deep water windfarms seminar - marine scotlandmarine.gov.scot/datafiles/misc/mrep/10/documents/deep...
TRANSCRIPT
Deep Water Windfarms Seminar
Turbine Design Developments for Deep Water Projects
Ranjit MeneREpower UK
25th September 2013
2
Agenda
Introduction
Conclusions
REpower‘s Approach to Deep Water Projects
3
Agenda
Introduction
Conclusions
REpower‘s Approach to Deep Water Projects
4
Beatrice (UK)
2 x 5M126(10 MW)
Ormonde (UK)
30 x 5M126(150 MW)
Thornton Bank I
(Belgium)
6 x 5M126(30 MW)
Alpha Ventus
(Germany)
6 x 5M126(30 MW)
Thornton Bank II & III(Belgium)
48 x 6M126(295 MW)
Nordsee Ost
(Germany)
48 x 6M126(295 MW)
Innogy Nordsee I(Germany)
54 x 6M126(332 MW)
Project (Germany)
80 x 6M126(492 MW)
2006-2007 2008-2009 2009-2010 2011-2012 2012-2013 2014
Preferred supplier
2016-20172015
FID pending
Repower Offshore Project References
5
Thornton Bank Wind Farm – Key Facts
Three Phases (54 REpower WTGs):Phase 1: 6 x 5M (2008)Phase 2: 30 x 6M (2012)Phase 3: 18 x 6M (2013)
Total Capacity: 325.2 MW
Location: 30 km from the Belgian coast line, 12 – 27 m water depth
Client: C-Power (Consortium comprising of RWE, EdF, Marguerite, DEME, SRIW, Socofe, and Nuhma)
Entirely project financed
First industrial-scale offshore project in the world using 6MW turbines
Gravity base foundations used in Phase 1; Jackets in Phases 2 & 3
6
Cost reduction for Round 3 is imperative if we want the ambitious 2020 renewables targets to be acheived
Duddon Sands (UK)
2003 2005 2007 2009 2011 2013 2015 2017
0,5
1,0
1,5
2,0
2,5
3,0
3,5
4,0
4,5
5,0
5,5
Alpha Ventus (D)
THB 1 (B)
Belwind 1 (B)
Greater Gabbard (UK)
Thanet (UK)Rhyl Flats (UK)
THB 2+3 (B)
NSO (D)
Cost per MW installed (€m/MW)
COE ~ €170/MWh
Rödsand 2 (DK)Robin Rigg (UK)
Gunfleet Sands (UK)
Lynn (UK)
Burbo (UK)
Barrow (UK)
Kentish (UK)
Scroby Sands (UK)
North Hoyle (UK)Future Projects (D/UK)
Year2019
COE ~ €120/MWhor ~ £100/MWh
The last of the EPCI contracts
Rising commodity pricesSupply chain shortagesExchange rate movements
7
However, we need to be clear which costs we are talking about
Cost Parameter Biggest Influence on Cost Reduction
Levelised Cost of Energy (GBP/MWh)
• Turbine Yield• Capital Costs (BoP, Turbine)
NPV (GBPm) or IRR (%) • Electricity Remuneration• Turbine Yield
Cost per Installed MW (GBP/MW)
• Capital Costs (BoP, Turbine)
8
Agenda
Introduction
Conclusions
REpower‘s Approach to Deep Water Projects
9
Turbines need to evolve to take advantage of deep water sites
Failure frequency
High
Low
highlow
high
LowEnergy yield
System price
1
2
3
10
Increasing the yield of the well-proven 6M126 turbine requires a focus on the rotor as well as availability
Larger rotor
Blade length increases to 150m+Turbine rating remains the same
1
Lower risk
New turbine model based on the proven, bankable technology found in the 6M126~80% of components remain the sameInterface with suitable foundation types
Increased availability
Next-generation access technologies allow greater access throughout the yearAdvanced Condition Monitoring systems built inOptimal service concept
152
+ +
1 Copyright Houlder
1
11
Making turbines more reliable needs experience
Design failure mode analysisHighly accelerated lifetime testing can spot potential weaknesses in design
2
End-of-line
testing
CMS
Operational
experience
DFMEA
analysis
Increased
reliability
Optimised service conceptLearning curve effects reduce the number of unplanned service eventsRobust quality procedures need to be in place
Sophisticated condition monitoring sensorsAllows remote intervention of all but the most serious issues
Quality checks at production facility outletEnsures turbine arrives at lay-down port ready to ‘plug and play’
12
We are looking at six main levers for driving down capital costs
3
Levers for lower capex Requirements
Industrialisation • Certainty of pipeline• Political support
Early project-specific optimisation
• Early engagement with developers
Reduced interface risks • Strong collaboration within the supply chain
Redesign of some components
• Strong engineering support• Good relationship with
suppliers
Localisation of production saves on logistics costs and good politically
• Development of local supply chain
Needs Developer
support
13
Industrialisation and innovation are key to reducing the LEC
Comments
Industrialisation and innovation are key to reducing LEC in the offshore wind sectorStandardisation of large components such as foundations is criticalInnovative solutions need support from the entire supply chainIt all starts with market certainty...
Source: Carbon Trust - “Offshore Wind: Big Challenge, Big Opportunity” (2008)
14
LEC
The balance of plant costs need to be optimised as well to lower the LEC of the whole project
BoP
TurbineO&M
I&C
Foundations
Electrical Systems
Cables
15
Example: Methods for foundation cost reduction typically involve decreasing the fabrication and installation costs
Methods Mechanism
Reduce steel Optimise structures for depth, soils
Increase vessel utilisation
Increase weather windowLarger vessels Shuttling
Cheaper manufacturing
Mass production and standardisation
Reduce vessel hire Fewer repositionsMinimise operations at sea
Eliminate vessels Integrated installation
Focus
Reduction of
Fabrication
Costs
Reduction of
Installation
Costs
Early engagement with turbine manufacturers crucial
16
Agenda
Introduction
Conclusions
REpower‘s Approach to Deep Water Projects
17
Conclusion
17
Greater deployment of state-of-the-art offshore turbines needs the following
The UK government needs to Provide certainty to developersEnsure that the UK becomes renewables friendlyPromote innovation in the offshore wind sector, e.g. the OWA, demonstration sites for new foundations and turbines
Developers need to Provide certainty to the Tier 1 suppliers: Turbine OEMs, Installation contractors, Foundation manufacturers, Electrical contractorsBe open to alternatives in project execution methods, technology, risk sharing etc
The Tier 1 suppliers need to contribute to the reduction in LEC by InnovatingStandardisingOptimisingLocalising
18
© REpower Systems SE
All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photography, recording, or any information storage and retrieval system, without permission from REpower Systems SE.