department of water and power city of los angeles renewables portfolio standard (rps) master plan...

17
Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

Upload: shonda-johns

Post on 17-Dec-2015

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

Department of Water and Power City of Los Angeles

Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities

October 9, 2006

Page 2: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

2

LADWP Generation Resources

HAYNES

HARBOR

CASTAIC

SCATTERGOOD

VALLEY

Page 3: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

3

LADWP RPS Master Plan

On December 13, 2005 LADWP management presented to the Board on how LADWP plan to meet the RPS goal of 20% by 2010

Six general areas that make up the Master Plan

– Existing resources – Consisting of Aqueduct, Hyperion digestion, Lopez microturbines, solar rooftops, landfill gas contracts, Wyoming Wind project, and purchases

– Planned resources – Consisting of Pine Tree Wind Project, Powerex Small Hydro, and the ongoing solar rooftops program

– 2004 LADWP RFP – Resource acquisition consisting of originally seven projects

– 2005 SCPPA RFP – Resource acquisition consisting of originally seven projects and now new 2006 SCPPA RFP that closes October 16th.

– LADWP Development – Resource development on LADWP owned properties.

– Transmission Developments – Consisting of the Pine Tree Transmission Line, new Tehachapi Transmission System, Green Path Project, and Southern Transmission System upgrade

DSM Assumptions – Use the Maximum Achievable Level

Page 4: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

4

From Northwest

Hydro

Wind

Biomass

Landfill Gas

Waste to Energy

Solar

Geothermal

TransmissionConstraint

Location of Proposed Renewable Energy Projects and Existing Transmission Constraints

Page 5: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

5

0%

5%

10%

15%

20%

25%

2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Re

ne

wa

ble

Ge

ne

rati

on

, GW

h

Hydro

Biomass

Geothermal

Wind

Solar

Mix

Projected Resources by Percent of Load (Sep 5, 2006)

20% by 2010 Goal

Existing

2005 SCPPA RFP

2004 LADWP RFP

Planned

LADWP Development

Page 6: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

6

Planned and Developed Renewable Resources

Pine Tree Wind Project (120 MW)

– Completed draft RFP specification for BOP work.

– A final draft RFP specification for design build of the 230 kV transmission line is complete.

– Barren Ridge switching station under construction.

Waste to Energy Conversion – Proposed four 25 MW (total of 100 MW) Municipal Solid Waste to energy conversion technology developments with Los Angeles Bureau of Sanitation. The projects will be located in Los Angeles and the in-service dates are projects to be 2010 through 2013.

Concentrated Solar Power – Proposing two 125 MW CSPs for development by LADWP on owned lands with transmission access and tentative in-service dates of 2010.

Geothermal – 50+ MW of geothermal development in the Salton Sea area on owned land with tentative in-service date of 2012.

Page 7: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

7

MAP 1SOLAR RESOURCE

MAP 4

MAP 3

MAP 2

Page 8: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

8

INYO-RINALDI

TRANSMISSION

LINEINDEPENDENCE

LONE PINE

BIG PINE

MAP 2SOUTHERN OWENS VALLEY

Page 9: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

9

MOJAVE

ADELANTO SWITCHING STATION

BARREN RIDGE SWITCHING STATION (PROPOSED)

INYO

-RIN

ALDI

TRAN

SMIS

SIO

N LI

NE

HARPERDRY LAKEKRAMER

JUNCTION

MAP 3HIGH DESERT

Page 10: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

10

MAP 4SALTON SEA

LADWP PROPERTIES

Page 11: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

11

Inyo - Rinaldi Line Upgrade Project

OWENS GORGE

COTTONWOOD

BARREN RIDGE

RINALDI

9 miles

81 miles

68 miles

76 miles

234 miles

INYO

SCE

CASTAIC

SYLMAR

NORTHRIDGE

71.6 miles

1. Reconductor Barren Ridge to Rinaldi w/ 1113 ACSS.

2. New line from Barren Ridge to Castaic w/ 1113ACSS.

OLIVE

500MW WTG

Pine Tree120 MW2007 COD

Wind 3100+ MW2009 COD

Wind 2150+ MW2008 COD

Barren Ridge

Pine Tree

Wind # 3 Substation

To Cottonwood/Inyo

To Rinaldi

To Castaic

Page 12: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

12

Inyo - Rinaldi Line Upgrade Project Information

Pine Tree Project Construction (1/2007 COD)

– Barren Ridge 230 kV Substation

– Pine Tree 34.5 kV Substation

– Barren Ridge – Pine Tree Line (10 Miles)

– Environmental Studies: Completed

Wind #2 Project Construction (10/2008 COD)

– Pine Tree 230 kV Bus

– Wind #2 – Pine Tree 230 kV (10 miles)

Wind #3 Project Construction (12/2008 COD)

– Wind #3 230 kV Substation

– Barren Ridge – Wind #3 230 kV Line (12 miles, 1113 ACSS conductor)

– Wind #3 – Castaic 230 kV Line (72 miles, 1113 ACSS conductor)

– Environmental Studies: Will be conducted by LADWP (need 2 years)

Re-conductor Barren Ridge – Rinaldi 230 kV line (12/2010 COD)

– 1113 ACSS conductor (76 miles)

Page 13: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

13

Southern Transmission System (STS)

Page 14: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

14

DC (STS) Upgrade Project Information

Upgrade Project Level:

– Recommended Upgrade: 480 MW (2400 MW rating)

– Upgrade cost & benefit expected to be shared by existing STS owners

– LADWP upgrade share: 286 MW (59.53%)

Upgrade Timeline:

– Project Rating Studies (12/2006)

– HVDC Control and Design Studies (12/2006)

– HVDC Equipment Installation (10/2008)

– 2400 MW DC Rating COD (12/2008)

Page 15: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

15

Palo Verde – Devers #2 and Green Path Project Lines

LADWP Transmission Project

IID Transmission Project

IID Transmission

Upgrades

ARIZONACALIFORNIA

Century

Upland

Victorville

Lugo

Mira Loma

Serrano

Valley

Devers

Mirage

Ramon

Indian Hills

Coachella

Ave 58

Bannister

Miguel I.V.ECSS

Highline

Midway

Palo Verde

Hassayampa

North Gila

Valley

Rancho Vista

Geothermal

San FelipeS.D.

Central

New 500kV Line

Existing 230/287kV Line

Rebuild/New 230/287kV

CAISO Meter Point

Existing 500kV Line

Palo Verde – Devers Line #2

Page 16: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

16

LADWP Green Path Transmission Project

Century

Upland

Victorville

Lugo

Mira Loma

Serrano

Valley

Devers

Mirage

Ramon

Indian Hills

Coachella

Ave 58

Bannister

Miguel I.V.ECSS

Highline

Midway

Palo Verde

Hassayampa

North Gila

Valley

Rancho Vista

Geothermal

San FelipeS.D.

Central

New 500kV Line

Existing 230/287kV Line

Rebuild/New 230/287kV

CAISO Meter Point

Existing 500kV Line

Page 17: Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006

17

LADWP Green Path Transmission Project

Project Plan-of- Service:

– 500 kV, 100 mile line from a new Indian Hills Substation (IID) to a new Upland Substation (LADWP – near Rancho Cucamonga)

– Expected project rating at 1200 MW (Phase 1 WECC rating process)

– Ownership: LADWP 80%, others 20%

– Project include upgrade about 40 miles of Victorville – Century 287 kV line 1 from Victorville to 500 kV.

– Projects Provides substantial system reliability improvement to the Grid

Project Timeline:

– Rating Studies and Reliability Assessment: 7/2004 – 12/2006

– Environmental Studies: 10/2005 – 6/2008

– Project Construction Period: 3/2009-10/2009

– Project COD: November 2010