Work Progress as of February 2013 A. Early Industries The Early Industrial Estate to be established in the Pagaw Zoon Oil Palm area has emerged to serve the initial demand of manufacturers and investors in light and medium industries who inquire the early opportunity of investment in Myanmar with more cost and tax benefits under the Dawei Special Economic Zone (SEZ) Law. The Early Industrial Estate is plan to begin operation by early 2014 with all supporting infrastructure necessary by the target date such as: small port (to be completed by early 2013), access road from the Myanmar/Thailand border (upgrade of road condition ongoing for all year use), electricity (early 2014), water (early 2014) and telecommunication (early 2014). For medium and light industrial zones, we have provided land areas (Zones) for potential industries as follow: Zone 1: Garment & Textile Industries Zone 2: Electronics & Electrical Industries Zone 3: Rubber Industry Zone 4: Furniture (Rubber Wood) Industry Zone 5: Plastic & Construction Material Industries Zone 6: Tanning & Leather-based Industries Zone 7: Canned & Frozen Food Industries The investors will receive particular benefits from their investment such as (1) massively local labor force in manufacturing process, (2) GSP privilege, several tax benefits and import-export incentives from SEZ, (3) convenience of land and marine transportation conveying raw materials or finished products to neighboring countries and importer’s destinations, (4) availability of abundant raw materials/resources available in Dawei and its vicinities, and (5) gaining the position of business leadership to surf on growing investment opportunity in Myanmar.

Upload: dawei-project

Post on 12-Mar-2016

224 views

Category:

Documents


4 download

DESCRIPTION

Dawei Project Work Progress February 2013

TRANSCRIPT

Page 1: Dawei Project Work Progress February 2013

Work Progress as of February 2013

A. Early Industries

The Early Industrial Estate to be established in the Pagaw Zoon Oil Palm area

has emerged to serve the initial demand of manufacturers and investors in light

and medium industries who inquire the early opportunity of investment in

Myanmar with more cost and tax benefits under the Dawei Special Economic

Zone (SEZ) Law. The Early Industrial Estate is plan to begin operation by early

2014 with all supporting infrastructure necessary by the target date such as:

small port (to be completed by early 2013), access road from the

Myanmar/Thailand border (upgrade of road condition ongoing for all year use),

electricity (early 2014), water (early 2014) and telecommunication (early 2014).

For medium and light industrial zones, we have provided land areas (Zones) for

potential industries as follow:

Zone 1: Garment & Textile Industries

Zone 2: Electronics & Electrical Industries

Zone 3: Rubber Industry

Zone 4: Furniture (Rubber Wood) Industry

Zone 5: Plastic & Construction Material Industries

Zone 6: Tanning & Leather-based Industries

Zone 7: Canned & Frozen Food Industries

The investors will receive particular benefits from their investment such as (1)

massively local labor force in manufacturing process, (2) GSP privilege, several

tax benefits and import-export incentives from SEZ, (3) convenience of land

and marine transportation conveying raw materials or finished products to

neighboring countries and importer’s destinations, (4) availability of abundant

raw materials/resources available in Dawei and its vicinities, and (5) gaining the

position of business leadership to surf on growing investment opportunity in

Myanmar.

Page 2: Dawei Project Work Progress February 2013

Physical elements

- Total land area initially 7 km2 or 1,750 acres (4,375 rais) (each zone

occupies 1 km2 - expandable upon demand )

- Location benefits

Zone 1 and 2 - connected to main road and township area

Zone 3, 4, 5, 6 – connected to sub-main road, Pa Yain Byu Reservoir

and Pagaw Zoon relocation village

Zone 7 – connected to small port and fishery port (for canned & frozen

food industries)

- Supporting utilities and infrastructure:

Electricity

33 MW initial phase gas engine in 2014

250 MW Combine Cycle (Q4 2015)

400 MW Clean Coal (Q4 2016)

Water Supply:

33,600 cu. m./day from Pa Yain Byu Reservoir 5.9 million cu. m. (Q1

2014)

Ka Loat Htar Reservoir 500 million cu. m.(Q4 2015)

Water treatment plant and distribution network

Telecommunication:

High speed internet (up to 10 Mbps), fixed lines, mobile lines with 3G

technology, International calls

Roads:

18 km main road 18 km within Dawei Project area (4 lanes in early

phase)

Page 3: Dawei Project Work Progress February 2013

132 km access road from/to Thailand (Dawei – Ban Phu Nam Ron)

upgrading to become usable all year round by 2013)

Small Port:

100-m long jetty berth, 8,000 – 10,000 DWT general cargo ship or 250 -

400 TEU container ship

Other services:

Waste water treatment, One Stop Service Centre, Flood Protection by

flood control channel with concrete sheet piles 50-100 m wide and 2.5-

6.0 m deep and 3 pumping stations

Page 4: Dawei Project Work Progress February 2013

Figure 1: Project Layout - Dawei Early Industrial Estate Zone1-7

Page 5: Dawei Project Work Progress February 2013

Figure 2: Conceptual Layout of Early Industrial Estate Zone 1-2 and Township

Figure 3: Conceptual Layout of Early Industrial Estate Zone 3-6

Page 6: Dawei Project Work Progress February 2013

Figure 4: Conceptual Layout of Early Industrial Estate Zone 7

Page 7: Dawei Project Work Progress February 2013

Clearing and Grubbing for Early Industries and Township

Progress Photos

Picture 1: Clearing Area, Phase1

Picture 3: Clearing by Back Hoe, Casting Yard

Page 8: Dawei Project Work Progress February 2013

Picture 4: Temporary Stock of Palm Truck, Casting Yard

Page 9: Dawei Project Work Progress February 2013

Early Township

In order to support the Dawei Early Industrial Estate Project, the first phase of Dawei

Local Township aims to have the capacity to contain 32,000 workforces minimum

and will keep expanding in parallel along with the industrial development until fulfill

the 7 sq.km. designated area.

The goal of this town is to provide the most suitable atmosphere for the local

workforce along with the Energy Saving Concept. All the layout and building designs

are applied with the green concepts. The residential blocks are well calculated by the

perfect walking distance in order to create a walking-friendly town. The typical 5 floor

apartment building design orientation is to avoid daylight heat and take the

advantage of natural ventilation into the public area in the building. For the

landscape design, the field survey has been conducted for the purpose of relocating

and nursing the local endangered plants. All these natural treasures will be carefully

planted into all the township green areas and walkways.

Picture 5-6: Local Township Construction Area

Page 10: Dawei Project Work Progress February 2013

Picture 7-9: Model of Local Worker Apartment

Page 11: Dawei Project Work Progress February 2013

Picture 10: Model of Local Township Retail Shops & Hostels

Page 12: Dawei Project Work Progress February 2013

Picture 11-12: Perspective of Township Sale Office

Page 13: Dawei Project Work Progress February 2013

B. Access Road

Progress Photos

Section 1 (from Route No.8 to Myitta):

Picture 1: Complete Construction the 4th Labor House at Main Camp, Star Moo

Picture 2: Clearing Alignment ROW 80 m.

Page 14: Dawei Project Work Progress February 2013

Picture 3: Under Construction Pile Temporary Bridge

Picture 4: Footing of Temporary Bridge (Under Construction)

Page 15: Dawei Project Work Progress February 2013

Picture 5: Filling Road Preparing for Realignment

Section 2 (from Myitta to Sin Byu Daing):

Picture 6: Complete Installation Box Culvert

Page 16: Dawei Project Work Progress February 2013

Picture 7: Under Construction of Labour House

Picture 8: Complete Construction the 3rd Staff House at Myitta Camp.

Page 17: Dawei Project Work Progress February 2013

Section 3 (from Sin Byu Daing to Hti Khee):

Picture 9: Widening Access Road

Picture 10: Material Covering

Page 18: Dawei Project Work Progress February 2013

Picture 11: the 2nd Staff at Base 1 under Construction

Picture 12: Base for 6 tanks Fuel Storage at Base 1

Page 19: Dawei Project Work Progress February 2013

Picture 13: Completion of Elevation Temporary Bridge

Page 20: Dawei Project Work Progress February 2013

C. Port

Progress Photos

Picture 1-2: Temporary Access Road for North Quay Wall

Picture 3-4: Temporary Access Road for South Quay Wall

Picture 5-6: Site Clearing for Main Port Area Works

Page 21: Dawei Project Work Progress February 2013

D. Reservoir

Progress Photos

Picture 1-2: Test Pit

Picture 3: SPT at Main Dam

Page 22: Dawei Project Work Progress February 2013

Picture 4: Soil Sample from SPT

Picture 5: Aquatic Ecology Investigation with Pisuth Technology’s Experts

Page 23: Dawei Project Work Progress February 2013

Picture 6: Topographic Survey at Pa Yian Byu Reservoir

Picture 7: Access Road Improvement

Page 24: Dawei Project Work Progress February 2013

E. Relocation & Compensation

Progress Photos

Picture 1-2: Compensation Paid for Bawah Area

Picture 3-4: Compensation Paid for Port Area

Picture 5-6: Compensation Paid for Main Road Area

Page 25: Dawei Project Work Progress February 2013

Picture 7-8: Compensation Paid for Combined Cycle Power Plant Area

Picture 9-10: Pagawzoon Early Township phase 1-2 Area

Picture 11-12: Compensation Paid for Early Water Treatment Plant

Page 26: Dawei Project Work Progress February 2013

Picture 13-14: Compensation Paid for Pa Yain Byu Reservoir Area

Page 27: Dawei Project Work Progress February 2013

F. Industrial Estate Infrastructure

Clearing and Grubbing for Main Road and Access Road Construction

Progress Photos

Picture 1: Access Road at sta. 5+000

Picture 2: Access Road at sta. 9+000

Page 28: Dawei Project Work Progress February 2013

Picture 3: Clearing Right of way at sta. 14+000

Picture 4: Clearing Right of way at sta. 17+000

Page 29: Dawei Project Work Progress February 2013

Clearing and Grubbing for Pagaw Zoon Relocation Construction Project

Progress Photos

Picture 5: Clearing Pagaw Zoon Relocation Area

Picture 6: Temporary Stock and Dispose Rubbish

Page 30: Dawei Project Work Progress February 2013

Picture 7: Temporary Stock of Palm Trunk

Picture 8: Clearing Pagaw Zoon Relocation Area

Page 31: Dawei Project Work Progress February 2013

G. Corporate Social Responsibility (CSR)

Social Development Program

Religious Support: Purification Ceremony of the ground to set up the

Pagoda at Ma Yin Gyi Hill Side.

Picture 1-4: ITD and Representatives from Myanmar Government Joined the

Purifacation Ceremony of the Ground to Set Up the Pagoda at Ma Yin Gyi

Hill Side

Public Health: Malaria Control

icture 5-7: 8,000 Mosquito Nets Were Shipped to CSR at Dawei Site

Page 32: Dawei Project Work Progress February 2013

Picture 8-12: Blood Testing and Mosquito Nets Distribution at CSR Office

Picture 13-14 : Blood Testing and Mosquito Nets Donation at Ka Loat Htar

Medical treatment and hospitalization

Picture 15 : Medicines Are Refilled in Our Stock on the 19th January 2013

Page 33: Dawei Project Work Progress February 2013

Community Development

Picture 16-17: Before and After Photos of the Road Repairing

Job Opportunity and Livelihood Development

Agricultural and Livelihood Training Programs

Picture 18-19: Training at Lae Shuang Village

Picture 20-21: Trainging at Pain Shaung Village

Page 34: Dawei Project Work Progress February 2013

Skill Trainings: Computer training

Picture 22-23: Computer Training Program Atmosphere

Public Relation: CSR Exhibition

Picture 24-25: Independence Day Exhibition Hall at Shwe Wei Thiri

Page 35: Dawei Project Work Progress February 2013

H. Bawah Resettlement Site

Progress Photos

Picture 1: Work Progress of Concrete Plank

Picture 2: Work Progress of Concrete Block

Page 36: Dawei Project Work Progress February 2013

Picture 3-4: Work Progress of Door and Window

Picture 5-6: Work Progress of Precast Concrete Electricity Post

Picture 7-8: Work Progress of Precast Concrete Electricity Post Installation

I.

Page 37: Dawei Project Work Progress February 2013

Picture 9-12: Work Progress of Relocation House Construvtion

Picture 13-14: Work Progress of Primary School

Page 38: Dawei Project Work Progress February 2013

Picture 15-16: Work Progress of Clinic

Picture 17-18: Work Progress of Monastery

Picture 19-20: Work Progress of Local Market

Page 39: Dawei Project Work Progress February 2013

J. Quarry

Progress Photo

Picture 1: Area of Crushing Plant

Picture 2: Truck Waiting to Dump Rock into Crushing Plant

Page 40: Dawei Project Work Progress February 2013

Picture 3: Dumping Point for Crushing and Further Differentiating Size of Rock,

Soil and Sand

Picture 4: Process System Controlling Room

Page 41: Dawei Project Work Progress February 2013

Picture 5: Differentiated Rock, Soil and Sand Sending by Conveyor Belt

Picture 6: Rock, Soil and Sand from Crushing Process in Many Size Passed by

Conveyor Belt

Page 42: Dawei Project Work Progress February 2013

Picture 7: Pile of Soil Seperated from Rock (Waste)

Picture 8: Pile of Big Crushed Rock (Aggregate) from Crushing Plant

Page 43: Dawei Project Work Progress February 2013

Picture 9: Pile of Crushed Stone (Base Course) From Crushing Plant

Picture 10: Pile of Size 3/8 Rock from Crushing Plant

Page 44: Dawei Project Work Progress February 2013

Picture 11: Pile of Stone Dust from Crushing Plant

Picture 12: Pile of Size 3/4 Rock from Crushing Plant

Page 45: Dawei Project Work Progress February 2013

K.Small Port

Picture of small port construction

Picture 1: Pouring Topping Concrete to Beams, Loading Platform as of January

14th, 2013

Picture 2: West Zone of Loading Platform as of January 14th, 2013

Page 46: Dawei Project Work Progress February 2013

Picture 3: East Zone of Loading Platform as of January 14th, 2013

Picture 4: Piling Line 19, 20 and 21 of Loading Platform as of January 15th, 2013

Page 47: Dawei Project Work Progress February 2013

Picture 5: West Zone of Loading Platform as of January 15th, 2013

Picture 6: East Zone of Loading Platform as of January 14th, 2013

Page 48: Dawei Project Work Progress February 2013

Picture 7: Middle Zone of Loading Platform as of January 16th, 2013

Picture 8: West Zone of Loading Platform as of January 16th, 2013

Page 49: Dawei Project Work Progress February 2013

Picture 11: The Southeast Corner of Loading Platform as of January 17th, 2013

Picture 12: The Northeast Corner of Loading Platform as of January 17th, 2013