dc switchboard checksheet

Upload: warwick-audet

Post on 14-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 DC Switchboard Checksheet

    1/3

    COMMISSIONING CHECKSHEETDC SWITCHBOARD DOCUMENT NUMBER

    Document1 Page 1 of 3 Revision: A

    18/10/10

    Project name Drawing number

    Project number Function

    Contract Operation number

    Client Location

    Standard AS:3000 Fed From

    Manufacturer Serial number

    NOTE: Where automated relay test equipment is used, the test results obtained may take priority over or supplement theinformation recorded on this check sheet. In this case a reference will be made to an attached result sheet.

    ABIDE BY SAFETY AND ISOLATION PROCEDURES IN SWMS7

    1 VERIFY INSTALLATION

    Tests Required (Minimum)

    Schematics

    Green-lined/Updated

    Operation

    (Pass/Fail)

    Accepted

    By(signature)

    Verify board installation method

    Verify board design and labelling as per schematic notes

    Verify clearances, terminal shrouding/pole blanks are installed and labelled

    Verify operation of all handles/locks N/A

    Verify door seals N/A

    Ensure all penetrations are filled/blanked N/A

    2 VERIFY CIRCUIT BREAKER/FUSE/LINK/RELAY TYPES AND RATINGS

    Tests Required (Minimum)

    Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    Accepted

    By(signature)

    Verify circuit breaker/fuse and link type and ratings

    Verify relay types and ratings

    3 VERIFY EARTHING

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify earthing to each cubicle section/gland plate/escutcheon plate/door

    Verify cable screen earthing

    Verify spare cores are earthed

    Test earth resistance to earth grid/stakeSwitchboard Earth bar to grid/stake

    Acceptance 0.5

  • 7/27/2019 DC Switchboard Checksheet

    2/3

    COMMISSIONING CHECKSHEETDC SWITCHBOARD DOCUMENT NUMBER

    Document1 Page 2 of 3 Revision: A

    18/10/10

    4 VERIFY CABLE INSTALLATION

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify cable types as per schematics

    Verify cable glanding N/A

    Verify cable bending radius(12x diameter for multi-core, 15x diameter for single-core)

    N/A

    Verify segregation N/A

    Verify ducting/cable ties

    Verify internal and external labelling

    Verify ferruling as per schematics

    Verify termination lugs for correct size/type N/A

    Verify terminal tightness N/A

    5 TEST INSULATION RESISTANCE

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify switchboard insulation resistance N/A

    Test at 1kV for 1 MinutePOS E NEG E POS - NEG Acceptance

    100M (New), 1M (Aged)M M M

    6 TEST INCOMMING SUPPLIES

    Tests Required (Minimum)

    Schematics

    Green-lined/Updated

    Operation

    (Pass/Fail)

    Accepted

    By(signature)

    Verify incoming supply polarity and phasing N/A

    7 RECORD VOLTAGES

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Record switchboard voltages N/A

    POS-E NEG-E POS-NEG

  • 7/27/2019 DC Switchboard Checksheet

    3/3

    COMMISSIONING CHECKSHEETDC SWITCHBOARD DOCUMENT NUMBER

    Document1 Page 3 of 3 Revision: A

    18/10/10

    Remarks:

    The associated system has been tested and proved to operate successfully as per the design information provided. Please refer to the DefectReport list and Testing Equipment Details.

    Commissioning Officer: Signed: Date:

    The test results have been reviewed, are within tolerance and are consistent with the design information provided.

    Client Commissioning Engineer: Signed: Date:

    DefectReport

    Date Subject Recommendation Resolved

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    Test equipment Description Serial Number