Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 1 of 99
DIRECTOR GENERAL OF CIVIL AVIATION
DIRECTORATE OF AS & ANS
Inspection checklist for CNS and ATM facilities:
NAME OF AIRPORT
PERIOD FOR INSPECTION
DATE
NAME DESIGNATION PERIOD
STATION INCHARGES DURING THE PERIOD
UNIT NAME DESIGNATION
1. VHF /VCCS/ RECORDER/
TIME SIGNAL
DISTRIBUTION
2. VOR/DME/NDB
UNIT
INCHARGES
3. ILS
S. NO. FACILITIES INSTALLED
1. VHF
2. RECORDER
3. TIMING SIGNAL DISTRIBUTION
4. CNS FACILITY STATUS INDICATOR
5. NDB
6. VOR/DME
7. ILS
NAME STAUS CALIBRATION
VALID UP TO
1.
2.
3.
TEST EQPTS
REQUIRED FOR
PERFORMANCE
CHECK AND
MAINTENANCE
OF ABOVE
FACILITIES
4.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 2 of 99
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 3 of 99
NAME OF THE SITE: CVOR/DVOR
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 4 of 99
FACILITY INSPECTED VOR & DME
MAKE OF THE EQUIPMENT
MODEL OF THE EQUIPMENT
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 5 of 99
FACILITY INSPECTION
1
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 6 of 99
. Equipment History
No. Aspects CAR
Reference
Compliance
Status
Remarks
A
B
Age
What is the prescribed life of the equipment as per manufacturer?
i. Year of manufacture/ procurement?
ii. Year of installation/ commissioning
iii. What is the service life in years till now?
iv. If it has out lived then what is the action plan for replacement/ continuation?
Major changes since last inspection
i. Has there been any major site related change
since last inspection which might have an
impact on the normal functioning of the facility?
ii. If yes, then has its impact been studied and
analysed?
iii. What steps have been taken to mitigate the
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 7 of 99
impact.
2
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 8 of 99
. Equipment Performance
The compliance status of the CARs associated with performance of VOR/DME may please be given in the format as given below.
Facility General Status
i. Are both channels working normal?
ii. If not then give reasons for un-serviceability
and action plan for restoration.
iii. Are the remote control systems for both the
channel functioning normally?
iv. If not then give action plan for restoration.
v. Are the facility status indicators at tower and
equipment room for both the channels working
normal?
Flight / Ground checks
i. When was the last ground check
done?(enclose last report)
ii. When was the last flight check done? (enclose
last report)
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 9 of 99
CAR compliance status for DVOR S no. Parameter CAR
ReferenceReference value/ tolerance Value Compliance
Status Remarks
1. Radio Frequency 3.3.2 ±0.002%
2. Deviation 3.3.3.1 ±2.0°
3. Alignment with
neighboring stations
3.3.2.1 ±2.0°
4. i. Accuracy
ii. Polarization
iii. Alignment
iv. Bends
v. Roughness and
scalloping
vi. Flyability
3.3.3.2 ±2.0°
±2.0°
±2.0°
±3.5°
±3.0°
Flyable
5. Coverage 3.3.4.1 Up to required distance and to an
elevation angle of 400
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 10 of 99
S no. Parameter CAR Reference
Reference value/ tolerance Value Compliance Status
Remarks
6. Field strength 3.3.4.2 90 μV/m
7. 9 960 Hz deviation 3.3.5.1 16+1
8. 9 960 Hz modulation
depth
3.3.5.2 28% to 32%
9. 30 Hz modulation
depth
3.3.5.3 28% to 32%
10. 30 Hz modulation
frequency
3.3.5.4 30 Hz +1%
11. 9 960 Hz subcarrier
frequency
3.3.5.5 9960 Hz+1%
12. Amp. Mod. Of 9 960
Hz subcarrier
frequency
3.3.5.6 < 5%
13. Sideband level of
harmonics of 9 960 Hz
3.3.5.7 2nd Harmonics -30 dB
3rd Harmonics -50 dB
4th Harmonics -60 dB
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 11 of 99
S no. Parameter CAR Reference
Reference value/ tolerance Value Compliance Status
Remarks
14. Identification speed 3.3.6.5 7 words per minute
15. Identification repetition 3.3.6.5 > once every 30 sec.
16. Identification tone
frequency
3.3.6.5 1020 Hz+50 Hz
17. Identification modulation depth with no communications channel
3.3.6.6 < 20%
18. Bearing monitor 3.3.7.1 Radiation should cease if a change in
excess of 10 monitored
19. Modulation monitor 3.3.7.1 Radiation should cease if reduction of
15% of modulation is monitored for
either subcarrier of 30 Hz or both
20. Failure of monitor
3.3.7.2 By removing the ident and navigations component
or Cause radiation to cease.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 12 of 99
CAR compliance status for DME (HP/LP)
S no. Parameter CAR
Reference
Reference value/ tolerance Value Compliance
Status
Remarks
1. Transmitter
- Frequency stability - Pulse spectrum - Pulse shape
- Pulse spacing - Peak power output - Peak variation
- Pulse repetition
frequency
3.5.4.1.2
3.5.4.1.3
3.5.4.1.3
3.5.4.1.4
3.5.4.1.5
3.5.4.1.5.4
3.5.4.1.5.6
+0.002%
+ 2MHz of central frequency
Rise time <3µS,Duration
3.5+0.5µS,Decay time< 3.5µS
nominal 2.5µS
12-6sec.+0.25-6sec
>-89dBW/m2
Any pair of pulses shall not differ by
more than 1 dB.
Minimum 700 PP/Sec to Maximum
2700 +90 PP/Sec
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 13 of 99
S no. Parameter CAR
Reference
Reference value/ tolerance Value Compliance
Status
Remarks
2. Receiver
- Frequency stability - Sensitivity - Sensitivity variation
with load - - Bandwidth
3.5.4.2.2
3.5.4.2.3.1
3.5.4.2.6
3.5.4.2.3.5
+0.002%
-103dBW/m2
≤3dB for +100KHz drift in
interrogation frequency
< 1dB for transponder loading of 0 to
90% of maximum transmission rate.
3. Decoder 3.5.4.3 No response to interrogations with pulse spacing more than 2 μs from nominal
4. Time delay 3.5.4.4 X-channel: 50 μs
5. Identification 3.5.3.6 1 350 pulse pairs during key down periods proper Morse code sequence dot length = 0.1 to 0.16 s; dash = 0.3 to 0.48 s; spacing between dot and dash = dot length ±10%; spacing between letters <3 dots 10 μs total length of one code sequence <10 seconds
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 14 of 99
S no. Parameter CAR
Reference
Reference value/ tolerance Value Compliance
Status
Remarks
6. Monitor action 3.5.4.7.2.2 Monitor alarms when: Reply delay varies by more than 1 μs (0.5 μs for DME associated with a landing aid)
7. Monitor action delay 3.5.4.7.2.5 Delay <10 seconds
8. Coverage 3.5.3.1.2
/3.5.4.1.5.2
Signal strength such that field density >-89 dBW/m2 at limits or operational requirements
9. Accuracy 3.5.4.5 <150 m
<75 m for DME associated with
landing aids
10. Pulse shape 3.5.4.1.3 Rise time <3 μs Duration 3.5 μs, ±0.5 μs Decay time <3.5 μs Instant amplitude, between 95% rise/fall edge, should not fall below 95% of maximum amplitude
11. Pulse spacing 3.5.4.1.4 X channel: 12 ±0.25 μs
12. Identification 3.5.3.6 Correct, clear, properly
synchronized
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 15 of 99
S no. Parameter CAR
Reference
Reference value/ tolerance Value Compliance
Status
Remarks
13. Reply efficiency 3.5.4.6.1 Note areas where this changes
significantly
14. Unlocks 3.3.15
(Doc 8071)
Note where unlocking occurs
15. Standby equipment 3.3.16
(Doc 8071)
Same as primary transmitter
16. Standby power 3.3.17
(Doc 8071)
Should not affect transponder
parameters
3
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 16 of 99
. Equipment Failure analysis
A.
B.
DVOR
i. List all the NOTAMs related to the facility since last
inspection.
ii. What is the total duration, total numbers of failures and
their causes in the last one year? (prepare a chart as per
format given in annex)
iii. What is the MTBF for each channel?
iv. What is the MTTR for faults?
DME
v. List all the NOTAMs related to the facility since last
inspection.
vi. What is the total duration, total numbers of failures and
their causes in the last one year? (prepare a chart as per
format given in annex)
vii. What is the MTBF for each channel?
viii. What is the MTTR for faults?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 17 of 99
4. Equipment Maintenance & Spares
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 18 of 99
Are all the maintenance activities being performed in the unit and
duly being recorded?
Preventive
a. Daily recording of essential parameters and meter
readings.
b. Weekly as per approved schedules.
c. Monthly as per approved schedules.
d. Six monthly as per schedule.
e. Maintenance of Fault log book.
2. Is there any parameter out of tolerance for which remedial
action is yet to be taken?
3. If yes then indicate the parameter and mitigation plan?
Corrective
4. Is the manufacturer or indigenous backup support available
for fault isolation and rectification?
5. If not then what is the contingency plan in case of failure?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 19 of 99
Spares
6. Have the critical spares been identified?
7. Are they available (on site or depot)?
Note : If any of the above activity not required as per
manufacturer recommendation and AAI approval, the same may
be notified and concurrence of DGCA may be obtained
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 20 of 99
5. Equipment Manuals & Documents
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 21 of 99
A. Schedules
i. Are these preventive schedules as approved by DGCA
available?
a. Daily schedule
b. Weekly schedule
c. Monthly schedule
d. Six monthly schedule
e. Yearly schedule
B. Log books
i. Are the following Log books available?
a. Fault log book
b. Equipment history book
c. Shift duty log book
d. General duty log book
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 22 of 99
C. Manuals
i. Are the following manuals as supplied by manufacturer
available?
a. Are all the volumes of technical manuals available?
b. Are all the volumes of operational manuals
available?
D. ICAO Documents/DGCA CARs/CNS Manuals
i. Are these ICAO documents/ DGCA CARs available?
a. Annex- 10
b. CARs
c. Doc 8071
d. CNS manual
Note: Manuals and documents should be made available at the time of inspection
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 23 of 99
6. Human resource:
A. Adequacy
i. What is the manpower requirement, for maintenance and operation of the facility, as per approved norms?
ii. Is the same available?
iii. If not, what is the mitigation plan
B. Training & Proficiency
i. Is the staff deployed, for the operation and maintenance of
the facility, proficient on this type of equipment?
ii. Have they undergone refresher training & OJT before
deployment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 24 of 99
DVOR - SITE INSPECTION
No. Aspects CAR
Reference
Compliance
Status
Remarks
1. Civil
Building
i. Is the approach to the building clear of grass
and other vegetation?
ii. Is the equipment building in good condition
(check for breakage, leakage etc)?
iii. Is the building properly painted as per standard
design pattern?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 25 of 99
Ambience
i. Is the equipment room meeting the
environmental conditions for satisfactory
equipment performance?
a. Temperature
b. Humidity c. Dust-proof (check for window pane
breakage, space between the door frames
and doors)?
Frangible huts
i. In case the building is a frangible hut :
a. Is building properly sealed from all sides to
prevent entry of any reptile such as rats,
snakes etc.?
b. Is the thermal insulation in walls and roof
sufficient to meet the temperature
requirement of the equipment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 26 of 99
2. Electrical
Earthing
i. Is the earthing of the electrical installations ok?
a. What is the resistance of the system?
b. Name the standard being followed.
ii. Is the earthing of the equipment ok?
a. What is the resistance of the system?
b. Name the standard being followed.
Lighting protection
iii. Is the lightening protection system working
normal?
a. Name the type
b. If multi-strike type give the count
Surge protection
iv. Is the surge protection system working
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 27 of 99
normal?
a. Name the type and give operational
range.
Power Supply
v. Is the power supply available meets the
standard (voltage, frequency)?
vi. Which power back up system (Generator,
UPS, and Battery) available?
vii. AMF panel is manual or automatic?
a. Mention the switchover time.
viii. What is the back-up period
a. UPS
b. Batteries
Cooling
ix. Are the number of a/c sufficient to maintain the
temperature required for the equipment
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 28 of 99
a. Is their preventive maintenance being
done as per schedule?
b. When was the last preventive
maintenance done?
3. Fire protection
1. Are the fire extinguishers working
normal
2. Mention type of extinguisher used
3. Are they suitably placed for easy
approach?
4. Are they tested for functionality as per
schedule?
5. When they were last tested?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 29 of 99
NAME OF THE SITE: ILS - LOCALIZER
FACILITY LLZ
MAKE OF THE EQUIPMENT
MODEL OF THE EQUIPMENT
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 30 of 99
FACILITY INSPECTION
1. Equipment History No. Aspects CAR
Reference
Compliance
Status
Remarks
A
B
Age
What is the prescribed life of the equipment as per manufacturer?
i. Year of manufacture/ procurement? ii. Year of installation/ commissioning iii. What is the service life in years till now? iv. If it has out lived then what is the action plan
for replacement/ continuation?
Major changes since last inspection
i. Has there been any major site related change since last inspection which might have an impact on the normal functioning of the facility?
i. If yes, then has its impact been studied and analysed?
ii. What steps have been taken to mitigate the impact.
2
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 31 of 99
. Equipment Performance
Facility General Status
i. Are both channels working normal?
ii. If not then give reasons for un-serviceability
and action plan for restoration.
iii. Are the remote control systems for both the
channel functioning normally?
iv. If not then give action plan for restoration.
v. Are the facility status indicators at tower and
equipment room for both the channels working
normal?
Flight / Ground checks
vi. When was the last ground check
done?(enclose last report)
vii. When was the last flight check done? (enclose last report)
The compliance status of the CARs associated with performance of ILS may please be given in the format as given below.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 32 of 99
CAR Compliance status for ILS (LLZ)
S no. Parameter CAR
Reference
Reference value/ tolerance Value Compliance
Status
Remarks
1. Frequency 3.1.3.2.1 Frequency single: 0.005% Dual: 0.002%
Separation: >5 kHz <14 kHz.
2. Spurious modulation 3.1.3.2.3 <0.005 DDM peak-to-peak
3. Coverage (usable
distance)
3.1.3.3.1 As set at commissioning
4. Field strength 3.1.3.3.2 CAT – I : >-107dBW/m2 at 10 NM
to threshold
CAT- II: >-106dBW/m2 at 10 NM to
-100dBW/m2 at threshold
CAT – III: >-106dBW/m2 at 10 NM
to -100dBW/m2 at threshold and
along the length of the runway in
the direction of the LLz
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 33 of 99
5. Course structure 3.1.3.4 As described in Annex 10.
6. Carrier modulation - Balance - Depth
3.1.3.5.1 Within 10 μA of the modulation
balance value.
18-22%
7. Carrier modulation
frequency
3.1.3.5.3 Cat I: ±2.5% Cat II: ±1.5% Cat III: ±1%
8. Carrier modulation
harmonic content (90 Hz)
3.1.3.5.3 d) <10%
<5% (Cat III)
9. Carrier modulation
harmonic content (150
Hz)
3.1.3.5.3 e) <10%
<5% (Cat III)
10. Phasing of alternative
systems
3.1.3.5.3.5 Cat I, II, nominal: ±20° Cat III nominal: ±10°
11. Sum of modulation
depths
3.1.3.5.3.6 Modulation depth <95%
12. Course alignment 3.1.3.6 Cat I: <10.5 m. Cat II: <7.5 m Cat III: < 3 m
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 34 of 99
13. Displacement sensitivity 3.1.3.7 0.00145 Nominal. See Note 2. Cat I, II: ±17% Cat III: ±10%
14. Peak modulation depth 3.1.3.8.3.2 <50%
15. Audio frequency
characteristic
3.1.3.8.3.3 ±3dB
16. Identification tone
frequency
3.1.3.9.2 1 020 ±50 Hz
17. Identification modulation
depth
3.1.3.9.2 As commissioned.
18. Identification repetition
rate
3.1.3.9.4 As commissioned.
19. Phase modulation 3.1.3.5.4 Limits given in FM Hz/PM radians 90 Hz 150 Hz (Difference Hz) Cat I: 135/1.5 135/0.9 45 Cat II: 60/0.66 60/0.4 20 Cat III: 45/0.5 45/0.3 15
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 35 of 99
20. Monitoring
- Course shift
- Change in
displacement
sensitivity
- Clearance signal
3.1.3.11.2
3.1.3.11.2.f
3.1.3.11.2.1
Monitor must alarm for a shift in the main course line from the runway centre line equivalent to or more than the following distances at the ILS reference datum. Cat I: 10.5 m (35 ft) Cat II: 7.5 m (25 ft) Cat III: 6.0 m (20 ft) Monitor must alarm for a change in displacement sensitivity to a value differing from the nominal value by more than: Cat I: 17% Cat II: 17% Cat III: 17% Monitor must alarm when the off-course clearance cross-pointer deflection falls below 150 μA anywhere in the off-course coverage area.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 36 of 99
- Reduction in power
- Total time, out-of-
tolerance radiation
3.1.3.11.2 d) and e) 3.1.3.11.3
Monitor must alarm either for a power reduction of 3 dB, or when the coverage falls below the requirement for the facility, whichever is the smaller change. For two-frequency localizers, the monitor must alarm for a change of ±1dB in either carrier, unless tests have proved that use of the wider Limits above will not cause unacceptable signal degradation (>150 μa in clearance sector). Cat I: 10 s Cat II:5 s Cat III: 2 s
3
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 37 of 99
. Equipment Failure analysis
A.
LLZ
i. List all the NOTAMs related to the facility since last
inspection.
ii. What is the total duration, total numbers of failures and
their causes in the last one year? (prepare a chart as per
format given in annex)
iii. What is the MTBF for each channel?
iv. What is the MTTR for faults?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 38 of 99
4. Equipment Maintenance & Spares
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 39 of 99
Are all the maintenance activities being performed in the unit and
duly being recorded?
Preventive
a. Daily recording of essential parameters and meter
readings.
b. Weekly as per approved schedules.
c. Monthly as per approved schedules.
d. Six monthly as per schedule.
e. Maintenance of Fault log book.
ii. Is there any parameter out of tolerance for which remedial
action is yet to be taken?
iii. If yes then indicate the parameter and mitigation plan?
Corrective
iv. Is the manufacturer or indigenous backup support
available for fault isolation and rectification?
v. If not then what is the contingency plan in case of failure?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 40 of 99
Spares
vi. Have the critical spares been identified?
vii. Are they available (on site or depot?
Note : If any of the above activity not required as per
manufacturer recommendation and AAI approval, the same may
be notified and concurrence of DGCA may be obtained
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 41 of 99
5. Equipment Manuals & Documents
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 42 of 99
A. Schedules
i. Are these preventive schedules as approved by DGCA
available?
a. Daily schedule
b. Weekly schedule
c. Monthly schedule
d. Six monthly schedule
e. Yearly schedule
B. Log books
i. Are the following Log books available?
a. Fault log book
b. Equipment history book
c. Shift duty log book
d. General duty log book
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 43 of 99
C. Manuals
i. Are the following manuals as supplied by manufacturer
available?
a. Are all the volumes of technical manuals available?
b. Are all the volumes of operational manuals
available?
D. ICAO Documents/DGCA CARs/CNS Manuals
i. Are these ICAO documents/ DGCA CARs available?
a. Annex- 10
b. CARs
c. Doc 8071
d. CNS manual
Note: Manuals and documents should be made available at the time of inspection
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 44 of 99
6. Human resource:
A. Adequacy
i. What is the manpower requirement, for maintenance and operation of the facility, as per approved norms?
ii. Is the same available?
iii. If not, what is the mitigation plan
B. Training & Proficiency
i. Is the staff deployed, for the operation and maintenance of
the facility, proficient on this type of equipment?
ii. Have they undergone refresher training & OJT before
deployment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 45 of 99
LLZ SITE INSPECTION No. Aspects CAR
Reference
Compliance Status Remarks
1. Civil
Building i. Is the approach to the building clear of grass
and other vegetation?
ii. Is the equipment building in good condition (check for breakage, leakage etc)?
iii. Is the building properly painted as per standard design pattern?
Ambience
i. Is the equipment room meeting the environmental conditions for satisfactory equipment performance? a. Temperature
b. Humidity
c. Dust-proof (check for window pane
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 46 of 99
breakage, space between the door frames
and doors)?
Frangible huts
ii. In case the building is a frangible hut :
a. Is building properly sealed from all sides to
prevent entry of any reptile such as rats,
snakes etc.?
b. Is the thermal insulation in walls and roof
sufficient to meet the temperature
requirement of the equipment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 47 of 99
2. Electrical
Earthing
i. Is the earthing of the electrical installations
ok?
a. What is the resistance of the system?
b. Name the standard being followed.
ii. Is the earthing of the equipment ok?
a. What is the resistance of the system?
b. Name the standard being followed.
Lighting protection
iii. Is the lightening protection system working
normal?
a. Name the type
b. If multi-strike type give the count
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 48 of 99
Surge protection
iv. Is the surge protection system working
normal?
a. Name the type and give operational
range.
Power Supply
v. Is the power supply available meets the
standard (voltage, frequency)?
vi. Which power back up system (Generator,
UPS, and Battery) available?
vii. AMF panel is manual or automatic?
a. Mention the switchover time.
viii. What is the back-up period
a. UPS
b. Batteries
Cooling
ix. Are the number of a/c sufficient to maintain
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 49 of 99
the temperature required for the equipment
a. Is their preventive maintenance being
done as per schedule?
b. When was the last preventive
maintenance done?
3. Fire protection
i. Are the fire extinguishers working
normal
ii. Mention type of extinguisher used
iii. Are they suitably placed for easy
approach?
iv. Are they tested for functionality as per
schedule?
v. When they were last tested?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 50 of 99
NAME OF THE SITE: ILS - GLIDEPATH
FACILITY GLIDEPATH
MAKE OF THE EQUIPMENT
MODEL OF THE EQUIPMENT
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 51 of 99
FACILITY INSPECTION
1. Equipment History
No. Aspects CAR
Reference
Compliance
Status
Remarks
1. Age
i. What is the prescribed life of the equipment as per manufacturer?
ii. Year of manufacture/ procurement?
iii. Year of installation/ commissioning
iv. What is the service life in years till now?
v. If it has out lived then what is the action plan for replacement/ continuation?
Major changes since last inspection Has there been any major site related change since last inspection which might have an impact on the normal functioning of the facility? vi. If yes, then has its impact been studied and
analysed? vii. What steps have been taken to mitigate the
impact.
2
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 52 of 99
. Equipment Performance
No. Aspects CAR
Reference
Compliance
Status
Remarks
Facility General Status
i. Are both channels working normal?
ii. If not then give reasons for un-serviceability and action plan for restoration.
iii. Are the remote control systems for both the channel functioning normally?
iv. If not then give action plan for restoration.
v. Are the facility status indicators at tower and equipment room for both the channels working normal?
Flight / Ground checks
vi. When was the last ground check done?(enclose last report)
vii. When was the last flight check done? (enclose last report)
The compliance status of the CARs associated with performance of ILS may please be given in the format as given below.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 53 of 99
CAR Compliance for ILS (GP)
S no. Parameter CAR
Reference
Reference value/ tolerance Value Compliance
Status
Remarks
1. Path angle 3.1.5.1.2.2 Cat I: Within 7.5% of nominal angle Cat II: Within 7.5% of nominal angle Cat III: Within 4% of nominal angle
2. Frequency 3.1.5.2.1 Single 0.005% Dual 0.002% Separation >4 kHz, <32 kHz
3. Unwanted modulation 3.1.5.2.3 ±0.02 DDM peak-to-peak
4. Coverage (usable
distance) 3.1.5.3 As commissioned.
5. Carrier modulation - Balance - Depth
3.1.5.5.1 0.002 DDM 37.5% to 42.5% for each tone
6. Carrier modulation
frequency 3.1.5.5.2
a), b), and c)
Cat I: 2.5% Cat II: 1.5% Cat III: 1%
7. Carrier modulation harmonic content (90 Hz)
3.1.5.5.2
d) <10% <5% (Cat III)
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 54 of 99
8. Carrier modulation harmonic content (150 Hz)
3.1.5.5.2
e) <10% < 5% (Cat III)
9. Unwanted amplitude modulation
3.1.5.5.2.2 <1%
10. Phase of modulation tones
3.1.5.5.3 Cat I, II: <20° Cat III: <10°
11. Phase of modulation tones, dual frequency systems (each carrier and between carriers)
3.1.5.5.3.1
Cat I, II: <20° Cat III: <10°
12. Phase of modulation tones,
alternative systems
3.1.5.5.3.2 Cat I, II: Nominal ± 20° Cat III: Nominal ± 10°
13. Displacement sensitivity 3.1.5.6 Refer to CAR, Sec. 4 Series D Part-II, 3.1.5.6
14. Monitoring
- Path angle
3.1.5.7.1
a)
Monitor must alarm for a change in angle of 7.5% of the promulgated angle.
- Change in
displacement
3.1.5.7.1
d), e) Cat I: Monitor must alarm for a change in the angle between the glide path and the line below the
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 55 of 99
sensitivity glide path at which 75 μA is obtained, by more than 3.75% of path angle. Cat II: Monitor must alarm for a change in displacement sensitivity by more than 25%. Cat III: Monitor must alarm for a change in displacement sensitivity by more than 25%.
- Reduction in power 3.1.5.7.1
b), c) Monitor must alarm either for a power reduction of 3 dB, or when the coverage falls below the requirement for the facility, whichever is the smaller change.
- Clearance signal 3.1.5.7.1
g) Monitor must alarm for DDM <0.175 below path clearance area
- Total time of out-of-tolerance radiation
3.1.5.7.3.1 Cat I: 6 s Cat II, III:2 s
- Monitor System
Failure
3.1.5.7.4 Monitor system should be consistent with the requirement that the radiation shall cease and warning shall be provided at the designated remote control point in the event of failure of the monitor system itself
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 56 of 99
3. Equipment Failure analysis
A.
Glide Path
i. List all the NOTAMs related to the facility since last
inspection.
ii. What is the total duration,total numbers of failures and
their causes in the last one year? (prepare a chart as per
format given in annex)
iii. What is the MTBF for each channel?
iv. What is the MTTR for faults?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 57 of 99
4. Equipment Maintenance & Spares
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 58 of 99
Are all the maintenance activities being performed in the unit and
duly being recorded?
Preventive
f. Daily recording of essential parameters and meter
readings.
g. Weekly as per approved schedules.
h. Monthly as per approved schedules.
i. Six monthly as per schedule.
j. Maintenance of Fault log book.
ii. Is there any parameter out of tolerance for which remedial
action is yet to be taken.
iii. If yes then indicate the parameter and mitigation plan?
Corrective
iv. Is the manufacturer or indigenous backup support
available for fault isolation and rectification?
v. If not then what is the contingency plan in case of failure?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 59 of 99
Spares
vi. Have the critical spares been identified?
vii. Are they available (on site or depot?
Note : If any of the above activity not required as per
manufacturer recommendation and AAI approval, the same may
be notified and concurrence of DGCA may be obtained
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 60 of 99
5. Equipment Manuals & Documents
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 61 of 99
A. Schedules
i. Are these preventive schedules as approved by DGCA
available?
a. Daily schedule
b. Weekly schedule
c. Monthly schedule
d. Six monthly schedule
e. Yearly schedule
B. Log books
i. Are the following Log books available?
a. Fault log book
b. Equipment history book
c. Shift duty log book
d. General duty log book
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 62 of 99
C. Manuals
i. Are the following manuals as supplied by manufacturer
available?
a. Are all the volumes of technical manuals available?
b. Are all the volumes of operational manuals
available?
D. ICAO Documents/DGCA CARs/CNS Manuals
i. Are these ICAO documents/ DGCA CARs available?
a. Annex- 10
b. CARs
c. Doc 8071
d. CNS manual
Note: Manuals and documents should be made available at the time of inspection
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 63 of 99
6. Human resource:
A. Adequacy
i. What is the manpower requirement, for maintenance and operation of the facility, as per approved norms?
ii. Is the same available?
iii. If not, what is the mitigation plan
B. Training & Proficiency
i. Is the staff deployed, for the operation and maintenance of
the facility, proficient on this type of equipment?
ii. Have they undergone refresher training & OJT before
deployment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 64 of 99
GP SITE INSPECTION No. Aspects CAR
Reference
Compliance Status Remarks
1. Civil
Building i. Is the approach to the building clear of grass
and other vegetation?
ii. Is the equipment building in good condition (check for breakage, leakage etc)?
iii. Is the building properly painted as per standard design pattern?
Ambience
i. Is the equipment room meeting the environmental conditions for satisfactory equipment performance? a. Temperature
b. Humidity
c. Dust-proof (check for window pane
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 65 of 99
breakage, space between the door frames
and doors)?
Frangible huts
ii. In case the building is a frangible hut :
a. Is building properly sealed from all sides to
prevent entry of any reptile such as rats,
snakes etc.?
b. Is the thermal insulation in walls and roof
sufficient to meet the temperature
requirement of the equipment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 66 of 99
2. Electrical
Earthing
i. Is the earthing of the electrical installations
ok?
a. What is the resistance of the system?
b. Name the standard being followed.
ii. Is the earthing of the equipment ok?
a. What is the resistance of the system?
b. Name the standard being followed.
Lighting protection
iii. Is the lightening protection system working
normal?
a. Name the type
b. If multi-strike type give the count
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 67 of 99
Surge protection
iv. Is the surge protection system working
normal?
a. Name the type and give operational
range.
Power Supply
v. Is the power supply available meets the
standard (voltage, frequency)?
vi. Which power back up system (Generator,
UPS, and Battery) available?
vii. AMF panel is manual or automatic?
a. Mention the switchover time.
viii. What is the back-up period
a. UPS
b. Batteries
Cooling
ix. Are the number of a/c sufficient to maintain
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 68 of 99
the temperature required for the equipment
a. Is their preventive maintenance being
done as per schedule?
b. When was the last preventive
maintenance done?
3. Fire protection
vi. Are the fire extinguishers working
normal
vii. Mention type of extinguisher used
viii. Are they suitably placed for easy
approach?
ix. Are they tested for functionality as per
schedule?
x. When they were last tested?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 69 of 99
NAME OF THE SITE: NDB
FACILITY INSPECTED NDB
MAKE OF THE EQUIPMENT
MODEL OF THE EQUIPMENT
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 70 of 99
FACILITY INSPECTION
4. Equipment History
No. Aspects CAR
Reference
Compliance
Status
Remarks
A
B
Age
What is the prescribed life of the equipment as per manufacturer?
v. Year of manufacture/ procurement?
vi. Year of installation/ commissioning
vii. What is the service life in years till now?
viii. If it has out lived then what is the action plan for replacement/ continuation?
Major changes since last inspection
iv. Has there been any major site related change since last inspection which might have an impact on the normal functioning of the facility?
v. If yes, then has its impact been studied and analysed? vi. What steps have been taken to mitigate the impact.
5
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 71 of 99
. Equipment Performance
The compliance status of the CARs associated with performance of VOR/DME may please be given in the format as given below.
Facility General Status
vi. Are both channels working normal?
vii. If not then give reasons for un-serviceability
and action plan for restoration.
viii. Are the remote control systems for both the
channel functioning normally?
ix. If not then give action plan for restoration.
x. Are the facility status indicators at tower and
equipment room for both the channels working
normal?
Flight / Ground checks
iii. When was the last ground check
done?(enclose last report)
iv. When was the last flight check done? (enclose
last report)
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 72 of 99
CAR compliance status for NDB
Measured Value S no. Parameter CAR/Annex.
10 Reference
Nominal tolerance
TX- 1 TX-2
Compliance
Status
Remarks
1. Carrier Frequency 3.4.4.2 ±0.01% (+0.005% for
power > 200 W at
frequencies
above1606.5 kHz)
2. Modulation depth 3.4.6.2 ±85% to 95%
3. Modulation frequency 3.4.5.4 1020 Hz+50 Hz
400Hz+25 Hz
4. Modulation depth of
power supply frequency
components
3.4.6.5 Less than 5% modulation depth
5. Carrier level change
during the modulation
3.4.6.4 < 0.5 dB If coverage is
<50 NM , <1.5dB If
coverage is >50 NM
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 73 of 99
6. Identification 3.4.5.1,
3.4.5.3
Approx. 7 words
/minute
7. Monitoring system
a) Antenna current or
field strength
3.4.8.1a
Alarm for 3dB decrease
8. b) Failure of
identification
3.4.8.1b Alarm for loss of or
continuous modulation
9. c) Malfunctioning of
monitor itself
3.4.8.1c Alarm for malfunction of
monitor
10. Rated coverage 3.4.2.1 >70µV/meter
11. Antenna Current Doc. 8071
(5.2.4)
<+30% of the value set
at the time of
commissioning
12. Audio distortion Doc. 8071
(5.2.10)
10% of distortion
Maximum
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 74 of 99
NDB SITE INSPECTION
No. Aspects CAR
Reference
Compliance
Status
Remarks
1. Civil
Building
iv. Is the approach to the building clear of grass
and other vegetation?
v. Is the equipment building in good condition
(check for breakage, leakage etc)?
vi. Is the building properly painted as per standard
design pattern?
Ambience
ii. Is the equipment room meeting the
environmental conditions for satisfactory
equipment performance?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 75 of 99
a. Temperature
b. Humidity c. Dust-proof (check for window pane
breakage, space between the door frames
and doors)?
Frangible huts
ii. In case the building is a frangible hut :
a. Is building properly sealed from all sides to
prevent entry of any reptile such as rats,
snakes etc.?
b. Is the thermal insulation in walls and roof
sufficient to meet the temperature
requirement of the equipment?
2. Electrical
Earthing
x. Is the earthing of the electrical installations ok?
a. What is the resistance of the system?
b. Name the standard being followed.
xi. Is the earthing of the equipment ok?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 76 of 99
a. What is the resistance of the system?
b. Name the standard being followed.
Lighting protection
xii. Is the lightening protection system working
normal?
c. Name the type
d. If multi-strike type give the count
Surge protection
xiii. Is the surge protection system working
normal?
b. Name the type and give operational
range.
Power Supply
xiv. Is the power supply available meets the
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 77 of 99
standard ( voltage, frequency)?
xv. Which power back up system (Generator,
UPS, and Battery) available?
xvi. AMF panel is manual or automatic?
a. Mention the switchover time.
xvii. What is the back-up period
a. UPS
b. Batteries
Cooling
xviii. Are the number of a/c sufficient to maintain the
temperature required for the equipment
c. Is their preventive maintenance being
done as per schedule?
d. When was the last preventive
maintenance done?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 78 of 99
3. Fire protection
6. Are the fire extinguishers working
normal
7. Mention type of extinguisher used
8. Are they suitably placed for easy
approach?
9. Are they tested for functionality as per
schedule?
10. When were they last tested?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 79 of 99
NAME OF THE SITE: EQUIPMENT ROOM / TOWER
FACILITY INSPECTED – VHF and Equipment room Facilities
NAME MAKE MODEL VHF DATIS RECORDER
TIME SIGNAL
GENERATION &
DISTRIBUTION.
FACILITIES
RCAG
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 80 of 99
FACILITY INSPECTION
I. Equipment History
Age VHF
RECORDER TIME SIGNAL
DATIS RCAG
i. What is the prescribed life of the equipment as per
manufacturer?
ii. Year of manufacture/ procurement?
iii. Year of installation/ commissioning
iv. What is the service life in years till now?
A.
v. If it has out lived then what is the action plan for
replacement/ continuation?
II
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 81 of 99
. Equipment Performance
Status of VHF channels
i. Are both main and standby Tx/Rx of all channels working
normal?
ii. If not then give reasons for un-serviceability and action
plan for restoration.
iii. Are the changeover systems from main to standby Tx/Rx
for all channels functioning normally?
iv. If not then give action plan for restoration.
i. What is the general range of the VHF Tx/Rx as checked by
aircrafts?
ii. Are the ranges of the VHF Tx/Rx satisfactory as per
users?
iii. If not, what is the mitigation plan?
iv. Is the coverage area of the VHF communication
satisfactory as per the users?
v. If not, then what is the mitigation plan?
vi. Enclose performance check report.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 82 of 99
vii. What is the minimum separation between the antennas
required to prevent interference?
v. Is there any non compliance with respect to CARs for VHF
communication?
vi. Are there any interference in any of the channels?
a. If yes then mention the channels having
interference and what steps are being taken to stop
interference?
Status of VOR, DME, ILS Remote Monitoring and Control System
i. Are the RMCS working normal?
a. If no then give reasons and the restoration plans.
ii. Are there spare telephone lines available for RMCS?
a. From site to Equipment. Room.
b. From Equipment Room to tower?
Status of DATIS
i. Is the DATIS system working normal?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 83 of 99
a. If not give reasons b. What is the restoration plan?
Status of Recorder
viii. Is the Recorder equipment functioning normally?
ix. If no give reasons and restoration plan.
x. If yes
- Are both main and standby available?
- Are all the required facilities being recorded?
- Is the play back noise free?
- Are all indications and controls working fine?
- Are all inputs and outputs labeled properly?
- Are spare lines available between facilities and recorder?
I
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 84 of 99
II. Equipments Failure analysis
VHF
RECORDER TIME
SIGNAL
DATIS DVTR
i. List all the NOTAMs related to the facility since last
inspection
ii. What is the total duration, total numbers of failures and
their causes in the last one year? (prepare a chart as per
format given in annex)
iii. What is the MTBF for each communication channel?
iv. What is the MTTR for faults?
IV.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 85 of 99
Equipment Maintenance & Spares
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 86 of 99
DVTR RECORDER TIME
SIGNAL DATIS VHF
A.
B.
C.
Are all the maintenance activities being performed in the
unit and duly being recorded?
Preventive
a. Daily recording of essential parameters and meter
readings.
b. Weekly as per approved schedules.
c. Monthly as per approved schedules.
d. Six monthly as per approved schedule.
e. Maintenance of Fault log book.
ii. Is there any parameter out of tolerance for which remedial
action is yet to be taken.
iii. If yes then indicate the parameter and mitigation plan?
Corrective
iv. Is the manufacturer’s or indigenous backup support
available for fault isolation and rectification?
v. If not then what is the contingency plan in case of failure?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 87 of 99
Spares
vi. Have the critical spares been identified?
vii. Are they available (on site or depot?
Note: If any of the above activity not required as per
manufacturer’s recommendation and AAI approval, the same
may be notified and concurrence of DGCA may be obtained.
V.
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 88 of 99
Equipment Manual & Documents
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 89 of 99
A. Schedules
i. Are these preventive schedules as approved by DGCA
available?
a. Daily schedule
b. Weekly schedule
c. Monthly schedule
d. Six monthly schedule
e. Yearly schedule
B. Manuals
i. Are the following manuals as supplied by manufacturer
available?
a. Are all the volumes of technical manuals available?
b. Are all the volumes of operational manuals
available?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 90 of 99
C. ICAO Documents/DGCA CARs/CNS Manuals
i. Are these ICAO documents/ DGCA CARs available?
a. Annex- 10
b. CARs
c. Doc 8071
d. CNS manual
D. Log books
i. Are the following Log books available?
a. Fault log book
b. Equipment history book
c. Shift duty log book
d. General duty log book
V
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 91 of 99
I. Human resource:
A. Adequacy
i. What is the manpower requirement, for maintenance and
operation of the facility, as per approved norms?
ii. Is the same available?
iii. If not, what is the mitigation plan
B. Training & Proficiency
i. Is the staff deployed, for the operation and maintenance of
the facility, proficient on this type of equipment?
ii. Have they undergone refresher training & OJT before
deployment?
Note: Where ever required please attach separate sheets for presenting the data
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 92 of 99
EQUIPMENT ROOM / TOWER SITE INSPECTION No. Aspects CAR
Reference
Compliance Status Remarks
1. Civil
Building i. Is the approach to the building clear of grass
and other vegetation?
ii. Is the equipment building in good condition (check for breakage, leakage etc)?
iii. Is the building properly painted as per standard design pattern?
Ambience
i. Is the equipment room meeting the environmental conditions for satisfactory equipment performance? a. Temperature
b. Humidity
c. Dust-proof (check for window pane
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 93 of 99
breakage, space between the door frames
and doors)?
Frangible huts
i. In case the building is a frangible hut :
a. Is building properly sealed from all sides to
prevent entry of any reptile such as rats,
snakes etc.?
b. Is the thermal insulation in walls and roof
sufficient to meet the temperature
requirement of the equipment?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 94 of 99
2. Electrical
Earthing
i. Is the earthing of the electrical installations
ok?
a. What is the resistance of the system?
b. Name the standard being followed.
ii. Is the earthing of the equipment ok?
a. What is the resistance of the system?
b. Name the standard being followed.
Lighting protection
i. Is the lightening protection system working
normal?
c. Name the type
d. If multi-strike type give the count
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 95 of 99
Surge protection
i. Is the surge protection system working
normal?
a. Name the type and give operational
range.
Power Supply
i. Is the power supply available meets the
standard (voltage, frequency)?
ii. Which power back up system (Generator,
UPS, Battery) available?
iii. AMF panel is manual or automatic?
a. Mention the switchover time.
iv. What is the back-up period
a. UPS
b. Batteries
Cooling
i. Are the number of a/c sufficient to maintain
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 96 of 99
the temperature required for the equipment
a. Is their preventive maintenance being
done as per schedule?
b. When was the last preventive
maintenance done?
3. Fire protection
i. Are the fire extinguishers working normal
ii. Mention type of extinguisher used
iii. Are they suitably placed for easy approach?
iv. Are they tested for functionality as per
schedule?
v. When they were last tested?
4. Cabling & arrangement of CNS related equipage at tower
i. Are the cables properly layed and tagged?
ii. Is the arrangement of CNS monitoring and operational devices are in proper order and not causing any hindrance to normal
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 97 of 99
operation at tower?
iii. Is there proper access to the CNS installation at tower for easy corrective maintenance?
iv. Is the man-pack available at tower is in good working condition and its range is regularly checked.
a. Mention current range
v. Is the UPS power available for all vital facilities at the tower?
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 98 of 99
Daily activity log format Annex-1
Occurrence Resolution
Date Time
Activity/
Complaint Action taken
Date Time
Inspection check list of CNS & ATM facilities ver 4.2 21/07/10 (Signature of station in charge) Page 99 of 99
Failures and their causes Annex - 2
Facility:……………………………….. Tx/Rx………………………..
Date Duration
From To
Failure/Symptom Cause Remedial Action Remarks
DIRECTOR GENERAL OF CIVIL AVIATION
DIRECTORATE OF AS & ANS
CHECKLIST FOR CERTIFICATION OF CNS FACILITIES: MSSR
NAME OF AIRPORT
DATE OF COMPLETION OF INSTALLATION
PERIOD FOR INSPECTION
DATE
STATION INCHARGE NAME: DESIGNATION:
1 Ambience
i. Is the equipment room meeting the environmental conditions for satisfactory equipment performance?
a. Temperature
b. Humidity
c. Dust-proof (check for window pain breakage, space between the door frame and doors)?
2 Civil Works
Building
i. Is the approach to the building clear of grass and other vegetation?
ii. Is the equipment building in good condition (check for breakage, leakage etc)?
iii. Is the building properly painted as per standard design pattern?
No. Aspects CAR
Reference
Compliance
Status
Remark
Frangible huts
i. In case the building is a frangible hut :
a. Is building properly sealed from all sides to prevent entry of any reptile such as rats, snakes etc.?
b. Is the thermal insulation in walls and roof sufficient to meet the temperature requirement of the equipment?
3. Electrical Works
Earthing
i. Is the earthing of the electrical installations ok?
a. What is the resistance of the system?
b. Name the standard being followed.
ii. Is the earthing of the equipment ok?
a. What is the resistance of the system?
b. Name the standard being followed.
No. Aspects CAR
Reference
Compliance
Status
Remark
Lightning protection
iii. Is the lightning protection system working normal?
a. Name the type
b. If multi-strike type give the count
Surge protection
i. Is the surge protection system working normal?
a. Name the type and give operational range
Power supply
i. Is the power supply available meets the standard (Voltage, frequency)?
ii. Which power backup system (Generator, UPS, and Battery) available?
iii. AMF panel is manual or automatic?
a. Mention the switchover time.
iv. What is back-up period
a. UPS
b. Batteries
No. Aspects CAR
Reference
Compliance
Status
Remark
Cooling
i. Are the no. of a/c sufficient to maintain the temperature required for the equipment
a. Is their preventive maintenance being done as per schedule?
b. When was the last preventive maintenance done?
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
General Ground System Requirements
1.
Maximum range Shall have a maximum range of 256 NM.
2. Coverage a. System must provide coverage through 360 degrees of azimuth, from radio horizon to 60,000 feet, from 0.5 to 256 NM slant range.
b. Top coverage must be preserved to at least 45,000 feet at the angle of at least 45 degree above the horizontal, measured from an antenna position
3. Detection requirement Shall have a minimum detection range of
a. With GTC selected > ½ NM. b. With GTC deselected ¼ NM.
4. Reply detection Shall be capable of detecting and
processing replies from all targets having a
capability to reply with anyone of the 4096
codes.
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
5. Probability of detection a. The minimum overall probability of detection (Pd) shall be > 98% on all Targets.
b. Shall have a round reliability exceeding 90%.
6. False target report ratio The overall false target report ratio shall be
less than 0.1%.
7. Range Resolution Shall be capable to resolving two targets
that differ in range by 1/32 NM, but having
identical azimuth and identical transponder
delays.
8. Resolution capability Range resolution:
From 0 to 0.05 NM detection probability
shall be > 60%
From .05 NM to 2 NM detection probability
shall be > 98%
Azimuth resolution:
From 0 to 0.6 deg detection probability
shall be > 60%
From 0.6 to 2.4 deg detection probability
shall be > 98%
9. Range and Azimuth precision a. Range precision shall be of at least 1/128 NM at all ranges.
b. Azimuth precision shall be of at least 0.022 deg at all ranges and azimuths.
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
10. Target load Shall handle up to 900 targets per scan.
11. Correlation in the cone of silence Shall be able to maintain tracks of up to 12
targets simultaneously for correlation
between entry to and exit from cone of
silence.
12. Undesired targets Shall be capable to eliminate or suppress
any undesired phenomena such as
i. false replies (reflections) ii. garble replies iii. second-time-around replies iv. azimuth jitter v. azimuth/range splits vi. fruit vii. replies from antenna side lobes Without inhibiting the detection and
processing of desired replies within the
coverage volumes.
13. Built In Test Equipment (BITE) System shall have BITE which is capable of
continuous monitoring and automatic
changeover if the working channel fails.
14. Calibration Performance Monitoring
Equipment (CPME)
Minimum two nos. should be available
having high integrity and high reliability.
No. Aspects Reference value/ tolerance Annex/
CAR
Actual
value
Compliance
status
Remarks
Reference
15. Interrogation All Call Shall interrogate, detect and acquire Mode
A, C and S from appropriately equipped
aircrafts for operating on following
functions:
a. Mode 3/A,C,S All-Call; b. Mode A/C All-Call; c. Mode S All-Call.
16 Interrogation selective Shall provide addressed surveillance
functions and standard length
communication transactions as below:
a. Surveillance, altitude request; b. Comm A altitude request; c. Surveillance identity request; d. Comm A identity request; e. Surveillance, altitude reply; f. Comm B altitude reply; g. Surveillance identity reply; h. Comm B identity reply; i. Lockout protocols; j. Basic data protocol including:
- Flight status; - Capability reporting
k. Standard length comm. Protocols: - Comm A;
- Comm A broadcast;
- Ground initiated Comm B(DICB);
- Air initiated Comm B (AICB);
Detailed Technical Characteristics of Ground Equipment
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
1 Transmission frequency 1030+0.01 MHz
3.1.2.1.1
2 Receiver Frequency 1090+1 MHz
3.1.2.2.1
3 Transmission spectrum Shall conform to specifications shown in fig
3.2 in Annex-I
3.1.2.1.2
Power level + 4MHz from carrier
(dBc)
Power level + 6MHz from carrier
(dBc)
Power level + 8MHz from carrier
(dBc)
Power level +10MHz from carrier
(dBc)
Power level + 20MHz from carrier
(dBc)
Power level + 30MHz from carrier
(dBc)
Power level + 40MHz from carrier
(dBc)
Power level + 50MHz from carrier
(dBc)
Power level + 60MHz from carrier
(dBc)
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
4. Polarization of Sum, Control and
Reply transmission
Shall be vertical 3.1.2.1.3
Interrogation pulses characteristics
Modulation
Carrier frequency shall be pulse modulated
and P6 pulse shall have internal phase
modulation.
3.1.2.1.4
Pulse modulation: Shall conform to the values and the 3.1.2.1.4.1
tolerances given in Annex-I Table 3-1.
Phase modulation: The short and long P6 pulses internal binary
differential phase modulation shall consists
of 180-degree phase reversal of the carrier
at a 4 megabit per second rate.
3.1.2.1.4.2
Phase reversal duration < 0.08 μs
3.1.2.1.4.2.1
Phase relationship The tolerance on the 0 to 180 deg phase
relationship between chips and on the sync
phase reversal within the P6 pulse shall be
+5 deg.
3.1.2.1.4.2.2
5. Transmission power levels Provide the expected and obtained power outputs for sum and control signals at different power levels of the
systems.
No. Aspects Reference value/ tolerance Annex/ Actual Compliance Remarks
CAR
Reference
value status
6 Minimum effective radiated power
that is consistent with the
operationally required range without
creating any interference?
As per station operational requirement. 3.1.1.8.2
7 Inactive-state interrogator output
power
When the interrogator transmitter is not
transmitting an interrogation, its output
shall not exceed -5 dBm effective radiated
power at any frequency between 960 MHz
to 1215 MHz.
3.1.2.11.3
7 Spurious Signals radiation
Spurious CW radiation Shall exceed 76 dB below 1 W
3.1.1.11.1
Spurious response to signals not Shall be at least 60 dB below normal 3.1.2.11.5
within the receiver pass band
sensitivity
8. Mode A/C/S all-call interrogation
Interrogation pulses Shall conform to specification as shown in
fig 3.3 in Annexure –I
3.1.2.1.5.1.1
Pulse intervals Pulse intervals between P3 shall and P4
shall be 2 + 0.05 μs.
3.1.2.1.5.1.3
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
Pulse amplitude The amplitude of P4 shall be within 1 dB of
the amplitude of P3
3.1.2.1.5.1.4
All-call interrogation repetition rate a. Shall be less than 250 per second.
( This rate shall also apply to the paired Mode S-
only and mode A/C only all-call interrogations
used for acquisition in the multisite mode)
3.1.2.11.1.1
9. Mode S Interrogation
Interrogation pulses Shall conform to specification given in
Annex-I figure 3.4
3.1.2.1.5.2
Side-lobe suppression P5 pulse shall be used with the Mode S-
only all-call interrogation. It shall be
transmitted using a separate antenna
pattern.
3.1.2.1.5.2.1
Data phase reversals a) 16.25 μs P6 pulse shall contain at the
most 56 data phase reversals.
b) 30.25 μs P6 pulse shall contain at the
most 112 data phase reversals.
c) Each data phase reversal shall occur at a
time interval (N times 0.25) plus or minus
0.02 microsecond (N equal to, or greater
than 2) after the sync phase reversal.
d) The last chip, that is the 0.25
microsecond time interval following of the
last data phase reversal position, shall be
followed by a 0.5-microsecond guard
interval.
3.1.2.1.5.2.3
No. Aspects Reference value/ tolerance Annex/
CAR
Actual Compliance Remarks
Reference value status
Pulse intervals Between
a) P1 and P2 = 2+0.05 μs.
b) Leading edge of P2 and sync phase
reversal of P6= 2.75+0.05 μs
c) Leading edge of P2 and sync phase
reversal = 1.25+0.05 μs
d) P5 shall be centered over sync phase
reversal.
e) Leading edge of P5 shall occur 0.4+0.05
μs before the sync phase reversal.
3.1.2.1.5.2.4
Pulse amplitudes a) The amplitude ofP2 and the amplitude of
the first microsecond of P6 shall be greater
than the amplitude of P1 minus 0.25 dB
c) The amplitude variation between
successive chips in P6 shall be less than
0.25 dB.
d) The radiated amplitude of P5 at the
antenna of the transponder shall be:
i) equal to and greater than the radiated
amplitude of P6 from the side-lobe
transmissions of the antenna radiating P6
ii) at a level lower than 9 dB below the
radiated amplitude of P6 within the desired
3.1.2.1.5.2.5
arc of interrogation.
Interrogation repetition rates Mode S interrogators shall use the lowest
practicable interrogation repetition rates
for all interrogations modes.
3.1.2.11.1
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
Tolerances on transmitted signals. In order that the signal-in-space be
received by the transponder as described in
3.1.2.1, the tolerances on the transmitted
signal shall conform to tolerance as
summarized in Table 3-2.
3.1.2.11.4
11. Reply Detection & Code Detection
Mode 3/A reply detection a) Bracket detection: if F1 to F2 spacing is
20.3+0.2 μs
b) Code pulse detection: if they are at
nominal position +0.2 μs.
Mode S reply detection a) Preamble detection: If the pulse interval
from the first transmitted pulse to the
second, third and fourth transmitted pulses
shall be 1, 3.5 and 4.5 μs, respectively with
a tolerance of 50 ns.
b) If the reply data block begins 8
microseconds after the leading edge of the
first transmitted pulse.
12. Overlapped replies detection Shall be able to detect both Mode 3/A and
Mode S overlapped replies.
13. Detection of two close replies Shall be able to detect two close replies
separated by 1.75 μs.
No. Aspects Reference value/ tolerance Annex/
CAR
Reference
Actual
value
Compliance
status
Remarks
Antenna Sub System – Technical Performance Parameters
1 Central Frequency
Sum Channel : 1030+3.5 MHz and
1090+5Mhz
Difference Channel : 1090+5 MHz Omni-
directional Channel: 1030+3.5 MHz and
1090+ 5MHz.
2 VSWR
Shall not exceed 1.5:1 referred to a 50 ohm
line.
3 Cross polarized radiation
The cross polarized radiation shall be 25 dB
below the local peak.
4 Structural Strength
Shall be able to withstand a wind of 160
Km/h during operation.
A Are all the maintenance activities being performed in the unit and duly being
recorded?
Preventive
a. Daily recording of essential parameters and meter readings.
b. Weekly as per approved schedules.
c. Monthly as per approved schedules.
d. Six monthly as per approved schedules.
e. Maintenance of fault log book.
2. Is there any parameter out of tolerance for which remedial action is yet to be
taken?
3. If yes then indicate the parameter and mitigation plan?
Corrective
4. Is the manufacturer or indigenous backup support available for fault isolation
and rectification?
5. If not then what is the contingency plan in case of failure?
B Spares
1. Have the critical spares been identified?
2. Are they available (on site or depot)?
Note: If any of the above activity not required as per manufacturer
recommendation and AAI approval, the same may be notified and concurrence of
DGCA may be obtained
Equipment Manuals & Documents
A Schedules
i. Are these preventive schedules as approved by DGCA available?
a. Daily schedule
b. Weekly schedule
c. Monthly schedule
d. Six monthly schedule
e. Yearly schedule
B Log books
i. Are the following log books available?
a. Fault log book
b. Equipment history book
c. Shift duty log book
d. General duty log book
C Manuals
i. Are the following manuals as supplied by the manufacturer available?
a. Are all the volumes of technical manuals available?
b. Are all the volumes of operational manuals available?
D ICAO Documents/DGCA CARs/CNS Manuals
i. Are these ICAO documents/ DGCA CARs available?
a. Annex- 10
b. CARs
c. Doc 8071
d. CNS manual
Note: Manuals and documents should be made available at the time of inspection
Human resource:
A. Adequacy
i. What is the manpower requirement, for maintenance and the operation of the
facility, as per approved norms?
ii. Is the same available?
iii. If not, what is the mitigation plan?
B. Training & Proficiency
i Is the staff deployed, for the operation and maintenance of the facility,
proficient on this type of equipment?
ii Have they undergone refresher training & OJT before deployment?