v DESIGN TOLL WAY MOJOKERTO - KERTOSONO STA 5+350 STA 10+350 USING RIGID PAVEMENT AT MOJOKERTO REGENCY EAST JAVA PROVINCE Student : Muhammad Shofwan Donny Cahyono NRP : 3110.040.602 Department : Diploma IV Civil Engineering FTSP-ITS Counsellor Lecturer : R. Buyung Anugraha A, ST.MT NIP : 19740203 200212 1 002 ABSTRACT Mojokerto Kertosono toll road is an alternative way which the function is very important as a connecting road between Mojokerto until Kertosono which is a main path for the transportation vehicle, industrial, or personal vehicle,then the capacity and the service of road need to be improved. In this final project design toll way mojokerto - kertosonosta STA. 5+350 STA. 10+350 using rigid pavement at mojokerto regency east java province is planned along 5 km. In the analysis of capacity planning for road widening needs using “Manual Kapasitas Jalan Indonesia (MKJI 1997” , for pavement thickness design using guidance „Perencanaan Perkerasan Jalan Beton Semen Departemen Permukiman dan Prasarana Wilayah Pd. T-14-2003”, for the planning of roadside channel (drainage) using “Perencanaan Sistem Drainase Permukaan Jalan Departemen PU Pd. T-02-2006-B” and for RAB using HSPK Mojokerto 2011. Analysis result of road capacity in accordance with 20- year design period (2032) obtained the value of DS 0,749 with 21 m wide road. Construction analysis use continuously reinforced concrete pavement with 29 cm thick plate using

Upload: vunhi

Post on 11-May-2019

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DESIGN TOLL WAY MOJOKERTO KERTOSONO STA 10+350 … · channel (drainage) using “Perencanaan Sistem Drainase Permukaan Jalan Departemen PU Pd. T-02-2006-B” and for RAB using HSPK

v

DESIGN TOLL WAY MOJOKERTO - KERTOSONO

STA 5+350 – STA 10+350 USING RIGID PAVEMENT

AT MOJOKERTO REGENCY

EAST JAVA PROVINCE

Student : Muhammad Shofwan Donny Cahyono

NRP : 3110.040.602

Department : Diploma IV Civil Engineering

FTSP-ITS

Counsellor Lecturer : R. Buyung Anugraha A, ST.MT

NIP : 19740203 200212 1 002

ABSTRACT Mojokerto – Kertosono toll road is an alternative way

which the function is very important as a connecting road

between Mojokerto until Kertosono which is a main path for the

transportation vehicle, industrial, or personal vehicle,then the

capacity and the service of road need to be improved. In this final

project design toll way mojokerto - kertosonosta STA. 5+350 –

STA. 10+350 using rigid pavement at mojokerto regency east

java province is planned along 5 km.

In the analysis of capacity planning for road widening

needs using “Manual Kapasitas Jalan Indonesia (MKJI 1997” ,

for pavement thickness design using guidance „Perencanaan

Perkerasan Jalan Beton Semen Departemen Permukiman dan

Prasarana Wilayah Pd. T-14-2003”, for the planning of roadside

channel (drainage) using “Perencanaan Sistem Drainase

Permukaan Jalan Departemen PU Pd. T-02-2006-B” and for RAB

using HSPK Mojokerto 2011.

Analysis result of road capacity in accordance with 20-

year design period (2032) obtained the value of DS – 0,749 with

21 m wide road. Construction analysis use continuously

reinforced concrete pavement with 29 cm thick plate using

Page 2: DESIGN TOLL WAY MOJOKERTO KERTOSONO STA 10+350 … · channel (drainage) using “Perencanaan Sistem Drainase Permukaan Jalan Departemen PU Pd. T-02-2006-B” and for RAB using HSPK

vi

concrete tie on bone D13 – 200 mm for longitudinal direction and

D13 – 300 mm for transverse direction. For the palnned channel

dimesions using a trapezium with masonry materials with a

finishing time obtained by the following dimensions b = 43 cm, d

= 52 cm, w = 51 cm. Needed funds to construct this project is

Rp. 161.114.822.000,00 (Spelled Out Members One Hundred

Sixty Milliard One Hundred Fourteen Million Eight Hundred

Twenty Two thousands Rupiah). From the planning result of road above expected could

overcome and serve heavy traffic load according to design period

which have been palnned.

Keyword : Road Geometric,Rigid Pavement Thickness,

Reinforcement, dimesion of channel, RAB.