damac heights project
TRANSCRIPT
DAMAC Heights Project
Prepared by: Sameh Ibrahim Reviewed by: Fuad Hasan
DAMAC Heights Project DAMAC Heights Tower Location
Project Statistics
Project Description
DAMAC Heights Project Site Plan
Project Description
DAMAC Heights Tower located at plot No.A3A,392-569 at Dubai Marina and
comprises of the following criteria;
Dates/Cost Projection Date of Forecast Completion: 14-May-16 Project Value: 508,301,847 AED
Area/Height Calculations Tower Built Up Area: 141,542 m2 Tower Height: 335 m
Floor Distribution Non-Branded Flats: Level 6 to 42 Branded Flats (FENDI): Level 43 to 84
Parking Slots /Rooms Count Total Flats: 637 1 Bedroom: 282 2 Bedroom: 258 3 Bedroom: 86 4 Bedroom: 9
5 Bedroom: 2 Parking Slots: 649 Retail: 1
DAMAC Heights Project
Floors Count Basement Floors: 5 Podium Floors: 5
Typical Floors: 79 Mechanical Floors: 3 Top Roof: 1
Life Style
Podium 5 is called Life Style and includes the following service areas: 1- Swimming Pool 2- Bar Area 3- Residential Lounge 4- Kids Room 5- Cinema 6- Male Gym 7- Female Gym 8- Men SPA 9- Woman SPA 10- Reception 11- Gymnasium Room
DAMAC Heights Project
Fendi Entrance
At Ground floor, there is special Entrance Lobby and Lift Lobby for Branded Flats (FENDI)
Client Damac Gulf Properties
Supervision Consultant AECOM Middle East
Master Developer Emaar Properties
Main Contractor Arabtec Construction
L.L.C
MEP REMCO CO. L.L.C
Elevators Toshiba Middle East
External Facade ALICO CO. Ltd.
DAMAC Heights Project
Project Stakeholders
Client- Consultants
Designer Ramboll Middle East
Main Contractor
Key Sub-Contractors
BMU DANWAY L.L.C
Fit Out for Non Branded Flats JC Maclean
QATAR ACCOUNT
MANAGEMENT
PROGRAM
Main Packages-Delivery Structural & Finishes Package
Firm: Arabtec Construction L.L.C Contract Value: 244,747,597 AED
External Façade Package
Firm: ALICO CO. Ltd Contract Value: 62,967,933 AED
Electromechanical Package Firm: REMCO CO. L.L.C Contract Value: 82,000,000 AED
Fit Out Package (non branded flats)
Firm: JC Maclean Contract Value: 14,747,525 AED
DAMAC Heights Project
QATAR ACCOUNT
MANAGEMENT
PROGRAM
Main Packages-Delivery
Elevators Package Firm: Toshiba Middle East Contract Value: 11,332,200 AED
Fit Out Package (Life Style / Main entrance)
Firm: To be nominated Contract Value: N/A
BMU Package
Firm: DANWAY L.L.C Contract Value: 1,300,000 AED
Fit Out Package (branded flats)
Firm: To be nominated Contract Value: N/A
DAMAC Heights Project
QATAR ACCOUNT
MANAGEMENT
PROGRAM
AECOM Delivery Team
Project Control Architectural Structural MEP (Mechanical) MEP (Electrical) HSE
Planning Manager Sameh Ibrahim
Sr. Architect Ramon Olavydez
Inspector Sanat Rane
Sr. Struct. Engineer Reuben Samaniego
Sr. Struct. Engineer Ali Mahmoud
Mech. Manager Ahmed Raouf
Sr. Mech. Engineer Aiman Al-Nakawa
Elect. Manager Kousay Al Kureishi
Sr. Elec. Engineer Mateen Khawajah
Document Control Abdul Latheef
Project Secretary Abdulla Muhyiden
Project Director Fuad Hasan
Sr. Resident Engineer Radhi Mohamed
HSE Officer Mohammad Faisi
Inspector Roberto Magtira
Inspector Percival Vicente
Inspector Shibu Mathew
Admin
Inspector Frederick Abellar
Fit out Inspector TBA
DAMAC Heights Project
An Interview was run by Construction Week Online Magazine with DAMAC Senior Project Manager, Samer H. Skaik
Damac Heights Tower
Construction Week Online Dubai, United Arab Emirates
DAMAC Heights Project
Project Headlines
Fendi Apartments
Key Design Features
DAMAC Heights Project
Typical Floor Layout
Fendi Casa Apartments Bed Room
Fendi Casa Apartments Living Room
Fendi Casa Apartments Master Bathroom
Fendi Casa Apartments Powder Room
Fendi Casa Apartments Walk-IN Closet
Life Style @ Podium 5
Key Design Features
DAMAC Heights Project
Life Style Layout @ Podium 5
DAMAC Heights Project
Life Style ID @ Podium 5
Life Style Kids Play Area
Life Style Cinema
Life Style Bar Lounge
Life Style Gym Room
Life Style Ladies Jacuzzi
Life Style Ladies Make-Up
Life Style Lounge Area
Life Style Male Jacuzzi
Life Style Reception
Non Branded Entrance @ Ground Floor
Key Design Features
DAMAC Heights Project
Non Branded Entrance Layout @ Ground Floor
Non Branded Entrance Entrance Lobby
Non Branded Entrance Lift Lobby
Fendi Casa Entrance @ Ground Floor
Key Design Features
DAMAC Heights Project
Fendi Entrance Layout @ Ground Floor
Fendi Entrance Entrance Lobby
Fendi Entrance Reception Area
Site Works
Current Progress
DAMAC Heights Project
Project Schedule
Statistics – May 2014
Time
SPI EV / PV 0.91
SV EV - PV (AED m) -17.7
Float (MS01) Days Float
Remaining -79
Area Performance Indicators Measure This Month Last Month
0.91
-79
12.5 11.4
-6
Actual %
Structure Delay
Planned %
Schedule Performance
Index
Project Potential Delay
DAMAC Heights Project
Negative Floats Contour
Risk Rating
Structure - Slab at Level 20
Structural Progress
Levels
6th
7th
8th
9th
10th
11th
12th
13th
14th
15th
16th
17th
18th
19th
20th
21st
22nd
23rd
Concrete Pouring
Core Walls Slabs Columns Stairs
100% 100% 100% 100%
100% 100% 100% 100%
100% 100% 100% 100%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 100% 0%
100% 100% 50% 0%
100% 0% 0% 0%
100% 0% 0% 0%
40% 0% 0% 0%
38.8
9%
0.6
2%
4.2
1%
37.9
8%
0.1
7%
0.2
% %Pld %Act
MEP – H/L Installations at Level 6
High Level Installation
Levels
6th
7th
8th
9th
10th
11th
12th
13th
14th
15th
16th
HAVC Fire Fighting Plumbing Electrical
92% 95% 93% 79%
90% 86% 88% 56%
86% 86% 88% 56%
59% 86% 78% 44%
54% 86% 56% 44%
54% 76% 54% 35%
10% 38% 0% 35%
0% 48% 0% 35%
0% 0% 0% 35%
0% 0% 0% 35%
0% 0% 0% 35%
38.8
9%
0.6
2%
4.2
1%
37.9
8%
0.1
7%
0.2
%
%Pld %Act
MEP Progress
Architectural – Block Works at Level 6
Block Works
Levels
6th
7th
8th
9th
10th
11th
12th
13th
14th
15th
16th
Architectural Progress
Block Works
95%
95%
95%
85%
40%
0%
15%
0%
0%
0%
0%
38.8
9%
0.6
2%
4.2
1%
37.9
8%
0.1
7%
0.2
% %Pld %Act
Enabling Work– Pressure Grouting in Zone B
Zone B Construction
Enabling Work
Progress
Section
B-B
Due to the flood event that occurred in 2012 that caused
major flooding to the site. Pressure Grouting was
introduced as a method of reducing water infiltration.
The pressure grouting is still ongoing and is scheduled to
be completed by the 3rd week of June-14.
After completing the pressure grouting, the excavation
shall commence in Zone B and the remaining 11 stories of
that zone will take approx. 10 months.
The above event is the subject of an EOT claim and is
being negotiated between DAMAC and ATC.
Zone B
95% Pressure Grouting % Progress
Quality Assurance and Control
Current Progress
DAMAC Heights Project
Quality Assurance and Control
74% 26%
68 50
18
NCR Closed % NCR Opened %
Total NCR Raised Total NCR Closed
Total NCR Opened
Area Performance Indicators Measure This Month Last Month
Quality NCR Close Out Issued/Closed 68/50 59/41
Statistics – May 2014
DAMAC Heights Project
Quality Assurance and Control
Quality Improvement Measures
• Curre tly ATC keeps su itti g the o rete test results i ti ely a er as was instructed by AECOM.
• AECOM i stru ted ATC to su it the stru tural leara e efore the o e e e t of MEP work.
• AECOM is going to hold Quality Technical Meetings on weekly basis to monitor the
quality.
NCRs Root Cause
Key Quality Improvement Measures
Health and Safety
Current Progress
DAMAC Heights Project
Health and Safety
1201 8
3 4
64
Work Force Average Improvement Notices
issued
Near Misses First Aid Cases
Tool Box Talks
Area Performance Indicators Measure This Month Last Month
Statistics – May 2014
Health and
Safety Near Misses
No. of Near
Misses 3 0
Top 5 Risks
Project Risks
DAMAC Heights Project
Top 5 Risks
Risk ID Risk Event Cause Rating Risk Response Risk
Owner
RS_01 Flooding in Zone B
Existing ground cavities
that allows for the flow
of water through it.
Pressure Grouting has commenced
and is scheduled to be completed in
June 14.
DAMAC/
AECOM
RS_02
Delays in possessing
DEWA approval for LV
shop drawings and
delays in procuring LV
Panels and Bus Bars.
Late of issuing MEP IFC
drawings.
DAMAC has to finalize the ID design
for FENDI Apartments and then
RME has to issue the final MEP IFC
drawings to ATC.
DAMAC/R
ME
RS_03 Delays in pouring the
slab of level 30
8 days estimated cycle
will not be achieved as
the slab will need for 2
weeks at least.
AECOM highlighted this issue to
ATC in the weekly progress
meeting. ATC
RS_04 Delays In MEP high level
installations
Delays in giving access
from ATC to REMCO and
then delays from REMCO
in doing the installations
due to the shortage of
manpower.
ATC has to give full access to
REMCO on time. REMCO has to
increase the allocated manpower in
order to work concurrently in 5
levels.
ATC/
REMCO
RS_05 Delays in nomination of
the PS items
DAMAC's tenders
floating/awarding
process delayed.
DAMAC has to expedite the PS
items' procuring process in order to
avoid delaying the site works. DAMAC
0
1
2
3
4
5
Critical
Severe
Manageable
Negligible
Risk Rating
• Continuous design changes.
• Historical pre-existing issues.
• Soil improvement in Zone B.
“ Working with a Commercial Developer
demands a Bespoke
Approach ”
Project Challenges
• Employer procurement system.
• Management and coordination of client processes..
• Lack of detailed scheduling specification within the contract.