DAMAC Heights Project

Prepared by: Sameh Ibrahim Reviewed by: Fuad Hasan

Page 2: DAMAC Heights Project

DAMAC Heights Project DAMAC Heights Tower Location

Page 3: DAMAC Heights Project

Project Statistics

Project Description

Page 4: DAMAC Heights Project

DAMAC Heights Project Site Plan

Page 5: DAMAC Heights Project

Project Description

DAMAC Heights Tower located at plot No.A3A,392-569 at Dubai Marina and

comprises of the following criteria;

Dates/Cost Projection Date of Forecast Completion: 14-May-16 Project Value: 508,301,847 AED

Area/Height Calculations Tower Built Up Area: 141,542 m2 Tower Height: 335 m

Floor Distribution Non-Branded Flats: Level 6 to 42 Branded Flats (FENDI): Level 43 to 84

Parking Slots /Rooms Count Total Flats: 637 1 Bedroom: 282 2 Bedroom: 258 3 Bedroom: 86 4 Bedroom: 9

5 Bedroom: 2 Parking Slots: 649 Retail: 1

DAMAC Heights Project

Floors Count Basement Floors: 5 Podium Floors: 5

Typical Floors: 79 Mechanical Floors: 3 Top Roof: 1

Page 6: DAMAC Heights Project

Life Style

Podium 5 is called Life Style and includes the following service areas: 1- Swimming Pool 2- Bar Area 3- Residential Lounge 4- Kids Room 5- Cinema 6- Male Gym 7- Female Gym 8- Men SPA 9- Woman SPA 10- Reception 11- Gymnasium Room

DAMAC Heights Project

Fendi Entrance

At Ground floor, there is special Entrance Lobby and Lift Lobby for Branded Flats (FENDI)

Page 7: DAMAC Heights Project

Client Damac Gulf Properties

Supervision Consultant AECOM Middle East

Master Developer Emaar Properties

Main Contractor Arabtec Construction

L.L.C

MEP REMCO CO. L.L.C

Elevators Toshiba Middle East

External Facade ALICO CO. Ltd.

DAMAC Heights Project

Project Stakeholders

Client- Consultants

Designer Ramboll Middle East

Main Contractor

Key Sub-Contractors

BMU DANWAY L.L.C

Fit Out for Non Branded Flats JC Maclean

Page 8: DAMAC Heights Project

QATAR ACCOUNT

MANAGEMENT

PROGRAM

Main Packages-Delivery Structural & Finishes Package

Firm: Arabtec Construction L.L.C Contract Value: 244,747,597 AED

External Façade Package

Firm: ALICO CO. Ltd Contract Value: 62,967,933 AED

Electromechanical Package Firm: REMCO CO. L.L.C Contract Value: 82,000,000 AED

Fit Out Package (non branded flats)

Firm: JC Maclean Contract Value: 14,747,525 AED

DAMAC Heights Project

Page 9: DAMAC Heights Project

QATAR ACCOUNT

MANAGEMENT

PROGRAM

Main Packages-Delivery

Elevators Package Firm: Toshiba Middle East Contract Value: 11,332,200 AED

Fit Out Package (Life Style / Main entrance)

Firm: To be nominated Contract Value: N/A

BMU Package

Firm: DANWAY L.L.C Contract Value: 1,300,000 AED

Fit Out Package (branded flats)

Firm: To be nominated Contract Value: N/A

DAMAC Heights Project

Page 10: DAMAC Heights Project

QATAR ACCOUNT

MANAGEMENT

PROGRAM

AECOM Delivery Team

Project Control Architectural Structural MEP (Mechanical) MEP (Electrical) HSE

Planning Manager Sameh Ibrahim

Sr. Architect Ramon Olavydez

Inspector Sanat Rane

Sr. Struct. Engineer Reuben Samaniego

Sr. Struct. Engineer Ali Mahmoud

Mech. Manager Ahmed Raouf

Sr. Mech. Engineer Aiman Al-Nakawa

Elect. Manager Kousay Al Kureishi

Sr. Elec. Engineer Mateen Khawajah

Document Control Abdul Latheef

Project Secretary Abdulla Muhyiden

Project Director Fuad Hasan

Sr. Resident Engineer Radhi Mohamed

HSE Officer Mohammad Faisi

Inspector Roberto Magtira

Inspector Percival Vicente

Inspector Shibu Mathew

Admin

Inspector Frederick Abellar

Fit out Inspector TBA

DAMAC Heights Project

Page 11: DAMAC Heights Project

An Interview was run by Construction Week Online Magazine with DAMAC Senior Project Manager, Samer H. Skaik

Damac Heights Tower

Construction Week Online Dubai, United Arab Emirates

DAMAC Heights Project

Project Headlines

Page 12: DAMAC Heights Project

Fendi Apartments

Key Design Features

Page 13: DAMAC Heights Project

DAMAC Heights Project

Typical Floor Layout

Page 14: DAMAC Heights Project

Fendi Casa Apartments Bed Room

Page 15: DAMAC Heights Project

Fendi Casa Apartments Living Room

Page 16: DAMAC Heights Project

Fendi Casa Apartments Master Bathroom

Page 17: DAMAC Heights Project

Fendi Casa Apartments Powder Room

Page 18: DAMAC Heights Project

Fendi Casa Apartments Walk-IN Closet

Page 19: DAMAC Heights Project

Life Style @ Podium 5

Key Design Features

Page 20: DAMAC Heights Project

DAMAC Heights Project

Life Style Layout @ Podium 5

Page 21: DAMAC Heights Project

DAMAC Heights Project

Life Style ID @ Podium 5

Page 22: DAMAC Heights Project

Life Style Kids Play Area

Page 23: DAMAC Heights Project

Life Style Cinema

Page 24: DAMAC Heights Project

Life Style Bar Lounge

Page 25: DAMAC Heights Project

Life Style Gym Room

Page 26: DAMAC Heights Project

Life Style Ladies Jacuzzi

Page 27: DAMAC Heights Project

Life Style Ladies Make-Up

Page 28: DAMAC Heights Project

Life Style Lounge Area

Page 29: DAMAC Heights Project

Life Style Male Jacuzzi

Page 30: DAMAC Heights Project

Life Style Reception

Page 31: DAMAC Heights Project

Non Branded Entrance @ Ground Floor

Key Design Features

Page 32: DAMAC Heights Project

DAMAC Heights Project

Non Branded Entrance Layout @ Ground Floor

Page 33: DAMAC Heights Project

Non Branded Entrance Entrance Lobby

Page 34: DAMAC Heights Project

Non Branded Entrance Lift Lobby

Page 35: DAMAC Heights Project

Fendi Casa Entrance @ Ground Floor

Key Design Features

Page 36: DAMAC Heights Project

DAMAC Heights Project

Fendi Entrance Layout @ Ground Floor

Page 37: DAMAC Heights Project

Fendi Entrance Entrance Lobby

Page 38: DAMAC Heights Project

Fendi Entrance Reception Area

Page 39: DAMAC Heights Project

Site Works

Current Progress

Page 40: DAMAC Heights Project

DAMAC Heights Project

Project Schedule

Statistics – May 2014

Time

SPI EV / PV 0.91

SV EV - PV (AED m) -17.7

Float (MS01) Days Float

Remaining -79

Area Performance Indicators Measure This Month Last Month

0.91

-79

12.5 11.4

-6

Actual %

Structure Delay

Planned %

Schedule Performance

Index

Project Potential Delay

Page 41: DAMAC Heights Project

DAMAC Heights Project

Negative Floats Contour

Risk Rating

Page 42: DAMAC Heights Project

Structure - Slab at Level 20

Structural Progress

Levels

6th

7th

8th

9th

10th

11th

12th

13th

14th

15th

16th

17th

18th

19th

20th

21st

22nd

23rd

Concrete Pouring

Core Walls Slabs Columns Stairs

100% 100% 100% 100%

100% 100% 100% 100%

100% 100% 100% 100%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 100% 0%

100% 100% 50% 0%

100% 0% 0% 0%

100% 0% 0% 0%

40% 0% 0% 0%

38.8

9%

0.6

2%

4.2

1%

37.9

8%

0.1

7%

0.2

% %Pld %Act

Page 43: DAMAC Heights Project

MEP – H/L Installations at Level 6

High Level Installation

Levels

6th

7th

8th

9th

10th

11th

12th

13th

14th

15th

16th

HAVC Fire Fighting Plumbing Electrical

92% 95% 93% 79%

90% 86% 88% 56%

86% 86% 88% 56%

59% 86% 78% 44%

54% 86% 56% 44%

54% 76% 54% 35%

10% 38% 0% 35%

0% 48% 0% 35%

0% 0% 0% 35%

0% 0% 0% 35%

0% 0% 0% 35%

38.8

9%

0.6

2%

4.2

1%

37.9

8%

0.1

7%

0.2

%

%Pld %Act

MEP Progress

Page 44: DAMAC Heights Project

Architectural – Block Works at Level 6

Block Works

Levels

6th

7th

8th

9th

10th

11th

12th

13th

14th

15th

16th

Architectural Progress

Block Works

95%

95%

95%

85%

40%

0%

15%

0%

0%

0%

0%

38.8

9%

0.6

2%

4.2

1%

37.9

8%

0.1

7%

0.2

% %Pld %Act

Page 45: DAMAC Heights Project

Enabling Work– Pressure Grouting in Zone B

Zone B Construction

Enabling Work

Progress

Section

B-B

Due to the flood event that occurred in 2012 that caused

major flooding to the site. Pressure Grouting was

introduced as a method of reducing water infiltration.

The pressure grouting is still ongoing and is scheduled to

be completed by the 3rd week of June-14.

After completing the pressure grouting, the excavation

shall commence in Zone B and the remaining 11 stories of

that zone will take approx. 10 months.

The above event is the subject of an EOT claim and is

being negotiated between DAMAC and ATC.

Zone B

95% Pressure Grouting % Progress

Page 46: DAMAC Heights Project

Quality Assurance and Control

Current Progress

Page 47: DAMAC Heights Project

DAMAC Heights Project

Quality Assurance and Control

74% 26%

68 50

18

NCR Closed % NCR Opened %

Total NCR Raised Total NCR Closed

Total NCR Opened

Area Performance Indicators Measure This Month Last Month

Quality NCR Close Out Issued/Closed 68/50 59/41

Statistics – May 2014

Page 48: DAMAC Heights Project

DAMAC Heights Project

Quality Assurance and Control

Quality Improvement Measures

• Curre tly ATC keeps su itti g the o rete test results i ti ely a er as was instructed by AECOM.

• AECOM i stru ted ATC to su it the stru tural leara e efore the o e e e t of MEP work.

• AECOM is going to hold Quality Technical Meetings on weekly basis to monitor the

quality.

NCRs Root Cause

Key Quality Improvement Measures

Page 49: DAMAC Heights Project

Health and Safety

Current Progress

Page 50: DAMAC Heights Project

DAMAC Heights Project

Health and Safety

1201 8

3 4

64

Work Force Average Improvement Notices

issued

Near Misses First Aid Cases

Tool Box Talks

Area Performance Indicators Measure This Month Last Month

Statistics – May 2014

Health and

Safety Near Misses

No. of Near

Misses 3 0

Page 51: DAMAC Heights Project

Top 5 Risks

Project Risks

Page 52: DAMAC Heights Project

DAMAC Heights Project

Top 5 Risks

Risk ID Risk Event Cause Rating Risk Response Risk

Owner

RS_01 Flooding in Zone B

Existing ground cavities

that allows for the flow

of water through it.

Pressure Grouting has commenced

and is scheduled to be completed in

June 14.

DAMAC/

AECOM

RS_02

Delays in possessing

DEWA approval for LV

shop drawings and

delays in procuring LV

Panels and Bus Bars.

Late of issuing MEP IFC

drawings.

DAMAC has to finalize the ID design

for FENDI Apartments and then

RME has to issue the final MEP IFC

drawings to ATC.

DAMAC/R

ME

RS_03 Delays in pouring the

slab of level 30

8 days estimated cycle

will not be achieved as

the slab will need for 2

weeks at least.

AECOM highlighted this issue to

ATC in the weekly progress

meeting. ATC

RS_04 Delays In MEP high level

installations

Delays in giving access

from ATC to REMCO and

then delays from REMCO

in doing the installations

due to the shortage of

manpower.

ATC has to give full access to

REMCO on time. REMCO has to

increase the allocated manpower in

order to work concurrently in 5

levels.

ATC/

REMCO

RS_05 Delays in nomination of

the PS items

DAMAC's tenders

floating/awarding

process delayed.

DAMAC has to expedite the PS

items' procuring process in order to

avoid delaying the site works. DAMAC

0

1

2

3

4

5

Critical

Severe

Manageable

Negligible

Risk Rating

Page 53: DAMAC Heights Project

• Continuous design changes.

• Historical pre-existing issues.

• Soil improvement in Zone B.

“ Working with a Commercial Developer

demands a Bespoke

Approach ”

Project Challenges

• Employer procurement system.

• Management and coordination of client processes..

• Lack of detailed scheduling specification within the contract.

Page 54: DAMAC Heights Project