8/13/2019 Data Rates-Tunnel Works 1
1/20
TUNNEL AND ALLIED WORKS
FOR THE YEAR : 2010-11
CONTENTS PAGES
REFERENCE DATA 3 -- 5
NOTES ON BASIC RATES 6 -- 6
DATA RATES 7 -- 111
ANNEXURES 67--82
REVISED BY SCHEDULE OF RATES COMMITTEE
dA ES
WATER RESOURCES DEPARTMENT
SCHEDULE OF RATES
TUNNEL AND ALLIED WORKS
zgn wAz jjnz
1
-
8/13/2019 Data Rates-Tunnel Works 1
2/20
TUNNEL AND ALLIED WORKS
2
-
8/13/2019 Data Rates-Tunnel Works 1
3/20
TUNNEL AND ALLIED WORKS
FOR THE YEAR : 2010-11
COST OF MATERIALS:1 Acetylene gas per cum Rs: 258.00
2 Air hose 25 mm dia per Rm Rs: 150.00
3 Binding wire per kg Rs: 50.00
4 Cement 43 Gr per kg Rs: 4.00
5 Coarse aggregate 10-4.75 mm / cum Rs: 669.00
6 Coarse aggregate 20-10 mm / cum Rs: 520.00
7 Coarse aggregate40-20 mm / cum Rs: 381.00
8 Concrete admixture( Super plasticiser ) per ltr Rs: 75.00
9 Cross bit ( TC ) 75 mm dia per No. Rs: 7690.00
10 Detonating fuse coil per Rm Rs: 8.00
11 Detonator delay type per No. Rs: 18.00
12 Detonator electric per No. Rs: 10.00
13 Detonator ordinary per No. Rs: 5.50
14 Explosive ( small dia ) per kg Rs: 45.0015 Extension rod with coupling sleeve per Rm Rs: 3300.00
16 Fine aggregate/ sand ( screened ) per cum Rs: 199.00
17 G I Pipe 80 mm dia per Rm Rs: 230.00
18 G I Pipe100 mm dia per Rm Rs: 250.00
19 G.I. Bolts and Nuts per kg Rs: 80.00
20 Guniting nozzle per No. Rs: 312.00
21 Jungle wood planks per cum Rs: 19000.00
22 Jack hammer drill rod 1.5 m per No. Rs: 3400.00
23 Jack hammer drill rod 2.5 m per No. Rs: 5660.00
24 M S Bolts & Nuts per kg Rs: 55.00
25 Oxygen gas per cum Rs: 48.00
26 Plain G.I. Sheet per tonne Rs: 49800.00
27 Rails 30 kg / m per tonne Rs: 42000.0028 Reinforcement steel per kg Rs: 36.20
29 Resin bond cement grout capsule per No. Rs: 50.00
30 Rivets per kg Rs: 50.00
31 Shalimastic sealing compound per kg Rs: 90.00
32 Shutter oil per ltr Rs: 25.00
33 Stone chips at dump yard per cum Rs: 160.00
34 Structural steel angle / channel / beam / bar per kg Rs: 37.95
35 Structural steel plate / flat per kg Rs: 40.00
36 Un-coursed rubble stones at dump yard per cum Rs: 135.00
37 Water hose 20 mm dia per Rm Rs: 128.00
38 Welding electrodes ( general purpose ) per No. Rs: 6.00
39 Wire rope per kg Rs: 105.00
ROYALTY CHARGES : Per tonne
1 Sand / Fine aggregate Rs: 30.00
2 Stone / Coarse aggregate / Chips Rs: 30.00
TUNNEL AND ALLIED WORKS - REFERENCE DATA
3
-
8/13/2019 Data Rates-Tunnel Works 1
4/20
TUNNEL AND ALLIED WORKS
LEAD, LOADING & UNLOADING CHARGES: 1 km lead Loading Unloading
1 Cement Rs: 37.90 45.60 45.60
2 Earth / Sand / Gravel Rs: 35.10 41.30 8.50
3 Steel Rs: 37.90 45.60 45.60
4 Stone / Coarse aggregate Rs: 48.70 48.80 24.40
HIRE CHARGES OF MACHINERY: Crew charges
1 Agitator car truck mounted per hour Rs: 628.00 605.00 90.80
2 Air compressor 15 cmm ( ele ) per hour Rs: 108.00 627.00 60.10
3 Air compressor 8.5 cmm ( ele ) per hour Rs: 108.00 282.00 56.40
4 Bending machine per hour Rs: 39.00 75.00 45.90
5 Batching plant 6 cum / hr rated capacity Rs: 130.00 125.00 108.20
6 Concrete pneumatic placer pump per hour Rs: 133.00 3.00 28.80
7 Convey mucker per hour Rs: 658.00 174.00 60.10
8 DG set 30 KVA Rs: 60.00 440.00 45.10
9 Diesel loco 45 hp per hour Rs: 237.00 371.00 56.70
10 Drilling jumbo per hour Rs: 322.00 30.00 60.5011 Dumper 5 cum per hour Rs: 480.00 277.00 72.60
12 Grout pump per hour Rs: 19.00 25.00 89.20
13 Guniting equipment per hour Rs: 84.00 9.00 74.40
14 Jack hammer per hour Rs: 14.00 5.00 111.90
15 Pump 10 hp ( ele ) per hour Rs: 5.00 50.00 26.90
16 Pump 20 hp ( ele ) per hour Rs: 11.00 100.00 26.90
17 Pusher leg per hour Rs: 8.00 3.00 ---
18 Tipper 5 cum per hour Rs: 271.00 208.00 56.70
19 Tipping tub 1.5 cum per hour Rs: 30.00 9.00 ---
20 Transformer 250 KVA per month Rs: 3523.00 --- ---
21 Up-right drilling machine / Grinding machine Rs: 18.00 25.00 59.50
22 Ventilation fan 20 hp per hour Rs: 6.00 100.00 9.30
23 Vibrator ( ele ) per hour Rs: 7.00 5.00 53.30
24 Waggon drill Rs: 216.00 9.00 89.50
25 Welding transformer per hour Rs: 12.00 60.00 ---
26 Winch 35 hp electric per hour Rs: 98.00 175.00 90.80
WAGES OF WORKERS: Per day
1 Bar bender Rs: 159.00
2 Blasting helper Rs: 141.50
3 Carpentor Cl- II Rs: 148.50
4 Electrician Rs: 143.00
5 Fitter shuttering works Rs: 148.50
6 Mechanic Cl - I Rs: 157.50
7 Foreman Rs: 177.008 Helper fitter / erector / carpenter Rs: 141.50
9 Khalasi Rs: 145.50
10 Licensed Blaster Rs: 147.00
11 Lineman Rs: 141.50
12 Maistry Rs: 141.50
Fuel chargeHire charge
4
-
8/13/2019 Data Rates-Tunnel Works 1
5/20
TUNNEL AND ALLIED WORKS
13 Mason Cl-I Rs: 159.00
14 Mason Cl-II Rs: 148.50
15 Mazdoor ( Cement handling ) Rs: 134.00
16 Mazdoor ( Heavy) Rs: 132.00
17 Mazdoor ( Light ) Rs: 130.50
18 Pipe fitter Rs: 152.50
19 Stone breaker ( Hammerman ) Rs: 146.00
20 Stone chiseller Cl II Rs: 146.00
21 Structural steel Marker / Erector Rs: 157.50
22 Surveyor Rs: 154.50
23 Tinsmith Rs: 141.50
24 Turner / Driller Rs: 152.50
25 Welder / Gas cutter Rs: 157.50
ELECTRIC SUB-STATION MATERIALS:
1 Electric pole with fixtures per No. Rs: 4200.00
2 Flood light 500 W per Each Rs: 650.003 Flood light set per Each Rs: 1200.00
4 Fluoscent tube light 40 W per Each Rs: 50.00
5 Fluoscent tube light set per Each Rs: 190.00
6 Circuit breaker with accessories per set Rs: 30000.00
7 HT / LT Line conductor per 1000 Rm Rs: 27000.00
8 PVC Armoured cable 10 sqmm and below per Rm Rs: 48.00
9 PVC Armoured cable 16 sqmm per Rm Rs: 58.00
10 PVC Armoured cable 25 sqmm per Rm Rs: 100.00
11 PVC Armoured cable 70 sqmm per Rm Rs: 250.00
12 Transformer 250 kVA Rs: 297000.00
OTHER DATA :
1 Contractor's Overheads on Materials / Machinery / Labour % 5.00
2 Contractor's Profit on Materials / Fuel & Energy charges / Labour % 10.00
3 Demand charges on power supply per KVA / month Rs: 190.00
4 Electric Energy charges per kWhr Rs: 5.60
5 Insurance charges on machinery per annum % 1.00
6 Hidden cost on Labour % 15.00
Hidden cost on Labour ( additional for Tunnel works ) % 10.00
7 Rate of interest per annum % 11.00
8 Small Tools & Plant on Materials / Machinery / Labour % 1.00
9 Structural steel fabrication cost per kg Rs: 10.00
10 Sundries ( Lump sum rate for unquantified inputs ) Rs: 30.00
11 Cost of Electric sub-station & Demand charges ( Annexure - 1 ) % 4.20
12 Cost of Air and Water lines ( Annexure - 2 ) % 0.5013 Cost of Ventilation ( Annexure - 3 ) % 6.10
14 Cost of Lighting inside / out side tunnel ( Annexure - 4 ) % 1.90
15 Cost of Other enabling works ( Annexure - 5 ) % 1.70
5
-
8/13/2019 Data Rates-Tunnel Works 1
6/20
TUNNEL AND ALLIED WORKS
NOTES ON SCHEDULE OF RATES
TUNNEL AND ALLIED WORKS
FOR THE YEAR : 2010-11
1. All notes under General Notes on Schedule of Rates and Notes on Lead, Lift, Loading and
un-loading Charges are applicable to Tunnel and Allied Works also to the extent they arerelevant.
2. The basic rates are inclusive additional costs for working inside tunnel.
3. The basic rates are inclusive of scaling loose material, removal of under-cuts, cleaning bed and
lighting and ventilation inside tunnel .
4. Unless otherwise specified the basic rates are inclusive of all lifts.
5. Unless otherwise specified the basic rates are inclusive of standard finish required for concrete
surface.
6. For excavation and concrete lining works of approach / exit channels the basic rates as
provided under ' Canal and allied works ' and ' Canal cross drainage works ' shall be adopted.
7. For intake structure, tunnel portals, retaining walls, pitching etc., the rates as provided under '
Dam and allied works ' shall be adopted.
8. The lead charges, wherever applicable, for all materials under various items shall be considered
only between quarry/ source of supply and batching plant / fabrication site. Further conveyance
of concrete / fabricated parts / other materials upto final placing site inside tunnel is included in
the basic rates upto 1 km.
9. Cement content specified for cement concrete works in the item description is based on
theoritical design mix computations and is exclusive of wastage and requirement for any
incidentals. The actual cement content may vary based on trial mix studies. A suitable
clause shall be included in tender for regulating payment for any upword or downwordvariation in cement content.
10. The quantities of materials including wastage, requirements for incidentals etc., for working
out additional lead charges shall be as per the statement of requirement of materials under
this section.
6
-
8/13/2019 Data Rates-Tunnel Works 1
7/20
TUNNEL AND ALLIED WORKS
SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11 ITEM No: 1
ITEM: Excavation for adit by tunnelling methods in all types of rock including cost of all materials,
machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and
hauling the excavated muck outside adit upto specified dump area and all other ancil lary
operations etc., complete with initial lead upto 500 m and all lifts.
DATA:Size of adit assumed ( finished section ) : 4.50 m dia
Shape of adit assumed for excavation : D - shape
Height of adit assumed ( finished section ) : 4.50 m
Pay-line margin assumed : 0.20 m
Diameter of adit upto pay line for excavation : 4.90 m
Distance of dump yard from face : within 500 m
Haulage of excavated muck : By dumpers
Pay line
Minimum excavation line
Excavated profile
TYPICAL CROSS SECTION OF ADIT / TUNNEL
1. Checking alignment and marking hole locations :
Deploy drilling jumbo for 1 hour for marking hole locations.
2. Drilling holes :
Full face method of excavation is assumed.
Area of adit upto pay-line ( 0.5 x 0.7857x 4.9 x 4.9 )+( 4.9 x 2.45 ) : 21.43 sqm
The drilling pattern for excavation of tunnel / adit depends on the size and shape of tunnel, rock
formation, type of explosive and the fragmentation of rock required to suite the type of mucking
equipment. The drilling pattern shall ensure minimum over-break.
Cut holes
Easers
Trimmers
TYPICAL DRILLING PATTERN FOR ADIT / TUNNEL
TUNNEL AND ALLIED WORKS- DATA RATES
7
-
8/13/2019 Data Rates-Tunnel Works 1
8/20
TUNNEL AND ALLIED WORKS
Generally, the cut holes and easers will be spaced at 650 to 750 mm grid and the trimmers will
be spaced at 500 to 600 mm apart along the periphery of excavation area.
Considering this, the number of holes for tunnel excavation will be generally in the range of 2.5
to 3 per sqm of cross sectional area upto pay line for small tunnels ( cross sectional area less
than 45 sqm ) and in the range of 2.0 to 2.5 per sqm of cross sectional area for large tunnels.
For rate analysis 2.5 holes per sqm of cross sectional area upto pay line considered for adit.
Number of holes for full face excavation ( 21.43 x 2.5 ) : 54 Nos
Depth of holes : 2 m
Extra drilling considered at 10 percent for inclined cut holes and for any secondary blasting of
large fragments during mucking.
Depth of drill ing for 54 holes ( 54 x 2 x 1.10 ) : 119 m
Average rate of drilling per hour per jack hammer : 5 m
Time for 4 jack hammers with pusher leg for drilling. ( 119 / 4 / 5 ) say : 6 hours
Time for 1 air compressor 15 cmm for air supply to 4 jack hammers : 6 hours
Time for drilling jumbo for drilling : 6 hours
Time for 10 hp pump for water supply to drilling work. : 6 hours
3. Loading explosive and blasting :
Depth of pull per blast for 2 m deep holes : 1.80 mQuantity of in-situ excavation per blast ( 21.43 x 1.80 ) : 38.6 cum
Quantity of explosive small dia per blast @ 1.00 kg per cum : 38 kg
Quantity of explosive for secondary blasting @ 5 % : 2 kg
Quantity of delay detonators per blast : 54 Nos.
Quantity of electric detonators for secondary blasting ( LS ) : 5 Nos.
Fuse coil : 120 Rm
Time for drilling jumbo for loading explosives. : 1 hour
4. Defuming and scaling loose materials:
No machinery other than ventilation fans are required. For defuming adit ventilation fans are
installed in duct system at about 300 m interval and are run for about 1 hour after each blast.
Consider 20 hp fan 1 No. for 1 hour for defuming.
5. Mucking excavated rock :
Quantity of muck to be removed per blast considering 40 % bulkage : 54 cum
Capacity of dumper per load : 5.00 cum
Quantity of muck per load considered under adit working conditions : 4.50 cum
Loading cycle time:
Turning / moving and spotting : 1 minute
Loading muck by convey mucker and work force : 20 minutes
Cycle time of loading dumper per load of 4.50 cum : 21 minutes
Haulage cycle time:
Running time from loading point to dump yard @ av 10 km / hr : 3.0 minutes
Turning and unloading : 2.0 minutes
Return trip to reversing point @ av 15 km / hr : 2.0 minutes
Cycle time for haulage per load of 4.5 cum : 7.0 minutes
Since the waiting time will be more than the running time if 2 dumpers are deployed deploy
1 dumper for conveying muck.
Round trip cycle time of dumper say : 30 minutesQuantity of muck disposal per hour / dumper : 9.00 cum
Time for 1 dumper for conveying muck @ 9 cum per hour : 6 hours
Time for convey mucker and labour force for loading : 6 hours
8
-
8/13/2019 Data Rates-Tunnel Works 1
9/20
TUNNEL AND ALLIED WORKS
6. Overall cycle time :
Checking alignment and marking hole locations : 2.00 hours
Drilling holes : 6.00 hours
Loading explosive and blasting : 2.00 hours
Defuming and scaling loose rock fragments : 2.00 hours
Mucking excavated rock : 6.00 hours
Bed cleaning, support fixing, rock bolting, lighting etc say : 6.00 hours
Total cycle of excavation per blast of 1.8 m length : 24.00 hours
7. Requirement of materials :
Explosive small dia ( 38 + 2 ) : 40 kg
Electric short delay detonators ( 54 x 1 ) : 54 Nos
Electric detonators for secondary blasting ( 1 x 5 ) : 5 Nos
Fuse coil : 120 Rm
8. Requirement of machinery :
Deploy drilling jumbo for marking (1 hr) / drilling (6 hrs) / loading explosive (1 hr) : 8 hours
Deploy air compressor 15 cmm for air supply to 4 jack hammers : 6 hours
Deploy 4 jack hammers with pusher leg for drilling. : 6 hours
Deploy 10 hp pump for water supply to drilling work. : 6 hours
Deploy 20 hp ventilation fan for defuming : 1 hour
Deploy convey mucker for loading excavated rock : 6 hoursDeploy 1 dumper for conveying muck : 6 hours
9. Requirement of workforce ( other than machinery crew ) :
Surveyor
for checking alignment and marking hole locations for drilling : 0.5 No.
Foreman for supervising drilling of holes and other operations : 1 No.
Fitter / Mechanic
for extending air / water lines : 2 Nos.
Blaster ( Licensed ) : 1 No.
Helper blasting : 2 Nos.
Hammerman for scaling : 2 Nos.
Maistry 1 in each shift : 3 Nos.
Khalasi for mucking shift : 4 Nos.
Heavy mazdoor
for mucking shift : 4 Nos.
for other 2 shifts 1 No each shift : 2 Nos.
Light mazdoor
for cleaning & miscellaneous : 1 No.
10. Use rate of materials:
Cost of drill rod 2.5 m long @ Rs: 5660.00 / No. Rs: 5660.00
Life of drill rod with reconditionong : 150 m
Use rate of drill rod per Rm drilling ( cost / life ) Rs: 37.73
Length of air and water hose assumed : 25 m each
Cost of 25 mm dia air hose 25 m @ Rs: 150.00 / Rm Rs: 3750.00
Life of air hose : 800 hours
Use rate of air hose per hour ( cost / life ) Rs: 4.69
Cost of water hose 25 m each @ Rs: 128.00 / Rm Rs: 3200.00
Life of water hose : 800 hoursUse rate of water hose per hour ( cost / life ) Rs: 4.00
9
-
8/13/2019 Data Rates-Tunnel Works 1
10/20
TUNNEL AND ALLIED WORKS
RATE ANALYSIS UNIT : 38.60 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Small dia explosive kg 40.00 45.00 1800.00
2 Delay detonators Nos 54.00 18.00 972.00
3 Electric detonators Nos 5.00 10.00 50.00
4 Detonating fuse coil Rm 120.00 8.00 960.00
5 Use rate of drill rod 2.5 m long Rm 119.00 37.73 4490.27
Reconditioning charges @ 10% 449.03
6 Use rate of air hose Hour 24.00 4.69 112.50
7 Use rate of water hose Hour 24.00 4.00 96.00
8 Sundries( paint / template etc ) LS 15.00 30.00 450.00
Total Rs: 9379.79
Add for small Tools and Plants @ 1% Rs: 93.80
Add for Contractor's Profit @ 10% Rs: 937.98
Add for Contractor's Overheads @ 5% Rs: 468.99
Total cost of Materials : Rs: 10880.56
B. MACHINERY:
Sl No Unit Amountin Rs.
1 Drilling jumbo Hour 8.00 322.00 2576.00
Fuel / Energy charges Hour 8.00 30.00 240.00
2 Air compressor 15 cmm ( ele ) Hour 6.00 108.00 648.00
Fuel / Energy charges Hour 6.00 627.00 3762.00
3 Jack hammer ( 4 x 6 hrs ) Hour 24.00 14.00 336.00
Fuel / Energy charges Hour 24.00 5.00 120.00
4 Pusher leg Hour 24.00 8.00 192.00
Fuel / Energy charges Hour 24.00 3.00 72.00
5 Convey mucker Hour 6.00 658.00 3948.00
Fuel / Energy charges Hour 6.00 174.00 1044.00
6 Dumper ( 1 x 6 hrs ) Hour 6.00 480.00 2880.00
Fuel / Energy charges Hour 6.00 277.00 1662.00
7 Pump 10 hp ( ele ) ( 1 x 6 hrs ) Hour 6.00 5.00 30.00
Fuel / Energy charges Hour 6.00 50.00 300.00
8 Ventilation fans 20 hp ( 1 x 1 hr ) Hour 1.00 6.00 6.00
Fuel / Energy charges Hour 1.00 100.00 100.00
9 Sundries(explosive van / magazine ) LS 15.00 30.00 450.00
Total Rs: 18366.00
Add for small Tools and Plants @ 1% Rs: 183.66
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 775.00
Add for Contractor's Overheads @ 5% Rs: 918.30
Total hire charges of Machinery : Rs: 20242.96
C. LABOUR:
Sl No Unit Amount
in Rs.1 Crew for Drilling jumbo Hour 8.00 60.50 484.00
Contd
C. LABOUR ( Contd ) :
Description
Description
in Rs.
Quantity Rate
in Rs.
Quantity Rate
in Rs.
Quantity RatePerticulars
10
-
8/13/2019 Data Rates-Tunnel Works 1
11/20
TUNNEL AND ALLIED WORKS
Sl No Unit Amount
in Rs.
Contd
2 Crew for Air compressor Hour 6.00 60.10 360.60
3 Crew for Jack hammer Hour 24.00 111.90 2685.60
4 Crew for Convey mucker Hour 6.00 60.10 360.60
5 Crew for Dumper Hour 6.00 72.60 435.60
6 Crew for Pump Hour 6.00 26.90 161.40
7 Crew for ventilation fans Hour 1.00 9.30 9.30
8 Surveyor Day 0.50 154.50 77.25
9 Foreman Day 1.00 177.00 177.00
10 Fitter / Mechanic Day 2.00 157.50 315.00
11 Blaster ( Licensed ) Day 1.00 147.00 147.00
12 Helper blasting Day 2.00 141.50 283.00
13 Hammerman Day 2.00 146.00 292.00
14 Maistry 1 in each shift Day 3.00 141.50 424.50
15 Khalasi
for mucking shift 4 Nos Day 4.00 145.50 582.00
16 Heavy mazdoor
for mucking shift 4 Nos Day 4.00 132.00 528.00
for other 2 shifts 1 No each shift Day 2.00 132.00 264.0017 Light mazdoor
for cleaning & miscellaneous Day 1.00 130.50 130.50
Total Rs: 7717.35
Add for small Tools and Plants @ 1% Rs: 77.17
Add for Contractor's Profit @ 10% Rs: 771.74
Add for hidden cost on Labour @ 15% Rs: 1157.60
Add for additional hidden cost on labour @ 10% Rs: 771.74
Add for Contractor's Overheads @ 5% Rs: 385.87
Total cost of Labour : Rs: 10881.46
ABSTRACT:
A. Cost of Materials Rs: 10880.56
B. Hire charges of Machinery Rs: 20242.96
C. Cost of Labour Rs: 10881.46
TOTAL Rs: 42004.98
Add for Air and Water line @ 0.50% Rs: 210.02
Add for Ventilation @ 6.10% Rs: 2562.30
Add for Lighting @ 1.90% Rs: 798.09
Add for Ele sub-station / Demand charges @ 4.20% Rs: 1764.21
Add for other Enabling works @ 1.70% Rs: 714.08
Total cost for 38.60 cum Rs: 48053.70
Rate per cum Rs: 1245.00
Rate approved per cum Rs: 1245.00
SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11 ITEM No: 2
ITEM: Excavation for vertical / inclined shaftin all types of soft / hard rock including cost of allmaterials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,
drainage, removing and hauling excavated muck outside shaft upto specified dump area and
all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.
Description Quantity Rate
in Rs.
11
-
8/13/2019 Data Rates-Tunnel Works 1
12/20
TUNNEL AND ALLIED WORKS
DATA:Size of shaft assumed : 5.00 m dia
Shape of shaft assumed for excavation : Circular
Depth of shaft assumed : 75.00 m
Pay-line margin assumed : 0.20 m
Diameter of shaft upto pay line for excavation : 5.40 m
Distance of dump yard from face : within 500 m
Average lift assumed for excavation of shaft upto tunnel level : 40 m
1. Checking alignment and marking hole locations :
Use of winch & cradle during marking hole locations : 1 hour
2. Drilling holes :
Area of excavation upto payline ( 0.7857 x 5.4 x 5.4 ) : 22.91 sqm
Depth of drilling : 1.50 m
Depth of pull : 1.30 m
No.of peripheral holes @ 0.65 m spacing ( 20 times dia ) : 24 Nos.
No. of holes in shaft area @ 2 per sqm ( 0.7857 x 5 x 5 x 2 ) : 40 Nos.
Depth of drilling for 64 holes ( 64 x 1.5 ) : 96 m
Extra drilling considered at 5 percent for secondary blasting of large fragments.
Total depth of drilling ( 96 x 1.05 ) say : 101 m
Average rate of drilling per hour per jack hammer : 5 m
Time for 4 jack hammers for drilling. ( 101 / 4 / 5 ) say : 5 hoursTime for 1 air compressor 15 cmm for air supply to 4 jack hammers : : 5 hours
Time for 10 hp pump for pumping water to storage tank. : 5 hours
Time for 20 hp sludge pump for removing drill water from pit : 2 hours
Total time for drilling including preparation for drilling : 5 hours
3. Loading explosive and blasting :
Quantity of in-situ excavation per blast ( 22.91 x 1.30 ) : 30 cum
Quantity of explosive small dia per blast @ 1.0 kg per cum : 30 kg
Quantity of explosive for secondary blasting @ 5 % : 2 kg
Quantity of electric detonators for blasting : 69 Nos.
Detonating fuse coil : 120 Rm
Use of winch & cradle during loading of explosives : 1 hour
4. Defuming shaft:
Generally for shafts defuming is carried out by leaving compressed air by air hose for about
0.5 hour to remove blasting gases and dust. Use air compressor for 0.5 hour.
5. Mucking excavated rock :
Winch and 0.5 cum bottom / side opening bucket are considered for removing the muck from
shaft and rail mounted tipping tubs are considered for further haulage and disposal.
Quantity of muck to be removed per blast considering 40 % bulkage : 42 cum
Deploy 8 heavy mazdoors for mucking in the shaft.
Consider out-put of each mazdoor at 3 cum / day for working on rocky surface.
Time for loading 0.5 cum bucket ( 0.5 x 8 x 60 / 3 / 8 ) : 10 min
Cycle time for operating mucking bucket by winch :
Lowering bucket by winch @ 15 m / minute for av. 40 m : 3.00 min
Loading muck by work force : 10.00 min
Lifting by winch @ 15 m / minute for av. 40 m : 3.00 min
Unloading to tipping tub : 1.50 mun
Over all cycle time for mucking 0.5 cum by deploying 2 buckets say : 10.00 min
Quantity of muck per mucking bucket : 0.50 cum
Time required for mucking 42 cum ( 42 x 10 / 0.50 / 60 ) : 14 hours
12
-
8/13/2019 Data Rates-Tunnel Works 1
13/20
TUNNEL AND ALLIED WORKS
Considering time for shift change etc., total time required for mucking : 16 hours
Considering use of winch during marking / drilling / blasting / time for shift change / etc., deploy
winch for 24 hours with fuel / energy charges for 16 hours.
Use 2 mucking buckets for 16 hours for removing muck from shaft.
Use 1 tipping tub for 16 hours for disposal of muck outside shaft.
6. Overall cycle time :
Marking hole locations and preparation for drilling : 0.50 hours
Drilling holes : 5.00 hours
Loading explosive and blasting : 2.00 hours
Defuming by leaving compressed air : 0.50 hours
Mucking excavated rock : 16.00 hours
Total cycle of excavation per blast of 1.3 m depth : 24.00 hours
7. Requirement of materials :
Explosive small dia ( 30 + 2 ) : 32 kg
Electric detonators for main / secondary blasting ( 24 + 40 + 5 ) : 69 Nos
Fuse coil : 120 Rm
8. Requirement of machinery :
Deploy winch for various operations : 24 hours
( marking holes 1 hr + drilling 5 hrs + loading explosives 1 hr + mucking 16 hrs + misc 1 hr)
Deploy air compressor 15 cmm for air supply to 4 jack hammers : 5.5 hours
( drilling 5 hrs + defuming 0.5 hr )Deploy 4 jack hammers for drilling. : 5 hours
Deploy 10 hp pump for water supply to drilling work. : 5 hours
Deploy 20 hp sludge pump for removing drill water : 2 hours
Deploy 1 tipping tub for conveying muck : 16 hours
9. Requirement of workforce ( other than machinery crew ) :
Surveyor
for checking alignment and marking hole locations for drilling : 0.5 No.
Foreman for supervising winch and other operations ( 1 in each shif t ) : 3 Nos.
Fitter / Mechanic
for arranging air / water lines / sludge pump etc. : 2 Nos.
Blaster ( Licensed ) : 1 No.
Helper blasting : 2 Nos.
Hammerman for scaling / breaking large stones ( 4 in 2 mucking shifts ) : 4 Nos.
Maistry ( 1 in each shift ) : 3 Nos.
Khalasi ( 8 in 2 mucking shifts ) : 8 Nos.
Heavy mazdoor
for mucking shift ( 8 in each shift for 2 shifts ) : 16 Nos.
for other 1 shift ( 2 Nos ) : 2 Nos.
Light mazdoor
for cleaning & miscellaneous : 2 Nos.
10. Use rate of materials:
Cost of drill rod 1.5 m long @ Rs: 3400.00 / No. Rs: 3400.00
Life of drill rod with reconditioning : 150 m
Use rate of drill rod per Rm drilling ( cost / life ) Rs: 22.67
Length of air and water hose assumed : 100 m each
Cost of 25 mm dia air hose 100 m @ Rs: 150.00 / Rm Rs: 15000.00
Life of air hose : 800 hours
Use rate of air hose per hour ( cost / life ) Rs: 18.75
Cost of water hose 100 m each @ Rs: 128.00 / Rm Rs: 12800.00
13
-
8/13/2019 Data Rates-Tunnel Works 1
14/20
TUNNEL AND ALLIED WORKS
Life of water hose : 800 hours
Use rate of water hose per hour ( cost / life ) Rs: 16
Quantity of rails for haulage of tubs Haulage track outside : 2 x 150 m
Weigth of 30R rails 300 m length @ 30 kg / Rm : 9 tonnes
Cost of 30 R rails 300 m @ Rs: 42000.00 / tonne Rs: 378000.00
Add for fixtures @ 25% Rs: 94500.00
Total Rs: 472500.00
Less salvage value @ 10% ( - ) Rs: -47250.00
Total Rs: 425250.00
Life of rails under tunnel working conditions : 15 years
Use rate of rails per year ( cost / life ) Rs: 28350.00
Add for repairs & replacement @ 10% Rs: 2835.00
Total Rs: 31185.00
Use rate of rails per shift considering 300 working days Rs: 103.95
Consider use of rail track for 24 hours.
Length of 16 mm dia wire rope for winch assuming 80 m deep shaft : 150 m
Cost of wire rope 150 m ( 160 kg ) @ Rs: 105.00 / kg Rs: 16800.00
Life of wire rope for lifting : 2500 hours
Use rate of wire rope per hour ( cost / life ) Rs: 6.72
Weight of mucking bucket : 250 kg
Cost of steel plates @ 75 % @ Rs: 40.00 / kg Rs: 7500.00Cost of steel angles @ 25 % @ Rs: 37.95 / kg Rs: 2371.88
Cost of fabrication @ Rs: 10.00 / kg Rs: 2500.00
Total Rs: 12371.88
Add for hooks / door arrangements etc @ 25% Rs: 3092.97
Total Rs: 15464.84
Less salvage value @ 10% ( - ) Rs: -1546.48
Add for repairs / maintenance etc @ 10% Rs: 1546.48
Total Rs: 15464.84
Life of mucking bucket assumed : 2500 hours
Use rate of mucking bucket per hour ( cost / life ) Rs: 6.19
RATE ANALYSIS UNIT : 30.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Small dia explosive kg 32.00 45.00 1440.00
2 Electric detonator Nos 69.00 10.00 690.00
3 Detonating fuse coil Rm 120.00 8.00 960.00
4 Use rate of drill rod 1.5 m long Rm 101.00 22.67 2289.33
Reconditioning charges @ 10% 228.93
5 Use rate of air hose ( 4 x 5 + 0.5 ) Hour 22.00 18.75 412.50
6 Use rate of water hose ( 4 x 5 ) Hour 20.00 16.00 320.00
7 Use rate of rail track Shift 2.00 103.95 207.90
8 Use rate of wire rope Hour 24.00 6.72 161.28
Contd
A. MATERIALS ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
9 Use rate of mucking bucket ( 2 x 16 ) Hour 32.00 6.19 197.95
Perticulars
in Rs.
Quantity Rate
Perticulars Quantity Rate
in Rs.
14
-
8/13/2019 Data Rates-Tunnel Works 1
15/20
TUNNEL AND ALLIED WORKS
10 Sundries ( paint / template etc ) LS 10.00 30.00 300.00
Total Rs: 7207.90
Add for small Tools and Plants @ 1% Rs: 72.08
Add for Contractor's Profit @ 10% Rs: 720.79
Add for Contractor's Overheads @ 5% Rs: 360.39
Total cost of Materials : Rs: 8361.16
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Air compressor 15 cmm ( ele ) Hour 5.50 108.00 594.00
Fuel / Energy charges Hour 5.50 627.00 3448.50
2 Jack hammer ( 4 x 5 hrs ) Hour 20.00 14.00 280.00
Fuel / Energy charges Hour 20.00 5.00 100.00
3 Pump 10 hp ( ele ) Hour 5.00 5.00 25.00
Fuel / Energy charges Hour 5.00 50.00 250.00
4 Sludge pump 20 hp electric Hour 2.00 11.00 22.00
Fuel / Energy charges Hour 2.00 100.00 200.00
5 Winch 35 hp electric Hour 24.00 98.00 2352.00
Fuel / Energy charges Hour 16.00 175.00 2800.00
6 Tipping tub 1.5 cum Hour 16.00 30.00 480.00Fuel / Energy charges Hour 16.00 9.00 144.00
7 Sundries ( explosive van / magazine ) LS 10.00 30.00 300.00
Total Rs: 10995.50
Add for small Tools and Plants @ 1% Rs: 109.96
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 724.25
Add for Contractor's Overheads @ 5% Rs: 549.78
Total hire charges of Machinery : Rs: 12379.48
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Air compressor Hour 5.50 60.10 330.55
2 Crew for Jack hammer Hour 20.00 111.90 2238.00
3 Crew for Pump 10 hp Hour 5.00 26.90 134.50
4 Crew for Sludge pump 20 hp Hour 2.00 26.90 53.80
5 Crew for Winch Hour 24.00 90.80 2179.20
6 Surveyor Day 0.50 154.50 77.25
7 Foreman Day 3.00 177.00 531.00
8 Fitter / Mechanic Day 2.00 157.50 315.00
9 Blaster ( Licensed ) Day 1.00 147.00 147.00
10 Helper blasting Day 2.00 141.50 283.00
11 Hammerman 2 Nos each for 2 shifts Day 4.00 146.00 584.00
12 Maistry 1 in each shift Day 3.00 141.50 424.50
Contd
C. LABOUR ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
13 Khalasi
for mucking 4 Nos each for 2 shifts Day 8.00 145.50 1164.00
Description
Description
Quantity Rate
in Rs.
in Rs.
Description Quantity Rate
in Rs.
Quantity Rate
15
-
8/13/2019 Data Rates-Tunnel Works 1
16/20
TUNNEL AND ALLIED WORKS
14 Heavy mazdoor
for mucking 8 Nos each for 2 shifts Day 16.00 132.00 2112.00
for other 1 shift 2 Nos Day 2.00 132.00 264.00
15 Light mazdoor
for cleaning & miscellaneous Day 2.00 130.50 261.00
Total Rs: 11098.80
Add for small Tools and Plants @ 1% Rs: 110.99
Add for Contractor's Profit @ 10% Rs: 1109.88
Add for hidden cost on Labour @ 15% Rs: 1664.82
Add for additional hidden cost on labour @ 10% Rs: 1109.88
Add for Contractor's Overheads @ 5% Rs: 554.94
Total cost of Labour : Rs: 15649.31
ABSTRACT:
A. Cost of Materials Rs: 8361.16
B. Hire charges of Machinery Rs: 12379.48
C. Cost of Labour Rs: 15649.31
TOTAL Rs: 36389.95
Add for Air and Water line @ 0.50% Rs: 181.95
Add for Ventilation @ 0.00% Rs: 0.00
Add for Lighting @ 1.90% Rs: 691.41Add for Ele sub-station / Demand charges @ 4.20% Rs: 1528.38
Add for other Enabling works @ 1.70% Rs: 618.63
Total cost for 30.00 cum Rs: 39410.31
Rate per cum Rs: 1314.00
Rate approved per cum Rs: 1314.00
SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11 ITEM No: 3
ITEM: Excavation for tunnel by tunnelling methods in rock not requiring supports including cost
of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,
lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
DATA:Size of tunnel assumed ( finished section ) : 4.50 m dia
Shape of tunnel assumed for excavation : D - shape
Height of tunnel assumed ( finished section ) : 4.50 m
Length of tunnel assumed : 1000 m
Thickness of CC lining : 0.30 m
Pay-line margin assumed : 0.20 m
Diameter of tunnel upto pay line for excavation : 5.50 m
Distance of dump yard from face including approach / adit length : Average 1 km
Haulage of excavated muck : By dumpers
Pay line
Concrete lining
Minimum excavation line
Excavated profile Finished tunnel line
16
-
8/13/2019 Data Rates-Tunnel Works 1
17/20
TUNNEL AND ALLIED WORKS
TYPICAL CROSS SECTION OF TUNNEL 4.50 m dia.
1. Checking alignment and marking hole locations :
Use of drilling jumbo for marking hole locations : 1 hour
2. Drilling holes :
Area of tunnel upto pay-line( 0.5 x 0.786 x 5.5 x 5.5 )+( 5.5 x 2.75 ) : 27.00 sqm
The number of holes for tunnel excavation will be generally in the range of 2.5 to 3.0 per sqm
of cross sectional area upto pay line for tunnel upto 45 sqm and in the range of 2.0 to 2.5 per
sqm of cross sectional area upto pay line for tunnel exceeding 45 sqm.
For rate analysis 2.5 holes per sqm of cross sectional area considered.
Number of holes for full face excavation ( 27 x 2.5 ) : 68 Nos
Depth of holes : 2 m
Extra drilling considered at 10 percent for inclination of holes and for removal of any under cuts
and for secondary blasting of large fragments during mucking.
Depth of drill ing for 68 holes ( 68 x 2 x 1.10 ) : 150 m
Average rate of drilling per hour per jack hammer : 5 m
Time for 4 jack hammers with pusher leg for drilling. ( 150 / 4 / 5 ) say : 7.5 hoursTime for 1 air compressor 15 cmm for air supply to 4 jack hammers : 7.5 hours
Time for drilling jumbo for drilling : 8 hours
Time for 10 hp pump for water supply to drilling work. : 7.5 hours
3. Loading explosive and blasting :
Depth of pull per blast for 2 m deep holes : 1.80 m
Quantity of in-situ excavation per blast ( 27.00 x 1.80 ) : 49 cum
Quantity of explosive small dia per blast @ 1.00 kg per cum : 49 kg
Quantity of explosive for under cuts secondary blasting @ 10 % : 5 kg
Quantity of delay detonators per blast : 68 Nos.
Quantity of electric detonators for secondary blasting ( LS ) : 10 Nos.
Detonating fuse coil ( LS ) : 160 Rm
Time for drilling jumbo for loading explosives : 1.5 hour
4. Defuming and scaling loose materials:
No machinery other than ventilation fans required. For defuming tunnel ventilation fans are
installed in duct system at about 300 m interval and are run for about 1 hour after each blast.
For 1 km length of tunnel ventilation fans are required at 4 places at 300 m interval. As the fans
are installed progressively, for rate analysis consider average 2 fans for 1 hour.
5. Mucking excavated rock :
Quantity of muck to be removed per blast considering 40 % bulkage : 69 cum
Capacity of dumper per load : 5.00 cum
Quantity of muck per load considered under tunnel working conditions : 4.50 cum
Loading cycle time:
Moving from turning pocket position and spotting : 1 minutes
Loading muck by convey mucker and work force : 20 minutes
Time for loaded dumper to pass waiting point say : 1 minutes
Cycle time of loading dumper per load of 4.50 cum : 22 minutes
Haulage cycle time:
Running time from loading point to dump yard at av. 10 km / hr : 6 minutes
Turning and unloading : 2 minutes
17
-
8/13/2019 Data Rates-Tunnel Works 1
18/20
TUNNEL AND ALLIED WORKS
Return trip to waiting point @ av. 15 km / hr : 4 minutes
Waiting time before spotting : 9 minutes
Cycle time for haulage per load of 4.5 cum : 21 minutes
Round trip cycle time of dumper ( 22 + 21 ) say : 45 minutes
Quantity of muck disposal per hour / dumper : 6.00 cum
Deploy 2 dumpers for conveying muck @ 12 cum per hour say : 6 hours
Deploy convey mucker and labour force for loading : 6 hours
6. Overall cycle time :
Checking alignment and marking hole locations : 2.00 hours
Drilling holes : 7.50 hours
Loading explosive and blasting : 2.00 hours
Defuming and scaling loose rock fragments : 2.00 hours
Mucking excavated rock : 6.00 hours
Bed cleaning, support fixing, rock bolting, lighting etc say : 4.50 hours
Total cycle of excavation per blast of 1.8 m length : 24.00 hours
7. Requirement of materials :
Explosive small dia ( 49 + 5 ) : 32 kg
Electric short delay detonators ( 68 x 1 ) : 68 Nos
Electric detonators for secondary blasting ( 10 x 1 ) : 10 Nos
Fuse coil : 160 Rm
8. Requirement of machinery :Deploy drilling jumbo for various operations 11 hours
( marking holes 1 hr + drilling 7.5 hrs + loading explosives 1.5 hrs + misc 1 hr )
Deploy air compressor 15 cmm for air supply to 4 jack hammers : 7.5 hours
Deploy 4 jack hammers with pusher leg for drilling. : 7.5 hours
Deploy 10 hp pump for water supply to drilling work. : 7.5 hours
Deploy 20 hp ventilation fan for defuming : 2 hours
Deploy convey mucker for loading excavated rock : 6 hours
Deploy 2 dumper for conveying muck : 6 hours
9. Requirement of workforce ( other than machinery crew ) :
Surveyor
for checking alignment and marking hole locations for drilling : 1 No.
Foreman for supervising drilling of holes and other operations : 1 No.
Fitter / Mechanic
for extending air / water lines : 2 Nos.
Blaster ( Licensed ) : 1 No.
Helper blasting : 2 Nos.
Hammerman for scaling : 2 Nos.
Maistry 1 in each shift : 3 Nos.
Khalasi for mucking shift : 4 Nos.
Heavy mazdoor :for mucking shift : 8 Nos.
for other 2 shifts 2 No each shift : 4 Nos.
Light mazdoor :
for cleaning & miscellaneous : 2 Nos.
10. Use rate of materials:
Cost of drill rod 2.5 m long @ Rs: 5660.00 / No. Rs: 5660.00
Life of drill rod with reconditioning : 150 m
Use rate of drill rod per Rm drilling ( cost / life ) Rs: 37.73
18
-
8/13/2019 Data Rates-Tunnel Works 1
19/20
TUNNEL AND ALLIED WORKS
Length of air and water hose assumed : 25 m each
Cost of 25 mm dia air hose 25 m @ Rs: 150.00 / Rm Rs: 3750.00
Life of air hose : 800 hours
Use rate of air hose per hour ( cost / life ) Rs: 4.69
Cost of water hose 25 m each @ Rs: 128.00 / Rm Rs: 3200.00
Life of water hose : 800 hours
Use rate of water hose per hour ( cost / life ) Rs: 4.00
RATE ANALYSIS UNIT : 49.00 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Small dia explosive kg 54.00 45.00 2430.00
2 Delay detonators Nos 68.00 18.00 1224.00
3 Electric detonators Nos 10.00 10.00 100.00
4 Detonating fuse coil Rm 160.00 8.00 1280.00
5 Use rate of drill rod 2.5 m long Rm 150.00 37.73 5660.00
Reconditioning charges @ 10% 566.00
6 Use rate of air hose Hour 30.00 4.69 140.63
7 Use rate of water hose Hour 30.00 4.00 120.00
8 Sundries ( paint / template etc ) LS 8.00 30.00 240.00Total Rs: 11760.63
Add for small Tools and Plants @ 1% Rs: 117.61
Add for Contractor's Profit @ 10% Rs: 1176.06
Add for Contractor's Overheads @ 5% Rs: 588.03
Total cost of Materials : Rs: 13642.33
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Drilling jumbo Hour 11.00 322.00 3542.00
Fuel / Energy charges Hour 11.00 30.00 330.00
2 Air compressor 15 cmm ( ele ) Hour 7.50 108.00 810.00
Fuel / Energy charges Hour 7.50 627.00 4702.50
3 Jack hammer ( 4 x 7.5 hrs ) Hour 30.00 14.00 420.00
Fuel / Energy charges Hour 30.00 5.00 150.00
4 Pusher leg Hour 30.00 8.00 240.00
Fuel / Energy charges Hour 30.00 3.00 90.00
5 Convey mucker Hour 6.00 658.00 3948.00
Fuel / Energy charges Hour 6.00 174.00 1044.00
Contd
B. MACHINERY ( Contd ) :
Sl No Unit Amountin Rs.
Contd
6 Dumper ( 2 x 6 hrs ) Hour 12.00 480.00 5760.00
Fuel / Energy charges Hour 12.00 277.00 3324.00
7 Pump 10 hp ( ele ) Hour 7.50 5.00 37.50
Fuel / Energy charges Hour 7.50 50.00 375.00
8 Ventilation fans 20 hp ( 2 x 1 ) Hour 2.00 6.00 12.00
Fuel / Energy charges Hour 2.00 100.00 200.00
Perticulars
Description
in Rs.
in Rs.
Rate
Quantity Rate
Quantity
Description Quantity Ratein Rs.
19
-
8/13/2019 Data Rates-Tunnel Works 1
20/20
TUNNEL AND ALLIED WORKS
9 Sundries ( explosive van / magazine ) LS 8.00 30.00 240.00
Total Rs: 25225.00
Add for small Tools and Plants @ 1% Rs: 252.25
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 1045.55
Add for Contractor's Overheads @ 5% Rs: 1261.25
Total hire charges of Machinery : Rs: 27784.05
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Drilling jumbo Hour 11.00 60.50 665.50
2 Crew for Air compressor Hour 7.50 60.10 450.75
3 Crew for Jack hammer Hour 30.00 111.90 3357.00
4 Crew for Convey mucker Hour 6.00 60.10 360.60
5 Crew for Dumper Hour 12.00 72.60 871.20
6 Crew for Pump Hour 7.50 26.90 201.75
7 Crew for ventilation fans Hour 2.00 9.30 18.60
8 Surveyor Day 1.00 154.50 154.50
9 Foreman Day 1.00 177.00 177.00
10 Fitter / Mechanic Day 2.00 157.50 315.00
11 Blaster ( Licensed ) Day 1.00 147.00 147.0012 Helper blasting Day 2.00 141.50 283.00
13 Hammerman Day 2.00 146.00 292.00
14 Maistry 1 in each shift Day 3.00 141.50 424.50
15 Khalasi
for mucking shift 4 Nos Day 4.00 145.50 582.00
16 Heavy mazdoor
for mucking shift 8 Nos Day 8.00 132.00 1056.00
for other 2 shifts 2 No each shift Day 4.00 132.00 528.00
17 Light mazdoor
for cleaning & miscellaneous Day 2.00 130.50 261.00
Total Rs: 10145.40
Add for small Tools and Plants @ 1% Rs: 101.45
Add for Contractor's Profit @ 10% Rs: 1014.54
Add for hidden cost on Labour @ 15% Rs: 1521.81
Add for additional hidden cost on labour @ 10% Rs: 1014.54
Add for Contractor's Overheads @ 5% Rs: 507.27
Total cost of Labour : Rs: 14305.01
ABSTRACT:
A. Cost of Materials Rs: 13642.33
B. Hire charges of Machinery Rs: 27784.05C. Cost of Labour Rs: 14305.01
TOTAL Rs: 55731.39
Add for Air and Water line @ 0.50% Rs: 278.66
Add for Ventilation @ 6.10% Rs: 3399.61
Add for Lighting @ 1.90% Rs: 1058.90
Add for Ele sub-station / Demand charges @ 4.20% Rs: 2340.72
Add for other Enabling works @ 1.70% Rs: 947.43
Total cost for 49.00 cum Rs: 63756.71
Description Quantity Rate
in Rs.