c.tower.docx

Upload: mohsin-majeed

Post on 02-Jun-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 c.tower.docx

    1/5

    Subject: ORB-II COOLING TOWER SYSTEM

    BYCO purchased three pumps and 5 fans of a cooling water system from Milford Haven UK

    along with Refinery. There were four pumps at Milford Haven, two motor driven while two

    turbines driven. One Large capacity motor driven pump was missing during the time of

    purchase. Bosicor purchased new cells along with partial piping, side stream filters + pump.

    At first stage BYCO will run with three cells commissioned along with three pumps (one

    motor and two turbines driven). Specs of pumps and fans are given below:

    Milford Haven Refinery cooling water system was designed to reject 160.8MMBtu/h heat

    with its temperature change of 30oF (110- 80oF). So, the water circulation rate was around

    11000 gpm. Design conditions were as follows:

    Sr.No Parameter Summer

    1. Supply temperature, oF 80

    2. Return temperature, oF 110

    3. Ambient temperature (avg), oF 85

    4. Wet Bulb temperature, (avg), oF 75

    5. Relative Humidity, % 65 -

    At Milford Haven, there were two cooling towers. One cooling tower had two cells while the

    other had three cells. Two cells cooling tower had 16ft dia, 6 blades of GRP fans with 60hP

    motors while three cells cooling tower had 16ft dia, 4 blades of FRP fans with 50hP drivers.

    Two cells tower was feeding to VDU and Isomerization unit & Plat splitter unit while other

    process units were with 3 cells tower.

    1. Cooling Water pumps, Flow (5160gpm), head (175.4ft) and power 320 hp Motor/Turbine

    (1/1)

    2. Cooling Water pumps, Flow (6000gpm), head (161.7ft) and power 400 hp Motor/Turbine

    (1/1). Pump with motor is missing.

    3. Fans, 16 ft dia, 6 blade FRP 60 hP Motor 3

    4. Fans, 16 ft dia, 4 blades FRP 50 hP Motor 2

  • 8/11/2019 c.tower.docx

    2/5

    Ambient conditions in Pakistan are hotter than that at Milford Haven and they are as

    follows:

    Sr.No Parameter Summer

    1. Supply temperature, oF 90

    2. Return temperature, oF 120

    3. Ambient temperature (avg), oF 95

    4. Wet Bulb temperature, (avg), oF 85

    5. Relative Humidity, % 65

    So hot weather would require higher water circulation rate and/or increase in heat transfer

    area. To have more water circulation rate, provision has been taken to add 3 more cells.

    Only one additional pump will handle the future additional requirement of the water.

    However, current piping network, along with available differential head of pumps, will not

    be able to handle the additional water circulation rate and piping network debottlenecking

    would be required.

    For initial Refinery operation, 5 cells (induced draft counter flow) of each capacity 540

    m3/hr have been selected in order to achieve heat rejection of 160 MM BTU/HR.

    BYCO is installing 4 cells in first phase with refurbished rotating equipment (Fan motors,

    gear drives, shafts, fan blades & complete fan assembly), provided by BYCO while rest of

    cooling tower parts are in scope of supplier.

    Side Stream Filtration

    Side stream Filtration system has been designed to keep the turbidity level below 1 NTU by

    removing suspended solids. The design flow rate of the system is 600 gpm. Filtration

    system has two filters and one pump. It has been provided with line from main cooling

    water supply pumps.

    Filters are sand filled units which will operate at certain pressure drop. At specified

    pressure drop one of the filters will be taken off the line and will go on regeneration /

    backwashing while the other will be on line.

    Details & operational sequence of Side stream filter package is given in attached doc# SP-J-

    001.

    Chemical Dosing System:-

  • 8/11/2019 c.tower.docx

    3/5

    Chemical dosing system requirements are given in attached doc# 1197-22-CH-1502.

    COOLING TOWER DESIGN PARAMETERS

    Circulation rate m3/hr 2160

    No. of cells No. 4

    Summer Case

    Supply temperature 0C 32

    Return temperature 0C 47

    Range 0C 15

    Wet bulb temperature(Avg) 0C 29

    Approach 0C 3

    Relative Humidity % 65

    COOLING TOWER BASIN DIMENSIONS

    Length m 12.825

    Width m 8.7

    Depth 2.35

    Volume m3 262.2

    No. of basin 2

    Total Volume m3 524

    SYSTEM VOLUME

    ONE HEADER

    Pipe dia inch 20

    Length m 1000

    2nd HEADER

    Pipe dia inch 16

    Length m 1000

    2NDheader will2nd header will be in operation in future when

    cooling tower capacity would be 2700 m3/hr

    LABORATORY RESULTS MAKE UP WATER COOLING WATER

    Target Target

    pH 7.00 8 - 9

  • 8/11/2019 c.tower.docx

    4/5

    TDS ppm (as CaCO3) 300 - 350 < 1500

    NaCl ppm (as CaCO3) 50 - 70 < 500

    T.HARD ppm (as CaCO3) 89 - 150 < 800

    Ca HARD ppm (as CaCO3) 70 - 110 < 500

    M. ALK ppm (as CaCO3) 90 - 150 < 700

    ZINC - 1 - 2

    TO bemaintain

    FREE HALOGEN (B) -

    CONC. FACTOR (NaCl) - 5.0 - 6.0

    CONC. FACTOR (TDS) - 5.0 - 6.0

    RYZNAR INDEX:

  • 8/11/2019 c.tower.docx

    5/5

    As soon as all parameters are normalized, normal dosages of the chemicals

    shall be followed, and a corrosion coupon shall be installed in corrosion

    coupon assembly, corrosion coupon is lying with our rep. at site.

    We are already conducting biological counts test at site, you may ask your

    engineer to coordinate with our rep. for timing schedule.

    Cooling Tower is operated at high CF and TDS level, therefore, Turbidity hasno significant role in cooling water chemistry, however monitoring of

    suspended solids in cooling water circuit can help to address and resolve

    the sludge accumulation issue.