delaware energy efficiency investment fund program ... energy efficiency investment fund program...
TRANSCRIPT
Delaware Energy Efficiency Investment Fund
Program Guidelines and
Operational Procedures
Version 2017.1
Effective November 2017
Table of Contents
1.0 Purpose..................................................................................................................... 4
2.0 Statutory Authority ................................................................................................ 4
3.0 Energy Efficiency Investment Fund Statute and Appropriation ....................... 4
4.0 Delaware Energy Efficiency Investment Fund..................................................... 5
4.1 General Provisions ............................................................................................................... 5
4.1.1 Pre-Approval ..................................................................................................................... 5
4.1.2 Inspections ........................................................................................................................ 6
4.1.3 Invoices and Other Final Documentation .......................................................................... 6
4.1.4 Program Limits.................................................................................................................. 6
4.1.5 State Energy Program Revolving Loan Fund ................................................................... 7
4.2 Eligibility .............................................................................................................................. 7
4.3 Permits .................................................................................................................................. 7
4.4 Installing Contractor Guidelines........................................................................................... 8
4.4.1 Education and Licensure ................................................................................................... 8
4.4.2 Insurance Requirements .................................................................................................... 8
4.4.3 Statement of Reliability and Good Standing ..................................................................... 8
4.4.4 Limitation of Funds ........................................................................................................... 8
4.4.5 Participating Contractor List ............................................................................................. 8
4.4.5.1 Eligibility .................................................................................................................. 9
4.4.5.2 Application Requirements ...................................................................................... 10
4.4.5.3 Application Process ................................................................................................ 10
4.5 Warranty ............................................................................................................................. 11
4.6 Code Compliance ............................................................................................................... 11
5.0 Delaware Energy Efficiency Investment Fund Pathways ................................. 12
5.1 Prescriptive Pathway Grants .............................................................................................. 12
5.1.1 Prescriptive Grant Limits ................................................................................................ 12
5.1.2 Prescriptive Accepted Products and Equipment ............................................................. 13
5.1.3 Prescriptive Application Process ..................................................................................... 13
5.1.4 Prescriptive Application Timeline .................................................................................. 14
5.1.5 Prescriptive Application Requirements ........................................................................... 16
5.2 Custom Pathway Grants ..................................................................................................... 17
5.2.1 Custom Grant Limits ....................................................................................................... 17
5.2.2 Accepted Custom Products and Equipment .................................................................... 17
5.2.3 Custom Application Process ........................................................................................... 18
5.2.4 Custom Application Review Process .............................................................................. 19
5.2.5 Custom Application Timeline ......................................................................................... 21
5.2.6 Custom Application Requirements ................................................................................. 21
5.3 Energy Assessment Grants ................................................................................................. 21
5.3.1 Energy Assessment Grant Limits .................................................................................... 21
5.3.2 Accepted Audits .............................................................................................................. 22
3
5.3.2.1 Single Purpose or Targeted Energy Audit .............................................................. 22
5.3.2.2 Comprehensive Audit ............................................................................................. 22
5.3.3 Energy Assessment Application Process ........................................................................ 22
5.3.4 Energy Assessment Application Timeline ...................................................................... 23
5.4 Combined Heat and Power Grant Pathway ........................................................................ 23
5.4.1 CHP Grant Limits ........................................................................................................... 24
5.4.2 CHP Eligible Products and Equipment ........................................................................... 24
5.4.3 CHP Application Process ................................................................................................ 25
5.4.4 CHP Application Review Process ................................................................................... 26
5.4.5 CHP Application Timeline .............................................................................................. 27
5.4.6 CHP Application Requirements ...................................................................................... 27
6.0 Proprietary Application Information ................................................................. 29
7.0 Retirement and Disposal ...................................................................................... 29
8.0 Dispute Resolution ................................................................................................ 29
9.0 Tax Liability .......................................................................................................... 29
4
1.0 Purpose
The purpose of these guidelines is to define procedures relating to the Energy Efficiency
Investment Fund (EEIF). The goal in establishing these guidelines is to provide a
streamlined procedure for administering and distributing program funds.
These guidelines provide rules of practice and procedures for grant applications and
disbursement of grants for energy efficiency projects in Delaware.
2.0 Statutory Authority
These guidelines are disseminated under authority of 29 Delaware Code, Section 8030.
3.0 Energy Efficiency Investment Fund Statute and Appropriation
Senate Bill 129 which amended Title 29, §8030 and Title 30 §5502 of the Delaware Code
establishes the Energy Efficiency Investment Fund. The State shall transfer in each fiscal
year the first $5,000,000 in tax receipts received under Title 30 Chapter 55 that would
otherwise be deposited to the General Fund to the Energy Efficiency Investment Fund
(EEIF) maintained by the Department of Natural Resources and Environmental Control
(DNREC) pursuant to Chapter 80 of Title 29.
The EEIF program promotes the use of energy efficient technologies by Delaware non-
residential (commercial and industrial) customers that are users of gas or electricity whose
purchase of those commodities from a distributor is subject to the public utility tax on gas
or electricity. For more information on who pays the public utility tax, please see the
Public Utilities chapter of the Delaware State Code (30 Del.C. Chapter 55).
According to Title 29 §8030, DNREC shall give preference to those applications
proposing projects that are anticipated to produce the greatest reduction in energy
consumption per Fund dollar invested, improve environmental performance, spur capital
construction and facility modernization, encourage job retention and creation, and are
likely to be substantially complete no later than one year following the issuance of
financing from the Fund.
DNREC is the designated recipient and administrator of several funding streams, each
having specific disbursement requirements and customer eligibility. EEIF is funded in part
by the public utility tax (PUT), Regional Greenhouse Gas Initiative (RGGI) and lastly,
funding as a result of the recent merger between Exelon Corp and Pepco holdings.
Funds from the public utility tax are required for the benefit of the energy consumers that
pay for the funds. Two of the funding sources are RGGI, which is a mandatory market-
based program among 11 states including Delaware to reduce greenhouse gas emissions.
DNREC receives RGGI funding from the state selling emission allowances through
auctions to be used for investment in energy efficiency. DNREC has elected to utilize a
5
portion of the RGGI proceeds to fund EEIF in the absence of PUT funding. However, if
PUT funding is not restored, the programs offered will be reconsidered. The SEU has also
elected to provide DNREC with a portion of their RGGI funds to administer the EEIF
program.
Part of the agreement involving the merger between Exelon Corp and Pepco holdings
resulted in funds to be distributed to Delaware from the new company. The
Delaware Public Service Commission approved the allocation of $16,000,000 to be set
aside as an endowment fund for use as directed by DNREC for energy-efficiency
programs. $8,000,000 is to be allocated to the EEIF program under these guidelines.
The second $8,000,000 is to be allocated toward an industrial/large commercial grant or
loan fund to Delmarva Power’s large commercial and industrial customers. This program
will be called Delaware Energy Efficiency Industrial (E2I), and will be a grant program.
The E2I Program will be available to Delmarva large energy user facilities whose annual
energy consumption is greater than 10,000 MWh or 95,000 MMBtu annually. Grants will
be for custom projects and funding must be utilized within 5 years. For more information
on that program, please visit www.de.gov/e2i
4.0 Delaware Energy Efficiency Investment Fund
4.1 General Provisions
All grants are on a first-come first-served basis. With the exception of energy
assessments, in no event shall the Fund provide grant funding for more than 30
percent of the total costs of any proposed project nor support projects already
receiving support from the Green Energy Fund under this chapter or the Strategic
Fund under subchapter I-B of Chapter 50, Title 29 the Delaware Code. DNREC
reserves the right to suspend, terminate or modify the Fund at any time. DNREC
may change program requirements, eligible measures or grant amounts at any time.
DNREC is not obligated to approve any submitted application that may result in
exceeding the program budget. In the event of a program change, submitted
applications will be processed according to program terms at the time of application
pre-approval.
4.1.1 Pre-Approval
Upon pre-approval, equipment must be new, purchased, and installed before
the grant payment can be issued. Both payment and commitment of grant are
subject to availability of program funds. DNREC will provide designated
grant payments for qualifying equipment. All projects require pre-approval
prior to any equipment purchase or any services completed. Applications for
grants are subject to approval by DNREC and DNREC reserves sole
discretion to accept or reject any application under the Fund. DNREC makes
no commitment to provide grant payment prior to final application approval.
Once your grant is pre-approved, the applicant has 12 months to complete the
project or the application will be considered expired.
6
4.1.2 Inspections
All applications are subject to pre-installation and/or post-installation
inspections at the discretion of DNREC. All customers agree to allow access
to proposed and installed equipment for the purposes of inspection and
verification. If DNREC determines that the customer eligibility, proposed
equipment or installed equipment does not meet the program’s criteria,
DNREC may withhold payment of the grant amount and/or require changes
before issuing payment.
4.1.3 Invoices and Other Final Documentation
After the applicant received pre-approval and completed the installation, the
customer or contractor performing services on behalf of the customer must
provide copies of all itemized invoices and other documentation that verify
the costs of purchasing and installing all qualifying equipment including
material and installation costs. Invoices must be itemized for all eligible
equipment. At the time of project completion quotes cannot be accepted,
itemized invoices are required and the applicant must highlight any changes
in the project scope on those invoices from the proposed quote which may
result in an adjustment of the approved grant amount. Proof of payment must
be submitted prior to grant payment being issued.
4.1.4 Program Limits
The Fund will not pay more than 30 percent of the total project cost for any
proposed project as detailed on itemized invoices. Individual grants will not
exceed $500,000 without written approval from the Division Director.
The grant for a custom project will be paid at a rate of $0.12 per kilowatt-
hour saved and $5/MMBtu, up to 30% of the installed cost, whichever is less.
Energy Assessment Grants will not fund any energy audit or feasibility study
greater than 50 percent of the audit/study cost and will not exceed $10,000
per application for a single purpose/targeted energy audit or $20,000 per
application for a comprehensive energy audit.
No company or affiliated group of companies under common
ownership/control can receive more than $1,000,000 in grants awarded
within a three-year period. By way of example, a parent and subsidiary (or
sister entities with a common owner) would not be eligible to receive more
than $1,000,000 in total combined awards within three consecutive program
years. DNREC’s program years are deemed July 1st through June 30
th.
Within this $1,000,000 limit there is also a cap on total lighting awards. Total
lighting grant awards shall not exceed $400,000 within a three-year period.
By way of example, a parent and subsidiary (or sister entities with a common
owner) would not be eligible to receive more than $400,000 in total
combined lighting awards and would not be eligible to receive more than
7
$600,000 in total combined awards for all other measures within three
consecutive program years.
4.1.5 State Energy Program Revolving Loan Fund
The State Energy Program Revolving Loan Fund (SEPRLF) can be used to
supplement an EEIF grant or as a stand-alone loan. The program offers low-
interest loans for installation of energy efficiency measures that, in turn,
lower their bills while reducing the environmental impacts of energy
production, delivery and use. Applicants need an energy audit that includes a
detailed project description as well as documented energy savings.
Applicants can be from the commercial, industrial, nonprofit, schools, local
government, agricultural and institutional sectors. Underwriting is done in
house by DNREC thereby allowing for greater flexibility in loan terms and
conditions. Loan approval will not compromise an applicant’s EEIF grant
amount, meaning that loans can be used in combination with a grant to help
pay the balance of the project cost.
4.2 Eligibility
The Delaware EEIF Program is available to non-residential consumers that pay the
Delaware Public Utility Tax on electric and/or natural gas utility bills.
Additionally, for a limited time, all non-residential, commercial, industrial,
governmental and non-profit entities in the State of Delaware are eligible for grants
due to the availability of RGGI funding. These funds are subject to change due to
auction results which may result in changes to program eligibility.
Also, for a limited time, through a partnership between the Delaware SEU and
DNREC in which the SEU has agreed to give a portion of their RGGI proceeds to be
used solely on non-profit and local government entities in the State of Delaware for
grants, energy assessment grants and loans.
Finally, for a limited time, the Delaware Public Service Commission approved the
allocation of one-time funding for use as directed by DNREC for energy-efficiency
programs as part of the merger between Exelon Corp and Pepco holdings.
All funding sources are subject to change based on availability. Every funding
source will follow EEIF program requirements and the grant payment structure. The
various sources of additional funding not pertaining to the Public Utility Tax are all
limited and should be considered one-time monies.
New construction is not eligible for EEIF Funding at this time. Therefore, all
applications must be a retrofit of an existing building.
4.3 Permits
All EEIF projects must obtain all relevant permits from DNREC and all other
necessary state, local, regional, and federal permits to be considered for an
application.
8
4.4 Installing Contractor Guidelines
4.4.1 Education and Licensure
Installing contractors shall maintain appropriate education, licenses, industry
certificates and accreditations to ensure the program preserves the end-users’
expectation of professional work. The installing contractor must have an
active Delaware business license, Delaware trade specific license, certificate
of general liability insurance, and training certificates.
Where industry certification programs have been promulgated, grant
recipients are encouraged to use industry certified contractors.
4.4.2 Insurance Requirements
The installing contractor and anyone acting under its direction or control or
on its behalf shall at its own expense procure and maintain in full force at all
times Commercial General Liability Insurance with a bodily injury and
property damage combined single limit of liability of at least one million
dollars ($1,000,000) for any occurrence.
4.4.3 Statement of Reliability and Good Standing
The contractor must be reliable and in good standing with a “Satisfactory
Record” (or no negative reports) with the Better Business Bureau. The
contractor shall provide a copy of their Better Business Bureau report to
DNREC upon request. Reports may be obtained at the following address.
BBB of Delaware
60 Reads Way
New Castle, DE 19720
Phone: (302) 221-5255
Fax: (302) 221-5265
Web Site: www.delaware.bbb.org
Email: [email protected]
4.4.4 Limitation of Funds
The various sources of additional funding not pertaining to the Public Utility
Tax are all limited and should be considered one-time monies. The installing
contractor shall follow program guidelines to ensure reservation of funds
prior to any equipment purchase or installing a qualifying system. DNREC
will provide notice if program funds are close to being exhausted for the
fiscal year.
4.4.5 Participating Contractor List
Contractors installing qualifying energy efficiency measures under the EEIF
Program may apply to be included on the Participating Contractors List that
9
will be published quarterly on the EEIF Website. This list will benefit
consumers looking for contractors and aid contractors in the amount of
information they need to provide DNREC per application by keeping their
records on file. Those contractors identified on the list are in no way
endorsed by DNREC and are not considered trade-allies under any
circumstances. The EEIF participating contractor list is voluntary and does
not preclude eligibility for installers who do not want to be identified to
participate in the EEIF program. The list will be broken out into areas of
specialty/expertise.
New Contractors or Companies seeking to apply will not be listed on the
EEIF website until at least three installations have been completed and three
customer references for each energy efficiency measure have been submitted
to the EEIF Program Team. These installations may not include any installs
at the company’s business, for company employees, or for employee’s family
members.
4.4.5.1 Eligibility
Contractors who maintain an active Delaware business license,
Delaware trade specific license, certificate of general liability
insurance and training certificates are eligible to apply to be listed on
the Participating Contractors List.
4.4.5.1.1 Education and Licensure
Participating Contractors shall maintain appropriate
certifications and licenses, including Delaware business
license and Delaware trade specific license. Contractors
participating on the list must ensure that renewed licenses are
submitted to the EEIF Program Manager prior to their
expiration date. If contractors fail to submit renewed licenses
prior to their expiration date, the Participating Contractor will
be removed from the Participating Contractors List and will
be eligible to reapply.
4.4.5.1.2 Insurance Requirements
The Participating Contractor and anyone acting under its
direction or control or on its behalf shall at its own expense
procure and maintain Commercial General Liability Insurance
with a bodily injury and property damage combined single
limit of liability of at least one million dollars ($1,000,000) for
any occurrence. Contractors participating on the list must
ensure that renewed insurance certificates are submitted to the
EEIF Program Manager prior to their expiration date. If
contractors fail to submit renewed insurance certificates prior
to their expiration date, the Participating Contractor will be
removed from the Participating Contractors List and will be
eligible to reapply.
10
4.4.5.1.3 Statement of Reliability and Good Standing
Contractor must be reliable and in good standing with a
“Satisfactory Record” (or no negative reports) with the Better
Business Bureau. The Contractor shall provide a copy of their
Better Business Bureau report to the Department upon
request. Reports may be obtained at the following address.
BBB of Delaware
60 Reads Way
New Castle, DE 19720
Phone: (302) 221-5255
Fax: (302) 221-5265
Web Site: www.delaware.bbb.org
Email: [email protected]
4.4.5.2 Application Requirements
Contractors seeking to participate in the EEIF Participating
Contractors list must complete an application with the following
information:
Name of company and key contact information, AND
Brief history and organizational structure of company,
AND
Education, experience, and licensure, AND
General liability insurance, AND
Statement of reliability and good standing, AND
Date and location of the three most recently installed
energy efficiency measures, AND
Three customer references for each energy efficiency
measure
In addition to completing the Participating Contractors List
Application, Contractors shall submit copies of the following licenses
and documentation:
Delaware Business License, AND
Trade Specific License, AND
Commercial General Liability Insurance Certificate, AND
Licensed Professional’s Training Certificates or other
proof of training
4.4.5.3 Application Process
Contractors should determine eligibility by ensuring that licenses,
insurance, and other required documentation meets the application
requirements. Contractors should then submit the completed and
signed Participating Contractor Application with copies of the
required licenses, insurance, and documents to DNREC.
11
After receipt of the completed application and any required
supplementary documentation, DNREC will evaluate the
Participating Contractor application, required licenses, insurance, and
other required documentation. The contractors are fully responsible
for ensuring that all forms and documentation have been supplied and
meet all program requirements. If the requirements have been
successfully met, an approval letter will be issued by DNREC to the
Contractor. Failure to supply these documents will result in a delay of
approval or rejection of application.
The Participating Contractor list will be updated on the EEIF Website
on the first business day of each quarter of the Delaware Fiscal Year.
Contractors are fully responsible for ensuring that renewals and
updated documents are provided to DNREC to remain on the list. If
existing Participating Contractors fail to submit renewed licenses and
insurance prior to their expiration date, the Participating Contractor
will be removed from the Participating Contractors List and will be
eligible to reapply in the next update cycle.
The EEIF participating contractor list is voluntary and does not
preclude eligibility for installers who do not want to be identified to
participate in the EEIF program.
4.5 Warranty
All qualifying systems receiving an EEIF grant must have a full 3-year warranty
against component failure, malfunction and premature output degradation. The
warranty must cover all components for which the applicant is receiving grant
money for, and must cover the full cost of repair and replacement of all components
of the system. For professionally installed systems, the warranty must cover the
labor to remove and replace defective components and systems.
DNREC neither expressly nor implicitly warrants the performance of installed
equipment. Participants should contact their contractor for details regarding the
equipment warranties.
4.6 Code Compliance
All qualifying systems must be installed in accordance with the standards and
specifications of the manufacturers of the components in the system, in compliance
with all federal, state, and local safety, building and environmental codes and
ordinances and these guidelines. Where discrepancies, if any, exist with these
guidelines and local codes, local codes shall govern.
With regard to Delaware’s current building energy code, qualifying systems must
exceed minimum code requirements in order to be considered for energy efficiency
grant funds. For more on Delaware’s energy codes, please see de.gov/energycodes.
All equipment must be tested to Underwriters Laboratory (“UL”) standards, be UL
12
listed and installed per manufacturer’s instructions.
5.0 Delaware Energy Efficiency Investment Fund Pathways
There are several funding avenues and grant pathways available to Delaware businesses
with existing buildings tailored to differing needs and resources. There is a prescriptive
energy efficiency grant option by which a business may engage a contractor or otherwise
install specified efficiency equipment and be assured a prescribed grant according to a set
grant amount. There is also the customized option geared for businesses with more unique
or complex energy efficiency projects. There is an energy assessment option for
businesses needing more assistance in planning for efficiency. A fourth pathway has been
developed for combined heat and power (CHP) systems. The four options are described in
detail below.
All four of these pathways can be paired with the DNREC State Energy Program
Revolving Loan Fund (SEPRLF) detailed in section 4.1.6. Loan approval will not
compromise an applicant’s EEIF grant amount, meaning that loans can be used in
combination with a grant to help pay the balance of the project cost. Applications for
SEPRLF are available on the EEIF website (de.gov/eeif).
5.1 Prescriptive Pathway Grants
Prescribed measures contain technologies where energy savings can be predicted
with reasonable accuracy across all applications. The technologies currently eligible
for the program include: lighting, high efficiency commercial gas heating, hot water
heating, and vending misers.
The program may modify or expand the list of eligible measures under the
prescriptive grant pathway at any time. DNREC will notify applicants of any
changes on the website and update any published materials.
5.1.1 Prescriptive Grant Limits
The Fund will not pay more than 30 percent of the total project cost for
eligible prescriptive measures as detailed on itemized invoices and grants
will not exceed $500,000 without written approval from the Division
Director.
No company or affiliated group of companies under common
ownership/control can receive more than $1,000,000 in grants awarded
within a three-year period based on program years. By way of example, a
parent and subsidiary (or sister entities with a common owner) would not be
eligible to receive more than $1,000,000 in total combined awards within
three consecutive program years. DNREC’s program years are deemed July
1st through June 30
th.
Within this $1,000,000 limit there is also a cap on total lighting grant awards
13
which shall not exceed $400,000 within a three-year period. By way of
example, a parent and subsidiary (or sister entities with a common owner)
would not be eligible to receive more than $400,000 in total combined
lighting grants and would not be eligible to receive more than $600,000 in
total combined grants for all other measures within three consecutive
program years.
5.1.2 Prescriptive Accepted Products and Equipment
The following list details the products and equipment eligible for a grant
under the Energy Efficiency Investment Fund Prescriptive pathway.
Lighting
All products must meet the technical requirements listed on the Prescriptive
Grant Application Form for lighting equipment to be eligible for a grant.
All products must be UL listed and be installed according to local building
codes.
All products must be installed in such a way that the lighting power
allowance in either the Building Area or the Space-by-Space method of
ASHRAE 90.1-2010 and the current Delaware building codes is not
exceeded.
Heating Equipment
All products must meet the technical requirements listed on the Prescriptive
Grant Application Form for Natural Gas Heating and Water Heating
Equipment to be eligible for a grant.
Water Heating Equipment
All products must meet the technical requirements listed on the Prescriptive
Grant Application Form for Natural Gas Heating and Water Heating
Equipment to be eligible for a grant.
Vending Machine Miser
All products must meet the technical requirements listed on the Prescriptive
Grant Application Form for Vending Miser to be eligible for a grant.
The following are not eligible for a Prescriptive grant:
Routine maintenance procedures
Building energy code requirements (see ASHRAE 90.1-2010 and
2012 IECC) de.gov/energycodes
Other restrictions as deemed appropriate by DNREC
5.1.3 Prescriptive Application Process
The figure below shows the application process from the submission of the
application through grant payment. The workflow steps are further detailed
below.
14
The applicant or contractor acting on behalf of the applicant should confirm
that the proposed energy efficiency measure (EEM) qualifies for a grant
based on the program requirements. Then, submit a completed and signed
EEIF Prescriptive Grant Application form with copies of the manufacturer's
technical specification sheets (cut sheets) for each type of EEM to be
purchased. After an application is received, it is classified as ‘pending’ status,
and will expire after 3 months if any missing documentation is not provided.
After receipt of the completed application and all required supplementary
documentation, DNREC will evaluate the project for consideration of project
pre- approval. The contractor and customer are fully responsible for ensuring
that all forms and documentation have been supplied and the system meets
all program requirements. If the requirements have been successfully met, a
pre-approval letter will be issued by DNREC to the applicant.
After completing the installation of the project, the applicant or contractor
acting on behalf of the applicant must submit the final documents pertaining
to the project. DNREC will evaluate the project and the required
accompanying documents for consideration of grant final approval. DNREC
may conduct an inspection of the systems prior to final grant approval.
5.1.4 Prescriptive Application Timeline
Applications submitted to DNREC will follow the timelines specified in
these guidelines. DNREC will process the grant within 60 days of receipt of
the final application package and all supporting documentation, or 30 days
after a scheduled inspection if required. DNREC will ordinarily process the
payment to the purchaser, however, if the purchaser so requests in writing
and documentation reflects the grant value was reduced directly from the
purchase price, DNREC will process the payment to the retailer or installing
contractor. The following flowchart shows an overview of the full process
from application received through grant payment. Details of each workflow
step are described below:
15
Application Received:
Contractor or applicant submits the project application to DNREC. The
application and date received is logged into the tracking spreadsheet and a
review is scheduled.
Application review:
DNREC reviews the application and energy calculations for completeness. If
there is any missing information, or if anything is needed in order to
accurately estimate the energy savings from the project, DNREC will follow
up with the applicant. DNREC reserves the right to deny applications that are
unreasonably incomplete or that fail to become complete after due diligence
to collect the required information. The program manager may also decide
the application needs additional study or metering data to be confident in the
estimates, and may notify the applicant to request additional information or a
site visit. Depending on the additional information required, there may be
additional program funds available for these activities under the Energy
Assessment grants opportunity.
Pre-Installation Site Visit:
If necessary, DNREC will conduct a pre-installation site visit, in order to
ensure that the installation has not yet begun and that baseline conditions
were accurately described in the application. During the site visit, DNREC
may also collect information to enable it to accurately calculate savings.
DNREC will complete pre-inspections according to the following criteria
based on grant requests in order to maintain a high level of quality assurance:
Visit 10% of projects with grant requests < $10,000
Visit 25% of projects with grant requests ≥ $10,000 < $50,000
Visit 50% of projects with grant requests ≥ $50,000 < $100,000
Visit All of projects with grant requests ≥ $100,000
Project Technical Review and Grant Calculation:
If the project does not pass the initial review, the program manager will
notify the applicant. The applicant may choose to modify the project or
rescind the application. DNREC reserves the right to deny applications that
are unreasonably incomplete or that fail to become complete after due
diligence to collect the required information.
The grant award calculation will be based on the technical review results.
Pre-Approval Grant Letter:
If the project passes the technical review, the applicant will be sent a pre-
approval letter that reserves the grant amount for not more than 12 months.
The letter will also include a disclaimer that the grant award cannot be
guaranteed if there are changes in scope or cost.
16
The applicant is responsible for submitting the final documents once the
project is installed and completed.
Post-Installation Site Visit
A post-installation site visit may be necessary due to minor changes in scope
as a project proceeds from design to completion and to ensure that the final
savings estimates reflect the project as installed, rather than the project as
designed. These site visits will be performed on a sample of project sites
according to the following rates based on pre-approved grants to ensure
quality assurance:
Visit 10% of projects with grant requests < $10,000
Visit 25% of projects with grant requests ≥ $10,000 < $50,000
Visit 50% of projects with grant requests ≥ $50,000 < $100,000
Visit All of projects with grant requests ≥ $100,000
Final Review
Once the final costs and project specifications are submitted to DNREC, a
final review is performed using the measure screening tool. This will ensure
that the program records reflect the actual site conditions. If the scope of the
project changed enough to significantly lower savings, the grant amount will
be changed to reflect the installed savings.
Grant Payment
Once the project passes the final review, the grant is ready to be disbursed to
the applicant. DNREC will send a letter notifying the applicant of payment
approval and will record the payment information in the Payment Summary
sheet.
5.1.5 Prescriptive Application Requirements
Applications must be completely and accurately submitted before grants can
be paid. Required documentation includes:
Specification (cut) sheets for all equipment, AND
Technical data and testing laboratory information, AND
Quotes and estimates for all equipment and the scope of work,
AND
Twelve consecutive electric and/or natural gas utility bills, AND
Installer’s Commercial General Liability Insurance certificate,
AND
Installer’s appropriate business license(s) for the State of
Delaware and trade specific license, AND
Delaware State Substitute W-9 form submitted electronically to
https://w9.accounting.delaware.gov/, AND
If a lighting project, a lighting schedule is required. DNREC
reserves the right to also request a ceiling plan, AND
After project completion, itemized invoices for all installed
equipment.
17
Additional information may be requested upon review of initial proposal as
deemed appropriate by DNREC.
5.2 Custom Pathway Grants
The custom pathway grant option is designed to encourage non-standard energy-
efficiency measures, including measures not listed in the prescriptive pathway above
and prescribed measures bundled into a comprehensive full-facility upgrade that
maximizes energy savings and cost effectiveness. The custom grant pathway allows
for more comprehensive, unique and creative solutions to projects that are more
complex than the prescriptive program offers.
The custom grants are based on calculated energy and demand savings of retrofit
projects, as well as cost effectiveness, and are limited by total project cost. The projects
qualifying under this program are generally more complex and aggressive measures
that permanently raise the efficiency levels beyond that of standard equipment.
5.2.1 Custom Grant Limits
Subject to the availability of funds and the per business limit, a custom grant
pathway must propose a project offering an annual energy savings. The grant
will be paid at a rate of $0.12 per kilowatt-hour saved and $5.00/MMBtu, up
to 30 percent of the total project costs, whichever is less. Program funds are
limited and projects must be pre-approved to reserve funds prior to the
purchase of any equipment.
Typically, the savings generated by these custom measures are site and end
use specific and require a detailed analysis to qualify for a grant.
Recognizing this, DNREC reserves the right to require a detailed system
design and a predicted performance calculation verified by a Professional
Engineer (P.E.) on 100 percent of proposed projects.
All custom applications require documentation of the energy savings
information. Acceptable forms of documentation include: energy modeling
by a consultant or other third party, specification sheets for ALL existing and
proposed systems, and/or signature by a licensed professional engineer
(P.E.). Failure to submit acceptable documentation will result in a
determination of ineligibility. For example, ASHRAE 90.1-2010 Appendix G
simulation may be used to demonstrate beyond-code energy performance,
and ASHRAE's energy cost budget method may be used to demonstrate
energy cost avoidances.
5.2.2 Accepted Custom Products and Equipment
All projects that are considered energy efficiency measures may be eligible
to receive a custom pathway grant, as long as they exceed minimum building
energy code requirements. Examples of possible improvements over baseline
include:
Building envelope
Steam / Boiler improvements
18
Process Heat recovery
Compressed Air improvements
Chillers
Variable Speed Drives
Heating Ventilation and Air Conditioning improvements
Plug Load Controls
Service Water Heating improvements
Lighting Power Density improvements beyond code (using a mix
of daylighting, delamping, highly reflective interior surfaces, and
fixture efficiency)
Whole Building Retrofits (using three or more energy efficiency
measures to deliver a minimum of 30% energy use reduction from
pre-installation baseline)
The following are not eligible for the custom pathway grant:
Routine maintenance procedures
Renewable energy generation (e.g. wind, geothermal, solar, etc.)
Projects with less than a 6-month simple payback
Industrial technologies not approved by nationally recognized
laboratories
Power conditioning/power factor equipment
Equipment studies
Projects with less than 1.0 benefit cost ratio (using the Total
Resource Cost (TRC) method)
Projects that bring the building up to minimum code requirements
Other restrictions as deemed appropriate by DNREC
5.2.3 Custom Application Process
Applications for the custom pathway must receive pre-approval from
DNREC prior to beginning the project with the purchase of any materials. A
statement of reservation of funds and authorization to proceed will be issued
by DNREC upon acceptance as a custom project. DNREC reserves the right
to pre-inspect all facilities requesting a custom path grant. Applications with
missing information or documentation will be classified as “pending” status,
these applications will expire after 3 months if the missing information is not
provided.
After receipt of the completed application and any required supplementary
documentation, DNREC will evaluate the project for consideration of grant
pre- approval. The contractor and customer are fully responsible for ensuring
that all forms and documentation have been supplied and the system meets
all program requirements. If the requirements have been successfully met, a
pre-approval letter will be issued by DNREC to the applicant.
Funds will be reserved for 12 months on a first-come, first-served basis. The
final grant claim form and supporting documents shall be submitted within
19
the 12 months of the reservation date or funds will be forfeited. If the claim
form is not received at the end of the 12-month reservation period, and the
applicant wishes for an extension, a milestone accomplishments report and
form letter should be submitted to DNREC two months ahead of the
reservation expiration date or the reservation will be forfeited. DNREC will
determine if a reservation extension should be granted. Granted extensions
are for 1 or 3-months only.
After completing the project, the applicant must submit the final documents
pertaining to the project. DNREC will evaluate the project and the required
accompanying documents for consideration of grant approval. DNREC may
conduct an inspection of the systems prior to final grant approval.
5.2.4 Custom Application Review Process
The following shows a flowchart of each workflow step with definitions
detailing each step below:
Application Received:
Contractor or applicant submits the project application to DNREC. The
application and date received is logged into the tracking spreadsheet and a
review is scheduled.
Application review:
DNREC reviews the application and energy calculations for completeness. If
there is any missing information, or if anything is needed in order to
accurately estimate the energy savings from the project, DNREC will follow
up with the applicant. DNREC reserves the right to deny applications that are
unreasonably incomplete or that fail to become complete after due diligence
to collect the required information. The program manager may also decide
the application needs additional study or metering data to be confident in the
estimates, and may notify the applicant to request additional information or a
site visit. Depending on the additional information required, there may be
additional program funds available for these activities under the Energy
Assessment grants opportunity.
Pre-Installation Site Visit:
If necessary, DNREC will conduct a pre-installation site visit, in order to
ensure that the installation has not yet begun and that baseline conditions
were accurately described in the application. During the site visit, DNREC
may also collect information to enable it to accurately calculate savings.
20
DNREC will complete pre-inspections according to the following criteria
based on grant requests in order to maintain a high level of quality assurance:
Visit 10% of projects with grant requests < $10,000
Visit 25% of projects with grant requests ≥ $10,000 < $50,000
Visit 50% of projects with grant requests ≥ $50,000 < $100,000
Visit All of projects with grant requests ≥ $100,000
Project Technical Review and Grant Calculation:
If the project does not pass the initial review, the program manager will
notify the applicant. The applicant may choose to modify the project or
rescind the application. DNREC reserves the right to deny applications that
are unreasonably incomplete or that fail to become complete after due
diligence to collect the required information.
The grant award calculation will be based on the technical review results.
Pre-Approval Grant Letter:
If the project passes the pre-screening, the applicant will be sent a pre-
approval letter that reserves the grant amount for not more than 12 months.
The letter will also include a disclaimer that the grant award cannot be
guaranteed if there are changes in scope or cost.
The applicant is responsible for submitting the final documents once the
project is installed and completed.
Post-Installation Site Visit
A post-installation site visit may be necessary due to minor changes in scope
as a project proceeds from design to completion and to ensure that the final
savings estimates reflect the project as installed, rather than the project as
designed. These site visits will be performed on a sample of project sites
according to the following rates based on pre-approved grants to ensure
quality assurance:
Visit 10% of projects with grant requests < $10,000
Visit 25% of projects with grant requests ≥ $10,000 < $50,000
Visit 50% of projects with grant requests ≥ $50,000 < $100,000
Visit All of projects with grant requests ≥ $100,000
Final Review
Once the final costs and project specifications are submitted to DNREC, a
final review is performed using the measure screening tool. This will ensure
that the program records reflect the actual site conditions. If the scope of the
project changed enough to significantly lower savings, the grant amount will
be changed to reflect the installed savings.
Grant Payment
Once the project passes the final review, the grant is ready to be disbursed to
the applicant. DNREC will send a letter notifying the applicant of payment
21
approval and will record the payment information in the Payment Summary
sheet.
5.2.5 Custom Application Timeline
Applications submitted to DNREC will follow the timelines specified in
these guidelines which are detailed in section 5.1.4. DNREC will process the
grant within 60 days of receipt of the final application package and all
supporting documentation, or 30 days after a scheduled inspection if
required. DNREC will ordinarily process the payment to the purchaser,
however, if the purchaser so requests in writing and documentation reflects
the grant value was reduced directly from the purchase price, DNREC will
process the payment to the retailer or installing contractor.
5.2.6 Custom Application Requirements
Applications must be completely and accurately submitted before grants can
be paid. Required documentation includes:
Specification (cut) sheets for all equipment, AND
Technical data and testing laboratory information, AND
Itemized quotes and estimates for all equipment and the scope of
work, AND
Twelve consecutive electric and/or natural gas utility bills, AND
Installer’s Commercial General Liability Insurance certificate,
AND
Installer’s appropriate business license(s) for the State of
Delaware and Delaware trade specific license, AND
Documentation of the energy savings calculations and cost
estimates, AND
Project schedule including detailed milestones, AND
Delaware State Substitute W-9 form submitted electronically to
https://w9.accounting.delaware.gov/, AND
If a lighting project, a lighting schedule and a ceiling plan, AND
After project completion, itemized invoices for all installed
equipment.
Additional information may be requested upon review of initial proposal as
deemed appropriate by DNREC.
5.3 Energy Assessment Grants
For businesses in need of technical assistance to evaluate their facility for cost
effective energy efficient upgrades, grants are available to help with the cost of the
audit, feasibility study and project design. Energy Assessment funding is limited.
Funding must be reserved prior to beginning the audit or study to ensure funding
availability.
5.3.1 Energy Assessment Grant Limits
The Energy Assessment grants will pay up to 50 percent of the cost of the
22
proposed audit per application, up to $10,000 for a single purpose/targeted
energy audit or up to $20,000 per application for a comprehensive audit.
5.3.2 Accepted Audits
5.3.2.1 Single Purpose or Targeted Energy Audit
A single purpose or a targeted energy audit will provide a detailed
analysis on one or more types of projects. Audit types included but
are not limited to a focused analysis on lighting, energy management
systems, variable speed drives, boiler/chiller replacements, thermal
energy storage systems, energy generation, or a combination of these
projects.
5.3.2.2 Comprehensive Audit
A comprehensive energy audit will provide a detailed analysis of a
facility and potential project. The audit will include the interactive
effects of the projects and account for the energy use of all major
equipment while providing detailed energy cost saving calculations
and installed project cost. Comprehensive audits typically use
computer models such as DOE-2, Trane/Trace or equivalent packages
to simulate building and equipment operations based on weather,
equipment set points and hours of operation.
Recognizing that a comprehensive audit evaluates all major energy
using systems, the audit will include an implementation plan for the
facility upgrades. Systems eligible for a comprehensive audit include
but are not limited:
Building envelope
Lighting
Domestic hot water
HVAC and controls
Combined heat and power
The audit must comply with ASHRAE Level II audit requirements.
5.3.3 Energy Assessment Application Process
Applicants for the Energy Assessment grant option shall submit Part 1 of the
application and the winning audit proposal to DNREC and receive pre-
approval prior to beginning the project. A statement of reservation of funds
and authorization to proceed will be issued by DNREC upon acceptance of
Part 1 of the application.
Upon receipt of the completed study and all final documentation pertaining
to the project, DNREC will evaluate the project for grant payment. The
contractor and customer are fully responsible for ensuring that all forms and
documentation have been supplied and the proposal meets all program
requirements. Applications submitting only a scope of work for the proposed
23
study will be considered incomplete and not eligible for grant award.
In addition to the requirements in this section, applications for Energy
Assessment grants must include the following:
Completed Application Form Part 1 and appropriate audit proposal,
AND
Copy of the customer’s last 12 months of electric and natural gas
bills, AND
The completed energy study, which shall include all requirements
needed for the prescriptive and custom grants including the
following:
1. Executive Summary
2. Technical Information and Analysis
a) Description of the project and proposed energy saving
measures
b) Base case information
c) Enhanced case information
d) Estimated energy and demand savings associated with the
proposed project
e) Any applicable figures and tables
f) Simple payback period and/or life cycle costs
g) Estimated costs including design, materials, and
installation
3. Conclusions and Recommendations
a) Findings and key points summarized
b) Recommendations should be evaluated separately and
combined in the enhanced case
4. Appendix
a) Engineering assumptions and supporting information
b) Building data and plans
c) Cost assumptions
d) Publication information for each source cited in the
“Technical Information” section of your report
e) Listing of the publication title, author, place of
publication, page numbers, and date of publication
5.3.4 Energy Assessment Application Timeline
Applications submitted to DNREC will follow the timelines specified in
these guidelines which are detailed in section 5.1.4. DNREC will process the
grant within 60 days of receipt of the final application package and all
supporting documentation.
5.4 Combined Heat and Power Grant Pathway
This pathway was designed to encourage the development of CHP in Delaware.
Unlike traditional systems that produce electricity and heat separately, CHP, or
cogeneration, is the concurrent production of electricity and useful thermal energy
24
from a single source of energy. CHP systems are ideal for businesses with high
annual hours of operation and a high thermal load. CHP systems yield increased
energy efficiency, reduction in energy operating costs and improvements in energy
resiliency.
The CHP grant is based on a minimum efficiency requirement, minimum useful
thermal output requirement, and the size of system ($/kW).
5.4.1 CHP Grant Limits
CHP grant applications must propose a project offering a system that meets
the minimum 60% annual efficiency requirement and the minimum 1.0
MMBtu/hour useful thermal output requirement. The grants for eligible
projects will be awarded at a flat rate of $500 per kilo-watt installed up to
30% of the installed cost of the system, whichever is less. Grant payments
will not exceed $500,000 per project without written approval of the Division
Director.
Eligible measures for installed costs are limited to Genset equipment,
associated equipment (e.g. heat recovery jacket, switchgear, absorption
chillers), installation costs, engineering and project management costs and
decommissioning costs of pre-existing equipment.
No company or affiliated group of companies under common
ownership/control can receive more than $1,000,000 in grant awards within a
three-year period. By way of example, a parent and subsidiary (or sister
entities with a common owner) would not be eligible to receive more than
$1,000,000 in total combined grant awards within three consecutive program
years.
Program funds are limited and must be reserved prior to purchasing any
equipment to ensure availability.
5.4.2 CHP Eligible Products and Equipment
The following CHP system designs are eligible for review. Professional
Engineer (P.E.) signatures are required for the design portion of the project:
Reciprocating Engine
Microturbine
Steam Turbine
Gas Turbine
Fuel Cells
Equipment must be new and permanently installed. Equipment must receive
a full 3-year warranty against component failure, malfunction, and premature
output degradation. The warranty must cover all components for which the
program money is granted and cover the full cost of repair and replacement
of all components of the system. For professionally installed systems, the
warranty must cover the labor to remove and replace defective components
25
and systems. All products must be UL listed and installed according to local,
state, regional, and/or federal building and environmental codes.
A decommissioning plan must be provided outlining the proper disposal and
recycling details of any pre-existing equipment that will be removed.
Expansion of an Existing System
The incremental expansions of an existing CHP system are eligible. Grants
will be calculated based on the incremental expansion of the system, not total
system size. Equipment must be new and permanently installed.
Power Purchase Agreements
Third Party Vendor’s and Power Purchase Agreements are eligible. The full
Power Purchase Agreement with final signatures must be provided prior to
receiving grant payment.
Existing and Future Flood Risk Mitigation
Installations must be designed to avoid impacts from flooding, including
future sea-level rise. Applicants are encouraged to utilize the Flood Risk
Adaptation Map (FRAM) to determine whether the proposed site is within
the one-hundred year, one-meter, sea-level rise flood plain. See site:
www.firstmap.delaware.gov/FRAM
If applicants are within the one-hundred year, one-meter, sea-level rise flood
plain, applicants must submit a flood risk mitigation plan as part of the
design portion of the proposed system with their application.
5.4.3 CHP Application Process
Confirm that the proposed CHP system qualifies for a grant based on the
program requirements. Submit a completed and signed EEIF CHP grant
application form with a completed application package (See 5.4.6
Application Requirements Below).
After receipt of the completed application and all required supplementary
documentation, DNREC will evaluate the project for consideration of grant
pre-approval. All projects must be pre-approved before any equipment is
purchased or installation is started. The contractor and customer are fully
responsible for ensuring that all forms and documentation have been supplied
and the system meets all program requirements. DNREC will arrange a pre-
installation site inspection for all proposed CHP projects prior to issuing pre-
approval. If the requirements have been successfully met, a pre-approval
letter will be issued by DNREC to the applicant.
Funds will be reserved for 18 months on a first-come, first-served basis. The
final grant claim form and supporting documents shall be submitted within
18 months of the reservation date or funds will be forfeited. If the project
26
cannot be completed within the 18-month period of reservation and the
applicant wishes for an extension, a milestone accomplishments report and
form letter should be submitted to DNREC two months ahead of the
reservation expiration date. DNREC will determine if a reservation extension
should be granted. After completing the project, the applicant must submit
the final documents pertaining to the project. DNREC will evaluate the
project and the required accompanying documents for consideration of grant
approval. DNREC will conduct a post-installation site inspection of the
system prior to final grant approval.
5.4.4 CHP Application Review Process
The following shows a flowchart of each workflow step with definitions
detailing each step below:
Application Received:
Contractor or applicant submits the project application to DNREC. The
application and date received is logged into the tracking spreadsheet and a
review is scheduled.
Application review:
DNREC reviews the application and design plan for completeness. If there is
any missing information, or if anything is needed in order to accurately
review the project, DNREC will follow up with the applicant. DNREC
reserves the right to deny applications that are unreasonably incomplete or
that fail to become complete after due diligence to collect the required
information. The program manager may also decide the application needs
additional study or metering data to be confident in the estimates, and may
notify the applicant to request additional information. Depending on the
additional information required, there may be additional program funds
available for these activities under the Energy Assessment grants
opportunity.
Pre-Installation Site Visit:
DNREC will conduct a pre-installation site visit on all proposed CHP
projects, in order to ensure that the installation has not yet begun and that
baseline conditions were accurately described in the application. During the
site visit, DNREC may also collect information to enable it to accurately
calculate savings.
27
Pre-Approval Grant Letter:
If the project passes the primary and secondary application review, and is
approved by the Program Administrator, the applicant will be sent a pre-
qualification letter that reserves the grant amount for not more than 18
months. Applicants may begin the purchase and install of equipment upon
receiving the pre-approval letter. The letter will also include a disclaimer that
the grant award cannot be guaranteed if there are changes in scope or cost.
The applicant is responsible for submitting the final documents once the
project is installed and completed.
Post-Installation Site Visit
A post-installation site will be conducted to ensure that the project proceeds
from design to completion prior to awarding grant payment. Site visits will
be performed on all CHP project sites.
Final Review
Once the required final application requirements are submitted to DNREC, a
final review is performed on the application. This will ensure that the
program records reflect the actual site conditions. If the project passes both a
primary and secondary final review, and receives Program Administrator
approval, the application will be scheduled for grant payment.
Grant Payment
Once the project passes the final screening, the grant is ready to be disbursed
to the applicant. DNREC will send a letter notifying the applicant of payment
approval and will record the payment information in the Payment Summary
sheet.
5.4.5 CHP Application Timelines
Applications submitted to DNREC will follow the timelines specified in
these guidelines which are detailed in section 5.1.4. DNREC will process the
grant within 60 days of receipt of the final application package and all
supporting documentation, or 30 days after a scheduled inspection if
required. DNREC will ordinarily process the payment to the purchaser,
however, if the purchaser so requests in writing and documentation reflects
the grant value was reduced directly from the purchase price, DNREC will
process the payment to the retailer or installing contractor.
5.4.6 CHP Application Requirements
Applications must be completely and accurately submitted before any grant
can be paid. Required documentation includes:
Pre-Approval:
Specification (cut) sheets for all equipment, AND
Technical data and testing laboratory information, AND
Itemized quotes and estimates for all equipment and the scope of
work, AND
28
Twelve consecutive electric and/or natural gas utility bills for each
meter on site, AND
If enrolled in a Third-Party Supplier Agreement for electric and/or
natural gas, twelve consecutive electric and/or natural gas supply
bills for each meter on site, AND
Typical Day (Peak Day alone is not sufficient) Hourly Electricity
and Heating Load Profile for the Facility for each month of the year
(based on metered data, utility 15-minute interval data, or estimated
based on other documented facility usage data), AND
If the system is greater than or equal to 800kW, a draft
Measurement and Verification Plan (M&V) must be submitted as
part of the application, AND
Installer’s Delaware Business License, Delaware Trade Specific
License, and Commercial General Liability Insurance Certificate,
AND
Design Plan with Professional Engineer (P.E.) signature showing
waste-to-heat end use, make and model, operation schedule, and
generation capacity, AND
Detailed Energy Model showing electrical generation on a monthly
basis, heat recovery on a monthly basis, avoided annual energy use,
fuel input on a monthly basis, total annual avoided electricity and
natural gas (or other) fuel consumption, total annual fuel input, and
calculation of overall system efficiency, AND
Installation Schedule outlining delivery dates for major components
and must show full operation within a year of pre-approval, AND
All applicable federal, regional, state, and/or local permits, AND
Interconnection Agreement, AND
Delaware State Substitute W-9 form submitted electronically to
https://w9.accounting.delaware.gov/, AND
If financed through a Power Purchase Agreement, the full
agreement and final signatures must be provided, AND
If proposed project site is within the one-hundred year, one-meter,
sea-level rise flood plain, a flood risk mitigation plan as part of the
design portion of proposed system must be submitted
Final Approval:
Finalized itemized project invoices, AND
Proof of Payment, AND
Finalized Interconnection Agreement with Proper System
Inspections, AND
Commissioning Report
Additional information may be requested upon review of initial proposal as
deemed appropriate by DNREC.
29
6.0 Proprietary Application Information
DNREC may make all applications submitted available to non-State personnel for the sole
purpose of assisting in its evaluation of the applications. These individuals will be
required to protect the confidentiality of any specifically identified proprietary information
obtained as a result of their participation in the evaluation.
Proposals submitted may contain trade secrets and/or privileged or confidential
commercial or financial information which the applicant does not want to be used or
disclosed for any purpose other than evaluation of the application. The use and disclosure
of such data may be restricted, provided the applicant follows DNREC’s “Request for
Confidentiality” procedure contained in DNREC’s “Freedom of Information Act” or
“FOIA” regulation. It is important to understand that this FOIA regulation’s
confidentiality procedure is a necessary part of this regulation in that any information
submitted to DNREC is subject to public review unless deemed to be confidential by the
Secretary in accordance with the criteria and procedures established in the FOIA
regulation.
The burden lies with the applicant asserting the claim of confidentiality to meet the criteria
established in the FOIA regulation.
7.0 Retirement and Disposal
The intent of the Energy Efficiency Investment Fund is to increase energy efficiency
through retirement and replacement of inefficient equipment. The customer and contractor
shall appropriately retire and dispose of any product replaced as a result of an Energy
Efficiency Investment Fund grant.
The customer is responsible for the proper disposal or recycling of any waste generated as
a result of the project, including the disposal of fluorescent lamps (which contain mercury)
and ballasts suspected of containing PCBs. Any fluorescent ballast dated pre-1979 should
be considered to contain PCBs unless otherwise labeled.
8.0 Dispute Resolution
Should an applicant be denied a grant and disagrees with outcome, the applicant must
contact DNREC in writing. DNREC will respond within 10 days after the determination.
Should DNREC deem the application eligible, the application will be processed within the
next 10 business days.
9.0 Tax Liability
The applicant is responsible for any tax liability imposed as a result of the payment of
grants. Applicants are advised to contact a tax professional for more information.