Construction Project Delivery Methods

Project Delivery Methods = method to complete construction project

Types

1) Design-Bid-Build

2) Design-Build

3) Construction Manager At Risk

4) Integrated Project Delivery (“IPD”)

5) Public Private Partnership (“P3”)

Page 2: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(1) Design-Bid-Build

Design phase

Procurement / bidding phase

Construction phase

Page 3: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(1) Design-Bid-Build

Owner

General Contractor

Subcontractor Subcontractor Subcontractor

Sub-subcontractor

Design Professional

Page 4: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(2) Design-Build

�  There is single point of responsibility as design and construction are under the same umbrella by the design-builder

�  Design-builder is typically general contractor that hires design professional and subcontractors

Page 5: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(2) Design-Build

Design-Builder

Owner

Subcontractors Design Professional

Page 6: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(3) Construction Manager At Risk

�  Construction manager has active role preconstruction / during design phase interacting with owner and design professional to assist in getting design of the project within owner’s budget

�  Typically utilized with cost-plus contract (with a GMP)

�  Construction manager also serves as the general contractor

Page 7: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(3) Construction Manager At Risk

Owner

Construction Manager at Risk •  Hires Subs

Interact during preconstruction /

design phase

Design Professional

Page 8: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(4) Integrated Project Delivery (“IPD”)

�  Involves collaboration amongst owner, design professional, and contractor from project’s inception

�  An integrated “project team” is created to align owner, contractor, and design professional’s interests

�  Building Information Modeling (“BIM”) is typically utilized as collaborative software

�  The integrated project delivery relationship is generally created through multi-party contractual agreement and/or formation of single purpose entity

Page 9: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(4) Integrated Project Delivery (“IPD”)

Owner

Contractor Design

Professional

Collaboration

Page 10: Construction Project Delivery Methods · 2019-08-08 · Construction Project Delivery Methods Project Delivery Methods = method to complete construction project Types 1) Design-Bid-Build

(5) Public Private Partnership (“P3”)

�  Partnership between public entity and private entity to deliver public project (such as infrastructure project or service)

�  Private entity / consortium finances (and, potentially operates and maintains) public project in consideration for revenue (or sharing in revenue) completed project will generate for “x” number of years

�  Private entity and public entity enter into contract that highlights funding, operation, ownership, maintenance, risks, revenue allocation, etc.