© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. Current Status of MHI CO 2 Capture Plant Technology and Commercial Experiences 2014 CO 2 Conference Week; The 12 th Annual (2014) EOR Carbon Management Workshop, TX December 9 th , 2014 Mitsubishi Heavy Industries, LTD. Takashi Kamijo

Upload: dothien

Post on 15-Mar-2018

227 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.

Current Status of MHI CO2 Capture Plant Technology and Commercial Experiences

2014 CO2 Conference Week; The 12th Annual (2014) EOR Carbon Management Workshop, TX December 9th, 2014 Mitsubishi Heavy Industries, LTD. Takashi Kamijo

Page 2: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 2

Contents

1. Introduction of KM CDR® Process

2. Application of KM CDR® Process to CO2 EOR

3. Latest MHI CO2 Capture Project

4. Summary

Page 3: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.

1. Introduction of KM CDR® Process

Page 4: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

Proprietary Technology by MHI & Kansai Electric Power Company (KEPCO) Hindered Amine Solvent “KS-1TM” & Proprietary equipment

Advantages

KS-1TM solvent - High CO2 Loading - Negligible Corrosion - Negligible Solvent Degradation

Process - Low Utility & Solvent Consumption - Easy operation & Maintenance

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 4

MHI CO2 Capture Process: KM CDR® Process

Page 5: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

Advanced CO2 Capture Process – MHI’s Own Technology

MHI CO2 Capture Technology [KM-CDR Process®]

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. Confidential 5

Page 6: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

2006 India (Aonla) 450 Mt/d

2009 India (Kakinada) 450 Mt/d 5

2011 Pakistan 340 Mt/d 9

2012 India (Vijaipur) 450 Mt/d

2011 U.S.A (SoCo) 500 Mt/d 11

12

13 2016 U.S.A (WA Parish) 4,776 t/d

MHI is a World leading LARGE-SCALE post combustion CO2 capture technology licensor, with 11 commercial PCC plants in operation

7

2014 Qatar 500 Mt/d

2009 Bahrain 450 Mt/d

6 2010 UAE 400 Mt/d

3

4 2006 India (Phulpur) 450 Mt/d

8

10

2 2005 Japan 330 Mt/d

2010 Vietnam 240 Mt/d

1 1999 Malaysia 210 Mt/d

Plants under construction

MHI CO2 Capture Reference Plants

Plants under operation

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 6

Page 7: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

Commercial Experiences

2005 330 t/d Japan

2009 450 t/d India

2006 450 t/d India

1999 200 t/d Malaysia

CO2 Recovery (CDR) Plant – IFFCO Phulpur Unit (India)

2006 450 t/d India

CO2 Recovery (CDR) Plant – IFFCO AonlaUnit (India)

2010 400 t/d UAE

2009 450 t/d Bahrain

2010 240 t/d Vietnam

2011 340 t/d Pakistan

2012 450 t/d India

2014 500 t/d Qatar

7 © 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. Confidential

1999 210 t/d Malaysia

2016 4,776 t/d U.S.A.

Page 8: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. Confidential 8

What is Amine Emission ? Amine is contained in treated gas from Absorber

and is one of VOC source.

MHI discovered the first in the World in 2010 that SO3 accelerates amine emission drastically. Reference: Electric Power Research Institute (EPRI).

2011. “Amines for Post-Combustion Capture”

This is common phenomena among all amine CO2 capture processes.

Amine Emission form CO2 Capture Plant

Page 9: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. Confidential 9

MHI Amine Emission Reduction Technology (1)

MHI Amine Emission Reduction Technology

Deep understanding of Amine emission phenomena through abundant R&D activities.

Already incorporated operation data and lesson

learned from Commercial Plants into current Parish Unit 8 project design.

Proprietary Emission Reduction System (MHI Patent), including Proprietary Demister.

Page 10: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 10

SO3 in flue gas from power plant significantly increases amine emission from CO2 absorber outlet. This will cause increase solvent consumption and VOC significantly MHI proprietary amine emission reduction system drastically reduce amine emission – VOC figures and solvent consumption Applied for multiple patents and some were already granted

Item Before Modification

After Modification

SO3 concentration at Quencher inlet [ppm] 2.1-2.7 2.3-3.6 Amine (KS-1) emission [ppm] 12 - 35 0.7 - 3 Solvent consumption Base 1/4

Before modification After modification

Amine Emission

Page 11: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.

2. Application of KM CDR® Process to CO2 EOR

Page 12: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 12

Application of KM CDR® Process to CO2 EOR (1/2)

Boiler FGD SCR ESP CO2 Injection to

Oil Reservoir

CO2 Recovery

CO2 Compression Dehydration

Utilities

Power Plant

CO2 Purity CO2: App 99.95% Impurity: Others are mostly nitrogen and trace O2

Page 13: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 13

Application of KM CDR® Process to CO2 EOR (2/2)

Page 14: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.

3. Latest MHI CO2 Capture Project

Page 15: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 15

Southern Company Plant Barry

500 Metric TPD Demonstration Plant

Flue gas demister and outlet

CO2 absorber (lower) and Water wash (upper) column

Solvent regeneration (“CO2 stripper”) column

CO2 compression and dehydration unit

Flue gas inlet

Flue gas quench column

World’s First Integrated CCS plant from Coal-fired Power Plant to CO2 injection

Page 16: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

*As of August 31th, 2014

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 16

500 Metric TPD Integrated CCS Demo PJ (1/2)

CO2 Capture and Compression SCS/MHI collaboration with partners KM-CDR® capture technology

Transportation and Sequestration DOE SECARB Phase III “Anthropogenic Test” 12 mile CO2 pipeline to Citronelle Dome

World’s First CCS Project integrated with Amine-based Post Combustion Process and CO2 Injection

Reference: Denbury, “SECARB - Plant Barry to Citronelle”, Knowledge Sharing Conference – Mobile, May 17, 2012

Items Results Total Operation Time * hrs 12,400 Total Amount of Captured CO2 * metric tons 230,100 Total Amount of Injected CO2 * metric tons 115,500

Gas In for CO2 Capture Plant: June, 2011 CO2 injection started on August 20th, 2012 100,000 metric tons of CO2 injection was achieved as of October 29th, 2013

<Project Overview>

<Operation Status>

Page 17: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 17

500 Metric TPD Integrated CCS Demo PJ (2/2)

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

180,000

200,000

Jun-11 Sep-11 Dec-11 Mar-12 Jun-12 Sep-12 Dec-12 Mar-13 Jun-13 Sep-13 Dec-13

CO

2[m

etric

ton]

CO2 Captured [ton]

CO2 Transportation [ton]

CO2 Captured [ton]CO2 Transportation [ton]

Boiler Off-line

10,000 tonsInjected

Injection Begins8/20/12

Operation History

Page 18: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 18

500 Metric TPD Integrated CCS Demo PJ (2/2)

Operation Reliability > 98% Reliability calculation basis Remarks *1) Operation hours does not contain commissioning period *2) Unexpected S/D is defined as a period of outage by operation malfunction. Plant outage for test implementation purpose and test originated purpose is excluded

𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹 =𝑶𝑶𝑹𝑶𝑹𝑹𝑹𝑶𝑶 𝒉𝑶𝒉𝑶𝒉

𝑶𝑶𝑹𝑶𝑹𝑹𝑹𝑶𝑶 𝒉𝑶𝒉𝑶𝒉 + 𝑼𝑶𝑹𝑼𝑶𝑹𝑼𝑹𝑹𝑼 𝑺/𝑫 𝑶𝑹𝑶𝑹𝑶𝑼

Page 19: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

CO2 Capture Plant for CO2-EOR

Flue Gas Quencher

Absorber

Regenerator

CO2 Compressor Cooling Tower

Project owner: NRG Energy Inc. and JX Nippon Oil & Gas Exploration Corporation Location:NRG WA Parish Power Plant near Houston, TX. Flue gas source: 240MWe slipstream from an existing 650MW coal-fired boiler CO2 concentration: 11.5% CO2 capture capacity:4,776 TPD CO2 recovery ratio: 90% CO2 Use: Enhanced Oil Recovery (EOR) Transport: 12 inch diameter pipeline, Approximately 81 miles Injection Site: West Ranch oil field in Jackson County, TX Operation Start:4th Quarter, 2016

The worlds largest CO2 capture plant from an existing coal-fired power plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 19

Page 20: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.

4. Summary

Page 21: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 21

Summary

MHI can provide cost competitive and reliable CO2 capture plant from flue gas based on our abundant commercial experiences Southern Company’s Plant Barry 500 TPD CCS plant has successfully completed its 2nd year of operation MHI has started to construct the world largest CO2 capture and compression plant near Houston, Texas for NRG Energy Inc. and JX Nippon Oil & Gas Exploration Corporation CO2 capture from flue gas can contribute to global warming issue and useful for CO2 EOR

Page 22: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.

Appendix

Page 23: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

Deployment of R&D Facilities for specific CO2 capture testing. More than 25 years R&D Experience

(A) R&D laboratories (MHI Technologies and Innovation Headquarters) (B) 2.0 TPD Nanko Osaka pilot plant from 1991 (C) 1.0 TPD Hiroshima pilot plant (D) 0.2 TPD mobile test unit (E) Absorber 1 by 1 scale test plant in Mihara (400 MW equivalent) (F) 10 TPD Matsushima pilot for testing coal fired flue gas (G) 500 TPD Barry CCS demonstration plant in Alabama, (25MW equivalent)

To help protect your privacy, PowerPoint has blocked automatic download of this picture.

B C F

MHI - R&D Strength & Experience

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 23

G

2.0TPD Nanko Pilot Plant (Kansai Electric Power Co.)

1.0TPD Hiroshima Pilot Plant (MHI’ R&D Center)

10TPD Matsushima Pilot Plant (J-Power)

500TPD Barry Demonstration Plant (Southern Company)

Page 24: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

Summary of Coal-Fired Pilot & Demonstration Plants

Location Capacity Client/Host Flue gas source

Purpose Start up

U.S.A. SoCo Yates power station

0.2 MT/D Mobile unit (Southern Company)

Coal fired boiler flue gas

R&D September 2010

Japan MHI R&D Center

1 MT/D - Coal fired boiler flue gas

R&D April 1999

Japan Matsushima power station

10 MT/D J - Power Coal fired boiler flue gas

R&D July 2006

U.S.A. SoCo Barry power station

500 MT/D

Southern Company

Coal fired boiler flue gas

R&D June 2011

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 24

MHI conducted R&D at various stages of the test for coal-fired flue gas. 500 TPD demonstration plant integrated with coal-fired power plant and CO2 injection started in June, 2011. The demonstration test results verified the high reliability of the KM-CDR® Process

Page 25: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 25

CO2 Capture & Compression Test Items

Item Main Results

Initial Baseline Testing

• Verified that actual utility and solvent consumption were lower than the design but within the expectation (CO2 removal efficiency: 90%, CO2 capture rate: 500MTPD).

• Proven that KM-CDR® Process can follow the operation condition of CO2 injection • Captured CO2 quality is within the criteria of the pipeline and CO2 injection site

Emissions and Waste Stream Monitoring

• Successfully demonstrated amine emission reduction technologies under the various SO3 concentration condition (2013)

• Measured total Volatile Organic Compound (VOC) emissions and verified that the commercial scale CO2 capture plant using KM-CDR® Process will be acceptable

Process Parametric Test and Performance Optimization

• Verified operation performance under several controlled operating parameters changes (2011-2012)

• Achieved 0.95 ton-steam/ton-CO2 by optimizing steam consumption (2011)

Dynamic Response Evaluation Test

• Carried out continuous control testing to optimize the operation condition with self-developed dynamic simulator. The system successfully controlled the operation condition (Oct. 2013)

Long Term Impurities Influence Test

• Achieved 100,000 metric tons of CO2 injection without any operational issues • Verified that the amine emission increased as a result of higher SO3 loading

(Oct. 2011) • Verified that the impurities were removed from the solvent by reclaiming operation

(2012, 2013)

Page 26: Current Status of MHI CO Capture Plant Technology and ... · PDF file2 Capture Plant Technology and Commercial Experiences ... Recovery (CDR) Plant – IFFCO Phulpur Unit ... Plant

Basic Process Flow Diagram

© 2014 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 26

Post-Combustion CO2 capture process using MHI proprietary KS-1™ solvent MHI developed the KM-CDR® process with Kansai Electric Power Co. since 1990

Flue Gas Quencher

Absorber Regenerator

MHI Energy Saving System

CO2 Compressor

C.W. (Cooling Water)

C.W.

C.W.

Steam

Compressed CO2

Treated Flue Gas

The flue gas is cooled to a process desired

temperature.

90% of CO2 is recovered from the flue gas by contacting with

KS-1TM solvent

CO2 is stripped from KS-1TM solvent in the Regenerator