debonding in pretensioned beams-precast strands, part 2

258
SCHOOL OF CIVIL ENGINEERING INDIANA DEPARTMENT OF TRANSPORTATION r JOINT HIGHWAY RESEARCH PROJECT Part 2 Final Report FHWA/INDOT/JHRP-92-25 Strand Debonding in Pretensioned Beams - Precast Prestressed Concrete Bridges with Debonded Strands Simply Supported Tests 0=Ac Abdalla, J A. Ramirez, and R.H. Lee : p* % UNIVERSITY

Upload: others

Post on 11-Sep-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Debonding in Pretensioned Beams-Precast Strands, Part 2

SCHOOL OF

CIVIL ENGINEERING

INDIANA

DEPARTMENT OF TRANSPORTATION

r

JOINT HIGHWAY RESEARCH PROJECT

Part 2 Final Report

FHWA/INDOT/JHRP-92-25

Strand Debonding in Pretensioned Beams- Precast Prestressed Concrete Bridges

with Debonded Strands

Simply Supported Tests

0=Ac Abdalla, JA. Ramirez, and R.H. Lee

:

p*%

UNIVERSITY

Page 2: Debonding in Pretensioned Beams-Precast Strands, Part 2
Page 3: Debonding in Pretensioned Beams-Precast Strands, Part 2

JOINT HIGHWAY RESEARCH PROJECT

Part 2 Final Report

FHWA/INDOT/JHRP-92-25

Strand Debonding in Pretensioned Beams- Precast Prestressed Concrete Bridges

with Debonded Strands

Simply Supported Tests

O.A. Abdalla, J.A. Ramirez, and R.H. Lee

Page 4: Debonding in Pretensioned Beams-Precast Strands, Part 2
Page 5: Debonding in Pretensioned Beams-Precast Strands, Part 2

Purdue University

mSchool of Civil Engineering

Final Report

Strand Debonding in Pretensioned Beams - Precast Prestressed Concrete Bridge

Girders with Debonded Strands.

Part 2, Simply Supported Tests

June 1, 1993

Proj.No. :C-36-56B

File No. : 7-4-28

To: Vincent P. Drnevich, Director

Attached is Part 2, of 2, Final Report of a research project entitled, "Strand Debonding in

Pretensioned Beams" By O.A. Abdalla, J. A. Ramirez, and R.H. Lee. The report considers

the comments of the advisory committee.

Respectfully submitted,

Mio A. Ramirez, and R.H. Lee, Co-Principal Investigators

cc: A. G. Altschaeffl J. D. Flicker J. A. Ramirez

P. L. Bourdeau K. R. Hoover G. F. Rorbakken

M. D. Bowman R. B. Jacko C. F. Scholer

M. J. Cassidy L. S. Jones G. B. Shoener

L. M. Chang R. H. Lee K. C. Sinha

S. Diamond C. W. Lovell D. L. Tolbert

J. J. Dillon R. H. Lowry R. Vancleave

W. L. Dolch D. W. Lucas C. A. Venable

V. P. Drnevich B. G. McCullouch T. D. White

A. A. Fendrick B. K. Partridge

r \C 1 V 1 L

ENGINEERINGPURDUEIVERSITY

L. E. WoodJ. R. Wright

1284 Civil Engineering Building • West Lafayette. IN 47907-1284

Page 6: Debonding in Pretensioned Beams-Precast Strands, Part 2

Digitized by the Internet Archive

in 2011 with funding from

LYRASIS members and Sloan Foundation; Indiana Department of Transportation

http://www.archive.org/details/debondinginpreteOOabda

Page 7: Debonding in Pretensioned Beams-Precast Strands, Part 2

TECHNICAL REPORT STANDARD TITLE PACE

1. Report No.

FAWA/INDOT/JHRP-92

2. Government Accession No.

4. Title and Subtitle

Debonding in Pretensioned Beams-PrecastPrestressed Concrete Bridge Girders with DebondedStrands- Part 2, Simply Supported tests

3. Recipient's Catalog No.

5. Report Date

Timp 1 , 19936. Performing Organization Code

7. AuhSor(s)

O.A. Abdalla, J. A. Ramirez , R.H. Lee

8. Performing Orgonizotion Report No.

FHWA/INDOT/JHRP-92

9. Performing Organization Name and Address

Joint Highway Research ProjectPurdue University1284 Civil Engineering Building

10. Worlr Unit No.

1 1 . Contract or Grant No.

12. Sponsoring Agency Name and Addres*

Indiana Department of TransportationState Office Building100 N. Senate Ave. Indianapolis, IN 46204

13. Type of Report ond Period Covered

Final ReportExecutive SummaryJune 1 , 1QSQ- May Tl , 1QQ?

'4. Sponsoring Agency Code

15. Supplementary Notes

Conducted in cooperation with the U.S. Department of Transportation, FederalHighway Administration, NCP H401A2362

16. Abstroct

This report summarizes an experimental investigation regarding the effectsof strand debonding on the flexure and shear behavior of simply supported precastpretensioned bridge members composite with a cast-in-place deck slab.

Five specimen sets were fabricated and tested to failure as simply supportedmembers under a single concentrated load. Four specimen sets consisted of Type-IAASHTO girders composite with a cast-in-place deck slab. One specimen set consis-ted of Indiana State Type CB-27 box girders also composite with a cast-in-placedeck slab.

Each specimen set consisted of two identical beams with different stranddebonding schemes near the ends. In each set, one beam had the strands bondedthroughout the entire length. The other one had some percentage of the strandsdebonded near the ends.

The current ACI/AASHTO requirements for flexure and shear design of preten-sioned bridge girders with debonded strands were examined.

17. Key Words

Flexural strength, shear strength,blanketed strands, continuous bridges,precast construction

18. Distribution Statement

No restriction. This document is avail-able to the public through the NationalTechnical Information ServiceVirginia 22161

19. Security Classif. (of this report)

Unclassified

20. Security Classif. (of this page)

Haelaasifiad

21. No. of Pages 22. Price

Form DOT F 1700.7 <e-e»)

Page 8: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 11 -

ACKNOWLEDGEMENTS

Thanks are extended to the advisory committee members especially Mr. Scott

Herrin and Mr. Steve Toillion for their suggestions and helpful comments in finanlizing

the report.

The prestressed concrete girders tested in this investigation were manufactured by

Hydro Conduit Corporation in Lafayette, Indiana. Their cooperation and contributions

in the instrumentation, manufacture and transportation of the beams are appreciated.

Sincere thanks are expressed to Karl Schmid and Chris Ogg who tested the first two

specimen sets. Thanks are extended to Russ Maurey, Doug Cleary and Hendy Hassan

for their help during the experimental phase of this project.

Financial support was provided by the Federal Highway Administration and the

Indiana Department of Transportation through the Joint Highway Research Project,

School of Civil Engineering, Purdue University, West Lafayette, IN. Their cooperation

and encouragement are appreciated.

Page 9: Debonding in Pretensioned Beams-Precast Strands, Part 2

- Ill -

TABLE OF CONTENTS

Page

LIST OF TABLES vi

LIST OF FIGURES vii

NOTATION xix

ABSTRACT xxii

CHAPTER 1 - INTRODUCTION 1

CHAPTER 2 - BACKGROUND 3

2.1 Introduction 3

2.2 Curtailment of Reinforcing Steel 3

2.2.1 1959 Texas Tests 3

2.2.2 1969 Alberta Study 5

2.2.3 1972 Imperial College Approach 6

2.3 Strand Debonding 7

2.3.1 1965 PCA Tests 8

2.3.2 1971 Glasgow Tests 9

2.3.3 1975 Tulane Strand Blanketing Report... 9

2.3.4 1979 PCA Tests 10

2.3.5 1983 Auckland Shear Behavior Tests 1

1

2.3.6 1987 Purdue Fatigue Study 12

2.4 Development Length 12

2.4.1 Hanson and Kaar [1959] 13

2.4.2 ACI/AASHTO [1989] Provisions 14

2.4.3 Zia and Mostafa [1977] 15

2.4.4 EL Shahawy and Batchelor [1992] 16

2.5 Summary 16

CHAPTER 3 - EXPERIMENTAL PROGRAM 19

3.1 Introduction 19

3.2 Materials 19

Page 10: Debonding in Pretensioned Beams-Precast Strands, Part 2

- IV -

Page

3.2.1 Concrete 19

3.2.2 Prestressing Steel 20

3.2.3 Non-Prestressed Reinforcement 20

3.3 Simply Supported Tests 20

3.3.1 Specimen Set 1 22

3.3.1.1 Cracking 22

3.3.1.2 Deflections. 22

3.3.1.3 Concrete Top Fiber Strains 23

3.3. 1.4 Stirrup Strains 23

3.3.1.5 Longitudinal Bar Strains 23

3.3.1.6 Strand Strains 24

3.3. 1.7 Strand Movement 24

3.3.1.8 Failure Loads 25

3.3.2 Specimen Set 2 26

3.3.2.1 Cracking.... 26

3.3.2.2 Deflections.. 27

3.3.2.3 Concrete Top Fiber Strains 27

3.3.2.4 Stirrup Strains 27

3.3.2.5 Longitudinal Bar Strains 28

3.3.2.6 Strand Strains......... 28

3.3.2.7 Strand Movement 29

3.3.2.8 Failure Loads. 29

3.3.3 Specimen Set 3 30

3.3.3.1 Cracking 29

3.3.3.2 Deflections 31

3.3.3.3 Concrete Top Fiber Strains 32

3.3.3.4 Stirrup Strains 32

3.3.3.5 Longitudinal Bar Strains 32

3.3.3.6 Strand Strains 33

3.3.3.7 Strand Movement 33

3.3.3.8 Failure Loads 33

3.3.4 Specimen Set 4 35

3.3.4.1 Cracking 35

3.3.4.2 Deflections 36

3.3.4.3 Concrete Top Fiber Strains 36

3.3.4.4 Stirrup Strains 36

3.3.4.5 Longitudinal Bar Strains 37

3.3.4.6 Strand Strains 37

3.3.4.7 Strand Movement 37

3.3.4.8 Failure Loads 37

3.3.5 Specimen Set 5 39

3.3.5.1 Cracking 39

3.3.5.2 Deflections 40

Page 11: Debonding in Pretensioned Beams-Precast Strands, Part 2

V-

Page

3.3.5.3 Concrete Top Fiber Strains 40

3.3.5.4 Stirrup Strains 40

3.3.5.5 Longitudinal Bar Strains 41

3.3.5.6 Strand Strains 41

3.3.5.7 Strand Movement 42

3.3.5.8 Failure Loads 42

3.6 Summary 43

CHAPTER 4 - ANALYSIS OF EXPERIMENTAL RESULTS 45

4.1 Introduction 45

4.2 Effective Strand Stress 45

4.3 Web-Shear Cracking 46

4.4 Flexure-Shear Cracking 49

4.5 Shear Strength 52

4.6 Flexural Strength 55

4.7 Summary 60

CHAPTER 5 - SUMMARY AND CONCLUSIONS 62

5.1 Summary 62

5.2 Conclusions 62

5.3 Future Work 66

LIST OF REFERENCES 67

Page 12: Debonding in Pretensioned Beams-Precast Strands, Part 2

- VI

LIST OF TABLES

Table PaSe

4.1 Effective Strand Stress 47

4.2 Web-Shear Cracking Loads at Critical Section (H/2) 47

4.3 Web-Shear Cracking Loads at Initial Crack Location 48

4.4 Flexure-Shear Cracking Loads at Initial Crack Location 50

4.5 Flexure-Shear Cracking Loads at Critical Section 51

4.6 Flexure-Shear Cracking Loads at Critical Section

with a reduced Number of Effective Strands 52

4.7 Shear Failure Loads 54

4.8 Development Length • 56

4.9 Number of Effective Strands 58

4.10 Flexural Failure Loads 59

Page 13: Debonding in Pretensioned Beams-Precast Strands, Part 2

- Vll -

LIST OF FIGURES

Figure Page

3.1 Simply Supported Tests Setup for Specimen Sets 1, 2, 3, and 4 70

3.2 Simply Supported Tests Setup for Specimen Set 5 71

3.3 Composite Girder Cross-section and Details (Specimen Set 1) 72

3.4 Composite Girder Cross-section and Details

(Specimen Sets 2, 3, and 5) 73

3.5 Composite Girder Cross-section and Details (Specimen Set 4) 74

3.6 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen Set 1) 75

3.7 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen Set 2) 76

3.8 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen Set 3) 77

3.9 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen Set 4) 78

3.10 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen Set 5) 79

3.1

1

Measured Stress-Strain Behavior of Prestressing Strands

(Specimen Set 1) 80

3.12 Measured Stress-Strain Behavior of Prestressing Strands

(Specimen Sets 2 and 3) 81

3.13 Measured Stress-Strain Behavior of Prestressing Strands

Page 14: Debonding in Pretensioned Beams-Precast Strands, Part 2

VU1 -

Figure Page

(Specimen Sets 4 and 5) 82

3.14 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Set 1).. 83

3.15 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Sets 2 and 3) 84

3. 16 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Set 4) 85

3.17 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Set 5) 86

3.18 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen Set 1) 87

3.19 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen Sets 2 and 3) 88

3.20 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen Sets 4 and 5) 89

3.2

1

Top View of Location of Dial Gages and LVDT's for

Specimen Sets 1, 2, and 3 90

3.22 Top View of Location of Dial Gages and LVDT's for

Specimen Set 4 91

3.23 Top View of Location of Dial Gages and LVDT's for

Specimen Set 5 92

3.24 Strand Slip Instrumentation for Specimen 1 93

3.25 Strand Slip Instrumentation for Specimen 2 94

3.26 Strand Slip Instrumentation for Specimen 3 95

3.27 Strand Slip Instrumentation for Specimen 4 96

3.28 Strand Slip Instrumentation for Specimen 5 97

3.29 Strand Debonding Scheme and Instrumentation (Specimen Set 1) 98

Page 15: Debonding in Pretensioned Beams-Precast Strands, Part 2

- IX -

Figure Page

3.30 Crack Pattern of 0% Debonded Beam Before Slab Failure

(Specimen Set 1) 99

3.31 Crack Pattern of 0% Debonded Beam at Failure

(Specimen Set 1) 99

3.32 Crack Pattern of 50% Debonded Beam Before Slab Failure

(Specimen Set 1) 100

3.33 Crack Pattern of 50% Debonded Beam at Failure

(Specimen Set 1) 100

3.34 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 1) 101

3.35 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 1) 102

3.36 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 1) 103

3.37 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 1) 104

3.38 Surface Strain in Slab, 40 in. from Support

Beam with 0% Debonding (Specimen Set 1) 105

3.39 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 1) 106

3.40 Surface Strain in Slab at First Debonding Point

Beam with 50% Debonding (Specimen Set 1) 107

3.41 Surface Strain in Slab at the Point Load

Beam with 50% Debonding (Specimen Set 1) 108

3.42 Location of Stirrup Reinforcement and Instrumentation

for Specimen Sets 1 and 2 109

3.43 Stirrup Strain, Beam with 0% Debonding

(Specimen Set 1) 1 10

3.44 Stirrup Strain, Beam with 50% Debonding

Page 16: Debonding in Pretensioned Beams-Precast Strands, Part 2

X

Figure Page

(Specimen Set 1) 1 1

1

3.45 Slab Longitudinal Steel Instrumentation

for Specimen Sets 1,2, and 3 112

3.46 Strain in Slab Longitudinal Steel at 6.0 ft from Support

Beam with 0% Debonding (Specimen Set 1) 113

3.47 Strain in Slab Longitudinal Steel at 6.0 ft from Support

Beam with 50% Debonding (Specimen Set 1) 114

3.48 Strand Strain at 45 in. from Support

Beam with 0% Debonding (Specimen Set 1) 115

3.49 Strand Strain at 68 in. from Support

Beam with 0% Debonding (Specimen Set 1) 116

3.50 Strand Strain at 88 in. from Support

Beam with 0% Debonding (Specimen Set 1) 117

3.51 Strand Strain at First Debonding Point

Beam with 50% Debonding (Specimen Set 1) 118

3.52 Strand Strain at Second Debonding Point

Beam with 50% Debonding (Specimen Set 1) 119

3.53 Strand Strain at 82 in. from Support

Beam with 50% Debonding (Specimen Set 1) .120

3.54 Strand Movement, Beam with 50% Debonding

(Specimen Set 1) 121

3.55 Strand Debonding Scheme and Instrumentation

for Specimen Set 2 122

3.56 Crack Pattern of 0% debonded Beam at Failure

(Specimen Set 2) 123

3.57 Crack Pattern of 50% Debonded Beam at Failure

(Specimen Set 2) 123

3.58 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 2) 124

Page 17: Debonding in Pretensioned Beams-Precast Strands, Part 2

XI

Figure Page

3.59 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 2) 125

3.60 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 2) 126

3.61 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 2) 127

3.62 Surface Strain in Slab, 3.5 ft. from Support

Beam with 0% Debonding (Specimen Set 2) 128

3.63 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 2) 129

3.64 Surface Strain in Slab at First Debonding Point

Beam with 50% Debonding (Specimen Set 2) 130

3.65 Surface Strain in Slab at the Point Load

Beam with 50% Debonding (Specimen Set 2) 131

3.66 Stirrup Strain, Beam with 0% Debonding

(Specimen Set 2) 132

3.67 Stirrup Strain, Beam with 50% Debonding

(Specimen Set 2) 133

3.68 Strain in Slab Longitudinal Steel at 6.0 ft. from Support

Beam with 0% Debonding (Specimen Set 2) 134

3.69 Strain in Slab Longitudinal Steel at 6.0 ft. from Support

Beam with 50% Debonding (Specimen Set 2) 135

3.70 Strand Strain at 41 in. from Support

Beam with 0% Debonding (Specimen Set 2) 136

3.71 Strand Strain at 6 ft from Support

Beam with 0% Debonding (Specimen Set 2) 137

3.72 Strand Strain at 85 in. from Support

Beam with 0% Debonding (Specimen Set 2) 138

3.73 Strand Strain at First Debonding Point

Page 18: Debonding in Pretensioned Beams-Precast Strands, Part 2

Xll

Figure Page

Beam with 50% Debonding (Specimen Set 2) 139

3.74 Strand Strain at Second Debonding Point

Beam with 50% Debonding (Specimen Set 2) 140

3.75 Strand Slip, Beam with 0% Debonding

(Specimen Set 2) 141

3.76 Strand Movement, Beam with 50% Debonding

(Specimen Set 2) 142

3.77 Strand Debonding Scheme and Instrumentation

(Specimen Set 3) 143

3.78 Crack Pattern of 0% Debonded Beam at Failure

(Specimen Set 3) 144

3.79 Crack Pattern of 67% Debonded Beam at Failure

(Specimen Set 3) 144

3.80 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 3) 145

3.81 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 3) 146

3.82 Load-Deflection Relationship, Beam with 67% Debonding

(Specimen Set 3) 147

3.83 Load-Deflection Relationship, Beam with 67% Debonding

(Specimen Set 3) 148

3.84 Surface Strain in Slab, 3.5 ft from Support

Beam with 0% Debonding (Specimen Set 3) 149

3.85 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 3) 150

3.86 Surface Strain in Slab at First Debonding Point

Beam with 67% Debonding (Specimen Set 3) 151

3.87 Surface Strain in Slab at the Point Load

Beam with 67% Debonding (Specimen Set 3) 152

Page 19: Debonding in Pretensioned Beams-Precast Strands, Part 2

- Xlll -

Figure Page

3.88 Location of Stirrup Reinforcement and Instrumentation

(Specimen Sets 3 and 4) 153

3.89 Stirrup Strain, Beam with 0% Debonding

(Specimen Set 3) 154

3.90 Stirrup Strain, Beam with 67% Debonding

(Specimen Set 3) 155

3.91 Strain in Slab Longitudinal Steel at 6.0 ft from Support

Beam with 0% Debonding (Specimen Set 3) 156

3.92 Strain in Slab Longitudinal Steel at 6.0 ft. from Support

Beam with 67% Debonding (Specimen Set 3) 157

3.93 Strand Strain at 3.5 ft. from Support

Beam with 0% Debonding (Specimen Set 3) 158

3.94 Strand Strain at 6 ft from Support

Beam with 0% Debonding (Specimen Set 3) 159

3.95 Strand Strain at the Point Load

Beam with 0% Debonding (Specimen Set 3) 160

3.96 Strand Strain at First Debonding Point

Beam with 67% Debonding (Specimen Set 3) 161

3.97 Strand Strain at Second Debonding Point

Beam with 67% Debonding (Specimen Set 3) 162

3.98 Strand Strain at the Point Load

Beam with 67% Debonding (Specimen Set 3) 163

3.99 Strand Slip, Beam with 0% Debonding

(Specimen Set 3) 164

3.100 Strand Movement, Beam with 67% Debonding

(Specimen Set 3) 165

3.101 Strand Debonding Scheme and Instrumentation

(Specimen Set 4) 166

3. 102 Crack Pattern of 0% Debonded Beam at Failure

Page 20: Debonding in Pretensioned Beams-Precast Strands, Part 2

XIV

Figure Page

(Specimen Set 4) 168

3.103 Crack Pattern of 50% Debonded Beam at Failure

(Specimen Set 4) 169

3.104 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 4) 170

3.105 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 4) 171

3.106 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 4) 172

3.107 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 4) 173

3.108 Surface Strain in Slab, 3.5 ft from Support

Beam with 0% Debonding (Specimen Set 4) 174

3.109 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 4) 175

3.110 Surface Strain in Slab at First Debonding Point

Beam with 50% Debonding (Specimen Set 4) 176

3.111 Surface Strain in Slab at the Point Load

Beam with 50% Debonding (Specimen Set 4) 177

3.1 12 Stirrup Strain, Beam with 0% Debonding

(Specimen Set 4) 178

3.1 13 Stirrup Strain, Beam with 50% Debonding

(Specimen Set 4) 179

3.1 14 Slab Longitudinal Steel Instrumentation

for Specimen Set 4 180

3.1 15 Strain in Slab Longitudinal Steel at 6.0 ft. from Support

Beam with 0% Debonding (Specimen Set 4) 181

3.1 16 Strain in Slab Longitudinal Steel at 6.0 ft from Support

Beam with 50% Debonding (Specimen Set 4) 182

Page 21: Debonding in Pretensioned Beams-Precast Strands, Part 2

- XV -

Figure Page

3.1 17 Strand Strain at 16 in. from Support

Beam with 0% Debonding (Specimen Set 4) 183

3.118 Strand Strain at 3.5 ft from Support

Beam with 0% Debonding (Specimen Set 4) 184

3.119 Strand Strain at 6 ft. from Support

Beam with 0% Debonding (Specimen Set 4) 185

3.120 Strand Strain at the Point Load

Beam with 0% Debonding (Specimen Set 4) 186

3.121 Strand Strain at 16 in. from Support

Beam with 50% Debonding (Specimen Set 4) 187

3.122 Strand Strain at First Debonding Point

Beam with 50% Debonding (Specimen Set 4) 188

3.123 Strand Strain at Second Debonding Point

Beam with 50% Debonding (Specimen Set 4)........ 189

3.124 Strand Strain at the Point Load

Beam with 50% Debonding (Specimen Set 4) 190

3.125 Strand Slip, Beam with 0% Debonding

(Specimen Set 4) .. 191

3.126 Strand Movement, Beam with 50% Debonding

(Specimen Set 4) 192

3.127 Strand Debonding Scheme and Instrumentation

(Specimen Set 5) 193

3.128 Crack Pattern of 0% Debonded Beam at Failure

(Specimen Set 5) 194

3. 129 Web-shear Cracking at Right Support

of 0% Debonded Beam (Specimen Set 5) 194

3. 1 30 Flexure-shear Cracking at Deponding Point

(Specimen Set 5) 195

3. 13

1

Web-shear Cracking at Left Support

Page 22: Debonding in Pretensioned Beams-Precast Strands, Part 2

XVI

Figure Page

of 50% Debonded Beam (Specimen Set 5) 195

3.132 Crack Pattern of 50% Debonded Beam at Failure

(Specimen Set 5) 196

3.133 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 5) 197

3.134 Load-Deflection Relationship at 7 ft from Support

Beam with 0% Debonding (Specimen Set 5) 198

3.135 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 5) 199

3.136 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 5) 200

3.137 Surface Strain in Slab, 7 ft from Support

Beam with 0% Debonding (Specimen Set 5) 201

3.138 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 5) .202

3.139 Surface Strain in Slab at Debonding Point

Beam with 50% Debonding (Specimen Set 5) 203

3.140 Surface Strain in Slab at the Point Load

Beam with 50% Debonding (Specimen Set 5) 204

3.141 Location of Stirrup Reinforcement and Instrumentation

(Specimen Sets 3 and 4) 205

3. 142 Stirrup Strain in Left Shear Span

Beam with 0% Debonding (Specimen Set 5) 206

3.143 Stirrup Strain in Right Shear Span

Beam with 0% Debonding (Specimen Set 5) 207

3.144 Stirrup Strain in Left Shear Span

Beam with 50% Debonding (Specimen Set 5) 208

3.145 Slab Longitudinal Steel Instrumentation

for Specimen Set 5 209

Page 23: Debonding in Pretensioned Beams-Precast Strands, Part 2

XVII

Figure PaSe

3. 146 Slab Steel Strain in Left Shear Span

Beam with 0% Debonding (Specimen Set 5) 210

3.147 Slab Steel Strain in Right Shear Span

Beam with 0% Debonding (Specimen Set 5) 211

3.148 Slab Steel Strain in Left Shear Span

Beam with 50% Debonding (Specimen Set 5) 212

3. 149 Slab Steel Strain in Right Shear Span

Beam with 50% Debonding (Specimen Set 5) 213

3.150 Strand Strain at 20 in. from Support EDBeam with 0% Debonding (Specimen Set 5) 214

3.151 Strand Strain at 42 in. from Support EDBeam with 0% Debonding (Specimen Set 5) 215

3.152 Strand Strain at 84 in. from Support EDBeam with 0% Debonding (Specimen Set 5) 216

3. 153 Strand Strain at the Point Load

Beam with 0% Debonding (Specimen Set 5) 217

3.154 Strand Strain at 20 in. from Support IC

Beam with 0% Debonding (Specimen Set 5) 218

3. 155 Strand Strain at 42 in. from Support IC

Beam with 0% Debonding (Specimen Set 5) 219

3. 156 Strand Strain at 7 ft. from Support IC

Beam with 0% Debonding (Specimen Set 5) 220

3.157 Strand Strain at 16 in. from Support EABeam with 50% Debonding (Specimen Set 5) 221

3.158 Strand Strain at 42 in. from Support EABeam with 50% Debonding (Specimen Set 5) 222

3.159 Strand Strain at Left Debonding Point

Beam with 50% Debonding (Specimen Set 5) 223

3.160 Strand Strain at the Point Load

Page 24: Debonding in Pretensioned Beams-Precast Strands, Part 2

xvm -

Figure Page

Beam with 50% Debonding (Specimen Set 5) 224

3.161 Strand Strain at 20 in. from Support IB

Beam with 50% Debonding (Specimen Set 5) 225

3. 162 Strand Strain at 42 in. from Support IB

Beam with 50% Debonding (Specimen Set 5). 226

3. 1 63 Strand Strain at Right Debonding Point

Beam with 50% Debonding (Specimen Set 5) 227

3.164 Strand Slip, Beam with 0% Debonding

(Specimen Set 5) 228

3. 165 Failure Region of 50% Debonded Beam(Specimen Set 5) 229

3. 166 Failure Region of 0% Debonded Beam(Specimen Set 5) 229

Page 25: Debonding in Pretensioned Beams-Precast Strands, Part 2

- XIX -

NOTATION

Av = cross-sectional area of the stirrups

bw = web width of the girder

d = distance from the extreme compression fiber to the centroid of the

longitudinal tension reinforcement (>0.8 H)

dp = nominal diameter of prestressing strand

fd = stress due to unfactored dead load, at extreme fiber of section

where tensile stresses are caused by externally applied loads

fpc = compressive stress at the centroid of the composite section, or at

the junction of the web and flange when centroid lies within the

flange, due to both prestressing and the moment resisted by the

precast member acting alone

fpe = compressive stress, due to prestressing, at extreme fiber of section

where tensile stresses are caused by externally applied loads

fps = stress in prestress reinforcement at nominal strength

fse = effective stress in prestressed reinforcement

fpu = specified tensile strength of prestressing strands, psi

fpy

= specified yield strength of prestressing strands, psi

fy

= yield strength of nonprestressed reinforcement

fc = compressive strength of concrete

H = total depth of composite beam

Page 26: Debonding in Pretensioned Beams-Precast Strands, Part 2

- XX-

I = moment of inertia of the composite section

Id = development length of prestressing strand

MCT= moment causing flexural cracking at section due to applied loads

s = stirrup spacing

Vcj = nominal shear strength provided by concrete when diagonal

cracking results from combined shear and moment

Vcw = nominal shear strength provided by concrete when diagonal

cracking results from excessive principal tensile stress in

Vd = shear force at section due to unfactored dead load

Vj = factored shear force at section due to externally applied loads

Vs= nominal shear strength provided by web reinforcement

y t= distance from the centroid of the section to extreme fiber in tension

VV * bd

V = shear force at the point of bar cutoff

b = beam width

Asi = area of continuous steel

AS2 = area of steel cut off

x = the distance between the point of bar cutoff and the end reaction

Ki = constant to account for nonuniformity of stress distribution over the

M = bending moment at the point of steel cutoff

z\ = internal moment arm after steel cutoff

Page 27: Debonding in Pretensioned Beams-Precast Strands, Part 2

- XXI -

Z2 = internal moment arm before steel cutoff

xt

= distance over which redistribution of forces occurs

Ag! = area of main steel after curtailment

As2 = area of main steel before curtailment

V'c = shear cracking resistance of the same beam with continuous steel

of area equal to that following curtailment

Page 28: Debonding in Pretensioned Beams-Precast Strands, Part 2

XX11 -

ABSTRACT

This report summarizes an experimental investigation regarding the effects of strand

debonding on the flexure and shear behavior of simply supported precast pretensioned

bridge members composite with a cast-in-place deck slab.

Five specimen sets were fabricated and tested to failure as simply supported

members under a single concentrated load. Four specimen sets consisted of Type-I

AASHTO girders composite with a cast-in-place deck slab. One specimen set consisted

of Indiana State Type CB-27 box girders also composite with a cast-in-place deck slab.

Each specimen set consisted of two identical beams with different strand debonding

schemes near the ends. In each set, one beam had the strands bonded throughout the

entire length. The other one had some percentage of the strands debonded near the ends.

The current ACI/AASHTO requirements for flexure and shear design of

pretensioned bridge girders with debonded strands were examined.

Page 29: Debonding in Pretensioned Beams-Precast Strands, Part 2

CHAPTER 1

INTRODUCTION

This report addresses Phase 2 of the research study "Behavior of Pretensioned

Bridge Members with Debonded Strands". Part 1 of the study focussed on the behavior

of precast pretensioned bridge members made continuous with a cast-in-place slab and

diaphragm (Abdalla et al [1992]). Four continuous specimens were fabricated and

tested. Shear as well as flexural capacity of continuous pretensioned bridge members

with debonded strands were studied. The combined effects of time-dependent creep and

shrinkage deformations on the behavior of the beams at the continuous supports were

also investigated. The current AASHTO criteria for limiting the stress at the extreme

compression fiber near the continuous supports to allowable working stress values on

the load carrying capacity of continuous members was also investigated.

In this report, the shear and flexural behavior of simply supported precast

pretensioned girders, with debonded strands, composite with a cast-in-place slab, will

be studied. An experimental program carried out to determine whether the strand

debonding techniques has a detrimental effect on the load-response behavior of

prestressed beams, will be amply discussed. Also the ACI/AASHTO provisions for the

development length of the prestressing strands in pretensioned members with debonded

strands will be examined with the aid of the results obtained in this study.

Page 30: Debonding in Pretensioned Beams-Precast Strands, Part 2

2-

The purpose of Phase 2 of the research study was to evaluate the flexural and shear

behavior of simply supported pretensioned beams with debonded strands. The behavior

of debonded beams is compared to that of identical beams with fully bonded strands.

The possible premature failure of the debonded beams due to lack of strand anchorage

and the current ACI/AASHTO provisions for development length of prestressing

strands are also investigated.

Five sets of specimens were tested to failure as simply supported members under a

single concentrated load. Each specimen set consisted of two beams. One beam had all

strands bonded throughout its entire length. The other had some of the strands

blanketed near its end. Specimen Sets 1, 2, 3, and 5 were Type-I AASTHO girders with

a 4x48 inch cast-in-place concrete slab. Specimen Set 4 consisted of Indiana State Type

CB-27 box girders with a 4x36 inch cast-in-place slab.

The debonded beams in Specimen Sets 1 and 2 had 6 strands blanketed (50%

debonding). In Specimen Set 3, the debonded beam had 8 strands debonded (67%

debonding); and in 4 it had 10 strands (50%) debonded near its end. In Specimen Set 5,

one beam had 0% debonding while the other had 6 strands (50%) debonded near each

end.

In Chapter 2 of this report a literature review of relevant works is presented. The

results of the experimental program are given in Chapter 3. The experimental results are

thoroughly analyzed and compared with predicted values from current AASHTO

specification in Chapter 4. The summary and conclusions from this phase of the

research study are given in Chapter 5.

Page 31: Debonding in Pretensioned Beams-Precast Strands, Part 2

-3

CHAPTER 2

BACKGROUND

2.1 Introduction

Strand debonding in a pretensioned prestressed beam is analogous to the bar

curtailment technique often used in reinforced concrete beams. Both methods introduce

the so called intermediate anchorage These procedures induce high stress concentration,

at the point of bar cutoff in reinforced concrete members or strand debonding in

pretensioned beams, which may cause a deleterious effect on the ultimate strength of

the beam. Evidence of reduced shear strength as well as loss of ductility when bars are

cut off in the tension zone of a reinforced concrete beam has been reported in the

literature. Herein, a review of the previous studies conducted on concrete beams with

curtailed bars will be given first, followed by the discussion of the published work on

strand debonding in pretensioned prestressed beams.

2.2 Curtailment of Reinforcing Steel

2.2.1 1959 Texas Tests

Ferguson and Matloob [1959] studied the effect of bar cutoff on the shear strength

of non-prestressed reinforced concrete beams without web reinforcement. Simple span

rectangular beams with several sizes and lengths and a wide variety of reinforcing steel

arrangements were tested. It was reported that, when bars were cut off, flexural cracks

Page 32: Debonding in Pretensioned Beams-Precast Strands, Part 2

started at the cutoff point at a lower load than predicted. Soon thereafter this crack

propagated in an inclined direction and finally resulted in failure of the beam. This

premature development of the inclined crack was associated with the bar cutoff point

Beams with full length bars developed the full calculated moment capacity.

This loss in shear capacity was attributed to the additional longitudinal tension

introduced in the concrete, at the cutoff point, when tensile stresses were transferred

from the cutoff bars to the continuous bars. It has been found that the shear strength of

the concrete beams decreases as the area of the steel cut off increases.

According to Ferguson et al [1959] the total diagonal tensile stress, vt , at the bar

cutoff point is given by:

V^

=[V + V ¥^- ( A

Al\ )] (11)

K! d Asl + As2

where:

VV =

bd

V = shear force at the point of bar cutoff

b = beam width

d = beam effective depth

Asi - area of continuous steel

AS2 = area of steel cut off

x = the distance between the point of bar cutoff and the end reaction

Kj = constant to account for nonuniformity of stress distribution over the

cross-section of the beam

Page 33: Debonding in Pretensioned Beams-Precast Strands, Part 2

-5-

The first term in Equation (2.1) is the ordinary shear stress caused by the applied

loads at the point of steel cutoff. The second terra gives the increase in shear stress

caused by reinforcement curtailment However, the value of the constant Ktwas not

given.

2.2.2 1969 Alberta Study

An exploratory test program to study the effect of terminating part of the tensile

steel on the shear strength of reinforced concrete beams had been conducted by Baron

[1969]. Baron tested single span reinforced concrete beams in which an additional area

of tensile steel was placed in the central portion of the beam. The additional short bars

were terminated in the shear span of the simple beam. It was found that increasing the

number of the additional short bars had the effect of decreasing the shear strength of the

beams. It was also noticed that inclined cracks occurred in the web of the concrete

beams containing the stopped bars, at the point of cutoff, before the section had cracked

due to flexure. These findings confirmed the results obtained by Ferguson et al [1959].

It was concluded that diagonal tension failure was prone to occur at the locations of

reinforcement termination. The sudden transfer of tensile stresses at the point of bar

cutoff aggravated the shear stress at that location. An additional tensile force due to the

shift in the neutral axis existed at the point of cutoff. At the point of steel cutoff the

internal moment arm would be less on the side having the larger amount of steel.

Therefore, to develop the same resisting moment at that section the tensile force in the

longitudinal steel before curtailment will be greater than that after curtailment. Baron

related the sudden increase in shear stress at the point of steel cutoff to the reduction in

Page 34: Debonding in Pretensioned Beams-Precast Strands, Part 2

-6-

the steel tensile force at the cutoff point

According to Baron the average shear stress in the beam web due to the decrease in

the steel tensile force is given by:

vt= (2.2)

b xt

z\ Z2

The total shear stress acting at the point of bar cutoff is given by:

V M Z1-Z2 „,,.vt=-rr + -r (2-3)

b d b xt

zj Z2

where:

V = shear force acting at the point of steel cutoff

M = bending moment at the point of steel cutoff

b = beam width

d = beam effective depth

z\ = internal moment arm after steel cutoff

Z2 = internal moment arm before steel cutoff

xt= distance over which redistribution of forces occurs

2.2.3 1972 Imperial College Approach

Baron's approach was followed later by Reagan and Mitra [1972] for the evaluation

of the shear capacity of reinforced concrete beams with curtailed longitudinal steel.

The shear cracking resistance of a beam with curtailed steel was given by:

V«=V'« tl-0.2 ^(-J^-A/-£i.)] (2.4,

Page 35: Debonding in Pretensioned Beams-Precast Strands, Part 2

7-

VCT = shear cracking resistance of a beam with curtailed steel

V'CT = shear cracking resistance of the same beam with continuous steel of area

equal to that following curtailment

Asi = area of main steel after curtailment

Aj-2 = area of main steel before curtailment

M = bending moment at the point of cutoff

V = shear force at the point of cutoff

b = beam width

d = beam effective depth

It was shown that Equation (2.4) was in excellent agreement with the test results

reported by Baron [1969]. Reagan and Mitra suggested that the distance over which

redistribution of forces occurs, xtin Equations (2.2) and (2.3), is to be taken as equal to

the effective depth of the beam.

This study indicated that, the effect of curtailment of main steel on shear cracking

resistance is greater than that which would be predicted by the 1969 British Standards.

2.3 Strand Debonding

It has been stated earlier that strand debonding in prestressed beams is similar to bar

cutoff in non-prestressed reinforced concrete beams. It is expected that the adverse

effect of bar curtailment in non-prestressed beams will be also associated with strand

debonding in prestressed beams. Thus far, the effect of strand debonding on the shear

strength of pretensioned precast beams has not been given enough attention in the

technical literature. Very little experimental work has been carried out to evaluate the

Page 36: Debonding in Pretensioned Beams-Precast Strands, Part 2

-8-

shear strength of prestressed beams with blanketed strands.

2.3.1 1965 PCA Tests

Kaar and Magura [1965], as part of a wider study investigated the effect of strand

debonding on the shear strength of pretensioned concrete girders. The investigation

involved five half-scale Type m AASHTO bridge girders, 34 ft. long with a 39 x 3 inch

composite concrete slab. Three girders were designed and tested for the study of

flexural behavior of prestressed beams with debonded strands. The prestressing steel

used was seven-wire, stress relieved, Grade 270 ksi strand of 3/8 in. diameter. All three

beams were over-reinforced with stirrups to prevent the interference of shear distress

with the flexural behavior. These beams were tested statically to failure after 5 million

cycles of the design service load over a single span, 33 ft long. It was found that

debonding did not affect the behavior of the girders in the service load range. After

cracking, however, the overall stiffness of the girder was considerably reduced. Wider

flexural cracks were observed in girders with blanketed strands. It was concluded that

the requirement for embedment length of strands as specified by the ACI 318-63 code

was inadequate when applied to blanketed strands. The flexural behavior of girders with

embedment lengths twice those required by the ACI 318-63 code, was found to be

similar to the behavior of girders with fully bonded strands. The development length of

the prestressing strand according to the ACI 318-63 code was 5.5 ft. The shear

investigation involved static testing to failure of two girders similar to those tested for

the flexure study, except that the amount of web reinforcement was reduced to

determine the effect of blanketing on the shear capacity. The stirrups in these girders

Page 37: Debonding in Pretensioned Beams-Precast Strands, Part 2

-9

had a spacing 1— times that required by the 1963 ACI Building Code. The results

from these tests indicated no detrimental effects of blanketing upon the shear carrying

capacity of the pretensioned girders. It is worth mentioning that the blanketed strands

in the debonded girder had embedment lengths twice those required by the ACI 318-63

Code.

2.3.2 1971 Glasgow Tests

The shear strength of uniformly prestressed pretensioned concrete I-beams with

debonded strands was investigated by Krishnamurthy in 1971. All beams were simply

supported on a span of 9 ft. and subjected to a two-point loading with a shear span of 20

inches. Diagonal tension failure occurred in all the specimens tested in this study. It

was found that increasing the number of debonded tendons in the bottom flange,

decreased the bearing capacity in shear of the uniformly prestressed beams. On the

other hand, increasing the number of debonded strands in the top flange increased the

shear strength of the girders when compared to a similar girder with fully bonded

strands, these tests were conducted on beams without shear reinforcement.

2.3.3 1975 Tulane Strand Blanketing Report

Dane and Bruce [1975] performed tests on nine composite concrete girders to study

the effectiveness of debonding the prestressing strands as an alternative to draped

strands in pretensioned prestressed concrete beams. Six were half-scale Type EI

AASHTO girders, 34 ft long and simply supported on 33 ft span. The remaining three

were Type II AASHTO girders, 50 ft long and simply supported on 48 ft. span. Two of

the first six girders had draped strands, whereas the other four had straight strands

Page 38: Debonding in Pretensioned Beams-Precast Strands, Part 2

10

which were blanketed near the ends of the girders. One of the full scale Type II

AASHTO girders had draped strands and the other two had blanketed strands. The

stirrups in these specimens were designed to ensure a flexural mode of failure. All of

the girders were loaded with two equal concentrated loads applied at the third points of

their clear spans. The blanketed strands in two of the test specimens were surrounded

with a cage of mild reinforcing steel at the point where blanketing ended. In the other

two the blanketed strands were anchored with internal locking devices at the debonding

point In all the debonded beams, one development length as specified by the ACI

318-63 code was provided for the blanketed strands. It was found that either draping or

blanketing did not significantly affect neither flexural cracking nor inclined shear

cracking. It was also noticed that no significant reduction in flexural strength occurred

when using blanketed strands in place of draped strands. This was related to the

beneficial effects from wrapping the strands and the internal anchorage devices. Dane

and Bruce concluded that debonding the prestressing strands was an effective method

that could be used in lieu of draping in pretensioned concrete beams. However, the

effect of debonding the strands on the shear strength of pretensioned girders was not

addressed in this investigation.

2.3.4 1979 PCA Tests

Rabbat et al [1979] tested six full-size Type II AASHTO girders with a composite

concrete slab at the Construction Technology Laboratories of the Portland Cement

Association. Two of the test girders had draped strands. In the other four, only straight

strands blanketed at the ends of the girders were employed. The shear reinforcement in

Page 39: Debonding in Pretensioned Beams-Precast Strands, Part 2

11-

all beams consisted of #4 U-stirrup spaced at 6 inches on center. The behavior and

strength of the test girders under the effect of cyclic loading was investigated in this

study. The specimens were simply supported and loaded with four concentrated loads,

placed symmetrically about the center line of the span. The test girders were subjected

to 5 million cycles of the full service load. Subsequendy, the specimens were tested

statically to destruction. It was found that, pretensioned beams with debonded strands

performed satisfactorily if adequate strands development was provided. When no

tension was allowed in the precompressed tensile zone, one development length as

suggested by the ACI 318-77 specifications was found to be adequate. The fatigue life

of the beam was reduced when tensile stresses were allowed in the bottom fibers. It was

recommended that the development length specified by ACI 318-77 should be doubled

in such beams. The shear strength of pretensioned concrete beams with debonded

strands was not directly investigated in this study as the specimens were designed to

ensure flexural failure.

2.3.5 1983 Auckland Shear Behavior Tests

An experimental investigation to study the behavior of pretensioned I-beams with

debonded strands was carried out by Dale in 1983 at the University of Auckland, New

Zealand. It was reported that debonding the prestressing strands generally reduced the

ultimate capacity of the test beams in shear. Large strains and wide inclined cracks

were observed in beams with debonded strands. The addition of extra stirrups over the

transfer length of the debonded strands markedly improved the performance of the

prestressed concrete beams. The diagonal crack widths were smaller and stirrup and

Page 40: Debonding in Pretensioned Beams-Precast Strands, Part 2

12-

compression zone strains were less severe.

2.3.6 1987 Purdue Fatigue Study

The fatigue behavior of six prestressed box beams with various embedment lengths

was investigated by Pensinger in 1987 at Purdue University. Different development

lengths were used for the debonded strands. Pensinger investigated the validity of the

ACI 318-89 Specifications requiring an embedment length for debonded strands twice

that required for fully bonded strands when tensile stresses exist in the precompressed

zones under service load conditions.

The test girders were loaded cyclically up to 5 million cycles with a nominal tensile

stress of 6 yjfc in the precompressed zone. The stress level was increased to 8 yfc

when failure did not occur in the specimen. The specimen was then subjected to cyclic

loading until significant fatigue damage was observed. It was concluded that the

behavior of beams with 1.5 Id development length was similar to that of beams with

2 ld development length. ^ is the development length required by the ACI 318-89 Code

for fully bonded strands. The author suggested that 1.5 ^ of embedment length should

be used for debonded strands in members where 2 Id is required by the ACI 318-89

Building Code. The shear behavior was not addressed in this study.

2.4 Development Length

In pretensioned members, prestressing is achieved by transferring the prestressing

force imparted by the strands to the member by virtue of the bond between the concrete

and the prestressing steel. The distance, from the end of the member, over which the

effective prestressing force is developed is referred to as the transfer length. An

Page 41: Debonding in Pretensioned Beams-Precast Strands, Part 2

-13

additional bond length is always required in order that the ultimate strength of the

strand be developed at the critical section for flexure. This additional length is called

flexural bond length. The sum of these two lengths, the transfer length and the flexural

bond length, is the development length of the strand.

Accurate estimation of transfer and development lengths of prestressing strand is

essential for the prediction of the shear and flexural strength of pretensioned beams.

Insufficient development length could cause excessive strand slippage and alter the

overall behavior and mode of failure.

Several studies have been conducted during the last three decades trying to

determine the adequate embedment length of the prestressing strands. A brief

description of these studies will be given in the following sections.

2.4.1 Hanson and Kaar [1959]

Hanson and Kaar carried out an experimental investigation of flexural bond in

beams pretensioned with seven-wire strand of 1/4, 3/8, and 1/5 inch diameter. The test

program involved 47 pretensioned beams tested under static loading to evaluate the

effect of strand diameter and embedment length on bond performance. The concrete

strength of the specimens ranged from 3700 psi to 7800 psi. It was found that strand

size and embedment length have a considerable influence on the value of the average

bond stresses at which general bond slip occurs. The test results showed that beams

with adequate embedment length failed in flexure by crushing of the concrete after

yielding of the steel before general bond slip occurred. As the embedment length

decreased, failure occurred at lower loads due to slippage of the strands. Hanson and

Page 42: Debonding in Pretensioned Beams-Precast Strands, Part 2

-14

Kaar recommended that the following embedment lengths be provided from the

location of the applied load to beam end if the ultimate strength of strand was to be

developed by beam flexure before general bond slip occurred: 70 in. for 1/4 in. strand

(fpy= 275 ksi); 106 in. for 3/8 in. strand (fpy

= 263 ksi); and 134 in. for 1/2 in. strand

(fpy

= 263 ksi ). However, Martin and Scott [1976] after reevaluating the test data

reported by Hanson and Kaar stated that the minimum embedment length for 1/2 in.

(270 ksi ) strand should be 151 inches. It must be pointed out that the beams of high

strength tested by Hanson and Kaar failed by general bond slip, whereas the low

strength concrete beams failed in flexure by crushing of the concrete after yielding of

the steel. The prestressing steel stress immediately after transfer, which was gradual in

these tests, did not reach 70 percent of the ultimate tensile strength of the strand. These

effects contributed to the satisfactorily performance of the specimens.

2.4.2 ACI/AASHTO [1989] Provisions

The ACI/AASHTO specifications for development length are based primarily on

the work of Hanson and Kaar [1959]. The ACI/AASHTO provisions require that the

bonded embedment length of the prestressing strands from the critical section under

consideration shall not be less than:

ld=^dp + (fps -fse )dp (2.5)

where:

ld = development length of the prestressing strand (inch)

fps = stress in prestress reinforcement at nominal strength (ksi)

fse = effective stress in prestressed reinforcement (ksi)

Page 43: Debonding in Pretensioned Beams-Precast Strands, Part 2

-15

dp = nominal diameter of prestressing strand (inch)

Equation (2.5) was based on tests of beams with all strands fully bonded from the

section of maximum bending moment to the beam ends. Based on the paper published

by Kaar and Magura [1965] the ACI/AASHTO provisions were revised for blanketed

strands. The provisions required that, where bonding of a strand does not extend to the

end of the members, and design includes tension at service load in precompressed

tensile zones, development length specified in Equation (2.5) shall be doubled. Based

on a subsequent study by Rabbat et al [1979] it was established that doubling the

development length was not necessary if tension was not allowed at service loads in the

precompressed zone of the specimens.

2.4.3 Zia and Mostafa [1977]

Zia and Mostafa reanalyzed the test results from Hanson and Kaar pertaining to

development length. Zia and Mostafa stated that the actual embedment length for the

strands which developed the ultimate strength before a general bond slip were

considerably shorter than indicated by Hanson and Kaar tests. The authors proposed the

following formula for development length:

14=1.5 -p- dp - 4.6 + 1.25 ( fsu - fse ) dp (2.6)

Equation (2.6) is applicable for concrete strength ranging from 2000 to 8000 psi and

accounts for effects of strand size, initial prestress and concrete strength at transfer.

2.4.4 EL Shahawy and Batchelor

Current research on development of prestressing strands is being conducted at the

Page 44: Debonding in Pretensioned Beams-Precast Strands, Part 2

16-

Florida Department of Transportation Laboratories by EL Shahawy and Batchelor

[1991]. Pretensioned prestressed concrete beams were tested under static loading in

flexure and shear to determine the adequate development length of the strands.

Preliminary tests were conducted on fully bonded pretensioned beams reinforced with

0.5 inch diameter, low-lax, Grade 270 ksi strand with an effective prestress of 162 ksi.

These tests indicated that the current development length of such strand should be 1.69

times the development length required by ACI/AASHTO [1989] provisions.

The adequacy of the present provisions of the ACI/AASHTO Codes with respect to

development is controversial. In this report the results obtained from testing ten

pretensioned composite girders, five of which had blanketed strands, will be used to

check the adequacy of the development lengths recommended by ACI/AASHTO Codes

and the recently proposed FDOT specification.

2.5 Summary

This chapter contains a brief review of the studies that have dealt with the effects of

strand debonding and bar cutoff in concrete girders. It was found that, flexural cracks

developed at cutoff points at lower loads than expected. Inclined cracks were observed

soon thereafter and caused the early failure of the concrete beams. Beams with

continuous longitudinal steel failed at the predicted ultimate load. The analytical

studies conducted to evaluate the effect of bar cutoff on the load carrying capacity of

reinforced concrete beams were also presented in this chapter. It was determined that,

the reduction of the shear cracking capacity in beams with curtailed reinforcement was

due to the sudden increase in the shear stress at cutoff points.

Page 45: Debonding in Pretensioned Beams-Precast Strands, Part 2

17-

Previous studies on strand debonding revealed that strand debonding in

pretensioned beams reduced the cracking capacity. Upon cracking, the overall stiffness

of beams with debonded strands was observed to be considerably reduced. Wider

cracks and higher strains were observed in beams with debonded strands. However, the

addition of extra stirrups over the transfer length of debonded strands was found to

improve the performance of pretensioned beams. Crack widths were smaller and stirrup

and compression zone strains were less severe.

A brief summary concerning the research studies that led to the development of the

ACI/AASHTO equations for embedment length of prestressing strand in pretensioned

members was also presented. However, recent studies revealed that the embedment

length required by the current ACI/AASHTO Codes for prestressing strands is not

adequate. It is proposed that the development length of fully bonded strands should be

seventy per cent in excess to the requirement of the ACI/AASHTO Codes.

The next chapter is an outline of the experimental program carried out to evaluate

the behavior of pretensioned bridges with debonded strands tested as simply supported

members. Particular emphasis will be given to the effects of strand debonding on the

shear strength of these members.

In Chapter 4, a comparison of the experimental results of the tests with the

theoretical analysis based on the ACI/AASHTO Codes provisions will be presented.

Both the flexural and shear capacity of the simply supported pretensioned girders will

be evaluated and discussed.

Page 46: Debonding in Pretensioned Beams-Precast Strands, Part 2

18

Chapter 5 contains a summary of this phase of the study, the conclusions drawn

from the test data, and future research needs pertaining to the use of strand debonding

in simply supported pretensioned bridge members.

Page 47: Debonding in Pretensioned Beams-Precast Strands, Part 2

19

CHAPTER 3

EXPERIMENTAL PROGRAM

3.1 Introduction

In phase 1 of this research study (Abdalla et al [1992]), the testing of four of the

specimen sets as continuous members (Specimen Sets 1,2,3, and 4) was decided. After

each continuous test, each beam of the corresponding specimen set was further tested

over a simply supported span of 17.5 ft. In Specimen Set 5 each beam was tested only

as simply supported over a span of 24 ft. The simple supports were consisted of

greased rollers placed between two steel plates as described in Figures 3.1 and 3.2. The

specimen details are shown in Figures 3.3-3.5. Each beam was tested using a 600 kip

Baldwin testing machine. The composite girders of Specimens sets 1, 2, 3, and 4 were

positioned in such a way that the applied load would cause the critical region for high

shear force to occur at the end that had not been damaged by the continuous tests. The

girders with blanketed strands were tested so that the end with blanketed strands would

be in the region where shear failure was likely to occur.

3.2 Materials

3.2.1 Concrete

The girders were cast using the standard 6000 psi concrete mix for pretensioned

bridge members in the State of Indiana. The concrete compressive strength was

Page 48: Debonding in Pretensioned Beams-Precast Strands, Part 2

-20

monitored using the standard 6x12 test cylinders. The compressive strength of the

concrete used in the precast beams and the cast-in-place slab and diaphragm, for the

different test specimens, is shown in Figures 3.6-3.10.

3.2.2 Prestressing Steel

The prestressing steel, in both girders, consisted of stress relieved (Specimen Set 1)

and Lo-Lax (Specimen Sets 2, 3 and 4) Grade 270, uncoated seven-wire strands, 0.5

inch diameter (cross-sectional area of 0.153 in2). The stress-strain behavior of the

strand is shown in Figures 3.11-3.13. Strains were measured by means of electrical

resistance strain gages attached to the strand as in the test beams. The yield stress, the

ultimate strength, and the modulus of elasticity of the strand were determined from

these tests.

3.2.3 Non-Prestressed Reinforcement

Standard deformed Grade 60, #6 bars were used as the nonprestressed top

reinforcement in the precast beams and the deck slab reinforcing mat The properties of

these bars were determined from tension tests. The stress-strain behavior of the #6 bars

is shown in Figures 3.14-3.17.

The stirrup reinforcement consisted of deformed Grade 60, #3 bars. The stress-

strain curve for the stirrup steel is shown in Figures 3. 18-3.20.

3.3 Simply Supported Tests

The experimental setup for the simply supported tests is shown diagrammatically in

Figures 3.1 and 3.2.

Page 49: Debonding in Pretensioned Beams-Precast Strands, Part 2

-21 -

In these tests, the load was applied monotonically in small increments until the

specimen could not sustain any additional load. The applied load was measured by a

load cell with a 300 kip capacity.

Deflections under the point load and at debonding points location were measured

using LVDT's at both sides of the beam. The location of these measurement devices is

shown in Figures 3.21-3.23.

Strains in the prestressing strands, stirrups, and deck slab longitudinal steel were

monitored using electrical resistance strain gages. Concrete strains at the top fiber of the

cast-in-place slab were measured at the point load and at debonding points location as

shown in Figures 3.21-3.23.

The prestressing strand slip was measured using mechanical deflection gages

mounted on the strands protruding from the end of the beam. Figures 3.24-3.28

illustrate the position of these gages.

During each test, the applied load was increased in small increments. At each

increment, the external load, strains, and deflections were recorded using an automated

data acquisition system along with manual reading of the prestressing strand slip data.

New and extended cracks were identified and marked on the surface of the beam

together with the corresponding load level. The performance of the test girders will be

discussed in the following sections.

Page 50: Debonding in Pretensioned Beams-Precast Strands, Part 2

-22

3.3.1 Specimen Set 1

In Specimen Set 1, one beam had all 12 strands fully bonded. The other had 6 of the

strands debonded near the end EA (50% debonding) as shown in Figure 3.29. In this

specimen, transverse reinforcement was not provided in the cast-in-place slab. In both

beams longitudinal cracks developed in the slab at its junction with the flange of the

precast I-beam. Further loading caused failure of the slab to occur prior to the actual

girder failure. Slab failure occurred at a load of 1 85 kips in the 0% debonded beam, and

at a load of 135 kips in the 50% debonded beam. Data was recorded for both beams up

to the failure load of the slab.

3.3.1.1 Cracking

Web-shear cracking of the fully bonded girder occurred at an applied load of 150

kips at a distance of 22 inches from support. Flexure-shear cracking was observed at a

load of 165 kips at a distance of 73 inches from the support. Cracking patterns of the

fully bonded beam, before and after slab failure, are shown in Figures 3.30-3.31. In the

beam with 50% debonding, web-shear cracking was observed at a load of 120 kips at a

distance of 22 inches from the support The first flexure-shear crack occurred at a load

of 1 13 kips near the debonding point, a distance of 62.5 inches from the support Crack

patterns of the 50% debonded beam, before and after slab failure, are shown in Figures

3.32 and (3.33).

3.3.1.2 Deflections

The load-deflection relationship for the 50% debonded beam and the fully bonded

beam is shown in Figures 3.34-3.37. In both beams the measured deflection was

Page 51: Debonding in Pretensioned Beams-Precast Strands, Part 2

23-

proportional to the applied load until web-shear and flexure-shear cracking occurred.

Large increase in deflection was observed when cracking occurred. Comparison of the

deflection of the two beams shows that, up to the initiation of the first crack the two

beams had the same deflection. The second stage of load-deflection curves shows that at

the same applied load the 50% debonded beam had almost twice the deflection as the

fully bonded beam.

3.3.1.3 Concrete Top Fiber Strains

Concrete strains were monitored by surface strain gages in the compression region

,at the top fiber of the cast-in-place slab, at the point load and at debonding points

location as shown in Figure 3.21. Figures 3.38-3.41 show the concrete strain versus the

applied load for both tests. These gages show that similar behavior was exhibited by the

strains in the concrete for the different beams. Substantial increase in strain occurred

when flexure-shear cracking opened.

3.3.1.4 Stirrup Strains

The instrumented stirrups near the end of the test girders are shown in Figure 3.42.

Load versus stirrup strains curves are given in Figures 3.43 and 3.44 for the fully

bonded girder and the 50% debonded girder, respectively. Comparison of the stirrup

strains at beam failure shows that higher strains occurred in the stirrups of the 0%

debonded beam. None of the stirrups yielded in these tests.

3.3.1.5 Longitudinal Bar Strains

Three deck bars were instrumented near the applied load to measure the

longitudinal bar strains as illustrated in Figure 3.45. Typical curves are shown in

Page 52: Debonding in Pretensioned Beams-Precast Strands, Part 2

24-

Figures 3.46 and (3.47) for both the fully bonded girder and the 50% debonded girder

before failure of the cast-in-place slab. The strain in the slab longitudinal steel, in the

fully bonded beam, varied linearly with the applied load up to the slab failure. In the

debonded beam linear behavior occurred only up to flexure-shear cracking.

3.3.1.6 Strand Strains

The load-strain relationships for the prestressing strands are presented in Figures

3.48-3.53. Before flexure cracking occurred the change in the strand strain was small

and proportional to the applied load. Sudden increase in the strand strain occurred when

flexure cracking developed in the bottom flange of the beams.

3.3.1.7 Strand Movement

Four of the strands in each beam were monitored during each test to detect their

movement as shown in Figure 3.24. In the 0% debonded beam test, no movement of the

strands was recorded until failure of the girder had occurred. In the 50% debonded

beam, strand movement occurred when the first crack appeared, which was a flexure-

shear crack at an applied load of 113 kips. No movement was detected for the two

strands which were fully bonded throughout the length of the beam. Movement was

recorded for the two debonded strands, and Figure 3.54 shows the load versus strand

movement curves for the two debonded strands. The movement of the debonded strands

was the sum of two quantities: slippage of strands in the bonded region and the

movement of the strands inside the plastic tubes when crack opened in the debonded

region or at the debonding points. In this study the separate value of the two effects was

not determined.

Page 53: Debonding in Pretensioned Beams-Precast Strands, Part 2

-25-

3.3.1.8 Failure Loads

Both girders were tested to failure even though failure of the slab occurred before

girder failure. The 0% debonded beam failed at an applied load of 225.4 kips. Failure of

the beam occurred by crushing of the top concrete fibers, which led to an explosive

failure. The failure removed a section of the concrete from the bottom flange of the

beam.

Failure of the 50% debonded beam occurred at an applied load of 148.2 kips.

Failure of this beam was caused by flexure-shear cracks which opened near the two

debonding points. Four of the fully bonded strands ruptured in the failure region of this

beam.

Page 54: Debonding in Pretensioned Beams-Precast Strands, Part 2

-26

3.3.2 Specimen Set 2

The debonded girder, in Specimen Set 2, had 4 of the strands blanketed at a distance

of 6 ft. from the centerline of the support. Two additional strands were debonded at 3.5

ft from the centerline of the support. Figure 3.55 shows the strand debonding scheme

and instrumentation for the specimen.

3.3.2.1 Cracking

The first web-shear crack developed in the fully bonded girder at the 1 30 kip load

level, 30 inches from the support. The first flexure-shear crack developed at 180 kips

under the point load. At 194 kips the girder developed what became the failure crack in

the form of a flexure-shear crack as shown in Figure 3.56.

The 50% debonded girder developed its first web-shear and flexure-shear cracks at

lower loads than the fully bonded girder, as expected. The first web-shear crack in the

debonded girder occurred at a load level of 114 kips and was located at 14 inches from

the end support. The first flexure-shear crack in the debonded girder formed at the 120

kip load level. The flexure-shear crack originated at the bottom flange near the first

debonding point (42 inches from the support, see Figs. 3.55 and 3.57) and then

propagated diagonally toward the point load until it stopped at the web-top flange

junction one foot in front of the point load. Additional loading induced cracking in the

form of web-shear and flexure-shear cracks until the girder lost its capability to sustain

additional loading at the 172 kip load level as shown in Figure 3.57.

Page 55: Debonding in Pretensioned Beams-Precast Strands, Part 2

27-

3.3.2.2 Deflections

The fully bonded girder had a linear load-deflection relationship up to the load at

which web-shear cracking occurred. Subsequent loading caused larger deflection with

smaller load increments. Figures 3.58 and (3.59) illustrate the load-deflection

relationships for the fully bonded girder.

The load-deflection relationship for the debonded beam is linear up to 120 kips,

which is the load at which the girder experienced its first flexure-shear crack. After the

120 kip load, larger deflection was observed with smaller load increments as shown in

Figures 3.60-3.61. At failure the debonded girder deflected almost twice that of the

fully bonded girder.

3.3.2.3 Concrete Top Fiber Strains

Concrete strains were measured at the top fiber of the deck slab at the point load

and at 42 inches from the support as shown in Figure 3.21. The distance 42 inches from

the support corresponds to the location of the first debonding point in the 50%

debonded beam. The load-strain relationships are illustrated in Figures 3.62-3.65. At

the location of the debonding point, the top fiber strains for the two girders displayed

little difference. At the point load the debonded girder displayed much more strain than

the fully bonded girder. None of the strains reached the 0.003 limiting concrete

compressive strain.

3.3.2.4 Stirrup Strains

The location of the instrumented stirrups for Specimen Set 2 is shown in Figure

3.42. Figures 3.66 and 3.67 show the stirrup load-strain behavior for the two simply

Page 56: Debonding in Pretensioned Beams-Precast Strands, Part 2

28-

supported girders. Overall, the debonded girder displayed more stirrup strain for a given

load than the fully bonded girder except for the second instrumented stirrup (EA2 and

ED2). The second stirrup in the fully bonded girder displayed more strain. This was

caused by a diagonal crack that crossed this stirrup, the debonded girder did not have

any significant cracks that cross the corresponding stirrup. High strains were induced in

the stirrups only when diagonal cracking crossed them.

3.3.2.5 Longitudinal Bar Strains

The longitudinal slab bar strains are shown in Figures 3.68 and 3.69. The fully

bonded beam showed linear behavior up to the failure load. The 50% debonded beam

showed linear behavior up to the formation of the flexure-shear crack. After flexure-

shear cracking a reduction in strain was shown by these gages.

3.3.2.6 Strand Strains

The measured strain versus load behavior in the strands of Specimen Set 2 are

shown in Figures 3.70-3.74. No significant increase in the strain was recorded before

flexure cracking had occurred. In both beams large increase in the strain was observed

at flexure cracking. None of the strands in the fully bonded girder reached yielding prior

to the peak load. After the peak load was reached the strain gages began to malfunction

due to large amount of strand slip. Strand EA5 in the beam with 50% debonding,

shown in Figure 3.55, was stressed beyond the yield stress. This high strain was caused

by the failure flexure-shear crack that opened near the location of the gage. It must be

noted that this strand was fully bonded throughout the entire length of the beam. The

strain gages began to disfunction shortly thereafter.

Page 57: Debonding in Pretensioned Beams-Precast Strands, Part 2

-29

3.3.2.7 Strand Movement

Figure 3.25 illustrates the placement of the five dial gages used to monitor the

strand slip. In the debonded girder, all of the monitored strands began to move at 120

kips, the load that corresponds to the first flexure-shear crack. When the load reached

160 kips all of the dial gages had to be removed because the strand movement was

larger than their ranges. The reading of the dial gages mounted on the debonded

strands included the strand movement inside the plastic tubes which occurred when

cracks opened at the debonding point Three of the monitored strands in the 0%

debonded beam slipped at a load of 170 kips. In both beams, when the ultimate load

was reached, the load dropped. Subsequent loading caused all of the monitored strands

to slip beyond the range of the dial gages. All of the gages in both tests had to be

removed. Figures 3.75 and 3.76 show the load-movement behavior of the strands.

3.3.2.8 Failure Loads

The fully bonded girder failed at a load of 194 kips due to inadequate anchorage of

the required force in the strands. After the 194 kip-load was reached, the load dropped

to 170 kips and subsequent reloading caused several strands to rupture due to large

deformations.

The 50% debonded beam failed at a load of 172 kips. Examination of the test

results indicated that failure was caused by a similar mechanism as the one observed in

the specimen with 0% debonding but at a lower load level with far larger deflections.

Page 58: Debonding in Pretensioned Beams-Precast Strands, Part 2

30-

3.3.3 Specimen Set 3

The first beam in Specimen Set 3 had all 12 strands fully bonded, while the second

had 8 strands debonded (67%) as shown in Figure 3.77. The load was applied in small

increments. Data was collected after each load increment was applied, at which time

cracks were observed, marked, and photographed.

3.3.3.1 Cracking

Web-shear cracking in the fully bonded beam was observed at a load of 152 kips.

This crack originated at a distance of 20 inches from the centerline of the end support

(ED) and penetrated through the bottom flange. The applied load then dropped to 141

kips. The prestressing strands were observed to be pulling into the girder at the end of

the beam immediately after the web-shear crack formed. Mechanical deflection gages

were placed at the protruding ends of the strands to measure the resulting slippage as

shown in Figure 3.26. Additional cracks developed in the web and also penetrated

through the bottom flange when the load was subsequently increased to 152 kips. When

the load reached 158 kips a diagonal crack opened at at distance of 42 inches from the

support in the form of a flexure-shear crack. This crack then changed its direction and

propagated along the prestressing strands a distance of 20 inches towards the end of the

beam. The beam failed at 160 kips, when another inclined crack opened in the web and

joined this crack in the bottom flange. The crack pattern of the beam at failure is shown

in Figure 3.78.

The beam with 67% debonding was tested on simple supports, the load was applied

monotonically in small steps until the beam failed. When the load reached 102 kips a

Page 59: Debonding in Pretensioned Beams-Precast Strands, Part 2

-31

flexure-shear crack appeared at the second debonding point At a load of 1 10 kips three

parallel diagonal cracks opened in the web of the precast beam, between the support

and the second debonding point As soon as the load reached 1 1 8 kips three parallel

inclined cracks opened in the web. One of these cracks extended to the bottom of the

flange at the first debonding point The load then dropped to 96 kips. When the load

increased to 98 kips two cracks developed near the first debonding point and caused the

ultimate failure of the beam. The crack pattern of the beam at failure is shown in

Figure 3.79.

3.3.3.2 Deflections

The vertical deflection in both beams of Specimen Set 3 was measured at the point

of application of the external load and at the first debonding point location in the beam

with 67% debonding, a distance of 42 inches from the center line of the end support.

The deflection was measured with LVDT's placed at both sides of the beam as shown

in Figure 3.21. The load-deflection relationships for the fully bonded beam are shown in

Figures 3.80 and 3.81. The deflection of the beam varies linearly with the applied load

until web-shear cracking occurred. Once again, flexure-shear cracking clearly marked

the limit of the load carrying capacity of both beams in Specimen Set 3.

The load-deflection curves at the location of the external load and at the second

debonding point, for the beam with 67%, are presented in Figures 3.82 and 3.83

respectively. The response of this beam is similar to the beam with fully bonded

strands. Prior to cracking, the response is linear followed by nonlinear response after

cracking. However, comparison of the deflection curves for the two beams reveals that,

Page 60: Debonding in Pretensioned Beams-Precast Strands, Part 2

-32

the beam with 67% debonding had larger deflections.

3.3.3.3 Concrete Top Fiber Strains

The concrete compressive strains were monitored by surface gages installed at the

top of the slab. Figure 3.21 shows the location of the slab surface gages. In the fully

bonded beam substantial increase in concrete strains was exhibited by these gages after

the formation of web-shear cracking as indicated in Figures 3.84 and 3.85.

In the beam with 67% debonding the concrete strains in the deck slab at the external

point load showed linear variation with the load up to the formation of the flexure-shear

crack, at a load of 102 kips. However, the strains at the first debonding point, 3.5 ft.

from the center line of the support EA, continued to vary linearly with the load until the

web-shear crack formed near the end support when the load was 1 10 kips as shown in

Figures 3.86 and 3.87.

3.3.3.4 Stirrup Strains

The strain recorded by the gages mounted on four stirrups located at the ends of

the girders (see Figure 3.88), are plotted in Figures 3.89 and 3.90. As expected, these

gages did not register significant strains until they were crossed by diagonal cracks. It

can be noticed that the increase in stirrup strains was large and sudden. In the fully

bonded beam stirrup ED3 and ED4 reached their yield strain. In the beam with 67%

debonding stirrup EA4 reached the yield strain.

3.3.3.5 Longitudinal Bar Strains

The strain in the mild reinforcing steel in the slab was measured at , 6 ft. from the

center line of the end support as shown in Figure 3.45. Figures 3.91 and 3.92 show the

Page 61: Debonding in Pretensioned Beams-Precast Strands, Part 2

-33

measured strains in three different bars. For both beams the response was linear before

the opening of web-shear cracking and nonlinear after web-shear cracking occurred

owing to the drop in load carrying capacity.

3.3.3.6 Strand Strains

Figures 3.93-3.98 show the variation of strand strain with the applied load. In the

beam with 0% debonding the strand strains vary linearly with the applied load. At the

point load location sudden increase in the strand strain was noticed when a flexure

crack opened in the bottom flange. Similar behavior was exhibited by the beam with

67% debonding. However, a reduction in strains due to strand movement was observed

in the beam with 0% debonding as shown in Figure 3.93 and in the beam with 67%

debonding as shown in Figures 3.97 and 3.98.

3.3.3.7 Strand Movement

As mentioned earlier the prestressing strands slipped into the girder as soon as

web-shear cracking occurred in the 0% debonded beam. In the 67% debonded beam

movement of the strands was noticed when a flexure-shear crack opened at the second

debonding point at a load of 102 kips. The load-movement relationship for the

instrumented strands is shown in Figures 3.99 and 3.100. It can be seen that all the

instrumented strands showed significant movement when diagonal cracking occurred as

it penetrated into the strand level.

3.3.3.8 Failure Loads

Based on the previous discussion, it can be concluded that cracking in the bottom

flange near the ends of the girders disturbed the development of the prestressing steel

Page 62: Debonding in Pretensioned Beams-Precast Strands, Part 2

-34

and caused bond and anchorage failure. This led to the opening of wide diagonal cracks

which resulted in stressing the stirrups to their yielding points, thus causing premature

shear failure due to inadequate load carrying capacity of the bottom tension

reinforcement in the beams. The 0% debonded beam failed at a load of 160 kips. The

beam with 67% debonding failed at a load of 1 18 kips.

Page 63: Debonding in Pretensioned Beams-Precast Strands, Part 2

-35

3.3.4 Specimen Set 4

Specimen Set 4 consisted of two precast Indiana State Type CB-27 box girders with

a 4x36 inch composite slab. One girder had 10 strands (50%) debonded near its end.

The other had all strands fully bonded (0% debonding). The strand debonding scheme

and instrumentation is shown in Figure 3.101.

3.3.4.1 Cracking

The first appearance of diagonal cracking in the beam with 0% debonding was in

the form of web-shear cracking at a load of 160 kips at a distance of 16 inches from the

end support No web-shear crack was observed on the opposite side of the beam until

the load reached 245 kips. At that time, two parallel diagonal cracks opened in the shear

span as shown in Figure 3.102. A flexure-shear crack was also observed at a distance of

33 inches from the support The load then dropped to 190 kips. The beam lost its

ability to carry more load. At this time the test was concluded. No flexure cracks were

observed under the point load.

In the 50% debonded beam the first appearance of web-shear cracking was at a load

of 176 kips at a distance of 12 inches from the support. At the same load level a

flexure-shear crack opened at the first debonding point and propagated along the

junction of the slab and the precast beam until it reached the point of application of the

external load. At this point the beam could carry no additional load. The crack pattern

at peak load is shown in Figures 3.102.

Page 64: Debonding in Pretensioned Beams-Precast Strands, Part 2

36

3.3.4.2 Deflections

The load-deflection relationship for both beams is shown in Figures 3.104-3.107.

Figure 3.22 shows the location of the LVDT's used to measure the vertical deflection.

In both beams, the load-deflection curve is linear up to the formation of flexure-shear

cracking. After cracking the deflection increased significantly with additional applied

load. The beams were never able to reach the peak load corresponding to initial

flexure-shear cracking.

3.3.4.3 Concrete Top Fiber Strains

Figure 3.22 shows the location of the surface gages used to measure the concrete

compressive strain at the top of the deck slab. The variation of the slab top strain with

the applied load is given in Figures 3.108-3.111. In these figures it can be noticed that

higher strains occurred in the beam with 50% debonding at the point load location even

though it failed at a lower load level. Again as in the previous specimen sets, the

increase in strain is associated with larger deformations due to a reduced flexural

stiffness associated with flexure-shear cracking.

3.3.4.4 Stirrup Strains

Load versus stirrup strain is shown in Figures 3.112 and 3.113 for the 0%

debonded beam and the 50% debonded beam respectively. The stirrup reinforcement

and instrumentation is shown in Figure 3.88. It can be seen from these figures that the

stirrups near the failure region reached their yield strain at gages ED4 and EA4 location

when flexure-shear cracking occurred.

Page 65: Debonding in Pretensioned Beams-Precast Strands, Part 2

37

3.3.4.5 Longitudinal Bar Strains

The deck slab longitudinal reinforcement details and instrumentation are shown in

Figure 3.114. The measured strain in the cast-in-place slab longitudinal steel is shown

in Figures 3.115-3.116. Strains increased linearly with the applied load before flexure-

shear cracking developed. In the 50% debonded beam substantial increase in strain

without a corresponding increase in load was recorded after flexure-shear cracking

occurred.

3.3.4.6 Strand Strains

The strand strains are shown in Figures 3.117-3.124. The change in the

prestressing strand was relatively small. Large increase in the strain occurred when

flexure cracking opened. In both beams the measured strand strain was in the linear-

elastic range.

3.3.4.7 Strand Movement

Eight strands were monitored for movement in each beam as shown in Figure 3.27.

In the fully bonded beam strand movement was slightly noticeable after the formation

of web-shear cracking. However, significant movement did not occur until the

formation of flexure-shear cracking at a load level of 245 kips. In the 50% debonded

beam, strand movement was noticeable at a load level of 176 kips. Figures 3.125 and

3.126 show the load-movement behavior of the test specimen.

3.3.4.8 Failure Loads

Failure in both beams was due to lack of adequate anchorage of the prestressing

strands. Excessive strand slippage caused the early opening of flexure-shear cracking

Page 66: Debonding in Pretensioned Beams-Precast Strands, Part 2

-38

that resulted in premature failure of the beams. At failure the stirrups showed strains in

excess of the yield value.

The 0% debonded beam failed at a load of 245 kips when several diagonal cracks

opened in the web of the girder. Failure of the 50% debonded beam was also caused by

the opening of flexure-shear cracking at a load level of 177 kips.

Page 67: Debonding in Pretensioned Beams-Precast Strands, Part 2

-39-

3.3.5 Specimen Set 5

Specimen Set 5 consisted of two pretensioned Type-I AASHTO beams composite

with a 4x48 inch slab. Each beam was 308 inches long (25 feet-8 in.). One beam had

all strands fully bonded while the other had 6 strands (50%) debonded near each end.

The debonding points were located at 7 ft- 10 in. from ends EA and IB. The details of

the strand debonding and instrumentation are given in Figure 3.127.

3.3.5.1 Cracking

The first sign of shear cracking in the fully bonded beam was in the form of a

flexure-shear crack that opened near the point load at a load of 122 kips. This crack

originated as a flexure crack in the bottom flange at a load of 118 kip as shown in

Figure 3.128. Web-shear cracking occurred at a load of 158 kips as shown in Figure

3.129.

In the beam with 50% debonding, the first crack occurred near the debonding point,

7 ft.- 10 in. from end EA, in the left shear span in the form of a flexure-shear crack at a

load of 1 18 kips as shown in Figure 3.130. At a load of 127 kips a flexure-shear crack

occurred near the point load, in both shear spans, at a distance of 134 inches from the

supports. Flexure-shear cracking occurred at the debonding point in the right shear

span at a load of 128 kips. Web-shear cracking occurred at a load of 156 kips at a

distance of 28 inches from the left support as shown in Figure 3.131. No web-shear

cracking was observed in the left shear span. The crack pattern of the 50% debonded

beam at failure is shown in Figure 3.132.

Page 68: Debonding in Pretensioned Beams-Precast Strands, Part 2

-40-

3.3.5.2 Deflections

Deflection was measured using LVDTs placed at both sides of the beam as shown

in Figure 3.23. The measured load-deflection relationship, for both beams, are given in

Figures 3.133-3.136. In this specimen the deflection varied linearly with the applied

load before flexure-shear cracking occurred. After flexure-shear cracking an increase in

deflection was observed. At ultimate load, there was a large increase in deflection

without corresponding increase in the applied load.

3.3.5.3 Concrete Top Fiber Strains

Concrete strains were monitored by surface gages at the top fiber of the cast-in-

place slab at the point load and debonding points location as explained in Figure 3.23.

The measured strain versus load curves are shown in Figures 3.137-3.140. The two

beams exhibited similar behavior. At the point load location the concrete strain varied

linearly with the applied load before flexure-shear cracking occurred. Significant

increase in the strain was observed at failure. The limiting value of concrete strain in

compression (0.003) was approached at midspan of the debonded beam. This limit was

exceeded at midspan of the fully bonded beam. At the debonding point location the

measured strain showed a bi-linear behavior with the applied load throughout the test

for both beams. The limiting strain value was not reached at this location.

3.3.5.4 Stirrup Strains

Four of the stirrups in the shear spans of each beam were instrumented with strain

gages as shown in Figure 3.141. Stirrup load-strain curves for the two beams are shown

in Figures 3.142-3.144. In these beams the measured strain was very small before web-

Page 69: Debonding in Pretensioned Beams-Precast Strands, Part 2

41-

shear cracking occurred. As expected a sudden increase in stirrup strain occurred when

web-shear cracking opened. It can be noticed that none of the instrumented stirrups

yielded in these tests. Due to the absence of web-shear cracking in the right shear span

of the beam with 50% debonding, the stirrups near the right end (IB) did not register

any significant strain.

3.3.5.5 Longitudinal Bar Strains

Three longitudinal bars in the cast-in-place slab were instrumented at two different

locations as shown in Figure 3.145. The strain-load relationship is linear up to flexure-

shear cracking as shown in Figures 3.146-3.149. Bi-linear behavior was shown after

flexure-shear cracking. However, none of the slab longitudinal bars reached its yield

strain.

3.3.5.6 Strand Strains

Figure 3.127 shows the strand debonding scheme and instrumentation for both

beams. The measured strand strains for the fully bonded beam and the 50% debonded

beam are shown in Figures 3.150-3.163. Before cracking the increase in strand strain

was relatively small and varied linearly with the applied load. In the fully bonded beam

significant increase in strain was noticed when flexure-shear cracking occurred. At

failure the strands in the fully bonded beam showed strain values significantly above

yield.

In the beam with 50% debonding the first flexure-shear crack formed at the

debonding point in the left shear span at a load of 1 18 kips. As shown in Figures 3. 159

and 3.160 significant increase in the strand strain occurred at the flexure-shear cracking

Page 70: Debonding in Pretensioned Beams-Precast Strands, Part 2

-42

load. Similar behavior was shown at the debonding point in the right shear span as

shown in Figure 3.163. It must be noticed that at failure the yield stress of the strand

was reached near the point load location for the strands that were fully bonded.

3.3.5.7 Strand Movement

Four strands in each beam were instrumented using dial gages to detect their

movement during the test as shown in Figure 3.28. In the fully bonded beam three

strands moved into the girder when the load reached 172 kips. However no significant

slippage occurred in this test. The load versus strand slip for the fully bonded beam is

shown in Figure 3.164. In the beam with 50% debonding, all the instrumented strands

were fully bonded. No movement was detected in the strands of the beam with 50%

debonding until failure occurred.

3.3.5.8 Failure Loads

The fully bonded girder failed at a load of 196 kips. The beam with 50%

debonding failed at a load of 157 kips. Failure occurred by crushing of the top concrete

fibers of the cast-in-place slab as shown in Figures 3.165 and 3.166. This indicated a

typical flexure failure following yielding of the strands.

Page 71: Debonding in Pretensioned Beams-Precast Strands, Part 2

43

3.4 Summary

This chapter contains the description and results of the tests conducted in Phase 2 of

the research program. The behavior of simply supported precast pretensioned bridge

girders with debonded strands and a cast-in-place composite slab was evaluated. The

simply supported girders were tested under a single monotonic concentrated load.

Crack patterns, load-deflection curves, stirrup strains, strand strains, strand slip,

longitudinal non-prestressed reinforcement strains, and the concrete surface strain at the

top of the cast-in-place slab were presented.

In all the specimen sets large deflection were observed in the beams with debonded

strands even though the failure loads of the debonded beams were lower than those of

the fully bonded. The measured stirrup strains showed that, in each specimen set higher

strains were observed in the debonded beam.

Prior to cracking, the change in the prestressing strand strains was small and

proportional to the change in the applied load. Sudden increase in the strand strains

occurred when flexure-shear cracking developed. Measurements of the compressive

concrete strain at the top of the cast-in-place slab revealed that higher strains occurred

in the beams with debonded strands. It was also noticed that flexure-shear cracking in

the beams with debonded strands developed at the debonding points. This confirmed the

earlier findings in beam with debonded strands.

Both the debonded and the fully bonded beams of Specimen Sets 2, 3, and 4 failed

due to inadequate anchorage of the required force in the prestressing strands. Cracking

in the bottom flange near the ends of the girders disturbed the development length and

Page 72: Debonding in Pretensioned Beams-Precast Strands, Part 2

44-

caused bond and anchorage failure. This type of failure did not occur in Specimen Set

5 in which higher development lengths were provided for the prestressing strands in

spite of the presence of web-shear and flexure-shear cracking.

The next chapter contains the analysis of the results obtained from testing the

simply supported members under the effect of a single concentrated load. Summary,

conclusions, and future work are presented in chapter 5.

Page 73: Debonding in Pretensioned Beams-Precast Strands, Part 2

-45

CHAPTER 4

ANALYSIS OF EXPERIMENTAL RESULTS

4.1 Introduction

In this chapter the behavior of the simply supported beams reported in Chapter 3 is

evaluated and the results compared with predicted values from current ACI/AASHTO

provisions. The predicted web-shear and flexure-shear cracking loads at the critical

section and at the initial crack location are compared to the observed test values. The

predicted shear and flexural failure loads using ACI/AASHTO provisions are also

compared with the corresponding test results.

An evaluation of the current ACI/AASHTO requirement for strand development

length is presented in this chapter.

4.2 Effective Strand Stress

Strains in the prestressing strands were measured by electrical resistance strain

gages. The measured strains were used to calculate stress using the corresponding

stress-strain behavior given in Chapter 3. Table 4. 1 gives the effective strand stress at

the time of the tests. These values were used in all the calculations performed in this

investigation. These values represent the average of the measured strand stress at

different sections along the beam. The effective strand stress in the beams with

debonded strands was higher than in the fully bonded. It is seen that, the prestress

Page 74: Debonding in Pretensioned Beams-Precast Strands, Part 2

46

losses due to concrete elastic shortening and time-dependent creep deformations

resulting from the prestressing were less in the beams with debonded strands. These

values are in close agreement with predicted values from PCI method [1975] calculated

at midspan sections.

4.3 Web-shear Cracking

Web-shear cracking loads were calculated at the critical section, H/2 away from the

support face and at the initial crack location. H is the total depth of the composite beam.

The ACI/AASHTO equation given below is used to calculate the web cracking

strength:

Vcw=(3.5 VFT + OJfpc )bw d (4.1)

where:

Vcw =nominal shear strength provided by concrete when diagonal cracking results

from excessive principal tensile stress in the web

fc = compressive strength of concrete

fpc = compressive stress (after allowance for all prestress

losses) at the centroid of the composite section, or at the

junction of the web and flange when centroid lies within the flange,

due to both prestressing and the moment resisted by the precast member acting

alone

bw = web width of the girder

d = distance from the extreme compression fiber to the centroid of the prestressing

tension reinforcement (> 0.8 H)

Page 75: Debonding in Pretensioned Beams-Precast Strands, Part 2

47-

Table4.1

Effective Strand Stress

Specimen Set BeamEffective Strand Stress

(ksi)

1

2

3

4

5

50% Debonded

Fully Bonded

50% Debonded

Fully Bonded

67% Debonded

Fully Bonded

50% Debonded

Fully Bonded

50% Debonded

Fully Bonded

133.7

126.1

153.7

140.7

164.0

160.0

164.1

161.1

168.0

151.7

Table 4.2

Web-Shear Cracking Loads at Critical Section (H/2)

Specimen Set BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded 88 120 1.36

Fully Bonded 105 150 1.43

2 50% Debonded 87 114 1.31

Fully Bonded 97 130 1.34

3 67% Debonded 82 110 1.34

Fully Bonded 100 152 1.52

4 50% Debonded 191 176 0.92

Fully Bonded 241 160 (245) 0.66(1.02)

5 50% Debonded 111 156 1.41

Fully Bonded 136 158 1.16

Page 76: Debonding in Pretensioned Beams-Precast Strands, Part 2

48-

Table 4.3

Web-Shear Cracking Loads at Initial Crack Location

Specimen Set BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded 88 120 1.36

Fully Bonded 105 150 1.43

2 50% Debonded 86 114 1.33

Fully Bonded 98 130 1.33

3 67% Debonded 77 110 1.43

Fully Bonded 100 152 1.52

4 50% Debonded 179 176 0.98

Fully Bonded 241 160 (245) 0.66 (1.02)

5 50% Debonded 112 156 1.39

Fully Bonded 137 158 1.15

Tables 4.2 and 4.3 show that the ACI/AASHTO equations gave conservative estimates

of the web-shear cracking loads for the I-beams regradless of the amount of debonding.

However, the degree of conservatism decreased in regard to the actual web-shear

cracking capacity of the box beams. The early web-shear cracking in the fully bonded

box-beam specimen was in part determined to be due to the difference in the thickness

of the walls on the two sides of the beam. After testing, the thickness of the wall was

determined to be 4.5 inches on the side where cracks were first observed while the other

had a thickness of 5.5 inches. The values in parentheses in Tables 4.2 and 4.3 were the

observed loads when web-shear cracking occurred in the thicker wall.

Page 77: Debonding in Pretensioned Beams-Precast Strands, Part 2

49

4.4 Flexure-shear Cracking

The flexure-shear cracking capacity of prestressed beams according to the current

ACI/AASHTO Codes, Vd , is given by:

Vd =0.6 Vf'c bw d + Vd +'

c uw u-r v d•"max

(4.2)

where:

Vd = shear force at section due to unfactored dead load

V, = factored shear force at section due to externally applied loads

MmiUi= maximum factored bending moment at section due to externally applied loads

Ma = moment causing flexural cracking at section due to externally applied loads

mct=— (6VrT+fpe-fd)

I = moment of inertia of composite section

yt= distance from centroid of composite section to extreme tension fiber

fpe = compressive stress, due to effective prestressing, at extreme fiber of section where

tensile stresses are caused by externally applied loads

fd = stress due to unfactored dead load, at extreme fiber of section where

tensile stresses are caused by externally applied loads

The predicted flexure-shear cracking loads were compared to the observed values in

Table 4.4. The critical section for flexure-shear cracking was taken at the location

where these cracks occurred.

The ACI/AASHTO equations gave unconservative predictions of the flexure-shear

cracking loads for the debonded beams. For the fully bonded beams good agreement

Page 78: Debonding in Pretensioned Beams-Precast Strands, Part 2

-50

was achieved when no excessive strand slippage occurred (Specimen Sets 1, 2, and 5).

Table 4.4

Flexure-shear Cracking Loads at Initial Crack Location

Specimen Set BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded 135 113 0.84

Fully Bonded 160 165 1.03

2 50% Debonded 190 120 0.63

Fully Bonded 173 180 1.04

3 67% Debonded 143 102 0.71

Fully Bonded 206 158 0.77

4 50% Debonded 336 176 0.52

Fully Bonded 304 240 0.79

5 50% Debonded 111 118 1.06

Fully Bonded 121 122 1.01

Table 4.5 shows the predicted flexure-shear cracking loads at the critical section.

The theoretical critical section for flexure-shear cracking in the fully bonded beams, in

all specimen sets, was at the point of application of the external load. The critical

section for the beam with 50% debonding in Specimen Set 1 was at the second

debonding point, 62.5 inches from the centerline of the end support. In Specimen Set 2

the critical section for flexure-shear cracking was also at the second debonding point, a

distance of 71 inches from the end support. The critical section for the beam with 67%

debonding in Specimen Set 3 was at the first debonding point, 42 inches from the end

support. In Specimen Set 4 the critical section was at the point load. For Specimen Set 5

the critical section was at the debonding points, which were located at 84 inches from

Page 79: Debonding in Pretensioned Beams-Precast Strands, Part 2

51

the end supports. The results of Table 4.5 indicated that better agreement with test

results was obtained for flexure-shear cracking loads. However, the predicted cracking

loads for the beams with debonded strands of Specimen Sets 1, 2, 3, and 4 were

unconservative.

The predicted flexure-shear cracking loads for the debonded beams at the critical

section considering only the strands which had developed the full prestressing force are

given in Table 4.6. The theoretical critical section for all beams was at the point load.

Improved agreement with the observed flexure-shear cracking loads was obtained with

this modification. It must be noted that, the beam with 50% in Specimen set 5

developed the full prestressing force at the point load. The critical section for this beam

was at the debonding point.

Table 4.5

Flexure-shear Cracking Loads at Critical Section

Specimen Set BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded 135 113 0.84

Fully Bonded 131 165 1.26

2 50% Debonded 140 120 0.86

Fully Bonded 152 180 1.18

3 67% Debonded 140 102 0.73

Fully Bonded 166 158 0.95

4 50% Debonded 251 176 0.70

Fully Bonded 269 240 0.89

5 50% Debonded 111 118 1.06

Fully Bonded 101 122 1.21

Page 80: Debonding in Pretensioned Beams-Precast Strands, Part 2

52

Table 4.6

Flexure-shear Cracking Loads at Critical Section

with a Reduced Number of Effective Strands

Specimen Set BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded 95 113 1.19

Fully Bonded 131 165 1.26

2 50% Debonded 113 120 1.06

Fully Bonded 152 180 1.18

3 67% Debonded 116 102 0.88

Fully Bonded 166 158 0.95

4 50% Debonded 209 176 0.84

Fully Bonded 269 240 0.89

5 50% Debonded 111 118 1.06

Fully Bonded 101 122 1.21

4.5 Shear Strength

The shear capacity of the test beams was calculated by adding the contribution of

the web reinforcement to the lower value ofV^ and Vci at a given design section. The

shear resistance provided by the stirrup reinforcement is given by:

Vs=Av f

yd

(4.3)

where:

Vs= nominal shear strength provided by web reinforcement

fy= yield strength of web reinforcement

Av = cross-sectional area of the stirrups

d = distance from extreme compression fiber to the centroid of prestressing

tension reinforcement (> 0.8 H)

Page 81: Debonding in Pretensioned Beams-Precast Strands, Part 2

53

s = stirrup spacing

At any section along all the beams tested the contribution of the stirrup

reinforcement consisted of #3 U, Grade 60 stirrups at 4 inches on centers. This yields a

Vs term of 1 10 kips. All the beams were designed to ensure that shear failure would

not occur. The predicted shear failure loads are given in Table 4.7. It can be seen that

the beams tested in this study did not reach the predicted shear capacity. It also needs

to be pointed out that none of the specimens failed in shear. However, it should also be

observed that the considerable amount of stirrup reinforcement in these beams

Ar fv

= fy= 660 psi for the I-beams and 396 psi for the box beams, did not help to

bw s

prevent premature failures in the case of Specimen Sets 2, 3, and 4 where an adequate

anchorage of the longitudinal tension chord was not provided and the debonded beam in

Specimen Set 1. It must be remarked that both girders in Specimen Set 1 were tested to

failure, even though slab failure due to inadequate slab transverse reinforcement

occurred prior to beam failure. In the case of Specimen Set 5 the mode of failure was

flexure and both beams reached the expected capacity as it is discussed in the next

section.

Page 82: Debonding in Pretensioned Beams-Precast Strands, Part 2

-54

Table 4.7

Shear Failure Loads

Specimen Set BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred Failure

Mode

1 50% Debonded 268 148 0.55 Slab

Fully Bonded 297 225 0.76 failure

2 50% Debonded 267 172 0.64 Strand

Fully Bonded 288 194 0.67 anchora

3 67% Debonded 259 118 0.46 Strand

Fully Bonded 292 160 0.55 anchora;

4 50% Debonded 389 177 0.46 Strand

Fully Bonded 441 245 0.56 anchora;

5 50% Debonded 317 157 0.50 Flexure

Fully Bonded 319 196 0.61 Flexure

Page 83: Debonding in Pretensioned Beams-Precast Strands, Part 2

55-

4.6 Flexural Strength

All the pretensioned beams in Specimen Sets 2, 3 and 4 tested in this investigation

failed due to bond and anchorage loss. The girders in specimen Set 1 experience slab

failure due to inadequate slab reinforcement prior to actual beam failure. However,

they were loaded beyond slab failure until girder failures occurred. The results are

included herein for informational purposes only. The combined presence of shear and

flexural cracks in the bottom flange reduced the available anchorage length of the

strands causing failure of the pretensioned beams. As noted in the previous section,

even the close stirrup spacing provided was not adequate to prevent this failure mode.

This was not the case for Specimen Set 5. The development length specified by the ACI

Building Code [1989] is given by:

ld=-j-dp + (fps -fse )dp (4.3)

where:

ld = development length of the prestressing strand

fps = stress in prestress reinforcement at nominal strength

fse = effective stress in prestressed reinforcement

dp = nominal diameter of prestressing strand

The above expression was also adopted by AASHTO Specifications [1989]. Florida

Department of Transportation has suggested a revision in the ACI/AASHTO

specifications pertaining to the development of prestressing strands based on an

investigation carried out by El Shahawy and Batchelor in 1991. Based on the results

obtained from testing 33 AASHTO Type II pretensioned beams, El Shahawy and

Page 84: Debonding in Pretensioned Beams-Precast Strands, Part 2

-56

Batchelor concluded that the ACI/AASHTO requirement on development length of

prestressing strands is not adequate. They recommended that the development length

should be increased to 1.69 times the ACI/AASHTO values, if the full flexural strength

of the beam is to be developed. The development length for the fully bonded strands in

both fully bonded and debonded beams in each specimen set calculated based upon the

ACI/AASHTO Codes and FDOT Specifications are summarized in Table 4.8. The

values shown in parenthesis represent the requirement of doubling the development

length for strands not bonded all the way to the end of the member.

Table 4.8

Development Length

Development Length

Specimen Set Beam (inch)

ACI/AASHTO FDOT1 50% Debonded 90.4(180.8) 152.8

Fully Bonded 93.0 157.2

2 50% Debonded 83.8 (167.6) 141.6

Fully Bonded 88.1 149.0

3 67% Debonded 80.3 (160.6) 135.7

Fully Bonded 81.7 138.1

4 50% Debonded 80.3 (160.6) 135.7

Fully Bonded 81.3 137.4

5 50% Debonded 79.0(158) 133.5

Fully Bonded 84.4 142.6

The available development length of the fully bonded strands in Specimen Sets 1, 2,

3, and 4 was 100 inches. The available development length of the fully bonded strands

Page 85: Debonding in Pretensioned Beams-Precast Strands, Part 2

-57

in Specimen Set 5 was 154 inches. The number of effective strands at the location of

the maximum bending moment was calculated based on the available embedment

length of the strand. A linear relationship was used to find the effective area of the

strands which were not fully developed at the point of maximum moment. In this

analysis, the development length specified by ACI/AASHTO Specifications was

doubled for debonded strands as required. The number of strands considered effective

in computing the ultimate moment capacity of each of the girders tested is given in

Table 4.9.

The flexural strength of each girder was calculated with strain compatibility

analysis using only the effective strands given in Table 4.9. The calculated flexural

failure loads were compared to the observed test values in Table 4.10.

The results of Specimen Sets 1, 2, and 3 indicated that the predicted failure load

based on FDOT development length requirements was in general more conservative

than the values given by current ACI/AASHTO specifications. For debonded I-beams

the ACI/AASHTO predicted load is in better agreement with the test results of

Specimen sets 1, 2, and 3. The box girder specimens failed at load levels which are

below the loads predicted according to both FDOT and AASHTO recommendations.

The beams in Specimen Set 5 showed that both approaches yield comparable

conservative estimate of the failure capacity of I-beam girders.

Page 86: Debonding in Pretensioned Beams-Precast Strands, Part 2

58

Table 4.9

Number of Effective Strands

Specimen Set BeamNo. of Effective Strands

ACI/AASHTO FDOT1 50% Debonded 7.20 5.30

Fully Bonded 12.0 7.60

2 50% Debonded 7.00 5.50

Fully Bonded 12.0 8.10

3 67% Debonded 5.64 4.89

Fully Bonded 12.0 8.69

4 50% Debonded 11.9 9.58

Fully Bonded 20.0 14.6

5 50% Debonded 8.28 8.70

Fully Bonded 12.0 12.0

Page 87: Debonding in Pretensioned Beams-Precast Strands, Part 2

-59-

Table4.10

Flexural Failure Loads

Specimen Set BeamPredicted Load

(tips)

Observed Load

Gaps)

obs/pred

1 50% Debonded

ACI/AASHTOFDOT

Fully Bonded

ACI/AASHTOFDOT

141.0

105.1

228.6

148.4

148.2

148.2

225.4

225.4

1.05

1.41

0.99

1.52

2 50% Debonded

ACI/AASHTOFDOT

Fully Bonded

ACI/AASHTOFDOT

147.3

118.0

245.0

169.0

172.0

172.0

194.0

194.0

1.17

1.46

0.79

1.15

3 67% Debonded

ACI/AASHTOFDOT

Fully Bonded

ACI/AASHTOFDOT

119.0

104.4

242.0

178.5

118.0

118.0

160.0

160.0

0.99

1.13

0.66

0.90

4* 50% Debonded

ACI/AASHTOFDOT

Fully Bonded

ACI/AASHTOFDOT

250.7

205.5

408.8

303.5

177.0

177.0

245.0

245.0

0.71

0.86

0.60

0.81

5 50% Debonded

ACI/AASHTOFDOT

Fully Bonded

ACI/AASHTOFDOT

126.0

132.0

180.0

180.0

157.0

157.0

196.0

196.0

1.25

1.19

1.09

1.09

* Predicted capacity for debonded box beam in Specimen Set 4 neglecting the contribution of debonded

strands P=214 kips, obs/pred=0.83.

Page 88: Debonding in Pretensioned Beams-Precast Strands, Part 2

60

4.7 Summary

The shear and flexural behavior of the specimens reported in Chapter 3 was

evaluated in this chapter. Comparison of the predicted and observed results indicated

that the ACI/AASHTO Codes gave conservative estimates of the web-shear cracking

capacity for both the debonded and fully bonded I-beams. However, they gave adequate

estimates for the web-shear cracking capacity of the debonded box girder and

unconservative for the fully bonded one. It can be concluded that strand debonding did

not significantly influence the web-shear cracking capacity of the AASHTO I-beams as

predicted by current ACI/AASHTO specifications. Further work may be needed to

verify the findings in the case of box sections. It was noted that flexure-shear cracking

developed in the debonded beams earlier than predicted by the ACI/AASHTO

procedures. All flexure-shear cracks in the debonded beams originated at or near the

debonding points. Reasonable agreement with the test results was obtained when the

strands which were not fully developed at the critical section were not considered in the

analysis. All beams where anchorage failure of the fully bonded strands was noted

failed at loads lower than the lesser of the predicted shear and flexural failure loads. It

must also be noted that close stirrup spacing in these beams did not eliminate the

anchorage type failure.

Excessive strand slip after shear cracking had occurred, preceded the failure of both

beams in Specimen Sets 2, 3, and 4. It was concluded that the current ACI/AASHTO

provisions for development length of fully bonded prestressing strands in pretensioned

beams was not adequate in the presence of shear cracking. In the particular case of

Page 89: Debonding in Pretensioned Beams-Precast Strands, Part 2

61

web-shear cracking excessive slippage occurred when this crack penetrated into the

transfer length of the strand. A web-shear crack that does not penetrate into the transfer

length of the strand is not critical as shown by the fully bonded beam in Specimen Set

2. However, the requirement for doubling the development length for strands not

bonded all the way to the end of the member required by these codes resulted in a

conservative estimate of the flexural failure load when used in the calculation of the

effective number of strands at the critical section except for the box beam specimen.

Both beams in Specimen 5 failed at loads higher than the calculated ultimate loads

based on flexural capacity. The fully bonded prestressing strands in Specimen 5 had

development length of 1.9 1^ with ld based on the current ACI/AASHTO provisions.

This available length was also greater than the 1.7 1^ recommended by the FDOT.

Page 90: Debonding in Pretensioned Beams-Precast Strands, Part 2

-62

CHAPTER 5

SUMMARY AND CONCLUSIONS

5.1 Summary

This report presents the results of an experimental investigation conducted to

evaluate the effect of strand debonding on the behavior of simply supported

pretensioned concrete beams. The test program involved five specimen sets. Each

specimen set consisted of two beams, one of the beams had all strands fully bonded to

the surrounding concrete. The other had some strands debonded towards the ends.

Specimen Sets 1, 2, 3 and 5 were Type-I AASHTO girders composite with a 4x48 inch

cast-in-place concrete slab. Specimen Set 4 consisted of two Indiana State Type CB-27

box girders with a 4x36 inch cast-in-place slab. All beams were tested simply

supported under the effect of a single monotonic concentrated load. The flexural and

shear behavior of the debonded beams is compared to that identical fully bonded beams

in each set.

5.2 Conclusions

1. The current ACI/AASHTO equation for web-shear cracking of composite

prestressed beams gave conservative estimates of the web-shear cracking loads of

both fully bonded and debonded I-beams. Slightly unconservative results were

obtained for the box girders.

Page 91: Debonding in Pretensioned Beams-Precast Strands, Part 2

-63

2. Flexure-shear cracking developed in the debonded beams of Specimen Sets 1, 2,

3, and 4 earlier than predicted by the ACI/AASHTO codes. It was noted that

flexure-shear cracking occurred at the debonding points. It can be concluded that,

based on the predicted values of current specifications strand debonding reduces

flexure-shear cracking capacity of pretensioned beams compared to that of fully

bonded members. Good agreement with the observed flexure-shear cracking

loads at a given section was obtained when the strands which were not fully

developed based on current specifications, were not considered effective in the

calculation of the flexure-shear cracking load. The flexure-shear cracking load in

the debonded beam of Specimen Set 5, with 1.8 lj anchorage length for the fully

bonded strands, was adequately predicted by the current ACI/AASHTO

recommendations. The debonded strands developed the required prestressing

force at the point load. In this beam no slippage of the fully bonded strands was

observed. The fully bonded beams, in Specimen Sets 3 and 4, where excessive

strand slippage was observed prior to flexure-shear cracking, showed significant

reduction in the flexure-shear cracking loads with respect to predicted values. In

these specimens, web-shear cracking formed prior to flexure-shear cracking and

penetrated into the girder bottom flange within 20 inches from the support

centerline. Thus affecting the transfer length of the strands. The predicted

cracking loads were in good agreement with the test results of the fully bonded

beams in Specimen Set 1, 2, and 5 where flexure-shear cracking opened prior to

strand movement due to web-shear cracking affecting the strand transfer length.

Page 92: Debonding in Pretensioned Beams-Precast Strands, Part 2

-64-

3. In spite of the close stirrup spacing in the longitudinal direction, #3 U at 4 inches

on centers ( rfy= 660 psi for the I-beams and 396 psi for the box beams),

anchorage failures were observed in Specimen Sets 2, 3 and 4 and the debonded

beam in Specimen Set 1. Only when an anchorage length equal 1.8 1^ was

provided in Specimen Set 5, the flexural-shear capacity was achieved in both

debonded and fully bonded beams.

4. The fully bonded beams of the first four specimens failed before the predicted

flexural ultimate loads were reached. In Specimen Sets 2, 3 and 4 failure was

preceded by slippage of the prestressing strands. It can be concluded that the

strand development length specified by the ACI/AASHTO codes for fully bonded

strands is not adequate if web-shear cracking penetrates into the transfer length of

the strand, or if flexure-shear cracking occurs within the current full anchorage

length, ^ of the strand. The beams in Specimen set 5 with development length

available for the fully bonded strands, greater than that required by the

ACI/AASHTO codes failed at loads higher than the predicted values. However,

reasonable agreement with test results in the debonded beams of Specimen Sets

1, 2, 3, and 5 (I-beams) was obtained, when the number of the effective strands

was based on the current ACI/AASHTO provision for doubling the required

development length of debonded strands.

5. When the requirement of doubling the development length for debonded strands

was used in the calculation of the flexural failure loads, unconservative estimate

was obtained for the debonded box girder. Neglecting entirely the contribution of

Page 93: Debonding in Pretensioned Beams-Precast Strands, Part 2

-65

the debonded strands also resulted in unconservative estimate based on current

ACI/AASHTO requirements.

6. Adequate anchorage length for the prestressing strand in pretensioned beams is of

critical importance in reaching the full ultimate capacity both in flexure and

shear. Excessive strand slippage in beams with inadequate anchorage length

upon formation of web-shear cracks penetrating into the transfer length of the

strand or flexure-shear cracks within the anchorage length of the strand resulted

in a significant reduction in the load carrying capacity of the girders with respect

to predicted values based on current ACI/AASHTO recommendations. These

tests indicated that the required development length of Grade 270, seven-wire

strands, 0.5 inch diameter is greater than required by the ACI/AASHTO equation

if shear cracking as described above occurs within the anchorage length.

7. The flexure and shear design of both bonded and debonded pretensioned I-beams,

where the flexural capacity controls, based on current ACI/AASHTO design

provisions would be adequate provided that the fully bonded strands in the

member have anchorage length of at least 1.7 1^. This recommendation is based

on the results of the fully bonded beam in Specimen Set 3 as a lower bound. This

value of 1.7 Id is also in agreement with the finding in the FDOT study. In

debonded members the 1.7 1^ requirement should be applied to both fully bonded

and debonded strands.

8. The findings from this study indicate that the degree of conservatism decreases as

the percentage of debonding increases. It is recommended that no more than

Page 94: Debonding in Pretensioned Beams-Precast Strands, Part 2

-66-

67% of the strands be debonded. The current limit of 50% was shown to be

conservative provided the anchorage length of the fully bonded strand is at least

1.7 1^, with ld based on current ACI/AASHTO requirements.

9. Findings of this study indicate that no limitation would seem to be required in

regard to the number of strands debonded on a given row. However, to avoid

large stress concentration it is recommended to stagger the debonding with a total

percentage of strands debonded in the girder not greater than 67%.

5.3 Future Work

The current ACI/AASHTO Specifications yielded unconservative estimates of the

flexural failure loads of both beams in the box girder specimen set. Further research is

needed to examine the behavior of simply supported pretensioned box beams with

debonded strands.

The I-beam specimens in this study were all designed so that flexure would control

the member capacity. To fully determine the adequacy of current AASHTO design

recommendations for shear, it would be necessary to observe experimentally the

behavior of bonded and debonded specimens designed to fail in shear with an available

anchorage length of 1.7 Id for the fully bonded strands.

The current ACI/AASHTO provisions for the development length of fully bonded

strands appear inadequate. Further experimental research is needed to determine the

adequate development length for both fully bonded and debonded strands in

pretensioned concrete beams.

Page 95: Debonding in Pretensioned Beams-Precast Strands, Part 2

-67-

LIST OF REFERENCES

Page 96: Debonding in Pretensioned Beams-Precast Strands, Part 2

-68-

REFERENCES

1. Abdalla, O., A., Ramirez, J., A., and Lee, R., H., "Precast Prestressed Concrete

Bridges with Debonded Strands: Continuity Issues," Report No.

FHWA/INDOT/JHRP-92, Part 1 Final Report, Purdue University, June 1992.

2. ACI Standard 318-63, "Building Code Requirements for Reinforced Concrete."

American Concrete Institute, 1963.

3. ACI Committee 318, "Building Code Requirements for Reinforced Concrete

(ACI 318-77)." American Concrete Institute, Detroit, Michigan, December 1977,

102 pp.

4. ACI Committee 318, "Building Code Requirements for Reinforced Concrete

(ACI 318-89)." American Concrete Institute, Detroit, Michigan, December 1989,

353 pp.

5. American Association of State Highway and Transportation Officials , 1989,

"Standard Specifications for Highway Bridges", Fourteenth Edition, Washington,

D.C.

6. Baron, M., J., "Shear Strength of Reinforced Concrete Beams at Point of Bar

Cutoff." ACI Journal, Vol. 63, No. 6, January 1966, pp. 127-133.

7. British Standards Institution, "BLCP 80, Draft British Standard Code of Practice

for the Structural Use of Concrete." 1969.

8. Dale, J., T., "The Shear Strength of Partially Prestressed Concrete Beams."

Report No. 317, Department of Civil Engineering, University of Auckland, NewZealand, 1983,351 pp.

9. Dane, J. and Bruce, R., N, Jr., "Elimination of Draped strands in Prestressed

Concrete Girders." Department of Civil Enginnering, Tulane University, NewOrleans, Louisiana, Technical Report No. 107, June 1975, 147 pp.

10. El Shahawy, M., and Batchelor, B., "Bond and Shear Behavior of Prestressed

AASHTO Type II Beams." Progress Report No.l, Structural Research Center,

Florida Department of Transportation, February 1991, 69 pp.

1 1. Ferguson, P., M., and Matloob, F., N, "Effect of Bar Cutoff on Bond and Shear

Strength of Reinforced Concrete Beams." ACI Journal, Vol. 50, No. 1, July 1959,

pp. 5-23.

12. Hanson, N., W., and Kaar, P., H., "Flexural Bond Tests of Pretensioned

Prestressed Beams." ACI Journal, V. 55, No. 7, January 1959, pp.783-803.

13. Kaar, P., H., and Magura, D., D., "Effect of Strand Blanketing on Performance of

Pretensioned Girders." PCI Journal, Vol. 10, No. 6, December 1965, pp. 20-34.

Page 97: Debonding in Pretensioned Beams-Precast Strands, Part 2

-69

14. Krishnamurthy, D., "The shear Strength of I-Beams With Debonded Tendons."

Materiaux et Constructions, Vol. 4, No. 22, 1971, pp. 213-218.

15. MacGregor, J., G., Sozen, M., A., and Sies, C., P., "Effect of Draped

Reinforcement on Behavior of Prestressed Concrete Beams." ACI Journal,

Vol.23, NO.6, December 1960, pp. 649-677.

16. Maruyama, K., and Rizkalla, S., H., "Shear Design Consideration for

Pretensioned Prestressed Beams." ACI Structural Journal, V. 85, No. 5,

September-October 1988, pp. 492-498.

17. Martin, L., D., and Scott, N., L., "Development of Prestressing Strand in

Pretensioned Members". ACI Journal, V. 73, No. 8, August 1976, pp. 453-456.

18. PCI Committee on Prestress Losses, "Recommendation for Estimating Prestress

Losses." PCI Journal, V.20, No.4, July-August 1975, pp. 44-75.

19. Pensinger, K.., "A Fatigue Study of Debonded Strands in Pretensioned Prestressed

Members". M.Sc. Thesis, Department of Civil Engineering, Purdue University,

Indiana, August 1987.

20. Rabbat, B., G., Kaar, P., H., Russell, H., G., and Bruce, R. 5 N., Jr., "Fatigue Tests

of Pretensioned Girders With Blanketed and Draped Strands." PCI Journal,

Vol.24, No.4, July-August 1979, pp.88- 115.

21. Reagan, P., E., and Mitra, A., C, "Curtailment of Main Reinforcing Steel and its

Effect on Shear." The Structural Engineer, Vol. 50, No. 11, November 1972, pp.

445-449.

22. Zia, P., and Mostafa, T., "Development Length of Prestressing Strands." PCI

Journal, V. 22, No. 5, September-October 1977, pp. 54-65.

Page 98: Debonding in Pretensioned Beams-Precast Strands, Part 2

-70-

ccocoo

71

en

u

ucl/J

uC/3

Ur-

•oUtr

oD.9.

_^5.

5or;

en

Page 99: Debonding in Pretensioned Beams-Precast Strands, Part 2

71-

\

\\

\\\\\

C/9

re

U

c-_>

•3

uQ.

3

—-_>

coexex

c/j

en

3

Page 100: Debonding in Pretensioned Beams-Precast Strands, Part 2

72

co

i k - J k

co

i r

- * ^wh*

> r

- * kwr-;

^ri f

. i i

in

i i

inCOTT CO

>

i

in

_ i

in

r

I

f

I

-kinr*

"J

*A

>' i

CO CO COUJ UJ LUQ Q Q^ ^ ^ ._ ._DCCO

CCCD

OC COCL

CO

CO COoc CC CC in in

CDin

CD CQ CQn_ II

CO t CO=**: =*»: =**:

COo.CD1—

c/3

LU CO

LU II

00 £o-a:r--

CM QLU ZQ<<CCOCI-oco

m CM I CSJ I CNJ

uCO

c•J

E•3

u

c/5

u-

C

2"J

C

BC

O-J

-r.

£u_

"S

5u

oaEoU

B3

Page 101: Debonding in Pretensioned Beams-Precast Strands, Part 2

73

o ^^^^

1— ME

_1COLO

LU 1—'

cc O1

55II

o LU—1 QCo <r—CM QLU Zo«s:<ccCCI-C5 CO

to

in

C

of

cu

o-J

.0

u

e

uu

c

UUs5ij

o

£

a

en

BOB

Page 102: Debonding in Pretensioned Beams-Precast Strands, Part 2

— IH

2.625",

4">L 2.875";A

1.5"

27"

Cast-in-place slab

fc' = 4333 psi

I*5"->K- 26"- >*-5"1

» m_

18.5"

5.5"

^si I 14"

• I =5 i--S

^N

#6@15"#6, Grade 60

#4@18"

#5, Grade 60

#4@15"

#3, Grade 60 @ 4"

fci 5600 psi

fc' = 6732 psi

2" i

fiOfr

1/2" Lo - Laax

Grade 270 Strand (Area = 0.153 in.2

)

Figure (3.5) Composite Girder Cross-section and Details for Specimen Set 4.

Page 103: Debonding in Pretensioned Beams-Precast Strands, Part 2

-75

(psi)

7000

6000-

5000-

4000-

3000-

2000-

1000-

50

Precast Beams

Cast-in-place Slab

100 150

Age (Days)

200 250

Figure 3.6 Variation of Uniaxial Compressive Strength

of Concrete With AgeSpecimen Set 1

Page 104: Debonding in Pretensioned Beams-Precast Strands, Part 2

76

(psi)

e .

6000-/

5000- /

4000-

\3000-

\Pre

\Cast-in-place Slab

2000-cast Beams

1000-

o

1

1 1

20 401 1 1

60 80 1001

120i

140

Age (Days)

Figure 3.7 Variation of Uniaxial Compressive Strength

of Concrete With AgeSpecimen Set 2

Page 105: Debonding in Pretensioned Beams-Precast Strands, Part 2

77

6000

5000-

4000-

(psi).3000-

2000-

1000-

I I i i i i i i i r20 40 60 80 100 120 140 160 180 200 220

Age (Days)

Figure 3.8 Variation of Uniaxial Compressive Strength

of Concrete With AgeSpecimen Set 3

Page 106: Debonding in Pretensioned Beams-Precast Strands, Part 2

78

8000

60 80 100

Age (Days)

140

Figure 3.9 Variation of Uniaxial Compressive Strength

of Concrete With AgeSpecimen Set 4

Page 107: Debonding in Pretensioned Beams-Precast Strands, Part 2

8000

1000-

-79

20

Precast Beams

Cast-in-place Slab

40 60 80 100

Age (Days)

Figure 3.10 Variation of Uniaxial Compressive Strength

of Concrete With AgeSpecimen Set 5

Page 108: Debonding in Pretensioned Beams-Precast Strands, Part 2

-80

Stress

(ksi)

JW —

fpy= 255 ksi fpu = 280 ksi

250- f200- /150- / Modulus of Elasticity=28500 ksi

100- /50- /

/1

1 1 I 1 1

5000 10000 15000 20000 25000 300

Strain ( u— )in

Figure 3.11 Measured Stress-Strain Behavior

of Prestressing Strands (Stress Relieved)

Specimen Set 1

Page 109: Debonding in Pretensioned Beams-Precast Strands, Part 2

81

Stress

(ksi)

300

250-

200-

150-

100-

50-

fpy

=252ksi ^ = 280 ksi

Modulus of Elasticity=29 100 ksi

1 1 1

10000 15000 20000 25000 30000

Strain ( Li — )in

Figure 3.12 Measured Stress-Strain Behavior

of Prestressing Strands (Low-Lax)

Specimen Sets 2 and 3

Page 110: Debonding in Pretensioned Beams-Precast Strands, Part 2

-82-

Stress

(ksi)

JUW —fp

y= 264 ksi fp,, = 284 ksi

250-

200-

150-

Modulus of Elasticity=28600 ksi

100-

50-

ni

) 50001 1 1 l

10000 15000 20000 25000 300

StrainU^ )in

Figure 3.13 Measured Stress-Strain Behavior

of Prestressing Strands (Low-Lax)

(Specimen Sets 4 and 5)

Page 111: Debonding in Pretensioned Beams-Precast Strands, Part 2

-83-

Stress

(ksi)

T 1 1 T2000 4000 6000 8000 10000 12000 14000 16000

inStrain (\i— )

in

Figure 3.14 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Set 1)

Page 112: Debonding in Pretensioned Beams-Precast Strands, Part 2

84

80

Stress

(ksi)

fy= 62 ksi

Modulus of Ealsticity=30000 ksi

~~I I I I I I I

2000 4000 6000 8000 10000 12000 14000 16000

Strain (n™ )in

Figure 3.15 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Sets 2 and 3)

Page 113: Debonding in Pretensioned Beams-Precast Strands, Part 2

85-

80

Stress

(ksi)

fy= 64ksi

Modulus of Elasticity=28600 ksi

"I 1 1 1 1 1 1

2000 4000 6000 8000 10000 12000 14000 16000

inStrain (u-^- )

in

Figure 3.16 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Set 4)

Page 114: Debonding in Pretensioned Beams-Precast Strands, Part 2

86

80

Stress

(ksi)

fy= 62 ksi

Modulus of Elasticity=28000 ksi

1 1 1 1 1 1

2000 4000 6000 8000 10000 12000 14000 16000

Strain(n^. )in

Figure 3.17 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen Set 5)

Page 115: Debonding in Pretensioned Beams-Precast Strands, Part 2

87

Stress

(ksi)

uu —

80-fy =72 ksi ^^^^~

60- 1

40- JModulus of E lastic ity=28 100 ksi

20- /

o/

u1 1 1 1

5000 10000 15000 20000 250

Strain(ji^- )in

Figure 3.18 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen Set 1)

Page 116: Debonding in Pretensioned Beams-Precast Strands, Part 2

88

Stress

(ksi)

w —

80-fy=72 ksi ^^——

^^"

60-/

40- /

/ Modulus of Elasticity=28100 ksi

20-/

n /

(

1 1 l l

) 5000 10000 15000 20000 250

StrainCn^ )in

Figure 3.19 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen Sets 2 and 3)

Page 117: Debonding in Pretensioned Beams-Precast Strands, Part 2

89

Stress

(ksi)

uu —

80-fy= 71ksi

60-/

40-/

Modulus of Elasdcity=28000 ksi

20-

1

(

1

\ 50001 1 1

10000 15000 20000 250

Strain(ji^ )in

Figure 3.20 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen Sets 4 and 5)

Page 118: Debonding in Pretensioned Beams-Precast Strands, Part 2

90

o>._ \

9)0)0= = £<« 5

mac

n'

Ut/3

EU

u

C/3

u

C-

u

C/3

B

Q>

B

o-;

3H:C3

5u

>a.cE-

CO

w t:

<U_I 3

CO03

COtCO

;r t

b

Page 119: Debonding in Pretensioned Beams-Precast Strands, Part 2

-91-

to =

o\

cu a> o

c"J

-«0-

ouQ.00

em

u

uuf3

00

aeus

HQ>

cSS-« CO

CO

^r v

o

I

rea're

CO

-LVDT

-Surface

x D

c_g

oc

o=?

>a.

en

e

.co.CO

Page 120: Debonding in Pretensioned Beams-Precast Strands, Part 2

-92-

•- tr0>0)0= B 2:'

s3I A A

_ tr

= = £*

« CO

n-±

t

a

V V V

CO

CO09U•tz3CO

u

cuE-JuQ,on

V-

c

uu—3

—cca

r-

Q>

o

y

—>

mnen

B=60

Page 121: Debonding in Pretensioned Beams-Precast Strands, Part 2

93

\ CO

• •<§>!»CM

ECOCD

CD

CDo

re

So•o

COC3)

C3

3 a.

ajc/9

COSE2553

So

a ES

®XECOCD

CD

CD

U00

s

i

a.

!

i

c1—

I

a.

00

I00

Page 122: Debonding in Pretensioned Beams-Precast Strands, Part 2

-94-

in

\esi

EasCD•a09

09Q

IT3

\

XX e^ to cC309CO

• x« 09CO ^sco

• x« 09OCM

X

&0090)reCD^wre

•^Hay-

J QT3'~axo

^3 C^3c 03CCD E23*"00 wCQ^g e/>^as _coe a =o CO09

22eoS

® X

cu

uuQ,C/3

•—

cO

s<u

E3

1/3—

6CO

(Nen

£

Page 123: Debonding in Pretensioned Beams-Precast Strands, Part 2

-95

E

m09

09

S5r-(0

ted

with

Dial

Gages

^3 e-oc uen ESS

3?i53 ^°°o "^S0)a

^Oo'S

o so09

22a 532

®XECO09CD

09

09a

SGO

C"J

o

on

co

u

Page 124: Debonding in Pretensioned Beams-Precast Strands, Part 2

\

96-

E03CO

03

\

asQ

gin

00aio>COOH«waf

3 aT1'""axo

a e-ac 09SCO E2CO =co-o <"i;05a _=oe o<=o soja09a

22to®

®x

Ere

CO

u

u:/]

cI)

Suuaenu,C

c-J

E3

B

gCO

r-

en

3

-

in

Q3

\ X?

Page 125: Debonding in Pretensioned Beams-Precast Strands, Part 2

97-

^A® EA3asoa

as

oa>agin

•X®®

\x® USaso>reC3

"re

a

bonded

Strand

and

instrumented

will

Monitor

Strand

Slip

/as ±3™a co£1

__/ •* E03as

® X

\X X

cmas

asa

uC/3

c-J

Euua

C/3

co

E/3

c

•ac

gCO

oc

3to

XCO

Page 126: Debonding in Pretensioned Beams-Precast Strands, Part 2

-98-

O

a

Eas

COQQltjQluujQUI

Vs-

03

^V

U:/3

co£CJoa

c/3

Uc

•—

c

a •—

'

c= —CB u

E3

,„ "O —jg aj

t/3

re c =tu a}

m E t3TS 5 EO g u«J CO r*

as a) Oca ro J=O o u

c/3

E09

o<M

c

uQT3

ineo

CO

CD

3\r\

en

£3

-

>r m ir

ECDa>

Ere

CO

Page 127: Debonding in Pretensioned Beams-Precast Strands, Part 2

-99

Figure 3.30 Crack Pattern of0% Debonded Beam Before Slab Failure

Specimen Set 1

Figure 3.31 Crack Pattern of 0% Debonded Beam at Failure

Specimen Set 1

Page 128: Debonding in Pretensioned Beams-Precast Strands, Part 2

100-

Figure 3.32 Crack Pattern of 50% Debonded Beam Before Slab Failure

Specimen Set 1

Figure 3.33 Crack Pattern of 50% Debonded Beam at Failure

Specimen Set 1

Page 129: Debonding in Pretensioned Beams-Precast Strands, Part 2

101-

4X3 —

200-

175- ^150-

Load

(Kips)1(M) _

75-

50-

25-

A.Vf i 1 1 1 1

0.0 0.1 0.2 0.3 0.4 0.5

Deflection Under Load P (inch)

0.6

Figure 334 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 1)

Page 130: Debonding in Pretensioned Beams-Precast Strands, Part 2

-102

Load

0.2 0.3

Deflection at 40 in. from Support (inch)

0.4

Figure 3.35 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 1)

Page 131: Debonding in Pretensioned Beams-Precast Strands, Part 2

-103-

0.1 0.2 0J

Deflection Under Load P (inch)

0.4

Figure 3.36 Load-Deflection Relationship, for Simply Supported BeamBeam with 50% Debonding (Specimen Set 1)

Page 132: Debonding in Pretensioned Beams-Precast Strands, Part 2

104

0.05 0.10 0.15 0.20 0.25

Deflection at First Debonding Point (inch)

0J0

Figure 3.37 Load-Deflection Relationship, for Simply Supported BeamBeam with 50% Debonding (Specimen Set 1)

Page 133: Debonding in Pretensioned Beams-Precast Strands, Part 2

105

225

Strain(n^ )in

Figure 3.38 Surface Strain in Slab, 40 in. from the Support

Beam with 0% Debonding (Specimen Set 1)

Page 134: Debonding in Pretensioned Beams-Precast Strands, Part 2

106

225

350

Strain ( ji 4^- )in

Figure 3.39 Surface Strain in Slab, at the Point LoadBeam with 0% Debonding (Specimen Set 1)

Page 135: Debonding in Pretensioned Beams-Precast Strands, Part 2

-107

Strain ( u, — )in

Figure 3.40 Surface Strain in Slab, at First Debonding Point

Beam with 50% Debonding (Specimen Set 1)

Page 136: Debonding in Pretensioned Beams-Precast Strands, Part 2

108

50i 1

1 1 1 r

100 150 200 250 300 350 400 450

Strain ( u — )in

Figure 3.41 Surface Strain in Slab, at the Point LoadBeam with 50% Debonding (Specimen Set 1)

Page 137: Debonding in Pretensioned Beams-Precast Strands, Part 2

109

Ar= •2 a

1=1ca as

§«2o

1r

^>

0)

CO

« 3ca

1

k

Ma>

.CO

® j caucaa.3 a3

a

i

k

D

CO CM

^^ i

i 3

\

kt

aSr

2X t

1—•_ a

LU i k Cer LiolSuE to

CD i

V

C-4

-a

uCO

Cu

uCLCO

cc

coE

faC/J

c

•occs

cuE

,o

Cl3b

CO

c

2

(S

360

Page 138: Debonding in Pretensioned Beams-Precast Strands, Part 2

-110

2500

Strain (u^ )in

Figure 3.43 Stirrup Strain, Beam with 0% Debonding

(Specimen Set 1)

Page 139: Debonding in Pretensioned Beams-Precast Strands, Part 2

-Ill

40-1

20

Gage EA1

Gage EA2

_A GageEA3

.„ GageEA4

T T300 600 900 1200 1500

Strain ( Li— )in

1800

Figure 3.44 Stirrup Strain, Beam with 50% Debonding

(Specimen Set 1)

Page 140: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 112-

\ oo

-v• _ o » s o

CD(0

"*

O)C3>

o03

05

E0)QQ

ii'- []«M I l«*>

it

E03QQ

s * isT—

CD

i. r«J B o

[]£ 112

XJT XJT TXT7^ -*" \J/

in =

r- O

->

Page 141: Debonding in Pretensioned Beams-Precast Strands, Part 2

113

225

200-

Gage No. 13

Gage No. 14

Gage No.15

T100 200 300 400

in

500 600

Strain (u — )in

700

Figure 3.46 Strain in Slab Longitudinal Steel at 6.0 ft From Support

Beam with 0% Debonding (Specimen Set 1)

Page 142: Debonding in Pretensioned Beams-Precast Strands, Part 2

114

135

120-

100-

80-

Load

(Kips) 60 -

40-

20-

300

Strain ( u— )in

Gage No. 1

Gage No.3

400 500

Figure 3.47 Strain in Slab Longitudinal Steel at 6 ft from Support

Beam with 50% Debonding (Specimen Set 1)

Page 143: Debonding in Pretensioned Beams-Precast Strands, Part 2

115

2000 3000 4000 5000 6000 7000

Strain (u^- )in

Figure 3.48 Strand Strains at 45 in. from Support

Beam with 0% Debonding (Specimen Set 1)

Page 144: Debonding in Pretensioned Beams-Precast Strands, Part 2

116

225

200-

175-

150-

Load

(Kips)100 _

75

50-

25-

3000

Gage ED5

Gage ED6

4500 6000 7500

inStrain (n-^- )

in

9000

Figure 3.49 Strand Strains at 68 in. from Support

Beam with 0% Debonding (Specimen Set 1)

Page 145: Debonding in Pretensioned Beams-Precast Strands, Part 2

117

4000 9000

inStrain(n-^ )

in

Figure 3.50 Strand Strains at 88 in. from Support

Beam with 0% Debonding (Specimen Set 1)

Page 146: Debonding in Pretensioned Beams-Precast Strands, Part 2

135

118

120- GageEA2

100-

80-

Load

(Kips) 60-

40-

20-

5000 5500 6000

Strain (p. — )

in

6500 7000

Figure 3.51 Strand Strains at First Debonding Point

Beam with 50% Debonding (Specimen Set 1)

Page 147: Debonding in Pretensioned Beams-Precast Strands, Part 2

-119-

135—1

120-

-^*c

100-/ Gage EA6

80- /

Load 1

(Kips) 60-

40-

20-

J

1 l T~4000 5000 6000

Strain (a-)in

7000 8000

Figure 3.52 Strand Strains at Second Debonding Point

Beam with 50% Debonding (Specimen Set 1)

Page 148: Debonding in Pretensioned Beams-Precast Strands, Part 2

120

135 -r

120-

100-

80-

Load

(Kips) 60-

40-

20-

2000

Gage EA8

Gage EA9

3000 4000

Strain ( U— )in

5000

Figure 3.53 Strand Strains at 82 in. from Support

Beam with 50% Debonding (Specimen Set 1)

Page 149: Debonding in Pretensioned Beams-Precast Strands, Part 2

121

Load

(Kips)

14U-r

120-

r /

-JS-5-^-"

^^J

100-

80-

60-

40- Gage. Nn.2

_____ Gage No.4

20-1

J1

l

n1 1 1 1 1

0.00 0.02 0.04 0.06 0.08

Movement (inch)

0.10 0.12

Figure 3.54 Strand Movement, Beam with 50% Debonding

Specimen Set 1

Page 150: Debonding in Pretensioned Beams-Precast Strands, Part 2

122

*

0)

cu

o-J

O)

as

"V^EC3

OQ

in

03

aCD

a>

Eas

at

CO

\f V \f

ECOa>

"\A

i

3

3

aUiaLU

A

c

til

1CO

V)

u

<

ECDas

u

re —w Kj

CO Ua rj

at Uc ^~

cu oh s.

00c

QuQCu.

C/3

inin

en

i

so

I I l i

Page 151: Debonding in Pretensioned Beams-Precast Strands, Part 2

-123

Figure 3.56 Crack Pattern of 0% Debonded Beam at Failure

Specimen Set 2

1

"3SH

• % *-*-.- .*.

finest.

-

Figure 3.57 Crack Pattern of 50% Debonded Beam at Failure

Specimen Set 2

Page 152: Debonding in Pretensioned Beams-Precast Strands, Part 2

-124-

Load

(Kips)

0.10 0.20 0.30 0.40

Deflection Under Load P (inch)

0.50

Figure 3.58 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 2)

Page 153: Debonding in Pretensioned Beams-Precast Strands, Part 2

-125

Load

(Kips)

0.05 0.10 0.15 0.20 0.25

Deflection at 3.5 ft. from Support (inch)

0J0

Figure 3.59 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 2)

Page 154: Debonding in Pretensioned Beams-Precast Strands, Part 2

126

Load

(Kips)

0.20 0.40 0.60 0.80

Deflection Under Load P (inch)

1.00

Figure 3.60 Load-Deflection Relationship,Beam with 50% Debonding

(Specimen Set 2)

Page 155: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 127 -

Load

(Kips)

0.00 0.20 0.40 0.60 0.80 1.00

Deflection at the Second Debonding Point (inch)

Figure 3.61 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 2)

Page 156: Debonding in Pretensioned Beams-Precast Strands, Part 2

128

Load

(Kips)

Strain ( ji — )

in

Figure 3.62 Surface Strain in Slab, at 3.5 ft. from Support

Beam with 0% Debonding (Specimen Set 2)

Page 157: Debonding in Pretensioned Beams-Precast Strands, Part 2

129-

Load

(Kips)

500

o • / ln XStrain ( u.— )

in

Figure 3.63 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 2)

Page 158: Debonding in Pretensioned Beams-Precast Strands, Part 2

130-

Load

(Kips)

75 100 125 150 175 200

Strain ( |i — )

in

Figure 3.64 Surface Strain in Slab at First Debonding Point

Beam with 50% Debonding (Specimen Set 2)

Page 159: Debonding in Pretensioned Beams-Precast Strands, Part 2

-131

Load

(Kips)

i 1 1 r

600 800 1000 1200 1400 1600

Strain ( [i — )

in

Figure 3.65 Surface Strain in Slab at the Point LoadBeam with 50% Debonding (Specimen Set 2)

Page 160: Debonding in Pretensioned Beams-Precast Strands, Part 2

-132-

Load

(Kips)

2500

Strain ( jj. — )

in

Figure 3.66 Stirrup Strain, Beam with 0% Debonding

(Specimen Set 2)

Page 161: Debonding in Pretensioned Beams-Precast Strands, Part 2

133-

Load

(Kips)

1500

Strain ( u — )in

3000

Figure 3.67 Stirrup Strain, Beam with 50% Debonding

(Specimen Set 2)

Page 162: Debonding in Pretensioned Beams-Precast Strands, Part 2

134

Load

(Kips)

Strain ( \i — )in

Gage No. 1

3

Gage No. 14

Gage No. 15

400 500

Figure 3.68 Strain in Slab Longitudinal Steel, at 6.0 ft from Support

Beam with 0% Debonding (Specimen Set 2)

Page 163: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 135 -

Load

(Kips)

300

Strain ([i— )in

Gage No. 1

Gage No. 2

Gage No. 3

400 500

Figure 3.69 Strain in Slab Longitudinal Steel, 6.0 ft. from Support

Beam with 50% Debonding (Specimen Set 2)

Page 164: Debonding in Pretensioned Beams-Precast Strands, Part 2

136

Load

(Kips)

4500 4750 5000

Strain ( |i — )

in

5250 5500

Figure 3.70 Strand Strain at 41 in. from Support

Beam with 0% Debonding (Specimen Set 2)

Page 165: Debonding in Pretensioned Beams-Precast Strands, Part 2

-137-

Load

(Kips)

194

180 -|

160

140-

120-

100-

80-

60-

40-

20-

4000

Gage ED5

Gage ED7

4500 5000

Strain ( n — )

in

5500 6000

Figure 3.71 Strand Strain at 6 ft. from Support

Beam with 0% Debonding (Specimen Set 2)

Page 166: Debonding in Pretensioned Beams-Precast Strands, Part 2

138-

194

180-1

Load

(Kips)

4000

Gage ED 10

Gage ED 11

__ GageED12

4500 5000 5500

in

6000

Strain ( jj. — )

in

6500

Figure 3.72 Strand Strain at 85 in. from Support

Beam with 0% Debonding (Specimen Set 2)

Page 167: Debonding in Pretensioned Beams-Precast Strands, Part 2

139

Load

(Kips)

4500 5000 5500 6000 6500 7000

Strain ( u.— )

in

Figure 3.73 Strand Strain at First Debonding Point

Beam with 50% Debonding (Specimen Set 2)

Page 168: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 140

Load

(Kips)

172

160-

140-

120-

100-

80-

60

40-

20-

4000

Gage EA4

Gage EA5

6000 8000

Strain ( u.— )

in

10000 12000

Figure 3.74 Strand Strains at Second Debonding Point

Beam with 50% Debonding (Specimen Set 2)

Page 169: Debonding in Pretensioned Beams-Precast Strands, Part 2

141

Load

(Kips)

160-

140-

120-

100-

80-

60-

40-

20-

0.000 0.002

Gage No. 1

Gage No.2

„. Gage No.3

_> Gage No.4

_A GageNo.5

T0.004 0.006 0.008

Slip (inch)

—I

0.010 0.012

Figure 3.75 Strand Slip, Beam with 0% Debonding

Specimen Set 2

Page 170: Debonding in Pretensioned Beams-Precast Strands, Part 2

142

Load

(Kips)

100

I]

j]

60-

40

20-

0-u

0.00

Gage No. 1

Gage No.2

GageNo.3

A • . Gage No.4

_g Gage No.5

0.05i

1

0.10 0.15

Movement (inch)

0.20 0.25

Figure 3.76 Strand Movement, Beam with 50% DebondingSpecimen Set 2

Page 171: Debonding in Pretensioned Beams-Precast Strands, Part 2

-143

CO

mo

-V

'3uQ.CO

C

o

£=O09

"* • •<§)<§)

v^ECO09CD

5?r—to

0)O

ECO09

v 1

1

^V r

A

i

eo

r \fEnd

ED

A

u

I

it

o g^ r-e ~co <u— JZCO yT3 CO

E

Ere

tiii ECO

"3Co£1uQ—c

— CO

r-

3SO

Page 172: Debonding in Pretensioned Beams-Precast Strands, Part 2

144

Figure 3.78 Crack Pattern of 0% Debonded Beam at Failure

Specimen Set 3

Figure 3.79 Crack Pattern of 67% Debonded Beam at Failure

Specimen Set 3

Page 173: Debonding in Pretensioned Beams-Precast Strands, Part 2

145

Load

(Kips)

10U-

140- AV ^120- 1

100-

/80-

/60- 1

40-

/20- /

n /i i i i i

0.0 0.1 0.2 0.3 0.4 0.5

Deflection Under Load P (inch)

0.6

Figure 3.80 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 3)

Page 174: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 146

Load

(Kips)

0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

Deflection at 3.5 ft. from Support (inch)

Figure 3.81 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 3)

Page 175: Debonding in Pretensioned Beams-Precast Strands, Part 2

-147-

Load

(Kips)

i r 1i ~i

i r

0.25 0.50 0.75 1.00 1.25 1.50 1.75 2MDeflection Under Load P (inch)

Figure 3.82 Load-Deflection Relationship, for Simply Supported BeamBeam with 67% Debonding (Specimen Set 3)

Page 176: Debonding in Pretensioned Beams-Precast Strands, Part 2

148

Load

(Kips)

0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75

Deflection at the First Debonding Point (inch)

Figure 3.83 Load-Deflection Relationship, for Simply Supported BeamBeam with 67% Debonding (Specimen Set 3)

Page 177: Debonding in Pretensioned Beams-Precast Strands, Part 2

-149

160

140-

Load

(Kips)

Strain ( u. — )in

Figure 3.84 Surface Strain in Slab, at 3.5 ft. from Support

Beam with 0% Debonding (Specimen Set 3)

Page 178: Debonding in Pretensioned Beams-Precast Strands, Part 2

150

Load

(Kips)

Strain ( |i — )

in

600 700

Figure 3.85 Surface Strain in Slab at the Point Load

Beam with 0% Debonding (Specimen Set 3)

Page 179: Debonding in Pretensioned Beams-Precast Strands, Part 2

-151-

Load

(Kips)

inStrain ( u. -^-

)in

Figure 3.86 Surface Strain in Slab at First Debonding Point

Beam with 67% Debonding (Specimen Set 3)

Page 180: Debonding in Pretensioned Beams-Precast Strands, Part 2

152

Load

(Kips)

1200

Strain ( \i — )in

Figure 3.87 Surface Strain in Slab, at the Point LoadBeam with 67% Debonding (Specimen Set 3)

Page 181: Debonding in Pretensioned Beams-Precast Strands, Part 2

153-

oJ*to

a> as cl= = §

to

cm

2=3

s-_ j=S3

o*- 2

1^r

i

auT

<

i

3

eor

(Si

1

1

1

k

COa.a o

CO CM'

">^ 4

ic

i

o

'

Qi k

LM &LU

1f

LU i

Eto 4eo

k

o> as a.£ = §SJ5

ac

muon

cu

uucGO

co

uE3u

C53

C

£

usi

Q,

fc

co

c

00oocri

3

Page 182: Debonding in Pretensioned Beams-Precast Strands, Part 2

154

Load

(Kips)

60-

40

20

0^

Gage EDI

GageED2

-A— GageED3

GageED4

3000 6000 9000 12000 15000 18000

Strain ( p. — )in

Figure 3.89 Stirrup Strain, Beam with 0% Debonding(Specimen Set 3)

Page 183: Debonding in Pretensioned Beams-Precast Strands, Part 2

-155-

Load

(Kips)

4000

GageEAl

GageEA2

_A Gage EA3

GageEA4

8000

Strain ( u. — )

in

—I

12000 16000

Figure 3.90 Stirrup Strain, Beam with 67% Debonding

Specimen Set 3

Page 184: Debonding in Pretensioned Beams-Precast Strands, Part 2

-156

Load

(Kips)

"*"""*— \/*

140- / .*

120-

//

100 - ////

/f

80- ////

//60-

////ft

40- / y . Gage No. 13

Gage No. 14

20- Gage No. 15

oi i i l 1 1 1

100 200 300 400 500 600 700

Strain ( |i —• )

in

Figure 3.91 Strain in Slab Longitudinal Steel, 6.0 ft. From Support

Beam with 0% Debonding (Specimen Set 3)

Page 185: Debonding in Pretensioned Beams-Precast Strands, Part 2

-157-

Load

(Kips)

300

Strain ( a — )in

Gage No. 1

Gage No. 2

Gage No. 3

400 500

Figure 3.92 Strain in Slab Longitudinal Steel, at 6.0 ft. from Support

Beam with 67% Debonding (Specimen Set 3)

Page 186: Debonding in Pretensioned Beams-Precast Strands, Part 2

158

Load

(Kips)

2000 3000 6000

Strain (u— )in

Figure 3.93 Strand Strains, at 3.5 ft from Support

Beam with 0% Debonding (Specimen Set 3)

Page 187: Debonding in Pretensioned Beams-Precast Strands, Part 2

159-

Load

(Kips)

6500 6750 7000 7250 7500 7750

Strain ( |i — )in

8000

Figure 3.94 Strand Strains, at 6.0 ft. from Support

Beam with 0% Debonding (Specimen Set 3)

Page 188: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 160

Load

(Kips)

4500 5000 5500 6000 6500 7000 7500

Strain ( u. — )in

Figure 3.95 Strand Strains at the point Load

Beam with 0% Debonding (Specimen Set 3)

Page 189: Debonding in Pretensioned Beams-Precast Strands, Part 2

-161

5800 7000

Strain ( u. — )in

Figure 3.96 Strand Strain at First Debonding Point

Beam with 67% Debonding (Specimen Set 3)

Page 190: Debonding in Pretensioned Beams-Precast Strands, Part 2

162

Load

(Kips)

118

110-

100-

90-

80-

70-

60-

50

40-

30

20-

10-

3000

IP

PP

p

P

P

P

P

P

Gage EA3

...... Gage EA4

_^ Gage EA5

4500 6000

Strain (p.— )

in

7500 9000

Figure 3.97 Strand Strains at Second Debonding Point

Beam with 67% Debonding (Specimen Set 3)

Page 191: Debonding in Pretensioned Beams-Precast Strands, Part 2

163

Load

(Kips)

118

110-

100-

90-

80-

70-

60-

50-

40

30-

20-

10

3000

Gage EA8

Gage EA9

4500 6000

Strain ( p.— )

in

7500 9000

Figure 3.98 Strand Strains at at the Point LoadBeam with 67% Debonding (Specimen Set 3)

Page 192: Debonding in Pretensioned Beams-Precast Strands, Part 2

140-

120

164-

Load

(Kips)

100-

80-

60-

40-

20-

Gage No. 1

. Gage No.2

Gage No.3

-a Gage No.4

_A Gage No.5

0.0 0.1 0.2

Slip (inch)

0.3

Figure 3.99 Strand Slip, Beam with 0% Debonding

Specimen Set 3

0.4

Page 193: Debonding in Pretensioned Beams-Precast Strands, Part 2

-165

Load

(Kips)

80-

60-

40-

20-

0.0

Gage No. 1

Gage No. 2

Gage No. 3

_B Gage No. 4

_A Gage No. 5

0.1 0.2 0.3

Movement (inch)

0.4

Figure 3.100 Strand Movement, Beam with 67% Debonding

Specimen Set 3

Page 194: Debonding in Pretensioned Beams-Precast Strands, Part 2

166

CNJ

o>

03

ECOCDQQ

n in

**i i

CO

> k

CM

i i

Ic

33

i

J>

Bulkhead

/uc

1

3•J

'

• •

eo

®®

®

£

3

3

3

TO

WD

E

U

Cu

u&:/3

co£3u.

c/5

c

CMUEuj=u

00B

IUQ—c

c/3

B

Page 195: Debonding in Pretensioned Beams-Precast Strands, Part 2

167 -

CM

o09

ECOCD

re

a —

UJ QJ

E °

oa

I I

• •

nin

03

E

CMoo

ik IT5

1

TO

5 5

14

CO

O

uC/3

c

£'6oc

C/3

co

c

T3

so

c^5ccJQ

Q•aa73

QJ •-"

re on

•a

cc

r<~,

3ojo

Page 196: Debonding in Pretensioned Beams-Precast Strands, Part 2

-168

g

tu

a

uca

"S

CO

# eo*o .§

i Ica

Oh

M

uOC*1

g

Page 197: Debonding in Pretensioned Beams-Precast Strands, Part 2

169-

e3'atu

CQ

8co

Q 3

o cos

ex

Mu

o

HDA

Bh

Page 198: Debonding in Pretensioned Beams-Precast Strands, Part 2

170

Load

(Kips)

Deflection Under Load P (inch)

Figure 3.104 Load Deflection Relationship, Beam with 0% Debonding

(Specimen Set 4)

Page 199: Debonding in Pretensioned Beams-Precast Strands, Part 2

171

Load

(Kips)

i~ ~i r~ —\1

i i i r0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0

Deflection, 3.5 ft. from Support Centerline

Figure 3.105 Load Deflection Relationship, Beam with 0% Debonding

(Specimen Set 4)

Page 200: Debonding in Pretensioned Beams-Precast Strands, Part 2

172

Load

(Kips)

0.20 0.40 0.60 0.80

Deflection Under Load P (inch)

Figure 3.106 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 4)

Page 201: Debonding in Pretensioned Beams-Precast Strands, Part 2

173

Load

(Kips)

0.00 0.20 0.40 0.60 0.80 1.00

Deflection at the Second Debonding Point (inch)

Figure 3.107 Load Deflection Relationship, Beam with 50% Debonding

(Specimen Set 4)

Page 202: Debonding in Pretensioned Beams-Precast Strands, Part 2

174

Load

(Kips)

Strain ( ji — )in

800 1000

Figure 3.108 Surface Strain in Slab, 3.5 ft. from Support Centerline

Beam with 0% Debonding (Specimen Set 4)

Page 203: Debonding in Pretensioned Beams-Precast Strands, Part 2

175

Load

(Kips)

245

700

Strain ( u — )in

Figure 3.109 Surface Strain in Slab, at the Point Load

Beam with 0% Debonding (Specimen Set 4)

Page 204: Debonding in Pretensioned Beams-Precast Strands, Part 2

-176-

Load

(Kips)

Strain ( \i — )in

Figure 3.1 10 Surface Strain in Slab at First Debonding Point

Beam with 50% Debonding (Specimen Set 4)

Page 205: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 177 -

Load

(Kips)

1600

Strain ( a — )in

Figure 3. 1 1 1 Surface Strain in Slab at the Point Load

Beam with 50% Debonding (Specimen Set 4)

Page 206: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 178 -

245

225-

150 -;

Load

(Kips)

125 -j

100

75 -ji

50-

25-

Gage EDI

_ Gage ED2

A GageED3

GageED4

3000 6000

Strain ( |i — )in

9000 12000

Figure 3.1 12 Stirrup Strain, Beam with 0% Debonding

Specimen Set 4

Page 207: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 179-

Load

(Kips)

177

160

140-

120-

100-

80

60-4

40

20

GageEAl

Gage EA2

-a— GageEA3

Gage EA4

~I I I I I

^^ ^^ ^^1000 2000 3000 4000 5000 6000 7000 8000 9000

Strain ( jj. -:— )in

Figure 3.1 13 Stirrup Strain, Beam with 50% Debonding

Specimen Set 4

Page 208: Debonding in Pretensioned Beams-Precast Strands, Part 2

-180

a* Of '

03

ECOCDCD

v *

lit-

\

[JCM [|CO

»H * < »l< » *-* « »|« »[« » *+

« (D O

m10

"*

03

EC303

[]?

-Vi

[]? [1!?ii

o l« > < » « > « tjt » \* *\* p *>

< £

Page 209: Debonding in Pretensioned Beams-Precast Strands, Part 2

181

245

Load

(Kips)

Gage No. 15

Gage No. 14

Gage No. 13

100 200 300 400 500 600 700

Strain ( u. — )in

Figure 3.115 Strain in Slab Longitudinal Steel,at 6.0 ft. From Support

Beam with 0% Debonding (Specimen Set 4)

Page 210: Debonding in Pretensioned Beams-Precast Strands, Part 2

182

Load

(Kips)

177

160-

140-

120-

100-

80-

60-

40-

20-

2500

Strain ( j! — )in

Figure 3.1 16 Strain in Slab Longitudinal Steel, at 6.0 ft. from Support

Beam with 50% Debonding (Specimen Set 4)

Page 211: Debonding in Pretensioned Beams-Precast Strands, Part 2

183-

245

Load

(Kips)

1000

Gage EDI

Gage ED2

...... Gage ED3

_4 . Gage ED4

I

1

2000 3000 4000 5000

Strain ( \i— )in

6000

Figure 3.1 17 Strand Strains at 16 in. from Support

Beam with 0% Debonding (Specimen Set 4)

Page 212: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 184

Load

(Kips)

itj —r ?!

225-Oage. F.D7

GageEDIO '

1

ffj

200- ......... Gage ED11 j $ J/ w(

175- /;

f)

150-

i

1

i

i

*l

)

If

I

125- i

1i

i /

100-i

1

i

• I

75-

i

1

i

i

50-

i

1

l

i//

1

i

$

25- i

1

i

*

i

• i i

1 1 i

4500 4750 5000

Strain ( u — )in

5250 5500

Figure 3. 1 18 Strand Strains at 3.5 ft. from Support

Beam with 0% Debonding (Specimen Set 4)

Page 213: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 185 -

Load

(Kips)

245

225-

200-

175-

150-

125-

100-

75-

50-

25-

4000

Gage ED 12

Gage ED15

Gage ED16

»....GageED17

A Gage ED 18

I~ ^ I

4250 4500 4750 5000

Strain ( u.— )in

5250 5500

Figure 3.1 19 Strand Strains at 6.0 ft. from Support

Beam with 0% Debonding (Specimen Set 4)

Page 214: Debonding in Pretensioned Beams-Precast Strands, Part 2

186-

245

Load

(Kips)

4000 4500 5000

Strain ( u— )in

5500 6000

Figure 3.120 Strand Strains at the Point Load

Beam with 0% Debonding (Specimen Set 4)

Page 215: Debonding in Pretensioned Beams-Precast Strands, Part 2

187-

Load

(Kips)

5000 5125 5250

Strain ( n — )in

5375 5500

Figure 3.121 Strand Strains at 16 in. from Support

Beam with 50% Debonding (Specimen Set 4)

Page 216: Debonding in Pretensioned Beams-Precast Strands, Part 2

188

Load

(Kips)

177

160-

140-

120

100-

80-

60-

40-

20-

4000

n_ _ Gage EA9

GageEAl

1

i

m

4500 5000

Strain ( ^ — )

in

5500 6000

Figure 3.122 Strand Strains at First Debonding Point

Beam with 50% Debonding (Specimen Set 4)

Page 217: Debonding in Pretensioned Beams-Precast Strands, Part 2

189-

Load

(Kips)

177

160-

140-

120-

100-

80-

60-

40-

20-

4000

*

*

*

*

*

Gage EA12

GageEA14

GageEA15

. B .... GageEA16

_A Gage EA 17

_-*._ GageEA18

5000 6000 7000

inStrain ( u— )

in

Figure 3.123 Strand Strains at Second Debonding Point

Beam with 50% Debonding (Specimen Set 4)

Page 218: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 190-

Load

(Kips)

177

160-

140-

120-

100-

80-

60-

40-

20-

4000

Gage EA19

Gage EA21

GageEA22

.>.... Gage EA23

-A— Gage EA29

4500 5000

Strain ( (i — )in

5500 6000

Figure 3.124 Strand Strains at the Point LoadBeam with 50% Debonding (Specimen Set 4)

Page 219: Debonding in Pretensioned Beams-Precast Strands, Part 2

-191

Load

(Kips)

i 1 1 1 1 1 1

—~i

1 r

0.0 0.1 02 03 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1

Slip (inch)

Figure 3.125 Strand Slip, Beam with 0% Debonding

Specimen Set 4

Page 220: Debonding in Pretensioned Beams-Precast Strands, Part 2

192

Load

(Kips)

120-

100-

80-

60-

40-

20-

»+

-e-

Gage No. 1

Gage No.2

Gage No.3

Gage No.4

Gage No.5

Gage No.6

Gage No.7

Gage No.8

T T T0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9

Movement (inch)

1.0 1.1

Figure 3.126 Strand Movement, Beam with 50% Debonding

Specimen Set 4

Page 221: Debonding in Pretensioned Beams-Precast Strands, Part 2

-193-

i i i i

in

ra

aa

ik i

CD

k A

t11

^

/•vV

_ ^®mi

V^Eas

o mira

3^®_• »®®

_3/^®

mi

<*®

« nil

E

o09

1111ik ik

is

CVJ

ik

o

V

r-

"—\

V)0J

u5uu00

cc

tj qq «

c

£

-oc

u

uCO

bOC"5ccUQ-ac

3

Page 222: Debonding in Pretensioned Beams-Precast Strands, Part 2

194

Figure 3.128 Crack Pattern of 0% Debonded Beam at Failure

Specimen Set 5

Figure 3. 129 Web-Shear Cracking at Right Support of 0% Debonded BeamSpecimen Set 5

Page 223: Debonding in Pretensioned Beams-Precast Strands, Part 2

195

Figure 3.105 Flexure-Shear Cracking at Debonding Point

Specimen Set 5

Figure 3.131 Web-Shear Cracking at Left Support of 50% Debonded BeamSpecimen Set 5

Page 224: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 196-

Figure 3.132 Crack Pattern of 50% Debonded Beam at Failure

Specimen Set 5

Page 225: Debonding in Pretensioned Beams-Precast Strands, Part 2

197

Load

(Kips)

180- s^-^~~160-

140-

i in

/LZU —

100-

80-

/60- /

40- /

20- /

I i I I 1 1

0.0 0.5 1.0 1.5 2.0 2.5

Deflection Under Load P (inch)

3.0 3.5

Figure 3.133 Load-Deflection Relationship, Beam with 0% Debonding

(Specimen Set 5)

Page 226: Debonding in Pretensioned Beams-Precast Strands, Part 2

198 -

Load

(Kips)

0.0

Left Shear Span

Right Shear Span

0.5 1.0

Deflection (inch)

1.5 2.0

Figure 3.134 Load-Deflection Relationship at 7 ft. from Support

Beam with 0% Debonding (Specimen Set 5)

Page 227: Debonding in Pretensioned Beams-Precast Strands, Part 2

-199

Load

(Kips)

ID/ -

140- s^120-

f100-

J80- /

60- /

40- /

20- /

AU —1 1 1 1

0.0 0.5 1.0 1.5 2.0

Deflection Under Load P (inch)

2.5

Figure 3.135 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 5)

Page 228: Debonding in Pretensioned Beams-Precast Strands, Part 2

-200

157

140-

Load

(Kips)

Left Shear Span

Right Shear Span

11

0.25 0.50 0.75 1.00

Deflection at Debonding Points (inch)

1.25

Figure 3.136 Load-Deflection Relationship, Beam with 50% Debonding

(Specimen Set 5)

Page 229: Debonding in Pretensioned Beams-Precast Strands, Part 2

201-

Load

(Kips)

600

Strain ( (i— )in

Figure 3.137 Surface Strain in Slab at the 7 ft. from Support

Beam with 0% Debonding (Specimen Set 5)

Page 230: Debonding in Pretensioned Beams-Precast Strands, Part 2

202

Load

(Kips)

4000

Strain ( u.— )in

Figure 3.138 Surface Strain in Slab, at the Point Load

Beam with 0% Debonding (Specimen Set 5)

Page 231: Debonding in Pretensioned Beams-Precast Strands, Part 2

-203

Load

(Kips)

600

inStrain (11-)

in

Figure 3.139 Surface Strain in Slab, at Debonding Point

Beam with 50% Debonding (Specimen Set 5)

Page 232: Debonding in Pretensioned Beams-Precast Strands, Part 2

-204-

Load

(Kips)

2500

Strain ( (i— )

in

Figure 3.140 Surface Strain in Slab at the Point LoadBeam with 50% Debonding (Specimen Set 5)

Page 233: Debonding in Pretensioned Beams-Precast Strands, Part 2

-205-

oso*

Ecu

CM

-B-

-B-

f- = = a-

1— Ero

CO cu3O 00

3 oE sOo cuCO _JQ cu

533

1*r

r

i

iT

1

k

3

I

@

COf

i

1C

1

\.

COQ,s

to4k

3

CMt

N^*_ 1

1c

i.

3

T*r

Ot k

UJ

<"UJ

mCMr-

1c t

UJi

e

i

Ere 3

COir

C3

ra

CO

CU CU C3.

8->3

'J

soEun.

c

cu

•acca

£

ua:

3fc

55

EC

o

5

Page 234: Debonding in Pretensioned Beams-Precast Strands, Part 2

-206-

Load

(Kips)

200 400 600 800 1000 1200 1400 1600 1800

Strain ( p.— )

in

Figure 3.142 Stirrup Strain in Left Shear SpanBeam with 0% Debonding (Specimen Set 5)

Page 235: Debonding in Pretensioned Beams-Precast Strands, Part 2

207

Load

(Kips)

250 500 750 1000 1250 1500 1750 2000

Strain (p.— )in

Figure 3.143 Stirrup Strain in Right Shear Span

Beam with 0% Debonding (Specimen Set 5)

Page 236: Debonding in Pretensioned Beams-Precast Strands, Part 2

140-1

208-

T

Load

(Kips)

80-

GageEAl

Gage EA2

_A Gage EA3

....... GageEA4

250 500 750 1000 1250

inStrain

( (i— )

in

1500

Figure 3.144 Stirrup Strain in Left Shear SpanBeam with 50% Debonding (Specimen Set 5)

Page 237: Debonding in Pretensioned Beams-Precast Strands, Part 2

209-

•S • 2"

•. -c

[]">»•

[]'-

[ ]«>

|](M

[ 1<B

[)CO

w TITps p: CO

racs c

—i

E CD

CO —COCO CO

ra (Q

IT)

s

cu

uu

c_o

3cuS

uuGO

"3c-5

'SbcoJ-O_2c/3

in

3so

Page 238: Debonding in Pretensioned Beams-Precast Strands, Part 2

-210

Load

(Kips)

Gage No. 1

a Gage No.2

GageNo.3

600 700

Strain ( \i— )

in

Figure 3.146 Slab Steel Strain in Left Shear Span

Beam with 0% Debonding (Specimen Set 5)

Page 239: Debonding in Pretensioned Beams-Precast Strands, Part 2

-211

Load

(Kips)

, GageNo.4

A Gage No.5

.. GageNo.6

600 700

Strain ( (J. — )in

Figure 3.147 Slab Steel Strain in Right Shear Span

Beam with 0% Debonding (Specimen Set 5)

Page 240: Debonding in Pretensioned Beams-Precast Strands, Part 2

212

Load

(Kips)

Gage No. 1

4 Gage No.2

Gage No.3

600 700

Strain ( y.— )in

Figure 3.148 Slab Steel Strain in Left Shear Span

Beam with 50% Debonding (Specimen Set 5)

Page 241: Debonding in Pretensioned Beams-Precast Strands, Part 2

213

157

140-

120-

100-

Load

(Kips)

Gage No.4

^ Gage No.5

GageNo.6

Strain ( u.— )

in

500

Figure 3.149 Slab Steel Strain in Right Shear Span

Beam with 50% Debonding (Specimen Set 5)

Page 242: Debonding in Pretensioned Beams-Precast Strands, Part 2

-214

Load

(Kips)

196

180-

160-

140-

120-

100

80-

60-

40

20-1

T

Gage EDI

GageED3

_A Gage ED6

T T T3000 3500 4000 4500 5000 5500 6000 65

Strain ( (i— )

in

00

Figure 3.150 Strand Strain at 20 in. from Support EDBeam with 0% Debonding (Specimen Set 5)

Page 243: Debonding in Pretensioned Beams-Precast Strands, Part 2

- 215 -

Load

(Kips)

4000 5000 6000 7000

in

8000 9000

Strain ( |i -^-)

in

Figure 3.151 Strand Strain at 42 in. from Support EDBeam with 0% Debonding (Specimen Set 5)

Page 244: Debonding in Pretensioned Beams-Precast Strands, Part 2

216

Load

(Kips)

i 1 1 1 1 r

4000 4500 5000 5500 6000 6500 7000 7500 8000

Strain ( |i— )

in

Figure 3.152 Strand Strain at 84 in. from Support EDBeam with 0% Debonding (Specimen Set 5)

Page 245: Debonding in Pretensioned Beams-Precast Strands, Part 2

217 -

Load

(Kips)

5000

Gage ED 19

A Gage ED20

10000 15000 20000

Strain ( u— )

in

Figure 3.153 Strand Strain at the Point Load

Beam with 0% Debonding (Specimen Set 5)

Page 246: Debonding in Pretensioned Beams-Precast Strands, Part 2

218

Load

(Kips)

2000 2500 3000 3500 4000 4500

inStrain ( |i— )

in

5000

Figure 3. 154 Strand Strain at 20 in. from Support IC

Beam with 0% Debonding (Specimen Set 5)

Page 247: Debonding in Pretensioned Beams-Precast Strands, Part 2

219

Load

(Kips)

196 -r

180-

160-

140-

120-

100-

80-

60-

40-

20-

r

—\—3500 4000

Gage IC7

_A Gage IC9

GageIC12

4500—I

5000T T

inStrain ( u.— )

in

5500 6000 6500

Figure 3.155 Strand Strain at 42 in from Support IC

Beam with 0% Debonding (Specimen Set 5)

Page 248: Debonding in Pretensioned Beams-Precast Strands, Part 2

-220

Load

(Kips)

4000 5000 6000 7000 8000

inStrain ( (i — )

in

9000

Figure 3. 156 Strand Strain at 84 in. from Support ICBeam with 0% Debonding (Specimen Set 5)

Page 249: Debonding in Pretensioned Beams-Precast Strands, Part 2

221

Load

(Kips)

157

140-

120-

100

80-

60

40-

20-

4000

GageEAl

-A Gage EA2

GageEA3

4200 4400 4600 4800

inStrain ( u.— )

in

Figure 3.157 Strand Strain at 20 in from Support EABeam with 50% Debonding (Specimen Set 5)

Page 250: Debonding in Pretensioned Beams-Precast Strands, Part 2

-222-

Load

(Kips)

157

140-

120-

100-

80-

60-

40-

20

5000

Gage EA5

-A Gage EA6

5500 6000

Strain( fi — )

in

6500 7000

Figure 3.158 Strand Strain at 42 in. from Support EABeam with 50% Debonding (Specimen Set 5)

Page 251: Debonding in Pretensioned Beams-Precast Strands, Part 2

223

Load

(Kips)

157

140-1

120

100

80-

60-

40-

20

4500

Gage EA7

a Gage EA8

5500 6500

Strain ( u.— )in

7500 8500

Figure 3.159 Strand Strain at Left Debonding Point

Beam with 50% Debonding (Specimen Set 5)

Page 252: Debonding in Pretensioned Beams-Precast Strands, Part 2

-224

Load

(Kips)

157

140-

120-

100-

80-

60-

40-

20-

2000

Gage EA 11

A Gage EA 14

GageEAlS

4000 6000 8000 10000

inStrain ( u.— )

in

Figure 3.160 Strand Strain at the Point Load

Beam with 50% Debonding (Specimen Set 5)

12000

Page 253: Debonding in Pretensioned Beams-Precast Strands, Part 2

225

Load

(Kips)

157

140

120-

100-

80-

60-

40-

20

2500

Gage IB 1

^, Gage IB2

2750 3000 3250

in

3500 3750

Strain ( [i— )in

Figure 3.161 Strand Strain at 20 in. from Support IB

Beam with 50% Debonding (Specimen Set 5)

Page 254: Debonding in Pretensioned Beams-Precast Strands, Part 2

-226-

Load

(Kips)

157

140-

120-

100-

80-

60

40-

20-

5200 5600

Gage IB4

_A Gage IB 5

GageIB6

6000

in

/

6400

Strain ( (I— )

in

Figure 3.162 Strand Strain at 42 in. from Support IB

Beam with 50% Debonding (Specimen Set 5)

Page 255: Debonding in Pretensioned Beams-Precast Strands, Part 2

-227

Load

(Kips)

3500 4500 5500 6500 7500 8500

inStrain ( \i— )

in

Figure 3.163 Strand Strain at Right Debonding Point

Beam with 50% Debonding (Specimen Set 5)

Page 256: Debonding in Pretensioned Beams-Precast Strands, Part 2

228-

Load1

(Kips)

196

180

160

140-

120-

1

100-

80-

60-

40

20-|

Gage No. 1

Gage No.2

Gage No.4

I 1 I

0.00 0.01 0.02 0.03

Slip (inch)

0.04 0.05

Figure 3.164 Strand Slip, Beam with 0% Debonding

Specimen Set 5

Page 257: Debonding in Pretensioned Beams-Precast Strands, Part 2
Page 258: Debonding in Pretensioned Beams-Precast Strands, Part 2