Building the Future
Current Activities this Week:
Mass Excavation:
Grading is ongoing in Area 3. Backfilling of on-grade
is ongoing in Area 1.
Site Utilities:
Installation of the new electrical ductbank is ongoing.
Installation of North Sanitary Manhole is complete.
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Foundations:
Area 2 Field Level – Footing installation on North Stage
Footing is complete to Column Line 15.
Area 1 Mezzanine Level – Installation of Elevator Pit walls
are complete.
Area 4 Mezzanine Level – Installation of Drilled Piers
are ongoing.
Soil Nail Wall:
Area 2 – Shotcrete installation is complete.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 5.5.2010
Re: Wizards Stadium Project
Update – Week of
5.3.2010
Concourse Level Area 1/2 – E-Line Footing
Placement is ongoing.
Concourse Level Area 1 – Steel Decking
installation in Steel Erection Sequence 1-1 is
ongoing.
Field Level Area 1 – Secondary Electric
Ductbank installation has started at D-Line.
Building the Future
Structural Steel Erection:
Field Bowl – Structural Steel Erection is ongoing in
Sequence 1-1 (between Column Lines D-C). Installation of
steel decking has started.
Underground Electrical:
Secondary service ducts is complete from Electrical Room
01.34.04 south past Column Line 25.
Secondary service ducts at Column Line D have started.
Projected Activities occurring next Week:
Mass Excavation:
Grading at Truck Dock Area will begin.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue.
Deep Underground Plumbing:
Sanitary in Area 3 will begin.
Foundations:
Area 2 Field Level – Placement of foundation walls at stage
area will begin.
Area 3 Field Level – Footing excavation will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-2 will begin.
Area 1 – Structural Steel Erection at West
Building continues. First Level of Stadium
Suite Steel being set.
Field Level Area 1 – Shot looking north from
Concourse Level.
Field Level Area 1 – South Field Wall
Footings being placed.
Building the Future
Additional Photos:
Mezzanine Level Area 1 – VIP Entrance
taking shape.
Field Level Area 1 – Southeast Vomitory
Foundation Wall.
Field Level Area 2 – West Stage Foundation
Wall.
Field Level Area 1 – Southeast Vomitory
return wall formwork being installed.
Area 1 – Shot looking North West showing
West Building Structural Steel.
Field Level Area 2 – North Stage footings are
complete to Column Line 15.