dated: 6 aug. 2001 annexure “b”- spec. gc-5000- turbine and … - turbine... · 2018. 8. 9. ·...
TRANSCRIPT
GC-5000- for Vibrations
1
Dated: 6 Aug. 2001
Annexure “B”- Spec. GC-5000- Turbine and Generator
1. Vibration and dynamic
1.1 Design
1.1.1 General
A. Turbine shall be designed to minimize and withstand vibration according to
I.E.C. specification, and according to the relevant S & L specification (MSS
10.1), which ever is more severe.
B. Balancing of the Turbine shall be according to ISO 1940, latest edition.
Balance Quality Grade shall be G2.5 or better.
C. Vibrations measurements, measurement technique, location, measurement
equipment, criteria and limitations shall also meet the requirements of ISO:
7919-1, 7919-2, 10816-1 and ISO 10816-2 (=hereby ISO Standard) for new
equipment. Unless otherwise specified, the recommendations for vibrations
criteria in ISO Standard which are more severe from the requirements of
para. 1.1.1 (A) above shall be mandatory under this specification.
D. The Generator shall be design to minimize and withstand vibrations
according to NEMA MG-1 requirements for large machines.
E. Unless otherwise specified, alarm settings and limitations shall be according
to A.M. ISO standards Recommendations.
F. Critical speeds definitions under this specification:
Critical Speed: Rotative speed corresponding to a lateral natural frequency
of a rotor in which the amplification factor is more then 2.5.
H. The vibrations of the Turbine and Generator during rated speed operation
and run up/coast down of the units will be such that, continuous safe and
reliable operation of the unit shall be ensured. The vibration level in all speed
range shall not exceed the level specified by ISO Standard.
1.1.2 Any Critical responds of each rotor will fail to meet the separation margin
requirements according to API 612 standard Para. 2.8.2.5 and 2.8.4 But in
any case the separation margin shall be not less then 15% above and 10%
below rated speed limits, which is more sever.
GC-5000- for Vibrations
2
1.1.3 Unless otherwise specified, The Contractor shall provide complete Torsional
and Lateral Vibration Analysis. The analysis shall be done according to API
612 standard Para. 2.8 requirements and shall meet this API standard
limitations.
A. The complete Structural support system shall be taking into account for the
analysis.
B. The damped unbalance response analysis shall indicate that the machine in the
unbalanced condition will meet the acceptance criteria for separation margin as
described in paragraph 2.8.2.5 of the standard API 612.
C. The calculated unbalanced peak to peak rotor amplitudes at any speed from zero to
trip shall not exceed 75% of the minimum design diametrical running clearances
throughout the machine (with the exception of floating ring seal locations).
D. The torsional resonances of the complete train shall be at least 10% above or 10%
below the operating speed of the machine, 3000 rpm (50 Hz).
1.1.4 The Turbine and Generator assembly shall be supplied with a radial and axial shaft
vibration detecting system, including probes, indicators, 4-20mA transmitters and
alarm/trip switch power supplies, adequate NEMA 4X Type enclosures and
appurtenances.
1.1.5 Equipment vibration requirements and criteria
A. The Turbine rotor relative vibrations shall not exceed the level of 80 m, peak-to-
peak, according to the requirement for new equipment of ISO 7919-2 Standard. This
requirement is related to relative shaft vibrations of turbine generator sets, at
running speed of the unit 3000 rpm (50 Hz) (evaluation Zone “A”).
B. The bearing Housing/pedestal vibrations shall not exceed the level of 34 m, peak-
to-peak, noting that this requirement is for new equipment according to evaluation
Zone “A” in ISO 10816-2 Standard . This requirement related to turbine generator
sets, on low frequency foundations, at running speed of the unit 3000 rpm (50 Hz).
GC-5000- for Vibrations
3
1.2 Testing:
A. General
1.2.1 General QA requirements:
For QA requirements refer to Appendix “A”.
1.2.2 Vibration Testing:
B. Shop Test:
Turbine +Generator:
1.2.2.1 Vibrations and dynamics balancing shop test
Dynamics balancing of major parts of the rotating element and assembled
rotating elements will be performed according to requirements of paragraph
2.8.4 of API 612.
The shop test of the assembled machine with the balanced rotor, at specified
operation will meet specified unfiltered vibration limit values.
Electrical and mechanical run out will also be determined.
1.2.2.2 The Contractor shall be responsible for performing a shop verification of
unbalanced response analysis, according to paragraph 2.8.3 of API 612
standard.
A. The Contractor shall be responsible for measurements of the actual critical
speed responses of the unbalanced rotor on the test stand.
B. The measurements shall include speed, shaft vibration amplitudes and
phase.
The Peak to Peak Resultant amplitude value of each response peak shall not
exceed the limits specified in Para. 1.1.5.
C. During the shop test of the machine, assembled with the balanced rotor,
operating at its speed, 3000 rpm (50Hz), the vibration, measured on the shaft
adjacent and relative to each radial bearing, shall not exceed the value of 50
GC-5000- for Vibrations
4
m, peak-to-peak, for the turbine and 50 m, peak-to-peak, for the generator
and exciter.
1.3 Field Testing and Balancing
Turbine + Generator:
1.3.1 After full installation the Same tests as shop tests shall be carried on by the
contractor at the power station according to ISO 1940, ISO 10816, and ISO
7919 to assure that the equipment and its performance comply with the
requirements of the specifications and of the guarantees.
1.3.2 Any measured Critical responds of each rotor will fail to meet the separation
margin requirements according to API 612 standard Para. 2.8.2.5 and 2.8.4
But in any case the separation margin shall be not less then 15% above and
10% below rated speed limits, which is more sever.
1.3.3 The acceptance criteria for the machine, based on the measurements
from this test shall indicate:
(a) At no speed, the shaft deflections shall not exceed 90% of the minimum
design running clearances.
(b) During operating speed at 3000 rpm (50 Hz), the shaft deflection at the
probes, shall not exceed 55% of the minimum design running clearance or 40
m, 0-peak, for the Turbine and 40 m, 0-peak for the Generator
1.3.3 Major parts of the rotating element, such as shaft, balancing drum, and
impellers shall be dynamically balanced according to ISO 1940.
A. The rotating element shall be multiplane dynamically balanced during
assembly.
B After the final balancing has been completed, a residual unbalance check
shall be performed and recorded as described in Appendix “D” of API 612
standard.
GC-5000- for Vibrations
5
1.4. TESTING AND BALANCING DOCUMENTS
1.4.1 General
Documents, Reports and shop test records shall be, including but not limited
as required in this specification and as required in relevant parts of API 612
standard including the full requirements of Appendix E of that standard.
They will be submitted to the Purchaser according to agreed time table
1.4.2 Data of vibration test results shall be evaluated with the aid of vibration
performance chart based on API 612 or ISO standard criteria, whichever is
more severe.
1.4.3 The Contractor shall perform and submit to the Purchaser the results of
dynamic analysis and shop test verifications of the dynamic properties of the
unit components as specified in chapter 2.8 of API 612 Standard (latest
edition).
The following aspects shall be included:
A The analytical determination of machinery Critical Speeds for potential
exciting frequencies which are less, equal or greater than the rotational
speed of the rotor by means of a damped unbalanced rotor response
analysis according to paragraph 2.8.1 of API 612 Standard.
B. Compatibility of support system resonance and drive train critical speeds with
the critical speeds of the machinery being supplied shall be determined and
reported to the Purchaser (para. 2.8.1.6, 2.8.1.7 of API 612 Standard).
1.4.4 A lateral analysis (damped unbalance response analysis) for each machine
and for the whole train shall be performed and provided, in order to assure
acceptable amplitudes of vibration at any speed from zero to over speed trip
according to paragraph 2.8.2 of the API 612 standard. This analysis shall
include:
(a) a plot and identification of the mode shape at each resonant speed from
zero to trip, as well as the next mode occurring above the trip speed;
GC-5000- for Vibrations
6
(b) frequency, phase and response amplitude data at the vibration probe
locations through the range of each critical speed;
(c) modal diagrams for each response in item (b) above, including reference
to couplings, bearing centerlines, location of vibration probes and
machine seal areas;
(d) An additional plot of a test unbalance with prescribed test weight and
conditions (for the purpose of the verification test according to para. 2.8.3
of API 612)
1.4.6 Torsional analysis of each machine and of the complete coupled unit train for
possible excitation sources shall be performed (according to para. 2.8.4 in
API 612 Standard).
It refers to: calculation and acceptance criteria for torsional criticals at
operating speed, operating speed harmonics and possible non-synchronous
excitations; also stress analysis if necessary and transient torsional analysis
will be performed.
1.4.7 Shop verification of unbalanced response analysis (according to paragraph
2.8.3 of API 612 of API Standard).
1.5 Reports and certifications
- The charts of Shop and Filed vibration tests including, but not limited to the
following, shall be submitted to the Purchaser for review and approval:
- results of peak-to-peak displacement measurements of shaft vibrations,
and/or RMS vibration velocity of bearing.
- Results of detailed vibration analysis.
- Summary of the results, including brief conclusions showing that the results
are within all limitations.
GC-5000- for Vibrations
7
1.6. MEASUREMENT
1.6.1 Long Term Vibration measurements will be performed:
(a) On the shaft - relative or absolute displacement in radial planes adjacent
to the two (2) bearings of each of the Turbine and Generator rotors. For
each bearing measurement shall be performed with two (2) transducers
mounted in the same transverse plane perpendicular to the shaft axis
mounted 90 degree apart, on the same bearing half for each bearing.
(b) On machine surfaces or bearings.
1.6.2 The Contractor will specify monitoring system and vibration limits as following:
(a) Proposed vibration monitoring system according to the aims listed by
ISO Standard and appropriate measurement methods.
(b) Alarm and trip values for its conventional vibration measurement system
(bearing and shaft vibration).
(c) Additional relevant parameters and process variables to be incorporated
in the vibration measuring and monitoring system, according to its
standard practice.
1.6.3 Plant Noise and Building vibration
A. For Plant Noise and Building vibration requirements see IEC Spec. No.
92/252/3.30 “Environmental Noise and Vibration Requirements for Turbine
Generator Units” and ISO 2631 and ISO 2631-2.
B. Noise monitoring system
The Contractor will specify the requirements Noise measurement and
monitoring system (see Table 3 of attached Spec. No. 92/252/3.30
“Environmental Noise and Vibration Requirements for Turbine Generator
Units”).
GC-5000- for Vibrations
8
1.7 Monitoring equipment
The contractor shall provide a continuous bearing vibration monitoring
system as follows:
1.7.1 Bearing vibration measuring system
a) Each Turbine and Generator unit shall be provided with two (2) radially and
one (1) axially mounted seismic probes for measuring each bearing
vibrations. The transducers shall be mounted as follows:
- Two (2) Seismic transducers to measure vibrations on each of the
Turbine and Generator bearing. The transducers shall be mounted in the
radial direction, 45º to the vertical.
- one (1) seismic transducer to measure axial vibrations of the thrust
bearing housing
b) The bearing housing shall be furnished with appropriate surfaces, for the
mounting of the seismic transducers, (bosses or raised surfaces located at
the points of measurement for permanent mounting of the seismic
transducers).
The chosen locations shall be based on optimum transmissibility of the
vibration through the bearing housing and accessibility.
c) The protective monitoring system, based on bearing vibration survey shall be
supplied with two channel velocity monitors.
1.7.2 A shaft vibration measuring system
Each Turbine and Generator unit shall be provided with Two (2) pairs of X –
Y proximity probes for shaft vibration measurement on each bearing and at
least one key phasor for measuring shaft rotational speed and phase angle,
as follows:
a) X – Y dual proximity transducer system for each of the Turbine and
Generator bearings for the detection of shaft vibration relative to the
bearing housing.
GC-5000- for Vibrations
9
b) The proximity probes shall be radially oriented at each bearing housing
and spaced 90º apart. The probes shall be mounted 45º (5º) from each
side of the shaft vertical center plane, so that one of them will be at a
position as close as possible to the seismic transducer measuring the
bearing housing vibrations.
Viewed from the driver end of the Turbine, the probe mounted on the left
side shall be designated the Y-probe of the shaft, and the probe mounted
on the right side of the shaft shall be designated the X-probe. Each
bearing where vibration is measured shall utilize the same arrangement.
c) At least one proximity probe key phasor shall be supplied to measure
shaft rotation speed and phase angles. Axial float and differential
expansion between reference mark and probe shall be considered when
locating the reference mark and probe.
The proximity probe shall be of the same type and manufacturer as the
other proximity probes. The proximity probes shall be supplied complete
with cable, proximitors, and power supply.
1.7.3 The general design, conventional hardware, transducer and sensors
arrangement of the vibration measuring and monitoring system supplied by
the Contractor shall be according to API 670 and API 678 standards.
1.7.4 The Contractor shall furnish all required probe power supplies as part of the
monitoring system and signal conditioning devices mounted locally near the
a. m. transducers.
The signal-conditioning devices, probe and transducer housings shall meet
NEMA 4X requirements.
1.7.5 The Contractor shall provide the System Configuration Plan of the
turbogenerator vibration measuring and monitoring hardware including the
manufacturer and model numbers.
GC-5000- for Vibrations
10
1.7.6 The Contractor shall establish the vibration limits for alarm and the limit for
shutdown of the turbogenerator. Values shall be within accepted limits as
specified in Para. 1.1 E above.
1.7.7 Each vibration transducer shall be calibrated using the actual transducer
system to be installed on the machine. This calibration shall be verified and
documented by the agency that installs the transducer in the machine.
For proximity transducers a graph of the gap (a minimum of 10 points in both
mils and micrometers) versus the transducer’s output voltage shall be
prepared and supplied to the Purchaser.
1.7.8 The bearing and shaft measurement system, including rotational speed and
phase data shall permit easy access for external connection to vibration
analysis and/or recording instruments.
1.7.9 Each vibration monitoring channel shall have two (2) contacts, one for alarm
and one for trip, each rated at 125V DC capable of breaking 0.1 (Amp)
inductive current and an 4-10mA output for Purchaser’s use.
1.7.10 The monitoring system shall include the necessary communication link,
which shall enable the integration of all the data in the Plant Vibration
Diagnostic System provided by others.
1.7.11 The Turbine Supervisory Instrument System shall provide alarm signals from
the vibration and differential expansion channels, in case they should exceed
preset limits to the plant Process Control and Management System supplied
by others.
1.7.12 The generator monitoring system provided, shall be supplied complete with
all sensors necessary to detect, transmit, alarm and conditions generator and
auxiliaries malfunctions, and to assure safe, reliable and economic operation
of the Turbine Generator Unit.
GC-5000- for Vibrations
11
1.7.13 Options
A. The Contractor shall further provide an proposed option for Vibration
Monitoring System and Vibration Analysis Software based on his common
standard practice.
1.8 Long Term vibration criteria and alarms - after commissioning
1.8.1 Field vibration criteria for the turbine generator units
The field measured vibrations of the Turbine and Generator unit shall not
exceed at steady state operation the range classified as “Zone A” at least for
18 months after their commissioning according to the following:
- Bearings, according to ISO 10186-2 standard.
- Shafts, according to ISO 9719-2 standard.
1.8.2 Alarms:
According to ISO 9719-2 requirements the ALARM value should be set
higher than the baseline by an amount equal to 25% of the upper limit of
Zone B. If the baseline is low, the ALARM may be below the Zone C (see
Tables A.1and A.2 in ISO 9719-2).
If the steady-state baseline changes (for example after a machine overhaul),
the ALARM setting should be revised accordingly. Different operational
ALARM settings may then exist for different bearings on the machine,
reflecting differences in dynamic loading and bearing support stiffness.
1.8.3 Settings of TRIPS:
The Contractor shall submit to the Purchaser the TRIP values for Turbine
Generator shaft vibration.
The TRIP values recommended by ISO 7919-2 and 10816-2 Standards for
maximum shaft and bearing vibration ARE MANDATORY.
The TRIP values will generally relate to the mechanical integrity of the
machine and shall depend on any specific design feature which has been
introduced to enable the machine to withstand abnormal dynamic forces.
GC-5000- for Vibrations
12
Annexure “C2”- Spec. GC-5000 - Turbine and Generator
1. Does machine pass trough critical speed of any parts in coming up?
(if So , what part and what rpm?
- Turbine
- Generator
- Exciter
2. Calculated all Designed Lateral Critical Speed (R/min), that are below
rated speed
- For each Turbine Rotor
- Generator
- Exciter
3. Calculated all Designed Torsional Critical Speed (R/min), that are
below rated speed
- For each Turbine Rotor
- Generator
- Exciter
4. Maximum allowed Lateral vibration amplitude (p-p) during start up and
shut down for: bearings house and rotor (μm)
- For each Turbine Rotor
- Generator
- Exciter
5. Maximum allowed Lateral vibration amplitude (p-p) during steady state
for: bearings house and rotor (μm)
- For each Turbine Rotor
- Generator
- Exciter
6. Maximum allowed Lateral vibration amplitude (p-p) in frequencies
double then the rated speed for steady state for: bearings house and
rotor (μm)
- For each Turbine Rotor
GC-5000- for Vibrations
13
- Generator
- Exciter
7. Maximum allowed vibration amplitude (p-p) for the
base and foundation
- In steady state condition
- In critical speeds
8. Maximum allowed Lateral vibration amplitude (μm p-p) for rotor shaft
after it balancing at critical speed:
- For each Turbine Rotor
- Generator
- Exciter
9. Vibration Monitoring system for Rotor and Bearing:
- Type (s)
- Manufacturing (s)
GC-5000- for Vibrations
14
Appendix “A”- General QA requirements
A.1 The contractor shall submit to the Purchaser all the necessary information
describing the manufacturer's testing facilities, including test shop, testing
and instrumentation capabilities, and the tests, which are included in the
Contract Price.
A.2 The Purchaser shall have the right to appoint inspectors authorized to follow
the progress of the work and the manner in which it is being carried out, to
inspect materials at manufacturer or at the point of delivery, to reject
defective materials either at the source of supply or point of delivery at any
time, or to suspend work which is not being done properly or is not in
accordance with the plans and specifications.
A.3 The Purchaser's inspector shall have free access to the manufacturing
plant(s) and to all parts of the Vendor's plant engaged in work or equipment
and materials to be supplied to the Purchaser, at all reasonable working
hours while work is being performed on this specifications.
A,4 The Purchaser shall have the right after the complete erection of the
equipment to make, at its own expense, such field tests as it may deem
proper or necessary to satisfy itself that the equipment meets the
requirements of the Specifications in every respect. The contractor shall have
the right at its own expense to witness such tests to ensure that the
equipment is operated properly and to make such observations as he may
desire.
In making tests under this specification no minus (-) tolerance or margin shall
be allowed with respect to capacity, or efficiency at the rated or specified
conditions.
A.5 If the equipment fails in any respect to meet the requirements of the
Specifications or guarantees, the Contractor shall immediately, and at its own
expense, make such repairs, alterations and/or replacements as may be
necessary to assure that the equipment and its performance shall conform to
the requirements of the Specifications and guarantees. The Contractor shall
also, at its own expense, make such additional factory tests as the Purchaser
GC-5000- for Vibrations
15
may require to show the effect on the equipment and its performance of such
alterations and replacements.
Field tests shall be done by the Purchaser at the Power Station to assure that
the equipment and its performance shall conform to the requirements of the
specifications and guarantees.