COMMISSIONING CHECKSHEETDC SWITCHBOARD DOCUMENT NUMBER
Document1 Page 1 of 3 Revision: A
18/10/10
Project name Drawing number
Project number Function
Contract Operation number
Client Location
Standard AS:3000 Fed From
Manufacturer Serial number
NOTE: Where automated relay test equipment is used, the test results obtained may take priority over or supplement theinformation recorded on this check sheet. In this case a reference will be made to an attached result sheet.
ABIDE BY SAFETY AND ISOLATION PROCEDURES IN SWMS7
1 VERIFY INSTALLATION
Tests Required (Minimum)
Schematics
Green-lined/Updated
Operation
(Pass/Fail)
Accepted
By(signature)
Verify board installation method
Verify board design and labelling as per schematic notes
Verify clearances, terminal shrouding/pole blanks are installed and labelled
Verify operation of all handles/locks N/A
Verify door seals N/A
Ensure all penetrations are filled/blanked N/A
2 VERIFY CIRCUIT BREAKER/FUSE/LINK/RELAY TYPES AND RATINGS
Tests Required (Minimum)
Schematics
Green-lined/Updated
Operation(Pass/Fail)
Accepted
By(signature)
Verify circuit breaker/fuse and link type and ratings
Verify relay types and ratings
3 VERIFY EARTHING
Tests Required (Minimum)Schematics
Green-lined/Updated
Operation(Pass/Fail)
AcceptedBy
(signature)
Verify earthing to each cubicle section/gland plate/escutcheon plate/door
Verify cable screen earthing
Verify spare cores are earthed
Test earth resistance to earth grid/stakeSwitchboard Earth bar to grid/stake
Acceptance 0.5
-
7/27/2019 DC Switchboard Checksheet
2/3
COMMISSIONING CHECKSHEETDC SWITCHBOARD DOCUMENT NUMBER
Document1 Page 2 of 3 Revision: A
18/10/10
4 VERIFY CABLE INSTALLATION
Tests Required (Minimum)Schematics
Green-lined/Updated
Operation(Pass/Fail)
AcceptedBy
(signature)
Verify cable types as per schematics
Verify cable glanding N/A
Verify cable bending radius(12x diameter for multi-core, 15x diameter for single-core)
N/A
Verify segregation N/A
Verify ducting/cable ties
Verify internal and external labelling
Verify ferruling as per schematics
Verify termination lugs for correct size/type N/A
Verify terminal tightness N/A
5 TEST INSULATION RESISTANCE
Tests Required (Minimum)Schematics
Green-lined/Updated
Operation(Pass/Fail)
AcceptedBy
(signature)
Verify switchboard insulation resistance N/A
Test at 1kV for 1 MinutePOS E NEG E POS - NEG Acceptance
100M (New), 1M (Aged)M M M
6 TEST INCOMMING SUPPLIES
Tests Required (Minimum)
Schematics
Green-lined/Updated
Operation
(Pass/Fail)
Accepted
By(signature)
Verify incoming supply polarity and phasing N/A
7 RECORD VOLTAGES
Tests Required (Minimum)Schematics
Green-lined/Updated
Operation(Pass/Fail)
AcceptedBy
(signature)
Record switchboard voltages N/A
POS-E NEG-E POS-NEG
-
7/27/2019 DC Switchboard Checksheet
3/3
COMMISSIONING CHECKSHEETDC SWITCHBOARD DOCUMENT NUMBER
Document1 Page 3 of 3 Revision: A
18/10/10
Remarks:
The associated system has been tested and proved to operate successfully as per the design information provided. Please refer to the DefectReport list and Testing Equipment Details.
Commissioning Officer: Signed: Date:
The test results have been reviewed, are within tolerance and are consistent with the design information provided.
Client Commissioning Engineer: Signed: Date:
DefectReport
Date Subject Recommendation Resolved
1
2
3
4
5
6
7
8
9
10
Test equipment Description Serial Number