cr3 steam generator replacement movement steps for removal and installation
DESCRIPTION
CR3 Steam Generator Replacement Movement Steps for Removal and Installation. Information Derived from EC/ED 67484. Linda Pressley McCray Nuclear Designer Crystal River Nuclear Plant. Performance of Motion Analysis. - PowerPoint PPT PresentationTRANSCRIPT
CR3 Steam Generator ReplacementMovement Steps for Removal and Installation
Information Derived from EC/ED 67484
Linda Pressley McCrayNuclear Designer
Crystal River Nuclear Plant
Performance of Motion AnalysisFirst, a 3D Model was created which includes all structures, systems and components located within the D-ring.
All input for the model was gathered from pertinent component information located on the associated CR3 Station drawing.
Performance of Motion Analysis
Next, an independent validation of the original 3D model geometry was performed by the SGR Project Design group.
Performance of Motion AnalysisAn additional layer of model validation was performed by AREVA who overlaid our CR3 3D model on top of AREVA’s 3D Laser Scanned model
AREVA compiled a list of all deltas found within a four foot radius surrounding each generator
Each delta has been resolved and the SGR 3D model is considered to be an accurate depiction of the CR3 as-built configuration
Performance of Motion Analysis
A motion analysis has been performed for each generator which identifies all potential interferences and specifies a removal and installation path that provides sufficient clearances to all identified plant structures, systems and components
Symbols Used
The light blue North Arrow is used as a stationary point for tracking purposes on each clearance drawing. Point originates from the center of the generator @ EL 95'.
The yellow and red North Arrow is embedded in the generator to show generator movement.
Symbols UsedDenotes clearance of 6 inches or less. Great care must be taken at caution points to prevent the generator from colliding with plant structures, systems and/or components
Generator “A” Removal
STEP #GENERATORMOVEMENT
MOVEMENTDESCRIPTION
CLEARANCES< 6 INCHES
NOTES
1 Raise generator 25 FeetPositions cold leg pieces for unobstructed rotation
4 3/8" between service water piping and generator nozzle on east side (CLEARANCE MUST BE REDUCED BY PIPING INSULATION THICKNESS)
Remaining clearances exceed 6 inches
Generator Base @ 120'-0" EL
2Rotate Clockwise 90 Degrees
Repositions cold leg pieces for unobstructed removal
None < 6 Inches Generator Base @ 120'-0" EL
3 Raise 60 Feet - 6 InchesRaises generator above remaining obstructions
None < 6 Inches Generator Base @ 180'-6" EL
Path assumes all service water piping remains in place during the removal phase. This will provide the option of removing appropriate sections of service water piping after the existing generators have been removed.
Generator “A” Removal
The auxiliary feedwater header and main feedwater header will be disassembled and removed from generator “A” prior to removal of generator
Auxiliary Feedwater Header
Main Feedwater Header
Generator “A” Removal
INITIAL STEPPLAN VIEW
Prior to manipulation
Auxiliary feedwater header and main feedwater header will be removed prior to removal of generator
INITIAL STEPELEVATION VIEW
Prior to manipulation
Generator base is at EL 95’-0”
Auxiliary feedwater header and main feedwater header will be removed prior to removal of generator
Generator “A” Removal
INITIAL STEPISOMETRIC VIEW
Prior to manipulation
Generator base is at EL 95’-0”
Generator “A” Removal
STEP #1ELEVATION VIEW
Raise Generator 25 Feet
Generator base is at EL 120’-0”
Positions cold leg pieces for unobstructed rotation
Generator “A” Removal
Generator “A” Removal
STEP #1PLAN VIEWCLEARANCES
Raise 25 Feet
Clearances shown between vertical steel and generator cylinder on west side and between RCP steel and generator cylinder on both east and west sides
STEP #1ISOMETRIC VIEW
Raise 25 Feet
Generator base is at EL 120’-0”
Generator “A” Removal
Generator “A” RemovalSTEP #2PLAN VIEWCLEARANCES
Rotate Clockwise 90 Degrees
Positions cold leg pieces for unobstructed removal path
Clearances shown between vertical steel and generator cylinder on west side, between service water piping and generator cylinder on east side, and between RCP steel and generator cylinder on both east and west sides.
STEP #3ELEVATION VIEW
Raise 60 FEET – 6 INCHES
Raises generator above remaining obstructions
Generator base is at EL 180’-6”
Generator “A” Removal
Prepare To Install Replacement Generator
Some of the insulation support assemblies shown on the replacement generator are placed in temporary locations for installation to eliminate interferences during rigging
These insulation support assemblies will be moved to their final destination after the replacement generator has been installed
Generator “A” InstallationInsulation Support Assemblies
Generator “A” InstallationPath assumes removal of interfering portions of the following as designated in the governing EC package: Service Water Piping 305-706, 305-707, 305-710, 305-711 and associated hangers; and One Inch Piping 3A-4153-SW-2, 3A-4154-SW-1 and associated hangers.
STEP #GENERATORMOVEMENT
MOVEMENTDESCRIPTION
CLEARANCES< 6 INCHES
NOTES
1 Drift North 21 InchesPositions generator for initial lowering movement
None < 6 Inches Generator Base @ 180'-6" EL
2 Drift West 4.5 InchesEqualizes distance between interferences prior to lowering
None < 6 Inches Generator Base @ 180'-6" EL
3 Lower 68 FeetPlaces main feedwater header below rcp support steel
None < 6 Inches Generator Base @ 112'-6" EL
4 Drift South 10 InchesMoves generator away from main steam hangers
None < 6 Inches Generator Base @ 112'-6" EL
Generator “A” Installation
5 Drift East 4.5 InchesMoves generator away from vertical steel @ 128'-0" EL
None < 6 InchesGenerator Base @ 112'-6" EL
6 Lower 11 Feet 6 InchesMoves generator to suitable point for final positioning
4 13/16" between main feedwater header ring and vertical steel (see Step 6 Elevation #1)
Generator Base @ 101'-0" EL
7 Drift South 11 InchesReturns generator to original coordinates prior to setting
3 5/8" between rcp steel and nearest aux. feedwater header riser (see Step 7 Elevation #2)
4 13/16" between main feedwater header ring and vertical steel (see Step 7 Elevation #1)
Generator Base @ 101'-0" EL
8 Lower 6 Feet Sets generator
4 13/16" between main feedwater header ring and vertical steel (see Step 8 Elevation #1)
Generator Base @ 95'-0" EL
STEP #GENERATORMOVEMENT
MOVEMENTDESCRIPTION
CLEARANCES< 6 INCHES
NOTES
Generator “A” Installation
INITIAL STEPPLAN VIEW
Prior to manipulation
Generator base is at EL 180’-6”
INITIAL STEPELEVATION
Prior to manipulation
Generator base is at EL 180’-6”
Generator “A” Coordinates:(From Reactor Building center to center of generator base)
X = 17’-9 31/32”Y = 30’-4 ½”Z = 180’-6”
Generator “A” Installation
INITIAL STEPISOMETRIC VIEW
Prior to manipulation
Generator base is at EL 180’-6”
Generator “A” Installation
Generator “A” Installation
STEP #1PLAN VIEW
Drift North 21 Inches
Generator base is at EL 180’-6”
Moves generator away from obstacles interfering with first downward movement
Generator “A” Installation
STEP #2PLAN VIEW
Drift West 4.5 Inches
Generator base is at EL 180’-6”
Equalizes distance between interferences prior to lowering
STEP #3ELEVATION VIEW
Lower 68 Feet
Generator base is at EL 112’-6”
Places main feedwater header below RCP support steel
Generator “A” Installation
STEP #3PLAN VIEWCLEARANCES
Lower 68 Feet
Generator base is at EL 112’-6”
Places main feedwater header below RCP support steel
Generator “A” Installation
Clearances shown occur DURING downward movement.
STEP #3ELEVATION VIEWCLEARANCES
Lower 68 Feet
Generator base is at EL 112’-6”
Clearance shown is between main feedwater header outlet and steel at EL 164’-1”
Generator “A” Installation
STEP #3PLAN VIEWCLEARANCES
Lower 68 Feet
Generator base is at EL 112’-6”
Clearances shown reflect dimensions AFTER generator is lowered to EL 112’-6”
Generator “A” Installation
STEP #3ISOMETRIC VIEW
Lower 68 Feet
Generator base is at EL 112’-6”
Places main feedwater header below RCP support steel
Generator “A” Installation
STEP #4PLAN VIEWCLEARANCES
Drift South 10 Inches
Generator base is at EL 112’-6”
Moves generator away from main steam hangers
Generator “A” Installation
STEP #4ROTATEDISOMETRIC VIEW
Drift South 10 Inches
Generator base is at EL 112’-6”
Moves generator away from main steam hangers
Generator “A” Installation
STEP #5 PLAN VIEWCLEARANCES
Drift East 4.5 Inches
Generator base is at EL 112’-6”
Moves generator away from vertical steel at EL 128’-0”
Generator “A” Installation
STEP #6ELEVATION VIEW
Lower 11 Feet 6 Inches
Generator base is at EL 101’-0”
Moves generator to suitable point for final positioning
Generator “A” Installation
STEP #6PLAN VIEWCLEARANCES
Lower 11 Feet 6 Inches
Generator base is at EL 101’-0”
Moves generator to suitable point for final positioning
Generator “A” Installation
STEP #6ELEVATION VIEWCLEARANCES
Lower 11 Feet 6 Inches
Generator base is at EL 101’-0”
Clearances shown are between the main feedwater header ring and the vertical steel located on the east and west
Generator “A” Installation
STEP #7PLAN VIEWCLEARANCES
Drift South 11 Inches
Generator base is at EL 101’-0”
Returns generator to original coordinates prior to setting
3 5/8” clearance is between the corner of the RCP steel and the nearest aux. feedwater header riser and is shown in elevation view on the next slide
Generator “A” Installation
STEP #7ROTATED VIEWCLEARANCE
Drift South 11 Inches
3 5/8” clearance is between the corner of the RCP steel and the nearest aux. feedwater header riser
Clearance is shown in PLAN VIEW view on previous slide
Generator “A” Installation
STEP #7ELEVATION VIEWCLEARANCES
Drift South 11 Inches
Generator base is at EL 101’-0”
Clearances shown are between the main feedwater header ring and the vertical steel located on the east and west
Generator “A” Installation
As generator is drifted south the clearances between the main feedwater header ring and the vertical steel remain the same as in Step #6
STEP #8ELEVATION VIEWCLEARANCE
Lower 6 Feet
Sets Generator – Base is at EL 95’-0”
Clearance shown is between the main feedwater header ring and the vertical steel located east of the generator
Generator “A” Installation
STEP #8PLAN VIEWCLEARANCES
Lower 6 Feet
Sets Generator
Generator Base is at EL 95’-0”
This final lowering movement places the aux. feedwater header risers below the RCP steel. 4 13/16” clearance is between the main feedwater header ring and the vertical steel (see previous slide)
Generator “A” Installation
STEP #8SIDE VIEWVERTICAL
CLEARANCE
Lower 6 Feet
Sets Generator
Generator Base is at EL 95’-0”
Vertical clearance shown is between the RCP steel and the nearest aux. feedwater header riser
Generator “A” Installation
STEP #8ELEVATIONGENERATOR IS SET
Final Destination
Generator Base is at EL 95’-0”
Generator “A” Installation
Prepare To Remove “B” Generator
Generator “B” RemovalPath assumes all service water piping remains in place during the removal phase. This will provide the option of removing appropriate sections of service water piping after the existing generators have been removed.
STEP #GENERATORMOVEMENT
MOVEMENTDESCRIPTION
CLEARANCES< 6 INCHES
NOTES
1 Raise generator 25 FeetPositions cold leg pieces for unobstructed rotation
None < 6 InchesGenerator Base @ 120'-0" EL
2Rotate Counter-Clockwise 90 Degrees
Repositions cold leg pieces for unobstructed removal
None < 6 InchesGenerator Base @ 120'-0" EL
3 Raise 60 Feet - 6 InchesRaises generator above remaining obstructions
None < 6 InchesGenerator Base @ 180'-6" EL
Generator “B” Removal
The auxiliary feedwater header and main feedwater header will be disassembled and removed from generator “B” prior to removal of generator
Auxiliary Feedwater Header
Main Feedwater Header
INITIAL STEPELEVATION VIEW
Prior to manipulation
Generator base is at EL 95’-0”
Auxiliary feedwater header and main feedwater header have been removed
Generator “B” Removal
INITIAL STEPISOMETRIC VIEW
Prior to manipulation
Generator base is at EL 95’-0”
Generator “B” Removal
STEP #1ELEVATION VIEW
Raise Generator 25 Feet
Generator base is at EL 120’-0”
Positions cold leg pieces for unobstructed rotation
Generator “B” Removal
Generator “B” Removal
STEP #1PLAN VIEWCLEARANCES
Raise Generator 25 Feet
Generator base is at EL 120’-0”
Positions cold leg pieces for unobstructed rotation
Generator “B” Removal
STEP #2PLAN VIEWCLEARANCES
Rotate Counter-Clockwise
90 Degrees
Generator base is at EL 120’-0”
Repositions cold leg pieces for unobstructed removal
Generator “B” Removal
STEP #2ELEVATION VIEW
Rotate Counter-Clockwise
90 Degrees
Generator base is at EL 120’-0”
Repositions cold leg pieces for unobstructed removal
Generator “B” Removal
STEP #3PLAN VIEWCLEARANCES
Raise Generator 60 Feet – 6 Inches
Generator base is at EL 180’-6”
Raises generator above remaining obstructions
Generator “B” Removal
STEP #3ELEVATION
Raise Generator 60 Feet – 6 Inches
Generator base is at EL 180’-6”
Raises generator above remaining obstructions
Prepare To Install Replacement Generator
SAFETY….PRIORITY #1
A Motion Analysis Contingency Plan was created in case the service water piping in “B” cubicle is left in place
The Contingency Plan steps are located here:
EC/ED 67484 R1Attachment Z10
Generator “B” Installation
NOTE:
Some of the insulation support assemblies shown on the replacement generator are placed in temporary locations for installation to eliminate interferences during rigging
These insulation support assemblies will be moved to their final destination after the replacement generator has been installed
Generator “B” InstallationInsulation Support Assemblies
Generator “B” InstallationPath assumes removal of interfering portions of the following as designated in the governing EC package: Service Water Piping 305-712, 305-713, 305-716, 305-717 and associated hangers
STEP #GENERATORMOVEMENT
MOVEMENTDESCRIPTION
CLEARANCES< 6 INCHES
NOTES
1Drift South 19 Inches
Provides clearance between main feedwater header and rcp steel
None < 6 Inches Generator Base @ 180'-6" EL
2 Lower 68 FeetPlaces main feedwater header and risers below rcp steel
5 25/32" between main feedwater header ring and rcp steel west of generator
Generator Base @ 112'-6" EL
3Drift North 10 Inches
Equalizes distances between interferences for next downward movement (step #4)
None < 6 Inches Generator Base @ 112'-6" EL
4 Lower 8 Feet
Places main feedwater header below vertical main feedwater rupture restraints and places aux. feedwater header above rcp steel
None < 6 Inches Generator Base @ 104'-6" EL
5Drift South 3 Inches
Provides clearance between rcp steel and aux. feedwater header ring on west side of generator
5 3/32" clearance between main feedwater header ring and main feedwater piping support
Generator Base @ 104'-6" EL
6 Drift East 3 Inches
Provides additional clearance between rcp steel and aux feedwater header ring on the west side of generator prior to next lowering step
5 3/32" clearance between main feedwater header ring and main feedwater piping support
Generator Base @ 104'-6" EL
Generator “B” Installation
STEP #GENERATORMOVEMENT
MOVEMENTDESCRIPTION
CLEARANCES< 6 INCHES
NOTES
7 Lower 4 Feet
Places main feedwater header and risers below vertical steel and moves aux. feedwater header ring below rcp steel
4 15/16" clearance occurs when aux feedwater header ring passes the rcp steel during this lowering movement
Generator Base @ 100'-6" EL
8 Drift West 3 InchesReturns generator to original western coordinates
None < 6 InchesGenerator Base @ 100'-6" EL
9 Lower 4 Feet 3 InchesMoves aux. feedwater header risers below rcp steel
None < 6 InchesGenerator Base @ 96'-3" EL
10 Drift North 12 InchesReturns generator to original coordinates prior to setting
1 7/8" vertical clearance between RCP steel and nearest aux feedwater header riser - should not impede movement because the diagonal clearance exceeds 6" (See Elevation #1)
Generator Base @ 96'-3" EL
11 Lower 1 Foot 3 Inches Sets generator None < 6 InchesGenerator Base @ 95'-0" EL
Generator “B” Installation
INITIAL STEPPLAN VIEW
Prior to manipulation
Generator base is at EL 180’-6”
INITIAL STEPELEVATION
Prior to manipulation
Generator base is at EL 180’-6”
Generator “B” Coordinates:(From Reactor Building center to center of generator base)
X = 11’-21/32”Y = 30’-4 ½”Z = 180’-6”
Generator “B” Installation
INITIAL STEPISOMETRIC VIEW
Prior to manipulation
Generator base is at EL 180’-6”
Generator “B” Installation
Generator “B” Installation
STEP #1PLAN VIEW
Drift South 19 Inches
Generator base is at EL 180’-6”
Provides clearance between main feedwater header ring and RCP steel for first downward movement
Generator “B” Installation
STEP #2ELEVATION VIEW
Lower 68 Feet
Generator base is at EL 112’-6”
Places main feedwater header and risers below RCP steel
Generator “B” InstallationSTEP #2PLAN VIEWCLEARANCES
Lower 68 Feet
Generator base is at EL 112’-6”
Places main feedwater header and risers below RCP steel
Clearances shown reflect dimensions between the main feedwater header ring and all potential interferences that occur during this lowering step
Generator “B” Installation
STEP #3PLAN VIEWCLEARANCES
Drift North 10 Inches
Generator base is at EL 112’-6”
Equalizes distances between interferences for next downward movement (Step #4)
Generator “B” Installation
STEP #3ELEVATION VIEWCLEARANCES
Drift North 10 Inches
Generator base is at EL 112’-6”
Clearances shown are between the main feedwater header outlets and the vertical steel on east and west sides
STEP #4ELEVATION VIEW
Lower 8 Feet
Generator base is at EL 104’-6”
Places main feedwater header below vertical main feedwater rupture restraints and places aux feedwater header above RCP steel
Generator “B” Installation
STEP #4PLAN VIEWCLEARANCES
Lower 8 Feet
Generator base is at EL 104’-6”
Places main feedwater header below vertical main feedwater rupture restraints and places aux feedwater header above RCP steel
Generator “B” Installation
STEP #4ELEVATION VIEWCLEARANCES
Lower 8 Feet
Generator base is at EL 104’-6”
Places main feedwater header below vertical main feedwater rupture restraints and places aux feedwater header above RCP steel
Clearances shown above are between the main feedwater header ring and the vertical steel on east and west sides
Generator “B” Installation
STEP #5PLAN VIEWCLEARANCES
Drift South 3 Inches
Generator base is at EL 104’-6”
Provides clearance betweenRCP steel and aux. feedwater header ring on west side
5 3/32” clearance between main feedwater header ring and main feedwater piping support
Generator “B” Installation
STEP #6PLAN VIEWCLEARANCES
Drift East 3 Inches
Generator base is at EL 104’-6”
Provides additional clearance between RCP steel and aux. feedwater header ring on west side
5 3/32” clearance between main feedwater header ring and main feedwater piping support
Generator “B” Installation
STEP #6ELEVATION VIEW LKG SOUTHCLEARANCES
Drift East 3 Inches
Generator base is at EL 104’-6”
Provides additional clearance between RCP steel and aux. feedwater header ring on west side
Clearances shown are between the main feedwater header ring and the vertical steel on east and west sides
Generator “B” Installation
STEP #7ELEVATION VIEW
Lower 4 Feet
Generator base is at EL 100’-6”
Places main feedwater header and risers below vertical steel and moves aux. feedwater header ring below RCP steel
Generator “B” Installation
STEP #7PLAN VIEWCLEARANCES
Lower 4 Feet
Generator base is at EL 100’-6”
Places main feedwater header andrisers below vertical steel and movesaux. feedwater header ring below RCP steel
4 15/16” clearance occurs when aux. feedwater header ring passes the RCP steel during this lowering movement
RCP steel clearance on east side is larger because the aux. feedwater header ring has a gap at that location
Generator “B” Installation
STEP #8PLAN VIEWCLEARANCES
Drift West 3 Inches
Generator base is at EL 100’-6”
Returns generator to originalwestern coordinates
11 15/32” clearance is between the RCP steel and the nearest aux. feedwater header riser. The aux. feedwater header ring is below the RCP steel at this point
Generator “B” Installation
STEP #9ELEVATION VIEW
Lower 4 Feet 3 Inches
Generator base is at EL 96’-3”
Moves aux. feedwater header risers below RCP steel
Generator “B” Installation
STEP #9PLAN VIEWCLEARANCES
Lower 4 Feet 3 Inches
Generator base is at EL 96’-3”
Moves aux. feedwater header risers below RCP steel
11 15/32” clearance is between the RCP steel and the nearest aux. feedwater header riser DURING this lowering movement
Generator “B” Installation
STEP #9ROTATED ELEVATION VIEWCLEARANCES
Lower 4 Feet 3 Inches
Generator base is at EL 96’-3”
Moves aux. feedwater header risers below RCP steel
Shows proximity of RCP steel to nearest aux. feedwater header riser (approximately 1 foot)
This clearance becomes critical during the next step (Drift North 12")
Generator “B” Installation
RCP STEEL
AUX. FW HEADER RISER
STEP #9ROTATED ELEVATION VIEWCLEARANCES
Lower 4 Feet 3 Inches
Generator base is at EL 96’-3”
Moves aux. feedwater header risers below RCP steel
Shows proximity of main steam hangers to aux. feedwater headerring and main feedwater header ring
Generator “B” Installation
STEP #9ELEVATION VIEWCLEARANCES
Lower 4 Feet 3 Inches
Generator base is at EL 96’-3”
Moves aux. feedwater header risers below RCP steel
Shows proximity of generator cylinder to blowdown hangers
Generator “B” Installation
STEP #10PLAN VIEWCLEARANCES
Drift North 12 Inches
Generator base is at EL 96’-3”
Returns generator to original coordinates prior to setting
10 29/32” clearance is between the aux. feedwater header ring and the vertical steel
Generator “B” Installation
STEP #10ELEVATION VIEWCLEARANCES
Drift North 12 Inches
Generator base is at EL 96’-3”
Generator “B” Installation
Elevation View Looking EastShows proximity of RCP steel on west side of generator to nearest aux. feedwater header riser after drifting north 12 inches
Elevation View Looking WestShows proximity of RCP steel on east side of generator to nearest aux. feedwater header riser after drifting north 12 inches
STEP #11ELEVATION VIEWFINAL STEP
Lower 1 Foot – 3 Inches
Generator base is at EL 95’-0”
Sets Generator
Generator “B” Installation
Successful Removal and InstallationTime to Celebrate!