design report print
TRANSCRIPT
-
8/18/2019 Design Report Print
1/227
i
TABLE OF CONTENTS
1.0 - GEOMETRIC DESIGN OF ROADS ................................................................... 1
1.1 INTRODUCTION ............................................................................................... 2
1.1.1 GENERAL .................................................................................................... 2
1.1.2. PROJECT DESCRIPTION .......................................................................... 3
1.2. DESIGN CONTROL & CRITERIA .................................................................. 5
1.2.1. TOPOGRAPHY ........................................................................................... 5
1.2.2. TRAFFIC ..................................................................................................... 6
1.2.2.1. ROAD USER ........................................................................................ 6
1.2.2.2. TRAFFIC DATA .................................................................................. 6
1.2.2.3. THE VEHICLE ..................................................................................... 7
1.2.3. SPEED ......................................................................................................... 8
1.2.4. SAFETY ...................................................................................................... 91.2.5. ECONOMIC CONSIDERATIONS .......................................................... 10
1.3. WIDTH OF TRAFFIC LANES & SHOULDERS ........................................... 11
1.3.1. GENERAL ................................................................................................. 11
1.3.2. FACTORS AFFECTING THE LANE WIDTH ........................................ 11
1.3.2.1. VEHICULAR TRAFFIC .................................................................... 12
1.3.2.2. GENERAL LANE WIDTHS .............................................................. 12
1.3.2.3. DERIVATIONS OF NUMBER OF LANES ..................................... 12
1.3.3. SHOULDER WIDTHS .............................................................................. 18
1.3.3.1. FACTORS AFFECTING SHOULDER WIDTH ............................... 18
1.3.3.2. GENERAL SHOULDER WIDTH ..................................................... 18
1.4. CROSS SECTION ELEMENTS ...................................................................... 191.4.1. GENERAL ................................................................................................. 19
1.4.2. CARRIGEWAY ........................................................................................ 21
1.4.3. SHOULDER .............................................................................................. 21
1.4.4. MEDIAN.................................................................................................... 21
1.4.5. PLATFORM .............................................................................................. 22
1.4.6. CROSSFALL ............................................................................................. 22
1.4.6.1. GENERAL .......................................................................................... 22
1.4.6.2. PAVEMENT CROSSFALL ............................................................... 22
1.4.6.3. SHOULDER CROSSFALL................................................................ 23
1.4.7. DRAINS ..................................................................................................... 23
1.4.7.1. SIDE DRAINS .................................................................................... 241.4.7.2. INTERCEPTER DRAINS .................................................................. 24
1.4.7.3. SUB-SOIL DRAINS ........................................................................... 24
1.4.7.4. CROSS SHOULDER DRAINS .......................................................... 25
1.4.8. BATTERS .................................................................................................. 25
1.4.8.1. CUT BATTER .................................................................................... 25
1.4.8.2. FILL BATTER.................................................................................... 25
1.4.8.3. SLOPE BENCHES ............................................................................. 26
1.4.8.4. SIGHT BENCHES.............................................................................. 26
1.4.8.5. FILL SLOPE TREATMENT .............................................................. 26
1.4.9. PARKING STRIPS .................................................................................... 27
1.4.9.1. GENERAL .......................................................................................... 27
-
8/18/2019 Design Report Print
2/227
ii
1.4.9.2. WIDTH OF PARKING STRIPS ........................................................ 27
1.4.9.3. PARKING BAYS ............................................................................... 27
1.4.9.4. CROSS FALL OF PARKING STRIPS AND BAYS......................... 28
1.4.10. RIGHT OF WAY ..................................................................................... 28
1.5. SIGHT DISTANCE .......................................................................................... 28
1.5.1. GENERAL ................................................................................................. 281.5.2. CONSTANTS USED IN DESIGN FOR SIGHT DISTANCE ................. 28
1.5.3. STOPPING SIGHT DISTANCE (SSD) .................................................... 29
1.5.4. EFFECT OF GRADE IN BREAKING ..................................................... 30
1.5.5. OVERTAKING SIGHT DISTANCE (OSD) ............................................ 31
1.5.6. CONTINUATION SIGHT DISTANCE (CSD) ........................................ 32
1.5.7. SIGHT DISTANCE AT GRADE CRESTS .............................................. 33
1.5.8. HEAD LIGHT SIGHT DISTANCE .......................................................... 33
1.6. HORIZONTAL ALIGNMENT ........................................................................ 33
1.6.1. INTRODUCTION ..................................................................................... 33
1.6.2. MOVEMENT ON A CIRCULAR PATH ................................................. 33
1.6.3. SIDE FRICTION FACTOR ...................................................................... 351.6.4. HORIZONTAL CURVATURE ................................................................ 36
1.6.4.1 GENERAL ........................................................................................... 36
1.6.4.2. GENERAL CONSIDERATIONS IN DESIGNING HORIZONTAL
ALIGNMENT .................................................................................................. 36
1.6.4.3. SIMPLE CIRCULAR CURVE........................................................... 37
1.6.4.4. TRANSITION CURVE ...................................................................... 39
1.6.4.5. COMPOUND CURVE ....................................................................... 39
1.6.4.6. REVERSE CURVE ............................................................................ 40
1.6.4.7. SIMILAR CURVES ........................................................................... 40
1.6.4.8. WIDENING OF CARRIGEWAY ON CURVES .............................. 40
1.7. SUPERELEVATION ....................................................................................... 42
1.7.1. GENERAL ................................................................................................. 42
1.7.2. STANDARDS FOR SUPERELEVATION ............................................... 42
1.7.3. CURVES WITH ADVERSE CROSSFALL ............................................. 42
1.7.4. DEVELOPMENT OF SUPERELEVATION ............................................ 43
1.7.4.1. AXIS OF ROTATION ........................................................................ 43
1.7.4.2. SUPERELEVATION DEVELOPMENT LENGTH .......................... 44
1.7.4.2.1. RELATIVE GRADIENT METHOD .......................................... 44
1.7.4.2.2. RATE OF PAVEMENT ROTATION METHOD ....................... 45
1.7.4.3. POSITIONING OF SUPERELEVATION ......................................... 48
1.7.4.4. SUPERELEVATION DEVELOPMENT ON SHOULDERS............ 511.8. VERTICAL ALIGNMENT .............................................................................. 53
1.8.1. GENERAL ................................................................................................. 53
1.8.2. GENERAL CONSIDERATIONS OF IN DESIGNING THE VERTICAL
ALIGNMENT ...................................................................................................... 53
1.8.3. VERTICAL CURVES ............................................................................... 54
1.8.3.1. CREST VERTICAL CURVES........................................................... 55
1.8.3.1.1. GENERAL ................................................................................... 55
1.8.3.1.2. LENGTH OF CREST CURVES ................................................. 55
1.8.3.2. SAG VERTICAL CURVES ............................................................... 61
1.8.3.2.1. GENERAL ................................................................................... 61
1.8.3.2.2. LENGTH OF SAG CURVES ...................................................... 611.8.4. GRADES.................................................................................................... 64
-
8/18/2019 Design Report Print
3/227
iii
1.8.4.1. GENERAL .......................................................................................... 64
1.8.4.2. STANDARDS FOR GRADES ........................................................... 65
1.8.4.3. GRADES STEEPER THAN GENERAL MAXIMUM ..................... 67
1.8.4.4. CRITICAL LENGTH OF GRADES .................................................. 67
1.9. OTHER CONSIDERATIONS.......................................................................... 68
1.9.1. GENERAL ................................................................................................. 681.9.2. CO-ORDINATION OF HORIZONTAL AND VERTICAL ALIGNMENT
FOR SAFETY ...................................................................................................... 68
1.9.3. CO-ORDINATION OF HORIZONTAL AND VERTICAL ALIGNMENT
FOR AESTHETIC REASONS ............................................................................ 69
1.10. REFERENCES ............................................................................................... 70
2.0 - GEOMETRIC DESIGN OF INTERSECTION .................................................. 72
2.1. INTRODUCTION ............................................................................................ 73
2.1.1. GENERAL ................................................................................................. 73
2.1.2. PROJECT DESCRIPTION ........................................................................ 74
2.2. BASIC DATA FOR DESIGN .......................................................................... 75
2.2.1. TRAFFIC DATA ....................................................................................... 752.2.1.1. PEAK HOUR TRAFFIC VOLUMES INCLUDING TURNING
MOVEMENTS ................................................................................................ 75
2.2.1.2. VEHICLE CHARACTERISTICS ...................................................... 80
2.2.1.3. PEDESTRIAN TRAFFIC ................................................................... 81
2.2.1.4. ACCIDENT DATA ............................................................................ 81
2.2.1.5. PARKING DATA ............................................................................... 81
2.2.1.6. PUBLIC TRANSPORT REQUIREMENTS ...................................... 81
2.2.2. SITE TOPOGRAPHY ............................................................................... 82
2.2.3. PHYSICAL FEATURES AND ITEMS OF CULTURAL, HISTORICAL
AND RELIGIOUS SIGNIFICANCE .................................................................. 82
2.2.4. OVERHEAD AND UNDERGROUND UTILITY SERVICES ............... 82
2.2.5. RIGHT OF WAY PROBLEMS AND LIMITATIONS ............................ 83
2.3. ANALYSIS OF DATA..................................................................................... 83
2.3.1. ANALYSIS OF DATA FOR THE SELECTION OF DESIGN VEHICLE
.............................................................................................................................. 83
2.3.2. ANALYSIS OF DATA FOR SELECTION OF TYPE OF
INTERSECTION ................................................................................................. 84
2.3.2.1. TYPE OF INTERSECTION BASED ON TREATMENT ................. 84
2.3.2.2. FACTORS AFFECTING SELECTION OF TYPE OF
INTERSECTION ............................................................................................. 86
2.3.3. BEST INTERSECTION TREATMENT FOR THE PROBLEM IN HAND.............................................................................................................................. 86
2.4. ROUNDABOUTS ............................................................................................ 87
2.4.1. TYPES OF ROUNDABOUTS AND SELECTION OF THE TYPE FOR
THE DESIGN ...................................................................................................... 87
2.4.1.1. MINI ROUNDABOUTS .................................................................... 87
2.4.1.2. SMALL ROUNDABOUTS ................................................................ 87
2.4.1.3. LARGE ROUNDABOUTS ................................................................ 87
2.4.1.4. DOUBLE ROUNDABOUTS ............................................................. 88
2.4.1.5. CONVENTIONAL ROUNDABOUTS .............................................. 88
2.4.2. ELEMENTS OF A ROUNDABOUT ........................................................ 88
2.4.2.1. CENTRAL ISLAND .......................................................................... 882.4.2.2. CENTRE ISLAND DIAMETER ........................................................ 89
-
8/18/2019 Design Report Print
4/227
iv
2.4.2.3. INSCRIBED CIRCLE DIAMETER................................................... 90
2.4.2.4. CIRCULATING CARRIAGEWAY .................................................. 90
2.4.2.5. CRCULATING CARRIAGEWAY WIDTH ..................................... 90
2.4.2.6 GIVE WAY LINE ............................................................................... 90
2.4.2.7. ENTRY CURVE ................................................................................. 91
2.4.2.8. EXIT CURVE ..................................................................................... 912.4.2.9. APPROACH WIDTH ......................................................................... 91
2.4.2.10. ENTRY / EXIT WIDTH ................................................................... 91
2.4.2.11. DEPARTURE WIDTH ..................................................................... 92
2.4.2.12. CORNER KERB RADIUS (KERB RETURN) ............................... 92
2.4.2.13. SPLITTER ISLAND ......................................................................... 92
2.4.3. GEOMETRIC DESIGN STANDARDS ................................................... 93
2.5. CAPACITY ANALYSIS AND DELAY CALCULATIONS .......................... 93
2.5.1. METHODS OF CAPACITY ANALYSIS ................................................ 93
2.5.1.1. GAP ACCEPTANCE THEORY ........................................................ 93
2.5.1.2. ANALYSIS PACKAGE ..................................................................... 94
2.5.2. THE METHOD SELECTED FOR THE CAPACITY ANALYSIS ......... 942.6. PRELIMINARY DESIGN AND SELECTION OF A LAYOUT .................. 123
2.7. GEOMETRIC DESIGN CALCULATIONS .................................................. 130
2.7.1. CIRCULATING TRAFFIC SPEED ........................................................ 130
2.7.2. THROUGH TRAFFIC SPEED ............................................................... 130
2.7.3. CIRCULATING CARRIGEWAY WIDTH ............................................ 132
2.7.4. ENTRY AND EXIT CURVES ................................................................ 134
2.7.5. SIGHT DISTANCE ................................................................................. 135
2.7.6. VERTICAL CURVES ............................................................................. 135
2.7.7. SPLITTER ISLAND ................................................................................ 135
2.8. REFERENCES ............................................................................................... 137
3.0 - DESIGN OF SURFACE WATER DRAINAGE SYSTEM FOR
INTERSECTION ....................................................................................................... 139
3.1. INTRODUCTION .......................................................................................... 140
3.1.1. GENERAL ............................................................................................... 140
3.1.2. PROJECT DESCRIPTION ...................................................................... 140
3.2. STORM WATER RUNOFF ESTIMATION ................................................. 141
3.2.1. INTENSITY OF RAINFALL .................................................................. 141
3.2.2. SELECTION OF DESIGN STORM RECURRENCE INTERVAL ....... 143
3.2.3. TIME OF CONCENTRATION ............................................................... 143
3.2.4. PEAK RUN-OFF ..................................................................................... 144
3.2.4.1. DIFFERENT METHODS FOR ESTIMATING OF PEAK RUN-OFF........................................................................................................................ 145
3.2.4.2. RATIONAL METHOD .................................................................... 146
3.2.4.2.1. RATIONAL FORMULA........................................................... 146
3.2.4.2.2. ADVANTAGES AND DISADVANTAGES OF THE
RATIONAL FORMULA........................................................................... 147
3.2.4.2.3. COEFFICIENT OF RUN-OFF .................................................. 147
3.2.4.3. APPLICATION IN THE PROJECT ................................................ 148
3.2.5. DEPTH OF FLOW AND LENGTH OF FLOW PATH .......................... 150
3.2.5.1. DEPTH OF FLOW ........................................................................... 150
3.2.5.2. LENGTH OF FLOW PATH ............................................................. 150
3.3. FLOW IN HIGHWAY GUTTERS ................................................................ 1503.3.1. INTRODUCTION ................................................................................... 150
-
8/18/2019 Design Report Print
5/227
v
3.3.2. FORMULA FOR FLOW IN TRIANGULAR GUTTER ........................ 151
3.3.3. PONDED WIDTH ................................................................................... 153
3.3.4. CALCULATIONS FOR FLOW IN GUTTERS...................................... 153
3.4. INLETS ........................................................................................................... 154
3.4.1. INTRODUCTION ................................................................................... 154
3.4.2. TYPES OF INLETS ................................................................................ 1543.4.2.1. GRATED INLETS............................................................................ 154
3.4.2.2. KERB OPENING INLETS............................................................... 155
3.4.2.3. COMBINATION OF GRATED AND KERB OPENING INLETS 156
3.4.3. SELECTION OF TYPE OF INLET FOR THE DESIGN ....................... 156
3.4.4. CAPACITY OF INLETS ......................................................................... 156
3.4.4.1. GENERAL ........................................................................................ 156
3.4.4.1.1. CAPACITY OF KERB OPENING INLET ON A
CONTINUOUS GRADE ........................................................................... 156
3.4.4.1.2. CAPACITY OF KERB OPENING INLET ON SAG ............... 157
3.4.4.2. SPECIMEN CALCULATIONS ....................................................... 157
3.4.5. GENERAL RULES FOR SPACING OF INLETS ................................. 1573.4.6. INLET COMPUTATIONS ...................................................................... 158
3.4.6.1. DESCRIPTION OF TABLE FOR INLET COMPUTATIONS AND
SPECIMEN CALCULATIONS .................................................................... 158
3.5. FLOW IN RECTANGULAR DRAINS ......................................................... 163
3.5.1. INTRODUCTION ................................................................................... 163
3.5.2. DESIGN CRITERIA ............................................................................... 163
3.5.3. CAPACITY OF RECTANGULAR DRAINS ......................................... 164
3.5.3.1. GENERAL ........................................................................................ 164
3.5.3.2. CALCULATIONS AND PREPARATION OF GRAPHS FOR
DESIGN ......................................................................................................... 164
3.5.4. STORM DRAIN COMPUTATIONS ...................................................... 165
3.6. REFERENCES ............................................................................................... 170
4.0 – BILL OF QUANTITIES ................................................................................... 172
4.1. SUMMARY OF THE BILL OF QUANTITIES ............................................ 173
4.2. BILL OF QUANTITIES ................................................................................. 175
4.3. TAKING OFF SHEETS ................................................................................. 180
4.4. RATE ANALYSIS FOR B.O.Q. ITEMS ....................................................... 208
LIST OF TABLES
Table 1.2.1 – Classification of Terrain .......................................................................... 5
Table 1.2.2 – Traffic data for Palugama-Boralanda-Haputale road ............................... 7
Table 1.2.3 – Relationship of the Design Speed related with the Road Classification,
Terrain and the Design Volume. .................................................................................... 9
Table 1.3.1 – Minimum width of sealed pavements of undivided roads ..................... 13
Table 1.3.2 – Design Level of Service ......................................................................... 14
Table 1.3.3 – Adjustment factors for directional distribution (f d) .............................. 16
Table 1.3.4 - Adjustment factors for the combined effect of narrow lanes and
restricted shoulder width (f w) ...................................................................................... 16
Table 1.3.5 - Average Passenger Car Equivalent for Trucks and Buses on Two Lane
Highways over Different Terrain Segments ................................................................ 16Table 1.4.1 - Recommended Cross-falls on Straight for Different Surface Types ...... 23
-
8/18/2019 Design Report Print
6/227
vi
Table 1.4.2 - Recommended Shoulder Cross-falls on Straight .................................... 23
Table 1.5.1 – Longitudinal Friction Factors ................................................................ 30
Table 1.5.2 - Design Values for Stopping, Overtaking & Intermediate Sight Distances
on Bituminous and Concrete Pavements ..................................................................... 32
Table 1.6.1 – Maximum Superelevaion Values ........................................................... 35
Table 1.6.2 - Maximum Design Values of Co-efficient of Side Friction .................... 36Table 1.6.3 – Minimum Radii for Different Superelevation ....................................... 38
Table 1.6.4 – Radii selected, with corresponding Superelevation ............................... 38
Table 1.6.5 – Design values for pavement widening on open highway curves ........... 41
Table 1.7.1 - Minimum Radii with Adverse Cross Fall ............................................... 43
Table 1.7.2 – Maximum Relative Gradients ................................................................ 45
Table 1.7.3 - superelevation values and corresponding length of superelevation
development for various radii and design speed .......................................................... 47
Table 1.8.1 - Minimum Crest Vertical Curve Length Based on Sight Distance Criteria
...................................................................................................................................... 56
Table 1.8.2 – Minimum Vertical Curve Length Based on Appearance Criterion ....... 58
Table 1.8.3 – Minimum Vertical Curve Length Based on Comfort Criterion ............. 60Table 1.8.4 - Minimum Sag Vertical Curve Length Based on Head Light Sight
Distance Criterion ........................................................................................................ 62
Table 1.8.5 – Maximum Gradients .............................................................................. 66
Table 1.8.6 – Critical length of Grades ........................................................................ 68
Table 2.2.1 (a) - Summary of Peak Hour Turning Moments in Morning Peak (0915 –
1015 Hrs) at Gabada Junction (in Veh / h) .................................................................. 77
Table 2.2.1 (b) - Summary of Peak Hour Turning Moments in Mid day Peak (1100 –
1200 Hrs) at Gabada Junction (in Veh / h) .................................................................. 78
Table 2.2.1 (c) - Summary of Peak Hour Turning Moments in Evening Peak (1700 –
1800 Hrs) at Gabada Junction (in Veh / h) .................................................................. 79
Table 2.2.2 - Equivalent Passenger Car Units ............................................................. 80
Table 2.3.1 - Composition of Vehicles at Hambantota Intersection during Peak Hours
of the Day ..................................................................................................................... 84
Table 2.5.1(a) - Summary of Peak Hour Turning Moments in Morning Peak (0915 –
1015 Hrs) at Gabada Junction (in PCU / h) ................................................................. 96
Table 2.5.1(b) - Summary of Peak Hour Turning Moments in Mid day Peak (1100 –
1200 Hrs) at Gabada Junction (in PCU / h) ................................................................. 97
Table 2.5.1(c) - Summary of Peak Hour Turning Moments in Evening Peak (1700 –
1800 Hrs) at Gabada Junction (in PCU / h) ................................................................. 98
Table 2.5.3 – No. of entry lanes and approach lanes in Hambantota intersection ..... 103
Table 2.5.4 – Widths of entry lanes and approach lanes in Hambantota intersection103Table 2.5.5 - Dominant- Stream Follow-up Headways (tfd) (Initials Values) in seconds
.................................................................................................................................... 105
Table 2.5.6 - Adjustment Times for the Dominant Stream Follow-up Headway ...... 106
Table 2.5.7 - Sub-dominant Steam Follow-up headway tfs ....................................... 106
Table 2.5.8 - Ratio of the Critical Acceptance Gap to the Follow-up Headway(tad / tfd )
.................................................................................................................................... 107
Table 2.5.9 - Average headway between bunched vehicles in the circulating traffic (τ)and the number of effective lanes in the circulating carriageway. ............................ 108
Table 2.5.10 - Proportions of Bunched Vehicles, θ ................................................... 109Table 2.5.11 (a) - Geometric Delay for Stopped Vehicles (Seconds per Vehicles) .. 116
Table 2.5.11 (b) - Geometric Delay for Vehicles, Which Do Not Stop (Seconds perVehicles) .................................................................................................................... 117
-
8/18/2019 Design Report Print
7/227
vii
Table 2.5.12 - Geometric Delay Values for Gonnoruwa Leg of Hambantota
Roundabout ................................................................................................................ 118
Table 2.5.13 - Geometric Delay and Total Average Delay Values for Movements of
Gonnoruwa Leg of Hambantota Roundabout. ........................................................... 119
Table 2.5.14 - Data Required for Capacity Calculations ........................................... 120
Table 2.5.15 - Capacity Calculations & Queuing Delay Calculations ...................... 121Table 2.5.16 (a) - Geometric Delay Calculations & Total Delay Calculations –
Morning Peak ............................................................................................................. 122
Table 2.5.16 (b) - Geometric Delay Calculations & Total Delay Calculations – Mid-
Day Peak .................................................................................................................... 122
Table 2.5.16 (c) - Geometric Delay Calculations & Total Delay Calculations –
Evening Peak ............................................................................................................. 123
Table 2.7.1 - Entry and Exit Curve Radius of Hambantota Roundabout .................. 134
Table 2.7.2 - The splitter island areas for Habmantota Roundabout ......................... 136
Table 3.4.1 – Inlet Computations ............................................................................... 160
Table 3.5.1 - Q/S½
values for varying depth ............................................................. 165
Table 3.5.2 – Storm Drain Computations .................................................................. 169
LIST OF FIGURES
Figure 1.1.1 – Location Map of Palugama-Boralanda-Haputale road. .......................... 4
Figure 1.4.1 – Typical cross section of a road ............................................................. 20
Figure 1.7.2 - Edge profile for a Circular curve .......................................................... 49
Figure 1.7.3 - Edge profile for Reverse curve ............................................................. 50
Figure 1.7.4 - Edge profile for Compound curve......................................................... 51
Figure 1.7.5 – Development of superelevation in sealed shoulder .............................. 52Figure 1.7.6 – Development of superelevation in unsealed shoulder .......................... 52
Figure 1.8.1 – Basic Elements of a typical vertical curve ........................................... 54
Figure 1.8.2 – Crest vertical curves ............................................................................. 55
Figure 1.8.3 – Sag vertical curves ................................................................................ 61
Figure 2.2.1 – Traffic Data at the intersection from 7.00 to 19.00 hrs ........................ 76
Figure 2.4.1 – Geometric Elements of a Roundabout .................................................. 89
Figure 2.5.1(a) – Traffic turning volumes in Morning Peak hour (9.15-10.15) .......... 99
Figure 2.5.1(b) – Traffic turning volumes in Mid day Peak hour (11.00-12.00) ....... 100
Figure 2.5.1(c) – Traffic turning volumes in Evening Peak hour (17.00-18.00) ....... 101
Figure 2.5.2 – Required No. of Circulating and Entry lanes ................................... 102
Figure 2.5.3 –Proportion of vehicles stopped on a multi lane entry roundabout ....... 115
Figure 2.5.4 – Definitions of the terms used in Table 2.5.11(a) and 2.5.11(b) .......... 118
Figure 2.5.5 – Alternative 1 ....................................................................................... 125
Figure 2.5.6 – Alternative 2 ....................................................................................... 126
Figure 2.5.7 – Alternative 3 ....................................................................................... 127
Figure 2.5.8 – Alternative 4 ....................................................................................... 128
Figure 2.5.9 – Alternative 5 ....................................................................................... 129
Figure 2.7.1 – Derivation of turning roadway width on curves at intersection ......... 132
Figure 3.2.1 – Rainfall Intensity – Duration Curves .................................................. 142
Figure 3.2.2 – Coefficient of Run-off ........................................................................ 149
Figure 3.3.1 – Flow in Triangular Gutter ................................................................... 151
-
8/18/2019 Design Report Print
8/227
viii
-
8/18/2019 Design Report Print
9/227
1
1.0 - GEOMETRIC DESIGN OF ROADS
REPORT
ON
GEOMETRIC DESIGN
OF
PALUGAMA-BORALANDA-HAPUTALE ROAD
(B 353) FROM 0+000 TO 27+200(SECTION FROM 2+800 TO 5+450)
-
8/18/2019 Design Report Print
10/227
2
1.1 INTRODUCTION
1.1.1 GENERAL
Geometric design is an important aspect of Highway Design dealing with the visible
dimensions of a roadway. To produce a well balanced design, all geometric elements
such as
Horizontal alignment
Vertical alignment
Sight distances
Cross-section components
Lateral and vertical clearance
Intersection treatment
Control of access
should economically feasible as far as possible, while providing safe continuous
operation at a speed likely under the general conditions for the highway. Mainly this
is achieved through the use of design speed as the overall control. In the design of
highway curves, it is necessary to establish the proper relation between design speed
and curvature and their joint relations with super elevation and side friction.
A well designed highway has to be consistent with the economy. There are some
other factors influence the geometric design are the availability of funds and the
adjacent land use. If design is carried out improperly it may result in early
obsolescence of the new highway with considerable economic losses.
-
8/18/2019 Design Report Print
11/227
3
1.1.2. PROJECT DESCRIPTION
Palugama-Boralanda-Haputale road, which is approximately 27 km in length “B
353” route, connects the two major suburb towns, Keppetipola and Haputale in Uva
Province. The road stretch bears an Annual Daily Traffic of 1399 vehicles. Currently
it functions as two lane two way road with an average carriageway width of 5.0 m
and it runs on a rolling terrain of average gradient being 8%.
Carriageway is not divided into lanes and no built up drains are provided. Bends are
not met with geometric standards. The travelers those who are going visit the
Adisham Bungalow which is a historic place popular among the locals and foreignershave to go along the this particular road. If the mobility had been improved in this
road it will be helpful for the tourism industry. These factors had been inspired to
improve this road.
The other factors lead to improve the above road is the poor vertical alignment,
narrow carriageway width, poor sight distance and humpy road surface.
This report describes the general principles of the geometric design and its
application to the detailed design of Palugama-Boralanda-Haputale road from
chainage 2+800 to 5+450.
-
8/18/2019 Design Report Print
12/227
4
Figure 1.1.1 – Location Map of Palugama-Boralanda-Haputale road.
-
8/18/2019 Design Report Print
13/227
5
1.2. DESIGN CONTROL & CRITERIA
The design criteria determines roadway geometric. The principal factors influencing
the choice of design standard for a particular road section are as follows.I. Topography.
II. Traffic.
III. Speed.
IV. Safety.
V. Economic consideration
VI. Financial level.
1.2.1. TOPOGRAPHY
Terrain type is one of the main factors which govern the vehicular speed. Terrain also
has a significant effect on the costs of achieving high geometric standards. Therefore
terrain can be considered as one of the main element used in selecting the design
criteria. In geometric design, roads are divided into sections with uniform terrain
characteristics, i.e. Flat, Rolling, Mountainous. Table 1.2.1 gives the classification ofterrain based on its representative slope.
Table 1.2.1 – Classification of Terrain
Terrain Type Code Corridor Slope %
Flat
Rolling
Mountainous
F
R
M
10
10-25
>25
The topography of the section from 2+800 to 3+500 and from 4+750 to 5+450 of
Palugama-Boralanda-Haputale road can be considered as flat. The remaining section
is a Rolling terrain.
-
8/18/2019 Design Report Print
14/227
6
1.2.2. TRAFFIC
Traffic composes of the following groups.
1.
The road user2. Traffic data
3. The vehicle
1.2.2.1. ROAD USER
As the road user (Drivers and Pedestrians) is the main part of the road system. Human
behavior and limitations should be considered in all road designs.
1.2.2.2. TRAFFIC DATA
The geometric design of roads is mainly based on the traffic data. Traffic data is
classified as follows.
I. Volume of Traffic.
A road should be designed so that it will accommodate, or can be readily
changed to accommodate, the number of vehicles which is estimated will be
using at the end of its service life with a desired level of service. The traffic
volume is usually the Annual Average Daily Traffic (AADT) and number of
traffic lanes required is a function of traffic volume. The number of vehicles
using a road in a given time determines the number of traffic lanes required.
II.
Composition of Traffic.
Road traffic is a mixture of passenger cars and commercial vehicles. Compared
to passenger cars, commercial vehicles are slow in speed occupy a greater length
and width of road, and on ascending grades, their speeds fall to lower figures
quicker. Therefore such vehicles on a road reduce its capacity and a road
capable of carrying a set number of passenger cars will carry fewer mixed
vehicles. The composition of traffic is a factor in the determination of width of
traffic lanes and to some extent, the maximum grade on a road.
-
8/18/2019 Design Report Print
15/227
7
Traffic data given by the Traffic & Planning Division of Road Development Authority
in Palugama-Boralanda-Haputale road is tabulated in Table 1.2.2.
Table 1.2.2 – Traffic data for Palugama-Boralanda-Haputale road
Vehicle Composition ADT = 1399
Percentage %
Motor Cycle
Three wheel
CarVan
Medium Bus
Large Bus
Light Goods Vehicles
Medium Goods Vehicles
Large Lorries
Farm Vehicles
28.99
31.39
8.155.66
0.69
7.89
5.49
6.17
2.49
3.09
1.2.2.3. THE VEHICLE
The vehicle data which affect the design are axle load, axle spacing, wheel base,
overall length, width, height and minimum turning radius.
The design vehicle is a motor vehicle whose weight dimensions and operating
characteristics are used to establish design controls. For this purpose vehicles are
classified into following groups.
I. P design vehicle - Passenger Car class
II. SU design vehicle - Single unit trucks and buses
III. WB-40 design vehicle - Semi-trailor intermediate
IV.
WB-50 design vehicle - Semi-trailor combination
-
8/18/2019 Design Report Print
16/227
8
1.2.3. SPEED
Speed maintained by a driver for a given road section depends upon following
conditions.
I. Type of terrain.
II. Weather.
III. Volume of traffic.
IV. Speed limitations.
In a road section having uniform topographical character all curves should be of a
uniform speed value. At the places where there is a change of topography and if it is
necessary to change the speed from one section to another it is desirable to change the
speed in steps of 10km/h contributing to safe driving condition.
Design speed applies to individual geometric elements and is the speed that is used to
co-ordinate sight distance, curve radius, super elevation and friction demand for
elements of the road so that the driver negotiating each element at its design speeds.
The design speed for this particular road is 40km/h. But the topographic constrains
limit the design speed to 30km/h in some sections.
Table 1.2.3 gives the design speed values corresponding to the road class, terrain type
and design volume.
-
8/18/2019 Design Report Print
17/227
9
Table 1.2.3 – Relationship of the Design Speed related with the Road Classification,
Terrain and the Design Volume.
Type of
RoadRoad Class Terrain
Design
Volume
PCU/day
Design Speed
Km/h
Rural Urban
R0 A F72,000-
108,00080 70
R1 AF
40,000-72,00080 70
R 70 60
R2 A,B
F
25,000-40,000
80 70
R 70 70
M 60 60
R3 A,B
F
18,000-25,000
70 60
R 60 60
M 50 50
R4 C,D
F
300-18,000
60 50
R 50 50
M 40 40
R5 D,E
F
-
8/18/2019 Design Report Print
18/227
10
traffic control devices. To provide safety of pedestrians, sufficient width of sidewalks,
proper signing and pedestrian crossing to be accommodated.
The existing trace is having poor geometric features such as inadequate sight
distances at the bends and inadequate carriageway and shoulder width. As these sub
standard will tend to promotes accidents, in designing new trace adequate amounts
were provided for above.
1.2.5. ECONOMIC CONSIDERATIONS
Before taking the final decision on the horizontal alignment on a particular road, it isnecessary to compare the economic aspect of various alternative of horizontal design.
Above mentioned economic aspect should be made on,
The cost required for,
I. Construction.
II. Acquisition.
III. Vehicle operation.
A properly designed highway afford benefit to the community as it improve
transportation facilities, reduction of travel time, reducing accidents, dropping of
vehicle maintenance cost and enhancing vehicle lifetime.
In the design of Palugama-Boralanda-Haputale Road, attempts were made to
establish more favorable geometric features by following the existing centre line of
the road. Cost components of the project, when providing the improved facilities will
be the cost of land acquisition, cost of construction and cost of maintenance. Due
consideration was paid in establishing limitations for geometric elements such as
maximum grade, minimum curve radius, sight distance requirement etc. to keep the
total cost to minimum. Efforts were taken to reduce the number of buildings affected
due to the improvements.
-
8/18/2019 Design Report Print
19/227
11
1.3. WIDTH OF TRAFFIC LANES & SHOULDERS
1.3.1. GENERAL
Width of traffic lane influence the safety, comfort of driving and Level Of Service of
that particular road. With the increase of lane width vehicles could be driven freely in
a broaden width. Hence it provides safety and comfort of driving. The width of
carriageway is determined in terms of the number of traffic lanes and width of a
traffic lane. Number of lanes to be provided depends on the present and future
anticipated traffic volume. Shoulder is the portion traveled adjoining to the outer edge
of the traffic lane. Wider shoulder will be provided emergency stops for the vehicles.
1.3.2. FACTORS AFFECTING THE LANE WIDTH
When calculating the lane widths following factors are take into account.
I. Traffic –
The volume and composition of traffic are the major factors which
determine the width of traffic lanes. Average Annual Daily Traffic
(AADT) of the particular road and peak hour traffic volume are required.
II. Vehicle Dimension –
Commercial vehicles in traffic stream also influence the lane width.
Normal steering deviations as well as the tracking errors and pavement
imperfections reduce the clearance between passing vehicles.
III. Speed environment –
Drivers have less control over the lateral position of a vehicle at high
speed. Therefore at higher Design Speeds, high width of traffic lane is
required.
-
8/18/2019 Design Report Print
20/227
12
IV. Combination of speed and traffic volume –
When both the speed and traffic volume are high, narrow lane width
should be avoided.
1.3.2.1. VEHICULAR TRAFFIC
The importance of vehicular traffic in the event of determination of traffic lane width
was explained under Section 3.2.
1.3.2.2. GENERAL LANE WIDTHS
The width of carriageway is determined in terms of the number of traffic lanes and
width of a traffic lane. A traffic lane is defined as the width used for single line of
traffic operation. The desirable lane width is taken as 3.7m. The absolute minimum
lane width shall be 3.1m.
1.3.2.3. DERIVATIONS OF NUMBER OF LANES
a) By tables in NASSRA
Table 1.3.1 gives the recommended minimum width of sealed carriageway of
undivided roads.
-
8/18/2019 Design Report Print
21/227
13
Table 1.3.1 – Minimum width of sealed pavements of undivided roads
Design
Speed
Km/h
Minimum carriageway width(m) for design traffic
volumes(AADT)
1-140 141-300 301-1100 1101-2200 Over 2200
40 3.7 5.6 6.2 - -
50 3.7 5.6 6.2 6.8 7.4
60 3.7 6.2 6.8 6.8 7.4
70 3.7 6.2 6.8 6.8 7.4
80 3.7 6.2 6.8 7.4 7.4
90 3.7 6.2 6.8 7.4 7.4
100 3.7 6.8 6.8 7.4 7.4
110 3.7 6.8 7.4 7.4 7.4
120 3.7 6.8 7.4 7.4 7.4
As per Table 1.3.1 minimum carriageway width required, corresponding to design
speed of 30-50km/h and traffic volume (AADT) of 1399 is 6.8m. However taking in to
account the acquisition problems and construction cost a 6.4m wide carriageway is
provided.
b) Capacity analysis – level of service concept
The concept of Level Of Service (LOS) is the different operational qualities of the
traffic flow. Level Of Service is a qualitative measure of speed and travel time,
freedom to maneuvers, traffic interruption, driving comfort, convenience, safety and
operating cost.
Six Level Of Service are categorized from A to F and it cover entire range of traffic
condition which may occur.
Level Of Service A – Free flow with high speed and low volumes. Drivers can hold
their desired speeds without delays.
-
8/18/2019 Design Report Print
22/227
14
Level Of Service B – Reasonably free flow. Stable flow and drivers have reasonable
freedom to select their speed.
Level Of Service C – Stable flow. Most drivers are restricted in their freedom to select
their own speed, change lanes, overtake etc... But operating speeds are still
reasonable.
Level Of Service D – Approaches unstable flow with nearly all drivers restricted.
Comfort and convenience are low but may be tolerated for short periods. Fluctuations
in conditions cause substantial drops in speed. As this service volume corresponds to
what is referred as tolerable capacity, this level of service should be used to determine
the upper limit of traffic demand which should be tolerated.
Level Of Service E – Unstable flow and there may be momentary stoppages. This
LOS is obtained with traffic volumes with near or at capacity.
Level Of Service F – Forced or breakdown flow operating at low speed caused by the
demand exceeding capacity. There is stop-start operation with large queues and
delays. In the extreme both speed and volume can drop to zero.
New roads are normally designed for LOS C or even D. The design level of service
may be as in the Table 1.3.2.
Table 1.3.2 – Design Level of Service
Road ClassDesign
speed(km/h)
Design Level Of
Service
Volume/Capacity
ratio
A
B
C,D,E
70 or more
60 or more
50 or more
C
D
E
0.6-0.8
0.8-0.9
>0.9
-
8/18/2019 Design Report Print
23/227
15
The capacity is the maximum hourly rate at which vehicles can reasonably be
expected to traverse a point or uniform section of a lane at LOS E.
The service flow rate is the maximum hourly rate of a lane or roadway under
prevailing roadway, traffic and control conditions while maintaining a designated
level of service. To calculate the service flow rate, equation 1.3.1 and 1.3.2 is applied.
HV wd i
i f f f cvSF ****2800= ……. (1.3.1)
( ) ( )[ ]1111 −+−+= B BT T HV E P E P f ……. (1.3.2)
Where:
SFi = Total service flow rate in both directions for prevailing roadway and
Traffic conditions, for level of service i, in vph
(v/c)i = Ratio of flow rate to ideal capacity for level of service i, obtained from
Table 1.3.2
f d = Adjustment factor for directional distribution of traffic, obtained from
Table 1.3.3. In the absence of directional distribution factor, it is better to use
60/40 as the directional distribution factor
f w = Adjustment factor for narrow lanes and restricted shoulder width, obtained
from Table 1.3.4
f HV = Adjustment factor for the presence of heavy vehicles in the traffic stream
PT = Proportion of trucks in the traffic stream, expressed as a decimal
PB = Proportion of buses in the traffic stream, expressed as a decimal
ET, EB = Passenger car equivalent for trucks and buses obtained from Table 1.3.5
-
8/18/2019 Design Report Print
24/227
16
Table 1.3.3 – Adjustment factors for directional distribution (f d)
Table 1.3.4 - Adjustment factors for the combined effect of narrow lanes and
restricted shoulder width (f w)
Usable
Shoulder
Width
(m)
3.7 m Lanes 3.4 m Lanes 3.0 m Lanes 2.7 m Lanes
LOS
A - D
LOS
E
LOS
A - D
LOS
E
LOS
A - D
LOS
E
LOS
A - D
LOS
E
>=1.8 1.00 1.00 0.93 0.94 0.84 0.87 0.70 0.76
1.2 0.92 0.97 0.85 0.92 0.77 0.85 0.65 0.74
0.6 0.81 0.93 0.75 0.88 0.68 0.81 0.57 0.70
0 0.70 0.88 0.65 0.82 0.58 0.75 0.49 0.66
Table 1.3.5 - Average Passenger Car Equivalent for Trucks and Buses on Two Lane
Highways over Different Terrain Segments
Vehicle Type Level Of Service Type of Terrain
Level Rolling Mountainous
Trucks, ET
A 2.0 4.0 7.0
B and C 2.2 5.0 10.0
D and E 2.0 5.0 12.0
Buses, EB
A 1.8 3.0 5.7
B and C 2.0 3.4 6.0
D and E 1.6 2.9 6.5
Directional Distribution 100/0 90/10 80/20 70/30 60/40 50/50
Adjustment Factor, f d0.71 0.75 0.83 0.89 0.94 1.00
-
8/18/2019 Design Report Print
25/227
17
Specimen Calculation for Palugama-Boralanda-Haputale road;
Average Daily Traffic = 1399(In 2009)
Present peak Hour Traffic = 10% of ADT
= 140
f d =0.94(From Table 1.3.3- assuming 60/40
distribution)
f w = 0.77 (from Table 1.3.4)
(v/c) I =0.8 (from Table 1.3.2)
PT =17.24% (5.49%+6.17%+2.49%+3.09%)
P B =8.58% (0.69%+7.89%)
E T =5.0
E B =2.9
From Equation 1.3.2,
F HV = 1 /{ 1+[17.24 x (5.0 –1)/100 + 8.58 x (2.9 –1)/100]} = 0.54
From Equation 1.3.1
SF i = 2800 x 0.8 x 0.94 x 0.77 x 0.54 = 875
Traffic growth rate is 5% and assuming the road will reach to its capacity after n
years.
875 = 140 x (1.05)n
n =37.5
The road will maintain the LOS D for 37 years from 2009.
-
8/18/2019 Design Report Print
26/227
18
1.3.3. SHOULDER WIDTHS
1.3.3.1. FACTORS AFFECTING SHOULDER WIDTH
The width of shoulder should be chosen in relationship to the traffic and topography
after due consideration of the following
a) Provision of space for -
• Maneuvering to escape potential accidents.
• Emergency and rest stops.
• Emergency operations
•
Guide posts or guard fence
b) Reduction of driving strain by the provision of extra width.
c) Separation of drains from pavement with resultant decrease in seepage effects.
d) Structural support for the pavements.
e) Appearance and traffic capacity of the road.
1.3.3.2. GENERAL SHOULDER WIDTH
The minimum shoulder width for two-way rural roads unless the volumes are below
150 vpd should be 1.0 m. Shoulders less than 1.0 m width result in vehicles on the
adjacent lane travelling closer to the road centre line. A width of 1.5 m to 2.0 m
ensures capacity of the adjacent lane is unaffected by obstructions outside the
shoulder. These widths allow a vehicle to stop, or a maintenance vehicle to operate
with only partial obstruction of traffic lanes.
A lane width of 2.5 m is needed to allow a passenger vehicle to stop clear of the
traffic lane. A width of 3.0 m allows a passenger vehicle to stop clear of the traffic
lanes and provides an additional clearance to passing traffic. It also allows a
commercial vehicle to stop clear of the traffic lanes.
-
8/18/2019 Design Report Print
27/227
19
1.4. CROSS SECTION ELEMENTS
1.4.1. GENERAL
The cross section of a road consists of the following items. (Refer Figure 1.4.1)
I. Carriageway.
II. Shoulder.
III. Median.
IV. Platforms.
V.
Cross fall.
VI. Drains.
VII. Batters.
VIII. Parking Strips.
IX. Right Of Way.
-
8/18/2019 Design Report Print
28/227
20
Figure 1.4.1 – Typical cross section of a road
-
8/18/2019 Design Report Print
29/227
21
1.4.2. CARRIGEWAY
The carriageway is the surface on which the vehicles are expected to run.
Carriageways are classified as single-lane, two-lane or multi-lane. A traffic lane is
defined as the width used for single line of traffic operation. The desirable lane width
is taken as 3.7m. The absolute minimum lane width shall be 3.1m. For multi-lane
roads carriageway is divided into two parts by introducing a median. Then vehicles
are moving in opposite direction at each part. Such carriageway is called a duel-
carrigeway.
The width of the carriageway selected for Palugama-Boralanda-Haputale Road is 6.4
m (3.2m x 2).
1.4.3. SHOULDER
Shoulder is the portion traveled adjoining to the outer edge of the carriageway that
accommodates stopped vehicles, emergency use and lateral support of sub base, base
and surface course. In the absence of foot walk, shoulders could be used for
pedestrians also. It may be of compacted earth or gravel. In some cases shoulders may
be totally or partly sealed. The desirable width of shoulder is 3.0m and minimum
shoulder width may be 2.4m and absolute minimum width may be 1.8m.
The shoulder width selected for this particular road is 1.2 m.
1.4.4. MEDIAN
Median is the land of dividing the carriageway in order to avoid the collision of
opposing vehicles. Normally center median accommodate for 4-lane or multi-lane
roads. To clearly identify the centre median from the carriageway, median may be
raised, flush or provide small humps at regular intervals. The main advantages of
providing the centre median are to separate opposing traffics, provide refugee area for
-
8/18/2019 Design Report Print
30/227
22
crossing pedestrians, provide a stopping area in case of emergency situation, allow
space for U-turning vehicles, provide open green space and minimize opposing head
light glare at night.
No centre median is provided for Palugama-Boralanda-Haputale road since it was
designed as two way two lane road.
1.4.5. PLATFORM
Carriageway and shoulder on either side when taking together is called as the
platform.
A platform width of 10.6 m is selected for Palugama-Boralanda-Haputale road.
1.4.6. CROSSFALL
1.4.6.1. GENERAL
The carriageway crossfall is the slope of the carriageway measured at right angles to
the horizontal alignment and shoulder crossfall could be similarly defined. The main
purpose of introducing crossfall is to ensure sufficient drain the road surface.
Generally shoulder crossfall is steeper than the carriageway crossfall and should be
varied with the surface material.
1.4.6.2. PAVEMENT CROSSFALL
The carriageway is cambered to form an inverted “U” which is rounded at its highest
point known as crown. The recommended crossfall values for various surface
materials are tabulated in Table 1.4.1.
-
8/18/2019 Design Report Print
31/227
23
Table 1.4.1 - Recommended Cross-falls on Straight for Different Surface Types
Type of surface on carriageway Recommended Crossfall
Portland Cement Concrete
Asphalt Concrete
Surface Seals
Unsealed Gravel
2.0%
2.5%
3.0%
4.0%
Since Asphalt Pavement surface is applied for Palugama-Boralanda-Haputale road,
2.5 % slope is selected as normal cross-fall.
1.4.6.3. SHOULDER CROSSFALL
The shoulder cross-fall is generally steeper than the carriageway cross-fall and the
cross-falls should be varied with the surface material.
The recommended crossfall values for the shoulder are tabulated Table 1.4.2.
Table 1.4.2 - Recommended Shoulder Cross-falls on Straight
For Palugama-Boralanda-Haputale road, 4.0 % slope is selected as the soft shoulder
cross-fall.
1.4.7. DRAINS
Drains are provided for collecting and conveying of water from the road surface. The
selected cross section of drain should have the sufficient capacity to dispose the rain
water collected from the road platform.
Type of Shoulder Recommended Crossfall
Bitumen or other all weather surface
Gravel
3-4%
4-5%
-
8/18/2019 Design Report Print
32/227
24
1.4.7.1. SIDE DRAINS
These are located on outside of shoulder in either side. The surface water should be
drained away as quickly as possible before seepaging water from top of pavement
layers to subgrade. To overcome this issue side drain of adequate section shall be
provided. The cross section may be either trapezoidal if that is earth drain or
rectangular if that is concrete drain.
For Palugama-Boralanda-Haputale road 0.9m wide side drains are provided on
either side of the road where necessary.
1.4.7.2. INTERCEPTER DRAINS
Intercepter drains are also known as catch or cut-off drains. These are located at the
top of cut slopes behind the rounded batter. Their purpose is to interrupt the seepage
water within the upper soil layer and flow of surface water and prevent the scour of
the cut slope face. Intercepter drains are occupied as open channels.
No intercepter drains are provided for this particular section on Palugama-
Boralanda-Haputale road since embankment cut height is always less than 6m.
1.4.7.3. SUB-SOIL DRAINS
Sub-soil drains deals with drainage of underground water. The main purpose of
providing sub-soil drains are:• Intercept groundwater.
• To drain the subgrade and pavement during and after construction.
• Drain wet areas below the surface or outside the carriageway.
• Stabilize or lower the water table.
As the finished level of Palugama-Boralanda-Haputale road lies considerably above
the water table, the necessity of providing of sub-soil drains is not arisen.
-
8/18/2019 Design Report Print
33/227
25
1.4.7.4. CROSS SHOULDER DRAINS
Cross shoulder drains (mitre or boxing drains) are designed to drain the pavement
through the shoulder, usually via a coarse permeable filter media. This type of drains
is generally occupied to places where water is collected during the construction stage.
Therefore it is not included in the design.
Cross Shoulder Drains were not provided in the design of Palugama-Boralanda-
Haputale road.
1.4.8. BATTERS
1.4.8.1. CUT BATTER
Cut batter slope will depend on the depth of cut and soil properties. For general
conditions a cut slope of 4:1 could be adopted. It is preferable to limit the depth of cut
to 6m when adopting 4:1 cut slope. For special condition of soil properties and site
conditions it is better to investigate the batter stability.
A cut slope of 4:1 is adopted, in the design of Palugama-Boralanda-Haputale road
where necessary.
1.4.8.2. FILL BATTER
Fill batter slope will depend on the soil properties. For general conditions a fill slope
of 1:1.5 could usually be adopted.
A fill slope of 1:1.5 is adopted for the design of Palugama-Boralanda-Haputale road
where required.
-
8/18/2019 Design Report Print
34/227
26
1.4.8.3. SLOPE BENCHES
When material in a cut slope is sufficiently unstable to warrant flatter than average
slopes, then providing of benches may be more suitable in the case of deep cuts. The
necessity of benches in unstable material, their width and vertical spacing should be
determined only after an adequate materials investigation. When cuts exceed 12m
consideration shall be given to benching of batters to facilitate maintenance and
possibly improve aesthetics. Benches should be sloped to form a valley along the
centre so that rain water can be drained off toward the ends of bench and discharged
onto natural ground where possible. Minimum width of bench should be 3m with a
maximum crossfall of 0.10m/m. The slope should be suitably protected by grassing.
In the design of Palugama-Boralanda-Haputale road, slope benches were not
provided as no deep cuttings were involved.
1.4.8.4. SIGHT BENCHES
When benches are provided mainly for purpose of improving the sight distances, they
are called as sight benches.
In the design of Palugama-Boralanda-Haputale road, the minimum sight distance
was provided without adopting sight benches.
1.4.8.5. FILL SLOPE TREATMENT
The run-off from the pavement surface and the shoulders ultimately flows over the
slopes of the embankment. The extent of erosion of fill slope from surface run-off
depends on various factors such as soil type, slope of the embankment, and rainfall
intensity. The measure adopted overcome the erosion is called fill slope treatment.
Various types of treatments are available such as
a. Turfing
b. Pitching with rip-rap
-
8/18/2019 Design Report Print
35/227
27
c. Raised curbs, gutters and flumes
d. Geotextiles
e. Bituminious treatment
Turfing is used as fill slope treatment in designing of Palugama-Boralanda-Haputale
road.
1.4.9. PARKING STRIPS
1.4.9.1. GENERAL
Every vehicle owner wishes to park the vehicle as close as possible to his destination
so as to minimize his walking. Also spaces are required to vehicles to load or unload
goods. This results a great demand for parking spaces in the urban area where bare
land around the road is limited.
1.4.9.2. WIDTH OF PARKING STRIPS
The most commonly used angle parking arrangement provides for 450 parking on a
strip 4.9 m wide, measured at right angle to the kerb. For parallel parking
arrangement, a 2.4 m strip is the minimum acceptable width and this is the usual
width marked on the pavement.
1.4.9.3. PARKING BAYS
In urban areas, parking bays should be provided for commercial vehicles to load and
unload merchandise and customer’s vehicles. Location of parking bay is important as
it influence the success in attracting motorists.
In the design of this particular section of Palugama-Boralanda-Haputale road,
parking bays were not provided, as the trace was located in un-urbanized area.
-
8/18/2019 Design Report Print
36/227
28
1.4.9.4. CROSS FALL OF PARKING STRIPS AND BAYS
Generally 3% -4% cross fall is adopted for parking strips in both angle and parallel
parking.
1.4.10. RIGHT OF WAY
Right of Way is the clear width required to accommodate all the facilities of the road.
In the design of Palugama-Boralanda-Haputale road, 12 m wide right of way is
provided.
1.5. SIGHT DISTANCE
1.5.1. GENERAL
Sight distance in road design is the distance at which a driver of a vehicle can see an
object of specified height on the road ahead of him assuming satisfactory conditions
prevail to ensure visibility. A driver ability to see ahead is of the most importance in
the safe and efficient operation of a vehicle on a road. For safety on road the designer
should provide sight distance of sufficient length that drivers can control the vehicles
to avoid striking an unexpected object on traveled way.
1.5.2. CONSTANTS USED IN DESIGN FOR SIGHT DISTANCE
In calculating various sight distances, following values of reaction time and heights of
objects have been adopted.
a) Total reaction time
This is the time between the instant the hazard comes into view and the
instant the vehicle begins to slow after breaks have been applied. (Taken
as 2.5sec.)
-
8/18/2019 Design Report Print
37/227
29
b) Driver eye height
Passenger car = 1.05m
Commercial Vehicle = 1.80m
c) Object cut off height above road surface
Approaching vehicle = 1.15m
Stationary Object = 0.20m
Vehicle tail height/Stop light = 0.60m
Height of head light = 0.75m
Upward divergence angle = 1.00deg
Vertical clearance = 5.20m
1.5.3. STOPPING SIGHT DISTANCE (SSD)
Stopping sight distance is the minimum distance required by an average driver of a
vehicle traveling at a given speed to react and stop before reaching an object in its
path. Stopping sight distance is measured from the driver’s eyes, which are assumed
to be 1.05m above the pavement, to an object 0.20m high on the road.
Stopping sight distance has two compartments; the distance traveled during total
reaction time and the distance traveled during breaking time.
………….. (1.5.1)
SSD =Stopping Sight Distance (m)
t R =Total Reaction Time (sec)
V =Speed of vehicle (km/h)
µ =Coefficient of Longitudinal Friction between vehicle tyres and road
pavement assumed constant throughout the breaking period.
µ 2546.3
2V V t
SSD R +=
-
8/18/2019 Design Report Print
38/227
30
The value of Coefficient of Longitudinal Friction ( µ) varies with speed, tyre pressure,
tyre condition, type of pavement and whether the surface is dry or wet. The
Coefficient of Longitudinal Friction ( µ) values assumed are tabulated in Table 1.5.1.
Table 1.5.1 – Longitudinal Friction Factors
Design Speed (kmph) Friction Factor ( µ)
30
40
50
60
70
80
90
100
0.40
0.38
0.35
0.33
0.31
0.30
0.30
0.29
Specimen Calculation for Palugama-Boralanda-Haputale road,
V = 40 km/h
f = 0.38 (Refer Table 1.5.1)
t R = 2.5s
From Equation 1.5.1,
SSD = 2.5 x 40/3.6 + 402 / (254 x 0.38)
= 44.35 m
By rounding, SSD = 45 m
1.5.4. EFFECT OF GRADE IN BREAKING
The distance a vehicle travels while being breaked to a halt is longer on downhill
grades and shorter uphill. Therefore above breaking distance formula adjusted to take
into account the effect of grade is;
-
8/18/2019 Design Report Print
39/227
31
………….. (1.5.1)
G = Longitudinal grade as a percentage (+ uphill, - downhill)
The calculated stopping sight distances for each speed are given in Table 1.5.2.
1.5.5. OVERTAKING SIGHT DISTANCE (OSD)
The distance needs to see ahead to safely overtake the front vehicle moving at
constant speed is called the Overtaking Sight Distance (OSD). Vehicles in two-lane,
two-way highways need to overtake slower moving vehicles. If passing is to be
accomplished safely, the passing driver should be able to see a sufficient distance
ahead, clear of traffic, to complete the passing manoeuvre without cutting off the
passed vehicle before meeting an opposing vehicle that appears during the
manoeuvre. The actual safe overtaking sight distance depends on many variables, but
the following simplifying assumptions could be made.
• The overtaken vehicle travels uniformly at one step lower than the
design speed.
• The overtaking vehicle trails the overtaken vehicle as it enters the
overtaking section.
• Overtaking manoeuvre is accomplished by accelerating in the early part
of the manoeuvre up to reaching design speed and completing the
manoeuvre at the same speed.
• Only one vehicle at a time is overtaken.
With these assumptions, calculated sight distances required for overtaking at various
speeds are also tabulated in Table 1.5.2.
( )GV V t
SSD R
01.02546.3
2
±+=
µ
-
8/18/2019 Design Report Print
40/227
32
As the road is located in mountainous terrain and due to land acquisition problems
overtaking sight distance was not strictly followed.
1.5.6. CONTINUATION SIGHT DISTANCE (CSD)
Continuation sight distance is equal to twice the stopping sight distance needed for
two drivers traveling at design speed approaching each other head on to stop before
colliding. It provides reasonable opportunity to overtake assuming that a driver has a
choice to either proceed or withdraw when he is nearly opposite the overtaken
vehicle.
If continuation sight distance could be provided, it will automatically fulfill the
stopping sight distance values for speeds greater than the specified design speed.
The design Continuation sight distance values are tabulated in Table 1.5.2
Table 1.5.2 - Design Values for Stopping, Overtaking & Intermediate Sight Distances
on Bituminous and Concrete Pavements
Design speed(kmph)Stopping Sight
Distance(SSD) - m
Continuation Sight
Distance(CSD) - m
Overtaking Sight
Distance(OSD) -
m
30
40
50
60
70
80
100
30.0
45.0
65.0
85.0
115.0
140.0
205.0
60.0
90.0
130.0
170.0
230.0
280.0
410.0
160
220
280
350
430
520
690
Height of Eye (m)
Height of Object (m)
1.05
0.20
1.05
1.15
1.05
1.15
-
8/18/2019 Design Report Print
41/227
33
1.5.7. SIGHT DISTANCE AT GRADE CRESTS
Stopping, Overtaking and Intermediate Sight Distances required can be achieved by
designing appropriate vertical curve radius and curve lengths for different speeds.This will be discussed in the Section 1.8.
1.5.8. HEAD LIGHT SIGHT DISTANCE
This illuminated distance is important traveling at night, because the sight distance at
night is governed by the distance illuminated by the head light beam. This effect is
discussed in Section 1.8.
1.6. HORIZONTAL ALIGNMENT
1.6.1. INTRODUCTION
The important consideration in determining the horizontal alignment of a road is the
provision of safe and continuation operation for substantial lengths of roadway. The
horizontal alignment of a road is usually a series of straights and circular curves
connected by transition curves.
When introducing horizontal curves, following aspects such as the minimum radii,
transition lengths, pavement widening and superelevation required has to pay special
attention.
1.6.2. MOVEMENT ON A CIRCULAR PATH
When a vehicle moves in a circular path it undergoes a centripetal force that act
toward the centre of curvature. In road design it is assumed that the above force is
balanced by the side friction developed between tyre & pavement and by the
superelevation.
-
8/18/2019 Design Report Print
42/227
34
From the first principals the following equation could be derived for normal values of
superelevation;
RV f e
127
2=+
………….. (1.6.1)
Where;
e = Superelevation.
f = Coefficient of side friction between vehicle tyres & road pavement.
V = Design speed (kmph).
R = Curve radius (m).
Superelevation is a percentage that the pavement to be superelevated. The
superelevation to be adopted is chosen primarily for safety, other factors being
comfort and appearance.
By rearranging the above formula, a minimum curve radius can be determined using
the maximum values for superelevation (emax) and maximum side friction factors
(f max) for a given design speed(V).
( )maxmax
2
min127 f e
V R
+=
………… (1.6.2)
Therefore maximum values for superelevation and side friction factors have to be
determined. The maximum superelevation used on highways is controlled by many
factors. Those are climate condition, terrain type, type of area and frequency of slow
moving vehicles whose operation might be affected by high superelevation rates.
Consideration of these factors jointly leads to the conclusion that no single maximum
superelevation rate is universally applicable that a range of value should be used.
Therefore the range of values suit Sri Lanka for Maximum superelevation (emax) was
tabulated in Table 1.6.1.
-
8/18/2019 Design Report Print
43/227
35
Table 1.6.1 – Maximum Superelevaion Values
Terrain typeemax
Open Build-up
Flat
Rolling
Mountainous
6%
8%
10%
6%
6%
6%
Also it is necessary to specify a minimum value for superelevation due to a minimum
crossfall is defined for drainage considerations. Therefore it is recommended to take
minimum superelevation equal to normal crossfall although for larger radii, a small
superelevation is sufficient for stability.
1.6.3. SIDE FRICTION FACTOR
The side friction factor represents the vehicle’s need of side friction. The upper limit
of the side friction factor is the point at which the tyre would begin to skid. This is
known as the point of impending skid. Because the highway curves are designed to
avoid skidding condition with a margin of safety, side friction factor value used in
design should be substantially less than the coefficient of friction at impending skid.
By considering safety and comfort the maximum values of side friction factor adopted
for the design of horizontal curves for paved and unpaved roads are tabulated in Table
1.6.2.
-
8/18/2019 Design Report Print
44/227
36
Table 1.6.2 - Maximum Design Values of Co-efficient of Side Friction
Design speed(kmph)Maximum design values of coefficient of side friction
Bituminous Roads Gravel Roads
30
40
50
60
70
80
90
100
0.210
0.190
0.170
0.160
0.150
0.140
0.130
0.128
0.140
0.130
0.120
0.110
0.100
0.090
-
-
1.6.4. HORIZONTAL CURVATURE
1.6.4.1 GENERAL
Horizontal curvature is a shape to provide for places where change in direction occurs
of the designed centre line. Depending on the changes of the direction, one of the
following curve types could be introduced at the design stage.
I. Simple circular curve.
II. Transition curve.
III. Compound curve (Unidirectional curve).
IV.
Reverse curve.
1.6.4.2. GENERAL CONSIDERATIONS IN DESIGNING HORIZONTAL
ALIGNMENT
The following general controls for horizontal alignment should be kept in view in a
sound design practice.
-
8/18/2019 Design Report Print
45/227
37
I. Alignment should be as directional as possible but should be consistent with the
topography and with preserving developed properties.
II. The number of short curves should be kept to a minimum.
III. For a given design speed, use of minimum radius for that speed should be
avoided wherever possible.
IV. Sharp curves should not be introduced at the ends of long tangents.
V. Sudden changes from areas of flat curvature to areas of sharp curvature should
be avoided.
VI. At places where sharp curvature must be introduced it should be approached by
successively sharper curves from the generally flat curvature.
VII. The minimum length of horizontal curve on main highways should be about
three times the design speed.
VIII. On high long fills, tangents or flat curves should be used as far as possible.
IX. Compound curves with large difference in curvature should be avoided. The
radius of the flatter circular curve should not be more than 50% greater than the
radius of the sharper circular curve.
X. Introducing short tangents between two curves in the same direction should be
avoided except where topography or right-of-way restrictions make their use
necessary.
1.6.4.3. SIMPLE CIRCULAR CURVE
These are plain circular curves and simplest to use. In designing the curves followings
will be governed.
I. Minimum radius of curve.
II. Minimum length of curve.
By substituting values of maximum superelevation (emax) and maximum side friction
factors (f max) minimum curve radius could be calculated for a given design speed.
These values are shown in the Table 1.6.3.
-
8/18/2019 Design Report Print
46/227
38
Table 1.6.3 – Minimum Radii for Different Superelevation
Design
Speed(kmph)
Superelevation
2.5% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0%
30 35 30 30 30 30 30 25 25 25
40 60 60 55 55 55 50 50 45 45
50 105 100 95 90 90 85 80 80 75
60 155 150 145 135 130 125 120 115 110
70 225 215 205 195 185 180 170 165 155
80 310 300 280 270 255 240 230 220 210
90 415 400 380 355 340 320 305 290 280
100 515 500 470 445 420 400 380 365 350
In this design the radius selected for two curves and their corresponding
superelevation values are as in the Table 1.6.4
Table 1.6.4 – Radii selected, with corresponding Superelevation
Chainage Radius of the
Curve (m)Superelevation
3+272.04 – 3+327.28 70 2.5%
3+737.00 – 3+791.99 160 2.5%
To accommodate the super-elevation development length (Ls) at two edges of the
curve, curve length should be sufficient enough. The length of 32 Ls is required to
accommodate superelevation development at two edges and full superelevation is
accommodated over length equal to Ls.
Thus minimum total length of the curve should be equal to 35 Ls.
Curve lengths are provided to fulfill above requirement in Palugama-Boralanda-
Haputale road.
-
8/18/2019 Design Report Print
47/227
39
1.6.4.4. TRANSITION CURVE
Transition curves are introduced between tangents and circular curves, between two
tangents, between two similar curves or between two reverse curves. Clothoid(spiral
curve) is used as the transition curve.
The advantages of adopting the transition curve in horizontal alignment are the
following.
I. To provide a natural, easy-to-follow path for drivers, such that the lateral
force increases and decreases gradually as a vehicle enters and leaves a
circular curve.
II. To provide a length over which the super elevation development can be
applied.
III. To provide flexibility in accomplishing the widening of sharp curves.
IV. To improve the appearance of the road by avoiding sharp discontinuities in
alignment at the circular curves.
Transition curves are used when the design speed is higher than 70km/h. Since
maximum design speed used in Sri Lanka is less or equal to 70 km/h use of transition
curve has been limited.
In designing Palugama-Boralanda-Haputale road, transition curve is not been used.
1.6.4.5. COMPOUND CURVE
This type comprises of successive curves of different radii in the same direction, with
common or closely spaced tangent points. The radius of the larger curve should not be
higher than 50% of the radius of the smaller curve. Generally compound curve should
be avoided and a single curve shall be adopted if topography and ground control is not
making an obstacle.
In designing of Palugama-Boralanda-Haputale road, compound curves are used.
-
8/18/2019 Design Report Print
48/227
40
1.6.4.6. REVERSE CURVE
These curves consists with successive curve having common or closely spaced
tangent points but in opposite direction. Reverse curve having common tangent point
make difficulty in achieving change of superelevation rates. Therefore short tangent
could be introduced between two curves to overcome the above problem.
In designing of Palugama-Boralanda-Haputale road, reverse curves are used.
1.6.4.7. SIMILAR CURVES
This consists of two curves in the same direction formed by a short tangent. Attempt
should be made to avoid this type of alignment by adopting a Simple Curve or a
Compound Curve. When Similar Curves are unavoidable, tangent lengths in the range
of 0.6 V to 3 V should be avoided. (Where V is the Design Speed in km/h for the
particular trace)
In designing of Palugama-Boralanda-Haputale road, similar curves were not used.
1.6.4.8. WIDENING OF CARRIGEWAY ON CURVES
Carriageways are widened on some curves because a vehicle passing through on a
curve occupies a greater width than it goes on a straight and to avoid difficulty in
steering their vehicles in the centre of the lane. The amount of widening required
depends on;
I. Radius of the curve.
II. Vehicle length and width.
III. Width of lane on straight.
IV. Lateral clearance between two vehicles.
-
8/18/2019 Design Report Print
49/227
41
In general practice minimum amount of widening is limited to 0.6m. The amount of
widening for a SU vehicle and for two lane highway is given in the table 1.6.5.
Table 1.6.5 – Design values for pavement widening on open highway curves
Radius of
curve (m)
6.2 meters
Design speed (km/h)
30 40 50 60 70
300 0.5 0.6 0.6 0.7 0.7
250 0.5 0.6 0.7 0.7 0.8
200 0.6 0.7 0.8 0.8 0.9
150 0.8 0.9 1.0 1.1 1.1
140 0.8 0.9 1.0 1.1 -
130 0.9 0.9 1.0 1.1 -
120 0.9 1.0 1.1 1.2 -
110 0.9 1.0 1.1 1.2 -
100 1.0 1.1 1.2 - -
90 1.1 1.2 1.3 - -
80 1.1 1.2 1.3 - -
70 1.2 1.3 - - -
60 1.3 1.5 - - -
50 1.6 1.7 - - -
40 1.8 - - - -
30 2.0 - - - -
-
8/18/2019 Design Report Print
50/227
42
1.7. SUPERELEVATION
1.7.1. GENERAL
When vehicle travels along a curve it experiences a force called centrifugal force.
Centrifugal force increases when the velocity of the vehicle increases and the radius
of the curvature decreases. To balance the effects of the centrifugal force curves
should be superelevated. The amount of superelevation will depend on the radius of
the curve, design speed and pavement surface characteristics.
1.7.2. STANDARDS FOR SUPERELEVATION
The superelevation to be adopted is selected for safety, comfort and appearance. Use
of maximum superelevation should be confined to mountainous terrain or places
where there are physical obstructions which confine the radius of the particular curve
with respect to the adjacent curves.
The maximum superelevation varies from 10% in m