZANINEConstruct Plant Room Blockwork WallsInstall & Hook up MSB / Sub-mains

Comms - Install Panel & ConnectInstall Remaining Plant & Equipment

Preliminary Test & Commission Main Services Final Services Fitoff / Clean / Defects Rectification

ROOF PLANTBuilders Work Prior to Handover

Install CondensersTesting & Commissioning

GROUND LEVELRemove Back Propping & Clear Floor

FAÇADEInstall Wall Framing / Window Sub Sills & FramesTop Hats Install Wall Cladding

Install Glazing Sections and External Shop FrontsInstall Entry Doors29/03/2019

TRADING AREAHL Services Rough-In

Paint Exposed HL ServicesTopping Screed to Trading Floor & Cure Period

Internal Walls / Wall Rough-in & LiningsBulkheads / Susp. Ceiling Grid / PB Lining

Joinery & Services Rough-inServices Fit-off / Paint / Builders Fit-off

Install Floor Finishes (Including Polished Concrete Floor)Final Paint & Clean / FF & E

Fitout - Signage, Hardware, etc.Builders Clean & Touch up / Defecting

BACK OF HOUSE & STORAGE AREABlockwork Walls

HL Services Rough-inInternal Walls / Wall Panels, etc.

Wall Rough-in & LiningsSuspended Ceiling Grid / PB CeilingsFitout Transfer RoomJoinery & Services Rough-in

Cool Rooms, Freezers, Complete Floor Finishes In AreaServices Fit-off / Paint / Builders Fit-off

Floor FinishesFitout - Signage, Hardware, etc.

Final Paint & Clean / FF & EBuilders Clean & Touch up / Defecting

OFFICE & STAFF AREASHL Services Rough-in

Construct Internal WallsServices Rough-In Walls

PB Wall Lining / Set & SandInstall Susp. Ceilings & Bulkheads / Linings

Amenities - WP Membranes & CureAmenities - Screeds & Tiling

Amenities - Partitions, Joinery & Hydr FitoutAmenities - Fit-Off & Final Finishes

Offices - Fitout & FinishesHang Doors & Hardware / Fixtures / Fitout

Lay Carpet & Other Floor FinishesServices Fit-Off / Final Paint / FF & E

Builders Clean & Touch up / DefectingLOADING DOCK AREA

Install Dock Levellers, Roller DoorsHL Services Rough-inConstruct Internal Walls, Panels, etc.

Wall Rough-in & LiningsCeiling Panels

Install Loading Dock EquipmentJoinery & Services Rough-in

Services Fit-off / Paint / Builders Fit-off

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 8 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 28: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

645 Fitout - Signage, Hardware Wed 3/07/19 Tue 16/07/19 9 d646 Floor Finishes Mon 15/07/19 Tue 23/07/19 6 d647 Final Paint & Clean / FF & E Wed 24/07/19 Tue 30/07/19 5 d648 Builders Clean & Touch up / Defecting Wed 31/07/19 Wed 7/08/19 5 d649 Separable Portion 1 - Base Build Work Complete Hand Over Coles (Net) Wed 7/08/19 Wed 7/08/19 0 d650 Inclement Weather Delay Contingency Thu 8/08/19 Fri 20/09/19 30 d651 Separable Portion 1 - Base Build Work Complete Hand Over Coles (Net) Fri 20/09/19 Fri 20/09/19 0 d652 COLES FITOUT BY OTHERS (12 Weeks) Mon 23/09/19 Wed 18/12/19 61 d653 Separable Portion 2 Coles Open & Trading Wed 18/12/19 Wed 18/12/19 0 d654 LOT 2 ABOVE COLES Fri 1/03/19 Wed 9/10/19 138 d655 EAST Fri 1/03/19 Tue 17/09/19 124 d656 LEVEL 1 Fri 1/03/19 Tue 30/07/19 92 d657 Set Out, Frames Primary Walls, High Level Sheet Fri 1/03/19 Thu 7/03/19 5 d658 Services Hl Rough In To Corridors & Mechanical Duct To Apartments Fri 8/03/19 Wed 20/03/19 7 d659 Install Sub Sills Measure Window Frames & Frames Lead-In Time Fri 8/03/19 Wed 20/03/19 7 d660 Set Out , Frame Secondary Walls Fri 15/03/19 Tue 26/03/19 8 d661 Install Windows Thu 21/03/19 Fri 29/03/19 7 d662 Balcony Wall Cladding Tue 2/04/19 Tue 9/04/19 6 d663 Balcony Measure / Install Balustrade Wed 10/04/19 Thu 18/04/19 7 d664 Balcony Membrane Mon 29/04/19 Fri 3/05/19 5 d665 Membrane Inspection Mon 6/05/19 Tue 7/05/19 2 d666 Balcony Tile Wed 8/05/19 Fri 17/05/19 7 d667 Noggins Set Out & Install For Trades Fri 22/03/19 Wed 27/03/19 4 d668 Services Rough-In In Wall & Ceilings (Inc Fire Caulk) Mon 25/03/19 Fri 5/04/19 9 d669 Wall Linings / Ceiling Frame / Ceiling Linings / Stop & Sand Tue 2/04/19 Tue 9/04/19 6 d670 First Fix Carpentry Doors / Skirts To Carpet Areas Fri 29/03/19 Mon 8/04/19 6 d671 Paint 1st Coat Defect Ceiling, Paint 2nd Coat Ceilings Wed 3/04/19 Wed 10/04/19 6 d672 Wet Areas Bottom Membrane, Screed, Top Membrane Wed 10/04/19 Mon 15/04/19 4 d673 Waterproofing Inspection Tue 16/04/19 Wed 17/04/19 2 d674 Wet Areas Floor & Wall Tiling Inc. Grout Thu 18/04/19 Thu 9/05/19 10 d675 Measure Shower Screens Fri 10/05/19 Fri 10/05/19 1 d676 Wet Areas - Install Joinery & Vanity Units Mon 6/05/19 Wed 15/05/19 7 d677 Install Shower Screens & Robes Tue 21/05/19 Tue 28/05/19 5 d678 Prototype Apartment Complete Ready For Inspection Thu 23/05/19 Thu 23/05/19 0 d679 Kitchen - Install Joinery Thu 11/04/19 Wed 1/05/19 9 d680 Measure Stone Benchtops Thu 2/05/19 Thu 2/05/19 1 d681 Patch & Float Floors Thu 2/05/19 Mon 6/05/19 3 d682 Install Bench Tops Wed 15/05/19 Fri 17/05/19 3 d683 Fit Off Hydraulic Mon 20/05/19 Thu 23/05/19 4 d684 Defect Walls & Patch Thu 23/05/19 Thu 30/05/19 5 d685 Timber Flooring Wed 29/05/19 Tue 4/06/19 5 d686 2nd Fix Carpentry Tue 4/06/19 Fri 7/06/19 4 d687 Lay Carpet / Protect Fri 7/06/19 Fri 14/06/19 4 d688 Corridors Complete Services Rough Mon 20/05/19 Fri 24/05/19 5 d689 Corridors Sheet Walls & Ceilings Thu 23/05/19 Thu 30/05/19 5 d690 Corridors Initial Paint Fri 31/05/19 Wed 5/06/19 4 d691 Corridors Defect Thu 6/06/19 Wed 12/06/19 3 d692 Corridors Final Paint Thu 13/06/19 Mon 17/06/19 3 d693 Corridors Signage Tue 18/06/19 Wed 19/06/19 2 d694 1st Clean (builders) Mon 17/06/19 Wed 19/06/19 3 d695 Final Paint Thu 20/06/19 Tue 25/06/19 3 d696 Final Caulk Tue 25/06/19 Thu 27/06/19 3 d697 Builders Inspection Fri 28/06/19 Tue 2/07/19 3 d698 Defect Rectification Wed 3/07/19 Tue 9/07/19 4 d699 Defect Clean Wed 10/07/19 Mon 15/07/19 4 d700 Client Inspection Tue 16/07/19 Wed 17/07/19 2 d701 Defect Rectification Thu 18/07/19 Wed 24/07/19 4 d702 Defect Clean Thu 25/07/19 Tue 30/07/19 4 d703 LEVEL 2 Fri 15/03/19 Mon 12/08/19 92 d704 LEVEL 3 Wed 27/03/19 Fri 23/08/19 92 d705 LEVEL 4 Tue 9/04/19 Wed 4/09/19 92 d706 LEVEL 5 Mon 29/04/19 Tue 17/09/19 92 d707 WEST Fri 15/03/19 Wed 9/10/19 130 d708 LEVEL 1 Fri 15/03/19 Tue 13/08/19 93 d709 Set Out, Frames Primary Walls, High Level Sheet Fri 15/03/19 Thu 21/03/19 5 d710 Services Hl Rough In To Corridors & Mechanical Duct To Apartments Fri 22/03/19 Tue 2/04/19 7 d711 Install Sub Sills Measure Window Frames & Frames Lead-In Time Fri 22/03/19 Tue 2/04/19 7 d712 Set Out , Frame Secondary Walls Wed 27/03/19 Mon 8/04/19 8 d713 Install Windows Wed 3/04/19 Thu 11/04/19 7 d714 Balcony Wall Cladding Fri 12/04/19 Mon 29/04/19 6 d715 Balcony Measure / Install Balustrade Tue 30/04/19 Wed 8/05/19 7 d716 Balcony Membrane Thu 9/05/19 Thu 16/05/19 5 d717 Membrane Inspection Fri 17/05/19 Mon 20/05/19 2 d718 Balcony Tile Tue 21/05/19 Thu 30/05/19 7 d719 Noggins Set Out & Install For Trades Thu 4/04/19 Tue 9/04/19 4 d720 Services Rough-In In Wall & Ceilings (Inc Fire Caulk) Fri 5/04/19 Wed 17/04/19 9 d721 Wall Linings / Ceiling Frame / Ceiling Linings / Stop & Sand Fri 12/04/19 Mon 29/04/19 6 d722 First Fix Carpentry Doors / Skirts To Carpet Areas Thu 11/04/19 Thu 18/04/19 6 d723 Paint 1st Coat Defect Ceiling, Paint 2nd Coat Ceilings Mon 15/04/19 Tue 30/04/19 6 d724 Wet Areas Bottom Membrane, Screed, Top Membrane Tue 30/04/19 Fri 3/05/19 4 d725 Waterproofing Inspection Mon 6/05/19 Tue 7/05/19 2 d

Fitout - Signage, HardwareFloor Finishes

Final Paint & Clean / FF & EBuilders Clean & Touch up / Defecting7/08/2019

Inclement Weather Delay Contingency 20/09/2019

COLES FITOUT BY OTHERS (12 W18/12/2019

LOT 2 ABOVE COLESEAST

LEVEL 1Set Out, Frames Primary Walls, High Level Sheet

Services Hl Rough In To Corridors & Mechanical Duct To ApartmentsInstall Sub Sills Measure Window Frames & Frames Lead-In Time

Set Out , Frame Secondary WallsInstall Windows

Balcony Wall CladdingBalcony Measure / Install Balustrade

Balcony MembraneMembrane Inspection

Balcony TileNoggins Set Out & Install For Trades

Services Rough-In In Wall & Ceilings (Inc Fire Caulk)Wall Linings / Ceiling Frame / Ceiling Linings / Stop & SandFirst Fix Carpentry Doors / Skirts To Carpet AreasPaint 1st Coat Defect Ceiling, Paint 2nd Coat CeilingsWet Areas Bottom Membrane, Screed, Top MembraneWaterproofing Inspection

Wet Areas Floor & Wall Tiling Inc. GroutMeasure Shower ScreensWet Areas - Install Joinery & Vanity Units

Install Shower Screens & Robes23/05/2019

Kitchen - Install JoineryMeasure Stone BenchtopsPatch & Float Floors

Install Bench TopsFit Off Hydraulic

Defect Walls & PatchTimber Flooring2nd Fix Carpentry

Lay Carpet / ProtectCorridors Complete Services Rough

Corridors Sheet Walls & CeilingsCorridors Initial Paint

Corridors DefectCorridors Final PaintCorridors Signage1st Clean (builders)

Final PaintFinal CaulkBuilders Inspection

Defect RectificationDefect CleanClient Inspection

Defect RectificationDefect Clean

LEVEL 2LEVEL 3

LEVEL 4LEVEL 5

WESTLEVEL 1

Set Out, Frames Primary Walls, High Level SheetServices Hl Rough In To Corridors & Mechanical Duct To ApartmentsInstall Sub Sills Measure Window Frames & Frames Lead-In Time

Set Out , Frame Secondary WallsInstall Windows

Balcony Wall CladdingBalcony Measure / Install Balustrade

Balcony MembraneMembrane Inspection

Balcony TileNoggins Set Out & Install For Trades

Services Rough-In In Wall & Ceilings (Inc Fire Caulk)Wall Linings / Ceiling Frame / Ceiling Linings / Stop & Sand

First Fix Carpentry Doors / Skirts To Carpet AreasPaint 1st Coat Defect Ceiling, Paint 2nd Coat CeilingsWet Areas Bottom Membrane, Screed, Top MembraneWaterproofing Inspection

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 9 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 29: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

726 Wet Areas Floor & Wall Tiling Inc. Grout Wed 8/05/19 Wed 22/05/19 10 d727 Measure Shower Screens Thu 23/05/19 Thu 23/05/19 1 d728 Wet Areas - Install Joinery & Vanity Units Fri 17/05/19 Tue 28/05/19 7 d729 Install Shower Screens & Robes Mon 3/06/19 Fri 7/06/19 5 d730 Kitchen - Install Joinery Wed 1/05/19 Tue 14/05/19 9 d731 Measure Stone Benchtops Wed 15/05/19 Wed 15/05/19 1 d732 Patch & Float Floors Wed 15/05/19 Fri 17/05/19 3 d733 Install Bench Tops Tue 28/05/19 Thu 30/05/19 3 d734 Fit Off Hydraulic Fri 31/05/19 Wed 5/06/19 4 d735 Defect Walls & Patch Wed 5/06/19 Thu 13/06/19 5 d736 Timber Flooring Wed 12/06/19 Tue 18/06/19 5 d737 2nd Fix Carpentry Mon 17/06/19 Thu 20/06/19 4 d738 Lay Carpet / Protect Thu 20/06/19 Wed 26/06/19 4 d739 Corridors Complete Services Rough Fri 31/05/19 Thu 6/06/19 5 d740 Corridors Sheet Walls & Ceilings Wed 5/06/19 Thu 13/06/19 5 d741 Corridors Initial Paint Fri 14/06/19 Wed 19/06/19 4 d742 Corridors Defect Thu 20/06/19 Tue 25/06/19 3 d743 Corridors Final Paint Wed 26/06/19 Fri 28/06/19 3 d744 Corridors Signage Mon 1/07/19 Tue 2/07/19 2 d745 1st Clean (builders) Thu 27/06/19 Mon 1/07/19 3 d746 Final Paint Wed 3/07/19 Fri 5/07/19 3 d747 Final Caulk Fri 5/07/19 Wed 10/07/19 3 d748 Builders Inspection Thu 11/07/19 Tue 16/07/19 4 d749 Defect Rectification Wed 17/07/19 Tue 23/07/19 4 d750 Defect Clean Wed 24/07/19 Mon 29/07/19 4 d751 Client Inspection Tue 30/07/19 Wed 31/07/19 2 d752 Defect Rectification Thu 1/08/19 Wed 7/08/19 4 d753 Defect Clean Thu 8/08/19 Tue 13/08/19 4 d754 LEVEL 2 Thu 28/03/19 Tue 27/08/19 93 d755 LEVEL 3 Wed 10/04/19 Fri 6/09/19 93 d756 LEVEL 4 Thu 2/05/19 Mon 23/09/19 93 d757 LEVEL 5 Fri 17/05/19 Wed 9/10/19 93 d758 MAKE GOOD WORKS AFTER CRANE & MATERIAL REMOVAL Wed 3/07/19 Wed 14/08/19 28 d759 Make Good Where Crane Removed Wed 3/07/19 Thu 1/08/19 20 d760 Make Good After Removal Man & Materials Hoist Tue 16/07/19 Wed 14/08/19 20 d761 PURCHASER DEFECTS Thu 1/08/19 Wed 9/10/19 45 d762 Lot 2 Fit Out & Finishes Complete Wed 9/10/19 Wed 9/10/19 0 d763 LOT 1 Wed 28/11/18 Thu 11/07/19 130 d764 GROUND LEVEL Wed 28/11/18 Mon 29/04/19 83 d765 LEVEL 1 Mon 10/12/18 Fri 31/05/19 98 d766 Set Out, Frames Primary Walls, High Level Sheet Mon 10/12/18 Fri 14/12/18 5 d767 Services Hl Rough In To Corridors & Mechanical Duct To Apartments Thu 13/12/18 Wed 9/01/19 8 d768 Install Sub Sills Measure Window Frames & Frames Lead-In Time Mon 17/12/18 Fri 11/01/19 8 d769 Set Out , Frame Secondary Walls Wed 19/12/18 Wed 16/01/19 9 d770 Install Windows Mon 14/01/19 Tue 22/01/19 7 d771 Balcony Wall Cladding Wed 23/01/19 Thu 31/01/19 5 d772 Balcony Measure / Install Balustrade Fri 1/02/19 Fri 8/02/19 6 d773 Balcony Membrane Tue 12/02/19 Mon 18/02/19 5 d774 Membrane Inspection Tue 19/02/19 Wed 20/02/19 2 d775 Balcony Tile Thu 21/02/19 Tue 5/03/19 8 d776 Noggins Set Out & Install For Trades Mon 14/01/19 Thu 17/01/19 4 d777 Services Rough-In In Wall & Ceilings (Inc Fire Caulk) Tue 15/01/19 Wed 30/01/19 10 d778 Wall Linings / Ceiling Frame / Ceiling Linings / Stop & Sand Wed 23/01/19 Mon 4/02/19 7 d779 First Fix Carpentry Doors / Skirts To Carpet Areas Wed 23/01/19 Mon 4/02/19 7 d780 Paint 1st Coat Defect Ceiling, Paint 2nd Coat Ceilings Wed 30/01/19 Wed 6/02/19 6 d781 Wet Areas Bottom Membrane, Screed, Top Membrane Tue 5/02/19 Tue 12/02/19 5 d782 Waterproofing Inspection Wed 13/02/19 Thu 14/02/19 2 d783 Wet Areas Floor & Wall Tiling Inc. Grout Fri 15/02/19 Mon 4/03/19 11 d784 Measure Shower Screens Tue 5/03/19 Tue 5/03/19 1 d785 Wet Areas - Install Joinery & Vanity Units Wed 27/02/19 Thu 7/03/19 7 d786 Prototype Apartment Complete Ready For Inspection Wed 13/03/19 Wed 13/03/19 0 d787 Install Shower Screens & Robes Fri 15/03/19 Thu 21/03/19 5 d788 Kitchen - Install Joinery Thu 7/02/19 Mon 18/02/19 7 d789 Measure Stone Benchtops Tue 19/02/19 Tue 19/02/19 1 d790 Patch & Float Floors Tue 19/02/19 Thu 21/02/19 3 d791 Install Bench Tops Mon 4/03/19 Wed 6/03/19 3 d792 Fit Off Hydraulic Thu 7/03/19 Thu 14/03/19 4 d793 Defect Walls & Patch Tue 19/03/19 Fri 22/03/19 4 d794 Timber Flooring Thu 21/03/19 Thu 28/03/19 6 d795 2nd Fix Carpentry Wed 27/03/19 Wed 3/04/19 5 d796 Lay Carpet / Protect Wed 3/04/19 Fri 5/04/19 3 d797 Corridors Complete Services Rough Thu 7/03/19 Thu 14/03/19 4 d798 Corridors Sheet Walls & Ceilings Wed 13/03/19 Mon 18/03/19 4 d799 Corridors Initial Paint Tue 19/03/19 Thu 21/03/19 3 d800 Corridors Defect Fri 22/03/19 Tue 26/03/19 3 d801 Corridors Final Paint Wed 27/03/19 Fri 29/03/19 3 d802 Corridors Signage Tue 2/04/19 Wed 3/04/19 2 d803 1st Clean (builders) Mon 8/04/19 Thu 11/04/19 4 d804 Final Paint Fri 12/04/19 Wed 17/04/19 4 d805 Final Caulk Wed 17/04/19 Mon 29/04/19 3 d806 Builders Inspection Tue 30/04/19 Fri 3/05/19 4 d807 Defect Rectification Mon 6/05/19 Thu 9/05/19 4 d

Wet Areas Floor & Wall Tiling Inc. GroutMeasure Shower ScreensWet Areas - Install Joinery & Vanity Units

Install Shower Screens & RobesKitchen - Install JoineryMeasure Stone BenchtopsPatch & Float Floors

Install Bench TopsFit Off Hydraulic

Defect Walls & PatchTimber Flooring2nd Fix Carpentry

Lay Carpet / ProtectCorridors Complete Services Rough

Corridors Sheet Walls & CeilingsCorridors Initial Paint

Corridors DefectCorridors Final PaintCorridors Signage1st Clean (builders)Final PaintFinal Caulk

Builders InspectionDefect Rectification

Defect CleanClient Inspection

Defect RectificationDefect Clean

LEVEL 2LEVEL 3

LEVEL 4LEVEL 5

MAKE GOOD WORKS AFTER CRANE & MATERIAL REMOVALMake Good Where Crane Removed

Make Good After Removal Man & Materials HoistPURCHASER DEFECTS9/10/2019

LOT 1GROUND LEVEL

LEVEL 1Set Out, Frames Primary Walls, High Level Sheet

Services Hl Rough In To Corridors & Mechanical Duct To ApartmentsInstall Sub Sills Measure Window Frames & Frames Lead-In TimeSet Out , Frame Secondary Walls

Install WindowsBalcony Wall Cladding

Balcony Measure / Install BalustradeBalcony MembraneMembrane Inspection

Balcony TileNoggins Set Out & Install For Trades

Services Rough-In In Wall & Ceilings (Inc Fire Caulk)Wall Linings / Ceiling Frame / Ceiling Linings / Stop & SandFirst Fix Carpentry Doors / Skirts To Carpet AreasPaint 1st Coat Defect Ceiling, Paint 2nd Coat Ceilings

Wet Areas Bottom Membrane, Screed, Top MembraneWaterproofing Inspection

Wet Areas Floor & Wall Tiling Inc. GroutMeasure Shower ScreensWet Areas - Install Joinery & Vanity Units

13/03/2019Install Shower Screens & Robes

Kitchen - Install JoineryMeasure Stone BenchtopsPatch & Float Floors

Install Bench TopsFit Off Hydraulic

Defect Walls & PatchTimber Flooring

2nd Fix Carpentry Lay Carpet / Protect

Corridors Complete Services RoughCorridors Sheet Walls & CeilingsCorridors Initial PaintCorridors DefectCorridors Final PaintCorridors Signage

1st Clean (builders)Final Paint

Final CaulkBuilders Inspection

Defect Rectification

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 10 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 30: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

ID Task Name Start Finish Dur.

808 Defect Clean Fri 10/05/19 Thu 16/05/19 4 d809 Client Inspection Fri 17/05/19 Mon 20/05/19 2 d810 Defect Rectification Tue 21/05/19 Fri 24/05/19 4 d811 Defect Clean Tue 28/05/19 Fri 31/05/19 4 d812 LEVEL 2 Wed 19/12/18 Thu 13/06/19 98 d813 LEVEL 3 Thu 17/01/19 Thu 27/06/19 98 d814 LEVEL 4 Fri 1/02/19 Thu 11/07/19 98 d815 MAKE GOOD WORKS AFTER CRANE & MATERIAL REMOVAL Fri 22/03/19 Thu 2/05/19 23 d816 Make Good Where Crane Removed Fri 22/03/19 Mon 29/04/19 20 d817 Make Good After Removal Man & Materials Hoist Wed 27/03/19 Thu 2/05/19 20 d818 PURCHASER DEFECTS Thu 9/05/19 Thu 11/07/19 40 d819 Lot 1 Fit Out & Finishes Complete Thu 11/07/19 Thu 11/07/19 0 d820 EXTERNAL & ROAD WORKS Mon 6/05/19 Wed 11/09/19 83 d821 Works to Nicholson Street Entry/Exit Mon 6/05/19 Thu 20/06/19 30 d822 Topping Screed to Pavement Levels Create Falls Fri 17/05/19 Mon 17/06/19 19 d823 Kerbs & Channels Thu 13/06/19 Mon 1/07/19 12 d824 Install Drainage Pits & Grates Thu 27/06/19 Mon 15/07/19 12 d825 Asphalt Toping to Village Avenue & Entry Off Nicholson Street Tue 16/07/19 Tue 30/07/19 10 d826 Set Out Car Park, Line Marking, Bollards, Trolley Bays Wed 31/07/19 Thu 15/08/19 11 d827 Install Light Poles & Lighting, Test & Commission Fri 16/08/19 Tue 3/09/19 12 d828 Paving Works Tue 18/06/19 Thu 1/08/19 30 d829 Construct Raised Planters Thu 18/07/19 Fri 9/08/19 15 d830 Complete Works to Entries to Buildings Fri 2/08/19 Thu 29/08/19 18 d831 Planting & Landscaping Works Tue 6/08/19 Wed 11/09/19 25 d832 External Works Complete Wed 11/09/19 Wed 11/09/19 0 d833 COMPLETION OF WORKS Thu 26/09/19 Wed 18/12/19 53 d834 Overall Inspections & Rectifications Thu 26/09/19 Mon 28/10/19 20 d835 Certificate of Occupancy Thu 24/10/19 Thu 24/10/19 0 d836 Separable Portion 3 Practical Completion (Net) Thu 31/10/19 Thu 31/10/19 0 d837 Inclement Weather Delay Contingency Fri 1/11/19 Wed 18/12/19 30 d838 Separable Portion 3 Practical Completion (Gross) Wed 18/12/19 Wed 18/12/19 0 d

Defect CleanClient InspectionDefect Rectification

Defect CleanLEVEL 2

LEVEL 3LEVEL 4

MAKE GOOD WORKS AFTER CRANE & MATERIAL REMOVALMake Good Where Crane RemovedMake Good After Removal Man & Materials Hoist

PURCHASER DEFECTS11/07/2019

EXTERNAL & ROAD WORKSWorks to Nicholson Street Entry/Exit

Topping Screed to Pavement Levels Create FallsKerbs & Channels

Install Drainage Pits & GratesAsphalt Toping to Village Avenue & Entry Off Nicholson Street

Set Out Car Park, Line Marking, Bollards, Trolley BaysInstall Light Poles & Lighting, Test & Commission

Paving WorksConstruct Raised Planters

Complete Works to Entries to BuildingsPlanting & Landscaping Works11/09/2019

COMPLETION OF WORKSOverall Inspections & Rectifications24/10/2019

31/10/2019Inclement Weather Delay Contingen18/12/2019

-9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Date : 28 August 2017Planner : DLHRevision : Rev B

EAST BRUNSWICK VILLAGE - STAGE 1 DEVELOPMENT127-139 NICHOLSON STREET, EAST BRUNSWICK

CONTRACT PROGRAMME

Print Date : Fri 13/04/18 Page 11 of 12

PROGRAMME IS BASED ON VICTORIAN 5 DAY (CFMEU) BUILDER'S CALENDAR

File: East Brunswick Village Head Contract Programme - Rev B

Page 31: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 20 of 24 East Brunswick Village: Stage 1

APPENDIX B: PROJECT DOCUMENT REGISTER

Page 32: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register

EBV - PROJECT DOCUMENT REGISTER

DOCOMENT NO. TITLE/DESCRIPTION REVISION

Architectural - General

TP01.15 Lower Basement 2 Construction Demarcation Plan A

TP01.16 Upper Basement 1 Construction Demarcation Plan A

TP01.17 Ground Floor Construction Demarcation Plan A

1512_1513_1514 Specification Basement Lot 1 Lot 2 A

VJW170332 Novas Door Hardware Schedule (Stage 1 including lots 1 and 2) R3

VJW170332 Novas Door Hardware Legend (Stage 1 including lots 1 and 2) R3

Architectural - Basement Levels

CD0.00.01 Cover Sheet A

CD0.00.02 Standards A

CD0.01.01 Lower Basement B2 Plan 1/2 B

CD0.01.02 Lower Basement B2 Plan 2/2 A

CD0.01.03 Upper Basement B1 Plan 1/2 E

CD0.01.04 Upper Basement B1 Plan 2/2 B

CD0.01.05 Ground Floor External Works 1/2 D

CD0.01.06 Ground Floor External Works 2/2 D

CD0.02.01 Lower Basement B2 RCP 1/2 A

CD0.02.02 Lower Basement B2 RCP 2/2 A

CD0.02.03 Upper Basement B1 RCP 1/2 A

CD0.02.04 Upper Basement B1 RCP 2/2 A

CD0.04.01 1:200 Sections A

CD0.04.02 1:200 Sections A

CD0.04.03 1:200 Sections A

CD0.04.04 1:200 Sections A

CD0.06.01 Substation Details A

CD0.06.02 Details A

CD0.07.01 1:5 Typical Wall Types B

CD0.08.01 Amenity Details A

CD0.08.02 Amenity Details A

CD0.11.05 Ground Floor Slab Setout Plan 1/2 A

CD0.11.06 Ground Floor Slab Setout Plan 2/2 A

CD0.12.01 Stair Details A

CD0.12.02 Stair Details A

CD0.12.03 Stair Details A

CD0.12.04 Lift Details A

CD0.12.05 Lift Details A

1512_SC01a Door Type Schedule A

1512_SC01b Door Allocation Schedule B

1512_SC02 External Materials and Finishes Schedule C

1512_SC03 Internal Materials and Finishes Schedule B

1512_SC04 Basement Retail Amenities A

1512_SC05 Joinery Hardware Schedule A

Architectural - Building A

CD1.00.00 Cover Page A

CD1.00.01 Standards A

CD1.00.02 Site Plan - Lot 1 A

CD1.01.01 Ground Floor Plan C

Page 33: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register CD1.01.02 1st Floor Plan B

CD1.01.03 2nd Floor Plan B

CD1.01.04 3rd Floor Plan B

CD1.01.05 4th Floor Plan B

CD1.01.06 Roof Plans (5th-6th Floor) B

CD1.01.07 Canopy Plan A

CD1.02.01 Ground Floor RCP B

CD1.02.02 1st Floor RCP B

CD1.02.03 2nd Floor RCP A

CD1.02.04 3rd Floor RCP A

CD1.02.05 4th Floor RCP A

CD1.02.06 Roof (5th Floor) RCP A

CD1.03.01 Elevations B

CD1.03.02 Elevations B

CD1.04.01 Sections A

CD1.04.02 Sections B

CD1.04.03 Sections A

CD1.04.04 Sections A

CD1.04.05 Sections B

CD1.04.06 Sections A

CD1.05.01 Window Schedule - Type List D

CD1.05.02 Window Schedule C

CD1.05.03 Window Schedule C

CD1.06.01 Details 1_10 A

CD1.06.02 Details 1_10 A

CD1.06.03 Details Balustrades & Screens B

CD1.07.01 1:5 Typical Wall Types B

CD1.08.01.1 Bathroom Details A

CD1.08.01.2 Bathroom Details A

CD1.08.01.3 Bathroom Details A

CD1.08.01.4 Bathroom Details A

CD1.08.01.5 Bathroom Details A

CD1.08.01.6 Bathroom Details A

CD1.08.01.7 Bathroom Details A

CD1.08.01.8 Bathroom Details A

CD1.08.01.9 Bathroom Details A

CD1.08.01.10 Bathroom Details B

CD1.08.02.01 Laundry Details A

CD1.09.01.01 Kitchen Details A

CD1.09.01.02 Kitchen Details A

CD1.09.01.03 Kitchen Details A

CD1.09.01.04 Kitchen Details A

CD1.09.01.05 Kitchen Details A

CD1.09.01.06 Kitchen Details A

CD1.09.01.07 Kitchen Details A

CD1.09.01.08 Kitchen Details A

CD1.09.02.01 Robe, Cupboard & Desk Details A

CD1.10.01 Unit Details A

CD1.10.02 Unit Details A

CD1.10.03 Unit Details A

CD1.10.04 Unit Details A

CD1.10.05 Unit Details A

CD1.12.01 Stair Details A

CD1.12.02 Stair Details B

CD1.12.03 Stair Details A

Page 34: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register CD1.12.04 Lift Details A

CD1.13.01 Lobby Details A

CD1.13.02 Lobby Details A

CD1.13.03 Lobby Details A

CD1.13.04 Lobby Details B

CD1.14.01 External Works 1st Floor Plan B

CD1.14.02 External Works Roof Plan B

CD1.14.03 External Works Details B

1513_SC01a Door Allocation Schedule B

1513_SC01b Door Type Schedule B

1513_SC02 External Materials & Finishes Schedule C

1513_SC03 Internal Materials & Finishes Schedule C

1513_SC04 Fixtures and Fittings Schedule C

1513_SC05 Joinery Hardware Schedule B

1513 Unit Matrix C

Architectural - Buildings B & C

CD2.00.00 Cover Page A

CD2.00.01 Standards A

CD2.00.02 Site Plan - Lot 2 A

CD2.01.01 Ground Floor Plan D

CD2.01.02 Mezzanine Plan D

CD2.01.03 1st Floor Plan C

CD2.01.04 2nd Floor Plan C

CD2.01.05 3rd Floor Plan C

CD2.01.06 4th Floor Plan C

CD2.01.07 5th Floor Plan C

CD2.01.08 Roof Plans (6th-7th Floor) D

CD2.02.01 Ground Floor RCP A

CD2.02.02 Mezzanine Floor RCP A

CD2.02.03 1st Floor RCP A

CD2.02.04 2nd Floor RCP A

CD2.02.05 3rd Floor RCP A

CD2.02.06 4th Floor RCP A

CD2.02.07 5th Floor RCP A

CD2.02.08 Roof (6th Floor) RCP A

CD2.03.01 Elevations B

CD2.03.02 Elevations B

CD2.04.01 Sections A

CD2.04.02 Sections A

CD2.04.03 Sections A

CD2.04.04 Sections A

CD2.04.05 Sections A

CD2.04.06 Sections A

CD2.04.07 Sections A

CD2.04.08 Sections A

CD2.04.09 Sections A

CD2.04.10 Sections A

CD2.05.01 Window Schedule - Type List C

CD2.05.02 Window Schedule C

CD2.05.03 Window Schedule B

CD2.05.04 Window Schedule B

CD2.06.01 Details 1:10 A

CD2.06.02 Details 1:10 A

CD2.06.03 Details 1:10 A

CD2.06.04 Details 1:10 A

CD2.06.05 Details Balustrades & Screens B

Page 35: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register CD2.07.01 1:5 Typical Wall Types B

CD2.08.01.01 Bathroom Details A

CD2.08.01.02 Bathroom Details A

CD2.08.01.03 Bathroom Details A

CD2.08.01.04 Bathroom Details A

CD2.08.01.05 Bathroom Details A

CD2.08.01.06 Bathroom Details A

CD2.08.01.07 Bathroom Details A

CD2.08.01.08 Bathroom Details A

CD2.08.01.09 Bathroom Details A

CD2.08.02.01 Laundry Details A

CD2.08.02.02 Laundry Details A

CD2.09.01.01 Kitchen Details A

CD2.09.01.02 Kitchen Details A

CD2.09.01.03 Kitchen Details A

CD2.09.01.04 Kitchen Details A

CD2.09.01.05 Kitchen Details A

CD2.09.01.06 Kitchen Details A

CD2.09.01.07 Kitchen Details A

CD2.09.01.08 Kitchen Details A

CD2.09.02.01 Robe & Cupboard Details A

CD2.09.03.01 Study Details A

CD2.10.01 Unit Details A

CD2.10.02 Unit Details A

CD2.10.03 Unit Details A

CD2.10.04 Unit Details A

CD2.10.05 Unit Details A

CD2.10.06 Unit Details A

CD2.10.07 Unit Details A

CD2.10.08 Unit Details A

CD2.12.01 Stair Details A

CD2.12.02 Stair Details A

CD2.12.03 Stair Details B

CD2.12.04 Stair Details A

CD2.12.05 Stair Details B

CD2.12.06 Lift Details A

CD2.12.07 Lift Details B

CD2.12.08 Lift Details A

CD2.12.09 Travelator Details A

CD2.13.01 West Residential Lobby Details (Ground Floor) A

CD2.13.02 East Residential Lobby Details (Ground Floor) B

CD2.13.03 Smoke Lobby (Basement 2) A

CD2.13.04 Lift Shafts (Basement 1 & 2) A

CD2.13.05 Travelator Lobby (Basement 1) A

CD2.13.06 Travelator Lobby (Ground Floor) A

CD2.13.07 Travelator Lobby (Basement 1 & Ground Floor) A

CD2.13.08 Rooftop Common Rooms B

CD2.13.09 Typical Corridor A

CD2.14.01 External Works 1st Floor Plan B

CD2.14.02 External Works Roof Plan B

CD2.14.03 External Works Details A

CD2.14.04 External Works Details B

CD2.15.01 Coles Lower and Upper Floor Plans B

CD2.15.02 Coles Ground Floor Plan B

CD2.15.03 Coles Lower and Upper Setout Plans B

CD2.15.04 Coles Ground Floor Setout B

CD2.15.05 Coles Lower and Upper Floor RCPS B

CD2.15.06 Coles Ground Floor RCP B

Page 36: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register CD2.15.09 Coles Mezzanine Floor RCP B

CD2.15.10 Coles Basement 1 Floor Finish Plan B

CD2.15.11 Coles Ground Floor Finishes Plan B

CD2.15.12 Coles Mezzanine Floor Finishes Plan B

CD2.15.13 Coles Section and Elevations B

CD2.15.19 Coles Equipment Schedules B

CD2.15.20 Coles Finishes Schedules B

CD2.15.21 Coles Door Schedule B

1514_SC01a Door Allocation Schedule B

1514_SC01b Door Type Schedule B

1514_SC02 External Materials & Finishes Schedule C

1514_SC03 Internal Materials & Finishes Schedule C

1514_SC04 Fixtures & Fittings Schedule B

1514_SC05 Joinery Hardware Schedule B

1514 Unit Matrix C

Civil

11229.1 Civil Drawings Road and Drainage

111229.1TD01 Locality Plan, Notes, Drawing Index and Typical Details B

111229.1TD02 Typical Sections B

111229.1TD03 Typical Details - Sheet 01 B

111229.1TD04 Typical Details - Sheet 02 B

111229.1LP01 Layout Plan B

111229.1DP01 Detail Plan - Sheet 01 B

111229.1DP02 Detail Plan - Sheet 02 B

111229.1SDP01 Setout Plan - Sheet 01 B

111229.1SDP02 Setout Plan - Sheet 02 B

111229.1ID01 Intersection Details - Sheet 01 B

111229.1ID02 Intersection Details - Sheet 02 B

111229.1ID03 Intersection Details - Sheet 03 B

111229.1ID04 Intersection Details - Sheet 04 B

111229.1ID05 Intersection Details - Sheet 05 B

111229.1ID06 Intersection Details - Sheet 06 B

111229.1DP01 Detail Plan - Sheet 01 B

111229.1LM01 Line Marking and Signage B

111229.1LS01 Longitudinal Sections - Sheet 1 B

111229.1LS02 Longitudinal Sections - Sheet 2 B

111229.1XS01 Cross Sections - Sheet 01 B

111229.1XS02 Cross Sections Sheet 02 B

111229.1XS03 Cross Sections Sheet 03 B

111229.1XS04 Cross Sections Sheet 04 B

111229.1XS05 Cross Sections Sheet 05 B

111229.1XS06 Cross Sections Sheet 06 B

111229.1XS07 Cross Sections Sheet 07 B

111229.1DRP01 Ground Level Drainage Plan - Sheet 01 B

111229.1DRP02 Ground Level Drainage Plan - Sheet 02 B

111229.1BDP01 Basement Level 1 Drainage Plan - Sheet 01 B

111229.1BDP02 Basement Level 1 Drainage Plan - Sheet 02 B

111229.1BDP03 Basement Level 2 Drainage Plan - Sheet 01 B

111229.1BDP04 Basement Level 2 Drainage Plan - Sheet 02 B

111229.1EF01 Existing Features Plan B

111229.1PK01 Carpark Plan A

Structural

S000 Drawing Index 5

S001 General Notes 3

S100 Site Retention And Bulk Excavation Plan 2

S101 Site Retention And Bulk Excavation Part Plan - Sheet 1 1

S102 Site Retention And Bulk Excavation Part Plan - Sheet 2 2

S103 Site Retention And Bulk Excavation Part Plan - Sheet 3 2

S104 Site Retention And Bulk Excavation Part Plan - Sheet 4 1

S105 Site Retention And Bulk Excavation Part Plan - Sheet 5 1

S106 Retaining Wall Elevations - Sheet 1 1

S107 Retaining Wall Elevations - Sheet 2 1

S108 Retaining Wall Elevations - Sheet 3 2

Page 37: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register S109 Retaining Wall Elevations - Sheet 4 1

S110 Retaining Wall Elevations - Sheet 5 1

S111 Retaining Wall Elevations - Sheet 6 1

S112 Retaining Wall Sections - Sheet 1 1

S113 Retaining Wall Sections - Sheet 2 1

S114 Retaining Wall Sections - Sheet 3 1

S115 Retaining Wall Sections - Sheet 4 1

S116 Retaining Wall Sections - Sheet 5 2

S117 Site Retention Details 2

S200 Footing Layout Plan A

S201 Footing Layout Part Plan - Sheet 1 A

S202 Footing Layout Part Plan - Sheet 2 B

S203 Footing Layout Part Plan - Sheet 3 A

S204 Footing Layout Part Plan - Sheet 4 A

S205 Footing Layout Part Plan - Sheet 5 A

S206 Footing Layout Part Plan - Sheet 6 A

S207 Footing Layout Part Plan - Sheet 7 A

S208 Footing Layout Part Plan - Sheet 8 A

S209 Footing Layout Part Plan - Sheet 9 A

S210 Footing Layout Part Plan - Sheet 10 A

S220 Footing Details - Sheet 1 A

S221 Footing Details - Sheet 2 A

S200 Footing Layout Plan A

S221 Footing Details - Sheet 2 A

S300 Lower Basement Plan A

S301 Lower Basement Part Plan - Sheet 1 A

S302 Lower Basement Part Plan - Sheet 2 B

S303 Lower Basement Part Plan - Sheet 3 A

S304 Lower Basement Part Plan - Sheet 4 B

S305 Lower Basement Part Plan - Sheet 5 B

S306 Lower Basement Part Plan - Sheet 6 A

S307 Lower Basement Part Plan - Sheet 7 A

S308 Lower Basement Part Plan - Sheet 8 A

S309 Lower Basement Part Plan - Sheet 9 A

S310 Lower Basement Part Plan - Sheet 10 B

S320 Upper Basement Plan A

S321 Upper Basement Part Plan - Sheet 1 A

S322 Upper Basement Part Plan - Sheet 2 B

S323 Upper Basement Part Plan - Sheet 3 B

S324 Upper Basement Part Plan - Sheet 4 B

S325 Upper Basement Part Plan - Sheet 5 B

S326 Upper Basement Part Plan - Sheet 6 A

S327 Upper Basement Part Plan - Sheet 7 A

S328 Upper Basement Part Plan - Sheet 8 B

S329 Upper Basement Part Plan - Sheet 9 B

S330 Upper Basement Part Plan - Sheet 10 A

S331 Ramp Structure Part Plans A

S332 Ramp Structure Details A

S340 Ground Floor Plan A

S341 Ground Floor Part Plan - Sheet 1 B

S342 Ground Floor Part Plan - Sheet 2 D

S343 Ground Floor Part Plan - Sheet 3 D

S344 Ground Floor Part Plan - Sheet 4 B

S345 Ground Floor Part Plan - Sheet 5 D

S346 Ground Floor Part Plan - Sheet 6 B

S347 Ground Floor Part Plan - Sheet 7 B

S348 Ground Floor Part Plan - Sheet 8 B

S349 Ground Floor Part Plan - Sheet 9 B

S350 Ground Floor Part Plan - Sheet 10 B

S400 Lot 1 - Level 1 Floor Plan C

S401 Lot 1 - Level 2 Floor Plan A

S402 Lot 1 - Level 3 Floor Plan A

Page 38: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register S403 Lot 1 - Level 4 Floor Plan A

S404 Lot 1 - Roof Floor Plan A

S410 Lot 2 - Mezzanine Floor Plan - Sheet 1 B

S411 Lot 2 - Mezzanine Floor Plan - Sheet 2 C

S412 Lot 2 - Level 1 Floor Plan - Sheet 1 C

S413 Lot 2 - Level 1 Floor Plan - Sheet 2 C

S414 Lot 2 - Level 2 Floor Plan - Sheet 1 B

S415 Lot 2 - Level 2 Floor Plan - Sheet 2 A

S416 Lot 2 - Level 3 Floor Plan - Sheet 1 B

S417 Lot 2 - Level 3 Floor Plan - Sheet 2 A

S418 Lot 2 - Level 4 Floor Plan - Sheet 1 B

S419 Lot 2 - Level 4 Floor Plan - Sheet 2 A

S420 Lot 2 - Level 5 Floor Plan - Sheet 1 B

S421 Lot 2 - Level 5 Floor Plan - Sheet 2 A

S422 Lot 2 - Roof Floor Plan - Sheet 1 C

S423 Lot 2 - Roof Floor Plan - Sheet 2 B

S500 Typical Insitu Column Details A

S510 Column Schedules A

S600 Precast Panel Details B

S601 Insitu & AFS Wall Details A

S610 Basement - Precast Elevations - Sheet 1 A

S611 Basement - Precast Elevations - Sheet 2 A

S612 Basement - Precast Elevations - Sheet 3 A

S613 Basement - Precast Elevations - Sheet 4 A

S614 Basement - Precast Elevations - Sheet 5 A

S615 Basement - Precast Elevations - Sheet 6 A

S616 Basement - Precast Elevations - Sheet 7 A

S617 Basement - Precast Elevations - Sheet 8 A

S620 Lot 1 - Precast Elevations - Sheet 1 B

S621 Lot 1 - Precast Elevations - Sheet 2 B

S622 Lot 1 - Precast Elevations - Sheet 3 B

S623 Lot 1 - Precast Elevations - Sheet 4 B

S624 Lot 1 - Precast Elevations - Sheet 5 B

S625 Lot 1 - Precast Elevations - Sheet 6 B

S626 Lot 1 - Precast Elevations - Sheet 7 B

S627 Lot 1 - Precast Elevations - Sheet 8 B

S628 Lot 1 - Precast Elevations - Sheet 9 B

S629 Lot 1 - Precast Elevations - Sheet 10 A

S640 Lot 2 - Precast Elevations - Sheet 1 B

S641 Lot 2 - Precast Elevations - Sheet 2 B

S642 Lot 2 - Precast Elevations - Sheet 3 B

S643 Lot 2 - Precast Elevations - Sheet 4 B

S644 Lot 2 - Precast Elevations - Sheet 5 B

S645 Lot 2 - Precast Elevations - Sheet 6 B

S646 Lot 2 - Precast Elevations - Sheet 7 B

S647 Lot 2 - Precast Elevations - Sheet 8 B

S648 Lot 2 - Precast Elevations - Sheet 9 B

S649 Lot 2 - Precast Elevations - Sheet 10 B

S650 Lot 2 - Precast Elevations - Sheet 11 B

S651 Lot 2 - Precast Elevations - Sheet 12 B

S652 Lot 2 - Precast Elevations - Sheet 13 B

S653 Lot 2 - Precast Elevations - Sheet 14 B

S654 Lot 2 - Precast Elevations - Sheet 15 B

S655 Lot 2 - Precast Elevations - Sheet 16 B

S656 Lot 2 - Precast Elevations - Sheet 17 B

S700 Typical Concrete Slab on Ground Details A

S710 Typical Concrete Stair Details A

S720 Typical Concrete Details - Sheet 1 A

S721 Typical Concrete Details - Sheet 2 A

S730 Concrete Sections - Sheet 1 A

Page 39: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register S800 Blockwork Details A

S810 Typical Steelwork Details 1

S820 Lot 1 - Canopy Plan P2

S821 Lot 1 - Roof Framing Plans P2

S830 Lot 2 - Canopy Plans P2

S831 Lot 2 - Planter Frames P3

S832 Lot 2 - Roof Framing Plans P2

S833 Lot 2 - South Screen Frames P2

S834 Lot 2 - Mezzanine & Level 1 Steelworks P2

S835 Lot 2 - Level 5 Framing Plan P2

Electrical

E000 Drawing Index, Locality Plan, General Notes & Legend Of Symbols T2

E010 Ground Floor Overall Electrical Layout T3

E011 Upper Basement B1 Overall Electrical Layout T2

E012 Lower Basement B2 Overall Electrical Layout T2

E020 Ground Floor Car Park System Layout T3

E021 Upper Basement B1 Car Park System Layout T3

E022 Car Park System Details & Schematic T3

E100 Lower Basement B2 - Zone A - Lighting, Fire, Power, Comms & Security Layout T2

E101 Lower Basement B2 - Zone B - Lighting, Fire, Power, Comms & Security Layout T2

E102 Lower Basement B2 - Zone C - Lighting, Fire, Power, Comms & Security Layout T2

E103 Lower Basement B2 - Zone D - Lighting, Fire, Power, Comms & Security Layout T2

E110 Upper Basement B1 - Zone A - Lighting, Fire, Power, Comms & Security Layout T2

E111 Upper Basement B1 - Zone B - Lighting, Fire, Power, Comms & Security Layout T2

E112 Upper Basement B1 - Zone C- Lighting, Fire, Power, Comms & Security Layout T2

E113 Upper Basement B1 - Zone D - Lighting, Fire, Power, Comms & Security Layout T2

E310 Lot 1 - Ground Floor - Lighting & Fire Detection Layout T3

E311 Lot 1 - First Floor - Lighting & Fire Detection Layout T2

E312 Lot 1 - Second Floor - Lighting & Fire Detection Layout T2

E313 Lot 1 - Third Floor - Lighting & Fire Detection Layout T2

E314 Lot 1 - Fourth Floor - Lighting & Fire Detection Layout T2

E315 Lot 1 - Roof (Fifth Floor) - Lighting & Fire Detection Layout T2

E320 Lot 2 - Ground Floor - Lighting & Fire Detection Layout T3

E320M Lot 2 - Mezzanine Floor - Lighting & Fire Detection Layout T2

E321 Lot 2 - First Floor - Lighting & Fire Detection Layout T2

E322 Lot 2 - Second Floor - Lighting & Fire Detection Layout T2

E323 Lot 2 - Third Floor - Lighting & Fire Detection Layout T2

E324 Lot 2 - Fourth Floor - Lighting & Fire Detection Layout T2

E325 Lot 2 - Fifth Floor - Lighting & Fire Detection Layout T2

E326 Lot 2 - Roof (Sixth Floor) - Lighting & Fire Detection Layout T2

E410 Lot 1 - Ground Floor - Power, Communications & Security Layout T2

E411 Lot 1 - First Floor - Power, Communications & Security Layout T2

E412 Lot 1 - Second Floor - Power, Communications & Security Layout T2

E413 Lot 1 - Third Floor - Power, Communications & Security Layout T2

E414 Lot 1 - Fourth Floor - Power, Communications & Security Layout T2

E415 Lot 1 - Roof (Fifth Floor) - Power, Communications & Security Layout T2

E420 Lot 2 - Ground Floor - Power, Communications & Security Layout T3

E420M Lot 2 - Mezzanine Floor - Power, Communications & Security Layout T2

E421 Lot 2 - First Floor - Power, Communications & Security Layout T2

E422 Lot 2 - Second Floor - Power, Communications & Security Layout T2

E423 Lot 2 - Third Floor - Power, Communications & Security Layout T2

E424 Lot 2 - Fourth Floor - Power, Communications & Security Layout T2

E425 Lot 2 - Fifth Floor - Power, Communications & Security Layout T2

E426 Lot 2 - Roof (Sixth Floor) - Power, Communications & Security Layout T2

E600 Main Switchboard Schematic - Sheet 1 T3

E601 Main Switchboard Schematic - Sheet 2 T3

E602 Schematics & Details - Sheet 3 T2

E603 Schematics & Details - Sheet 4 T2

E604 Schematics & Details - Sheet 5 T2

Page 40: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register E605 Schematics & Details - Sheet 6 T2

Electrical Services specification T2

Hydraulic

H000 Drawing Index, Locality Plan And Legend Of Symbols T2

H100 Lower Basement B2 - Zone A - Sewer Layout T1

H110 Upper Basement B1 - Zone A - Sewer, Stormwater, Water & Gas Layout T2

H111 Upper Basement B1 - Zone B - Sewer, Stormwater, Water & Gas Layout T2

H310 Lot 1 - Ground Floor - Sanitary Drainage & Stormwater Layout T2

H311 Lot 1 - First Floor - Sanitary Drainage & Stormwater Layout T2

H312 Lot 1 - Second Floor - Sanitary Drainage & Stormwater Layout T2

H313 Lot 1 - Third Floor - Sanitary Drainage & Stormwater Layout T2

H314 Lot 1 - Fourth Floor - Sanitary Drainage & Stormwater Layout T2

H315 Lot 1 - Roof (Fifth Floor) - Sanitary Drainage & Stormwater Layout T2

H320 Lot 2 - Ground Floor - Sanitary Drainage & Stormwater Layout T2

H320M Lot 2 - Mezzanine Floor - Sanitary Drainage & Stormwater Layout T2

H321 Lot 2 - First Floor - Sanitary Drainage & Stormwater Layout T2

H322 Lot 2 - Second Floor - Sanitary Drainage & Stormwater Layout T2

H323 Lot 2 - Third Floor - Sanitary Drainage & Stormwater Layout T2

H324 Lot 2 - Fourth Floor - Sanitary Drainage & Stormwater Layout T2

H325 Lot 2 - Fifth Floor - Sanitary Drainage & Stormwater Layout T2

H326 Lot 2 - Roof (Sixth Floor) - Sanitary Drainage & Stormwater Layout T2

H410 Lot 1 - Ground Floor - Water & Gas Layout T2

H411 Lot 1 - First Floor - Water & Gas Layout T2

H412 Lot 1 - Second Floor - Water & Gas Layout T2

H413 Lot 1 - Third Floor - Water & Gas Layout T2

H414 Lot 1 - Fourth Floor - Water & Gas Layout T2

H415 Lot 1 - Roof (Fifth) Floor - Water & Gas Layout T2

H420 Lot 2 - Ground Floor - Water & Gas Layout T2

H421 Lot 2 - First Floor - Water & Gas Layout T2

H422 Lot 2 - Second Floor - Water & Gas Layout T2

H423 Lot 2 - Third Floor - Water & Gas Layout T2

H424 Lot 2 - Fourth Floor - Water & Gas Layout T2

H425 Lot 2 - Fifth Floor - Water & Gas Layout T2

H426 Lot 2 - Roof (Sixth) Floor - Water & Gas Layout T2

H500 Cold Water Schematics T2

H501 Gas Schematics T2

H502 Hot Water Schematics T2

H503 NC Schematics T2

Hydraulic Services Specification T2

Mechanical

M000 Drawing Index, General Notes & Legend Of Symbols T2

M100 Lot 1 & 2 Lower Basement B2 Layout T2

M101 Lot 1 & 2 Upper Basement B1 Layout T2

M102 Lot 1 & 2 Ground Floor Site Layout T2

M210 Lot 1 Typical Apartments Sheet 1 Of 3 T2

M211 Lot 1 Typical Apartments Sheet 2 Of 3 T2

M212 Lot 1 Typical Apartments Sheet 3 Of 3 T2

M220 Lot 2 Typical Apartment Sheet 1 Of 3 T2

M221 Lot 2 Typical Apartments Sheet 2 Of 3 T2

M222 Lot 2 Typical Apartment Sheet 3 Of 3 T2

M310 Lot 1 Ground Level Layout T2

M311 Lot 1 First Floor Layout T2

M312 Lot 1 Second Floor Layout T2

M313 Lot 1 Third Floor Layout T2

M314 Lot 1 Fourth Floor Layout T2

M315 Lot 1 Roof (5th Floor) Layout T2

Page 41: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register M321 Lot 2 First Floor Layout T2

M322 Lot 2 Second Floor Layout T2

M323 Lot 2 Third Floor Layout T2

M324 Lot 2 Fourth Floor Layout T2

M325 Lot 2 Fifth Floor Layout T2

M326 Lot 2 Roof (6th Floor) Layout T2

M700 Stage 1 Coles Basement 1 and 2 Layouts T3

M701 Stage 1 Coles Ground Floor Layout T3

M702 Stage 1 Coles Mezzanine Level Layout T3

M703 Stage 1 Coles Roof Layout T2

Mechanical Services Specification T2

Fire

F000 Drawing Index, Legend Of Symbols & General Notes T3

F001 Booster, Hydrant, Hosereel Detail and Hydrant & Hosereel Schematic T1

F002 Stage 1 Site Plan Sprinkler Main Layout T2

F100 Lower Basement 2 - Hydrant & Hose Reel Layout - Part 1 Of 4 T2

F101 Lower Basement 2 - Hydrant & Hose Reel Layout - Part 2 Of 4 T2

F102 Lower Basement 2 - Hydrant & Hose Reel Layout - Part 3 Of 4 T2

F103 Lower Basement 2 - Hydrant & Hose Reel Layout - Part 4 Of 4 T2

F110 Lower Basement 2 - Sprinkler Layout - Part 1 Of 4 T2

F111 Lower Basement 2 - Sprinkler Layout - Part 2 Of 4 T3

F112 Lower Basement 2 - Sprinkler Layout - Part 3 Of 4 T2

F113 Lower Basement 2 - Sprinkler Layout - Part 4 Of 4 T3

F200 Upper Basement 1 - Hydrant & Hose Reel Layout - Part 1 Of 4 T2

F201 Upper Basement 1 - Hydrant & Hose Reel Layout - Part 2 Of 4 T2

F202 Upper Basement 1 - Hydrant & Hose Reel Layout - Part 3 Of 4 T2

F203 Upper Basement 1 - Hydrant & Hose Reel Layout - Part 4 Of 4 T2

F210 Upper Basement 1 - Sprinkler Layout - Part 1 Of 4 T2

F211 Upper Basement 1 - Sprinkler Layout - Part 2 Of 4 T2

F212 Upper Basement 1 - Sprinkler Layout - Part 3 Of 4 T2

F213 Upper Basement 1 - Sprinkler Layout - Part 4 Of 4 T2

F310 Lot 1 - Ground Floor - Hydrant & Sprinkler Layout T4

F311 Lot 1 - First Floor - Hydrant & Sprinkler Layout T3

F312 Lot 1 - Second Floor - Hydrant & Sprinkler Layout T3

F313 Lot 1 - Third Floor - Hydrant & Sprinkler Layout T3

F314 Lot 1 - Fourth Floor - Hydrant & Sprinkler Layout T3

F315 Lot 1 - Roof (Fifth Floor) - Hydrant & Sprinkler Layout T3

F320 Lot 2 - Ground Floor - Hydrant & Sprinkler Layout T3

F321 Lot 2 - First Floor - Hydrant & Sprinkler Layout T3

F322 Lot 2 - Second Floor - Hydrant & Sprinkler Layout T3

F323 Lot 2 - Third Floor - Hydrant & Sprinkler Layout T3

F324 Lot 2 - Fourth Floor - Hydrant & Sprinkler Layout T3

F325 Lot 2 - Fifth Floor - Hydrant & Sprinkler Layout T3

F326 Lot 2 - Roof (Sixth Floor) - Hydrant & Sprinkler Layout T3

- Fire Protection Services Specification T1

Vertical Transportation

20170509_1614 Vertical Transportation Specification T1

Coles

C7997-SK06 General Layout (Indicative) -

Liquorland Design Brief May 2016

Coles 2016 Design Kit (Brief) Issue 92

Coles 2015 Design Brief - Multi Level and Mixed Use Site Appendix B (Oct 15)

Coles (Polished) Concrete Specification Rev B 5/09/12

Coles Supermarket Standard Details Jan 2016

Coles Blueprint Typicals and Concepts Jan 2016

Miscellaneous Coles Docs

Page 42: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 – Project Document Register Landscaping

EBV_127 Podium Plants

EBV_127 Rooftop Plants

EBV_Piazza Plants

EBV_VillageAve_PodiumPlants

EBV_VillageAve_RooftopPlants

Page 43: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 21 of 24 East Brunswick Village: Stage 1

APPENDIX C: TRAFFIC MANAGMENT PLAN

Page 44: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

16 April 2018 Cardno i

Construction Traffic Management - Detailed Report

Nicholson Street, Brunswick East V180227

Prepared for Hacer Group Pty Ltd 16 April 2018

Page 45: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

© Cardno. Copyright in the whole and every part of this document belongs to Cardno and may not be used, sold, transferred, copied or reproduced in whole or in part in any manner or form or in or on any media to any person other than by agreement with Cardno.

This document is produced by Cardno solely for the benefit and use by the client in accordance with the terms of the engagement. Cardno does not and shall not assume any responsibility or liability whatsoever to any third party arising out of any use or reliance by any third party on the content of this document.

V180227 | 16 April 2018 | Commercial in Confidence ii

Contact Information Document Information

Cardno Victoria Pty Ltd

ABN 47 106 610 913

Level 4

501 Swanston Street

Melbourne 3000

Australia

www.cardno.com

Phone +61 3 8415 7777

Fax +61 3 8415 7788

Prepared for Hacer Group Pty Ltd

Project Name Nicholson Street, Brunswick

East

File Reference V180227-REP001-F03.docx

Job Reference V180227

Date 16 April 2018

Version Number F03

Author(s):

Name Glenn Carey

Senior Traffic Engineer

Effective Date 16/04/2018

Approved By:

Name Russell Meaney

Senior Traffic Designer

Date Approved 16/04/2018

Document History

Version Effective Date Description of Revision Prepared by Reviewed by

D01 28/02/2018 Issued For Information Elham Darabi Negin Vaez

F01 01/03/2018 Issued for Council Review Elham Darabi Glenn Carey

F02 05/03/2018 Issued for Council Review Elham Darabi Glenn Carey

F03 16/04/2018 Council comments incorp’d Glenn Carey Russell Meaney

Page 46: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence iii

Table of Contents

1 Introduction 1 2 Background and Existing Conditions 2

2.1 Location and surrounding land use 2 2.2 Planning Zones 3 2.3 Road Network 4 2.4 SmartRoads Network Operating Plans 11 2.5 Sustainable Transport 12

3 Proposed Development 15 4 Site Access and Traffic Management 16 5 Work Site Hazard Assessment 17 6 Traffic Controllers 18 7 Authority Applications and Approvals 19 8 Staged Construction Process 20 9 Proposed Traffic Management 21

9.1 General 21 9.2 Hours of Operation 21 9.3 Construction Stage 1 – Cardno Drawing V180227-TR-DG-9701 21 9.4 Construction Stage 2 – Cardno Drawing V180227-TR-DG-9702 22

10 Major Site Access Routes 23 10.1 19.0m semi-trailer route: 23 10.2 8.8m concrete trucks route: 24

Appendices

Appendix A TRAFFIC MANAGEMENT PLANS

Appendix B WORKSITE HAZARD ASSESSMENT

Tables

Table 2-1 Public Transport Provision 13 Table 2-2 Share Car Locations 14 Table 7-1 Authority Applications and Approvals 19 Table 8-1 Staged Construction Process 20

Page 47: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence iv

Figures

Figure 2-1 Site Location 2 Figure 2-2 Planning Scheme Zones 3 Figure 2-3 Nicholson Street, looking south adjacent to the subject site 4 Figure 2-4 Albert Street, looking west from Nicholson Street 5 Figure 2-5 John Street, looking south from Albert Street 6 Figure 2-6 Glenlyon Road, looking west from Rickard Street 7 Figure 2-7 Elm Grove, looking south towards the subject site 8 Figure 2-8 Gamble Street, looking north towards the subject site 9 Figure 2-9 Rickard Street, looking north towards the subject site 10 Figure 2-10 SmartRoads Network Operating Plan 11 Figure 2-11 Public Transport Victoria Map 12 Figure 3-1 Artist Impression 15 Figure 10-1 Truck Access Routes and Height Clearance Warnings 23 Figure 10-2 Truck Access Routes and Height Clearance Warnings 24

Page 48: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 1

1 Introduction

Cardno has been engaged by Hacer Group Pty Ltd to prepare Traffic Management Plans (TMPs) for the construction stage of the proposed “East Brunswick Village” mixed use development at Nicholson Street, Brunswick East.

Page 49: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 2

2 Background and Existing Conditions

2.1 Location and surrounding land use The subject site is located at Nicholson Street, Brunswick east, as shown in Figure 2-1, with street frontages to Nicholson Street and John Street.

The subject site is irregular in shape and is currently not occupied.

Surround land use are a mixture of residential and commercial.

Significant land marks/infrastructure in close proximity to the site are:

• Phillips Reserve School located to the east;

• East Brunswick Kindergarten & Childcare, and Northcote High, located to the south-east;

• Fleming Park, located to the north-west;

• Methven Park located to the west; and

• Balfe Park located to the south.

Figure 2-1 Site Location

Copyright © Discway Maps

SUBJECT SITE

Page 50: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 3

2.2 Planning Zones Figure 2-2 shows the location of the site and the City of Moreland Planning Scheme Zones.

Figure 2-2 Planning Scheme Zones

Figure 2-2 demonstrates that the subject site is located within the Commercial 1 Zone (C1Z). The permitted uses for the C1Z are listed in Clause 34.01 of the City of Moreland Planning Scheme.

SUBJECT SITE

Page 51: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 4

2.3 Road Network

2.3.1 Nicholson Street

Nicholson Street is a primary arterial road running in north-south direction between Lonsdale Street and Albert Street located to the south and Albion Street located to the north.

Nicholson Street comprises a 14.6 metre wide road pavement that provides for two trafficable lanes, restricted kerbside parking and tramways in both directions, as shown in Figure 2-3.

At the frontage of the subject site, a speed limit of 60km/h applies.

Figure 2-3 Nicholson Street, looking south adjacent to the subject site

Page 52: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 5

2.3.2 Albert Street

Albert Street is a local road running in east-west direction between King Street located to the east and Sydney Road located to the west.

Albert Street comprises an 8 metre wide road pavement that provides a trafficable lane with kerbside parking on both sides, as shown in Figure 2-4.

In the vicinity of the subject site, a speed limit of 40km/h applies.

Figure 2-4 Albert Street, looking west from Nicholson Street

Page 53: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 6

2.3.3 John Street

John Street is a local road running in north-south direction between St Phillip Street and Mary Moodie Way located to the south and Albert Street located to the north.

John Street comprises a 9.5 metre wide road pavement that provides one trafficable lane, non-restricted and restricted kerbside parking spaces, as shown in Figure 2-9.

At the frontage of the subject site, a speed limit of 40km/h applies.

Figure 2-5 John Street, looking south from Albert Street

Page 54: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 7

2.3.4 Glenlyon Road

Glenlyon Road is a major local road running east-west direction between King Street located to the east and Sydney Road located to the west.

Glenlyon Road comprises an approximate 13.5 metre wide road pavement that provides one trafficable lane, restricted kerbside parallel parking spaces and a formal bike lane in both directions, as shown in Figure 2-9.

In the vicinity of the subject site, a speed limit of 50km/h applies.

Figure 2-6 Glenlyon Road, looking west from Rickard Street

Page 55: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 8

2.3.5 Elm Grove

Elm Grove is a local road running south from Albert Street to the subject site.

Elm Grove comprises a 5 metre wide road pavement, as shown in Figure 2-9.

Figure 2-7 Elm Grove, looking south towards the subject site

Page 56: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 9

2.3.6 Gamble Street

Gamble Street is a local road running north from Glenlyon Road to the subject site.

Gamble Street comprises a 7.2 metre wide road pavement that provides one trafficable lane and restricted kerbside parking on both sides, as shown in Figure 2-9.

A speed limit of 40km/h applies.

Figure 2-8 Gamble Street, looking north towards the subject site

Page 57: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 10

2.3.7 Rickard Street

Rickard Street is a local road running north from Glenlyon Road to the subject site.

Rickard Street comprises a 6.5 metre wide road pavement that provides one trafficable lane in both directions, as shown in Figure 2-9.

A speed limit of 40km/h applies.

Figure 2-9 Rickard Street, looking north towards the subject site

Page 58: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 11

2.4 SmartRoads Network Operating Plans SmartRoads Network Operating Plans have been developed through extensive consultation with local councils, government agencies and relevant stakeholders, and illustrate which transport modes have priority on the road at different times of the day.

Figure 2-10 identifies the Network Operating Plan in the vicinity of the site, and indicates that Nicholson Street adjacent to the site is a Traffic and Tram Priority Route, John Street is a Bike Priority Route and Glenlyon Road is a Bus and Bike Priority Route.

Figure 2-10 SmartRoads Network Operating Plan

SUBJECT SITE

LEGEND

Tram Route

Traffic Route

Bike Route

Bus Route

Page 59: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 12

2.5 Sustainable Transport

2.5.1 Public Transport Victoria Map

The Public Transport Victoria Map for the City of Moreland in the vicinity of the site is shown in Figure 2-11.

Figure 2-11 Public Transport Victoria Map

Figure 2-11 identifies the public transport in the vicinity of the site, and indicates that:

• Tram route 96 operate along Nicholson Street;

• Bus routes 506 operate along Glenlyon Road and Bus routes 508 operate along Blyth Street at the vicinity of the subject site;

• A formal bike lane exists along Glenlyon Road at the vicinity of the subject site; and

• Northcote and Brunswick Train Stations are close to the subject site.

SUBJECT SITE

Page 60: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 13

2.5.2 Public Transport

The full public transport provision provided in Table 2-1 indicates services within close proximity of the subject site.

Table 2-1 Public Transport Provision

Service Route Description Nearest Stop

Train South Morang Line 23 min/1.9 km walk 14 min/ 508 Bus Nicholson Street and Blyth Street

Upfield Line 14 min / 508 Bus Nicholson Street and Blyth Street 14 min/ 506 Bus Glenlyon Road

Service Route No’s

Route Description Nearest Stop

Tram 96 East Brunswick - St Kilda Beach 1 min/100 m walk

Bus 506 Moonee Ponds - Westgarth Station via Brunswick 3 min/260 m walk

508 Alphington - Moonee Ponds via Northcote & Brunswick 6 min/500 m walk 3 min/ 96 Tram

Page 61: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 14

2.5.3 Share Car

Go-Get Car Share, Green Share Car and Flexicar currently operate within the City of Moreland.

Car sharing is becoming increasingly popular with the residents of inner city developments, where parking availability is restrictive and expensive. Listed in Table 2-2 are the car share spaces in close proximity of the subject site.

Table 2-2 Share Car Locations

Company Location Walk Time/ Distance*

Green Share Car Opposite 310 Park Street, Brunswick East 13 min/1.0 km walk 7 min/ 96 Tram

GoGet Corner of Albert and Nicholson Street, Brunswick East 1 min/120m walk

Glenlyon Road- between Deakin Street and Ethel Street 7 min/600m walk

3 min/ 506 Bus

Flexicar 252 Glenlyon Road, Brunswick East 3 min/270 m walk

*As described within GoGet, Green Car Share and Flexicar websites

It is noted that the listed share car spaces mentioned under in Table 2-2 will not be affected by proposed development at the subject site.

Page 62: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 15

3 Proposed Development

The proposal contemplates:

> Development of the “East Brunswick Village” for the purposes of seven mid-rise buildings; and

> Construction of 5-6 storey residential buildings, with a total area of 21,300.00 square meters, 603 dwellings, 752 bike spaces and 746 car spaces.

Figure 3-1 Artist Impression

Courtesy of JAM Architects

Page 63: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 16

4 Site Access and Traffic Management

The project construction will involve construction vehicle movements within and around the site. This will interface with existing vehicle and pedestrian activity within the surrounding precinct.

During the work, the objective for managing traffic will be to:

> Implement an effective management plan that achieves the planned construction activities in a safe and timely manner;

> Provide for public safety;

> Protect the environment; and

> Minimise the disruption to both vehicular and pedestrian traffic.

Page 64: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 17

5 Work Site Hazard Assessment

A work site hazard assessment is the first step in developing a construction traffic management plan for a work site and is a requirement of the Road Management Act 2004 – Code of Practice. The purpose of the Risk Assessment is to identify the risk of events, the probability of the event occurring and the severity of the consequences if the risk was to lead to, or contribute to an incident. Based on those assessments the Risk Assessment process then identifies appropriate design elements and management procedures to eliminate or minimise the risk.

This Construction Traffic Management Plan outlines the design elements and management procedures that are to be put in place for vehicles accessing the site during the construction phase of the project.

The risk assessment process has been documented using the Road Management Act 2004 Worksite safety – Traffic Management site risk rating checklist and is attached as Appendix B.

Page 65: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 18

6 Traffic Controllers

Traffic controllers are used when signs and devices for works alone are considered insufficient to provide for personal safety, public convenience and efficient control and management of traffic around the worksite. Traffic controllers act to compliment the traffic management devices to safely enforce the traffic management strategy.

Traffic controllers are to be appropriately trained in their duties and certified as competent. All accredited traffic controllers at worksites on roads should comply with the according state authority guidelines.

Accredited traffic controllers responsibilities include, but are not limited to the following:

> Own personal safety

> Safety of co-workers

> Safety of motorists and other road users

> Enabling works at the site to be conducted safely by minimising the risk associated with traffic movement

> Controlling traffic in a professional manner to enable drivers to negotiate through, past, or around the worksite safely

> Maintaining traffic control in emergencies and other difficult situations

> Minimising delays to traffic

Page 66: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 19

7 Authority Applications and Approvals

Prior to implementation of the proposed traffic management, all relevant authorities are required to review and approve the site specific traffic management strategy. Table 7-1 summarises the known authorities from which approval will be required. Note that consultation with other authorities may be required.

Table 7-1 Authority Applications and Approvals

Authority Item

City of Moreland Traffic Management Strategy

Consent to Work

VicRoads MOA Application

Consent to Work on Road Reserves

Yarra Trams Consent to Work for traffic management on tram route

Page 67: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 20

8 Staged Construction Process

The number of personnel and vehicle deliveries during the staged construction process has been provided by Hacer Group Pty Ltd as follows.

The traffic management plans may be required to be modified to accommodate the stage of the process as shown in Table 8-1.

Table 8-1 Staged Construction Process

Stages Commence

Works

Pers

onne

l

19.0

m T

ruck

and

Dog

Per

Day

19.0

m S

emi-T

raile

rs P

er D

ay

8.8m Agitator Truck

Oth

er T

ruck

s (u

p to

12.

5m)

Pour Per Week

Trucks Per Pour Day

Early Works & Site Establishment April 2018 20 2 to 3 - - - -

Reinforced Concrete Structure April 2018 60 - 10 2 15 2

External Facade Systems October 2018 100 - 10-15 - - 10

Internal Fit Out / Finishes October 2018 150-

200 - 10-15 - - 10

Building Commissioning & Compliance

March 2019 50 -

- - - 2

Total Project Duration 14 Months

Page 68: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 21

9 Proposed Traffic Management

9.1 General Traffic Management Plans (TMPs) have been developed for the typical construction stage. The TMPs can be found attached as Appendix A.

Detailed discussion of the proposed traffic management for each stage of works is as follows:

9.2 Hours of Operation The proposed hours of operation for the project are as follows:

- Monday to Friday 7:00 am to 7:00 pm

- Saturdays 7:00 am to 1:00 pm

- Shift/Night Works Subject to approval

9.3 Construction Stage 1 – Cardno Drawing V180227-TR-DG-9701 During Stage 1, the following items are to be implemented:

− Timber hoarding is to be stablished along the subject site title boundaries with a site access gate at Nicholson Street;

− In order to facilitate construction vehicle movements, it is proposed to widen the existing cross-over;

− Two (2) loading areas are to be established within the site;

− It is understood that most trucks servicing the site will be semi-trailers or agitator trucks;

− The design (largest) vehicle for entry to the site is a 19m semi-trailer.

− Trucks are to both enter and leave the site in a forward direction; turning around within the site. As the arterial road connection with Citylink is much shorter to the south via Brunswick Street, than to the north via Moreland road or Bell Street, it is anticipated that most trucks will turn left into the site from the south and depart by right turn to the south. Pedestrian access is to be maintained at all times;

− A gateman will supervise pedestrians during site entry and exit; and

− All construction works will be advised using appropriate standard traffic management signage.

9.3.1 Loss of Car Parking

No loss of car parking.

Page 69: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 22

9.4 Construction Stage 2 – Cardno Drawing V180227-TR-DG-9702 During Stage 2, the following items are to be implemented:

− Previously established timber hoarding, site access gate and loading bays are to be maintained;

− Additionally, it is proposed to establish two (2) site access gates at the Rickard Street subject site title boundaries along with two (2) concrete pouring bays within the site.

− In order to facilitate construction vehicle movements, it is proposed to relocate the site gate on Nicholson street and construct a new cross-over;

− It is understood that most trucks servicing the site will be semi-trailers or agitator trucks;

− Semi-trailer access is to be as per Stage 1;

− Agitator trucks are to approach the site from Glenlyon Road turning left onto Rickard Street and reverse up to the appropriate concrete pump by performing a reverse manoeuvre either within the site or at the end of Rickard Street. Upon departure the trucks are to egress in a forward direction and turn left onto Glenlyon Road (eastbound);

− The design (largest) vehicles are:

o 19m semi-trailer for entry to the site from Nicholson Street.

o 8.8m long agitator truck for entry to the site from Rickard Street.

− Pedestrian access is to be maintained at all times;

− Traffic controllers will supervise construction vehicle movements as required; and

− All construction works will be advised using appropriate standard traffic management signage.

9.4.1 Loss of Car Parking

No loss of car parking.

Page 70: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 23

10 Major Site Access Routes

The recommended inbound and outbound routes are prescribed as shown in Figure 10-1 and 10.2.

The Citylink will be the preferred major access route to and from the site.

10.1 19.0m semi-trailer route: > Inbound Route: City Link – Brunswick Road – Nicholson Street – Subject Site;

> Outbound Route: Subject Site – Nicholson Street – Brunswick Road – City Link.

Alternatively:

> Inbound Route: City Link – Moreland Road – Holmes Street – Albion Street – Nicholson Street – Subject Site;

> Outbound Route: Subject Site – Nicholson Street – Albion Street – Holmes Street – Moreland Road – City Link.

Figure 10-1 Truck Access Routes and Height Clearance Warnings

SUBJECT SITE

LEGEND Recommended inbound route

Recommended outbound route

Citylink

Alternative inbound route

Alternative outbound route

Page 71: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 24

10.2 8.8m concrete trucks route: > Inbound Route: City Link – Brunswick Road – Lygon Street – Glenlyon Road – Rickard Street – Subject

Site;

> Outbound Route: Subject Site – Rickard Street – Glenlyon Road – Nicholson Street – Nicholson Street – City Link.

Alternatively:

> Inbound Route: City Link – Moreland Road – Holmes Street – Albion Street – Nicholson Street – Subject Site;

> Outbound Route: Subject Site – Nicholson Street – Albion Street – Holmes Street – Moreland Road – City Link.

Figure 10-2 Truck Access Routes and Height Clearance Warnings

Hacer Group Pty Ltd will require all subcontractors to advise (and induct as required) operatives/drivers of the approved access route plan and the traffic management plan for the proposed development. Drivers are to be provided with a map highlighting the approved routes and potential hazards in the vicinity of the project.

LEGEND Recommended inbound route

Recommended outbound route

Citylink

Alternative inbound route

Alternative outbound route

Page 72: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 25

Nicholson Street, Brunswick East

APPENDIX

TRAFFIC MANAGEMENT PLANS

Page 73: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

5,083 8,225 8,225 8,225 8,225 9,835 7,800 8,400 7,800 8,400 7,800 8,400 7,800 4,550 8,100

7,6

50

8,1

00

8,1

00

8,1

00

8,1

00

7,9

00

5,4

90

5,160 8,200 9,100 8,100 9,100 8,100 9,100 7,820

5,3

40

8,1

46

8,3

75

8,3

75

8,3

75

8,3

75

4,5

95

7,9

00

8,4

00

7,9

00

5,2

20

1,5

27

550

1351

RL 4

1,4

60

RL 4

1,4

60

RL 4

1,7

00

RL 4

1,7

00

RL 4

1,3

80

RL 4

1,8

50

17°

102°

102°

102°

98°

98°

102°

23°

13°

13°

13°

17°

vicro

ads

satisfa

ctio

n of

sig

nal d

esig

n to

pro

posed tra

ffic

elm grove

pro

perty

adjoinin

g

pro

perty

adjoinin

g

pro

perty

adjoinin

g

pro

perty

adjoinin

g

pro

perty

adjoinin

g

fh fh

fh

fh

fh

fh

fhfh

fhfh

fhfh

ram

p 1:2

6

ram

p

lift

lift

lifts(sta

ge 2)

lift

(sta

ge 2)

stair

(sta

ge 2)

lifts

lift

(sta

ge 2)

stair

res. c

ar e

ntry (sta

ge 2)

residential c

ar e

ntry

stair

bin e

xh (B

2)(sta

ge 2)

lot 7 gro

und flo

or sla

b

B1(sta

ge2)

supply air to

(B1)(sta

ge2)

bin e

xh

carp

ark e

xh

lot 3 gro

und flo

or sla

b

carp

ark e

xh

bin e

xh

(part o

f sta

ge 3 w

orks)

outside s

upply air ris

er to

B1

require

ments

auth

ority

refer p

ower

T/B

substatio

n g

atic

2800x2450

lot 5 gro

und flo

or sla

b

travelator

Bld

F

stair 1

Bld

E

stair 2

Bld

F

stair 4

Bld J

stair 1

12x bikes

6x bikes

6 x bikes

8x bikes

6x bikes

fhfh

fw fw fw

fw

fw

fwfw

fwfw

fw

fw

fw

fw

fw

fw

fw

fw

fwfw

fwfw

fwfw

fwfw

fw

fw fw fw

fhfh

fw

fw fwfw

fw

fw

fw

fh

fh

4,8

00

8,2

00

9,2

00

8,2

00

9,2

00

8,2

00

5,5

15

3,6

85

2-1

0

2-9

2-7

2-8

2-6

2-5

2-4

2-3

2-1

1

2-1

2

1-8.1

1-7.1

1-9.1

1-9.2

1-1

0.1

1-1

1.1

1-1

2.1

1-1

2.1

1-1

2.2

1-1

2.2

1-6.1

1-O

1-O

1-P

1-P

1-N

1-N

1-M

1-M

1-L

1-L

1-K

1-K

1-Q

1-Q

1-J

1-J

1 12-D.1

2-F.1

2-J

2-K

2-H

2-E.1

2-C.1

2-B.1

2-B

2-B

2-A

2-A

2-1

2-2

2-C

2-D

2-E

2-F

2-G

1-A

1-A

2-1

3

2-1

4

2-1

5

2-1

6

2-L

2-H

2-J

2-K

1-6

1-6

1-5

1-5

1-4

1-4

1-3

1-3

1-2

1-2

1-1

1-1

1-1

51-1

5

1-1

41-1

4

1-1

3

1-1

2

1-1

1

1-1

0

1-H

1-H

1-G

1-G

1-F

1-F

1-E

1-E

1-9

1-B

1-B

1-C

1-C

1-8

1-D

1-D

2-L.1

1.7

1.7

1.7

3-N

3-O

5,3

40

7,2

90

5,5

50

8,9

50

8,1

50

8,1

50

8,1

50

8,1

50

8,1

50

8,1

50

4,9

71

1,5

27

4,8

00

8,2

00

9,2

00

8,2

00

9,2

00

8,2

00

5,5

15

3,6

85

7,6

50

550

3,6

55

5,550 8,150 10,525 5,550 7,890

8,1

00

8,1

00

7,9

00

5,4

90

6,500 8,750 8,150 10,750 10,750 10,750 10,750 9,900 10,750

john st

no. 9

8

gro

ve

no. 2 elm

pro

perty

adjoinin

g

john st

no. 8

0

ga

mble st

no. 9

ga

mble st

no. 6

nic

hols

on st

no. 1

25

sta

ge 3 tb

c

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

works

gro

und flo

or

sta

ge 1

exte

nt o

f

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

planter

8x bikes

4x bikes

4x bikes

4x bikes

pla

nter

pla

nter

planter

pla

nter

pla

nter

pla

nter

planter

planter

planter

pla

nter

pla

nter

pla

nter

pla

nter

Villa

ge A

venue

Way

Bluestone

Nicholson St

sta

ge 2 tb

c

(75 car s

paces)

tem

porary car p

ark

works

gro

und flo

or

sta

ge 1

exte

nt o

f

pla

nter

Village Avenue

seat

seat

seat

seat

seat

seat

seat

seat

seat

seat

planter

seat

seat

John St

SUBJECT SITE(EAST BRUNSWICK VILLAGE)

NICHOLSON STREET

RICKARD STREET

GAMBLE STREET

JOHN STREET

GLE

NL

YO

N R

OA

D

AL

BE

RT S

TR

EE

T

ST

RE

ET

PE

ER

S

ST

RE

ET

SU

MN

ER

ELM GROVE

MELWAY 30 A8

CITY OF MORELAND

CONSTRUCTION STAGE 1A3

GC RJM

HACER GROUP PTY LTD0 5

ISSUED FOR INFORMATION

1:1000 @ A3

RJMGC

MARCO LUCIONI

RUSSELL MEANEY 22.02.2018

GLENN CAREY

GLENN CAREY

V180227-TR-DG-9701

127-139 & PART 149 NICOLSON ST, EAST BRUNSWICK

EAST BRUNSWICK VILLAGE

2

1:1000

1 28.02.2018

10 20

DESIGN VEHICLES

K-to-K Turning Circle 25.1m

13.70

1.60 5.30

4.20

0.20

1.40 9.50

Articulating Angle

Lock to Lock Time

:2.50Trailer Width Steering Angle

Tractor Track

Trailer Track

:2.50

2.50:

Tractor Width

AUSTROADS S ARTICULATED 19M

2.50:

meters

27.7:

70.0:

6.0:

:

TRAFFIC MANAGEMENT PLAN

AINTREE STREET

2 16.04.2018 COUNCIL COMMENT - WORK HOURS

Email: [email protected] Web: www.cardno.com.au/victoria

Phone (+61 3) 8415 7777 Fax (+61 3) 8415 7788

501 Swanston Street, Melbourne, VIC Australia 3000

ABN: 47 106 610 913

content of this document.

party arising out of any use or reliance by third party on the

assume any responsibility or liability whatsoever to any third

of the retainer. Cardno Limited does not and shall not

benefit of and use by the client in accordance with the terms

This document is produced by Cardno Limited solely for the

Cardno Limited All Rights Reserved. ã

NOT TO BE USED FOR CONSTRUCTION PURPOSES

Authorised

Drawn

Designed

Checked

Title

Project

Client

Date

Status

Scale Size

RevisionProject Number

PRELIMINARY

Rev Date Description Drawn Appr.

glenn.care

yB

Y:

EXACT POSITION SHOULD BE PROVEN ON SITE.

SHOWN ARE APPROXIMATE ONLY AND THEIR

THE LOCATIONS OF UNDERGROUND SERVICES

CA

D FIL

E:

DATE P

LO

TTE

D:

16/04/2018

9:05:27 A

M

WARNINGBEWARE OF UNDERGROUND SERVICES

M:\2018\0001_0500\V

180227_East_

Bru

nswick_Village\Traffic\Drafting\04 Dra

wings\01 C

AD\V

180227-T

R-D

G-9

701.dgn

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

STEP

YOUR

WATCH

STEP

YOUR

WATCH

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

DEVICES NOT REQUIRED OUTSIDE HOURS OF OPERATION.

2. REMOVE OR COVER UP TEMPORARY TRAFFIC MANAGEMENT SIGNS AND OTHER TRAFFIC CONTROL

SIGNS DURING HOURS OF OPERATION.

1. REMOVE OR COVER UP PERMANENT SIGNS THAT CONFLICT WITH TEMPORARY TRAFFIC MANAGEMENT

SIGN CONFLICTS

7:00AM - 1:00PM SATURDAY.

1. 7:00AM - 7:00PM MONDAY TO FRIDAY

HOURS OF OPERATION

OF SIGHT FROM THE DRIVER TO THE SIGN.

2. SIGNS SHALL FACE TOWARDS APPROACHING TRAFFIC APPROXIMATELY AT RIGHT ANGLES TO THE LINE

1. ALL SIGNS SHALL BE PERMANENTLY HIGH MOUNTED, UNLESS INDICATED OTHERWISE.

INSTALLATION NOTES

2.4m HIGH TIMBER HOARDING

PEDESTRIAN ROUTE

SWING GATE

DESIGN GRIDLINES

LEGEND

SIGN, SINGLE POST MOUNT

LOADING AREA

STAGE 1 CONSTRUCTION

TEMPORARY CROSS-OVER

SCISSOR GATE (OR EQUIVALENT)

GATEMAN

CLEARWAY 4:00 - 6:30PM MON-FRI

(EXISTING)

(EXISTING)

7:00AM - 7:00PM SAT, SUNL.Z. 6:00AM- 4:00PM MON-FRI

(EXISTING)

N.S.

(EXISTING)

N.S.

PATHS, 0.5m CLEARANCE SHOWNAUSTROADS 19m SEMI-TRAILER SWEPT

(OR EQUIVALENT) TO BLOCK PEDESTRIANSGATEMAN, WITH SCISSOR GATES

AREA 2LOADING

CONSTRUCTIONSTAGE 1

Page 74: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

5,083 8,225 8,225 8,225 8,225 9,835 7,800 8,400 7,800 8,400 7,800 8,400 7,800 4,550 8,100

7,6

50

8,1

00

8,1

00

8,1

00

8,1

00

7,9

00

5,4

90

5,160 8,200 9,100 8,100 9,100 8,100 9,100 7,820

5,3

40

8,1

46

8,3

75

8,3

75

8,3

75

8,3

75

4,5

95

7,9

00

8,4

00

7,9

00

5,2

20

1,5

27

550

1351

RL 4

1,4

60

RL 4

1,4

60

RL 4

1,7

00

RL 4

1,7

00

RL 4

1,3

80

RL 4

1,8

50

17°

102°

102°

102°

98°

98°

102°

23°

13°

13°

13°

17°

EE

FF

70.33

186°23'30"

5.7

9

277°2

8'

24.6

9

276°5

2'30"

1.21

6°24'

24.0

4

276°0

7'30"

10.3

9

276°3

8'

21.12

186°23'30"

45.5

0

276°4

8'30"

0.54

186°33'

47.7

2

276°1

8'

29.886°24'30"

42.0

2

276°3

3'30"

50.042°14'50"

16.3

4

96°2

9'

22.4

5

96°4

6'10"

10.2

2

96°3

6'

7.98

186°24'

6°37'30"

42.06

vicro

ads

satisfa

ctio

n of

sig

nal d

esig

n to

pro

posed tra

ffic

17.35

6°21'30"

30.7

6

276°2

4'

43.73

6°24'

153.01

186°23'30"

11.63186°15'

66.0

6

96°2

2'30"

1.796°24'

10.2

9

96°3

5'30"

29.9

4

96°1

4'30"

35.6

6

276°3

5'30"

4.0

7

96°3

4'

4.04

186°24'

3.94

186°32'

elm grove

pro

perty

adjoinin

g

pro

perty

adjoinin

g

pro

perty

adjoinin

g

pro

perty

adjoinin

g

pro

perty

adjoinin

g

fh fh

fh

fh

fh

fh

fhfh

fhfh

fhfh

ram

p 1:2

6

ram

p

lift

lift

lifts(sta

ge 2)

lift

(sta

ge 2)

stair

(sta

ge 2)

lifts

lift

(sta

ge 2)

stair

res. c

ar e

ntry (sta

ge 2)

residential c

ar e

ntry

stair

bin e

xh (B

2)(sta

ge 2)

lot 7 gro

und flo

or sla

b

B1(sta

ge2)

supply air to

(B1)(sta

ge2)

bin e

xh

carp

ark e

xh

lot 3 gro

und flo

or sla

b

carp

ark e

xh

bin e

xh

(part o

f sta

ge 3 w

orks)

outside s

upply air ris

er to

B1

require

ments

auth

ority

refer p

ower

T/B

substatio

n g

atic

2800x2450

lot 5 gro

und flo

or sla

b

travelator

Bld

F

stair 1

Bld

E

stair 2

Bld

F

stair 4

Bld J

stair 1

12x bikes

6x bikes

6 x bikes

8x bikes

6x bikes

fhfh

fw fw fw

fw

fw

fwfw

fwfw

fw

fw

fw

fw

fw

fw

fw

fw

fwfw

fwfw

fwfw

fwfw

fw

fw fw fw

fhfh

fw

fw fwfw

fw

fw

fw

fh

fh

4,8

00

8,2

00

9,2

00

8,2

00

9,2

00

8,2

00

5,5

15

3,6

85

2-1

0

2-9

2-7

2-8

2-6

2-5

2-4

2-3

2-1

1

2-1

2

1-8.1

1-7.1

1-9.1

1-9.2

1-1

0.1

1-1

1.1

1-1

2.1

1-1

2.1

1-1

2.2

1-1

2.2

1-6.1

1-O

1-O

1-P

1-P

1-N

1-N

1-M

1-M

1-L

1-L

1-K

1-K

1-Q

1-Q

1-J

1-J

1 12-D.1

2-F.1

2-J

2-K

2-H

2-E.1

2-C.1

2-B.1

2-B

2-B

2-A

2-A

2-1

2-2

2-C

2-D

2-E

2-F

2-G

1-A

1-A

2-1

3

2-1

4

2-1

5

2-1

6

2-L

2-H

2-J

2-K

1-6

1-6

1-5

1-5

1-4

1-4

1-3

1-3

1-2

1-2

1-1

1-1

1-1

51-1

5

1-1

41-1

4

1-1

3

1-1

2

1-1

1

1-1

0

1-H

1-H

1-G

1-G

1-F

1-F

1-E

1-E

1-9

1-B

1-B

1-C

1-C

1-8

1-D

1-D

2-L.1

1.7

1.7

1.7

3-N

3-O

2-1

5,3

40

7,2

90

5,5

50

8,9

50

8,1

50

8,1

50

8,1

50

8,1

50

8,1

50

8,1

50

4,9

71

1,5

27

4,8

00

8,2

00

9,2

00

8,2

00

9,2

00

8,2

00

5,5

15

3,6

85

7,6

50

550

3,6

55

5,550 8,150 10,525 5,550 7,890

8,1

00

8,1

00

7,9

00

5,4

90

6,500 8,750 8,150 10,750 10,750 10,750 10,750 9,900 10,750

AA

BBC

C

DD

GGH H

J J

K K

L L

M M

42.8

696°2

4'

john st

no. 9

8

gro

ve

no. 2 elm

pro

perty

adjoinin

g

john st

no. 8

0

ga

mble st

no. 9

ga

mble st

no. 6

nic

hols

on st

no. 1

25

sta

ge 3 tb

c

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

works

gro

und flo

or

sta

ge 1

exte

nt o

f

pla

nter

pla

nter

pla

nter

pla

nter

pla

nter

planter

8x bikes

4x bikes

4x bikes

4x bikes

pla

nter

pla

nter

planter

pla

nter

pla

nter

pla

nter

planter

planter

planter

pla

nter

pla

nter

pla

nter

pla

nter

Villa

ge A

venue

Way

Bluestone

Nicholson St

sta

ge 2 tb

c

(75 car s

paces)

tem

porary car p

ark

works

gro

und flo

or

sta

ge 1

exte

nt o

f

pla

nter

Village Avenue

seat

seat

seat

seat

seat

seat

seat

seat

seat

seat

planter

seat

seat

John St

SUBJECT SITE(EAST BRUNSWICK VILLAGE)

NICHOLSON STREET

RICKARD STREET

GAMBLE STREET

JOHN STREET

GLE

NL

YO

N R

OA

D

AL

BE

RT S

TR

EE

T

ST

RE

ET

PE

ER

S

ST

RE

ET

SU

MN

ER

ELM GROVE

MELWAY 30 A8

CITY OF MORELAND

CONSTRUCTION STAGE 2A3

GC RJM

HACER GROUP PTY LTD0 5

ISSUED FOR INFORMATION

1:1000 @ A3

RJMGC

RJMGC

MARCO LUCIONI

RUSSELL MEANEY 22.02.2018

GLENN CAREY

GLENN CAREY

V180227-TR-DG-9702

127-139 & PART 149 NICOLSON ST, EAST BRUNSWICK

EAST BRUNSWICK VILLAGE

3

1:1000

1 28.02.2018

10 20

DESIGN VEHICLES

K-to-K Turning Circle 25.1m

13.70

1.60 5.30

4.20

0.20

1.40 9.50

Articulating Angle

Lock to Lock Time

:2.50Trailer Width Steering Angle

Tractor Track

Trailer Track

:2.50

2.50:

Tractor Width

AUSTROADS S ARTICULATED 19M

2.50:

meters

27.7:

70.0:

6.0:

:

TRAFFIC MANAGEMENT PLAN

AINTREE STREET

2 11.04.2018 CLIENT COMMENT - RICKARD ST FOOTPATH

3 16.04.2018 COUNCIL COMMENT - WORKING HOURS

Email: [email protected] Web: www.cardno.com.au/victoria

Phone (+61 3) 8415 7777 Fax (+61 3) 8415 7788

501 Swanston Street, Melbourne, VIC Australia 3000

ABN: 47 106 610 913

content of this document.

party arising out of any use or reliance by third party on the

assume any responsibility or liability whatsoever to any third

of the retainer. Cardno Limited does not and shall not

benefit of and use by the client in accordance with the terms

This document is produced by Cardno Limited solely for the

Cardno Limited All Rights Reserved. ã

NOT TO BE USED FOR CONSTRUCTION PURPOSES

Authorised

Drawn

Designed

Checked

Title

Project

Client

Date

Status

Scale Size

RevisionProject Number

PRELIMINARY

Rev Date Description Drawn Appr.

glenn.care

yB

Y:

EXACT POSITION SHOULD BE PROVEN ON SITE.

SHOWN ARE APPROXIMATE ONLY AND THEIR

THE LOCATIONS OF UNDERGROUND SERVICES

CA

D FIL

E:

DATE P

LO

TTE

D:

16/04/2018

9:11:59 A

M

WARNINGBEWARE OF UNDERGROUND SERVICES

M:\2018\0001_0500\V

180227_East_

Bru

nswick_Village\Traffic\Drafting\04 Dra

wings\01 C

AD\V

180227-T

R-D

G-9

702.dgn

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

STEP

YOUR

WATCH

STEP

YOUR

WATCH

PREPARE TO STOP CLOSED

FOOTPATH

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

(c) 2018 Transoft Solutions, Inc. All rights reserved.

60.0R

60.0R

DEVICES NOT REQUIRED OUTSIDE HOURS OF OPERATION.

2. REMOVE OR COVER UP TEMPORARY TRAFFIC MANAGEMENT SIGNS AND OTHER TRAFFIC CONTROL

SIGNS DURING HOURS OF OPERATION.

1. REMOVE OR COVER UP PERMANENT SIGNS THAT CONFLICT WITH TEMPORARY TRAFFIC MANAGEMENT

SIGN CONFLICTS

7:00AM - 1:00PM SATURDAY.

1. 7:00AM - 7:00PM MONDAY TO FRIDAY

HOURS OF OPERATION

OF SIGHT FROM THE DRIVER TO THE SIGN.

2. SIGNS SHALL FACE TOWARDS APPROACHING TRAFFIC APPROXIMATELY AT RIGHT ANGLES TO THE LINE

1. ALL SIGNS SHALL BE PERMANENTLY HIGH MOUNTED, UNLESS INDICATED OTHERWISE.

INSTALLATION NOTES

2.4m HIGH TIMBER HOARDING

PEDESTRIAN ROUTE

SWING GATE

DESIGN GRIDLINES

LEGEND

SIGN, SINGLE POST MOUNT

LOADING AREA

STAGE 1 CONSTRUCTION

TEMPORARY CROSS-OVER

SCISSOR GATE (OR EQUIVALENT)

GATEMAN

CLEARWAY 4:00 - 6:30PM MON-FRI

(EXISTING)

(EXISTING)

7:00AM - 7:00PM SAT, SUNL.Z. 6:00AM- 4:00PM MON-FRI

(EXISTING)

N.S.

(EXISTING)

N.S.

(OR EQUIVALENT) TO BLOCK PEDESTRIANSGATEMAN, WITH SCISSOR GATES

AREA 2LOADING

CONSTRUCTIONSTAGE 2

CONSTRUCTIONSTAGE 2

CRANE 2

TOWER

CRANE 1

TOWER

8x4 AGITATOR TRUCK SWEPT PATHS

AREA 1LOADING

PUMP 1

PUMP 2

CONSTRUCTIONSTAGE 2

:

:2.50

2.50

:

:36.0

6.0

Track

Width

Steering Angle

Lock to Lock Time

8x4 Agitator

meters

5.451.47

8.77

K to K Turn Diam 20.6m:

CHANGE OF DIRECTION MANOEUVRES WITHIN SITE

EGRESS- FORWARD DIRECTIONSWEPT PATHS ANALYSIS, 0.5m CLEARANCE SHOWN,AUSTROADS 19m SEMI-TRAILER

INGRESS- FORWARD DIRECTIONSWEPT PATHS ANALYSIS, 0.5m CLEARANCE SHOWN,AUSTROADS 19m SEMI-TRAILER

(AS REQUIRED) TRAFFIC CONTROLLER

Page 75: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 26

Nicholson Street, Brunswick East

APPENDIX

WORKSITE HAZARD ASSESSMENT

Page 76: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 27

Worksite Hazard Assessment Checklist Project No: V180227 Project: East Brunswick Village

Date: 28.02.2018 Prepared By: Elham Darabi Checked By: Negin Vaez

Work Location: Nicholson Street, Brunswick East

Step 1 - Worksite Hazard Rating

Road Type: Arterial Roads (VicRoads) Traffic speed: 60 km/h

Clearance between workers and traffic: >3.0m Worksite Hazard Rating: Low

Step 2 - Required Level of Planning

A site specific traffic management plan has been prepared and reviewed by Cardno and discussed with and communicated to those on the worksite.

Step 3 - Hazards at Worksite and Step 4 - Hazard Control Measures Safety Hazard / Risk Factors Present at

Worksite Hazard Control Measure(s)

Clearance to Traffic (Lateral clearance between the nearest edge of a lane carrying traffic and the entire worksite, including all roadworks vehicles or equipment, and pedestrian workers)

>3.0m - Warning Signs - Timber Hoarding/Chain Wire Mesh/or Similar

High Speed Traffic Through Worksite No -

Poor Advance Sight Distance to Worksite (< 200 metres) No -

Poor Observance by Motorists of Directions / Instructions No -

Narrow Pavement Width with No Escape Route (< 2.9 metres width)

No -

Presence of Workers at the Worksite Yes - Warning Signs

Excavation Adjacent to Traffic No -

Presence of Unprotected Hazards within Clear Zone No -

Rough or Unsealed Road Surface due to Roadworks No -

High Volume of Traffic through Worksite (> 10,000 vehicles per day)

No -

High Volume of Heavy Vehicles through Worksite Potential -

Works Vehicles Entering / Leaving Worksite Yes - Warning Signs

End-of-queue Build-up of Traffic / Poor Sight Distance to End-of-queue

No -

Cyclists / Pedestrians through Worksite Yes - Warning Signs

Other N/A -

Step 5 - Hazard Control Measures to be Used (include details of the assessment in accordance with the Hierarchy of Safety Controls indicating why higher levels were considered not to be reasonably practicable) Having considered the nature of the works and identified all hazards in accordance with Table 3 of the Road Management Act, 2004 (Worksite Safety – Traffic Management), the hazard control measures to be applied, in consultation with those who will be working on the worksite or supervising the works, are shown on the Traffic Management Plan, Cardno drawing number V180227-TR-DG-9701 and 9702.

Step 6 - Traffic Management Plan Prepared and Implemented 1. For prepared traffic management plan refer to Cardno drawing number V180227-TR-DG-9701 and 9702. 2. It is important that workers are made aware of both the existence and contents of the traffic management plan that applies

to their worksite.

Step 7 - Traffic Management Plan in Practice Reviewed

Page 77: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

Construction Traffic Management - Detailed Report Nicholson Street, Brunswick East

V180227 | 16 April 2018 | Commercial in Confidence 28

For more details of the steps involved in the worksite hazard assessment, refer to The Road Management Act, 2004 (Worksite Safety – Traffic Management) - Part 2 Worksite Hazard Management Process.

After the traffic management plan has been implemented, a review should be undertaken to ensure that it is operating as expected. This review should take place before work commences on site (refer also Clause 14 of the Road Management Act, 2004 (Worksite Safety – Traffic Management).

Step 8 - Carry out the Work The Road Safety (Traffic Management) Regulations 2009 require that a copy of the traffic management plan, a hazard assessment and measures to control identified hazards must be kept at the worksite at all times when workers are present. In addition, all necessary written authorisations as required for the erection of certain traffic control devices shall also be kept at the worksite when workers are present.

Page 78: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 22 of 24 East Brunswick Village: Stage 1

APPENDIX D: SITE ESTABLISHMENT AND HOARDING PLAN

Page 79: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

LEGEND

SITE ESTABLISHMENT AND HOARDING PLAN

Source: Google Map data 2018

EAST BRUNSWICK

VILLAGE

NICHOLSON STREET

GLE

NLY

ON

RO

AD

RICKARD STREET

GAMBLE STREET

JOHN STREET

ALB

ERT

STR

EET

Gate 2 (Part 2)

Gate 3 (Part 2)

Gate 1 (Part 2) Gate 1 (Part 1)

= Hoarding

= Site Boundary

= Access Gate Site Amenities

Pedestrian gate

jwood
Rectangle
jwood
Line
Page 80: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage
Page 81: CONSTRUCTION MANAGEMENT PLAN · 2018. 6. 14. · East Brunswick Village: Stage 1 - Construction Management Plan Construction Management Plan Page 4 of 24 East Brunswick Village: Stage

East Brunswick Village: Stage 1 - Construction Management Plan

Construction Management Plan Page 23 of 24 East Brunswick Village: Stage 1

APPENDIX E: HACER GROUP PERSONNEL & EMERGENCY CONTACT RESPONSIBLE PERSONS

Senior Project Manager Darren McErlain – 0418 332 492 Contract Administrator Carly Wilkinson – 0419 191 524 Senior Site Manager Charlie Ursino – 0458 015 261 Occupational Health & Safety Representative Michael Kist – 03 9810 6888 Traffic Management Michael Kist – 03 9810 6888

Environmental and Waste Management Michael Kist – 03 9810 6888

EMERGENCY CONTACT

Senior Site Manager Charlie Ursino – 0458 015 261