Page 1: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Department of Transport

MTEF And Strategic Plan Presentation To

Select Committee

Presentation by Ms M. Mpofu

Director General: Transport

27 May 2008

Page 2: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

1. Vision, Mission, Mandate and Values

2. DoT Strategic Focus Areas

3. Management Issues

4. Performance Highlights for 07-08 financial year

5. Context of DoT Strategic Plan 5.1 January 2008 Cabinet Lekgotla Resolutions

5.2 Cluster Priorities for 2008

5.3 Apex Priorities

6. Overview of 2008 Medium-Term Expenditure Budget 6.1 List of additional allocations 6.2 Issues highlighted by the Minister of Finance 6.3 Budgets per Programme 6.4 Breakdown of major budgets 6.5 Other budgets and major projects 6.6 Under expenditure in 2007/08 6.7 Gautrain expenditure and budgets 6.8 PTIS expenditure and budgets 6.9 Growth in major capital budgets

7. Planned projects/activities over next three years

ContentsDepartment

of Transport

2

Page 3: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Vision and Mission

Our Vision “Transport, the Heartbeat of Economic Growth and SocialDevelopment”

Our Mission to “Lead the development of efficient integrated transport systemsby creating a framework of sustainable policies and regulators andimplementable models to support government strategies foreconomic, social and international development.”

3

Page 4: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

DOT Mandate

Our Mandate • to maximize the contribution of transport to the economic and social

development goals of the society by providing fully integrated transport operations and infrastructure.

Our Values • Maintain fairness and equity in all our operations• Strive for quality and affordable transport for all• Stimulate innovation in the transport sector• Ensure transparency, accountability and monitoring for all operations• Ensure sustainability, financial affordability, accessibility as well as

the upholding of the Batho Pele principles.

4

Page 5: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

DOT Focus Areas

• To effectively manage a national innovative research centre and provide economic advice and analysis for all modes of transport

• To create an enabling regulatory environment for road, aviation and maritime transport, and manage accident and incident investigations in all modes of transport

• To manage and facilitate integrated planning and intersphere coordination for transport infrastructure and operations

5

Page 6: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

DoT Focus Areas (Cont…)

• To manage the implementation of the transport logistics strategy and the development of freight movement corridors

• To develop integrated accessible and affordable quality public transport networks that meet the needs of both rural and urban passengers

• To develop appropriate mandates and monitoring mechanisms for public entities

6

Page 7: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

DoT07-08 Performance Highlights

Department of

Transport

7

Page 8: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Performance Highlights 2007-08

•Draft documents for the following policies have been developed and are awaiting Cabinet approval

–National Maritime Transport Policy –National Scholar Transport Policy–Intelligent Transport Systems Policy–Rail Gauge Width Policy–Intermodal Cargo Transfer Policy–Transport Environment and Health Charter–Transport Research and Innovation Strategy

•Airlift Implementation Plan was approved by the Minister in November 2007•Ministerial Approval to redefine the Port limits was granted.•SA retained FAA International Air Safety Category 1 status•The plan for the100 luxury/semi-luxury buses for intercity/airport –city operations was finalised in December 2007•Shova Kalula rollout plan was finalised•The Rural Transport Strategy was approved by Cabinet in December 2007•The Transport Appeal Tribunal Regulations, 2007 were gazetted in December 2007. The regulations give effect to the Transport Appeal Tribunal Act no39 of 1998

8

Page 9: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Performance Highlights 2007-08

•A South African Network of Women in Transport (SANWIT) was officially launched in October 2007 and institutionalised as an organisation to empower and mainstream women into transport opportunities.•8 provincial Freight Databanks were completed•Completed system requirements for National Freight Information System•Phase 1 of the National Freight Monitoring Framework is complete (Completed Landscape and Business Challenges Reports)•Scrapped 13 500 taxis•24 contact points for police were constructed at railway stations•515 Commuter rail coaches were refurbished•Approval of Public Entities General Laws Amendment Act.

–Approval of appointments of CEOs by Minister;– CEOs and Ministerial Representatives to be non-voting members of Boards.

•Establishment of Ports Regulators: Appointment of Board Members and CEO.•22% of female staff were exposed to women empowerment leadership programmes. Also registered 6 women staff members in a Food Aid Learnership. • Successful hosting of the AU Conferences: ROAD and RAIL Transportation

9

Page 10: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Context for DoT Strategic Plan

Department

of Transport

10

Page 11: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

January Cabinet Lekgotla Resolutions

• Integrated infrastructure plan• Implementation of the industrial policy• Implementation of Public Transport Key Action Plans (Taxi recapitalization, subsidy system and investment

plans) • Road accident fund • Implementation of the Rural Transport strategy and

Implementation of Shova- Kalula• 2010 FIFA World Cup – progress, challenges and

interventions required• Inter - cluster activities

11

Page 12: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Cluster Priorities

Economic Cluster Priorities

• Integrated infrastructure Plan – De Hoop Dam Pilot Project.• Electricity Shortage intervention plan • Increase economic efficiencies- ICT, Phased Rollout of Public Transport

network • Second Economy Framework integrated into Anti –Poverty Strategy • Promote dynamic growth sectors- implementation of the industrial policy • Integrate support for small and micro- enterprises

Governance and Administration Cluster Priorities

• Capacity of the state – 5 year local govt. agenda, Skills assessment and Capacity Development

• Good Governance- Anti- Corruption, Gender and Disability, Batho Pele and Public Participation

• Transversal Systems- Integrated Planning, the Government Wide- Monitoring and Evaluation System and the National Statistics System (NSS)

12

Page 13: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Cluster Priorities (continued)

International Relations, Peace and Security

• Consolidation of the African Agenda • The strengthening of the South- South Co-operation • Strengthening of the North- South Co-Operation • Participating in a Global System of Governance- Multilaterals • The strengthening of political and economic relations- Bilaterals

Justice Crime Prevention and Security Cluster Priorities

• Crime Prevention and Public Safety• Upholding National Security• Big events

Social Cluster Priorities

• Second Economy Interventions: Social Sector Cluster Aspects• Comprehensive Anti-poverty Strategy• Social Crime Prevention

13

Page 14: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Apex Priorities (Business Unusual)

• Industrial Policy Action Plan (Project 1, Economic Cluster) • Self-employment interventions in the Second Economy

(Project 9, Economic Cluster) • Speed up community infrastructure programme (Project 10

Social Cluster) • Ensure integrated planning across all spheres (Project 16, G&A Cluster)• Improve civic services (Project 17, G & A Cluster)• Implement special crime combating and security initiatives

(Project 18, JCPS)• Consolidate advances relating to peace and reconstruction in

DRC (Project 22, IRPS)

14

Page 15: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Overview of 2008 Medium-Term Expenditure Budget

Department

of Transport

15

Page 16: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportIssues highlighted by the Minister

of Finance

• PPP arrangements in funding large infrastructure projects, particularly in passenger rail

• Institutional arrangements and concurrent functions in transport, specifically the roles and responsibilities in public transport

• Progress on the Bus Rapid Transit system and PTIS spending and delivery in general

• RISFSA road quality assessments, reclassification and criteria for prioritisation

16

Page 17: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Issues highlighted by the Minister of Finance

• Alignment of the subsidised bus routes with the Public Transport Strategy and Rural Transport Strategy

• Outstanding business plan for Shosholoza Meyl as a ring fenced business within the SARCC.

• Finalisation of the National Land Transport Bill.

• Development of the institutional and regulatory framework to guide the implementation of the National Freight Logistics Strategy.

Department

of Transport

17

Page 18: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportAdditional allocations

Details (R’000) 2008/09 2009/10 2010/11

PTIS Grants to Local Government 0 0 2,000,000

SARCC 118,559 230,307 736,096

SARCC – incorporation of Shosholoza Meyl 500,000 450,000 400,000

SANRAL 13,010 20,028 830,367

Taxi recapitalisation 200,000 150,000 100,000

Bus subsidies 40,000 50,000 60,000

Non-personnel inflation adjustment 47,966 46,502 46,830

Compensation of Personnel 6,175 8,023 8,652

Regulating and training of the taxi industry 6,000 6,000 6,000

Railway Safety Regulator 5,000 5,000 5,000

Ports Regulator 3,000 5,000 5,000

Performance based quality contract model for buses

5,000 5,000 0

Performance management system 2,000 1,000 1,000

Efficiency saving -14,546 -19,444 -22,838

Total 932,164 957,416 4,176,10718

Page 19: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Budgets per Programme

Table 33.1: Transport

R thousand

2007/08 2008/09 2009/10 2010/11

Adjusted

Appropri-ation

Medium-term estimates

MTEF Baseline

1. Administration 144,408 170,537 179,230 182,449

2. Transport Policy and Economic Regulation

33,344 37,733 40,243 40,488

3. Transport Regulation and Accident and Incident Investigation

231,374 255,863 272,466 285,766

4. Integrated Planning and Inter-sphere Co-ordination

5,382,034 7,769,453 8,735,252 11,348,334

5. Transport Logistics and Corridor Development

18,637 22,225 21,322 21,876

6. Public Transport 10,559,225 12,073,463 12,985,884 11,780,249

7. Public Entity Oversight and Border Operations and Control

174,910 179,254 177,577 71,197

Total 16,543,932 20,508,528 22,411,974 23,730,359 19

Page 20: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Breakdown of major budgets (Continued)

0

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

8,000,000

9,000,000

Rail 3,955,197 5,371,276 6,848,101 7,673,958

Bus 2,835,997 2,829,596 3,048,815 3,238,744

Roads 3,391,929 4,072,974 5,524,939 6,665,573

PTIF 1,780,000 3,480,000 2,975,000 4,464,500

Gautrain 3,029,411 3,265,993 2,507,211 317,526

2007/08 2008/09 2009/10 2010/11

• Allocations for rail operations and capital remain the largest single budget item.

2008/09

5,371,276

2,829,596

4,072,974

3,480,000

3,265,993

• The National contribution to the Gautrain Rapid Rail Link was introduced in 2006/07 at R3,241Bn, and declines to R317,5m in 2010/11

• Allocations for infrastructure from the Public Transport Infrastructure and Systems Grant was introduced in 2005/06 at R241,7m, growing to R700m in 2006/07.

• The budget for road infrastructure overtakes that of bus subsidies from 2007/08 onwards.

R’000

20

Page 21: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportBreakdown of other budgets and major projects

Details R’000 2008/09 2009/10 2010/11

Compensation of Employees 196,176 207,398 203,772

P1: October Month & World Remembrance Day 15,000 15,750 16,500

P1: VPN, ECM, Recruitment 9,000 9,450 9,900

P1: Property management 14,242 15,666 17,233

P1: Other 54,427 56,167 58,716

P2: Transport Policy, Research and Economic Regulation 15,431 16,612 17,194

P3: eNaTIS 67,531 69,376 73,309

P3: Special Investigating Unit 20,579 22,353 23,620

P3: Rail Economic Regulator 8,250 8,962 9,470

P3: ICAO and IMO offices 7,140 7,755 8,194

P3: Watch Keeping services 26,271 28,536 30,152

P3: Oil Pollution prevention services 47,296 51,374 54,286

P3: Maritime Security Coordination Centre 6,356 6,904 7,295

P3: Commissioner of Civil Aviation 4,596 4,992 5,275

P3: Maritime Rescue Coordination Centre (Transfer payment) 5,023 5,273 5,589

P3: International membership fees 4,871 5,114 5,420

P3: Road Transport Regulation projects 20,158 21,895 23,137

P3: Other Regulation projects and Administration 5,570 5,965 6,29221

Page 22: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Breakdown of other budgets and major projects (Continued)

Details R’000 2008/09 2009/10 2010/11P4: Transport planning and infrastructure projects 13,212 13,633 13,922

P4: Rural transport and NMT projects 45,361 49,421 52,222

P4: Road infrastructure planning 61,907 65,326 67,674

P4: Sani Pass and Overload Control 38,796 42,562 45,116

P4: 2010 SWC Monitoring and Evaluation 20,000 25,000 0

P4: Other projects and Administration 8,465 9,196 9,697

P5: Transport Logistics and Corridor Development 11,434 9,362 9,866

P6: Bus contract model 5,000 5,000 0

P6: Other projects and Administration 19,158 17,857 18,319

P7: Transfers to RTMC 103,888 99,192 0

P7: Transfers to RSR 33,361 34,523 30,994

P7: Transfers to Ports Economic Regulator 11,382 13,699 8,921

P7: Transfers to SAMSA 8,535 8,959 9,497

P7: Transfers to SACAA 7,464 7,836 8,306

P7: Performance Management System 2,000 1,000 1,000

P7: Other projects and Administration 5,242 4,616 4,866

Total 923,122 966,724 855,75422

Page 23: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

0

50,000

100,000

150,000

200,0001

2

34

56

7

89 10 11 12 13 14 15 16

Department

of Transport

Breakdown of major other budgets for 2008/09

No. Details R’000 %

1 Compensation of Employees 196,176 21,3%

2 Road Traffic Management 171,419 18,6%

3 Administration 92,669 10,0%

4 Road infrastructure planning 91,907 10,0%

5 RSR, SAMSA, SACAA, MRCC, MSCC, NSRI, Ports and Rail Regulators and Memberships

85,242 9,2%

6 Oil Pollution prevention and Watch Keeping services

73,567 8,0%

7 Rural transport projects 45,361 4,9%

8 Inspectorates, Road, Rail, Maritime and Aviation regulation

37,464 4,0%

9 Public Transport and systems to devolve bus subsidies

24,158 2,6%

10 Transport planning and infrastructure projects

21,677 2,3%

11 Special Investigating Unit 20,579 2,2%

12 Monitoring and evaluation – SWC

20,000 2,2%

13 Transport Policy 15,431 1,7%

14 Freight Logistics projects and research

11,434 1,2%

15 Overloading Control 8,796 1,0%

16 Public Entity Oversight & Economic Regulation

7,242 0,8%

Total 923,122 100%

23

Page 24: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Budgets per economic classification

Details R’000 2008/09 2009/10 2010/11

Compensation Of Employees 196,176 207,398 203,772

Goods And Services 594,528 625,311 625,917

Payments For Capital Assets 42,290 46,254 49,030

Transfer Payments – Breakdown below and on the next two slides 19,675,534 21,533,011 22,851,640

Total 20,508,528 22,411,974 23,730,359

TRANSFER PAYMENTS:

Departmental agencies 4,342,793 5,894,596 6,729,066

Ports Regulator 11,382 13,699 8,921

Railway Safety Regulator 33,361 34,523 30,994

Road Traffic Management Corporation 103,888 99,192 0

South African Civil Aviation Authority 7,464 7,836 8,306

SA Maritime Safety Authority 8,535 8,959 9,497

SA Maritime Safety Authority - Maritime Rescue Co-ordination Centre 5,023 5,273 5,589

South African National Roads Agency Ltd 4,072,974 5,524,939 6,665,573

South African National Roads Agency Ltd (PTIS) 100,000 200,000 0

Transport Education and Training Authority 166 175 186

24

Page 25: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Details R’000 2008/09 2009/10 2010/11

Foreign Governments and international organisations 4,871 5,114 5,420

Membership Fees: African Civil Aviation Commission 701 736 780

Membership Fees: Cospas Sarsat Contribution 315 331 351

Membership Fees: Indian Ocean Memorandum of Understanding 211 222 235

Membership Fees: International Civil Aviation Organisation 2,687 2,821 2,990

Membership Fees: International Maritime Organisation 957 1,004 1,064

Households other transfers 459,116 430,887 397,740

Taxi Recapitalisation 459,000 430,765 397,611

Leave gratuity 116 122 129

Provinces and Municipalities 6,435,993 4,832,211 4,782,026

Public Transport Infrastructure and Systems Grant (PTIS) 3,170,000 2,325,000 4,464,500

Gautrain Rapid Rail Link 3,265,993 2,507,211 317,526

Budgets per economic classification (Continued)

25

Page 26: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Details R’000 2008/09 2009/10 2010/11

Non-profit institutions 14,093 15,109 16,017

Hamnet 55 58 62

Mountain Club of South Africa 55 58 62

Off Road Rescue 55 58 62

National Sea Rescue Institute 950 983 1,042

Taxi : SANTACO 12,978 13,952 14,789

Public Corporations 8,410,872 10,346,916 10,912,702

Bus subsidies 2,829,596 3,048,815 3,238,744

South African Rail Commuter Corporation (PTIS) 210,000 450,000

South African Rail Commuter Corporation 5,371,276 6,848,101 7,673,958

Universities and technikons 7,796 8,178 8,669

Universities of Pretoria, KwaZulu-Natal and Stellenbosch 7,796 8,178 8,669

Total for all Transfer Payments 19,675,534 21,533,011 22,851,640

Budgets per economic classification (Continued)

26

Page 27: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Gautrain expenditure and budgets

3,029

2,507

318

3,241 3,266

2006/07 2007/08 2008/09 2009/10 2010/11

Total budget R12,36 bn over 5 years

Actual Actual --------Medium term budgets--------

R Million

2008/09

27

Page 28: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportPTIS expenditure and budgets

241.7

698.0

1,780.0

3,480.0

2,975.0

4,464.5

2005/06 2006/07 2007/08 2008/09 2009/10 2010/11

Total budget R13,6 bn over 6 years (excl. monitoring & evaluation)

Actual Actual Actual ----Medium term budgets-----

R Million

2008/09

28

Page 29: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportGrowth in major capital budgets

0

2,000,000

4,000,000

6,000,000

8,000,000

10,000,000

12,000,000

14,000,000

Gautrain 0 0 3,241,000 3,029,411 3,265,993 2,507,211 317,526

PTIS 0 241,710 698,020 1,780,000 3,480,000 2,975,000 4,464,500

Roads 504,276 565,333 797,952 1,429,350 1,806,944 2,731,982 3,695,901

Rail 655,000 688,300 1,029,598 1,696,078 2,367,686 3,684,144 4,393,193

2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11

(R’000)

29

Page 30: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportUnder expenditure in 2007/08

Under expenditure in 2007/08 R’000 NoteCompensation of Employees across Programmes 14,068 1P1: National Land Transport Information System and Arrive Alive 5,703

P2: Policy development projects 10,448 2P3: Under expenditure across all Sub Programmes 24,132 3P4: Transport Planning 5,397

P4: Integrated Delivery (rural transport) 21,375 4P4: Infrastructure Planning 16,083 5P4: Monitoring and Evaluation 4,485

P4: Sani Pass and Overload control facilities 38,221 6P4: Administration 148

P5: Freight logistics projects 9,765

P6: Rail feasibility study and other savings 23,096 7P6: Taxi scrapping (R7,2m) and transfers to SANTACO (R8,9m) 16,193 8P7: RAF restructuring and oversight projects 16,030 9P7: Ports Regulator 11,144 10

Total 216,288

30

Page 31: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportUnder expenditure in 2007/08

1. The National Land Transport Information System and Arrive Alive project was not funded and the department identified and shifted savings within the department late during the 07-08 Financial Year.

2. The development of several policies was delayed due to sub standard bids received and delays in the payment to service providers who still have some work to complete.

3. The major areas and reasons for under expenditure in the Programme are detailed below:

3.1 Economic Regulation (Road Transport) R1,3 million:

Funds have been allocated to this component for operational expenditure but no posts could be filled in time in this regard to perform the functions attached to this post - this was after the resignation of the project leader.

3.2 Standards Regulation R3,4 million:

The Director attached to this component was only appointed during the second half of the financial year and he was only able to appoint the officials in the vacant posts during the second half of the financial year which had a negative influence on the operational expenditure (under expenditure). The appointees also had to be trained in service.31

Page 32: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportUnder expenditure in 2007/08

3.3 Traffic Safety Systems R5,113 million:

This under expenditure relates to the non transfer of the eNaTIS project to the RTMC.

3.4 Rail Transport Regulation R2,323 million:

Non appointment of any official in this component. One official in the then Rail Economic Regulation handled the establishment of the Rail Economic Regulator.

3.5 Civil Aviation Security R1,625 million:

A service provider has been appointed at a late stage to develop a security system for the OR Tambo Airport. The appointment has only been finalised in the 2008/09 financial year.

3.6 Maritime Safety and Bilateral Affairs R4,716 million:

Lack of capacity limited the development of the Maritime Safety Coordination Centre in its full context. 32

Page 33: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportUnder expenditure in 2007/08

3.7 Aviation and Maritime Investigations R3,483 million:

Funds have been allocated for the Commissioner of Civil Aviation which did not take place in the 2007/08 as clarity did not exist whether this function must be transferred from the SACAA to the Department. The FAA investigation and report and the published Civil Aviation Bill of 2008 give clear guidance in terms of the way forward with regard to this matter. It is envisaged that the Bill will be passed through the Parliamentary process during this Parliamentary session.

4 & 5. The Programme did not have enough funds to procure the required number of bicycles (500,000), which delayed the tender process. Most of the under expenditure was earmarked to purchase 60,000 bicycles and a rollover of R30,98 million was applied for. The remaining funds were earmarked for the National Airports Development Plan (NADP) and a rollover of R7 million was applied for. The appointment of an appropriate service provider too eight months for the NADP.

The Programme also applied for other rollovers of R6,5 million for projects that were delayed and longer term projects, such as the National Transport Master Plan, development of the National Land Transport Bill, and the development of guidelines and standards for monitoring of Transport Planning.33

Page 34: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportUnder expenditure in 2007/08

6. Amounts budgeted to assist Provinces with the construction of the Sani Pass and overload control facilities could not be paid because the budgets were not included in the Division of Revenue Act, and because there was uncertainty about the appropriate method of payment and ownership of the assets.The Treasury recommended that the Department should apply to roll over the funds and have the funds allocated to the Provinces via the Division of Revenue Act or Provincial Infrastructure Grant.

7. The Department, in collaboration with the Treasury’s PPP Unit, invited Requests for Proposals in September 2007, and planned to appoint service providers to develop the feasibility study for which R20 million was earmarked. The bids that were received were referred to the SARCC as the SARCC would be in a better position to manage the project. The Department applied to roll over the R20 million and to increase the transfers to the SARCC by that amount.

8.1 All of the funds that were budgeted for the scrapping of taxis were paid to the Scrapping Administrator by 31 March 2008. R7,25 million could not be utilised by 31 March 2008, because the scrapping process was slowed down to accommodate the available budget.34

Page 35: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of TransportUnder expenditure in 2007/08

8.2 The Department withheld transfer payments to SANTACO amounting to R8,9 million, because SANTACO could not provide progress reports and financial statements as required in the contract.

9. An amount of R14 million could not be spent on the RAF restructuring because Regulations had to be developed for the RAF Amendment Act before various provisions dealing with the liability of the RAF could come into operation. There were also delays due to the ill health of the Minister of Health, who has to be consulted on certain provisions.

10. The Ports Regulator only became operational late in the financial year, because the CEO could only be appointed in March 2008. During the year, effective governance structures were developed, and premises were secured and equipped. The Department made payments on behalf of the Ports Regulator, but could not transfer the amount budgeted, because the entity only became operational in March 2008.

35

Page 36: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Programme 2.

Transport Policy &

Economic Regulation

Department of

Transport

36

Page 37: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09Policy Analysis

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Approved Taxi Recapitalization Policy Cabinet approval May 2008

R 250 000

Approved white Paper on National Maritime policy

Cabinet approval June 2008

R 50 000

Integrated policy across three departments

(Transport Environment and Health Charter)

Engagement and signing of the Charter by Ministers of DOT, DOH and DEAT

January 2009

R 500 000

Legislation

Cross-Border Amendment Bill, 2008 Promulgation May 2008

R 20 000

Approved National Road Traffic Amendment Bill

by Parliament

Promulgation

Legislation Implementation

May 2008

R 30 000

Approved National Land Transport Bill by Parliament

Promulgation

Legislation Implementation

May 2008

R 30 000

37

Page 38: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09Economic Analysis

Key Performance Indicator

Key activities Target Date 2008/09

Budget

Gazetted

B-BBEE Charter

through DTI –Section

12 & 9

Complete alignment of charters

Present documents to the

Transport Sector BEE Steering

Committee for endorsement

Submit and present documents to the DG, Minister & DTI for approval & gazetting

May 2008 R 100 000

Successful B-BBEE Charter Launch

Content Management July 2008 R 1M

DoT approved, mass communicated, and quantified cost of transport, aimed at FDI attractions

Consultation with industry

Tabling at Transport Lekgotla

Tabling at Cabinet Lekgotla

May 2008

May 2008

July 2008

R 1M

38

Page 39: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09Economic Analysis (Conti..)

Key Performance Indicator

Key activities Target Date

2008/09

Budget

Approved

Infrastructure

Funding Model

Development of models, testing of models with various industry stakeholders, adoption and utilization of model by various stakeholders

July 2008 R 800 000

Economic Regulation Establishment of a Single Transport Regulator

Revision of the draft concept document

March 2009

R500 000

Establishment of Rail Economic Regulator

Amalgamation Plan for Transport regulators

Sep 2008

R 12 m

Rationalization of Aviation Regulators

Cabinet approval of Board Dec 2008 R200 000

39

Page 40: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Transport Policy & Economic Regulation 2009-10

Key Performance Indicator Key activities Target Date 2009-10

Budget

A Cycling Policy

Animal Drawn Transport Policy

Walking Policy for South Africa

Congestion Pricing Policy

Literature Review

Public Consultation Approval by Cabinet

May 2009

Sept 2009

October2009

June 2009

R 500 000

R200 000

R500 000

R800 000

Sustainable Mobility Strategy: 2010 & Beyond

Approved Aviation GHG Emissions Policy

Approved Energy Efficiency Framework for the transport sector.

Cabinet Approval

Full compliance with UNFCCC

Obtain EXCO approval of draft strategy

October 2009

Sept 2009

October 2009

R500 000

R 2 million

R 1 million

Drafting of 3 Merchant Shipping Bills

ATNS Amendment Bill 2008

Disseminate the final draft

June 2009 R 60 000

R 30 000.

40

Page 41: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Transport Policy & Economic Regulation 2010-11

Key Performance Indicator

Key activities Target Date

2010-11

Budget

Transport Policy

Intervention on key 2010 Soccer World Cup Initiatives

Vehicle Scrappage Policy

Stakeholder Consultation

Development of implementation plans

Public Consultation

Cabinet Approval

March 2009

June 2011

July 2011

R 300 000

R700 000

R1M

Updated National Paper on Transport Policy

Literature review

Stakeholder consultation

Cabinet Approval

February 2009

R600 000

Policy on the control of emissions from road-going vehicles.

Literature review

Stakeholder consultation

Cabinet approval

February 2011

R 500 000

41

Page 42: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Programme 3

Transport Regulation and Accident & Incident Investigation

Department of

Transport

42

Page 43: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key Activities Target Dates

2008/09 Budget

20% Reduction in Road

Fatalities – FIFA Host Cities

Regulatory Framework – AARTO including establishment of Road Traffic Infringement within RTMC

Monitor implementation of Road Safety Strategy.

Implementation of the Adjudication System.

March 2009

February 2009

R 60 M

Component for MIB’s Compliance established

Capacity to process 3000 buses per annum

Streamline buses for vehicle compliance testing.

Expedite homologation process.

March 2009

R 6 M

Apply to DOL – establish road traffic law enforcement services as essential services.

Consultation with treasury and Department of Public Services and Administration.

March 2009

R 2 M

43

Page 44: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key Activities Target Dates

2008/09 Budget

Specific Dispensation to

Expeditiously process 2010

Applications for regulatory

Compliance

Value Chain arrangement to prepare for 2010, to fast track applications for licenses, OLB’s etc.

March 2009

R 3 M

Establishment of the Office of the Civil Aviation Ombudsman

Structuring of an independent

Ombudsman separate from

the ambit of the Civil Aviation

Authority; Drafting and promulgation of legislation

Dec 2008 R 2 M

Draft Plan for Manufacture,

Repair and Maintenance Division of the Aviation industry in line with industrial policy

Develop Terms of Reference

Consultations with key stakeholders.

March 2009

R 2 M

44

Page 45: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key Activities Target Dates

2008/09 Budget

Framework developed Low

Cost Carrier infrastructure &

Support supply of transport

Access to airports.

Develop framework for Low Cost Carrier market – transport access to airports.

February 2009

R 2 M

Aviation Sector Operational Plan – 2010 Event

Updated Aviation Sector Operational Plan – 2010 Event

Coordination of aviation related activities in support of the 2010 World Cup - Aviation Sub-Sector Task Team.

March 2008

March 2009

R 1 M

AFI RAN – Sign MOU between Minister and ICAO

Negotiate the text of the MOU with ICAO. Signing of the MOU.

Hosting of the event.

April 2008

Nov 2008

R 5 M

Training of 120 Seafarers

for placement on ships

Joint cooperation with interested governments to set up an International Maritime University in Cape Town.

April 2008 R 18 M

45

Page 46: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Transport Regulation and Accident & Incident Investigation

2009-10Key Performance Indicator Key Activities Target

Dates2009-10 Budget

Increased number of workstations.

Introduction of online transactions – Phase 2 Enhanced transaction integrity

Expanded VPN supreme network (phase 2) local authorities.

eNaTIS. Introduction and enhancement of ICT according to the Best Practice Model (BPM) at registering authorities (RA’s), Driving licence testing centre’s, (DLTC’s) and vehicle Testing Stations (VTS’s).

March 2010

eNaTIS transaction fees

Aircraft emission and Aircraft noise management strategy

Implementation of the Noise and Aircraft Emission Plan

February 2010

R0.5 M

Enacted Maritime Transport Security legislative framework

Risk assessments report and maritime security plans approved by the DG/Minister

NQF level 5 maritime security unit standards developed

Regional/Cooperative LRIT management capability developed

Trials on Vessel Traffic System (VTS) in the Maritime Security Coordination Centre (MSCC) conducted

Maritime security in South African ports Nov 2009

May 2009

July 2009

Oct 2009

Nov 2009

R0.5 M

R1,5 M

R0.5 M

R0.5 M

R1.5 M

Training of 120 Seafarers

for placement on ships

Joint cooperation with interested governments to set up an International Maritime University in Cape Town.

April 2008

R 18 M

46

Page 47: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Transport Regulation and Accident & Incident Investigation

2010-11Key Performance Indicator Key Activities Target

Dates2010-11 Budget

Inspection of centers (As required by the NRTA)

Improve workflow efficiency.

Inspection DLTC, VTS’s and dangerous goods operators, drivers, consignors, consignees and packaging manufacturers

March 2010

R3 M

Promotion and management of South Africa’s and Africa’s international aviation interests in terms of performance agreement

Re-election to the Council of the International Civil Aviation Organisation

October 2010

R7 M

Withdrawal and Re Allocation of Unused Capacity on Key Routes

Continued implementation of the Airlift Strategy

March 2011

R3.5 M

Maritime security in South Africa’s ports

Arriving vessels for 2010 FIFA World Cup effectively monitored through the Vessel Traffic System (VTS)

The Regional/Cooperative LRIT Data Centre fully -operational in accordance with IMO specifications.

March 2010

July 2010

R3 M

R4 M

47

Page 48: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Programme 4.

Integrated Planning & Intersphere Coordination

Department of

Transport

48

Page 49: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Integrated Infrastructure Plan

report

Adopt info sharing protocol

100% integration of existing and available sectoral GIS information

Finalise plan

April 08

May 2008

July 08

R0,5m

Approved National Land Transport Act development

Submit draft Bill to Cabinet and Parliament

Promulgation

May 08

Oct. 08

49

Page 50: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Consolidated Ops Plan for 2010 Consolidate HCOP’s April 08 R2m

National Transport Ops Plan Develop detailed NTOP for 2009 (Confed. Cup) and 2010 (WC)

Dec 08 R3m

Integration of 2010 priorities with GEF initiatives

Integrate 2010 priorities with GEF initiatives and monitor performance

June 08 $10,9m (donation)

National Airports Development Plan (NADP)

A plan that will guide the development airports in the country.

Completion of Phase 2 and 3 of the NADP

Cabinet approval of NADP

September

2008

October

2008

R7m (to be roll-over from current) or budgeted in next years budget

2010 FIFA World Cup™

50

Page 51: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

NMT rollout framework for 2010

Develop the framework

Align 2010 NMT projects to the framework

Sept 08

March 09

R1m

2010 info on GIS Host on a web-based & GIS platform

April 08 R0,5m

M & E Programme Strengthen M & E Programme

July 08 R15m

OR Tambo International Road Transportation Study

Proposed road network improvement and expansion.

Proposed phasing and estimated corresponding costs.

Sept 2008 R1m

2010 FIFA World Cup™

51

Page 52: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport Quick Wins for 2008/09

Key Performance Indicator

Key activities Target

Dates

2008/09

Budget

Bicycle manufacturing plant

Investigate feasibility

Sign agreements

March 2009

R2,1m

20 000 bicycles procured and distributed

Procure and distribute 20 000 bicycles March 2009

R25m

Bicycle Master Plan for Sekhukhune (Limpopo)

Scoping study reports, District maps

Bicycle master Plans

March 2009

R800 000

Rural development mapping

Mapping using the GIS platform March 2009

R3m

Implementation of the rural transport strategy

Roll-out of the rural transport system in

Bophirima

Access road to Thusong service centre

restored

Maluti A Phofung: 3 Pedestrian bridges

constructed

Chris Hani: Public transport facilities

March

2009

R2m

R2m

R2m

52

Page 53: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Integrated Planning & Intersphere Coordination

2009-10

Key Performance Indicator Key activities Target

Dates

2009-10

Budget

Data requirements assessed

Data capturing system designed

Data aligned to GIS

ITP data operational

Populate ITP data on GIS

December 2009

R10m

Efficient transport operations for the 2009 Confederations Cup

Updated transport Operational plans for 2010

Call for 2009 Priority Statements

Implement transport operations for the 2009 Confederations Cup

June 2009

December 2009

R3m

90% of information from participating roads authorities populated into system

Piloting of a basic system with 5% of developing municipalities

Roll-out/Support to 50% of developing municipalities

Development of a National Road Asset Management System

March 2010

May 2009

July 2009

R 1m

R5,5 m

R20 m53

Page 54: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Integrated Planning & Intersphere Coordination

2010-11

Key Performance Indicator Key activities Target

Dates

2010-11

Budget

Business plans approved

Progress reports completed

Approved Comprehensive ITP’s

Integrated transport plans for 12 DPA’s as per NLTA

June 2011 R30m

100 % of unclassified road network classified

Reclassification of the road network as per RISFSA classification guidelines

March 2011

9 Provincial RTMS workshop run

1 National workshop

Auditor accreditation

Awareness campaigns in the roll-out of the RTMS

April 2010 to November 2010

R500 000

National Airports Development Plan (NADP)

Implementation of NADP recommendations

Ongoing

54

Page 55: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Programme 5:

Transport Logistics and Corridor Development Branch

Department of

Transport

55

Page 56: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09

Key Performance Indicator

Key activities Target

Dates

2008/09

Budget

Host City Freight Plans

Engage Confed Cup host cities on plans

Design host city freight routes for Confed Cup

Consolidate various municipal precinct freight plans

Apr 2008 R 1m

Freight Movement Optimisation plans for top freight border posts

Oshhoek FMOP, Lebombo FMOP; Beit Bridge FMOP; Ramatlhabama FMOP; Nakop FMOP; Maseru Bridge

Audit current freight movement patterns at all identified border posts

Recommend action and Implement

June 2008

Sept 2008

March 2009

R1 m

National Freight Monitoring Framework (NFMF)

Landscape on corridor freight movement

Develop business Challenges and Gap Analysis

Sept 2008

R8.4m

Department of

Transport

56

Page 57: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09

Key Performance Indicator

Key activities Target

Dates

2008/09

Budget

Institutional Frameworks and Legislative review of the freight sector

NFLS detailed implementation plan

Rail Act and Regulations

As is Institutional mandate and roles matrix for freight regulatory and service delivery functions in the state

Regulatory and institutional structure options aligned with policy and strategy

Private sector participation in infrastructure and operations framework and strategy

Appropriate Freight Investment plans

Network delivery mechanism

Detailed implementation plan of NFLS elements that are not dependent on the legislative changes required

Development of legislative mandate

Engagement with State Law Advisors

Cabinet Approval for consultation

Parliamentary process

Jun 2008

Jun 2008

Jul 2008

Jul 2008

R5 m

R 2 m

Department of

Transport

57

Page 58: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Transport Logistics and Corridor Development

2009-10

Key Performance Indicator

Key activities Target

Dates

2009-10

Budget

National Freight Filing Act and Regulations

Act promulgated and compliance enforced March 2010 R2 million

NFIS Analyse and evaluate available freight information

Establish National Freight Data Warehouse

Develop and design intelligence platform Architecture

Integrate with transport business intelligence and other existing systems

System interoperability standards in place

Plan and design an Industry Owned Cargo information and tracking system linked up to the NFIS

National Freight Monitoring Framework in place

May 2009

Jul 2009

Dec 2009

March 2010

Mar 2010

Mar 2010

Mar 2010

R120 m

Sub-sectoral strategies (National Freight Master Plan)

Develop plans and frameworks for integrated freight planning

Develop an institutional delivery mechanism for freight planning

March 2010 R10 m

Department of

Transport

58

Page 59: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Transport Logistics and Corridor Development 2010-11

Key Performance Indicator

Key activities Target

Dates

2010-11

Budget

NFIS Roll-out National Monitoring Infrastructure across the various networks

Roll-out and acquisition of software and hardware for the Data Warehouse and capturing stations

Integrate and implement an Industry Owned Cargo information and tracking system linked up to the NFIS

March 2011 R179 m

National Centre for Logistics Excellence (NCLE)

NCLE established

Priority skills identified

Standards & Curricular developed

March 2011 R5 m

Sub-regional integration (Border Operations)

Implementation plan for Ports of Entry (Border Operations Strategy)

Regional corridor Structures

Regional Transport Framework

March 2011 R15 m

Department of

Transport

59

Page 60: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Programme 6

Public Transport

Department of

Transport

60

Page 61: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator

Key activities Target

Dates

2008/09

Budget

Operational Plans for 2010 World Cup

Rail

Bus

Taxi

Metered Taxi

PT Operational Plans alignment to Host Cities Operational Plans

Engagement

Determine Vehicle requirements

Secure Guarantee to purchase buses

April 2008 SARCC & R4.5M

Rail: Improved loading capacity and rolling stock reliability

Accelerated Rolling Stock Programme:

272 Coaches: General Overhaul

425 Coaches: Refurbishment

March 2009

Moloto Rail Development Corridor

Update Municipal IDP and ITP

Environmental Impact Assessment

June 2008

Sept 2008

PT Operational Modal plans for 2010 FIFA World Cup

61

Page 62: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator

Key activities Target

Dates

2008/09

Budget

Rollout of improvements to security related infrastructure

Construction of railway police contact points at: Gauteng-Krugersdorp;Stretford; Springs; Kempton Park; Saulsville and Bel Ombre, KZN – Ottawa, Eastern Cape – East London and Mount Ruth Swartkops.

July 2008

Business & Merger

Integration Plan

Amendments to Legal Succession Act to include Autopax

Promulgated Alignment

with Rail Plan Strategy

Business Plan,Investment Plan and turn around strategy for long distance rail

Cabinet approval

Alignment of Shosholoza Meyl services and Autopax services and establishment of pricing strategy

Improve network access and reduce haulage charges through negotiations with Transnet

March 2008

Aug 2008

Nov 2008

SARCC

Second Phase of passenger rail consolidation

62

Page 63: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Establish Autopax under

SARCC

Funding requirements for

2010 bus needs:

Treasury guarantee

Private sector funding

Completion of the Business

Plan

Order buses

Obtain Treasury guarantee

and secure investment funding

Enabling legislation (Legal

Succession Act)

Recruitment of key personnel

and drivers

Operational plan for Autopax

April 2008

May 2008

June 2008

June 2008

Aug 2008

National Treasury

Acquisition of Autopax

63

Page 64: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Optimal service delivery model Implemented

Permit conversion process,

(including outstanding

SLP/BLC applications and

semi-legal operators

Elimination of backlog of

outstanding transfers,

replacements, renewals.

Audit capacity constraints &

processes at OLBs

Develop optimal business

processes at OLB

Regularisation of seating

capacity alignment to OLB

Finalise conversion process:

Outstanding backlog

Semi-legals

SLP and BLC

unprocecessed applications

April 2008

April 2008

July 2008

March 2008

R48m

Turnaround Strategy for OLB’s

64

Page 65: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Public Transport 2009-10

Key Performance Indicator Key activities Target

Dates

2009-10

Budget

Extension of the commuter rail line from Khayelitsha to Baden Powell.

Construction of the rail infrastructure, two new rail stations, four road over rail bridges, four pedestrian bridges, the transport network connectivity and two transport interchanges completed and new rail service commissioned.

May 2009 R 284 m

Taxi Sector training and development

Training and development of drivers; maintenance and repair personnel

November 2009

R4m

Lift Moratorium on Operating Licence

Municipal based Operating licence strategy

OLB systems in place

April 2009 R6m

65

Page 66: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Public Transport2010-11

Key Performance Indicator

Key activities Target

Dates

2010-11

Budget

Autopax Transfer of assets to address 2010 legacy

Allocate vehicles for rural transport service

Alignment with Shosholoza Meyl

December 2010

R30m

Implementation of accessible PT plan in the next 4 to 6 cities as part of Phase 1 networks

Implementation of accessibility Improvements by municipalities

Project plans developed

Progress reports submitted

March 2010 and ongoing

Law Enforcement (Continuation of Rollout)

Availability of Law enforcement officers

IT interfacing to remote law enforcement operations

Shift in focus to Road based Public Transport

Ongoing R200

Construction of the Moloto Rail Corridor

Facilitate the establishment of an Implementation Office at SARCC for the construction of the primary rail network

April 2010

66

Page 67: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Programme 7

PUBLIC ENTITY OVERSIGHT AND BORDER CONTROL

Department of

Transport

67

Page 68: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Public Enterprises reporting to DoT

•South African Rail Commuter Corporation•Road Accident Fund•South African National Roads Agency Limited•Road Traffic Management Corporation•Railway Safety Regulator•Cross-Border Road Transport Agency •South African Civil Aviation Authority •Air Traffic and Navigation Services Company •Airports Company South Africa •South African Maritime Safety Authority•Urban Transport Management

Department of

Transport

68

Page 69: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09

Key Performance Indicator

Key Activity Target Dates

2008/09 Budget

Amendment Bill and Regulations finalized 

Communication Plan for New Road Accident Benefit Scheme

Complete consultation on assessment method

Promulgate Amendment Act and Regulations 

Finalise MOU between RAF and DoT

Develop & roll-out communication plan

April 2008

June 2008

April 2008

Aug2008

R1m

R12m

Finalize CBRTA Amendment Act 

Finalize CBRTA Amendment Bill

Promulgation of Amendment Act.

March 2008

July 2008

Approved framework for financial and governance oversight

Formulate Entity Oversight Model to oversee entities’ performance 

August 08

  

R300K

Department of

Transport

69

Page 70: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09

Key Performance Indicator

Key Activity Target Dates

2008/09 Budget

Shareholder’s compact s / Performance Agreements Strategic plans / Corporate Plans

Evaluate and align submitted Strategic / Corporate Plans with DoT strategic goals and priorities – annual revision 

Revise and facilitate signing of Shareholder’s Compacts/Performance Agreements – annual revision

July

2008

 

 

 Aug 2008

Effective coordination of PE activities in Border Control

Clarify roles and mandates of PEs. Aug 2008

Department of

Transport

70

Page 71: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

PUBLIC ENTITY OVERSIGHT AND BORDER CONTROL 2009-10

Key Performance Indicator

Key Activity Target Dates

2009-10 Budget

Border Control Oversight framework

Integration of transport border control matters within the national agenda.

March 2010

R1.6

RAF Restructuring Implementation of new fault based system - pilot

Quarterly Reports

R5

Shareholder’s Compact and Performance Agreements & Corporate Plans/Strategic Plans

Shareholder’s compact/Performance Agreement to include by reference the strategic and operational plans of entities.

Annually – June 2010

Quarterly Financial oversight

Identification of intervention measures where necessary.

Quarterly R1.4

Department of

Transport

71

Page 72: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

PUBLIC ENTITY OVERSIGHT AND BORDER CONTROL 2010-11

Key Performance Indicator

Key Activity Target Dates

2010-11 Budget

Entity Oversight Framework

Implement electronic performance management system for all entities.

March 2011 R2m

Evaluation of Quarterly and Annual Report

Proper implementation of Ministerial directives

Timely scheduling of AGMs.

Quarterly and annually

Shareholder’s Compact and Performance Agreements & Corporate Plans/Strategic Plans

Shareholder’s compact/Performance Agreement to include by reference the strategic and operational plans of entities.

Annually – June 2011

CBRTA Restructuring Implementation of Turnaround Strategy

Quarterly Report

R2m

Department of

Transport

72

Page 73: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Planned projects/activities over next three years

Management Services

Department of

Transport

73

Page 74: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Reduction in vacancies to 17% by March 2009

Consultation with EXCO and organized labour on amendments to policies and processes

Formulation of a Retention Strategy

June 2008

June 2008

R300,000.00

Enterprise Content Management Solution (ECM)

Pilot deployed in the selected offices.

File plan drafted

June 2008 (Pilot)

R5m

74

Page 75: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator Key activities Target

Dates

2008/09

Budget

Accessibility of DOT information (i.e. email, voice, data etc)

Upgrade of DOT Local Area Network (LAN) and implementation of Virtual Private Network (VPN).

July 2008 R8m

Compliance with the Security Policy and Physical Security Standards

Conduct physical security assessment, formulate implementation plan.

Implement measures for physical security and access control

Sept 2008

March 2009

R4m

Enhanced Reception Service that facilitates Citizen and Stakeholder access to documentation and information

Formulate a plan for information flow, logistics, and distribution of information.

July 2008 R50,000.00

75

Page 76: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Management Services

2009-10

Key Performance Indicator Key activities Target

Dates

2009-10

Budget

Develop capacity of youth to address skills requirements beyond 2010

Ensure training of at least 50% prospective transport workers.

March 2010

R1m

Transport studies within FET curriculum

Fully integrated transport programme at FET level

March 2009

R 500,000

Adoption of IT Governance Framework and compliance to government MSP requirement

Finalization of implementation of improved security and governance compliance.

Disaster Recovery Plan (DRP) implementation.

June 2010

March 2010

R400,000

R4m

76

Page 77: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Management Services

2010-11

Key Performance Indicator Key activities Target

Dates

2010-11

Budget

Develop Capacity building plan to address 2010 skills requirements in collaboration with TETA

Ensure training of at least 60% prospective transport workers.

March 2011

R1,5m

Resourcing Strategy Develop optimal resource capacity levels through devising frameworks to manage talent

March 2011

R1.2m

Develop and implement a culture change strategy

Improved integration and cohesion; increased knowledge sharing and improved teamwork

March 2011

R1,4m

77

Page 78: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

DEPARTMENTAL STRUCTUREDEPARTMENTAL STRUCTURE

• Total Establishment: 1020

• 668 posts activated

• 352 posts inactive

• Vacancy rate 35.48%

• Current turnover rate:10,67% (46)

• Number of internal promotions (Apr – March ’08): 32

78

Page 79: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

EMPLOYMENT EQUITY STATUSEMPLOYMENT EQUITY STATUS

Total Post: 668

Filled: 431 (64,52%)

All LevelsBLACKS: 368 (87.70%)

– African: 349 (80.97%)– Coloureds: 13 (3.02%) – Indian: 16 (3,71%)

WHITE: 53 (12.30%)

DISABLED: 9 (2%)

WOMEN: 228 (52.9%)

– Level 1 - 10: 163 (71,49%)– Level 11 – 12: 33 (14,47%) – Level 13 above - 32 (14,04%)

SMS onlyBLACKS: 72 (85,71%)

– African:57 (67,86%)– Coloureds: 3 (3.57%) – Indian: 12 (14.28%)

WHITE: 12 (13.41%)

DISABLED: 1 (0.23%)

WOMEN: 32 (39%)

79

Page 80: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

VACANCY STATUSVACANCY STATUS

BRANCH/COMPONENT

SALARY LEVELS TOTAL POSTS ON ESTABLISHMENT

FILLED POSTS VACANT POSTS

TRANSPORT MINISTRY Senior Management Levels 13-26 5 5 0

Middle ManagementLevels 11-12 3 3 0

Lower ManagementLevels 1-10 8 8 0

SUB TOTAL 16 16 0

OFFICE OF THE DIRECTOR-GENERAL

Senior Management Levels 13-26 5 5 0

Middle ManagementLevels 11-12 3 2 1

Lower ManagementLevels 1-10 6 5 1

SUB TOTAL 14 12 02

COMPONENT: COMMUNICATIONS

Senior Management Levels 13-26

6 2 4

Middle ManagementLevels 11-12

10 3 7

Lower ManagementLevels 1-10

14 7 7

SUB TOTAL 30 12 18

80

Page 81: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

BRANCH/COMPONENT SALARY LEVELS TOTAL POSTS ON ESTABLISHMENT

FILLED POSTS VACANT POSTS

COMPONENT: FINANCIAL SERVICES

Senior Management Levels 13-26

11 8 3

Middle ManagementLevels 11-12

8 6 2

Lower ManagementLevels 1-10

52 39 13

SUB TOTAL 71 53 18

BRANCH: MANAGEMENT SERVICES

Senior Management Levels 13-26

19 10 9

Middle ManagementLevels 11-12

28 19 9

Lower ManagementLevels 1-10

111 75 36

SUB TOTAL 158 104 54

BRANCH: TRANSPORT POLICY AND ECONOMIC REGULATION

Senior Management Levels 13-26

21 9 12

Middle ManagementLevels 11-12

18 12 6

Lower ManagementLevels 1-10

28 19 9

SUB TOTAL 67 40 27

BRANCH; TRANSPORT REGULATION AND ACCIDENT AND INCIDENT INVESTIGATION

Senior Management Levels 13-26

18 14 04

Middle ManagementLevels 11-12

23 15 8

Lower ManagementLevels 1-10

81 56 25

SUB TOTAL 122 85 3781

VACANCY STATUSVACANCY STATUS

Page 82: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

BRANCH/COMPONENT SALARY LEVELSTOTAL POSTS ON ESTABLISHMENT

FILLED POSTS VACANT POSTS

INTEGRATED PLANNING AND INTERSPHERE COORDINATION

Senior Management Levels 13-26

19 10 9

Middle ManagementLevels 11-12

31 19 12

Lower ManagementLevels 1-10

39 23 16

SUB TOTAL 89 52 37

PUBLIC TRANSPORT Senior Management Levels 13-26

17 13 4

Middle ManagementLevels 11-12

10 6 4

Lower ManagementLevels 1-10

23 18 5

SUB TOTAL 50 37 13

TRANSPORT LOGISTICS AND CORRIDOR DEVELOPMENT

Senior Management Levels 13-26

10 4 6

Middle ManagementLevels 11-12

6 2 4

Lower ManagementLevels 1-10

17 5 12

SUB TOTAL 33 11 22

PUBLIC ENTITY OVERSIGHT AND BORDER OPERATIONS AND CONTROL

Senior Management Levels 13-26

7 4 3

Middle ManagementLevels 11-12

3 1 2

Lower ManagementLevels 1-10

8 4 4

SUB TOTAL 18 9 9

TOTAL668 431 237

VACANCY RATE35.48%

82

Page 83: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

AdvertisingPrepare advert & confirmation 3 daysProcurement 2 daysRun advertisement for 2 weeksExecutive Summary+-2 working days per post depending on the number of postsFinal 1 Month depending on the availability of managers & applications

received Short-listingPreliminary: 1 dayFinal: 1 Month depending on the availability of managers  TestsCompetency: Conducted within 2 weeks from date of scheduling PPA: On the date of interview  InterviewsA week after the Competency Assessment report is due

 Submission for filling of post5 working days (within HRM)

 Appointment Offer1 day Total3 Months

FILLING OF POSTS TIMETABLEFILLING OF POSTS TIMETABLE

83

Page 84: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

TURN-OVER ANALYSISTURN-OVER ANALYSIS

Current turnover rate: 10.67% Current turnover rate: 10.67% (46)(46)

Total posts Transfers

Levels 3-8 262 24 (16.03%)

Levels 9-12 268 15 (5.6%)

Levels 13-16 138 7 (5.07%)

Total 668 46 (10.67%)

84

Page 85: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

LEARNERSHIP RACE F M TOTAL

Public Admin A - 1 1

Road Transport Management A 4 2 6

TOTAL 4 3 7

LEARNERSHIPSLEARNERSHIPS

85

Page 86: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Internal BURSARIESInternal BURSARIES

RACE GENDER TOTAL

A W I C F M  

129 4 6 3 86 55 142

       

Active Bursaries 51

Not Active 71

Resigned from Public Service 3

Studies Completed 5

Transferred files 11

Withdrawn 1

TOTAL 142

86

Page 87: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

EXTERNAL BURSARIES - 2007EXTERNAL BURSARIES - 2007

87

Gender Race (total) Race (Demographic

s)

TOTAL

(716)

M: 421 (58%)

F: 295 (41%)

B: 564 (78%)

W:152 (21%)

A: 479 (66%)

C & I: 85 (12%)

Page 88: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

OVERALL TRANSPORT STUDENT OUTPUT: 2007OVERALL TRANSPORT STUDENT OUTPUT: 2007

STCDSTCD Total Total No.No.

ECOTDECOTD Total No.Total No. NCODNCOD Total No.Total No.

PhD 3 UNITE 1 B Eng (Civil) 1

M Eng 2 BSc Eng 2 Transport Management D

16

MSc Eng 1 MSc Eng - Road Transport Cert 13

B Phil 11 B Com (Hons) 5 ND Transport Mng -

M Phil 7 BSocSc (Hons) 4 B Tech Transport -

M Econ - MsocSc 2 Programme in Logistics

7

M Comm 2 M Tech - B Com log Mngt 5

M Comm Hons 1 M Com 1 B Com Hons Log Mngt 3

PGD 6 ND: Civil Eng 4

MCRP - Transport Economics 25

M Tech -

ND-CE 7

B Tech 4

N Dip -

M Dip Tech -

TOTAL 44 15 7488

Page 89: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

INTERVENTIONS TO REDUCE INTERVENTIONS TO REDUCE THE VACANCY RATE TO 17% BY THE VACANCY RATE TO 17% BY

MARCH 2009MARCH 2009

• Weekly monitoring the vacancy rate• Implementation of Retention Policy:

-Relationship management interventions

-Employee satisfaction survey

-Reward outstanding performers with scarce &

critical skills• Accelerated management development programmes• Streamline the short listing process• Outsourced response handling for posts below SMS

89

Page 90: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

JOB STANDARDIZATION / JOB JOB STANDARDIZATION / JOB EVALUATIONEVALUATION

• The job standardization process has been finalized

and related posts job evaluated,• JE Unit consulted the DPSA to seek clarity on some

issues raised by the JE Panel,• JE Panel to finalize all outstanding cases by end of

May 2008, • JE conducted in line with the Public Service

Regulations, 2001 and DPSA’s directives:– Departmental Job Evaluation Policy, – Benchmark similar posts within and against other Depts, – Job enrichment where applicable, – Implement DPSA’S benchmark job descriptions.

90

Page 91: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

STATUS OF PMDSSTATUS OF PMDS

Employees on salary levels 12 and lower

2007/08 performance cycle• Annual Performance Assessment finalized: 317• Outstanding: 0

Employees on SMS level

2005/06 and 2006/07 performance cycles

Moderation of performance ratings currently underway.

2007/08 performance cycle

Performance Agreement submitted: 69

Outstanding: 15

SMS members recently appointed: 4

91

Page 92: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Financial Services

Quick wins – 2008-09

92

Page 93: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09

Key Performance Indicator

Key Activities Target Dates 2008/09 Budget

Output: Complete financial statements of the driver’s license card Trading Entity for audit and publish Annual Report

Financial statements submitted for audit

Annual Report completed

Records written up for 2008

Financial statements

Audit Committee review

Annual report completed

April 2008

May 2008

May 2008

August 08

Trading Entity

Output: Operationalise the driving license card Trading Entity

Trading Entity complies with PFMA

New service provider

Monthly reports

Audit Committee appointed

Access to e NaTIS in place

April 2008

From April 2008

May 2008

May 2008

Trading Entity

93

Page 94: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09 (continued)

Key Performance Indicator

Key Activities Target Dates 2008/09 Budget

Output: Oversee contract management in the Department

Contract management overseen and reported on

Contract awarded

Monthly reports

Database established

Relevant staff trained

Contracts managed properly

April 2008

May 2008

July 2008

Sept 2008

Sept 2008

To shift funds

Output: Control environment risk assessment

Report on the risk assessment

Report and create awareness

Update risk register

June 2008

July 2008

R300,000

Output: Incorporate risk management in Performance Agreements

Amended Performance Agreements

Risk Register referenced

Information to be taken on

Update Agreements

Cross refer risk register

May 2008

June 2008

July 2008

IC

94

Page 95: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Quick Wins for 2008/09 (continued)

Key Performance Indicator

Key Activities Target Dates 2008/09 Budget

Output: Anti-corruption implementation plan

Availability of Anti-corruption implementation plan

Develop implementation planImplement the plan

May 2008March 2009

IC

Output: Implement BarnOwl audit software

Implementation of audit software & trained staff

Train staffElectronic / automated audit

working papers

April 2008April 2008

R200,000

Output: Conduct performance audits

Quality and timely performance audits

Conduct performance audits for 5 areas in Audit Plan

April 2008 to January 2009

IA

Output: Outsource Information Technology audit functions

Quality Information Technology audits

Two risk based Information Technology audit reports

June and November 2008

R500,000

95

Page 96: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Office of the DG

Department

of Transport

96

Page 97: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

2008/09 Business Plan

KPI Key Activities Target

Dates

2008/09

Budget

Flagship project committee set up and list of flagship projects approved

Institute project reporting framework

Establish criteria for flagship projects

Evaluate progress, make recommendation and report to EXCO

April 2008 100,000

Close-out report of completed flagship projects

Submit close-out report to EXCO within 1 month of project completion

Develop and communicate “lessons learnt” guidelines

Bi-annually

Fully functional M&E system for DoT Flagship Projects

97

Page 98: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Communications

Department of

Transport

98

Page 99: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Quick Wins for 2008/09

Output KPI Key Activities Target Dates

2008/09 Budget

Intensified messaging on Arrive Alive Campaign

Hard-hitting messaging on consequences of irresponsible road use (alcohol, speed, fatigue, non wearing of seatbelt and pedestrian safety)

Heightened communication during peak periods (Easter and Festive season)

Launch 2 new focused campaigns

April to March 2009

Reposition SANWIT

Launch of provincial charters

Organise and market Conference

Rebrand Sanwit coorporate identity

Package information on BEE oppportunities for 20101

June to March 2009

R2m

99

Page 100: Department of Transport MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008

Department

of Transport

Thank you

100