creative project management

25
BY TOMAS DOS SANTOS, MANDAKH NYAMSUREN, CLARE JARRED AND ISLAM DZHABIEV [email protected] Our Project: Creating a more sustainable business

Upload: association-for-project-management

Post on 02-Jul-2015

343 views

Category:

Business


1 download

DESCRIPTION

This was one of the finalist team's presentations at the APM Wessex branch's PM Challenge finals night held on 25th February at Southampton Football Club.

TRANSCRIPT

Page 1: Creative Project Management

BY TOMAS DOS SANTOS, MANDAKH NYAMSUREN, CLARE JARRED AND ISLAM DZHABIEV

[email protected]

Our Project:

Creating a more sustainable business

Page 2: Creative Project Management

Agenda

• Project Delivery

• Project Documentation

• Project Financial Management

• Project Success & Benefits

• Main Issues Encountered

• Lessons Learned

Page 3: Creative Project Management

Project Delivery

Page 4: Creative Project Management

1st Stage of the Project

• Discussed project with Ambition Consultancy potential ideas

• Met with owners of Chocol8 and pitched project ideas

• Worked with Chocol8 and Ambition Consultancy to define our project

2nd Stage of the Project

• Delivery of activities

- Westbourne Christmas Fair

- Kaplan Language School event

• Produce all documentation for the project

• Monitoring and Controlling the project

3rd Stage of the Project • Final documentation

• Project Closure

Page 5: Creative Project Management

Planning

• Keep SMART

• Meet the project Objective

• Time scale (Schedule)

• Project Materials

Organisation

• Manage Constraints

(Scope, Schedule & Budget)

• Monitoring & Control

• Quality Control

Execution

•Manage the Budget &

Deliverables

• Assigned Tasks

• Gain Acceptance

• Manage Issues

• Communication Plan

• Project Team

• Implementation & Transition

Closure

• Document all the information

• Post – closure analyses

Page 6: Creative Project Management

Level of

Org

aniz

ati

onal eff

ort

Conceptualization/

Planning Organisation Management/Execution Closure

Page 7: Creative Project Management

Risk Management Strategy

Identify the Risk Areas

Assess the Risks

Develop Risk Management

Plan

Implement Risk

Management Action

Re-evaluate the Risks

Page 8: Creative Project Management

Project Documentation

Page 9: Creative Project Management

Initial Risk Assessment

Page 10: Creative Project Management

Roles and Responsibilities

R – Responsible

A – Accountable

C – Consulted

I - Informed

Page 11: Creative Project Management

Network Diagram

Page 12: Creative Project Management

Product Breakdown Structure

Page 13: Creative Project Management

Work Breakdown StructureChocol8 Project

[2] Running of event at Kaplan on

11th Dec

[2.3]Creation of student

discount card

[2.2]Producing

promotional material

[2.1]Running of the

stand

[3] Production of project

documentation

[3.2]APM Project

documentation

[3.1]Initial Project

documentation

[1] Running of the Christmas Fair on

7th Dec

[1.4]Production of promotional

material

[1.3]Create box for completed quiz

forms

[1.2]Creation of quiz

[1.1]Delivery of quiz at

Christmas fair

[1.2.c]Approval from

Chocol8 owners

[1.2.a]Research into

event

[1.2.b]Creation of questions

[1.2.d]Printing of quiz

[1.3.a]Design box

[1.3.b]Deliver box to

shop

[1.2.c]Approval from

Chocol8 owners

[1.4.a]Design leaflets

[1.2.b]Design posters

[1.2.d]Design t-shirts

[1.2.e]Printing of t-

shirts

[1.1.a]Dispensing of

quiz

[1.1.b]Collection of quiz

[1.1.c]Drawing and contacting

winner

[1.1..d]Giving of hamper

and photo of winner

[1.1.e]Collection of

email addresses

[2.1.a]Booking the

stand

[2.1b]Manning the

stand throughout day

[2.1.c]Distribution of discount card

[2.1..d]Collection of

email addresses

[2.2.a]Designing

promotional material

[2.2b]Approval from

Chocol8 owners

[2.2.c]Printing of

promotional materials

[2.2..d]Distribution of promotional

material

[2.3.a]Consultation with Chocol8

owners

[2.3b]Designing of card

[2.3.c]Printing of

discount card

[3.1.a]Produce Project

Proposal

[3.1.b]Produce Network

and Gantt

[3.1.c]Construct risk assessment

[3.1.d]Carry out

stakeholder analysis/ map

[3.2.a]Produce

amended Project Proposal

[3.2.b]Submit 3 reports

[3.2.c]Monitor budget

[3.2.d]Preparation for

final presentation

Quality

Check quality of promotional

material

Review quality of any

documentation

Brief team on day of events

Collect feedback from Chocol8

owners

ManagementTechnical

Briefing on project

Defining scope

Allocation of tasks

Reviewing progress

Liaising with Chocol8 owners

Page 14: Creative Project Management

Pow

er

High

Low

Keep Satisfied

Government Bournemouth University

Manage Closely

Chocol8 Owners

Students (Our Team)

APM (Sponsors)

Monitor Keep Satisfied

Local Community

Competitors

Kaplan International College

Suppliers

Low Interest High

Keep Satisfied

Government Bournemouth University

Manage Closely

Chocol8 Owners

Students (Our Team)

APM (Sponsors)

Monitor Keep Satisfied

Local Community

Competitors

Kaplan International College

Suppliers

Stakeholder Map

Page 15: Creative Project Management

Project Financial Management

Page 16: Creative Project Management

Project Budget Overview (£)

Expenditures Original(£) Revised(£) Final(£)

International student discount cards (Kaplan) 25 20 20

Colour leaflets double sided (Kaplan) 20 17.23 17.23

Colour leaflets double sided (Chocol8) 20 15 15

colour posters (Quiz) 10 9.98 9.98

colour poster (Kaplan) 10 9.98 9.98

Christmas Quiz 10 7.50 7.50

T-shirts 50 39.96 39.96

Hamper (Quiz) 90 60 60

Hamper (Kaplan) 40 25 25

Box for completed quiz forms 5 5 5

Sample chocolates (Kaplan) 35 28 28

Ribbon to wrap around quiz forms 5 5 5

Total Project Costs 320 245.65 245.65

Page 17: Creative Project Management

Cost Performance Index

Cost performance index (CPI) £0.97 Unit

Budgeted cost of work performed (BCWP) £242.67

Actual cost of work performed (ACWP) £250.65

Schedule performance index (SPI) 34 days

Budgeted cost of work scheduled (BCWS) 238.20

Schedule Variance

Budget at completion (BAC) £242.65

Schedule variance (SV) £235.27

Variance at completion (VAC) £8.02

Estimate at completion (EAC) £234.63

Note: The results presented in this report are based on the activities and expenditures made during the project. Some of the results are based on the calculation of the budget

given for the project and the amount expended for every activity and material used for completion of the project.

Page 18: Creative Project Management

Project Success & Benefits

realised

Page 19: Creative Project Management

Project’s Outcomes

The project helped Chocol8 to develop a sustainable approach for its business and the number of young people visiting the store have increased.

Over 100 e-mail addresses were collected and forward to Ambition Consultancy for further use for Chocol8’s online business.

Both local community and Kaplan students have received seasonal deals products with more customised services.

More local people are aware the existence of Chocol8 in Westbourne through both Christmas fair and Kaplan event.

Page 20: Creative Project Management

How we measured the project’s success

• Good project plan

• Open communication within the team

• Careful Risk Management

• Managing the project Expectation

• Control the changes within the project

• Review of the scope of the project

• Good deliverables

• Strong Project Closure

Page 21: Creative Project Management

Main Issues Encountered

Page 22: Creative Project Management

Unwillingness to participate from some individuals

Problems to get budget on time for the events

Weather condition

Monitoring the project

Cost constraints

Page 23: Creative Project Management

Lessons Learnt

Page 24: Creative Project Management

Lessons Learnt

Control &

Monitoring the

Project

Manage all the

project’s

element

Skills &

Strengths of the

Team

Constant

changes within

the project

Communication

Risks Decision Making

Paper Work &

Documentation

Page 25: Creative Project Management

Thank you for listening…

Any Questions?

[email protected]