Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel Gereklilikler Defne Arısoy, Kıdemli Çevre Mühendisi

Upload: others

Post on 19-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

DEK TANAP AKADEMİAnkara, Nisan 2019

Projenin Lender Süreci ve ÇevreselGereklilikler

Defne Arısoy,Kıdemli Çevre Mühendisi

Page 2: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

* TANAP’ınpolitika veyönetim sistemidokümanları* Mühendislikdokümanları/sahadokümanları

Hükümetler arasısözleşmeler

Türkiye’nin taraf olduğu ilgili Uluslararası Anlaşmalar

Türkiye’deki ilgili mevzuat

Uluslararası Gereklilikler

• İmza tarihi: 26 Haziran 2012.Resmi Gazete; 13 Mart 2013.

DestekleyiciDokümanlar;

Proje’nin yaşamdöngüsüsürecinde

* KrediKuruluşlarınınGereklilikleri; IFC, EBRD, EIB, EkvatorPrensipleri, DünyaBankasıGereklilikleri

TANAP Dokümanları

Proje’nin itici güçleri

Page 4: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Kredi Kuruluşları ile ilgili son durum

Banka Tarihçe Mevcut durum Tamamlanan ve devam eden aksiyonlar

IBRD/AIIB 2016 yılındaimzalandı.

2 uygulama misyonu/yıl Bağımsız Çevre & Sosyal & İş Salığı GüvenliğiİzlemesiYeniden Yerleşim Eylem Planı (iç izleme & bağımsız izleme) ve uygulamalarıBalıkçılık Gelir Kaybını Önleme Planı veUygulamalarıYer Üstü Tesisleri için Geçim Kaynaklarını Geri Kazandırma Planı ve UygulamalarıYeniden Yerleşim Eylem Planı KapanışDenetimiOperasyonel Çevre & Sosyal & İş Sağlığı veGüvenliği Yönetim Sistemi DokümanlarıBiyoçeşitlilik Dengeleme Yönetim Planı

EBRD 2017 yılındaimzalandı.

Uluslararası Bağımsız DanışmanEkibi ile birlikte izlemelere katılım. İzleme raporları TANAP web sitesinde yayınlanmaktadır.

EIB Ön inceleme-gözdengeçirme sürecitamamlandı.Projemiz için EIB Kurul onayı alındı.

Uzlaşmalar devam etmektedir.

MIGA/Citibank/KfW, EH, UfKetc.

2018 yılındaimzalandı.

Citibank ve MIGA saha ziyeretleriyaptı. MIGA Uluslararası BağımsızDanışman ziyaretine katılım sağladı.

Page 5: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

2015’den itibaren Proje’ye dahil olan

Kredi Kuruluşlarının Ziyaret ettiği

Sahalar

Page 6: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Kredi Kuruluşlarının Yürüttüğü

İzleme Çalışmaları

Banka Nasıl izliyor? Neyi izliyor? Nasılraporluyor?

Ek eylem takibi

IBRD/AIIB Misyon Ziyaretleri Onaylı Çevre veSosyal Eylem PlanıDünya Bankası Çevreve Sosyal Kriterleri

Kendi içiraporlamalarıve /Action requests with deadlines

* Bağımsız izleme ekibi (3 ayda bir)* Zamanında çalışmaların tamamlanması vepaylaşılması

EBRD EBRD Çevre/ Sosyal/BiyoçeşitlilikUzmanları yoluylaBağımsız izlemedanışmanıziyaretlerine katılım

Onaylı Çevre veSosyal Eylem PlanıEBRD Çevre veSosyal GereklilikleriTANAP YıllıkRaporları

Danışmanraporları veraporlarınyayınlanmasızorunluluğu

• Onaylı Çevre ve Sosyal Eylem Planıdoğrultusunda zamanında çalışmalarıntamamlanması ve paylaşılması

• Yıllık raporlarla

EIB Ön inceleme-gözdengeçirme çalışmasıtamamlandı. Web sitesinde yayınlandı.

- - * Yıllık raporlarla

MIGA/Citibank/KfW, EH, UfK etc.

Citibank & MIGA Çevre ve SosyalUzmanları

Onaylı Çevre veSosyal Eylem PlanıMIGA Çevre veSosyal GereklilikleriEkvator Prensipleri

- • Onaylı Çevre ve Sosyal Eylem Planıdoğrultusunda zamanında çalışmalarıntamamlanması ve paylaşılması

• Yıllık raporlarla

Page 7: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Halka açılan ÇSED Paketi

Dokümanlar Durum Yorumlar Tarih

Biyoçeşitlilik EylemPlanı, BAP

Ek doküman olarak BOS hazırlandı ve TANAP web sitesinde yayınlandı

- -

BiyoçeşitlilikDengeleme Stratejisive Yönetim Planı, BOS/BOMP

Biyoçeşitlilik Uzmanıtarafından saha çalışmalarıtamamlandı.

BOMP devamediyor

2019 (2020-2040) uygulama

Çevre ve SosyalYönetim Planı

İşletme dönemi Çevre veSosyal Yönetim Sistemi

- -

Değişiklik Yönetimi Tamamlandı;Kamp sahalarıGüzergah Değişiklikleriİletim hatlarıDeniz geçişi

- -

Page 9: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

İzleme

Yönetim Planlarının Takibi

Yönetim Planları

Önlemlerin alınması için system oluşturma ve performans göstergeleri doğrultusunda takip

Yayınlama

Halka duyurma ve halkın katılımıHalktan gelen yorumlarla ÇSED’in

tamamlanması

Yönetim Planları

Önlem belirleme Önemli etkiler için Yönetim Planları

Etki Değerlendirme

Etki Analizi Etki Değerlendirme

Mevcut Durum ÇalışmalarıMevcut durum very toplama ve ikincil very

toplamaMevcut durum raporlama

Kapsam Belirleme

Bakanlık tarafından format belirlenmesi Proje Kapsam Değerlendirme Raporu

Çevre ve Sosyal Gözden Geçirme–

Aşamalı yaklaşım

Page 10: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

ÇSED:

• Çınar (Yerel Danışman)

• Golder (Küresel Danışman)

• ERM (Kredi Kuruluşları Gereklilikleri Danışmanı)

• Bechtel, Ön Mühendislik Aşaması

• Worley Parsons, Detay Mühendislik aşaması

ÇSED Sürecindeki Yapılanma

Page 11: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

ÇSED Aşaması

10 yeni tür

246 istasyonda karasal bitki

133 istasyonda amfibiler

243 istasyonda karasalomugasızlar

189 istasyonda sucul habitatlarda

Biyoçeşitlilik Eylem Planı

67 Karasal

27 Sucul Kiritik Habitat

Biyoçeşitlilik Dengeleme Stratejisi

SOSYAL

Anketler ve Halk toplantıları

• 513 muhtar anketi

• 2253 ev anketleri

• 307 odak grup toplantıları

• 151 detay görüşmeler

• 63 halkın katılımı toplantıları

Paydaş Katılım Planı

Yeniden Yerleşim Eylem Planı

Geçim Kaynaklarını Geri KazandırmaPlanı

Şikayet mekanizması

106 Güzergah seçimindekeşfedilen alanlar

48 yeni arkeolojik alan, inşaatsürecinde

EKOLOJİK ARKEOLOJİKFİZİKSEL

Toz 162 noktada

Emisyon 40 noktada

Gürültü ve titreşim 69 noktada

Toprak kirliliği 105 istasyonda

Yüzey suyu ölçümleri 327 noktada, ıslak dönem, 218 noktada kurudönem

Yeraltısuyu 37 noktada

Page 12: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

500 M KORİDORDA

20 İLDEN GEÇEN

Türkiye’deki ilk örnek: EUNIS Seviye 3

Habitat Haritaları

Page 13: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

ÇSED Onayı ve İzleme

İzlemeler; Bakanlık, Dünya Bankası ve INEA

EIA Positive Decision

24 July 2014

1. Monitoring Period

July – October 2014

3. Monitoring Period

January – April 2015

2. Monitoring Period

October 2014 – January 2015

4. Monitoring Period April

– July 2015

5. Monitoring Period

July – October 2015

6. Monitoring Period

October 2015 – January 2016

7. Monitoring Period

January – April 2016

8. Monitoring Period

April – July 2016 10. Monitoring Period

October 2016 – January

2017

9. Monitoring Period

July – October 201611. Monitoring Period

January-April 2017

12. Monitoring

Period

April-July 2017

13. Monitoring Period

July-October 2017

Page 14: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

TNP-REG-ENV-GEN-004 PROJECT ENVIRONMENTAL & SOCIAL IMPACTS REGISTER

TNP-REG-ENV-GEN-003 PROJECT ENVIRONMENTAL & SOCIAL COMMITMENTS REGISTER

TNP-PCD-ENV-GEN-004 ENVIRONMENTAL ASPECT AND IMPACT PROCEDURE

TNP-PLN-ENV-GEN-004 ENVIRONMENTAL TRAINING PLAN

TNP-REG-ENV-GEN-002 ESIA REPORT ENGLISH VERSION MODIFICATION REGISTER

TNP-PLN-ENV-GEN-001 ENVIRONMENTAL & SOCIAL MANAGEMENT PLAN

TNP-PLN-ENV-GEN-003 ENVIRONMENTAL MONITORING PLAN

TNP-PLN-ENV-GEN-002 ENVIRONMENTAL ACTION PLAN

TNP-PCD-ENV-GEN-003 PROCEDURE FOR ENVIRONMENTAL MANAGEMENT OF TANAP OFFICES

TNP-PCD-ENV-GEN-002 ENVIRONMENTAL MANAGEMENT OF CHANGE PROCEDURE

TNP-PCD-ENV-GEN-001 ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT PROCEDURE

TNP-REP-ENV-GEN-002 ESIA REPORT (ENGLISH)

TNP-REP-ENV-GEN-001 CED RAPORU (TURKISH)

TNP-REG-ENV-GEN-001 ESIA REPORT MODIFICATIONS REGISTER

TNP-PCD-ENV-GEN-003 PROCEDURE FOR ENVIRONMENTAL MANAGEMENT OF TANAP OFFICES

TNP-PCD-ENV-GEN-002 ENVIRONMENTAL MANAGEMENT OF CHANGE PROCEDURE

TNP-PCD-ENV-GEN-001 ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT PROCEDURE

Çevre ve

Sosyal

Yönetim

Sistemi

Kurulumu

Page 15: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Organizasyonel Yapı

Sektörden Profesyoneller;

• Petrol ve Doğalgaz sektörü;

• İnşaat Sektörü;

• Yapımı tamamlanan BTC Boru Hattı

deneyimli

• Yapımından vazgeçilen Nabucco Boru Hattı

Deneyimli

Nabucco

BTC

Page 16: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Organizasyonel Yapı

Çevre

Page 17: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Organizasyonel Yapı

Sosyal

Page 18: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Çevre ve Sosyal Uyum Değerlendirme

Page 19: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Plansız Saha Kontrolleri

Page 20: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Saha Mühendislerinin İzleme ve Raporlamaları

Page 21: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Page 22: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Kritik Habitat 38 Çalışmaları öncesi çalışan bilgilendirme

toplantıları

Page 23: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Page 24: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Yeraltısuyu Kullanımında Sürdürülebilirlik Takibi

Alan Kamp sahaları Sorumlu Ne yapıldı?

Lot 1 2 Kamp TANAP Raporlar Dünya Bankası’nagönderildi.

Lot 2 1 Kamp Müteahhit Raporların Banka kriterleridoğrultusunda oluşturulmasısağlandı.

Lot 3 0 - -

Lot 4 1 Kamp Müteahhit Raporların Banka kriterleridoğrultusunda oluşturulmasısağlandı.

İstasyonlar 3 istasyon Müteahhit Raporların Banka kriterleridoğrultusunda oluşturulmasısağlandı.

Page 25: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline ProjectTrans Anatolian Natural Gas Pipeline Project

İnşaat Alanı Uyarı Ceza

Lot 1 - -

Lot 2 - -

Lot 3 - -

Lot 4 - -

İstasyonlar - -

Deniz geçişi - -

Kredi Kuruluşlarına sunulan Kamu

Kurumları Nezdinde Değerlendirme

Page 26: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Sorunlu Başlıklar / İleri Aşama

Çalışmalar

• Evsel Atık Yönetimi – Düzenli Depolama

Alanlarının Kullandırılması/Mesafe

• Biyoçeşitlilik Eylem Planı - Kritik

Habitatlarda tohum toplama etkinliği

• Bitkisel Toprak Muhafazası

• Güzergah dışına taşma

Page 27: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

İşletme Dönemi takipleri

İnşaat Müteahhitleri;

• 2 yıl süresince izleme ve raporlama

İşletme Müteahhitleri;

• Uluslararası kiriterlerin ÇSED

gereklilikleri ve yasal mevzut

doğrultusunda takibi

İşveren;

• İnşaat Müteahhitleri Raporlarının Takibi

• İşletme Dönemi Bağımsız Çevre İzleme

• Yeniden Yerleşim Planı Bağımsız

İzleme/Kapanış Denetimi

• Bankalar (Kredi Kuruluşları) adına

yapılan Bağımsız Çevre, Sosyal, İş

Sağlığı ve Güvenliği İzlemesi

Page 28: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

Projenin Biyoçeşitlilik Stratejisi-

Biyoçeşitlilik Dengeleme (Ofset) Yönetim

Planı

-Planning based on ESIA/BAP i.e.March Charts

Plans, procedures, method statements

Method statements, biorestoration monitoring

Biodiversity Offset Management Plan

Page 29: DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender ... · Trans Anatolian Natural Gas Pipeline Project DEK TANAP AKADEMİ Ankara, Nisan 2019 Projenin Lender Süreci ve Çevresel

Trans Anatolian Natural Gas Pipeline Project

BOMP Uygulama Adımları

TANAP PROJESİ – BOMP• ANA ÇIKTILAR:

• Task 1:

• C) NET KAYIP HESABI (Q1 2019)

• Task 2:• A) POTANSİYEL OFSET ALANLARI LİSTESİ

(2018)

• Task 3:

• B) POTANSİYEL PAYDAŞLARIN LİSTESİ(2018)

• D) ÖN OFSET PROJELERİNİN BELİRLENMESİ (Q2 2019)

• E) NET KAZANÇ HESABI (Q3 2019)

• F) BELİRLENEN OFSET PROJELERİNİN PLANLARININ OLUŞTURULMASI(Q4 2019)