design report print

Upload: suranga

Post on 07-Jul-2018

232 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/18/2019 Design Report Print

    1/227

      i

     

    TABLE OF CONTENTS

    1.0 - GEOMETRIC DESIGN OF ROADS ................................................................... 1

    1.1 INTRODUCTION ............................................................................................... 2

    1.1.1 GENERAL .................................................................................................... 2

    1.1.2. PROJECT DESCRIPTION .......................................................................... 3

    1.2. DESIGN CONTROL & CRITERIA .................................................................. 5

    1.2.1. TOPOGRAPHY ........................................................................................... 5

    1.2.2. TRAFFIC ..................................................................................................... 6

    1.2.2.1. ROAD USER ........................................................................................ 6

    1.2.2.2. TRAFFIC DATA .................................................................................. 6

    1.2.2.3. THE VEHICLE ..................................................................................... 7

    1.2.3. SPEED ......................................................................................................... 8

    1.2.4. SAFETY ...................................................................................................... 91.2.5. ECONOMIC CONSIDERATIONS .......................................................... 10

    1.3. WIDTH OF TRAFFIC LANES & SHOULDERS ........................................... 11

    1.3.1. GENERAL ................................................................................................. 11

    1.3.2. FACTORS AFFECTING THE LANE WIDTH ........................................ 11

    1.3.2.1. VEHICULAR TRAFFIC .................................................................... 12

    1.3.2.2. GENERAL LANE WIDTHS .............................................................. 12

    1.3.2.3. DERIVATIONS OF NUMBER OF LANES ..................................... 12

    1.3.3. SHOULDER WIDTHS .............................................................................. 18

    1.3.3.1. FACTORS AFFECTING SHOULDER WIDTH ............................... 18

    1.3.3.2. GENERAL SHOULDER WIDTH ..................................................... 18

    1.4. CROSS SECTION ELEMENTS ...................................................................... 191.4.1. GENERAL ................................................................................................. 19

    1.4.2. CARRIGEWAY ........................................................................................ 21

    1.4.3. SHOULDER .............................................................................................. 21

    1.4.4. MEDIAN.................................................................................................... 21

    1.4.5. PLATFORM .............................................................................................. 22

    1.4.6. CROSSFALL ............................................................................................. 22

    1.4.6.1. GENERAL .......................................................................................... 22

    1.4.6.2. PAVEMENT CROSSFALL ............................................................... 22

    1.4.6.3. SHOULDER CROSSFALL................................................................ 23

    1.4.7. DRAINS ..................................................................................................... 23

    1.4.7.1. SIDE DRAINS .................................................................................... 241.4.7.2. INTERCEPTER DRAINS .................................................................. 24

    1.4.7.3. SUB-SOIL DRAINS ........................................................................... 24

    1.4.7.4. CROSS SHOULDER DRAINS .......................................................... 25

    1.4.8. BATTERS .................................................................................................. 25

    1.4.8.1. CUT BATTER .................................................................................... 25

    1.4.8.2. FILL BATTER.................................................................................... 25

    1.4.8.3. SLOPE BENCHES ............................................................................. 26

    1.4.8.4. SIGHT BENCHES.............................................................................. 26

    1.4.8.5. FILL SLOPE TREATMENT .............................................................. 26

    1.4.9. PARKING STRIPS .................................................................................... 27

    1.4.9.1. GENERAL .......................................................................................... 27

  • 8/18/2019 Design Report Print

    2/227

      ii

    1.4.9.2. WIDTH OF PARKING STRIPS ........................................................ 27

    1.4.9.3. PARKING BAYS ............................................................................... 27

    1.4.9.4. CROSS FALL OF PARKING STRIPS AND BAYS......................... 28

    1.4.10. RIGHT OF WAY ..................................................................................... 28

    1.5. SIGHT DISTANCE .......................................................................................... 28

    1.5.1. GENERAL ................................................................................................. 281.5.2. CONSTANTS USED IN DESIGN FOR SIGHT DISTANCE ................. 28

    1.5.3. STOPPING SIGHT DISTANCE (SSD) .................................................... 29

    1.5.4. EFFECT OF GRADE IN BREAKING ..................................................... 30

    1.5.5. OVERTAKING SIGHT DISTANCE (OSD) ............................................ 31

    1.5.6. CONTINUATION SIGHT DISTANCE (CSD) ........................................ 32

    1.5.7. SIGHT DISTANCE AT GRADE CRESTS .............................................. 33

    1.5.8. HEAD LIGHT SIGHT DISTANCE .......................................................... 33

    1.6. HORIZONTAL ALIGNMENT ........................................................................ 33

    1.6.1. INTRODUCTION ..................................................................................... 33

    1.6.2. MOVEMENT ON A CIRCULAR PATH ................................................. 33

    1.6.3. SIDE FRICTION FACTOR ...................................................................... 351.6.4. HORIZONTAL CURVATURE ................................................................ 36

    1.6.4.1 GENERAL ........................................................................................... 36

    1.6.4.2. GENERAL CONSIDERATIONS IN DESIGNING HORIZONTAL

    ALIGNMENT .................................................................................................. 36

    1.6.4.3. SIMPLE CIRCULAR CURVE........................................................... 37

    1.6.4.4. TRANSITION CURVE ...................................................................... 39

    1.6.4.5. COMPOUND CURVE ....................................................................... 39

    1.6.4.6. REVERSE CURVE ............................................................................ 40

    1.6.4.7. SIMILAR CURVES ........................................................................... 40

    1.6.4.8. WIDENING OF CARRIGEWAY ON CURVES .............................. 40

    1.7. SUPERELEVATION ....................................................................................... 42

    1.7.1. GENERAL ................................................................................................. 42

    1.7.2. STANDARDS FOR SUPERELEVATION ............................................... 42

    1.7.3. CURVES WITH ADVERSE CROSSFALL ............................................. 42

    1.7.4. DEVELOPMENT OF SUPERELEVATION ............................................ 43

    1.7.4.1. AXIS OF ROTATION ........................................................................ 43

    1.7.4.2. SUPERELEVATION DEVELOPMENT LENGTH .......................... 44

    1.7.4.2.1. RELATIVE GRADIENT METHOD .......................................... 44

    1.7.4.2.2. RATE OF PAVEMENT ROTATION METHOD ....................... 45

    1.7.4.3. POSITIONING OF SUPERELEVATION ......................................... 48

    1.7.4.4. SUPERELEVATION DEVELOPMENT ON SHOULDERS............ 511.8. VERTICAL ALIGNMENT .............................................................................. 53

    1.8.1. GENERAL ................................................................................................. 53

    1.8.2. GENERAL CONSIDERATIONS OF IN DESIGNING THE VERTICAL

    ALIGNMENT ...................................................................................................... 53

    1.8.3. VERTICAL CURVES ............................................................................... 54

    1.8.3.1. CREST VERTICAL CURVES........................................................... 55

    1.8.3.1.1. GENERAL ................................................................................... 55

    1.8.3.1.2. LENGTH OF CREST CURVES ................................................. 55

    1.8.3.2. SAG VERTICAL CURVES ............................................................... 61

    1.8.3.2.1. GENERAL ................................................................................... 61

    1.8.3.2.2. LENGTH OF SAG CURVES ...................................................... 611.8.4. GRADES.................................................................................................... 64

  • 8/18/2019 Design Report Print

    3/227

      iii

    1.8.4.1. GENERAL .......................................................................................... 64

    1.8.4.2. STANDARDS FOR GRADES ........................................................... 65

    1.8.4.3. GRADES STEEPER THAN GENERAL MAXIMUM ..................... 67

    1.8.4.4. CRITICAL LENGTH OF GRADES .................................................. 67

    1.9. OTHER CONSIDERATIONS.......................................................................... 68

    1.9.1. GENERAL ................................................................................................. 681.9.2. CO-ORDINATION OF HORIZONTAL AND VERTICAL ALIGNMENT

    FOR SAFETY ...................................................................................................... 68

    1.9.3. CO-ORDINATION OF HORIZONTAL AND VERTICAL ALIGNMENT

    FOR AESTHETIC REASONS ............................................................................ 69

    1.10. REFERENCES ............................................................................................... 70

    2.0 - GEOMETRIC DESIGN OF INTERSECTION .................................................. 72

    2.1. INTRODUCTION ............................................................................................ 73

    2.1.1. GENERAL ................................................................................................. 73

    2.1.2. PROJECT DESCRIPTION ........................................................................ 74

    2.2. BASIC DATA FOR DESIGN .......................................................................... 75

    2.2.1. TRAFFIC DATA ....................................................................................... 752.2.1.1. PEAK HOUR TRAFFIC VOLUMES INCLUDING TURNING

    MOVEMENTS ................................................................................................ 75

    2.2.1.2. VEHICLE CHARACTERISTICS ...................................................... 80

    2.2.1.3. PEDESTRIAN TRAFFIC ................................................................... 81

    2.2.1.4. ACCIDENT DATA ............................................................................ 81

    2.2.1.5. PARKING DATA ............................................................................... 81

    2.2.1.6. PUBLIC TRANSPORT REQUIREMENTS ...................................... 81

    2.2.2. SITE TOPOGRAPHY ............................................................................... 82

    2.2.3. PHYSICAL FEATURES AND ITEMS OF CULTURAL, HISTORICAL

    AND RELIGIOUS SIGNIFICANCE .................................................................. 82

    2.2.4. OVERHEAD AND UNDERGROUND UTILITY SERVICES ............... 82

    2.2.5. RIGHT OF WAY PROBLEMS AND LIMITATIONS ............................ 83

    2.3. ANALYSIS OF DATA..................................................................................... 83

    2.3.1. ANALYSIS OF DATA FOR THE SELECTION OF DESIGN VEHICLE

    .............................................................................................................................. 83

    2.3.2. ANALYSIS OF DATA FOR SELECTION OF TYPE OF

    INTERSECTION ................................................................................................. 84

    2.3.2.1. TYPE OF INTERSECTION BASED ON TREATMENT ................. 84

    2.3.2.2. FACTORS AFFECTING SELECTION OF TYPE OF

    INTERSECTION ............................................................................................. 86

    2.3.3. BEST INTERSECTION TREATMENT FOR THE PROBLEM IN HAND.............................................................................................................................. 86

    2.4. ROUNDABOUTS ............................................................................................ 87

    2.4.1. TYPES OF ROUNDABOUTS AND SELECTION OF THE TYPE FOR

    THE DESIGN ...................................................................................................... 87

    2.4.1.1. MINI ROUNDABOUTS .................................................................... 87

    2.4.1.2. SMALL ROUNDABOUTS ................................................................ 87

    2.4.1.3. LARGE ROUNDABOUTS ................................................................ 87

    2.4.1.4. DOUBLE ROUNDABOUTS ............................................................. 88

    2.4.1.5. CONVENTIONAL ROUNDABOUTS .............................................. 88

    2.4.2. ELEMENTS OF A ROUNDABOUT ........................................................ 88

    2.4.2.1. CENTRAL ISLAND .......................................................................... 882.4.2.2. CENTRE ISLAND DIAMETER ........................................................ 89

  • 8/18/2019 Design Report Print

    4/227

      iv

    2.4.2.3. INSCRIBED CIRCLE DIAMETER................................................... 90

    2.4.2.4. CIRCULATING CARRIAGEWAY .................................................. 90

    2.4.2.5. CRCULATING CARRIAGEWAY WIDTH ..................................... 90

    2.4.2.6 GIVE WAY LINE ............................................................................... 90

    2.4.2.7. ENTRY CURVE ................................................................................. 91

    2.4.2.8. EXIT CURVE ..................................................................................... 912.4.2.9. APPROACH WIDTH ......................................................................... 91

    2.4.2.10. ENTRY / EXIT WIDTH ................................................................... 91

    2.4.2.11. DEPARTURE WIDTH ..................................................................... 92

    2.4.2.12. CORNER KERB RADIUS (KERB RETURN) ............................... 92

    2.4.2.13. SPLITTER ISLAND ......................................................................... 92

    2.4.3. GEOMETRIC DESIGN STANDARDS ................................................... 93

    2.5. CAPACITY ANALYSIS AND DELAY CALCULATIONS .......................... 93

    2.5.1. METHODS OF CAPACITY ANALYSIS ................................................ 93

    2.5.1.1. GAP ACCEPTANCE THEORY ........................................................ 93

    2.5.1.2. ANALYSIS PACKAGE ..................................................................... 94

    2.5.2. THE METHOD SELECTED FOR THE CAPACITY ANALYSIS ......... 942.6. PRELIMINARY DESIGN AND SELECTION OF A LAYOUT .................. 123

    2.7. GEOMETRIC DESIGN CALCULATIONS .................................................. 130

    2.7.1. CIRCULATING TRAFFIC SPEED ........................................................ 130

    2.7.2. THROUGH TRAFFIC SPEED ............................................................... 130

    2.7.3. CIRCULATING CARRIGEWAY WIDTH ............................................ 132

    2.7.4. ENTRY AND EXIT CURVES ................................................................ 134

    2.7.5. SIGHT DISTANCE ................................................................................. 135

    2.7.6. VERTICAL CURVES ............................................................................. 135

    2.7.7. SPLITTER ISLAND ................................................................................ 135

    2.8. REFERENCES ............................................................................................... 137

    3.0 - DESIGN OF SURFACE WATER DRAINAGE SYSTEM FOR

    INTERSECTION ....................................................................................................... 139

    3.1. INTRODUCTION .......................................................................................... 140

    3.1.1. GENERAL ............................................................................................... 140

    3.1.2. PROJECT DESCRIPTION ...................................................................... 140

    3.2. STORM WATER RUNOFF ESTIMATION ................................................. 141

    3.2.1. INTENSITY OF RAINFALL .................................................................. 141

    3.2.2. SELECTION OF DESIGN STORM RECURRENCE INTERVAL ....... 143

    3.2.3. TIME OF CONCENTRATION ............................................................... 143

    3.2.4. PEAK RUN-OFF ..................................................................................... 144

    3.2.4.1. DIFFERENT METHODS FOR ESTIMATING OF PEAK RUN-OFF........................................................................................................................ 145

    3.2.4.2. RATIONAL METHOD .................................................................... 146

    3.2.4.2.1. RATIONAL FORMULA........................................................... 146

    3.2.4.2.2. ADVANTAGES AND DISADVANTAGES OF THE

    RATIONAL FORMULA........................................................................... 147

    3.2.4.2.3. COEFFICIENT OF RUN-OFF .................................................. 147

    3.2.4.3. APPLICATION IN THE PROJECT ................................................ 148

    3.2.5. DEPTH OF FLOW AND LENGTH OF FLOW PATH .......................... 150

    3.2.5.1. DEPTH OF FLOW ........................................................................... 150

    3.2.5.2. LENGTH OF FLOW PATH ............................................................. 150

    3.3. FLOW IN HIGHWAY GUTTERS ................................................................ 1503.3.1. INTRODUCTION ................................................................................... 150

  • 8/18/2019 Design Report Print

    5/227

      v

    3.3.2. FORMULA FOR FLOW IN TRIANGULAR GUTTER ........................ 151

    3.3.3. PONDED WIDTH ................................................................................... 153

    3.3.4. CALCULATIONS FOR FLOW IN GUTTERS...................................... 153

    3.4. INLETS ........................................................................................................... 154

    3.4.1. INTRODUCTION ................................................................................... 154

    3.4.2. TYPES OF INLETS ................................................................................ 1543.4.2.1. GRATED INLETS............................................................................ 154

    3.4.2.2. KERB OPENING INLETS............................................................... 155

    3.4.2.3. COMBINATION OF GRATED AND KERB OPENING INLETS 156

    3.4.3. SELECTION OF TYPE OF INLET FOR THE DESIGN ....................... 156

    3.4.4. CAPACITY OF INLETS ......................................................................... 156

    3.4.4.1. GENERAL ........................................................................................ 156

    3.4.4.1.1. CAPACITY OF KERB OPENING INLET ON A

    CONTINUOUS GRADE ........................................................................... 156

    3.4.4.1.2. CAPACITY OF KERB OPENING INLET ON SAG ............... 157

    3.4.4.2. SPECIMEN CALCULATIONS ....................................................... 157

    3.4.5. GENERAL RULES FOR SPACING OF INLETS ................................. 1573.4.6. INLET COMPUTATIONS ...................................................................... 158

    3.4.6.1. DESCRIPTION OF TABLE FOR INLET COMPUTATIONS AND

    SPECIMEN CALCULATIONS .................................................................... 158

    3.5. FLOW IN RECTANGULAR DRAINS ......................................................... 163

    3.5.1. INTRODUCTION ................................................................................... 163

    3.5.2. DESIGN CRITERIA ............................................................................... 163

    3.5.3. CAPACITY OF RECTANGULAR DRAINS ......................................... 164

    3.5.3.1. GENERAL ........................................................................................ 164

    3.5.3.2. CALCULATIONS AND PREPARATION OF GRAPHS FOR

    DESIGN ......................................................................................................... 164

    3.5.4. STORM DRAIN COMPUTATIONS ...................................................... 165

    3.6. REFERENCES ............................................................................................... 170

    4.0 – BILL OF QUANTITIES ................................................................................... 172

    4.1. SUMMARY OF THE BILL OF QUANTITIES ............................................ 173

    4.2. BILL OF QUANTITIES ................................................................................. 175

    4.3. TAKING OFF SHEETS ................................................................................. 180

    4.4. RATE ANALYSIS FOR B.O.Q. ITEMS ....................................................... 208

    LIST OF TABLES

    Table 1.2.1 – Classification of Terrain .......................................................................... 5

    Table 1.2.2 – Traffic data for Palugama-Boralanda-Haputale road ............................... 7

    Table 1.2.3 – Relationship of the Design Speed related with the Road Classification,

    Terrain and the Design Volume. .................................................................................... 9

    Table 1.3.1 – Minimum width of sealed pavements of undivided roads ..................... 13

    Table 1.3.2 – Design Level of Service ......................................................................... 14

    Table 1.3.3 – Adjustment factors for directional distribution (f d) .............................. 16

    Table 1.3.4 - Adjustment factors for the combined effect of narrow lanes and

    restricted shoulder width (f w) ...................................................................................... 16

    Table 1.3.5 - Average Passenger Car Equivalent for Trucks and Buses on Two Lane

    Highways over Different Terrain Segments ................................................................ 16Table 1.4.1 - Recommended Cross-falls on Straight for Different Surface Types ...... 23

  • 8/18/2019 Design Report Print

    6/227

      vi

    Table 1.4.2 - Recommended Shoulder Cross-falls on Straight .................................... 23

    Table 1.5.1 – Longitudinal Friction Factors ................................................................ 30

    Table 1.5.2 - Design Values for Stopping, Overtaking & Intermediate Sight Distances

    on Bituminous and Concrete Pavements ..................................................................... 32

    Table 1.6.1 – Maximum Superelevaion Values ........................................................... 35

    Table 1.6.2 - Maximum Design Values of Co-efficient of Side Friction .................... 36Table 1.6.3 – Minimum Radii for Different Superelevation ....................................... 38

    Table 1.6.4 – Radii selected, with corresponding Superelevation ............................... 38

    Table 1.6.5 – Design values for pavement widening on open highway curves ........... 41

    Table 1.7.1 - Minimum Radii with Adverse Cross Fall ............................................... 43

    Table 1.7.2 – Maximum Relative Gradients ................................................................ 45

    Table 1.7.3 - superelevation values and corresponding length of superelevation

    development for various radii and design speed .......................................................... 47

    Table 1.8.1 - Minimum Crest Vertical Curve Length Based on Sight Distance Criteria

    ...................................................................................................................................... 56

    Table 1.8.2 – Minimum Vertical Curve Length Based on Appearance Criterion ....... 58

    Table 1.8.3 – Minimum Vertical Curve Length Based on Comfort Criterion ............. 60Table 1.8.4 - Minimum Sag Vertical Curve Length Based on Head Light Sight

    Distance Criterion ........................................................................................................ 62

    Table 1.8.5 – Maximum Gradients .............................................................................. 66

    Table 1.8.6 – Critical length of Grades ........................................................................ 68

    Table 2.2.1 (a) - Summary of Peak Hour Turning Moments in Morning Peak (0915 –

    1015 Hrs) at Gabada Junction (in Veh / h) .................................................................. 77

    Table 2.2.1 (b) - Summary of Peak Hour Turning Moments in Mid day Peak (1100 –

    1200 Hrs) at Gabada Junction (in Veh / h) .................................................................. 78

    Table 2.2.1 (c) - Summary of Peak Hour Turning Moments in Evening Peak (1700 –

    1800 Hrs) at Gabada Junction (in Veh / h) .................................................................. 79

    Table 2.2.2 - Equivalent Passenger Car Units ............................................................. 80

    Table 2.3.1 - Composition of Vehicles at Hambantota Intersection during Peak Hours

    of the Day ..................................................................................................................... 84

    Table 2.5.1(a) - Summary of Peak Hour Turning Moments in Morning Peak (0915 –

    1015 Hrs) at Gabada Junction (in PCU / h) ................................................................. 96

    Table 2.5.1(b) - Summary of Peak Hour Turning Moments in Mid day Peak (1100 –

    1200 Hrs) at Gabada Junction (in PCU / h) ................................................................. 97

    Table 2.5.1(c) - Summary of Peak Hour Turning Moments in Evening Peak (1700 –

    1800 Hrs) at Gabada Junction (in PCU / h) ................................................................. 98

    Table 2.5.3 – No. of entry lanes and approach lanes in Hambantota intersection ..... 103

    Table 2.5.4 – Widths of entry lanes and approach lanes in Hambantota intersection103Table 2.5.5 - Dominant- Stream Follow-up Headways (tfd) (Initials Values) in seconds

    .................................................................................................................................... 105

    Table 2.5.6 - Adjustment Times for the Dominant Stream Follow-up Headway ...... 106

    Table 2.5.7 - Sub-dominant Steam Follow-up headway tfs ....................................... 106

    Table 2.5.8 - Ratio of the Critical Acceptance Gap to the Follow-up Headway(tad / tfd )

    .................................................................................................................................... 107

    Table 2.5.9 - Average headway between bunched vehicles in the circulating traffic (τ)and the number of effective lanes in the circulating carriageway. ............................ 108

    Table 2.5.10 - Proportions of Bunched Vehicles, θ ................................................... 109Table 2.5.11 (a) - Geometric Delay for Stopped Vehicles (Seconds per Vehicles) .. 116

    Table 2.5.11 (b) - Geometric Delay for Vehicles, Which Do Not Stop (Seconds perVehicles) .................................................................................................................... 117

  • 8/18/2019 Design Report Print

    7/227

      vii

    Table 2.5.12 - Geometric Delay Values for Gonnoruwa Leg of Hambantota

    Roundabout ................................................................................................................ 118

    Table 2.5.13 - Geometric Delay and Total Average Delay Values for Movements of

    Gonnoruwa Leg of Hambantota Roundabout. ........................................................... 119

    Table 2.5.14 - Data Required for Capacity Calculations ........................................... 120

    Table 2.5.15 - Capacity Calculations & Queuing Delay Calculations ...................... 121Table 2.5.16 (a) - Geometric Delay Calculations & Total Delay Calculations –

    Morning Peak ............................................................................................................. 122

    Table 2.5.16 (b) - Geometric Delay Calculations & Total Delay Calculations – Mid-

    Day Peak .................................................................................................................... 122

    Table 2.5.16 (c) - Geometric Delay Calculations & Total Delay Calculations –

    Evening Peak ............................................................................................................. 123

    Table 2.7.1 - Entry and Exit Curve Radius of Hambantota Roundabout .................. 134

    Table 2.7.2 - The splitter island areas for Habmantota Roundabout ......................... 136

    Table 3.4.1 – Inlet Computations ............................................................................... 160

    Table 3.5.1 - Q/S½

     values for varying depth ............................................................. 165

    Table 3.5.2 – Storm Drain Computations .................................................................. 169

    LIST OF FIGURES

    Figure 1.1.1 – Location Map of Palugama-Boralanda-Haputale road. .......................... 4

    Figure 1.4.1 – Typical cross section of a road ............................................................. 20

    Figure 1.7.2 - Edge profile for a Circular curve .......................................................... 49

    Figure 1.7.3 - Edge profile for Reverse curve ............................................................. 50

    Figure 1.7.4 - Edge profile for Compound curve......................................................... 51

    Figure 1.7.5 – Development of superelevation in sealed shoulder .............................. 52Figure 1.7.6 – Development of superelevation in unsealed shoulder .......................... 52

    Figure 1.8.1 – Basic Elements of a typical vertical curve ........................................... 54

    Figure 1.8.2 – Crest vertical curves ............................................................................. 55

    Figure 1.8.3 – Sag vertical curves ................................................................................ 61

    Figure 2.2.1 – Traffic Data at the intersection from 7.00 to 19.00 hrs ........................ 76

    Figure 2.4.1 – Geometric Elements of a Roundabout .................................................. 89

    Figure 2.5.1(a) – Traffic turning volumes in Morning Peak hour (9.15-10.15) .......... 99

    Figure 2.5.1(b) – Traffic turning volumes in Mid day Peak hour (11.00-12.00) ....... 100

    Figure 2.5.1(c) – Traffic turning volumes in Evening Peak hour (17.00-18.00) ....... 101

    Figure 2.5.2 – Required No. of Circulating and Entry lanes ................................... 102

    Figure 2.5.3 –Proportion of vehicles stopped on a multi lane entry roundabout ....... 115

    Figure 2.5.4 – Definitions of the terms used in Table 2.5.11(a) and 2.5.11(b) .......... 118

    Figure 2.5.5 – Alternative 1 ....................................................................................... 125

    Figure 2.5.6 – Alternative 2 ....................................................................................... 126

    Figure 2.5.7 – Alternative 3 ....................................................................................... 127

    Figure 2.5.8 – Alternative 4 ....................................................................................... 128

    Figure 2.5.9 – Alternative 5 ....................................................................................... 129

    Figure 2.7.1 – Derivation of turning roadway width on curves at intersection ......... 132

    Figure 3.2.1 – Rainfall Intensity – Duration Curves .................................................. 142

    Figure 3.2.2 – Coefficient of Run-off ........................................................................ 149

    Figure 3.3.1 – Flow in Triangular Gutter ................................................................... 151

  • 8/18/2019 Design Report Print

    8/227

      viii

  • 8/18/2019 Design Report Print

    9/227

      1

     

    1.0 - GEOMETRIC DESIGN OF ROADS

    REPORT

    ON

    GEOMETRIC DESIGN

    OF

    PALUGAMA-BORALANDA-HAPUTALE ROAD

    (B 353) FROM 0+000 TO 27+200(SECTION FROM 2+800 TO 5+450)

  • 8/18/2019 Design Report Print

    10/227

      2

    1.1 INTRODUCTION

    1.1.1 GENERAL

    Geometric design is an important aspect of Highway Design dealing with the visible

    dimensions of a roadway. To produce a well balanced design, all geometric elements

    such as

    Horizontal alignment

    Vertical alignment

    Sight distances

    Cross-section components

    Lateral and vertical clearance

    Intersection treatment

    Control of access

    should economically feasible as far as possible, while providing safe continuous

    operation at a speed likely under the general conditions for the highway. Mainly this

    is achieved through the use of design speed as the overall control. In the design of

    highway curves, it is necessary to establish the proper relation between design speed

    and curvature and their joint relations with super elevation and side friction.

    A well designed highway has to be consistent with the economy. There are some

    other factors influence the geometric design are the availability of funds and the

    adjacent land use. If design is carried out improperly it may result in early

    obsolescence of the new highway with considerable economic losses.

  • 8/18/2019 Design Report Print

    11/227

      3

    1.1.2. PROJECT DESCRIPTION

    Palugama-Boralanda-Haputale road, which is approximately 27 km in length “B

    353” route, connects the two major suburb towns, Keppetipola and Haputale in Uva

    Province. The road stretch bears an Annual Daily Traffic of 1399 vehicles. Currently

    it functions as two lane two way road with an average carriageway width of 5.0 m

    and it runs on a rolling terrain of average gradient being 8%.

    Carriageway is not divided into lanes and no built up drains are provided. Bends are

    not met with geometric standards. The travelers those who are going visit the

     Adisham Bungalow which is a historic place popular among the locals and foreignershave to go along the this particular road. If the mobility had been improved in this

    road it will be helpful for the tourism industry. These factors had been inspired to

    improve this road.

    The other factors lead to improve the above road is the poor vertical alignment,

    narrow carriageway width, poor sight distance and humpy road surface.

    This report describes the general principles of the geometric design and its

    application to the detailed design of Palugama-Boralanda-Haputale road from

    chainage 2+800 to 5+450.

  • 8/18/2019 Design Report Print

    12/227

      4

    Figure 1.1.1 – Location Map of Palugama-Boralanda-Haputale road.

  • 8/18/2019 Design Report Print

    13/227

      5

    1.2. DESIGN CONTROL & CRITERIA

    The design criteria determines roadway geometric. The principal factors influencing

    the choice of design standard for a particular road section are as follows.I.  Topography.

    II.  Traffic.

    III.  Speed.

    IV.  Safety.

    V.  Economic consideration

    VI.  Financial level.

    1.2.1. TOPOGRAPHY

    Terrain type is one of the main factors which govern the vehicular speed. Terrain also

    has a significant effect on the costs of achieving high geometric standards. Therefore

    terrain can be considered as one of the main element used in selecting the design

    criteria. In geometric design, roads are divided into sections with uniform terrain

    characteristics, i.e. Flat, Rolling, Mountainous. Table 1.2.1 gives the classification ofterrain based on its representative slope.

    Table 1.2.1 – Classification of Terrain

    Terrain Type Code Corridor Slope %

    Flat

    Rolling

    Mountainous

    F

    R

    M

    10

    10-25

    >25

    The topography of the section from 2+800 to 3+500 and from 4+750 to 5+450 of

    Palugama-Boralanda-Haputale road can be considered as flat. The remaining section

    is a Rolling terrain.

  • 8/18/2019 Design Report Print

    14/227

      6

    1.2.2. TRAFFIC

    Traffic composes of the following groups.

    1. 

    The road user2.  Traffic data

    3.  The vehicle

    1.2.2.1. ROAD USER

    As the road user (Drivers and Pedestrians) is the main part of the road system. Human

    behavior and limitations should be considered in all road designs.

    1.2.2.2. TRAFFIC DATA

    The geometric design of roads is mainly based on the traffic data. Traffic data is

    classified as follows.

    I.  Volume of Traffic.

    A road should be designed so that it will accommodate, or can be readily

    changed to accommodate, the number of vehicles which is estimated will be

    using at the end of its service life with a desired level of service. The traffic

    volume is usually the Annual Average Daily Traffic (AADT) and number of

    traffic lanes required is a function of traffic volume. The number of vehicles

    using a road in a given time determines the number of traffic lanes required.

    II. 

    Composition of Traffic.

    Road traffic is a mixture of passenger cars and commercial vehicles. Compared

    to passenger cars, commercial vehicles are slow in speed occupy a greater length

    and width of road, and on ascending grades, their speeds fall to lower figures

    quicker. Therefore such vehicles on a road reduce its capacity and a road

    capable of carrying a set number of passenger cars will carry fewer mixed

    vehicles. The composition of traffic is a factor in the determination of width of

    traffic lanes and to some extent, the maximum grade on a road.

  • 8/18/2019 Design Report Print

    15/227

      7

     

    Traffic data given by the Traffic & Planning Division of Road Development Authority

    in Palugama-Boralanda-Haputale road is tabulated in Table 1.2.2.

    Table 1.2.2 – Traffic data for Palugama-Boralanda-Haputale road

    Vehicle Composition ADT = 1399

    Percentage %

     Motor Cycle

    Three wheel

    CarVan

     Medium Bus

     Large Bus

     Light Goods Vehicles

     Medium Goods Vehicles

     Large Lorries

    Farm Vehicles

    28.99

    31.39

    8.155.66

    0.69

    7.89

    5.49

    6.17

    2.49

    3.09

    1.2.2.3. THE VEHICLE

    The vehicle data which affect the design are axle load, axle spacing, wheel base,

    overall length, width, height and minimum turning radius.

    The design vehicle is a motor vehicle whose weight dimensions and operating

    characteristics are used to establish design controls. For this purpose vehicles are

    classified into following groups.

    I.  P design vehicle - Passenger Car class

    II.  SU design vehicle - Single unit trucks and buses

    III.  WB-40 design vehicle - Semi-trailor intermediate

    IV. 

    WB-50 design vehicle - Semi-trailor combination

  • 8/18/2019 Design Report Print

    16/227

      8

    1.2.3. SPEED

    Speed maintained by a driver for a given road section depends upon following

    conditions.

    I.  Type of terrain.

    II.  Weather.

    III.  Volume of traffic.

    IV.  Speed limitations.

    In a road section having uniform topographical character all curves should be of a

    uniform speed value. At the places where there is a change of topography and if it is

    necessary to change the speed from one section to another it is desirable to change the

    speed in steps of 10km/h contributing to safe driving condition.

    Design speed applies to individual geometric elements and is the speed that is used to

    co-ordinate sight distance, curve radius, super elevation and friction demand for

    elements of the road so that the driver negotiating each element at its design speeds.

    The design speed for this particular road is 40km/h. But the topographic constrains

    limit the design speed to 30km/h in some sections.

    Table 1.2.3 gives the design speed values corresponding to the road class, terrain type

    and design volume.

  • 8/18/2019 Design Report Print

    17/227

      9

    Table 1.2.3 – Relationship of the Design Speed related with the Road Classification,

    Terrain and the Design Volume.

    Type of

    RoadRoad Class Terrain

    Design

    Volume

    PCU/day

    Design Speed

    Km/h

    Rural Urban

    R0 A F72,000-

    108,00080 70

    R1 AF

    40,000-72,00080 70

    R 70 60

    R2 A,B

    F

    25,000-40,000

    80 70

    R 70 70

    M 60 60

    R3 A,B

    F

    18,000-25,000

    70 60

    R 60 60

    M 50 50

    R4 C,D

    F

    300-18,000

    60 50

    R 50 50

    M 40 40

    R5 D,E

    F

  • 8/18/2019 Design Report Print

    18/227

      10

    traffic control devices. To provide safety of pedestrians, sufficient width of sidewalks,

    proper signing and pedestrian crossing to be accommodated.

    The existing trace is having poor geometric features such as inadequate sight

    distances at the bends and inadequate carriageway and shoulder width. As these sub

    standard will tend to promotes accidents, in designing new trace adequate amounts

    were provided for above.

    1.2.5. ECONOMIC CONSIDERATIONS

    Before taking the final decision on the horizontal alignment on a particular road, it isnecessary to compare the economic aspect of various alternative of horizontal design.

    Above mentioned economic aspect should be made on,

    The cost required for,

    I.  Construction.

    II.  Acquisition.

    III.  Vehicle operation.

    A properly designed highway afford benefit to the community as it improve

    transportation facilities, reduction of travel time, reducing accidents, dropping of

    vehicle maintenance cost and enhancing vehicle lifetime.

     In the design of Palugama-Boralanda-Haputale Road, attempts were made to

    establish more favorable geometric features by following the existing centre line of

    the road. Cost components of the project, when providing the improved facilities will

    be the cost of land acquisition, cost of construction and cost of maintenance. Due

    consideration was paid in establishing limitations for geometric elements such as

    maximum grade, minimum curve radius, sight distance requirement etc. to keep the

    total cost to minimum. Efforts were taken to reduce the number of buildings affected

    due to the improvements.

  • 8/18/2019 Design Report Print

    19/227

      11

    1.3. WIDTH OF TRAFFIC LANES & SHOULDERS

    1.3.1. GENERAL

    Width of traffic lane influence the safety, comfort of driving and Level Of Service of

    that particular road. With the increase of lane width vehicles could be driven freely in

    a broaden width. Hence it provides safety and comfort of driving. The width of

    carriageway is determined in terms of the number of traffic lanes and width of a

    traffic lane. Number of lanes to be provided depends on the present and future

    anticipated traffic volume. Shoulder is the portion traveled adjoining to the outer edge

    of the traffic lane. Wider shoulder will be provided emergency stops for the vehicles.

    1.3.2. FACTORS AFFECTING THE LANE WIDTH

    When calculating the lane widths following factors are take into account.

    I.  Traffic –

    The volume and composition of traffic are the major factors which

    determine the width of traffic lanes. Average Annual Daily Traffic

    (AADT) of the particular road and peak hour traffic volume are required.

    II.  Vehicle Dimension –

    Commercial vehicles in traffic stream also influence the lane width.

    Normal steering deviations as well as the tracking errors and pavement

    imperfections reduce the clearance between passing vehicles.

    III.  Speed environment –

    Drivers have less control over the lateral position of a vehicle at high

    speed. Therefore at higher Design Speeds, high width of traffic lane is

    required.

  • 8/18/2019 Design Report Print

    20/227

      12

    IV.  Combination of speed and traffic volume –

    When both the speed and traffic volume are high, narrow lane width

    should be avoided.

    1.3.2.1. VEHICULAR TRAFFIC

    The importance of vehicular traffic in the event of determination of traffic lane width

    was explained under Section 3.2.

    1.3.2.2. GENERAL LANE WIDTHS

    The width of carriageway is determined in terms of the number of traffic lanes and

    width of a traffic lane. A traffic lane is defined as the width used for single line of

    traffic operation. The desirable lane width is taken as 3.7m. The absolute minimum

    lane width shall be 3.1m.

    1.3.2.3. DERIVATIONS OF NUMBER OF LANES

    a)  By tables in NASSRA

    Table 1.3.1 gives the recommended minimum width of sealed carriageway of

    undivided roads.

  • 8/18/2019 Design Report Print

    21/227

      13

     

    Table 1.3.1 – Minimum width of sealed pavements of undivided roads

    Design

    Speed

    Km/h

    Minimum carriageway width(m) for design traffic

    volumes(AADT)

    1-140 141-300 301-1100 1101-2200 Over 2200

    40 3.7 5.6 6.2 - -

    50 3.7 5.6 6.2 6.8 7.4

    60 3.7 6.2 6.8 6.8 7.4

    70 3.7 6.2 6.8 6.8 7.4

    80 3.7 6.2 6.8 7.4 7.4

    90 3.7 6.2 6.8 7.4 7.4

    100 3.7 6.8 6.8 7.4 7.4

    110 3.7 6.8 7.4 7.4 7.4

    120 3.7 6.8 7.4 7.4 7.4

     As per Table 1.3.1 minimum carriageway width required, corresponding to design

    speed of 30-50km/h and traffic volume (AADT) of 1399 is 6.8m. However taking in to

    account the acquisition problems and construction cost a 6.4m wide carriageway is

     provided.

    b)  Capacity analysis – level of service concept

    The concept of Level Of Service (LOS) is the different operational qualities of the

    traffic flow. Level Of Service is a qualitative measure of speed and travel time,

    freedom to maneuvers, traffic interruption, driving comfort, convenience, safety and

    operating cost.

    Six Level Of Service are categorized from A to F and it cover entire range of traffic

    condition which may occur.

    Level Of Service A – Free flow with high speed and low volumes. Drivers can hold

    their desired speeds without delays.

  • 8/18/2019 Design Report Print

    22/227

      14

     

    Level Of Service B – Reasonably free flow. Stable flow and drivers have reasonable

    freedom to select their speed.

    Level Of Service C – Stable flow. Most drivers are restricted in their freedom to select

    their own speed, change lanes, overtake etc... But operating speeds are still

    reasonable.

    Level Of Service D – Approaches unstable flow with nearly all drivers restricted.

    Comfort and convenience are low but may be tolerated for short periods. Fluctuations

    in conditions cause substantial drops in speed. As this service volume corresponds to

    what is referred as tolerable capacity, this level of service should be used to determine

    the upper limit of traffic demand which should be tolerated.

    Level Of Service E – Unstable flow and there may be momentary stoppages. This

    LOS is obtained with traffic volumes with near or at capacity.

    Level Of Service F – Forced or breakdown flow operating at low speed caused by the

    demand exceeding capacity. There is stop-start operation with large queues and

    delays. In the extreme both speed and volume can drop to zero.

    New roads are normally designed for LOS C or even D. The design level of service

    may be as in the Table 1.3.2.

    Table 1.3.2 – Design Level of Service

    Road ClassDesign

    speed(km/h)

    Design Level Of

    Service

    Volume/Capacity

    ratio

    A

    B

    C,D,E

    70 or more

    60 or more

    50 or more

    C

    D

    E

    0.6-0.8

    0.8-0.9

    >0.9

  • 8/18/2019 Design Report Print

    23/227

      15

    The capacity is the maximum hourly rate at which vehicles can reasonably be

    expected to traverse a point or uniform section of a lane at LOS E.

    The service flow rate is the maximum hourly rate of a lane or roadway under

    prevailing roadway, traffic and control conditions while maintaining a designated

    level of service. To calculate the service flow rate, equation 1.3.1 and 1.3.2 is applied.

     HV wd i

    i  f  f  f cvSF  ****2800=   ……. (1.3.1)

    ( ) ( )[ ]1111   −+−+=  B BT T  HV   E P E P f    ……. (1.3.2)

    Where:

    SFi  = Total service flow rate in both directions for prevailing roadway and

    Traffic conditions, for level of service i, in vph

    (v/c)i  = Ratio of flow rate to ideal capacity for level of service i, obtained from

    Table 1.3.2

    f d  = Adjustment factor for directional distribution of traffic, obtained from

    Table 1.3.3. In the absence of directional distribution factor, it is better to use

    60/40 as the directional distribution factor

    f w  = Adjustment factor for narrow lanes and restricted shoulder width, obtained

    from Table 1.3.4

    f HV  = Adjustment factor for the presence of heavy vehicles in the traffic stream

    PT = Proportion of trucks in the traffic stream, expressed as a decimal

    PB  = Proportion of buses in the traffic stream, expressed as a decimal

    ET, EB  = Passenger car equivalent for trucks and buses obtained from Table 1.3.5

  • 8/18/2019 Design Report Print

    24/227

      16

     

    Table 1.3.3 – Adjustment factors for directional distribution (f d)

    Table 1.3.4 - Adjustment factors for the combined effect of narrow lanes and

    restricted shoulder width (f w)

    Usable

    Shoulder

    Width

    (m)

    3.7 m Lanes 3.4 m Lanes 3.0 m Lanes 2.7 m Lanes

    LOS

    A - D

    LOS

    E

    LOS

    A - D

    LOS

    E

    LOS

    A - D

    LOS

    E

    LOS

    A - D

    LOS

    E

    >=1.8 1.00 1.00 0.93 0.94 0.84 0.87 0.70 0.76

    1.2 0.92 0.97 0.85 0.92 0.77 0.85 0.65 0.74

    0.6 0.81 0.93 0.75 0.88 0.68 0.81 0.57 0.70

    0 0.70 0.88 0.65 0.82 0.58 0.75 0.49 0.66

    Table 1.3.5 - Average Passenger Car Equivalent for Trucks and Buses on Two Lane

    Highways over Different Terrain Segments

    Vehicle Type Level Of Service Type of Terrain

    Level Rolling Mountainous

    Trucks, ET

    A 2.0 4.0 7.0

    B and C 2.2 5.0 10.0

    D and E 2.0 5.0 12.0

    Buses, EB

    A 1.8 3.0 5.7

    B and C 2.0 3.4 6.0

    D and E 1.6 2.9 6.5

    Directional Distribution 100/0 90/10 80/20 70/30 60/40 50/50

    Adjustment Factor, f d0.71 0.75 0.83 0.89 0.94 1.00

  • 8/18/2019 Design Report Print

    25/227

      17

     

    Specimen Calculation for Palugama-Boralanda-Haputale road;

     Average Daily Traffic = 1399(In 2009)

    Present peak Hour Traffic = 10% of ADT

    = 140

     f d   =0.94(From Table 1.3.3- assuming 60/40

    distribution)

     f w = 0.77 (from Table 1.3.4)

    (v/c) I =0.8 (from Table 1.3.2)

    PT =17.24% (5.49%+6.17%+2.49%+3.09%)

    P B  =8.58% (0.69%+7.89%)

     E T   =5.0

     E  B  =2.9

    From Equation 1.3.2,

    F  HV   = 1 /{ 1+[17.24 x (5.0 –1)/100 + 8.58 x (2.9 –1)/100]} = 0.54

    From Equation 1.3.1

    SF i  = 2800 x 0.8 x 0.94 x 0.77 x 0.54 = 875

    Traffic growth rate is 5% and assuming the road will reach to its capacity after n

     years.

    875 = 140 x (1.05)n

    n =37.5

    The road will maintain the LOS D for 37 years from 2009. 

  • 8/18/2019 Design Report Print

    26/227

      18

    1.3.3. SHOULDER WIDTHS

    1.3.3.1. FACTORS AFFECTING SHOULDER WIDTH

    The width of shoulder should be chosen in relationship to the traffic and topography

    after due consideration of the following

    a)  Provision of space for -

    •  Maneuvering to escape potential accidents.

    •  Emergency and rest stops.

    •  Emergency operations

    • 

    Guide posts or guard fence

    b)  Reduction of driving strain by the provision of extra width.

    c)  Separation of drains from pavement with resultant decrease in seepage effects.

    d)  Structural support for the pavements.

    e)  Appearance and traffic capacity of the road.

    1.3.3.2. GENERAL SHOULDER WIDTH

    The minimum shoulder width for two-way rural roads unless the volumes are below

    150 vpd should be 1.0 m. Shoulders less than 1.0 m width result in vehicles on the

    adjacent lane travelling closer to the road centre line. A width of 1.5 m to 2.0 m

    ensures capacity of the adjacent lane is unaffected by obstructions outside the

    shoulder. These widths allow a vehicle to stop, or a maintenance vehicle to operate

    with only partial obstruction of traffic lanes.

    A lane width of 2.5 m is needed to allow a passenger vehicle to stop clear of the

    traffic lane. A width of 3.0 m allows a passenger vehicle to stop clear of the traffic

    lanes and provides an additional clearance to passing traffic. It also allows a

    commercial vehicle to stop clear of the traffic lanes.

  • 8/18/2019 Design Report Print

    27/227

      19

    1.4. CROSS SECTION ELEMENTS

    1.4.1. GENERAL

    The cross section of a road consists of the following items. (Refer Figure 1.4.1)

    I.  Carriageway.

    II.  Shoulder.

    III.  Median.

    IV.  Platforms.

    V. 

    Cross fall.

    VI.  Drains.

    VII.  Batters.

    VIII.  Parking Strips.

    IX.  Right Of Way.

  • 8/18/2019 Design Report Print

    28/227

      20

    Figure 1.4.1 – Typical cross section of a road

  • 8/18/2019 Design Report Print

    29/227

      21

    1.4.2. CARRIGEWAY

    The carriageway is the surface on which the vehicles are expected to run.

    Carriageways are classified as single-lane, two-lane or multi-lane. A traffic lane is

    defined as the width used for single line of traffic operation. The desirable lane width

    is taken as 3.7m. The absolute minimum lane width shall be 3.1m. For multi-lane

    roads carriageway is divided into two parts by introducing a median. Then vehicles

    are moving in opposite direction at each part. Such carriageway is called a duel-

    carrigeway.

    The width of the carriageway selected for Palugama-Boralanda-Haputale Road is 6.4

    m (3.2m x 2). 

    1.4.3. SHOULDER

    Shoulder is the portion traveled adjoining to the outer edge of the carriageway that

    accommodates stopped vehicles, emergency use and lateral support of sub base, base

    and surface course. In the absence of foot walk, shoulders could be used for

    pedestrians also. It may be of compacted earth or gravel. In some cases shoulders may

    be totally or partly sealed. The desirable width of shoulder is 3.0m and minimum

    shoulder width may be 2.4m and absolute minimum width may be 1.8m.

    The shoulder width selected for this particular road is 1.2 m. 

    1.4.4. MEDIAN

    Median is the land of dividing the carriageway in order to avoid the collision of

    opposing vehicles. Normally center median accommodate for 4-lane or multi-lane

    roads. To clearly identify the centre median from the carriageway, median may be

    raised, flush or provide small humps at regular intervals. The main advantages of

    providing the centre median are to separate opposing traffics, provide refugee area for

  • 8/18/2019 Design Report Print

    30/227

      22

    crossing pedestrians, provide a stopping area in case of emergency situation, allow

    space for U-turning vehicles, provide open green space and minimize opposing head

    light glare at night.

     No centre median is provided for Palugama-Boralanda-Haputale road since it was

    designed as two way two lane road.

    1.4.5. PLATFORM

    Carriageway and shoulder on either side when taking together is called as the

    platform.

     A platform width of 10.6 m is selected for Palugama-Boralanda-Haputale road.

    1.4.6. CROSSFALL

    1.4.6.1. GENERAL

    The carriageway crossfall is the slope of the carriageway measured at right angles to

    the horizontal alignment and shoulder crossfall could be similarly defined. The main

    purpose of introducing crossfall is to ensure sufficient drain the road surface.

    Generally shoulder crossfall is steeper than the carriageway crossfall and should be

    varied with the surface material.

    1.4.6.2. PAVEMENT CROSSFALL

    The carriageway is cambered to form an inverted “U” which is rounded at its highest

    point known as crown. The recommended crossfall values for various surface

    materials are tabulated in Table 1.4.1.

  • 8/18/2019 Design Report Print

    31/227

      23

    Table 1.4.1 - Recommended Cross-falls on Straight for Different Surface Types

    Type of surface on carriageway Recommended Crossfall

    Portland Cement Concrete

    Asphalt Concrete

    Surface Seals

    Unsealed Gravel

    2.0%

    2.5%

    3.0%

    4.0%

    Since Asphalt Pavement surface is applied for Palugama-Boralanda-Haputale road,

    2.5 % slope is selected as normal cross-fall.

    1.4.6.3. SHOULDER CROSSFALL

    The shoulder cross-fall is generally steeper than the carriageway cross-fall and the

    cross-falls should be varied with the surface material.

    The recommended crossfall values for the shoulder are tabulated Table 1.4.2.

    Table 1.4.2 - Recommended Shoulder Cross-falls on Straight

    For Palugama-Boralanda-Haputale road, 4.0 % slope is selected as the soft shoulder

    cross-fall.

    1.4.7. DRAINS

    Drains are provided for collecting and conveying of water from the road surface. The

    selected cross section of drain should have the sufficient capacity to dispose the rain

    water collected from the road platform.

    Type of Shoulder Recommended Crossfall

    Bitumen or other all weather surface

    Gravel

    3-4%

    4-5%

  • 8/18/2019 Design Report Print

    32/227

      24

    1.4.7.1. SIDE DRAINS

    These are located on outside of shoulder in either side. The surface water should be

    drained away as quickly as possible before seepaging water from top of pavement

    layers to subgrade. To overcome this issue side drain of adequate section shall be

    provided. The cross section may be either trapezoidal if that is earth drain or

    rectangular if that is concrete drain.

    For   Palugama-Boralanda-Haputale road 0.9m wide side drains are provided on

    either side of the road where necessary. 

    1.4.7.2. INTERCEPTER DRAINS

    Intercepter drains are also known as catch or cut-off drains. These are located at the

    top of cut slopes behind the rounded batter. Their purpose is to interrupt the seepage

    water within the upper soil layer and flow of surface water and prevent the scour of

    the cut slope face. Intercepter drains are occupied as open channels.

     No intercepter drains are provided for this particular section on Palugama-

     Boralanda-Haputale road since embankment cut height is always less than 6m.

    1.4.7.3. SUB-SOIL DRAINS

    Sub-soil drains deals with drainage of underground water. The main purpose of

    providing sub-soil drains are:• Intercept groundwater.

    • To drain the subgrade and pavement during and after construction.

    • Drain wet areas below the surface or outside the carriageway.

    • Stabilize or lower the water table.

     As the finished level of Palugama-Boralanda-Haputale road lies considerably above

    the water table, the necessity of providing of sub-soil drains is not arisen.

  • 8/18/2019 Design Report Print

    33/227

      25

    1.4.7.4. CROSS SHOULDER DRAINS

    Cross shoulder drains (mitre or boxing drains) are designed to drain the pavement

    through the shoulder, usually via a coarse permeable filter media. This type of drains

    is generally occupied to places where water is collected during the construction stage.

    Therefore it is not included in the design.

    Cross Shoulder Drains were not provided in the design of Palugama-Boralanda-

     Haputale road.

    1.4.8. BATTERS

    1.4.8.1. CUT BATTER

    Cut batter slope will depend on the depth of cut and soil properties. For general

    conditions a cut slope of 4:1 could be adopted. It is preferable to limit the depth of cut

    to 6m when adopting 4:1 cut slope. For special condition of soil properties and site

    conditions it is better to investigate the batter stability.

     A cut slope of 4:1 is adopted, in the design of Palugama-Boralanda-Haputale road

    where necessary. 

    1.4.8.2. FILL BATTER

    Fill batter slope will depend on the soil properties. For general conditions a fill slope

    of 1:1.5 could usually be adopted.

     A fill slope of 1:1.5 is adopted for the design of Palugama-Boralanda-Haputale road

    where required.

  • 8/18/2019 Design Report Print

    34/227

      26

    1.4.8.3. SLOPE BENCHES

    When material in a cut slope is sufficiently unstable to warrant flatter than average

    slopes, then providing of benches may be more suitable in the case of deep cuts. The

    necessity of benches in unstable material, their width and vertical spacing should be

    determined only after an adequate materials investigation. When cuts exceed 12m

    consideration shall be given to benching of batters to facilitate maintenance and

    possibly improve aesthetics. Benches should be sloped to form a valley along the

    centre so that rain water can be drained off toward the ends of bench and discharged

    onto natural ground where possible. Minimum width of bench should be 3m with a

    maximum crossfall of 0.10m/m. The slope should be suitably protected by grassing.

     In the design of Palugama-Boralanda-Haputale road, slope benches were not

     provided as no deep cuttings were involved. 

    1.4.8.4. SIGHT BENCHES

    When benches are provided mainly for purpose of improving the sight distances, they

    are called as sight benches.

     In the design of Palugama-Boralanda-Haputale road, the minimum sight distance

    was provided without adopting sight benches.

    1.4.8.5. FILL SLOPE TREATMENT

    The run-off from the pavement surface and the shoulders ultimately flows over the

    slopes of the embankment. The extent of erosion of fill slope from surface run-off

    depends on various factors such as soil type, slope of the embankment, and rainfall

    intensity. The measure adopted overcome the erosion is called fill slope treatment.

    Various types of treatments are available such as

    a. Turfing

    b. Pitching with rip-rap

  • 8/18/2019 Design Report Print

    35/227

      27

    c. Raised curbs, gutters and flumes

    d. Geotextiles

    e. Bituminious treatment

    Turfing is used as fill slope treatment in designing of Palugama-Boralanda-Haputale

    road.

    1.4.9. PARKING STRIPS

    1.4.9.1. GENERAL

    Every vehicle owner wishes to park the vehicle as close as possible to his destination

    so as to minimize his walking. Also spaces are required to vehicles to load or unload

    goods. This results a great demand for parking spaces in the urban area where bare

    land around the road is limited.

    1.4.9.2. WIDTH OF PARKING STRIPS

    The most commonly used angle parking arrangement provides for 450 parking on a

    strip 4.9 m wide, measured at right angle to the kerb. For parallel parking

    arrangement, a 2.4 m strip is the minimum acceptable width and this is the usual

    width marked on the pavement.

    1.4.9.3. PARKING BAYS

    In urban areas, parking bays should be provided for commercial vehicles to load and

    unload merchandise and customer’s vehicles. Location of parking bay is important as

    it influence the success in attracting motorists.

     In the design of this particular section of Palugama-Boralanda-Haputale road,

     parking bays were not provided, as the trace was located in un-urbanized area.

  • 8/18/2019 Design Report Print

    36/227

      28

    1.4.9.4. CROSS FALL OF PARKING STRIPS AND BAYS

    Generally 3% -4% cross fall is adopted for parking strips in both angle and parallel

    parking.

    1.4.10. RIGHT OF WAY

    Right of Way is the clear width required to accommodate all the facilities of the road.

     In the design of Palugama-Boralanda-Haputale road, 12 m wide right of way is

     provided.

    1.5. SIGHT DISTANCE

    1.5.1. GENERAL

    Sight distance in road design is the distance at which a driver of a vehicle can see an

    object of specified height on the road ahead of him assuming satisfactory conditions

    prevail to ensure visibility. A driver ability to see ahead is of the most importance in

    the safe and efficient operation of a vehicle on a road. For safety on road the designer

    should provide sight distance of sufficient length that drivers can control the vehicles

    to avoid striking an unexpected object on traveled way.

    1.5.2. CONSTANTS USED IN DESIGN FOR SIGHT DISTANCE

    In calculating various sight distances, following values of reaction time and heights of

    objects have been adopted.

    a)  Total reaction time

    This is the time between the instant the hazard comes into view and the

    instant the vehicle begins to slow after breaks have been applied. (Taken

    as 2.5sec.)

  • 8/18/2019 Design Report Print

    37/227

      29

    b)  Driver eye height

    Passenger car = 1.05m

    Commercial Vehicle = 1.80m

    c)  Object cut off height above road surface

    Approaching vehicle = 1.15m

    Stationary Object = 0.20m

    Vehicle tail height/Stop light = 0.60m

    Height of head light = 0.75m

    Upward divergence angle = 1.00deg

    Vertical clearance = 5.20m

    1.5.3. STOPPING SIGHT DISTANCE (SSD)

    Stopping sight distance is the minimum distance required by an average driver of a

    vehicle traveling at a given speed to react and stop before reaching an object in its

    path. Stopping sight distance is measured from the driver’s eyes, which are assumed

    to be 1.05m above the pavement, to an object 0.20m high on the road.

    Stopping sight distance has two compartments; the distance traveled during total

    reaction time and the distance traveled during breaking time.

    ………….. (1.5.1)

    SSD =Stopping Sight Distance (m)

    t  R =Total Reaction Time (sec)

    V =Speed of vehicle (km/h)

     µ =Coefficient of Longitudinal Friction between vehicle tyres and road

    pavement assumed constant throughout the breaking period.

     µ 2546.3

    2V V t 

    SSD  R += 

  • 8/18/2019 Design Report Print

    38/227

      30

    The value of Coefficient of Longitudinal Friction ( µ) varies with speed, tyre pressure,

    tyre condition, type of pavement and whether the surface is dry or wet. The

    Coefficient of Longitudinal Friction ( µ) values assumed are tabulated in Table 1.5.1.

    Table 1.5.1 – Longitudinal Friction Factors

    Design Speed (kmph) Friction Factor ( µ) 

    30

    40

    50

    60

    70

    80

    90

    100

    0.40

    0.38

    0.35

    0.33

    0.31

    0.30

    0.30

    0.29

    Specimen Calculation for Palugama-Boralanda-Haputale road,

    V = 40 km/h

     f = 0.38 (Refer Table 1.5.1)

    t  R = 2.5s

    From Equation 1.5.1,

    SSD = 2.5 x 40/3.6 + 402 / (254 x 0.38)

    = 44.35 m

     By rounding, SSD = 45 m

    1.5.4. EFFECT OF GRADE IN BREAKING

    The distance a vehicle travels while being breaked to a halt is longer on downhill

    grades and shorter uphill. Therefore above breaking distance formula adjusted to take

    into account the effect of grade is;

  • 8/18/2019 Design Report Print

    39/227

      31

     

    ………….. (1.5.1)

    G = Longitudinal grade as a percentage (+ uphill, - downhill)

    The calculated stopping sight distances for each speed are given in Table 1.5.2.

    1.5.5. OVERTAKING SIGHT DISTANCE (OSD)

    The distance needs to see ahead to safely overtake the front vehicle moving at

    constant speed is called the Overtaking Sight Distance (OSD). Vehicles in two-lane,

    two-way highways need to overtake slower moving vehicles. If passing is to be

    accomplished safely, the passing driver should be able to see a sufficient distance

    ahead, clear of traffic, to complete the passing manoeuvre without cutting off the

    passed vehicle before meeting an opposing vehicle that appears during the

    manoeuvre. The actual safe overtaking sight distance depends on many variables, but

    the following simplifying assumptions could be made.

    •  The overtaken vehicle travels uniformly at one step lower than the

    design speed.

    •  The overtaking vehicle trails the overtaken vehicle as it enters the

    overtaking section.

    •  Overtaking manoeuvre is accomplished by accelerating in the early part

    of the manoeuvre up to reaching design speed and completing the

    manoeuvre at the same speed.

    •  Only one vehicle at a time is overtaken.

    With these assumptions, calculated sight distances required for overtaking at various

    speeds are also tabulated in Table 1.5.2.

    ( )GV V t 

    SSD  R

    01.02546.3

    2

    ±+=

     µ   

  • 8/18/2019 Design Report Print

    40/227

      32

     As the road is located in mountainous terrain and due to land acquisition problems

    overtaking sight distance was not strictly followed.

    1.5.6. CONTINUATION SIGHT DISTANCE (CSD)

    Continuation sight distance is equal to twice the stopping sight distance needed for

    two drivers traveling at design speed approaching each other head on to stop before

    colliding. It provides reasonable opportunity to overtake assuming that a driver has a

    choice to either proceed or withdraw when he is nearly opposite the overtaken

    vehicle.

    If continuation sight distance could be provided, it will automatically fulfill the

    stopping sight distance values for speeds greater than the specified design speed.

    The design Continuation sight distance values are tabulated in Table 1.5.2

    Table 1.5.2 - Design Values for Stopping, Overtaking & Intermediate Sight Distances

    on Bituminous and Concrete Pavements

    Design speed(kmph)Stopping Sight

    Distance(SSD) - m

    Continuation Sight

    Distance(CSD) - m

    Overtaking Sight

    Distance(OSD) -

    m

    30

    40

    50

    60

    70

    80

    100

    30.0

    45.0

    65.0

    85.0

    115.0

    140.0

    205.0

    60.0

    90.0

    130.0

    170.0

    230.0

    280.0

    410.0

    160

    220

    280

    350

    430

    520

    690

    Height of Eye (m)

    Height of Object (m)

    1.05

    0.20

    1.05

    1.15

    1.05

    1.15

  • 8/18/2019 Design Report Print

    41/227

      33

    1.5.7. SIGHT DISTANCE AT GRADE CRESTS

    Stopping, Overtaking and Intermediate Sight Distances required can be achieved by

    designing appropriate vertical curve radius and curve lengths for different speeds.This will be discussed in the Section 1.8.

    1.5.8. HEAD LIGHT SIGHT DISTANCE

    This illuminated distance is important traveling at night, because the sight distance at

    night is governed by the distance illuminated by the head light beam. This effect is

    discussed in Section 1.8.

    1.6. HORIZONTAL ALIGNMENT

    1.6.1. INTRODUCTION

    The important consideration in determining the horizontal alignment of a road is the

    provision of safe and continuation operation for substantial lengths of roadway. The

    horizontal alignment of a road is usually a series of straights and circular curves

    connected by transition curves.

    When introducing horizontal curves, following aspects such as the minimum radii,

    transition lengths, pavement widening and superelevation required has to pay special

    attention.

    1.6.2. MOVEMENT ON A CIRCULAR PATH

    When a vehicle moves in a circular path it undergoes a centripetal force that act

    toward the centre of curvature. In road design it is assumed that the above force is

    balanced by the side friction developed between tyre & pavement and by the

    superelevation.

  • 8/18/2019 Design Report Print

    42/227

      34

    From the first principals the following equation could be derived for normal values of

    superelevation;

     RV  f e

    127

    2=+

      ………….. (1.6.1)

    Where;

    e = Superelevation.

    f = Coefficient of side friction between vehicle tyres & road pavement.

    V = Design speed (kmph).

    R = Curve radius (m).

    Superelevation is a percentage that the pavement to be superelevated. The

    superelevation to be adopted is chosen primarily for safety, other factors being

    comfort and appearance.

    By rearranging the above formula, a minimum curve radius can be determined using

    the maximum values for superelevation (emax) and maximum side friction factors

    (f max) for a given design speed(V).

    ( )maxmax

    2

    min127  f e

    V  R

    +=

      ………… (1.6.2)

    Therefore maximum values for superelevation and side friction factors have to be

    determined. The maximum superelevation used on highways is controlled by many

    factors. Those are climate condition, terrain type, type of area and frequency of slow

    moving vehicles whose operation might be affected by high superelevation rates.

    Consideration of these factors jointly leads to the conclusion that no single maximum

    superelevation rate is universally applicable that a range of value should be used.

    Therefore the range of values suit Sri Lanka for Maximum superelevation (emax) was

    tabulated in Table 1.6.1.

  • 8/18/2019 Design Report Print

    43/227

      35

    Table 1.6.1 – Maximum Superelevaion Values

    Terrain typeemax 

    Open Build-up

    Flat

    Rolling

    Mountainous

    6%

    8%

    10%

    6%

    6%

    6%

    Also it is necessary to specify a minimum value for superelevation due to a minimum

    crossfall is defined for drainage considerations. Therefore it is recommended to take

    minimum superelevation equal to normal crossfall although for larger radii, a small

    superelevation is sufficient for stability.

    1.6.3. SIDE FRICTION FACTOR

    The side friction factor represents the vehicle’s need of side friction. The upper limit

    of the side friction factor is the point at which the tyre would begin to skid. This is

    known as the point of impending skid. Because the highway curves are designed to

    avoid skidding condition with a margin of safety, side friction factor value used in

    design should be substantially less than the coefficient of friction at impending skid.

    By considering safety and comfort the maximum values of side friction factor adopted

    for the design of horizontal curves for paved and unpaved roads are tabulated in Table

    1.6.2.

  • 8/18/2019 Design Report Print

    44/227

      36

    Table 1.6.2 - Maximum Design Values of Co-efficient of Side Friction

    Design speed(kmph)Maximum design values of coefficient of side friction

    Bituminous Roads Gravel Roads

    30

    40

    50

    60

    70

    80

    90

    100

    0.210

    0.190

    0.170

    0.160

    0.150

    0.140

    0.130

    0.128

    0.140

    0.130

    0.120

    0.110

    0.100

    0.090

    -

    -

    1.6.4. HORIZONTAL CURVATURE

    1.6.4.1 GENERAL

    Horizontal curvature is a shape to provide for places where change in direction occurs

    of the designed centre line. Depending on the changes of the direction, one of the

    following curve types could be introduced at the design stage.

    I.  Simple circular curve.

    II.  Transition curve.

    III.  Compound curve (Unidirectional curve).

    IV. 

    Reverse curve.

    1.6.4.2. GENERAL CONSIDERATIONS IN DESIGNING HORIZONTAL

    ALIGNMENT

    The following general controls for horizontal alignment should be kept in view in a

    sound design practice.

  • 8/18/2019 Design Report Print

    45/227

      37

    I.  Alignment should be as directional as possible but should be consistent with the

    topography and with preserving developed properties.

    II.  The number of short curves should be kept to a minimum.

    III.  For a given design speed, use of minimum radius for that speed should be

    avoided wherever possible.

    IV.  Sharp curves should not be introduced at the ends of long tangents.

    V.  Sudden changes from areas of flat curvature to areas of sharp curvature should

    be avoided.

    VI.  At places where sharp curvature must be introduced it should be approached by

    successively sharper curves from the generally flat curvature.

    VII.  The minimum length of horizontal curve on main highways should be about

    three times the design speed.

    VIII.  On high long fills, tangents or flat curves should be used as far as possible.

    IX.  Compound curves with large difference in curvature should be avoided. The

    radius of the flatter circular curve should not be more than 50% greater than the

    radius of the sharper circular curve.

    X.  Introducing short tangents between two curves in the same direction should be

    avoided except where topography or right-of-way restrictions make their use

    necessary.

    1.6.4.3. SIMPLE CIRCULAR CURVE

    These are plain circular curves and simplest to use. In designing the curves followings

    will be governed.

    I.  Minimum radius of curve.

    II.  Minimum length of curve.

    By substituting values of maximum superelevation (emax) and maximum side friction

    factors (f max) minimum curve radius could be calculated for a given design speed.

    These values are shown in the Table 1.6.3.

  • 8/18/2019 Design Report Print

    46/227

      38

    Table 1.6.3 – Minimum Radii for Different Superelevation

    Design

    Speed(kmph)

    Superelevation

    2.5% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0%

    30 35 30 30 30 30 30 25 25 25

    40 60 60 55 55 55 50 50 45 45

    50 105 100 95 90 90 85 80 80 75

    60 155 150 145 135 130 125 120 115 110

    70 225 215 205 195 185 180 170 165 155

    80 310 300 280 270 255 240 230 220 210

    90 415 400 380 355 340 320 305 290 280

    100 515 500 470 445 420 400 380 365 350

    In this design the radius selected for two curves and their corresponding

    superelevation values are as in the Table 1.6.4

    Table 1.6.4 – Radii selected, with corresponding Superelevation

    Chainage Radius of the

    Curve (m)Superelevation

    3+272.04 – 3+327.28 70 2.5%

    3+737.00 – 3+791.99 160 2.5%

    To accommodate the super-elevation development length (Ls) at two edges of the

    curve, curve length should be sufficient enough. The length of 32 Ls is required to

    accommodate superelevation development at two edges and full superelevation is

    accommodated over length equal to Ls.

    Thus minimum total length of the curve should be equal to 35 Ls.

    Curve lengths are provided to fulfill above requirement in Palugama-Boralanda-

     Haputale road.

  • 8/18/2019 Design Report Print

    47/227

      39

    1.6.4.4. TRANSITION CURVE

    Transition curves are introduced between tangents and circular curves, between two

    tangents, between two similar curves or between two reverse curves. Clothoid(spiral

    curve) is used as the transition curve.

    The advantages of adopting the transition curve in horizontal alignment are the

    following.

    I.  To provide a natural, easy-to-follow path for drivers, such that the lateral

    force increases and decreases gradually as a vehicle enters and leaves a

    circular curve.

    II.  To provide a length over which the super elevation development can be

    applied.

    III.  To provide flexibility in accomplishing the widening of sharp curves.

    IV.  To improve the appearance of the road by avoiding sharp discontinuities in

    alignment at the circular curves.

    Transition curves are used when the design speed is higher than 70km/h. Since

    maximum design speed used in Sri Lanka is less or equal to 70 km/h use of transition

    curve has been limited.

     In designing Palugama-Boralanda-Haputale road, transition curve is not been used.

    1.6.4.5. COMPOUND CURVE

    This type comprises of successive curves of different radii in the same direction, with

    common or closely spaced tangent points. The radius of the larger curve should not be

    higher than 50% of the radius of the smaller curve. Generally compound curve should

    be avoided and a single curve shall be adopted if topography and ground control is not

    making an obstacle.

     In designing of Palugama-Boralanda-Haputale road, compound curves are used. 

  • 8/18/2019 Design Report Print

    48/227

      40

    1.6.4.6. REVERSE CURVE

    These curves consists with successive curve having common or closely spaced

    tangent points but in opposite direction. Reverse curve having common tangent point

    make difficulty in achieving change of superelevation rates. Therefore short tangent

    could be introduced between two curves to overcome the above problem.

     In designing of Palugama-Boralanda-Haputale road, reverse curves are used. 

    1.6.4.7. SIMILAR CURVES

    This consists of two curves in the same direction formed by a short tangent. Attempt

    should be made to avoid this type of alignment by adopting a Simple Curve or a

    Compound Curve. When Similar Curves are unavoidable, tangent lengths in the range

    of 0.6 V to 3 V should be avoided. (Where V is the Design Speed in km/h for the

    particular trace)

     In designing of Palugama-Boralanda-Haputale road, similar curves were not used. 

    1.6.4.8. WIDENING OF CARRIGEWAY ON CURVES

    Carriageways are widened on some curves because a vehicle passing through on a

    curve occupies a greater width than it goes on a straight and to avoid difficulty in

    steering their vehicles in the centre of the lane. The amount of widening required

    depends on;

    I.  Radius of the curve.

    II.  Vehicle length and width.

    III.  Width of lane on straight.

    IV.  Lateral clearance between two vehicles.

  • 8/18/2019 Design Report Print

    49/227

      41

     

    In general practice minimum amount of widening is limited to 0.6m. The amount of

    widening for a SU vehicle and for two lane highway is given in the table 1.6.5.

    Table 1.6.5 – Design values for pavement widening on open highway curves

    Radius of

    curve (m)

    6.2 meters

    Design speed (km/h)

    30 40 50 60 70

    300 0.5 0.6 0.6 0.7 0.7

    250 0.5 0.6 0.7 0.7 0.8

    200 0.6 0.7 0.8 0.8 0.9

    150 0.8 0.9 1.0 1.1 1.1

    140 0.8 0.9 1.0 1.1 -

    130 0.9 0.9 1.0 1.1 -

    120 0.9 1.0 1.1 1.2 -

    110 0.9 1.0 1.1 1.2 -

    100 1.0 1.1 1.2 - -

    90 1.1 1.2 1.3 - -

    80 1.1 1.2 1.3 - -

    70 1.2 1.3 - - -

    60 1.3 1.5 - - -

    50 1.6 1.7 - - -

    40 1.8 - - - -

    30 2.0 - - - -

  • 8/18/2019 Design Report Print

    50/227

      42

    1.7. SUPERELEVATION

    1.7.1. GENERAL

    When vehicle travels along a curve it experiences a force called centrifugal force.

    Centrifugal force increases when the velocity of the vehicle increases and the radius

    of the curvature decreases. To balance the effects of the centrifugal force curves

    should be superelevated. The amount of superelevation will depend on the radius of

    the curve, design speed and pavement surface characteristics.

    1.7.2. STANDARDS FOR SUPERELEVATION

    The superelevation to be adopted is selected for safety, comfort and appearance. Use

    of maximum superelevation should be confined to mountainous terrain or places

    where there are physical obstructions which confine the radius of the particular curve

    with respect to the adjacent curves.

    The maximum superelevation varies from 10% in m