design and manufacturing mman1130 final report · 4.1.10 conclusion ... the purpose of this report...
TRANSCRIPT
Design and Manufacturing MMAN1130
Final Report
GROUP THURSDAY-12-17-2
FIRST NAME
LAST NAME
ID
MARK
1 LIZA CHAO 3 4 6 3 3 1 9
2 JESSICA CHEN 3 4 6 1 9 5 8
3 GAVIN CHENG 3 4 6 3 2 2 8
4 ALVIN CHUNG 3 4 6 3 3 2 0
5 NADAV COHEN 3 4 6 0 6 9 6
Semester 1-2014
School of Mechanical and Manufacturing Engineering
The University of New South Wales
Page 1
Table of contents
1.0 Executive summary…………………………………………………………………..………….3
1.1 List of Illustrations………………………………………………………….……………4
2.0 Introduction…………………………………………………………………………….…………4
2.1 Purpose……………………………………………………………………….………….4
2.2 Background…………………………………………………………………….………...4
2.3 Scope……...………………………………………………………………….…………..5
2.4 Procedure …………………………………………………………………….………….5
3.0 Materials Selection ………………………………………………………………….……..…....6
4.0 Individual Components………………………………………………………….………….……7 4.1 Base……………………………………………………..…….………….….…..7
4.1.1 Conceptualisation…...………………………………………………..………7
4.1.2 Initial design prototype…...……………………………………………..……8
4.1.3 Final design prototype…...…………………………………………...…….8
4.1.4 Prototype manufacture…...…………………………………………..….…9
4.1.5 Prototype testing and analysis ................................................................9
4.1.6 High volume design…...……………………………………………..........10
4.1.7 High volume manufacture…...……………………………………………10
4.1.8 Economic analysis…...………………………………………………........11
4.1.9 High volume analysis…...……………………………………………...…13
4.1.10 Conclusion…...…………………………………………………...............13
4.2 Piston…...……………………………………………………...………………………14
4.2.1 Initial design prototype…...……………………………………………....14
4.2.2 Final design prototype…...…………………………………………........14
4.2.3 Prototype manufacture…...………………………………………...…...14
4.2.4 Prototype testing and analysis…...……………………………………..15
4.2.5 High volume design…...…………………………………………………15
Page 2
4.2.6 High volume manufacture…...……………………………………….…15
4.2.7 Economic analysis…...………………………………………….….…...16
4.2.8 High volume analysis…...……………………………………….…..….18
4.2.9 Conclusion…...………………………………………………….............18
4.3 Piston Housing…...………………………………………………………….………19
4.3.1 Initial design prototype…...………………………………………….…19
4.3.2 Final design prototype...………………………….…………................19
4.3.3 Prototype manufacture…...……………………………….……………20
4.3.4 Prototype testing and analysis…...…………………………..……….20
4.3.5 High volume design…...………………………………………...….….20
4.3.6 High volume manufacture…...……………………………..…………20
4.3.7 Economic analysis…...…………………………………………….......21
4.3.8 High volume analysis…...………………………………………..........22
4.3.9 Conclusion…...………………………………......................................23
4.4 Cover…...…………………………………………...…...………………….………23
4.4.1 Initial design prototype…...……..……………………………….…....23
4.4.2 Final design prototype…...………………………………………........23
4.4.3 Prototype manufacture…...……………………………......................24
4.4.4 Prototype testing and analysis..........................................................25
4.4.5 High volume design…...……………………….…………...................25
4.4.6 High volume manufacture…...……………...……………………..…26
4.4.7 Economic analysis…...…………………………….............................27
4.4.8 High volume analysis…...…………………………............................28
4.4.9 Conclusion…...……………………………….....................................28
4.5 Valves…...………………………………………….…...…………………………29
4.5.1 Initial design prototype…...………………………………………..….29
4.5.2 Final design prototype…...…………………….……..........................29
4.5.3 Prototype manufacture…...…………………………...……………...29
4.5.4 Prototype testing and analysis…...………………………………..…30
Page 3
4.5.5 High volume design…...……………………………..........................30
4.5.6 High volume manufacture…...…………………………..………..…31
4.5.7 Economic analysis…...……………………………..…………..........32
4.5.8 High volume analysis…...……………………...................................32
4.5.9 Conclusion…...…………………………...........................................33
5.0 Conclusion…...……………………………......………………………………..…33
6.0 Reflection…...…………………………..………………………………………….34
7.0 References…...…………………..…………………………………………..……35
8.0 Contributions….…………..…………………………………………………….…37
9.0 Appendix…………………..…………………………………………………….…38
1.0 Executive summary
The purpose of this report is to detail the process and analysis of designing and
manufacturing a PP175 pneumatic vertical displacement pump prototype in accordance
to ‘Solo Pump Australia’s’ specifications. It also features the method of manufacture and
design for a high volume design concept of the pump based on the outcome of the
prototype when tested. Group members initially had individual concept sketches of the
pneumatic pump. The best design was chosen as the basis of the prototype design for
the entire group. The group strived to attain an easily manufactured, cost effective
design with maximum volume displacement within the specified range of 20-22.5cm3.
The dimensions of each individual component were based on the specifications given
by ‘Solo Pump Australia’. Each member was designated a component of the pump to
construct an engineering drawing, routing chart and routing sheet. Following this, each
member was then allocated another team members component to manufacture the part.
Upon completion of each individual component the pump was assembled and tested on
a jig at 250rpm. From the results during testing, these observations were taken into
consideration when developing a modified concept design for high volume
manufacturing. The observations made during testing were that the pump had
Page 4
performed effectively only when air was prevented from entering the inlet valve due to
gravitational complications on the ball bearing. The pump managed to blow up the
balloon in a short period of time, thus proving its success. A new design for the valve
was then constructed and slight improvements were made on the other individual
components of the pump, increasing its lifespan and overall aesthetics. The choice to
die-cast the pump when manufacturing for high volume has allowed the production and
manufacturing of the pump to be of greater efficiency and cost effectiveness.
1.1 List of Illustrations
Table 1: Most important physical properties of aluminium and steel……………………..7
Table 2: Sand Casting compared to Die Casting (base)………………………………….11
Table 3: Cost Comparison between sand casting and die casting (base) ……………..12
Table 4: Cost comparison between sand Casting and die Casting (piston)…………....17
Table 5: Cost comparison between sand casting and die-casting (piston housing)…...22
Table 6: Cost comparison between sand casting and die-casting (cover)..........….…...27
Table 7: Sand casting compared to die casting (valves and cap)..................................32
2.0 Introduction
2.1Purpose
The purpose of this project is to design and develop a PP175 pneumatic vertical
displacement pump. Through the knowledge-based learning about specific
manufacturing documentation and high volume manufacturing processes students are
enabled to gain a basic introduction to manufacturing engineering and management.
2.2 Background
‘Solo Pump Australia’ requested that the product development team is to design and
manufacture a PP175 vertical displacement pump. The design must be of minimum
weight and maximum functionality given the design specifications.
Page 5
2.3 Scope
The design specifications were:
● Pneumatic
● High Volume Market
● Long Life Components
● Five Components: Base, Piston Housing, Piston, Cover, Input/output
Valves
● Base: Maximum Dimension of 100mm x 70mm
● Vertical Piston Travel
● Piston Housing: Maximum Envelope Dimension of 50mm x 50mm
● Displacement Volume: 20 cm3 to 22.5cm3
● Piston: 10mm diameter shaft with 6mm hole (hole is 10mm below base at
top of stroke.)
● Base: 10mm hole has a +0.1mm tolerance.
● Material will be selected from the attached material list.
● Keep Maximum Functionality and Minimum Weight in mind.
● Prototype will be tested on a Jig.
● Base: Include two parallel slots; designed to suit M5 bolts.
● Pump will operate at 250 RPM.
● Pump will be connected to crankshaft through the 6mm hole.
2.4 Procedure
After developing individual concept sketches, group members collaborated and
discussed each other’s designs keeping in mind of the design specifications. It was
agreed that the design should be easily manufactured, cost effective and have the
maximum volume displacement within the given restrictions. From these features the
product development team was able to establish the dimensions of each component.
Each member was assigned a component to produce the engineering drawing, routing
chart and routing sheet in order to manufacture the prototype. Each member was then
Page 6
assigned another team member’s component to manufacture the part. Once the
components were manufactured the pump was assembled and tested to determine its
functionality and efficiency. The results observed during the testing were analysed and
used to determine a final design for high volume manufacturing.
3.0 Material selection
The material used to make the pump will drastically determine the cost and efficiency of
the pump. The two main options were steel and aluminium. The low density of
aluminium in comparison to steel means a lighter material to work with, thus giving
aluminium a high strength to weight ratio. Aluminium is susceptible to vibrations, but
with the close-fitting design of the piston with the housing and the secure bolting to the
cover and base these vibrations would be minimised. The value of aluminium’s young’s
modulus from table 1 is a measure of elasticity. Young’s modulus for aluminium is less
than steel indicating its greater malleability and elasticity over steel. (Aluminium vs.
steel: general similarities) This property highlights that aluminium is more likely to
deform when a large load is placed on it. However since only air is being pumped the
effect of the pump is negligible.
Steel is a tough metal that is more susceptible to cracking during the spinning process
when being designed into intricate designs such as the individual components of the
pump. Aluminium is corrosion resistant without any further treatment and doesn’t rust
whereas steel needs to be painted or treated afterwards to protect it from rust and
corrosion. Aluminium is a lighter material and thus less work is needed to move the
piston up and down. Therefore aluminium is the chosen material for the pump, also it is
cheaper than steel. As all of the components of the pump are of the same material, they
would both all expand and contract equally in same ratio during thermal expansion. Due
to the equal thermal expansion rates this will not compromise the functioning of the
Page 7
pump allowing all the components to work in unison independent of the thermal
expansion experienced.
Property Aluminium Steel
Density, ρ Kg m−3 2,700 7,800
Young modulus, E N mm−2 70,000 210,000
Shear modulus, G N mm−2 27,000 81,000
Poisson ratio, ν 0.33 0.3
Coefficient of linear thermal expansion, α K−1 23 × 10−6 12 × 10−6
Table 1: Most important physical properties of aluminium and steel (aluMATTER: Aluminium v. steel: general similarities)
4.0 Individual components
4.1. Base
4.1.1 Conceptualization
The first thing that was considered when designing the pump base was fitting the
criteria that ‘Solo Pump Australia Ltd’ specified. They required a ‘PP175 Vertical
Displacement Pump’ that must be of a pneumatic nature. In terms of the pump base,
the base must have dimensions of 100mm x 70mm and have a 10mm diameter hole for
the piston shaft to fit through. The tolerance allowed between the hole and the shaft is
+0.1mm due to the transformation of circular motion to linear motion. The prototype
base must also have two parallel slots that are designed to fit M5 bolts so that the base
can be fixed onto the jig.
This criteria created the bulk of the design concept for the base but what was missing
was how the base was to be attached to the piston housing. A few concepts were
Page 8
considered such as making a round hole for the piston housing to be fixed on top and
using nuts and bolts to secure it. These concepts will be discussed further in the next
sections.
The last step was to consider the type of material that was to be used to create the
prototype in which the two choices were either: aluminium or mild steel. Though
aluminium was slightly more expensive than that of the steel, it provided a lightweight
base and had a very smooth surface finish adding to quality to the product. Aluminium
also has high malleability and excellent corrosion resistance as compared to mild steel.
This cost-benefit analysis will be examined in the economic analysis section.
4.1.2 Initial design prototype
According to the functional specifications, the base was to be a 100mm x 70mm
aluminium flat bar of 10mm thickness. There would be two parallel M5 slots of length
55mm that were 10mm away from the widths of the base. The 10mm diameter hole for
the piston shaft was to be at the centre of the base for aesthetic reasons and also to
evenly distribute the stress across the base. Our initial design prototype had a circular
groove on the base that was designed to have the piston housing sit within and this
groove also contained an O-ring to prevent any air leakages. M3 hexagonal socket
head screws were to be used to fix the base tightly with the piston housing. Therefore
there must be four M3 tapped counterbore holes, each 19mm up and 19mm across
from the centre hole.
4.1.3 Final design prototype
The final design prototype remained mostly the same but it was altered to minimise the
manufacturing time whilst maintaining the same high level of functionality. The circular
groove was dismissed because our analysis demonstrated that air leakages below the
piston did not affect the amount of air being displaced during the strokes. The holes for
screws remained in the same position but were changed to M5 bolts because of its
higher stock availability. These counterbore holes are also not tapped because the
Page 9
analysis showed it was unnecessary, reduced the efficiency of assembly and increased
the risk of misfitting.
4.1.4 Prototype manufacture
To manufacture the base for the pump, a 100mm x 10mm bar stock of aluminium was
ordered of length 75mm. The dimensions of the base were inspected using Vernier
Callipers before being put into the milling machine where the carbide cutter reduced the
dimensions to 100 x 70 x 10 at speed 320 RPM and feed 50mm/min. All points of
interest such as holes and slots are marked out using Vernier callipers, centre punch,
set square and a metal scriber. The M5 parallel slots of length 55mm are then milled
using a slot drill where coolant is being used during the process before being inspected
again. The slot drill operates at speed 16m/min and at feed 50mm/min.
The drill press is then used to create the 10mm diameter hole at the centre of the base
plate using a 10mm drill bit at speed 32m/min. The counterbore holes are made in a
different manner where 5mm diameter holes are drilled straight through at the marked
positions at speed 16m/min. The holes are then drilled with a counterbore from the
bottom at depth 5mm to allow for the head of the screws to fit within the base. The
component then has its final inspection using the Vernier callipers and telescopic
gauges, and any sharp edges/burrs are to be removed using a ‘second cut’ file (see
Appendix A for base drawing).
4.1.5 Prototype testing and analysis
The testing demonstrated that the prototype was successful in completing its functions
of supporting the piston housing, fixing itself onto the jig firmly as well as allowing the
piston to move smoothly up and down the centre hole. However, care must be taken
when marking the position of the holes and drilling them correctly afterwards to ensure
the tolerances do not exceed the allowed amount of +0.5mm. This will increase the
efficiency of assembly of all the components to make the pump.
Page 10
4.1.6 High volume design
The design for the high volume production of the pump base remains the same even
though the method of production has changed from machining to die casting. For high
volume, the product manufacturing process must be reliable, cost-effective, and create
accurate components that are consistent with each other.
4.1.7 High volume manufacture
The two alternative ways of producing the base in high volume are sand casting and die
casting. Sand casting involves pouring the molten aluminium into an empty cavity
shaped by a sand mould whilst die casting (cold chamber) involves injecting the molten
metal at high pressures into typically a hardened steel mould.
To create the base using the sand casting method, the startup time (including the
creation of the patterned sand moulds) requires a few days with low initial costs (West
Coast Castings Inc). Sand casting is cheaper when manufacturing in low volume due to
its low start-up costs but it is more expensive when run in high volume.
Cold chamber die casting can take up to several weeks to start-up and it is expensive to
set up but it has significant advantages over sand casting. Die casting uses a non-
expendable cast that does not need to be replaced and creates a smoother surface
finish, thus further machining the component within tolerance is not necessary. It is also
a faster process and therefore requires less labour (which minimises costs) as seen in
table 2. This is important for the manufacture of the base because the base must fit onto
the jig and its dimensions must be accurate to support the piston housing.
Page 11
Sand Casting Die Casting
Startup
Time
A few days Several weeks
Initial
Expense
Inexpensive Expensive
Labor
Costs
Higher labor costs on
long runs
Lower labor costs on long runs
Finish Pebbly Smooth
Alloys High temperatures High fluidity materials; Better life with lower
temperatures (e.g., zinc)
Product
Size
Unlimited Casting weight must be between 30 grams (1
oz) and 10 kg (20 lb).
Casting must be smaller than 600 mm (24 in.).
Wall
Thickness
Thicker than die
casting
Thinner than sand casting
Table 2: Sand Casting compared to Die Casting (WCCI, 2014, Online)
4.1.8 Economic analysis
The values that are being used in this analysis were extracted from the company
‘Kinetic Die Casting’ in which the tooling costs for both sand and die casting are
compared. For the cost of material, UNSW School of Mechanical and Manufacturing
has provided the cost per metre of 100mm x 10mm bar (see Appendix C for material
costs). The estimated time taken to manufacture one component from sand casting was
Page 12
15 minutes whilst the time taken by die casting was 12 minutes (see Appendix B for
base routing chart).
Cost of material per part: $56 x 0.07mm = $3.92
Cost of tooling for sand casting: $1,620/10,000 parts
Cost of tooling for die casting: $23,750
Cost of Labour: $25/ hour
Quantity Sand Casting Die Casting
1000 parts Tool Costs
Labour Costs
Totals Costs
$3920 $1620 $6250
$11,790
$3920 $23,750 $5000
$32,670
10,000 parts Tool Costs
Labour Costs
Totals Costs
$39,200 $3240
$62,500
$104,940
$39,200 $23,750 $50,000
$62,950
50,000 parts Tool Costs
Labour Costs
Totals Costs
$196,000 $16,200 $312,500
$524,700
$196,000 $23,750 $250,000
$469,750
100,000 parts Tool Costs
Labour Costs
Totals Costs
$392,000 $32,400 $625,000
$1,049,400
$392,000 $23,750 $500,000
$915,750
Table 3: Cost Comparison between sand casting and die casting
Page 13
From Table 3, for the high volume production of 100,000 aluminium pump bases, the
estimate cost per part by sand casting is $10.49 whilst by die casting it is $9.15. For low
volume production, it is more feasible to use sand casting for its low start up cost but it
less viable in the long run due to the large labour costs and tool costs.
4.1.9 High volume analysis
Die casting is demonstrated to be the most efficient and cost-effective way of producing
the pump bases in high volumes. This is because the die/cast is reusable and has a
very smooth surface finish eliminating unnecessary further machining. Aluminium is also
the most viable material to be used in this process because of its corrosion resistance,
thermal conductivity, low density and strength under high temperatures (SAPA, 2014,
Online).
4.1.10 Conclusion
The design of the base was created to maximise efficiency and functionality under the
set criteria by Solo Pump Australia Ltd whilst minimising costs. The prototype’s design
was finalised after feedback from the testing of the pump and this design remained the
same for the high volume production of the component. The pump base would be
created from aluminium due to its superior qualities such as low density and smooth
surface finish (i.e. high malleability). Die casting was determined to be the most feasible
method of manufacturing high quantities of the base as stated in the high volume
analysis.
Alvin Chung (z3463320)
Page 14
4.2 Piston
4.2.1 Initial design prototype
Before the initial design of the prototype for the piston, the functional specifications for
the whole pump had to be established. These included the type of pump (vertical
displacement pneumatic pump); the displacement volume (range of 20-22.5cm3) and
the piston having a 10mm diameter shaft (see Appendix C for design specifications).
After the considerations listed, calculations were made in order to maximise the
displacement volume with the given design restrictions. Thus, the dimensions for the
piston were established (see Appendix A for piston drawing ) with a stroke length of
30mm. The whole initial design process for the entire pump was done in collaboration.
4.2.2 Final design prototype
The final design of the piston prototype remained unchanged except for the O-ring
groove. After collaboration and consideration of the dimension of the piston head, it was
finalized that the Ludowici O-ring C.S. 1.5 is most suitable. Thus the dimensions of the
groove for the O-ring is established and adjusted on the final prototype engineering
drawing (see Appendix A for piston drawing).
The type of material for piston to be aluminium was also determined during
collaboration after consideration between the stocked material; steel and aluminium.
Aluminium was chosen due to its low density, higher malleability and its resistance to
corrosion compared to steel, which is favourable for a dynamic parts such as the piston.
4.2.3 Prototype manufacture
In order to manufacture piston for the prototype, a piece of aluminium stock sized at a
39mm diameter and 65mm depth is cut. The raw material is inspected; ends are faced
and cut to a 64mm height using the lathing machine. The O-ring groove is first
manufactured with a specific tolerance as specified, and then the shaft diameter is
lathed until it is 10mm (see Appendix A for routing sheet). The speed at which the piston
Page 15
is lathed during this process is slow to ensure a smooth machine surface finish,
reducing friction between the piston and the rest of the components.
4.2.4 Prototype testing and analysis
After the prototype was assembled, it was tested using a jig at 250 RPM as specified in
the design specifications. The testing was successful which demonstrated that the
pump is fully functional. On the other hand, due to the designed length of the piston and
precision of the manufactured length of the shaft, it was miscalculated that the stroke
length is 25mm instead of 35mm. However, this did not drastically affect the
functionality of the pump as a whole since the displacement volume remained constant
as well as reduced the likelihood of knocking.
4.2.5 High volume design
For manufacturing in high volume it is recommended that the piston part to be casted.
This however will affect the properties of the material as the piston is manufactured.
Therefore, some changes are made to the design. Every right angle of the piston except
for the O-ring groove is filleted. This is because right angles are structurally weaker
when casted and the stress concentration between the piston head and shaft is
reduced. The O-ring groove however remains the same as the specific dimensions are
given by the manufacturer of the O-ring.
4.2.6 High volume manufacture
One method of manufacturing the piston in high volume is by cold-chamber die casting.
Cold-chamber die casting requires the aluminium to be in molten form. After the molten
aluminium fills the cavity when the die is closed, a plunger pushes the metal in
pressures over 70,000 kPa until the aluminium solidifies. The die is then opened, the
ejector pins push out the casting and the whole process repeats (Dynacast, “Cold-
Chamber Conventional). The advantage of die casting the piston is that it is time
Page 16
efficient, low physical labour cost, highly accurate and consistent and high quality parts
are produced. Disadvantages however include the high cost of the machine, and also
as mentioned in the previous section, right angles are structurally weaker which this
affects the manufacturing of the O-ring groove. Therefore after die casting the piston,
the groove must be turned using a lathing machine.
Another method of manufacturing the piston is by sand casting. Sand casting involves
placing half of the pattern in a box where “green sand” (which consists of sand with 2-
3% clay and water) is compressed on top of it. The process repeats for the other side of
the pattern after flipping over the first mould, placing talcum powder on the surface,
marking the pouring basin and placing another box on top of it. The pouring basin is cut
out and the pattern is then carefully pulled out. Molten aluminium is poured into the
cavity, thus producing the shape. Advantages of this method of manufacturing the
piston are that it is initially lower in cost to manufacture parts from and the sand mould
is recyclable making it “essentially pollution free” (Classroom Video, “Metal Casting:
Sand Moulds”). Disadvantages of this method include that it is more time costly, labour
intensive, and more likely to have defects due to gas holes and shrinkage porosity
compared to die casting (Enginsoft, “Aluminium Sand Casting”).
4.2.7 Economic analysis
Based on the company “Kinetic Die Casting”, given cost comparisons between die
casting tooling and sand casting tooling (Kinetic Die Casting, “Sand Casting Tooling
Cost VS Kinetic Die Casting Tooling Cost”), and the provided cost per metre of material
from the UNSW School of Mechanical and Manufacturing Engineering (see Appendix C
for material costs), a rough estimation of the cost per part can be calculated. All costs
are converted to AUD.
Cost of material per part: $105.33 x 0.065mm = $6.85
Cost of tooling for sand casting: $1,620
Cost of tooling for die casting: $23,750
Page 17
Cost of tooling for lathe turning machine: $6,000
Cost of labour: $25/hr
Quantity Sand Casting Die Casting
1,000 parts Tool Cost
Labour Cost
Total Cost
$6,850 $7,620 $8,333
$22,803
$6,850 $29,750 $5,417
$42,016
10,000 parts Tool Cost
Labour Cost
Total Cost
$68,500 $7,620
$83,333
$159,453
$68,500 $29,750 $54,167
$152,417
50,000 parts Tool Cost
Labour Cost
Total Cost
$342,500 $9,240
$416,667
$768,407
$342,500 $29,750 $270,833
$643,083
100,000 parts Tool Cost
Labour Cost
Total Cost
$685,000 $12,480 $833,333
$1,530,813
$685,000 $29750
$541,667
$1,256,417
Table 4: Cost comparison between Sand Casting and Die Casting
From the cost calculations in Table 4, it is clear that in quantities below approximately
7,500 that sand casting is the preferred choice of manufacturing due to its lower cost.
However, in higher volume manufacturing die casting is the most cost effective way of
producing the piston, since a sand casted aluminium piston would cost approximately
Page 18
$15.30 per part to manufacture, compared to a die casted aluminium piston costing
approximately $12.56 per part.
4.2.8 High volume analysis
Based on the comparisons made between sand casting and die casting, it is concluded
that the most effective way to manufacture the piston part in high volume is by die
casting. This is because it is the most cost effective, time efficient, accurate and
consistent, and produces a higher quality finish.
4.2.9 Conclusion
Overall, the design for the aluminium piston is unchanged apart from filleting right
angled edges due to adapting to the die casting process in high volume manufacturing.
However, the manufacturing of the O-ring groove remains the same for both prototype
and high volume processes due to specific dimensions specified by the manufacturer of
the O-ring C.S. 1.5. In high volume, it is concluded overall that the most practical way to
manufacture the piston is by die casting due to the reasons as stated in the high volume
analysis.
Jessica Avedawn Chen (z3461958)
Page 19
4.3 Piston Housing
4.3.1 Initial design prototype
The dimensions of the piston housing were determined by the requirements according
to ‘Solo Pump Australia’s’ requests. The company required a pneumatic vertical
displacement pump with a displacement volume of 20-22.5cm3. The stock sizes given
along with the requirements by Solo Pump Australia limited our sizing of the piston
housing. The dimensions of each individual pump were discussed as a group based on
everyone’s initial design concept drawings. The best design was chosen and the
individual components of this design were looked into further detail. The piston housing
size was then determined to be a 50mm diameter cylindrical tube of height 52mm in
height with a hole in the centre with same diameter of the piston. A small 3mm in
diameter inlet hole on one side of the housing was designed to allow air to collect in the
housing. Eight tapped holes on the top and bottom were added be used to screw the
cover and base to.
4.3.2 Final design prototype
After careful consideration, the initial design was changed. The piston housing was no
longer a cylindrical shape, but instead we chose to use a 50mmx50mm square block of
aluminium. This allowed us to use larger bolts to screw the cover and base together for
more stability (change from M3 to M5 bolts). The inlet hole on the side was removed
and an extra valve was added instead. This reduced the height of the housing to 49mm.
An O-ring groove was also added to ensure air did not escape from the joining of the
cover and piston housing with an outer diameter of 47mm and an inner diameter of
43mm. This was also to ensure a secure fit between the two components.
Page 20
4.3.3 Prototype manufacture
Manufacturing a prototype of the piston housing saw ordering a stock size of
50mmx50mmx50mm block of aluminium. The top and bottom surfaces were faced off
and used as datum edges. The 39mm diameter centre hole was drilled along with an
addition 8 holes were drilled on top and bottom of the piston housing for the bolts to go
through. The O-ring groove was lathed and threads were added to the eight holes on
the housing (see Appendix A for routing chart).
4.3.4 Prototype testing and analysis
The testing of the piston housing along with other components once the pump was
assembled proved to be a success as the pump worked efficiently. However the inlet
valve did not work as assumed. Once the inlet valve was blocked however the pump
blew up the balloon in a matter of seconds.
4.3.5 High volume design
The high volume design for the piston housing was changed to decrease stress
concentrations. The overall dimensions have been kept the same, however the vertical
straight edges of the housing have been filleted to a 2 mm radius (see Appendix B for
housing drawing). The continuity of the sides of the piston housing will distribute stress
more evenly to its neighbouring areas as the straight edges act as stress raisers.
(Lesson 2: stress concentration).
4.3.6 High volume manufacture
There are two main methods to manufacture a high volume of piston housings, that
being sand casting and die-casting.
The sand casting process involves creating a mould out of sand for the prototype, and
molten metal is poured into this mould. Cold chamber die-casting is when the molten
Page 21
metal is poured into the injection cylinder and then quickly injected into the die under
pressure (Die casting methods). Metal is melted, poured into the holes to fill the mold,
and left to cool. When the cast part has cooled, the box is opened and the part is
removed. Sand casting will be cheaper initially as the sand used for the mold is
reusable and cheap. Sand casting also has a quick set-up time of a few days in
comparison to die casting, which may take up to several weeks. Die casting is initially
expensive as the mould is made of a hardened tool steel to withstand high pressure and
temperature, however it will take a shorter time to break even and will be cheaper in the
long run. (Sand casting compared to die-casting).
Die casting also has a smoother finish than sand casting and is better suited to pieces
with smaller wall thicknesses in comparison to sand casting. Since the casting weight is
above 30g die casting may be used. Costs for sand casting is high due to the sand
being disturbed when the part is removed, thus the set up operation must be repeated
for each part. Sand castings tend to have a grainy surface with poor dimensional
control. Most often castings are machined in post processing operations for smoothness
and dimensional integrity. Therefore die-casting is a more suitable process for making
the piston housing in high volume. Having the piston housing die-casted will reduce the
process of manufacturing to casting the mould and tapping M5 holes into the top and
bottom holes of the housing.
4.3.7 Economic analysis
The sand casting tools for aluminium range from $500 to $7,500 depending on the part
being made. Each casting part for the sand casting tool has a life of 5000 parts. While
the die casting tools for aluminium range from $5000 to $75,000 depending on the part
being made, this is ten times the price of sand casting. However the life of die-casting is
range from 100,000 to 1,000,000 parts, which is an increase of 20 to 200 times the life
of sand casting (Sand Casting Tooling Cost VS Kinetic Die Casting Tooling Cost). Table
5 shows that die-casting is more economically efficient than die-casting.
Page 22
Number
of parts
Sand casting Die casting
10,000 Material: $8,800 ($0.880 per part)
Production: $17,372 ($1.737 per part)
Tooling: $2,424 ($0.242 per part)
Total: $28,595 ($2.860 per part)
Material: $8,860 ($0.886 per part)
Production: $7,832 ($0.783 per part)
Tooling: $17,050 ($1.705 per part)
Total: $33,742 ($3.374 per part)
25,000 Material: $21,996 ($0.880 per part)
Production: $43,421 ($1.737 per part)
Tooling: $6,548 ($0.262 per part)
Total: $71,966 ($2.879 per part)
Material: $22,151 ($0.886 per part)
Production: $10,449 ($0.418 per part)
Tooling: $23,861 ($0.954 per part)
Total: $56,461 ($2.258 per part)
50,000 Material: $43,992 ($0.880 per part)
Production: $86,843 ($1.737 per part)
Tooling: $8,731 ($0.175 per part) Total:
$139,566 ($2.791 per part)
Material: $44,302 ($0.886 per part)
Production: $20,017 ($0.400 per part)
Tooling: $23,861 ($0.477 per part)
Total: $88,180 ($1.764 per part)
100,000 Material: $87,984 ($0.880 per part)
Production: $173,686 ($1.737 per part)
Tooling: $8,731 ($0.087 per part)
Total: $270,401 ($2.704 per part)
Material: $88,603 ($0.886 per part)
Production: $23,491 ($0.235 per part)
Tooling: $38,221 ($0.382 per part)
Total: $150,315 ($1.503 per part)
Table 5: cost comparison between sand casting and die-casting (Custom Part Cost Estimator)
4.3.8 High volume analysis
From the prices seen in the table 5 above, it can be seen that die-casting is preferred
over sand casting economically. Also the requirements for the piston housing is more
suited to die-casting methods as it requires a smooth finish, and has thin walls in which
the sand casting is unable to produce. The smooth finish will allow the piston housing to
have a longer lifespan as it the moving parts of the piston against it will move smoothly.
Page 23
4.3.9 Conclusion
The changes that the piston housing has seen has made the piston housing more
stronger and stable when assembled with the other components. Die-casting has been
chosen for production in high volume as it is more cost effective and is more suited to
the piston housing design requirements.
Liza Chao (z3463319)
4.4 Cover
4.4.1 Initial design prototype
Based on the functional requirements and constraints given by Solo Pump Australia,
each member of the group was tasked with creating one concept sketch each so that a
large variety of different solutions to the design problem could be obtained. These
concepts were gathered and notable features of a design were selected or combined to
make up the first design. The dimensions of the pump cover was determined using the
stock size in the materials sheet given by TAFE. A 50x50mm square block of aluminium
with a height of 10mm was selected for the prototype cover. Four threaded M3 and
counterbored holes with were made perpendicular to the top surface to allow bolts to
attach the cover to the housing. Similarly, a single M12 threaded hole was made in the
centre of the cover for an outlet valve to attach.
4.4.2 Final design prototype
After a series of iterations to the initial design, in which the manufacture process was
considered, a final design prototype was created. The envelope dimensions of the part
remain unchanged, but the screw holes were enlarged to 5mm diameter (for an M5
Page 24
bolt), threads and counterbore were removed (for a simpler design) and spaced closer
to the corners. This was because the housing was changed from a cylinder to a
50x50mm square (matching the cover), allowing for more free space on the cover
surface to put an enlarged bolt. The larger bolts allow for better attachment between the
two surfaces and hence better sealant. The inlet hole on the side of the housing was
changed to a inlet valve that was placed adjacent to the outlet valve at the top of the
cover. Some features originally designed for the valves were instead placed on the
cover to simplify the manufacturing process for the inlet valve. These included two small
holes drilled into the inlet hole to allow air to flow.
4.4.3 Prototype manufacture
An aluminium block of 50mmx50mmx12mm was cut from the flat bar stock as ordered.
The height was ordered larger than necessary so that the top and bottom surfaces
could be faced and squared on a milling machine to the required dimensions as
necessary. The bottom surface should ideally fit level with the top of the housing to
create the a leak-proof seal between the top components while in operation. The four
5mm holes were drilled using the drill press. For the outlet valve hole , a 10mm hole
was drilled and tapped with an M12 bit through the entire component. For the inlet valve
hole, a 10mm hole was drilled with a flat drill bit and tapped with an M12 tapping bit until
3mm from the bottom. 2 holes of 1.5mm diameter were then drilled into the remaining
material in the outlet hole, allowing air to pass while stopping the ball. These holes were
made off-centre to eliminate the risk of the ball blocking them and thus blocking airflow.
No special surface finish is required, as there are no moving parts causing friction (such
as the piston moving against the housing). Hence a fast speed/feed rate is utilised in
order to minimise the time needed to manufacture the part.
4.4.4 Prototype testing and analysis
Once the components were manufactured and assembled, the complete pump was
tested at 250 RPM as specified in the functional specifications. The pump was proven to
Page 25
be fully functional in that it fulfilled its objective (popping the balloon). The cover itself
was securely attached to the housing and valves and the o-ring seal prevented leakage
of air as intended.
Although the prototype design of the cover was very successful, possible improvements
could be made including:
- Placing the inlet valve further away from the outlet valve. As the balloon
(attached to the outlet valve) expands, the sides of the balloon tend to partially
cover the inlet valve. This obstruction reduces the airflow into the pump chamber
and hence the rate at which the balloon is pumped.
- Combining the cover and housing into one component. The gap between the
attaching surfaces of either component allows air to escape while the pump is in
operation. To prevent this, an o-ring seal is created in the housing so that no air
will leak. This involves increased machining operations and an additional shelf
component. This could be avoided if the two components were combined,
reducing manufacturing time and simplifying the design greatly. However, as
stated in the functional requirements, there MUST be five components, so this
improvement should only be a consideration instead of a design.
4.4.5 High volume design
The design for high volume was essentially the same for the prototype. The envelope
dimensions, manufacture material, size of holes, threads and the surface finish were
kept the same. However, as cold chamber die casting was the chosen manufacturing
process for high volume production, sharp corners and angles must be avoided (as they
act as stress raisers and cause cracking of the metal during solidification). As a result,
fillets of 2 mm radius have been used for the straight edges on the sides (continued to
the housing) and the top surface to reduce this stress concentration. This also makes
the cover slightly lighter.
Page 26
4.4.6 High volume manufacture
There were two main manufacturing processes that were considered for the high
volume production: sand casting and die casting. A comparison of the two
manufacturing methods is given below in table 6.
Sand Casting Die Casting
Startup
Time
A few days Several weeks
Initial
Expense
Inexpensive Expensive
Labor
Costs
Higher labor costs on
long runs
Lower labor costs on long runs
Finish Pebbly Smooth
Alloys High temperatures High fluidity materials; Better life with lower
temperatures (e.g., zinc)
Product
Size
Unlimited Casting weight must be between 30 grams (1 oz)
and 10 kg (20 lb).
Casting must be smaller than 600 mm (24 in.).
Wall
Thickness
Thicker than die casting Thinner than sand casting
Sand Casting compared to Die Casting (WCCI, 2014, Online)
Page 27
4.4.7 Economic analysis
Sand Casting Die Casting
Quantity Required 100,000 100,000
Special Tooling Sand mould (negligible) Die Cost = $32,000
Fixturing N/A N/A
Process Equipment Machine cost = $120,000 Machine cost = $300,000
Direct Labour 2 workers ($30 / hour /
person)
1 worker ($30 / hour /
person)
Direct Material $1.40 / unit $1.40 / unit
Overhead Cost N/A N/A
Production Capacity <20 / hour / shift <200 / hour / shift
Production Cost $560,000 $487,000
Production Cost/unit $5.60 / unit $4.87 / unit
Table 6: comparison between sand casting and die-casting
It is evident that sand casting is more cost-efficient in low quantities, but as quantity
increases, die casting becomes more economical. For a production quantity of 100,000,
there is a total saving of $73,000 over sand casting if die casting is used. The sand
used for the mould is cheap and reusable whereas the dies/mould used for die casting
Page 28
made of high-grade steel in order to withstand the high temperature and pressure, and
hence more expensive. The initial cost involved with die casting (purchasing of
equipment, tooling, set-up) is very expensive. However, in a high volume production,
the advantages offered by die casting (the speed at which the cast is made, significantly
less labour cost and quality of the cast) significantly outweighs the initial cost for the
setup. Die casting involves minimum labour as the process comprises of injection of
molten metal under high pressure into a cavity under gravity, which is performed
automatically by the process equipment. As a result, only one worker is required to
operate and manage the machinery. For sand casting, more manual labour is required
to break and remake a sand mould during each cast and two workers are required.
Manual machining is also required to achieve dimensional accuracy, leading to an
increase in labour cost.
4.4.8 High volume analysis
Die casting is the fastest and most cost-effective way of producing components in high
volumes of 100,000 units. The casts have very good dimensional accuracy and very
smooth surface finish, so machining after casting is not required. Although they are
costly to produce, the dies are re-useable, and in a production size this large, time is
greatly reduced, making it more applicable for mass production than sand casting.
4.4.9 Conclusion
It can be seen from the iterations made to the design and manufacturing of the cover
over time, the design has greatly improved to be more functional and applicable to the
design and functional constraints. Aluminium as the material and die casting as the
manufacturing process are both ideal choices for high volume as they are cost and time
efficient and satisfy the functional requirements stated by the client company.
Gavin Cheng (z3463228)
Page 29
4.5 Valves
4.5.1 Initial design prototype
Using the stock sizes of materials as a basis an initial design for the valve was
conceived. This design included a flap valve as an outlet with an outside diameter of
12mm and a small 3mm inlet hole placed in the piston housing to allow air into the
chamber when the piston is at the lowest point of its cycle. The valve was threaded to
provide a means of an airtight attachment to the cover. This design required a motor
strong enough to pull the piston while creating a low pressure chamber in the housing.
4.5.2 Final design prototype
After some deliberation within the group the initial design was changed. The assumption
that the motor was strong enough to handle the low pressure created was dismissed
and thus an inlet valve was added to the top of the pump. These valves were also
changed from a flap valve to ball valves. The design for the ball valve included a
recessed groove to hold the o-ring but was then removed as it was too difficult to
manufacture. To allow for ease of manufacture the length of the valve was increased
from 30mm to 60mm. A solution had to be devised to allow air to pass through the
valves but stop the ball from escaping. This prompted a change in design of the cover
for the inlet valve and a dome nut, modified to allow air through the top, was added to
the outlet.
4.5.3 Prototype manufacture
Manufacturing a prototype of the valve ordering a bar stock sized at 12mm diameter x
140mm cut of aluminium, an M12 Dome nut and two 7mm steel ball bearings. The bar
stock was cut in half to produce the basis for the two valves. A 6mm hole was bored
through the middle and a 7mm hole bored to a depth of 10mm. Finally an M12 thread
was tapped in the appropriate places on the valve.
Page 30
4.5.4 Prototype testing and analysis
The testing of the pump and specifically the valves proved to be partially successful. All
parts of the pump worked as expected with the exception of the inlet valve. This is due
to assumption made during the design of the pump that the force produced by the
piston will be enough to overcome the gravitational acceleration on the ball bearing in
the inlet valve. When the inlet valve was blocked the pump worked as expected.
4.5.5 High volume design
Three designs for the production of the valves at high volume were considered. The first
reverts to the original idea of an inlet hole at the lowest point of the piston cycle as it
was proven in the prototype testing that the motor was powerful enough to overcome
the low pressure created when there is no intake of air at the pistons down stroke.
However as the power of the motor was never specified it was decided that the pump
must be compatible with motors of lower power and thus this design was discarded. The
other two designs for the valve were considered based on the different methods of
manufacturing, sand casting and die casting. However it was decided that sand casting
did not produce the surface finish required to create a proper seal. Thus die casting was
selected to as the preferred method of manufacture. The features of this valve are:
- The inlet and outlet valve were shortened and made identical to reduce the cost
of producing different parts. Although this creates a redundant thread on the inlet
valve reducing its aesthetics, the cost of production is greatly reduced and is thus
a necessary compromise. This thread could be used as an attachment point for a
hose if a gas other than air is used as an alternative. However this is not
recommended and would have to be further researched for the pumps
compatibility with these gases.
- A tapered ball chamber to eliminate the need for an o-ring thus reducing the
cost of the o-ring and assemblage of the pump.
- A die cast, hex head cap with the correct thread needed to screw onto the
valve. This is required due to the limitations of die casting in that the mould would
not be removable if the ball chamber was completely sealed. The hexagonal
Page 31
shape of the cap allows for ease of assembly. Additionally the cap lowers the
cost of outsourcing and modifying a dome nut as a cap.
- Springs in both inlet and outlet valves. This eliminated the reliance on the motor
to produce enough force to overcome the effects of gravity on the ball. It also
allows the pump to be used in any orientation.
4.5.6 High volume manufacture
There are two main methods to manufacture a high volume of valves, machining and
die-casting.
Machining would use CNC lathes and mills to produce a high quality product. However
CNC machining is time consuming and wasteful of material (even if excess is recycled)
and thus is an expensive option when a high volume of valves is needed. Cold chamber
die-casting is when the molten metal is poured into the injection cylinder and then
quickly injected into the die under pressure (Die casting methods). Metal is melted,
poured into the holes to fill the mould, and it is left to cool. When the cast part has
cooled, the box is opened and the part is removed. Die casting is initially expensive as
the mould is made of a hardened tool steel to withstand high pressure and temperature,
however it will take a shorter time to break even with the machining option and will be
cheaper in the long run. While die casting produces a product with lower quality than
machining the process is sufficiently accurate for the purposes of this pump and the
compromise is necessary to reduce cost of production.
4.5.7 Economic Analysis
Machining Die Casting
Quantity Required 100 000 100 000
Special Tooling Tool Costs = $1000 Die Cost = $40 000
Process Machine cost = $150,000 Machine cost = $300,000
Page 32
Equipment
Direct Labour 1 workers ($30 / hour / person)
1 worker ($30 / hour / person)
Direct Material $0.50 / unit $0.50 / unit
Overhead Cost N/A N/A
Production Capacity
<10 / hour / shift <400 / hour / shift
Production Cost $501 000 $397 500
Production Cost/unit
$5.01 / unit $3.98 / unit
Table 7: Cost comparison between machining and die casting
4.5.8 High volume analysis
From the prices seen in the table 3 above, it can be seen that die-casting is preferred
over machining economically. This is due to the greatly decreased cost of production in
die casting in comparison to machining even when taking into account the higher quality
of machining with CNC.
4.5.9 Conclusion
The changes that the valves have seen have made them more efficient and cost
effective. Aluminium die-casting has been chosen for production in high volume as it is
more cost effective and is more suited to the valve design requirements.
Nadav Cohen (z3460696)
Page 33
5.0 Conclusion
A prototype of the vertical displacement pump was designed, manufactured and tested.
The pump prototype had performed its purpose successfully and thus few changes
were made to the design for high volume manufacturing.
The results from the testing were used to alter the designs of each individual
component. The valve design for high volume has been altered to be able to adapt to
different orientations, thus overcoming the gravitational issue emphasised during
testing. All other variables of the components designs were maintained with extra fillets
added to reduce stress concentrations. The method of production was changed to die-
casting to increase accuracy, efficiency and cost effectiveness in comparison to the
previous method. The product development team has designed and manufacturing a
fully functioning PP175 vertical displacement pump prototype and analysed high volume
manufacturing methods. This process has enabled the product development team to
learn about specific manufacturing documentation and high volume manufacturing while
gaining a basic introduction to manufacturing engineering and management.
Page 34
6.0 Reflection
CAD tutorial
All team members received the Solidworks tutorials equally in that they found them
useful and easy to understand. The tutors from were helpful and explained things
thoroughly with simple straightforward directions as opposed to the handbook given
which were slightly less helpful.
TAFE
All members favoured the Tafe sessions as it was engaging and interesting and
preferred this physical style of learning to the written method. The experiences gained
cannot be taught and thus were considered invaluable. The instructors at Tafe were
extremely helpful with all problems, they would check up on our job and our progress
frequently to ensure we understood everything. The instructors were patient and
genuinely concerned with our understanding and knowledge of the job at hand.
Lectures
All team members found the lecturer engaging and helpful but the content itself was at
times quite ‘dry’. A way to improve this is to maybe have interactive elements within
class and also set stronger expectations of what is to be learnt in the course. It is not
necessary to have a two hour lecture to cover the content but if it is to be two hours, a
break after every hour would be preferred. A strong learning point from the lectures is
when the content has a direct correlation with real world applications that we are aware
of. This was highlighted in the last lecture during the discussion of waste and the
afterlife of certain products.
Page 35
7.0 References
Dynacast. (2014). COLD-CHAMBER CONVENTIONAL. Available:
http://www.dynacast.com/die-casting/die-casting-processes/cold-chamber. Last
accessed 2nd Jun 2014.
Enginsoft. (2010). ALUMINUM SAND CASTING. Available:
http://www.enginsoft.com/technologies/metal-process-simulation/aluminum-sand-
casting/. Last accessed 2nd Jun 2014.
Difference Between Sand Casting and Die Casting . 2014. Difference Between Sand
Casting and Die Casting . [ONLINE] Available at: http://info.cpm-
industries.com/blog/bid/328544/Difference-Between-Sand-Casting-and-Die-Casting.
[Accessed 04 June 2014].
Aluminum Casting Methods - Sand Casting and Die Casting Comparison. 2014.
Aluminum Casting Methods - Sand Casting and Die Casting Comparison. [ONLINE]
Available at: http://www.westcoastcastings.com/die-casting.html. [Accessed 04 June
2014].
Sand Casting Aluminum Parts compared to Aluminum Die Castings. 2014. Sand
Casting Aluminum Parts compared to Aluminum Die Castings. [ONLINE] Available at:
http://www.kineticdiecasting.com/sandcasting.html. [Accessed 04 June 2014].
Die Casting Process, Defects, Design. 2014. Die Casting Process, Defects, Design.
[ONLINE] Available at: http://www.custompartnet.com/wu/die-casting. [Accessed 04
June 2014].
Sand Casting Cost Estimator. 2014. Sand Casting Cost Estimator. [ONLINE] Available
at: http://www.custompartnet.com/estimate/sand-casting/. [Accessed 04 June 2014].
The benefits of Aluminium . 2014. The benefits of Aluminium . [ONLINE] Available at:
http://www.sapagroup.com/en/sapa-pole-products/aluminium/. [Accessed 04 June
2014].
Australia die casting association, Die casting methods, accessed: 2nd june 2014,
http://www.diecasting.asn.au/Services/ViewServices.asp?Ref=5535
Page 36
Product Costing Guidelines, Integrated Product Development (IPD), by William Lovejoy,
Sebastian Fixson and Shaun Jackson, October 2005, Revised November 2008,
November 2010, Accessed: 1st june 2014
aluMATTER, Aluminium v. steel: general similarities, accessed: 1st june 2014
http://aluminium.matter.org.uk/content/html/eng/default.asp?catid=217&pageid=214441
7130
Wenzel Metal Spinning, Steel versus Aluminum - Weight, Strength, Cost, Malleability
Comparison, by Adam Hornbacher, accessed 3rd june 2014
http://www.wenzelmetalspinning.com/steel-vs-aluminum.html
Module 3: design for strength, Lesson 2: stress concentrations, Version 2 ME, IIT
Kharagpur, accessed 2nd june 2014
Page 37
8.0 Contributions
Appendix A
Prototype
5
50
10
100
70
19
19
10
TOP VIEW
10
9
5
5.50
FRONT VIEW
ISOMETRIC VIEW
AS1100
TITLE
TOLERANCE UNLESS NOTED OTHERWISE
APPROVED BY
CHECKED BY
REV DATE
DO NOT SCALE
A40.5mm ALUMINIUM
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSWDRAWN BY PUMP BASE
1QTY
J.A. CHEN (Z3461958)FIRST RELEASE DATE
1.6
1/6/143
DIMENSION IN MILLIMETRES DRAWING NUMBER
A. CHUNG (Z3463320)
2/4/14J.A. CHEN (Z3461958)
SURFACE FINISH UNLESS NOTED OTHERWISE
1
SCALEMATL1:1
SolidWorks Student Edition. For Academic Use Only.
15
49
6 THRU
A
39
10
TOP VIEW
ISOMETRIC VIEW
1.9
5 0 0
1.35 -00.05
DETAIL A SCALE 2 : 1
AS1100
FRONT VIEWTITLE
TOLERANCE UNLESS NOTED OTHERWISE
APPROVED BY
CHECKED BY
REV DATE
DO NOT SCALE
A40.3mm ALUMINIUM
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSWDRAWN BY PISTON
1QTY
G. CHENG (Z3463228)FIRST RELEASE DATE
1.6
04/06/20143
DIMENSION IN MILLIMETRES DRAWING NUMBER
J. A. CHEN (Z3461958)
06/06/2014G. CHENG (Z3463228)
SURFACE FINISH UNLESS NOTED OTHERWISE
2
SCALEMATL1:1
SolidWorks Student Edition. For Academic Use Only.
49
47
6
A
50 5
0
8 X M5 10 EQUALLY SPACED
6
47
43
39
1.2
0
DETAIL A SCALE 2 : 1
TOP VIEWISOMETRIC VIEW
FRONT VIEW
AS1100
TITLE
TOLERANCE UNLESS NOTED OTHERWISE
APPROVED BY
CHECKED BY
REV DATE
DO NOT SCALE
A40.5mm ALUMINIUM
DRAWN BYHOUSING
1QTY
ALVIN CHUNG (Z3463320)FIRST RELEASE DATE
1.6
03/06/143
DIMENSION IN MILLIMETRES DRAWING NUMBER
LIZA CHAO (Z3463319)
01/04/14ALVIN CHUNG (Z3463320)
SURFACE FINISH UNLESS NOTED OTHERWISE
3
SCALEMATL1:1
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSW
SolidWorks Student Edition. For Academic Use Only.
ISOMETRIC VIEW
FRONT VIEW
TOP VIEW
AS1100
A
5 HOLES EQUALLY SPACED
50
50
15
M12 M12 7 MIN LG
4x
R26.87
10
REV
TITLE
1:1
NOTED OTHERWISE
APPROVED BY
CHECKED BY
DATE
DO NOT SCALE
TOLERANCE UNLESS
A40.5mm ALUMINIUM
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSWDRAWN BY
PUMP COVER
1
QTY
NADAV COHEN (Z3460696)FIRST RELEASE DATE
MATL SCALE
1.6
02/06/2014
MILLIMETRESDRAWING NUMBER
GAVIN CHENG (Z3463228)
04/04/2014ALVIN CHUNG (Z3463320)
DIMENSION IN NOTED OTHERWISE
4
SURFACE FINISH UNLESS
3
DETAIL A SCALE 2 : 1
1.5 2x
4
SolidWorks Student License Academic Use Only
Assembled Pump
Base
Base Plate 4x M3 Screws
Piston Housing
Housing Block
1x O-ring
Piston
Piston shaft/head
1x 0-ring
Cover
Cover Plate 4x M3 Screws
Valves
Dome Nut Inlet Tube Outlet Tube 2x Balls
800
Put 4xM3 hexagon socket head cap screw through base
801
Put O-ring on groove of piston head
Put piston shaft through base
802
803
Attach piston housing to base
Place O-ring on groove of piston housing
Attach pump cover with 4xM3 hexagon socket head cap screw
Place O-ring and ball in inlet valve
Place O-ring and ball in outlet valve
Screw dome nut on outlet valve
Screw valves onto pump cover
804
803
803
805
803
803
806
803
803
807
803
803
808
803
803
809
803
803
Prototype Base Routing Chart
Pump Base
100 x 70 x 10mm, Aluminium
101
100 Inspect 2 min
2 min Mill to correct dimensions
2 min Drill centre hole
Inspect 1 min
Mill the slots 10 min
16 min Drill four M5 counter bore holes
2 min Inspect/Clean
Mark all centre lines and drill positions
5 min 102
103
104
105
106
107
Prototype Base Routing Sheet Part Name: Pump Base Customer Name: Solo Pump
Australia Ltd Quantity: 1
Stock size: 100 x 10 bar stock Material: Aluminium Length of bar stock: 75mm
Op. #
Process Description
Machine Speed Feed (mm/min)
Tooling Time (min)
Risk Assessment
100 Inspect dimensions of
material
n/a n/a n/a Vernier Calliper,
micrometer
2 Low
101 Mill material to 100 x 70 x 10
Milling machine
320 rpm 50 Face mill, carbide cutter
2 Close fitting clothing, eye protection and no wearing of
accessories that can be caught on spinning machinery
102 Mark all points of interest (i.e.
drill areas)
n/a n/a n/a Centre punch, ruler,
scriber, set square
5 Low
103 Mill out 5mm diameter slots
of 55mm length
Milling machine
16m/min 50 Slot drill 10 Close fitting clothing, eye protection and no wearing of
accessories that can be caught on spinning machinery
104 Inspect dimensions of
slots
n/a n/a n/a Telescopic gauges, Vernier Calliper
1 Low
105 Drill 10mm diameter hole in centre of top
face
Drill press
32m/min n/a 10mm drill bit
2 Close fitting clothing, eye protection and no wearing of
accessories that can be caught on spinning machinery
106 Drill four M5 counter bore
holes
Drill press
16m/min n/a 5.5mm drill bit, 9.0mm flat drill bit
16 Close fitting clothing, eye protection and no wearing of
accessories that can be caught on spinning machinery
107 Clean/Inspect and file off any sharp edges
n/a n/a n/a Vernier Callipers,
Brush, “Second
cut” file
2 Low
Total Time 40min
Piston
Ø39mm, Aluminium (65mm depth)
20
70
10 Inspect raw material 1 min
10 min Face ends, material, total 64mm height
25 min Turn shaft diameter to 11mm diameter, length 49mm from bottom surface, rough
Inspect 1 min 40
Turn O-ring groove to 1.95mm wide, 36.30 diameter, 6.53mm from the top surface
10 min
Inspect 1 min
30
50
80 5 min Drill 6mm hole 5mm from bottom surface
90 1 min File sharp ends
60 3 min Turn shaft diameter to 10mm
MMAN1130 ROUTING SHEET/ WORK METHOD SHEET Part Name: PISTON FOR PROTYPE Part Number: 2 Drawing No: 2 Revision No: 1 Date: 06/05/2014 Planner: JESSICA
AVEDAWN CHEN Material: Aluminium Stock Size: Ø39mm,65 mm length Comments: None
Operation Number
Description Machine/Tools Tools Speed/Feed (rpm)
Time (min)
Risk Assessment
200 Inspect raw material Vernier Caliper N/A N/A 1 Low 201 Face ends, material,
total 64mm height Centre Lathe
HSS Cutter 575 10 Sharp, high speed cutter and moving parts
202 Turn O-ring groove to 1.95mm wide, 36.30 diameter, 6.53mm from the top surface
Centre Lathe
HSS Cutter 575 10 Sharp, high speed cutter and moving parts
203 Inspect
Vernier Caliper N/A N/A 1 Low
204 Turn shaft diameter to 11mm diameter, length 49mm from bottom surface, rough
Centre Lathe
HSS Cutter 575, 640, 725, 830, 975, 1185, 1500
25 Sharp, high speed cutter and moving parts
205 Turn shaft diameter to 10mm
Centre Lathe
HSS Cutter 1500 3 Sharp, high speed cutter and moving parts
206 Inspect
Vernier Caliper N/A N/A 1 Low
207 Drill 6mm hole 5mm from bottom surface
Drill Press 6mm HSS Drill Bit 3750 5 High speed movement, sharp drill bit
208 Filing
Hand File Double Cut, Smooth Cut File
N/A 1 Low
TOTAL TIME: 57 min
Aluminium 50mmx50mmx49mm
301
302
306
307
308
300
305
304
303
1 minute
10 minutes
4 minutes
5 minutes
1 minute
10 minutes
15 minutes
1 minute
1 minute
Inspect material
Face top and bottom
Mark out center and points for holes
Drill 39mm hole in center
Check and measure
Drill eight 5mm holes on top and bottom
Tap eight M5 holes on top and bottom
Remove sharp edges and burs
Inspect
Routing sheet Part name: Piston Housing Part number: 3 Drawing number: 3 Stock size:
50mmx50mm Material: Aluminium Quantity: 1 Date: 02/06/14 Revision number: 2 Operation number
Process description
Machine/tool
Feed (m/min)
Speed (RPM)
Tooling Time (min)
Risk assessment
301 Inspect material
Calliper n/a n/a n/a 1 Low
302 Face both top and bottom
Mill 25 200 Face mill 10 Very sharp high speed cutter
303 Mark out centre and holes for 39mm hole and 8 10mm holes
Vernier calliper, magnetic angle plate, scriber
n/a n/a n/a 4 Low
304 Drill 39mm hole in centre
Drill 30 600 39mm twist drill bit
5 Very sharp high speed drill
305 Check and measure
Calliper n/a n/a n/a 1 Low
306 Drill 8 10mm holes on top and bottom
Drill 30 1000 5mm twist drill bit
10 Very sharp high speed cutter
307 Tap 8 M5 holes on top and bottom
Table vise n/a n/a M5 tapping bit, tap handle and set square
15 Low
308 Remove sharp edges and burs
File n/a n/a Second cut 1 Low
309 Inspect Calliper n/a n/a n/a 1 Low Total 53
Prototype Pump Cover
50mm x 50mm x 10mm, Aluminium
Inspect raw material 1 min
5 min Face surfaces
2 min
2 min
Drill and ream holes for 4 housing attachment screws 3 min
Drill hole for outlet tube
2 min
2 min
Tap inlet tube hole
1 min
Tap outlet tube hole
2 min
Drill hole for inlet tube
400
401
402
404
405
407
403
406
Drill holes at base of outlet tube hole
408 Inspect
PROTOTYPE HOUSING ROUTING SHEET
Part Name: Piston Cover Customer Name: Solo Pump Australia Ltd. Quantity: 1
Stock size: 50 x 50mm bar stock Material: Aluminium Length of bar stock: 10mm
Op.
# Process Description Machine Speed Feed (mm/min) Tools, Fixtures Time (min) Risk Assessment
400 INSPECT raw material - - - Vernier Calliper 1 -
401
FACE and SQUARE top and
bottom surfaces to
required dimensions
Turret Mill 300 rpm 240
Face Cutter
(carbide cutter),
Machine Vise
5
Loose clothing, jewellery, long hair/beards can get caught in spinning machinery. Must be confined or close fitting to body. Constant danger of flying particles. Eye protection must be warn.
402
DRILL and REAM 5mm
holes for the 4 housing
attachment screws
Drill Press 16 m/min 200 5mm Drill Bit,
Drill Vise 3
Loose clothing, jewellery, long hair/beards can get caught in spinning machinery. Must be confined or close fitting to body. Constant danger of flying particles. Eye protection must be warn.
403
DRILL and REAM 10mm
hole for inlet valve
(through entire block)
Drill Press 32 m/min 200 10mm Drill Bit,
Drill Vise 2
Loose clothing, jewellery, long hair/beards can get caught in spinning machinery. Must be confined or close fitting to body. Constant danger of flying particles. Eye protection must be warn.
404
DRILL and REAM 10mm
hole for outlet valve (until
3mm from bottom of
block)
Drill Press 32 m/min 200 10mm Flat Drill
Bit, Drill Vise 2
Loose clothing, jewellery, long hair/beards can get caught in spinning machinery. Must be confined or close fitting to body. Constant danger of flying particles. Eye protection must be warn.
405
DRILL and REAM 1.5mm
for the 2 holes at base of
outlet tube
Drill Press 5 m/min 200 1.5mm Drill Bit,
Drill Vise 2
Loose clothing, jewellery, long hair/beards can get caught in spinning machinery. Must be confined or close fitting to body.
Constant danger of flying particles. Eye protection must be warn.
406 TAP M12 for the inlet tube - - -
M12 Tapping Bit
(course), Bench
Vise
2 -
407 TAP M12 for the outlet
tube - - -
M12 Tapping Bit
(course), Bench
Vise
2 -
408 INSPECT holes and thread - - - Vernier Calliper 1 -
- TOTAL 20 -
Outlet valve
Ø12mm, Aluminium (35mm depth)
Inspect raw material 1 min
2 min Mill to size
3 min Cut O-ring groove
Bore 7.5mm hole 2 min
Drill 6mm hole 2 min
Tap external threads from top 2 min
Inspect/Clean 1 min
2 min Tap external threads from bottom
500
501
502
504
505
503
506
507
Inlet valve
Ø12mm, Aluminium (25mm depth)
Inspect raw material 1 min
2 min Mill to size
3 min Cut O-ring groove
Bore 7.5mm hole from bottom 2 min
Drill 6mm hole 2 min
Inspect/Clean 1 min
2 min Tap external threads from bottom
600
601
602
604
605
603
607
Dome nut
M12 x 1.75 Steel Dome Nut
Inspect 1 min
2 min Drill 4 holes
Inspect/Clean 1 min
700
701
702
Part: Outlet Valve
Stock Size: 12mm Dia Material: Aluminium
Length of bar: 35mm
Op. No Description Machine/Tools Speed/Feed Tooling Time (min)
1 Inspect Vernier Calliper 1
2 Cut to size Mill 2000RPM Face mill 2
3 Drill 6mm hole through Drill press 4000 RPM 6mm drill bit 2
4 Bore 7.5mm hole 10mm down from top
Drill press 3200 RPM 7.5mm flat bore ??
2
5 Cut o ring groove Lathe 2800 RPM ?? 3
6 Tap M12 threads on the exterior from bottom
Drill press 1300 mm/min
M12 tapping 2
7 Tap M12 threads on the exterior from top
Drill press 1300 mm/min
M12 tapping 2
8 Inspect Vernier Calliper 1
Table 1: Outlet valve routing sheet
Part: Inlet Valve
Stock Size: 12mm Dia Material: Aluminium
Length of bar: 25mm
Op. No Description Machine/Tools Speed/Feed Tooling Time (min)
9 Inspect Vernier Calliper
10 Cut to size Mill 2000RPM Face mill 2
11 Drill 6mm hole through Drill press 4000 RPM 6mm drill bit 2
12 Bore 7.5mm hole 10mm up from the bottom
Drill press 3200 RPM 7.5mm flat bore ??
2
13 Cut o ring groove Lathe 2800 RPM ?? 3
14 Tap M12 threads on the exterior from bottom
Drill press 1300 mm/min
M12 tapping 2
15 Inspect Vernier Calliper 1
Table 2: Inlet valve routing sheet
Part: Dome Nut
Shelf Component Material: Aluminium
M12x1.75 Dome Nut
Op. No Description Machine/Tools Speed/Feed Tooling Time (min)
16 Inspect Vernier Callipers 1
17 Drill 4 holes Drill press 9500 2.5mm drill bit 3
18 Inspect Vernier Calliper 1
Table 3: Dome Nut routing sheet
Outlet Valve
12 dia x 35, Aluminium
fig 1: Outlet valve routing chart
20
1 Inspect 1 min
2 min Mill to size
2 min Tap external threads from bottom
Cut o-ring groove 3 min
Bore 7.5mm hole 2 min
Tap external threads from top 2 min
4
6
1 min Inspect/Clean
Drill 6mm hole 2 min 3
2
5
7
8
Outlet Valve
12 dia x 25, Aluminium
fig 2: Inlet valve routing chart
Dome nut
M12 x 1.75 Steel Dome Nut
fig 3: Dome Nut routing chart
20
9 Inspect 1 min
2 min Mill to size
2 min Tap external threads from bottom
Cut o-ring groove 3 min
Bore 7.5mm hole from bottom 2 min 12
14
1 min Inspect/Clean
Drill 6mm hole 2 min 11
10
13
15
20
16 Inspect 1 min
2 min Drill 4 Holes
1 min Inspect/Clean
17
18
Appendix B
High Volume
5
50
10
100
70
19
19
10
TOP VIEW
10
9
5
5.50
FRONT VIEW
ISOMETRIC VIEW
AS1100
TITLE
TOLERANCE UNLESS NOTED OTHERWISE
APPROVED BY
CHECKED BY
REV DATE
DO NOT SCALE
A40.5mm ALUMINIUM
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSWDRAWN BY PUMP BASE
1QTY
J.A. CHEN (Z3461958)FIRST RELEASE DATE
1.6
1/6/143
DIMENSION IN MILLIMETRES DRAWING NUMBER
A. CHUNG (Z3463320)
2/4/14J.A. CHEN (Z3461958)
SURFACE FINISH UNLESS NOTED OTHERWISE
1
SCALEMATL1:1
SolidWorks Student Edition. For Academic Use Only.
R2
R2
R2
6
15
45
A
39
10
ISOMETRIC VIEW
1.9
5 0 0
1.35 -00.05
DETAIL A SCALE 2 : 1
AS1100
FRONT VIEW
TOP VIEW
TITLE
TOLERANCE UNLESS NOTED OTHERWISE
APPROVED BY
CHECKED BY
REV DATE
DO NOT SCALE
A40.3mm ALUMINIUM
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSWDRAWN BY
PISTON
100000QTY
G. CHENG (Z3463228)FIRST RELEASE DATE
1.6
04/06/20141
DIMENSION IN MILLIMETRES DRAWING NUMBER
J. A. CHEN (Z3461958)
06/06/2014G. CHENG (Z3463228)
SURFACE FINISH UNLESS NOTED OTHERWISE
2
SCALEMATL1:1
SolidWorks Student Edition. For Academic Use Only.
49
47
6
A
50
47
43 39
50
8 X M5 10 EQUALLY SPACED R2
6
1.2
0
DETAIL A SCALE 2 : 1
TOP VIEW
ISOMETRIC VIEW
FRONT VIEW
AS1100
TITLE
TOLERANCE UNLESS NOTED OTHERWISE
APPROVED BY
CHECKED BY
REV DATE
DO NOT SCALE
A40.5mm ALUMINIUM
DRAWN BYHOUSING
100000QTY
ALVIN CHUNG (Z3463320)FIRST RELEASE DATE
1.6
03/06/141
DIMENSION IN MILLIMETRES DRAWING NUMBER
LIZA CHAO(Z3463320)
03/03/14ALVIN CHUNG (Z3463320)
SURFACE FINISH UNLESS NOTED OTHERWISE
3
SCALEMATL1:1
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSW
SolidWorks Student Edition. For Academic Use Only.
A
50
R26.87
50
4x R2
M12
15
4.2 4 HOLES EQUALLY SPACED
M12 7 MIN LG
45°
ISOMETRIC VIEW
FRONT VIEW
TOP VIEW
AS1100
REV
TITLE
1:1
NOTED OTHERWISE
APPROVED BY
CHECKED BY
DATE
DO NOT SCALE
TOLERANCE UNLESS
A40.5mm ALUMINIUM
SCHOOL OF MECHANICAL AND MANUFACTURING ENGINEERING - UNSWDRAWN BY
PUMP COVER
1
QTY
NADAV COHEN (Z3460696)FIRST RELEASE DATE
MATL SCALE
1.6
06/06/2014
MILLIMETRESDRAWING NUMBER
GAVIN CHENG (Z3463228)
04/04/2014ALVIN CHUNG (Z3463320)
DIMENSION IN NOTED OTHERWISE
4
SURFACE FINISH UNLESS
1
10
4X R2
DETAIL A SCALE 2 : 1
4
2 X 1.5
SolidWorks Student License Academic Use Only
High Volume Routing Chart
Pump Base
Molten Aluminium
100
100
Die Cast 5 min
2 min Inspect
High Volume Base Routing Sheet Part Name: Pump Base Customer Name: Solo Pump
Australia Ltd Quantity: 100,000
Stock size: Size as casted Material: Aluminium Part Number: 1
Op. #
Process Description
Machine Speed Feed (mm/min)
Tooling Time (min)
Risk Assessment
100 Die cast using a pre-made
mold
Cold Chamber Machine
n/a n/a Die cast mold
10 Material of high temperatures are being used therefore
gloves, long sleeve clothing, eye protection must be worn
101 Inspect Optical Compara
tors
n/a n/a n/a 2 Low
Piston
Molten Aluminium
Die Cast Material
10 min
1 min Inspect Die Cast Material
200
201
PISTON ROUTING CHART FOR HIGH VOLUME
202 1 min Turn O-ring groove to 1.95mm wide, 36.30 diameter, 6.53mm from the top surface
201 1 min Clean and Inspect
MMAN1130 ROUTING SHEET/ WORK METHOD SHEET Part Name: PISTON FOR HIGH VOLUME Part Number: 2 Drawing No: 2 Revision No: 1 Date: 03/06/2014 Planner: JESSICA
AVEDAWN CHEN Material: Aluminium Stock Size: As Cast Comments: None
Operation Number
Description Machine/Tools Tools Speed/Feed (rpm)
Time (min)
Risk Assessment
200 Die Cast Material
Cold-Chamber Die Casting Machine
N/A N/A 10 Very hot material
201 Inspect Die Cast Material
N/A N/A N/A 1 Low
202 Turn O-ring groove to 1.95mm wide, 36.30 diameter, 6.53mm from the top surface
Lathe
HSS Cutter 575 1 Sharp, high speed cutter and moving parts
203 Clean and Inspect
N/A N/A N/A 1 Low
TOTAL TIME: 13 min
Molten aluminium
Part name: Piston Housing high volume
Part number: 3 Drawing number: 3 Stock size: as cast
Material: Aluminium Quantity: 100,000 Date: 02/06/14 Revision number: 1 Operation number
Process description
Machine/tool
Feed (m/min)
Speed (RPM)
Tooling Time (min)
Risk assessment
300 Inspect material
n/a n/a n/a Calliper 1 Low
301 Die-cast a 50mmx50mm square with filleted edges of 2mm. 39mm hole in centre. 4xM5 10mm holes on top and bottom
Cold chamber die machine
n/a n/a n/a 10 Hot molten metal
302 Mark out centre 8x10mm holes
n/a n/a n/a Vernier calliper, magnetic angle plate, scriber
4 Low
303 Tap 8 M5 holes on top and bottom
n/a n/a n/a M5 tapping bit, table vise, T square,
15 Low
304 Inspect Calliper n/a n/a n/a 1 Low Total 31
301
302
300
304
303
1 minute
10 minutes
4 minutes
1 minute
15 minutes
Inspect material
Die casting
Mark out center and points
for holes
Tap eight M5 holes on top and
bottom
Inspect
High Volume Pump Cover
Molten Aluminium
Die cast material 10 min
1 min Inspect casted material
Tap M12 for inlet and outlet valve holes 3 min
1 min
401
400
402
403 Inspect holes and threads
HIGH VOLUME HOUSING ROUTING SHEET
Part Name: Piston Cover Customer Name: Solo Pump Australia Ltd. Quantity: 100,000
Stock size: 50 x 50mm bar stock Material: Aluminium Length of bar stock: 10mm
Op. # Process Description Machine Speed Feed (mm/min) Tools, Fixtures Time (min) Risk Assessment
400 INSPECT casted material - - - Vernier Calliper 1 -
401 REAM all holes to required
dimension Drill Press 5 m/min 200
Drill Bits (5mm,
10mm, 1.5mm),
Drill Vise
4
Loose clothing, jewellery, long hair/beards can get caught in spinning machinery. They must be confined or close fitting to body Constant danger of flying particles. Eye protection must be warn.
402 TAP M12 for the inlet and
outlet valve holes - - -
M12 Tapping Bit
(course), Bench
Vise
3 -
403 INSPECT holes and thread - - - Vernier Calliper 1 -
- TOTAL 9 -
High Volume Routing Chart
Valve
Molten Aluminium
High Volume Routing Chart
Cap
Molten Aluminium
501
502
Die Cast 3 min
0.5 min Inspect
601
602
Die Cast 3 min
0.5 min Inspect
High Volume Valve Routing Sheet Part Name: Valve Customer Name: Solo
Pump Australia Ltd Quantity: 200 000
Stock size: Size as casted Material: Aluminium Part Number: 5
Op. #
Process Description
Machine Speed Feed (mm/min)
Tooling Time (min)
Risk Assessment
501 Die cast using a pre-made mould
Cold Chamber Machine
n/a n/a Die cast mould
3 Material of high temperatures are being used therefore
gloves, long sleeve clothing, eye protection must be worn
502 Inspect Optical Comparators
n/a n/a n/a 0.5 Low
High Volume Valve Routing Sheet Part Name: Cap Customer Name: Solo
Pump Australia Ltd Quantity: 100 000
Stock size: Size as casted Material: Aluminium Part Number: 5
Op. #
Process Description
Machine Speed Feed (mm/min)
Tooling Time (min)
Risk Assessment
601 Die cast using a pre-made mould
Cold Chamber Machine
n/a n/a Die cast mould
3 Material of high temperatures are being used therefore
gloves, long sleeve clothing, eye protection must be worn
602 Inspect Optical Comparators
n/a n/a n/a 0.5 Low
Appendix C
Solo Pump Australia Ltd 333 Princess Rd
Woodlawn, NSW 2330 Phone 9888 3344
Fax 9888 4433
To: PP175 product development team
FUNCTIONAL SPECIFICATION for the
PP175 Vertical Displacement Pump
must
The University of New South Wales School of Mechanical and Manufacturing Engineering
MMAN1130 Design and Manufacturing
Material List Material Section Material Cost per metre
50.0mm diameter round bar Aluminium $136.67 Steel $83.33
39.0mm diameter round bar Aluminium $105.33 Steel $62.00
10.0mm diameter round bar Aluminium $6.00 Steel $3.00
50mm x 50mm square Aluminium $140.00 Steel $122.67
Flat section: 100mm wide x 10mm thick Aluminium $56.00
Steel $47.33