DATA CENTER DESIGN OVERVIEWINTRODUCTIONIn the next couple of hours I will touch on various aspects of Data Center DesignThe intend today, is not to have a detailed discussion, but to have an overview only of various elements of Data Center DesignThe goal is to get feed-back in what topics the group is interested in so we can schedule a more detailed presentation in the future

Page 3: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

The following items will be discussed:Project Development and Execution ProcessOrganizing and StaffingBuilding Design: Interior/ExteriorPower DistributionProcess CoolingCommissioningEnergy Efficiency

Page 4: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

The Project Development and Execution Process (PDEP) consists of five phases1. Identify and Assess Opportunities

Clearly frame the goal to be pursued and insure alignment with business objectivesPerform a preliminary assessment of uncertainties and associated risksPlan for the next phase of the process

Page 5: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

PDEP (continued)2. Generate and Select Alternatives- Generate alternatives and reduce the

uncertainties of each alternative- Develop the expected value for selected

alternatives & select the preferred alternative

- Plan for the next phase of the process

Page 6: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

PDEP (continued)3. Develop Preferred Alternatives- Fully define the scope of the alternatives &

develop detailed execution plans- Check for expected value to meet business

objectives- Refine estimates & economic analysis to meet

funding requirements- Submit for funding approval, as appropriate

Page 7: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

PDEP (continued)4. Execute

Implement execution plan and finalize operating planCollect, analyze, and share metrics and lessons learned

Page 8: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

PDEP (continued)5. Operate and Evaluate

Monitor performance of the assetBenchmark performance of the assets against objectives and competitorsShare results and lessons learnedContinue performance assessment and identify other opportunities

Page 9: DATA CENTER DESIGN OVERVIEW
Page 10: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Organization and StaffingProject Manager familiar with Company Policy/OperationIn-House Personnel; i.e. Building EngineerArchitectAsset Protection ConsultantElectrical ConsultantMechanical ConsultantStructural ConsultantData Center Relocation Team

Page 11: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Site SelectionNew/Old/Own/Lease/Outsource BuildingEnvironmental HazardsTransportationAccess to SiteUtility ServiceTelecommunication Service

Page 12: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Project Total Data Center Requirements in sq. ft.

Hardware RequirementsPower RequirementsProcess Cooling RequirementAccess Floor RequirementSupport Space (Non-Raised Floor)Circulating Areas

Page 13: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Exterior ConsiderationUtilityAccess to Data CenterSecurityWall and roof Construction

Page 14: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Interior ConsiderationFloorsWallsBuilding Column SpacingHallwaysFreight ElevatorStorage/Uncrating AreaPower DistributionProcess CoolingWater Detection

Page 15: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

CommissioningCommissioning is a process that extends through all phases of the projectThe goal of commissioning is to obtain a facility that operates efficiently, according to the design intent

Page 16: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Commissioning (continued)Commissioning:

Provides owners with a facility that operates in accordance with original design intentReduces energy and operating costs by having systems function at maximum efficiencyReduces the number of contractor call backsReduces Occupant complaints due to discomfortProvides documentation, training and education for operators and facility managers

Page 17: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Commissioning (continued)The following should be in the commissioning specification

Responsibilities of parties involved in the projectDescription of the commissioning processRequirements for pre-functional performance testRequirements for functional performance testRequirements for O&M manualsRequirements for O&M trainingRequirements for documentationRequirements for “as-built” drawings

Page 18: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Energy EfficiencyEnergy Efficiency vs. Energy Conservation

…Both activities lower energy consumption. However, conservation implies a decrease in service; energy efficiency must meet or exceed the quality of service that it replaces…

Page 19: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Energy EfficiencyWe use the EPA’s five-step approach in our energy efficiency management plan

Lighting efficiency upgrade (Green Lights)Building tune-up (re-commissioning)Building load reductionHVAC distribution system upgradesHVAC plant upgrade

Page 20: DATA CENTER DESIGN OVERVIEW
Page 21: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEW

Energy Efficiency Case Study Office/Warehouse Building

Benefits of Green Lights ProgramEnvironmental

Reduced Power Plant emission-1,000,000 KWH/YearEliminated PCB Ballasts

Reduced Energy CostsEnergy Savings-$115,000/yearPG&E Rebate-$60,000Project Payout <Nine Month

Page 22: DATA CENTER DESIGN OVERVIEW

DATA CENTER DESIGN OVERVIEWEnergy Efficiency Case Study Office/Warehouse Building (continued)

Benefits of Mechanical UpgradesReduced Energy Usage

Electrical Savings: 249,600 KWH/YearDemand Savings: 249KWGas Savings: 1,416 Therms/Year

Reduced Energy CostsEnergy Savings: $80,000/YearPG&E Rebate: $60,000Project Payback: < 2 Years

Page 23: DATA CENTER DESIGN OVERVIEW
Page 24: DATA CENTER DESIGN OVERVIEW
Page 25: DATA CENTER DESIGN OVERVIEW
Page 26: DATA CENTER DESIGN OVERVIEW
Page 27: DATA CENTER DESIGN OVERVIEW
Page 28: DATA CENTER DESIGN OVERVIEW
Page 29: DATA CENTER DESIGN OVERVIEW
Page 30: DATA CENTER DESIGN OVERVIEW
Page 31: DATA CENTER DESIGN OVERVIEW
Page 32: DATA CENTER DESIGN OVERVIEW
Page 33: DATA CENTER DESIGN OVERVIEW
Page 34: DATA CENTER DESIGN OVERVIEW
Page 35: DATA CENTER DESIGN OVERVIEW
Page 36: DATA CENTER DESIGN OVERVIEW