discussion paper report - world bankdocuments.worldbank.org/curated/en/... · survey such...

78
DISCUSSION PAPER Report No. UDD-99 THE COSTS OF LAND INFORMATION SYSTEMS by Janis D. Bernstein April 1986 Water Supply and Urban Development Department Operations Policy Staff The World Bank The views presented herein are -,hose of the -uthor(s), and they should not be interpreted as reflecting those of t'e World Bank. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 23-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

DISCUSSION PAPER

Report No. UDD-99

THE COSTS OF LAND INFORMATION SYSTEMS

by

Janis D. Bernstein

April 1986

Water Supply and Urban Development DepartmentOperations Policy Staff

The World Bank

The views presented herein are -,hose of the -uthor(s), and they should not beinterpreted as reflecting those of t'e World Bank.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

Janis Bernstein is a consultant to the Water Supplyand Urban Development Department, where she has worked onurban land management issues. This paper was presented atthe World Bank Seminar on Land Information Systems,March 19-22, 1985.

Page 3: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

ABSTRACT

This paper presents an overview of the costs of parcel-based land information systems. It addresses researchmethodologies directed at analyzing and comparing costs on aninternational basis; approaches for reducing costs; andillustrative programs in Brazil, the Philippines and Canada.

Page 4: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

CONTENTS

page

I. Introduction ................................................... 1

II. Some General Observatiorns About Costs .......................... 4

III. The Multipurpose Cadastre ..................................... 12

IV. Illustrative Programs ......................................... 39

V. Current Research on Cost Methodologies ........................ 60

References. ...................................................71

Annex I: Papers Addressing Cost Aspectsof Land Information Systems .......................... 73

Page 5: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

I. Introduction

In most developing countries, the inadequacy of land

information poses a severe co-,traint on land transactions, land

consolidation, property taxation and public planning of all kinds. Due

to intensifying pressures on land for development as well as the need to

mobilize increased revenues from the property tax, governments are

investing in programs to clarify land ownership and boundaries, value

property, and in some cases, establish computerized multipurpose land

data banks. Unfortunately, thc2 investments are often not appropriate to

the limited resources available on a continuing basis and not consistent

with prevailing levels of expertise, instituitional capacity and economic

development. In manv cases, foreign consultants have recommended

advanced systems requiring high front end capital costs and extensive

external assistance. Very often these new systems have failed within a

few years because of the lack of adequate capacity to maintain equipment

and properly use and update the data outputs.

Although tnere is no international agreement on what

constitutes appropriate technologv in this field, past experience has

demonstrated that new systems should be planned so as to be efficiently

operated with existing resources plus a minimum of foreign input. The

system must also be easily understood and accepted by landowners and

users, continuously updated and cost-effective. This latter criterion,

however, is a difficult one to gauge - one of the most elusive asDects

of a land information system is a reliable estimation of cost.

Page 6: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-2-

Currently, there is no consensus among the professionals and

government officials on the costs to be anticipated in collecting land-

related data, producing maps, and introducing and maintaining the

various systems that process, store and administer them. Most of the

component costs vary according to such factors as the level of accuracy

required, the nature of the terrain to be surveyed, the density and

complexity of ownership, as well as the availability of pre-existing

information, equipment, and expertise. Each situation is-different and

it is clearly dangerous to generalize on costs from one country to

another. Conditions may vary considerably even within a country.

To make matters worse, governments rarely have accurate

figures on the total costs or unit costs associated with each element of

a particular system. The responsibilities for land information are

usually assigned to a number of agencies which do not disaggregate rosts

for land data from their total operating budgets. The agencies that do

have cost figures usually maintain records on the direct costs for

production rather than on the overall costs which account for updating,

maintenance and overhead, including training. Moreover, the available

cost figures are usually not in a form which can be meaningfully

compared to those in other countries. Research and analyses of unit

costs for specific types of land information products are almost non-

existent.

Despite the above deficiencies, reliable cost data remain

critical inputs into the planning and decisionmaking related to the

development of new or improved parcel-based land information systems.

There are many technologies, instruments and approaches through which

project planners and policy officials can build these systems, yet they

Page 7: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-3-

have limited knowledge about how to apply them in the post cost-

effective manner to meet various objectives. Decisionmakers should be

able to determine what kind of investment in land information will

produce an acceptable product with maximum benefit. According to some

experts, 90 percent of the objectives can often be achieved for a

fraction of the cost of achieving 100 percent. Program officials need

to know what are the cut-oft points, and given a very limited financial

base, what kind of an investment makes sense to initiate as a first

step.

With so many unknowns regarding the actual unit costs of land

information, it would probably require several years of research and

program monitoring to ascertain the real costs Ocr developing and

maintaining a land information system under a variety of local

conditions to establish norms. The purpose of this paper is to document

what little we currently do know about the costs of land information

systems and to suggest methodologies for improving this situation.

For convenience, the report focuses primarily on the multi-

purpose cadastre, the type of land information system which facilitates

land transactions, property taxation, land administration and various

kinds of public planning and development control. Clearly not all the

components will be relevant or appropriate to local conditions, needs

and resources in difterent places at different times. Moreover, the

costs are no more than illustrative. They represent estimated or actual

costs of programs serving the particular purposes of individual

couuntries and the particular conditions prevailing. They cannot be

readily applied to the calculation of costs for programs elsewhere.

Page 8: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-4-

The paper consists of five chapters. It begins with some

general observations about the costs of building a multipurpose

cadastral system, including approaches to cost reduction, and

suggew.tions for further research. Chapter three discusses the unit

costs associated with the geodetic network, base mapping, cadastral

surveys, land values and other parcel data, the land data bank and

system maintenance and updating. Chapter four presents a discussion of

tine costs of four illustrative programs. Chapter five briefly notes

curcent research on costs and methodologies for analyzing or estimating

unit costs. An annex of selected reports for further research related

to costs has also been prepared. This paper is an initial effort to

survey such information as is readily available. If it stimulates

further discussion and work in this field, it will have achiLVed its

principal purpose.

II. Some General Observations About Costs

In most developing countries, the authorities responsible for

various Kinds of land information, e.g. land ownership, spatial data,

and land values, are located in different ministries which maintain

separate, yet often similar types of land records. To reduce

duplication of effort, there has been a Lrend in recent years toward

integrating these data bases through the development of multipurpose

cadastres. The modern multipurpose cadastre is a form of land

information system which contains data on the legal, physical, fiscal,

economic and other aspects of land parcels. The building of such a

system involves the design and implementation of a series of

Page 9: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

interrelated legal, administrative, and technical operations necessary

for data acquisition, processing, storage, administration and system

maintenance and updating.

As previously noted, it is impossible to predict accurately on

the basis of existing information how much a multipurpose cadastre will

cust. The cost of any particular project will always depend not only on

the land area covered and number of parcels, but also on the extent of

existing data, staff resources, expertise, equipment, and local land

conditions, i.e., density, terrain, complexity of land ownership. OL;aer

influences on cost include the nature of the existing land institutions,

the legal tramework and public attitudes toward land and title

registration. The range of costs of the projects reviewed has been from

several million to tens of millions of dollars. A review of the

literature and illustrative programs as well as discussions with experts

in the field suggest that one can expect the unit cost for a modern

multipurpose cadastre to range from about $5 to $25 per hectare for

ruraL land and from about $60 to as high as $9,000 per hectare for urban

land.

The $9,000 per hectare cost is the highest price encountered

in tnis investigation. It was derived from the cost calculations

prepared by Francois Brun of the Institut Geographique National (France)

for a hypothetical multipurpose (legal, technical, fiscal) cadastre

project using state of the art technologies. The costs below are those

which would apply in an industrial country. They account for all

necessary operations from project appraisal through project

completion. The man-month rates include overhead, administrative costs,

equipment, office accommodation, etc. For professional services, the

Page 10: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-6-

cost is $8000/month. The cost for a technician (survey,

administrative/legal and fiscal) is $6000/month and for a laborer,

$1000/month. The project area is about 1000 hectares and assumes 23

plots per hectare. There are pre-existing formal rights (titles and

deeds) and customary rights. The table is included here to illustrate

the types of activities and costs associated with the establishment of a

modern land information system. This particular system covers: the

densification of the geodetic network, base mapping, land adjudication,

cadast' ;l survey and mapping, collection of fiscal data, and the

building of a land data bank. The total cost of the project is $8.9

million; the unit cost per hectare is $8,950 or $390 per plot.

Page 11: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-7-

Breakdown of Project Costs for HypotheticalMultipurpose (Legal, Technical, Fiscal) Cadastre

Staff DurationProject Stase Reauirements (Months) Cost

1. Project Appraisal 1 Expert 3 324,000Analysifof Existing -

Conditions, Definitionof Major ProjectComponents

2. Preoaration of ProjectImplementation Plan 3 Experts 3 S72,000Definition of Insti-tional, Legal, Fiscaland Admin. Framework;Prepare Terms of Referencefor Project Execution

3. St T'' Training 3 ExDerts 3 S612,000Trainiing in Tooo/Cart, 9 TechniciansAdmin./Fin./Law, and (3 Survey, 3Taxacion for Existing Admin./Legal,Technic-ans in & 3 Fiscal)Cadascral Depts.

4. Preliminarv Publicitv 550,000Media Presentacion andAdvertising on ProjectScope, Phases, and PublicRights and Obligations

:. Suoolementary informationbv Town Ouarters 1 Professional S20,000Dissemination of 2 Technicians ($2,000/ha)information Through (Survey, Admin.'Direct Contact Legal)

6. Preliminarv rnformationF;athering I Professional 58 $1,160,000Identification of 0wners, 2 Technicians ($1,160/ha)Houses and Rights (Survey, Admin./

Leeal)

7. Base YapoineAir Photo at 1:5000 S30,000Densification ofGeodatic Network andLevel $38,000Digital Mapoing at1:500 Incl. Stereoplotting,Field Completion andVerification S240,000

S 308,000($308/ha)

3. Cadastral Surve_yAdjudication, MonumentatronEvaluation 1 Professional 92 $6,152,000Rate of 6 Plots/Day :for 29 months)

3 Technicians(Admin. /Legal,Survey, Fiscal)2 Laborers

3. Preoarat:on nf CadastralMaos and Revisters 1 Professional 96 S1,968,000integration of Cadastral (for 30 months)Field Survey into Digital 3 TechniciansAir Mapping, Building (Survey, FiscalFiles of Owners and Admin.iLegalProperties, IncludingLegal and Fiscal AsDects-xecuced at Rate of12 Plots/Day

;0. Verification AeainstOfficial Documentation 1 Professional 53 $396,000axecuted at Rate or (for 6 months)' Fi'es/Day I rechnician(Assumes thac 10% cfthe plots have t4tlesor leeds with recoenizedleeal value and thatfi'ing system is ofvery poor quality)

U. Litigation Sertlement 15 $180,000A Comoecent CourtSectles . Disputes/DayAssumes that the claimand JisDute oercentage-s .)

Page 12: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-8-

A system such as that Jpst described would be highly

inappropriate in mcost parts of the world (given the low economic and

individual levels as well ar', the need to accommodate the unprecedented

growti' rates. in the urban areas of developing countries. Governments

cannot afford to invest in systems that require sophisticated equipment

which cannot be operated and maintained by existing staff, nor can they

afford to pay excessive costs for surveying the land of households in

whicL. the per capita income averages $270, as is the case for about half

of the world's ponulation.

To ensure that the development of new systems are more

appropriate to local conditions in developing countries, project

planners should design systems in whic!t the cost of surveying, mapping

and documenting a parcel is closely related to the value of the land.

One rule of thumb is that costs should be about 2 percent of the value

of tne land. AS a maximum, the cost should not exceed five percent.

Any system costing more than 5 percent of the land value is almost

certainly excessive and should be modified through various cost

reduction approaches, such as the ones briefly cutlined below.

One traditional approach to cutting costs is to reduce the

inputs into a system in order to produce a less expensive product.

Thus, accuracy requirements c? n be reduced and the use of less

sophisticated instruments and techniques should be promnoted as long as

the result is sufficient for legal purposes. For example, where

appropriate, rectified photomaps are less costly alternatives to

orthophotomaps. In certain situations, the unrectified aerial

photograph itself may be sufficient for titling purposes. The

emnployment of non-professional surveyors without expert supervision to

Page 13: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

-9-

perform various types of cadastral surveys should also be considered.

In the boundary demarcation process, considerable savings in time and

money can be accomplished through the reduction of the number of

boundary markers needed for each parcel. It is not always necessary to

implant new boundary monuments in each corner of a parcel when existing

markers such as fences, trails, trees are already accepted. In one

country, the cost for concrete monuments at the corners of outside

perimeters increased the overall cost of surveying and mapping by nearly

100 percent. In addition, project officials might solicit the

cooperation of private landowners for the clearing of bushes and shrubs

in anticipation of boundary demarcation. They might also ask landowners

to agree among themselves on parcel boundaries before the land

adjudication takes place.

Anothei approach to cost reduction is to introduce measures to

improve production. For large-scale programs, the use of new

technologies such as inertial surveys and GPS may be appropriate.

Photogrammetric techniques have already proven their cost efficiency for

a number of applications, particularly base mapping. However, in order

to use these technologies to the best advantage for cost reduction and

greater speed in executing the surveying and mapping operations, a

country must demonstrate sufficient in-house expertise, staff resources

and continuing commitment to the program.

Where conditions are rigtit, e.g. reliable supplies of

electricicy, availability of repair services, training etc., the

introduction of computers can substantially increase the cost efficiency

of new systems, particularly when new data can be directly fed into the

computer and there is a minimum amount of existing data to be converted

into machine readable form. Although the costs of digitized mapping may

Page 14: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

be excessive for many developing countries, the use tf micro-computers

for processing, storing and updating non-graphic legal and fiscal data

can provide significant savings in many situations.

Another approach to cost savings is to target special areas

for surveying and mapping programs. When financial resources are

scarce, policy makers should select areas where these programs can bring

the most beneficial results. For example, a land registration program

facilitating potentially high revenue--producing development will be more

economically beneficial than a similar program carried out in squatter

areas. For the latter, it may be more appropriate to document the land

through less accurate low-cost aerial surveys as needed for project

purposes.

Lastly, considerable savings can be achieved when new survey

and mapping programs are planned so as to be compatible with the

requirements of a maximum amount of users. In the planning of new

systems, program planners and policy officials should ensure that all

agencies involved in large-scale mapping and cadastral surveys for legal

and fiscal purposes are involved in the determination of scale and data

requirements. For maximum cost-efficiency, they should consider the

development of a multipurpose cadastre whicht relates all parcel-related

data in a jurisdiction, and wherever possible, is linked to or

compatible with other land data bases within the larger region or state.

To develop cost-effective systems appropriate to developing

country conditions, project designers and policy officials need to

consider costs and benefits of alternative approaches and standards ot

accturacy. To accomplish this satisfactorily, however, requires more

information than is presently available on the costs of difterent

Page 15: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

technologies and procedures, as well as the economic benefits of the

different kinds of systems and approaches. With such information, they

would be better equipped to deal with the various cost trade-offs

encountered in the design of new systems. More importantly, they would

be better able to: build optimum systems suited to the needs and

available financial and technical resources in each situation; assess

the cost-effectiveness of new procedures and technological advancements;

make more accurate estimates of project costs; compare program costs to

those in other countries; and monitor actual implementation.

In conclusion, there is a great need for coordinated research

among international organizations and training institutions focusing on

the economics of land information systems. As a start, efforts should

be directed at the establishment of standard methodologies for analyzing

and estimating the costs of all aspects of land information systems

which can be compared on an international basis. For the developing

countries, where tne need for low-cost solutions is critical, research

and experimentation should be directed at the development of inexpensive

replicable approaches to identifying the minimum data requirements for

meeting the most essential user needs, and utilizing technologies and

procedures which can be operated and maintained with limited

resources. The initiation of pilot programs will provide the best means

for determining costs and standards under different local conditions.

Lastly, the agencies and individuals involved should establish a network

through which the research findings and other developments in the field

can be disseminated and incorporated into future work.

Page 16: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 12 -

III. The Piultipurpose Cadastre

The basic elements of a modern multipurpose cadastre are a

geodetic reterence frameworkc, a series of large-scale maps (1:500 -

1:25,000) showing major man-made and natural features, a cadastral map

or overlay delineating property boundaries, a unique identifier assigned

to each parcel, and a register or series of registers containing parce-'

based information about the ownership, value, land use and other

actributes of the land in a jurisdiction. This chapter addresses the

cost considerations for the principal elements of a multipurpose

cadastre in which the legal register is the most important component.

They include the geodetic reterence framnework, base mapping, caaastral

surveys and mapping, land valuation, the land data bank and system

maintenance and updating.

Geodetic Reference Framework

The geodetic reference framework is the spatial foundation for

the multipurpose cadastre. It consists of monumented points whose

horizontal and vertical positions and interrelationships have been

accurately determined by field, photogrammetic or other techniques.

Typically, the distance between monumented points ranges from .2 to .5

miles (.3 - .8 km) between monuments in urban areas and I to 2 miles

(1.6 - 3.2 km) in rural areas.1/

The establishment of a control inetwork is an expensive

process. In order of the least capital cost, the following are

1/ National Academy of Sciences. Procedures and Standards for aMultipurpose Cadastre, 1983, pp.23-24.

Page 17: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 13 -

alternative techniques for ground control: (1) triangulation,

trilateration or traversing using theodolite and electromagnetic

distance meters (EDM); (2) photogrammetric densification; (3) inertial

surveying techniques; (4) Satellite Doppler surveys; and the (5) Global

Positioning System.A/ which is expected to be fully operational by about

1989. Using a conventional field method (e.g. triangulation and

traversing with theodolite and EDM), the cost ranges between about $500

to $1,500 per point according to thie required accuracy.2/ In general,

the cost for control surveys by field techniques account for one quarter

to one third the cosc of the finished naps. The costs of the newer,

more sophisticated methods are discussed separately below.

Inertial Survey., Inertial surveying (ISS) is a means for

densifying control within an existing geodetic network. Using cars or

helicopters for the determination of x, y and z coordinates, the method

can achieve an accuracy ot 1:20,000 or 5 cm. over 1 kilometer. Although

tnere will be slight variations in cost under different conditions, the

followiuig estimates show cost comparisons between inertial and

conventional surveying (ground traversing with theodolite) for the

densitication of a primary geodetic network in developing countries.-/

1/ holstein, Lynni. The University of New South Wales, New SouthWales, Australia, March 1985.

2/ Kulick, Gary. Nortech Surveys. Arlington, Virginia, February1985.

3/ Kulick, Gary. Nortech Surveys. Arlington, Virginia, February1985. Based on experience in Egypt, Ethiopia, Nigeria,Philippines, Tanzania, Tunisia, and Zimbabwe, among othercountries.

Page 18: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 14 4

Costs Per Point

Inertial Conventional

Second Order fIl $750 - 1,000 $1,000 - 1,500

Third Order I2/ 400 - 650 600 - 1,000

II3/ 350 - 500 500 - 750

(Note: Air freight and transportation costs are not included in the

above estimates).

Developing country governments generally do not purchase the

very costly equipment required. Instead, a toreign contractor wouid

provide the equipment and at Least two highly trained and experienced

technicians to train indigenous personnel and provide project

guidance. Project duration and locations influence personnel

requirements. In general, however, about six to twelve people are hired

and trained for a project. A typical project lasts for one to two

months during which time about 800 to 1,000 points are established.

The required training time differs according to prior survey

or electronics experience of the individuals concerned. For example, an

individual with a fundamental knowle%dge of these fields will require

approximately two weeks of supervised training for a cost of about

61,000 - 1,500. An individual with no prior experience will require

1/ horizontal accuracy of 1/20,000 and vertical accuracy 1.3 mm.

2/ Horizontal accuracy of 1/10,000 and vertical accuracy of 2 mm.

3/ horizontal accuracy of 1/5,000 and vertical accuracy of 2 mm.

Page 19: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 15 -

approximately four to eight weeks of supervised training to be able to

generate i:e'.able field data. The estimated cost for this training is

$2,700.1/

Satellite Doppler Positioning System. In terms of cost,

accuracy and timeliness, the Satellite Doppler Positioning System

competes with conventional surveying for the establishment of the

primary geodetic network. Using the most advanced observational

procedures and precise methods of data reduction, the system can produce

accuracies on the order of 10 to 20 cm. (0.33 to .66 ft.) for relative

positioning ot stations separated by up to 100 km. (about 60 miles). To

achieve these accuracies, the system requires substantial capital

investment in technology. For example, to establishi a primary geodetic

network of 18 stations within a typical countrywide area at accuracies

on the order of 10 cm. (.33 ft.), the following would be required: a

pair of base stations established at convenient points with*in the

existing primary net; two mobile units, each occupying a designated

station tor a period of 4-5 days; and the field work, which would be

completed within a month. When stations are separated by 10 km. (about

16 miles), the system can produce proportional accuracies of

1/100,000. For stations separated by 50 km. (approx. 30 miles)

proportional accuracies can oe 1/500,000. The cost of this type of

survey can be about $75,000 or about $4,000 per station. Approximately

$50,000 would be allocated to field work and $25,000 would he allocated

1/ Kulick, Gary. Nortech Surveys, Arlington, Virginia. February1985.

Page 20: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 16 -

to data reduction, which could be completed within 60 days after the

field work.l/

Global Positioning System. The Global Positioning System

(GPS), when fully operational, is expected to determine relative

positions with 1 to 2 cm. accuracies in all-weather conditions over 100

km. or less within a few hours. The system will increase productivity,

reduce costs, and produce accuracies equal to or greater thian those of

conventional surveying. As of 1983, a receiver costs $100,000. This

price, however, will decrease as equipment comes into more widespread

use.2/ In late 1985, the cost is expected 'to be about $50,000.3/The

costs are generally in the range of $1,500 - $2,000 per point for first

order accuracy.-4/

Photogrammetric triangulation or aerotriangulationi. Aerotri-

angulation is an alternative to or used to supplement conventional tield

surveying when there is an existing primary geodetic network. It is the

process by which horizontal and/or vertical control is extended over an

ares by overlapping (at least 60 percent along strips and 20 percent

across) pairs of photographs. A small number of points previously

surveyed on the ground serve as a framework within which all other

points on the photographs are established through an interpolative

1/ NAS, Procedures and Standards for a Multipurpose Cadastre,1983, pl. 32-33.

2/ National Academy of Science, Procedures and Standards for alultipurpose Cadastre, 1983, pp.33-34.

3/ Holstein, Lynn. The University of New South WVales, New SouthWales, Australia, March 1985.

4/ Kulick, Gary. Nortech Surveys. Arlington, Virginia, February1985.

Page 21: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 17 -

process based on measurements or the coordinates of film images. When

projects require a moderately high density of points, aerotriangulation

is a cost-effective alternative to ground surveys, including ISS The

process can produce almost any desired accuracy and can provide as much

as a 3-to-I cost advantage over first order ground traversing.-

Photogrammetric triangulation as well as the satellite

positioning systems, inertial surveying, and GPS, are costly, capital-

intensive techniques. Once introduced, however, they can save an

enormous amount of field work, time and money, and produce large volumes

of data in a shorter period of time than conventional field

techniques. Ettective implementation requires statt with extensive

relevant experience and training to run them. To introduce the advanced

systems in a developing country, factors such as the purchase price for

hardware, required skilled manpower, and the loss of jobs for less-

skilled personnel who would otherwise be involved must be considered.

Whatever method is used, the control surveys should be undertaken

systematically and planned so as to benefit a maximum number of users.

Thus the points would be used for cadastral, topographic and engineering

purposes. All surveys would be tied to these marks.

Base Mapping

Within the context of a multipurpose cadastre, the large-scale

base map constitutes the graphic framework within which the locations of

cadastral parcels, political boundaries, and important natural and man-

made features can be related to the geodetic reference network. It also

1/ National Academy of Science. Procedures and Standards for theKultipurpose Cadastre, 1983, p.29.

Page 22: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 18 -

provides a means by which all land-related information may be tied

graphically to cadastral parcels. In many countries, photogrammetric

techniques provide a quicker and more cost-effective approach to base

mapping than conventional ground compilation methods.

Photogrammetry is the method by which measurements of land are

made on photographs. The basic stages are the flying of the aerial

photography, provision of ground control, stereoplotting and

cartographic processing. In order of the most simple and inexpensive to

the most elaborate and expensive, the final map products include the

enlarged unrectified air plhotographs, rectified photomaps,

orthophotomaps and line maps. With respect to the orthophotomap and

line map, there is a cost ratio of about one to three-I/ Rectified

photomaps are less expensive than orthophotomaps, but they can only be

used when the terrain is relatively flat. Photogrammetry is most cost-

eftective when the number of points to be measured are great, the detail

to be plotted or digitized is dense and the area to be surveyed is large

and covered systemmatically. The greater the required precision,

however, the higher the cost since larger-scaled photographs are

required and thus a larger number or photographs are needed to cover an

area.

Aerial photography. The most important factors influencing

the cost or acquiring the aerial photography are the flying height,

terrain, distaLnce to nearest airport, availability of gasoline, local

weather conditions affecting flying time and the type of aircraft

1/ brun, Francois. Institut Geographique Nationale, December1984.

Page 23: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 19 -

used. Jerie and Holland list the full range of factors influencing

production rates for aerial photography and che acquiisition of other

primary lanid data.i/

Aerial Photography Acquisition

Factors influencing production rates.

A. Factors appertaining to the PRODUCT SPECIFICATION

A 1 Size and shape of project area2 Photo scale3 Flying and navigation specification and tolerances4 Image quality specification and tolerances5 orientation Data / Auxiliary Data specification and tolerances

B. Factors appertaining to the PROCESS SPECIFICATION

B 1 Type of survey aircraft2 Type of aerial survey camera3 Type of navigation sysi:em4 Flying height5 Flying pattern (inc. coastal and cross strips)6 Ground control and signalisation7 Processing of aerial film (local facilities, method and equipment)8 Type of auxiliary equipment9 Method of processing orientation Data / Auxiliary Data

C/D ENVIRONMENTAL FACTORS:

C. Factors appertaining to the PROJECT AREA

C 1 Geographic position: absolute position of local base with respectto executing organizations home airfield

2 Position of target area with respect to local base3 Meteorological and climatic conditions4 Topographic characteristics5 Communications situation6 Air traffic control situation7 Fuel situation8 Security situation9 Maintenance situation

10 Local political/administrative situation

D. Factors appertaining to the EXECUTING ORGANIZATION

D 1 Skill, motivation and productivity of staff (inc. efficiency ofmanagement)

2 Experience in operational conditions.

I/ Jerie, H.G. and Holland, E.W. Cost Models for PhotogrammetricProcesses. Invited Paper for Auto Carto 5/ISPRS Commission IVSymposium, Crystal City, Virginia. August 1982, p.10.

Page 24: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 20 -

In general, the aerial photography is a relatively inexpensive

part of the process of surveying and mapping. It may account for

between five to fifteen percent of the cost of the photogrammetric

operations. It is import ant, however, that the photography is timely,

flown during the most favorable season by skilled operators, and

produced at the precise scale selected. For most purposes, the scale of

the aerial photograph acquired is three to five times smaller than the

scale ot the maps to be produced. The following compares costs of

aerial photography tor an area of 34,225 km2 (185 km x 105 km) at

different scales.-L/ As indicated, the cost for greater accuracy

iaicreases by about the same factor as the increase in scaleQ.

1;25,000 1:50,UOO 1:100,000

No. of strips 41 + 1 (42) 21 + 1 (22) 11 + 1 (12)No. ot photos/strip 81 + 4 (85) 41 + 4 (45) 21 + 4 (25)No. of photos 3570 990 300No. of flight kms 7770 4070 2220

Photographic costs2/(at $5 per photo) $17,850 $4,950 $1,500

3/Flying costs-/(at $25 per line km) $194,250 $101,750 $55,500

Total costs $212,100 $106,700 $57,000

Cost (per km2) $6.2 $3.1 $1.7

1/ Kure, J., ITC, Enschede, The Netherlands, September 1984.

2/ Assumes only paper print required tor photo-interpretationpurposes.

3/ Flying costs per line km vary according to type of aircraft(range, speed), location of project area from air base andespecially wearher conditions.

Page 25: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 21 -

Stereoplotting. Based on the research of Jerie and Holland

for the ITC/OEEPE Cost Modelling project, production rates for

conventional stereoplotting vary widely among the production

organizations which were asked to provide cost data for different

terLrain standards. According to their findings, there can be a factor

of 20 in production estimates (contouring rates) depending on whether

the terrain is open or dense; the average variation is about 10 times.

Moreover, the different private and public organizations estimating

rates for the same terrain sample can vary by a factor of 60; the

average variation is nearer to 20 to 30 times.l/ The following lists

the factors influencing production rates.2/

1/ Holland, Eric. ITC. Enschede. The Netherlands, December1984.

2/ Jerie, H.G. and Holland, E.W. Cost Models for PhotogrammetricProcesses, 1982, p.9.

Page 26: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 22 -

STEREO PLOTTING: INFLUENCING FACTORS

Factors influencing production rates.

A. Factors appertaining to the PRODUCT SPECIFICATION

A 1 Size of project area2 Map scale3 Sheet size, lay out, no. of separate traces, projection4 Map content, symbols, generalization5 % completion required6 Planimetric accuracy7 Amcunt of annotation required8 Contouz. VI, Spot heiyht/DGM/Profile spacing9 Height accuracy

B. Factors appertaining to the PROCESS SPECIFICATIONB 1 Type and distrihution of ground control (inc. signalization)

2 Amount of minor control/auxiliary data3 Type of aerial photography4 Photo scale(s)5 Model scale (relative to photo scale)6 Manuscript scale (relative to model scale)7 Pype of stereo plotting equipmentS Type of computer hardward and peripherals9 Type of computer software

10 Amount of photo interpretation at stereo plotter11 Method of plotting and type of output (graphical)12 Method of digital plotting and type of output13 Method of DGM data capture14 Method of relative orientation

C/D ENVJIRONM.ENTAL FACTORS

C. Factors appertaining to the PROJECT AREA

C 1 C,uant tazive aspectsa. topographic (height diffs, steepness/slopes)b. density of natural featuresc. density of cultural features

C 2 Qualitative aspectsa. terrain roughnessb. surface characteristics (swamps, deserts, etc.)c. vegetation coverage (trees, grass, crops)

D. Factors appertaining to the EXECUTING ORGANIZATIOND 1 Skill, mot:ivation and productivity of staff (inc. efficiency ofmanagement and oraanization)

E . DERIVED FACTORS

E 1 Quality of ground control2 Quality of aerial photography3 Quality of aerial triangulationi4 Quality of map sheet preparation5 Quality of pre-plotting interpolation6 Quality of plotting

Page 27: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 23 -

Illustrative Base Mapping Program. An extensive urban mapping

program is currently being carried out in Indonesia. The program is

designed to produce large-scale photogrammetric base maps covering about

100 large (10,000 hectares), medium (3,000 hectares), and small size

(1,500 hectares) cities to support the government's national programs to

expand basic urban services. The aerial photography is being flown at

750 meters above the ground using 153 mm cameras to produce 1:5000 scale

aerial photos and subsequently 1:1000 scale photomaps with superimposed

one meter contours and vertical accuracy to 0.2 meters on spot

elevations_./ The program will also produce a 1:250,000 scale map of

L,ie island of Java, based on color edge-enhanced Landsat imagery and

corrected to a UTH grid. The latter would provide base data for the

planning and acquisition of urban aerial photography. The following is

the cost breakdown for the $9.5 million mapping program-2/

US$ Million

TMonumenting .13Vertical aerial photography 1.86Mappinga. Ground control 1.42b. Aerial trianguLation .92c. Ortho photo scanning .48d. Rectification .28e. Contouring/spot heights 1.17f. Cartography .50g. Automated cartography .05h. LANSAR base map-Java .04

Project management 1.00File .06Price contingencies 1.00

1/ Orthophotomaps, rectified photomaps or even line maps will beproduced depending on the terrain. The contour sheet will notalways be produced, especially where the terrain is flat.

2/ Staff Appraisal Report, Fourth Indonesia Urban DevelopmentProject, March 16, 1981, (Report No. 31232A-IND) p.68.

Page 28: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 24 -

In addition, the project includes 80 man-months (US$1 million) ot

foreign consulting services, eighteen man months of which would be

allocated to the national agency responsi.ble for matching the needs of

individual agencies to available mapping capacities and integrating the

urban mapping work with other government mapping projects.

The Indonesian government appointed approved Indonesian

companies to carry out the surveying and mapping operations. The

following chartsl/ show the estimated timing for the photomapping of the

large, medium and small size cities.

1/ hunting Surveys & Consultants, Ltd. Urban IV Mapping AdvisoryTeam Inception Report, June 1982.

Page 29: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

ESTIMATED TIMING FOR THE MAPPING OF A LARGE CITY.ORTHOPHiOTO

Weeks 10 20 30 - 40 5;

Photo./Surv.fMapPig Q'TY .2.3.4.5.6.7.8.9.0..2.3.4.5.67.8.9.01.2.3.4.5.6.7..9.01.2.3.4.5.6.7.8.9.0..2.3.4-5.67.8.9.. 2

Aerial photography 260 '_______________***_____e____**_____t1______________________.Delivery of 'hotos rt-

Rec. Monumnent n * 3 0 a I a a a | * * * * * * * , * * g a a * | * * 5 ' 5 5 s a a 5

r ve S ng 65 __ _ __ _ _ __ _ _

L e e l n 1 2 0 ' '_ _ _ _ _ _ _ _ _ _

Co .~ Documenet'n U _ _ _ _ _ _ _ _ _ _

Photo Preparation a , * * , ,

Triaonguation L Adj. 250

Con~touring 240 ______

Orthophoto 450

Rectifi^atior. -Cartogr aphy 450 .___ ._._. ._._--_.__._._.________________ ____________________

Reproduction 1450_._*_._*_*_._*_._ _*_._._._._,_._._._. . . . . . . . .____,

Quantity unit for aerial photography and surveying is in line Km.

preparation, aerial triangulation, contouring and orthophoto is in Models.

5 ' "rectification, cartography and reproduction is in no. of sheets.

1 Traversin.g team ( Surveyor + Ass. )/ contract 9 weeks/team.

1 Levelling team 12

2 Survey calculator " " u6

1 Point transfer device. working 1 shift/day/inst. 7. weeks/inst.

1 Precision plotter 4 recorder. " 1 8.3 or, 1 Precision plotter + recorder.

1 First order plotter. 2 r U U 19. W Jorking 3 shifts for 16 veeks

- Rectifier. -- U U U

1 Orthophoto. 3 25.

2 cartographic team (3 draftsmen each) U 40 hours/week/pers 19. weeks/team.

2 Laboratory (1 laboratorian + 1 ass. each). 40 U U U 1 U

1 Operator for general preparation. 40 U u U 25. U U

Page 30: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

ESTIMATED TIMING FOR THE MAPPING OF A MEDIUM CITY.

Weeks 10 20 30 40 50

Photo./Surv./Mapping Y1.2.3.4.5.6.78.9.0.1.2.3.4.5.6.7.8.9.0.1.2.3.4.5.6.7.8.9.0.1.2.3.4'.5.6.7.8.9.0.1.2.3.4.5.6.7.B.9.0.1.2.

Aerial photography 85 .___ . .__ . ,.___* .___* *___. *___._._____. * __._____* .__* ..__

Delivery of photos # * a a a a a a a a a a a a a a a a o a a a a a a e r a a a a a e a a a S S a i S a a a

Rec. L Monument'n 16 a , , , , , .' a a a a a a . a a a a a a a a a a .... a t a e a a a a a a a a a

Traversing 30 a|a_a_A_ _ _|_._|_,, ,||

L-evelling 60 aaa aaaaa

Comp. L Document'n a a a a a a a a a a a a a a a ' ' a a a * a a a a a a a a a a a a a a a a a a a

Photo Preparation a a a a a a a a . a a a a a a a a a a a a a a a a a a a a a a a a a a a a a a a a a a a

Triangulation 6 Adj. 8o a a * a a * a a a a a a a a . a a a a a a a a a a a a a a a a

Contouring 75 a 0

_ _

Orthophoto 140 a

Rectification 140 a ..

Cartography 140 . * . .-* *

Reproduction 140 . . . . . - ' '_*.___..* .. .

Quantity unit for aerial photography and surveying is in line Km.

S 4 preparation, aerial triangulation, contouring and orthophoto is in models.

. " "rectification, cartography and reproduction is in no. of sheets.

1 Traversing team ( Surveyor + Ass. U/ contract 5 weeks/team.

1 Levelling tearm a, 6

2 Survey calculator a' n 4 'a

1 Point transfer device. working 1 shift/day/inst. 2.2 weeks/inst.

1 Precision plotter t recorder. 1 " n 2.6 or, I Precision plotter + recorder.

1 First order plotter. 2 a ' a. 6.2 Working 3 shifts for 5 weeks.

1 Rectifier. " 2 " 5.8

1 Orthophoto. ' 3 7 .as 7 U U

2 Cartographic team (3 draftsmen each) ' 40 hours/week/pers. 5.8 weeks/team.

2 Laboratory a (1 labo':atorian + 1 ass. each). ' 40 ' ' 4.E s -

1 Operator for general preparation. n 40 S a 8 . '

Page 31: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

ESTIMATED TIMING FOR THE MAPPING OF A SHALL CITY.

Weeks 10 20 .30 ;40 50Photo./Surv./Mapping Q'TYWek 02.3405| ilpotrpy|4 1. 2;3.4. 5.6. 7.8.'9 01. 2* 3. 4. 5.6.7.h8.9. 0.l.2. 3. 45.6. 7.8.9.0. 1.-2. 3. 4.5.6.7.B. 9.0l.1.2. 3.4.5.6.7.9.9.0j.1.2.

Aerial photography 48 aaaaa aaaaa.*aaaaaaaaa 6

IJelive of h tos ga aa a a a a a a a a a a a a a a a

Rec. & Monument'n 10 * t a a | a a aTraversing 20_________

Levelling 30 _ _ _ _ _ __ _ _ _ _ __ _ _ _ _ _ _

Comnp. & Documnent'n- -- aa aa__

Photo Preparation S 3 a * a a a a a a a a a a a a a a a a a a a a aaTriangulation S Adj. 60 | * S * * a a a a X a a a a a ' a a * * * a a a a a a * S S * * * S a a a a a *Contouring 45Orthophoto 75Rectification 75 _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ __ _ _ _ _ _ _ _ _

Cartography |75:

Re roduction 7

Quantity unit for aerial photography and surveying is in line Km."i " preparation, aerial triangulation, contouring and orthophoto is in models.

" " rectification, cartography and reproduction is in no. of sheets.

1 Traversing team ( Surveyor + Ass. )/ contract 4 weeks/team.1 Levelling team n4 m

2 Survey calculator a a " 3 n

1 Point transfer device. working 1 shift/day/inst. 1.6 weeks/inst.1 Precision plotter + recorder. a 1 ' ' 2 or, 1 Precision plotter + recorder.1 First order plotter. h 2 3.7 " W Working 3 shifts for 3.2weeks.1 Rectifier. n 2 3.11 Orthophoto. - 3 " n n 4.12 Cartographic team (3 draftsmen each) n 40 hours/week/pers. 3.1 weeks/team.2 Laboratory 0 (1 laboratorian + 1 ass. each). n 40 U U U 2.5 "

1 Operator for general preparation. 4 a as 5,

Page 32: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 28 -

Cadastral Survey

A cadastral survey consists of three interrelated operations:

land adjudication, demarcation, and the survey and recording or the

parcel boundaries. For a comprehensive cadastral survey program, per

parcel costs vary according to such factors as the complexity of

ownership, size of parcels, quality of base maps, quality of previous

local surveys and records and the accuracies required. Typical

accuracies are 1-2 feet for rural areas and .1 foot for urban areas.

For the Cadastral Survey and Registration Project in the Caribbean, the

average unit cost was L30 (about US$75 in 1974). The percentage

breakdown of costs for this project is presented below.- /

Estimated Percentage Costs 1972/1973

Operation

Administrative overheads (includes training and

supervision of staff 12

Demarcation 28

RPecording 14

Survey 40

Adjudication of Disputes/Petitions 6

100

1/ The average unit cost of L30 per parcel included preliminaryclerical and field work to process claims for an averageparcel, investigation of title, and display period foradjudication records and index maps. Howell, L.J. TheCadastral Survey and Registration Project in the Caribbean,Chartered Surveyor, Land Hydrographic and Minerals Quarterly,1974 Vol. 1, No. 4, p. 57.

Page 33: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 29 -

Land Adjudication. Land adjudication is the official

determination of the rights and boundaries of a land parcel. Generally,

this ascertainment of rights in a land parcel is not an expensive part

of the entire process of compiling a register. According to Lawrance,

the procedures should cost no more than 15 to 20% of the total cost,

although there will be variation between countries. Moreover,

systematic adjudication is quicker and cheaper per parcel registered

tthan sporadic.adjudication.1/ For sporadic adjudication, an individual

parcel is usually surveyed by expensive ground methods. In the process

of adjudicating one parcel, the rights of the adjoining parcels are also

ascertained but not necessarily registered. At a later time, however,

wheni the adjoining parcels require documentation, a survey team will

have to return to the same area to resurvey the parcels. Thus, for

maximum cost-effectiveness, among other reasons, systematic adjudication

should be the preferred method under most conditions.

Boundary Demarcation. According to Dale, the single most

important aspect of cadastral survey for title purposes is the boundary

demarcation. The process of marking a boundary is always undertaken on

the ground and corresponds to the results of the adjudication

exercise. Monuments may be a concrete peg, fence post, mark on a wall,

or be an actual physical boundary marker such as the river bank or the

fence itself. In the course of development, however, many of these

marks are lost or destroyed, causing survey costs to double as the whole

survey has to be repeated when the markers are lost.

1/ Lawrance, Jeremy. Land Adjudication, 1985.

Page 34: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 30 -

Survey. A survey of boundaries for description purposes

involves conventional ground survey methods, photogrammetric methods, or

a combination of both. The principal advantage of conventional methods

is that the investment in instruments is relatively low and the process

of transforming field observations into maps and plans does not require

extensive investment. One of the main disadvantages is that a detailed

survey may require the establishment of a relatively dense network of

geodetic points which is time-consuming and expensive. Another

disadvantage is that field procedures are labor intensive; the survey

can last a long period of time or require a large number of skilled

personnel to complete the work in a shorter time period.

Photogrammetric methods, on the other hand, require initial aerial

phtotography, supporting ground control and high investments in expensive

instruments. The advantage of photogrammetry, however, is its utility

in providing maps or map substitutes in a variety of costs, speeds and

accuracies. In addition, the time and manpower requirements can be

considerably less than those needed for conventional field techniques.

Costs. In many countries, the costs of cadastral surveying

approach or even exceed the capital value of the land surveyed. In less

affluent countries, even under favorable conditions, the costs of the

survey normally amount to a significant percentage of the land value.

In Malaysia, for example, the average cost for surveys has been reported

to be 5-10% of land values. In Kenya, the average cost is reported to

be about 5% and in South Africa, 10% of underdeveloped land value.i' In

Malaysia, the cost for sLrveying is reported to reach as high as five

1/ Dale, P.F. Cadastral Surveys in the Commonwealth, 1976.

Page 35: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 31 -

times the value of the land. Based on the 1983 tariff rates set by the

Land Survey Act, the following costs (in Kwacha) are for the sporadic

I/surveying of land in tMalawi.o

Plot Area Capital Survey Fee as %(hectares) value (K) fee (K) of value

1. Blantyre, prime commercial 0.15 48,000 247 0.52. Blantyre, medium-density residential 0.15 700 255 36.53. Mzuzu, industrial 0.15 1,100 251 22.84. Mzuzu, medium-density residential 0.15 550 251 45.25. Mchinji, commercial 0.15 200 503 251.56. Mchinji, medium-density residential 0.15 100 503 503.07. Narnwera, tobacco estate 100.00 10,000 1,122 11.28. Chikwawa, pastoral estate 100.00 2,500 813 32.1

The principal cause of variation in survey fees between

identical plots in different areas is the transport charge from Mzuzu,

Lilongwe or Blantyre, where the surveyors are based. Another factor

contributing to the high cost of some surveys is that they were under-

taken on a sporadic basis. According to Green, the inclusion of any of

the examples 1 to 6 above in a single survey exercise of 10 similar plot

would have reduced the survey fee by about K135 in each case. Thus, for

examples 1 to 4, there would be a cost reduction by about half; for

examples 5 and 6, the cost wou'ld be reduced by about 30 percent.

As mentioned above, a systematic approach to a cadastral

survey is more cost-effective than sporadic surveying. According to

uale, the systematic approachi can lead to savings by as much as 85 to 95

1/ Green, J. W. Reducing the Cost of Cadastral Surveys, 1984.

Page 36: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 32 -

percent when 40 to 5t contiguous land parcels are surveyed. Nonetheless,

there is no significant economy of scale when dealing with more than 50

contiguous parcels in one survey. Moreover, the cost per plot in the

survey of fewer than 50 parcels at one time increases steadily as the

number of plots decreases.l/

Photogrammetry is another cost savings device for carrying out

cadastral surveys. A photogrammetric cadastral survey involves the pre-

marking of boundary beacons or control points, ground survey for control

and checking, aerial photography, photogrammetric operations, checking

of survey data and field survey of boundaries not visible in the

stereoplotters, and the production of cadastral data in standard maps

which, as mentioned earlier, can take the form of unrectified air

photographs, rectified photomaps, orthophotomaps or line maps. These

processes are capital intensive; considerable sums are required for the

equipment, photography and training of personnel. Under the right

conditions, however - i.e. when boundaries are air visible, and large

areas of land are covered systematically - photograminetry can reduce the

cost of producing cadastral maps by about one third the cost of a

conventional survey. Even in Switzerland, for example, where high

standards ot accuracy are maintained, comparisons between different

survey methods showed that photogrammetric methods reduced the cost of

conventional ground survey methods by as much as 25 percent.2/

1/ Dale, P.F. Cadastral Surveys in the Commonwealth, 1976,p. 161.

2/ Dale, P.F. Cadastral Surveys in the Commonwealth, 1976, p.116.

Page 37: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 33 -

A principal cost determinant of a cadastral survey is the

degree of accuracy required to carry it out. Nonetheless, there has

been no economic analysis comparing the relative costs and benefits or

different levels of precision. According to Dale,

'there is no quantifiable evidence to indicate a relationshipbetween land disputes and the level of precision of cadastralsurveys. Disputes generally occur either over land,regardless of its value, or over the ownership of featuresnear a boundary. Although there is some evidence to suggestthat disputes increase in geometrical proportion with thenumber of boundaries that have to be respected, there is noevidence that a higher precision of survey has a significanteffect on reducitig the incidence of dispute rather thanadjudication and better monumentation.'l/

Land Valuation and Collection ot Other Land Data

Land Valuation. Intormation about land vaLues is a principal

element of a multipurpose cadastre. Ideally, the land valuation occurs

at the same time as the collection of other parce. data such as legal

ownership and boundaries. Thus, when a cadastral survey is currently

underway or recently completed, land valuation for property tax purposes

can be fast and inexpensive. It represents a marginal cost that could

be turther reduced when undertaken as part of a multipurpose land

information system. In the Philippines, for example, the cost for tax

mapping at difterent scales in 272 municipalities was about $4.2 per

hectare since the initiation of a tax mapping project in 1972.2/ Under

a proposed integrated land intormation system, the cost tor land

valuation will be considerably less than $3 per hectare.

1/ Dale, P.F. Cadastral Surveys in the Comamonwealth, 1976, pp.274-5.

2/ Falloux, Francois and Cremont, Daniel. The Philippines LandSettlement Development II Project, The Land Component WorkingPaper. April 1983, p. 20.

Page 38: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 34 -

Collection of Other Land Data. During a cadastral survev or

land tenure identification process, the additional cost for obtaining

such information as land use and services is usually negligible. With

respect to these types of land data, the cost for putting them into the

computer and then updating them on a regular basis is the more

significant cost consideration.

Land Data Bank

The establishment of the land data bank requires that all

parcels are assigned a unique identifier so that all records can be

linked to others containing information on the same parcel. The actual

recording and storage of graphic and non-graphic land information mav be

in hard copy or digital form. The most common system involves the

digitizing of non-graphic land data which is 1inked to the non-digitized

maps and graphic data. Inexpensive microcomputers can usually handle

this kind of data base for a relatively small jurisdiction. The

building of modern multinurpose cadastre, however, involves the

digitizing of graphic as well as non-graphic data.

The typical hardware required for a land data bank include

computers, digitizing tables, tracing tables, auitomatic drafters,

interactive consoles, and a storage system. The development of software

and the digitizing process are the more expensive and time-consuming

components in the building of a computerized land data bank. According

to one souirce, the development of software may require up to 200 or more

man years at an estimated cost of $60-70 per hour.1/ The following are

illustrative costs for acquiring the hardware and software for computer

1/ Boew. ITC, Enschede, The Netherlands, December 1984

Page 39: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 35 -

assisted mapping and land records systems in the United States and Canada.l/

Total cost Cost per parcel, excluding(in thousands of S) hardware and software tS)

Lower Upper Lower Upperthird Mean third third Mean third

Package price from vendor, including all hardware.software & training cost 35'i! 645 1000Software improvemmnts 5 20 48Training 6 17 26 0.06 0.10 0.14Other purchase costs

Feasibility 3 22 34 0.02 0.06 0.11Purchase 3 9 12 0.01 0.03 0.08Pilot 4 12 140 0.06 0.25 0.60

Special facilities 3 6 16 0,02 0.04 0.08Sub-total, training & services 19 66 228 0.20 0.40 1.10Total purchase cost 375 730 1275

The cost of digitizing the data for input into the computer is

influenced by the complexity of data and the number of errors or source

documents. According to Tomlinson, the total cost of editing, error

correction and subsequent re-formating ranges from $.24-$1.60 per line

centimeter or $.60-$4.00 per inch. Using 1979/80 prices for North

Anerican and European Labor, the cost of converting mapped data into

machine-readable form ranges from approximately $.12-$.40 per line

1/ hansen, Daniel, HN. An Overview of the Organization Costs andBenefits of Computer Assisted Mapping and Records ActivitySystems (CAMRAS), p. 185. These data are based on a survey of35 organizations which have the capacity to map at the parcellevel and have one base map for all land informationoraanizations in the same geographical area. Eachorganization is responsible for its own special purposeoverlays.

Page 40: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 36 -

centimeter or $.30-$1.00 per inch.1/ The following aata illustrate

costs in man hours for digitizing utility data.2/

Utility Cost/Km in Man Hours

Gas 5.3

Water 4e2

Local Telephone 8.5

Long Dis':ance Telephone 9.9

Electricity Low Voltage 4.6

Electricity High Voltage 8.2

The accuracy requirement for the data base is usually the

single most important factor atfecting the total cost ot establishing a

digitized land data bank. The figure below shows how costs for

computer-assisted mapping of property boundaries rise in relation to an

increase in the accuracy level. 3/ For a program in The Netherlands,

50

'0

c 30

. 20

10

0

0 I0 20 30 40 50 60 70 80 90

Positional accuracy in feet

Tomlinson, R.F. The Handling of Data for Natural ResourcesDevelopment, 1980, p. 74, Proceedings of the WorkshopInformation Requirements for Development Planning inDeveloping Countries, ITC, Enschede, The Netherlands, February18-23, 19b0.

2/ Bogaerts, Theo. Rotterdam, The Netherlands, December 1984.

3/ Hansen, Daniel M. An Overview of the Organization Costs andBenefits of Computer Assisted Mapping and Records ActivitySystems (CAC4RAS) p. 184.

Page 41: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 37 -

however, the estimated costs for the conversion of topographic maps into

a digital system show a more irregular pattern. Although the test area

was relatively small and the number of points per hectare were not

always the same, the costs presented below illustrate the differences in

unit costs for achieving various accuracies using five different methods.l/

COSTS FOR DIGITIZING TOPOGRAPHIC BASE MAP

ALTERNATIVE METHODS FOR BUILDING FILE PER HECTARE COSTS, f 1980

1 2 3 4 5Digitize Digitize Use Original GroundExisting Existing Field New NewCad. Map Top Map Measurements Surveying Photogrammetry

Total ha 70 12.5 70 70 12.5Ooeration

Preparation 3 5 19 19

ClosedTraverse 140

Demarcation 115

DetailedMeasurement 330

Ph'otogrammetricPoint Determination

211

Flights 5

Aerotriangulation/Block Adjustment 19

Coding 179 131 104

ComputerCalculation 213 139 158

Digitizing 54 60

Digital 75PhotogrammetricMappingChecking 75

Checking andProcessing 51

57 65 411 289 847 436Tctal f/Ha 57 65 350 847 436Accuracy 19c 2.1c 2 .2c .3c 22c

The exchange rate in 1980 was approximately f2 = US$l

1/ Bogaerts, Theo. Rotterdam, The Netherlands. December 1984.

Page 42: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 38 -

System Maintenance and Updating

The maintenance and updating of any land information system is

critical to its success. Thus, a budget tor these activities must be

built into the cost calculation for every project. As a rule of thumb,

one should allocate about ten percent of the initial cost of the entire

program to its annual update and maintenance. Average costs have ranged

from five to twenty percent.-/

In the Netherlands, it cost $9 million in 1984 to maintain the

niational multipurpose cadastre, covering 6 million parcels, 3.5 million

owners, 30,000 square kilometers and 30,000 maps, which are updated

every two years. 2/ The charge to notaries and private citizens who buy

maps or register deeds contributes to the financial support of the

system.

For the city of Rotterdam, the cost of maintaining a digitized

land data bank for one year was about M2 million and about $170,000 to

keep it operating. The system covers 120,000 parcels, 60,000 owners and

400,000 objects. The charge to users finances the system; in 1983, the

system made a profit of about $6U,000.3/

1/ hamilton, Angus. University of New Brunswick, December 1984.

2/ Hennsen, J.L.G. The Cadastral Information System in theNetherlands, 1984, and Koen, Jr., L.A., Dienst van netKadaster en de Openbare Registers, Apeldoorn, The Netherlands,December 1984.

3/ van Alphen, L. Stafafdeling BasisinFormatie, Rotterdam, TheNetherlands, December 1984.

Page 43: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 39 -

IV. Illustrative Programs

The cost of land information programs in Brazil, the

Philippines and Canada are discussed briefly below to illustrate the

range of costs that one might expect in the planning of comparable

programs in different countries. These particular programs were

selected because each involve typical activities leading up to the

development of a multipurpose cadastre: aerial photography, ground

contral, land adjudication and titling, cadastral survey, property

valuation, and the setting up of a computerized land data bank.

Brazil: The Northeast Region Land Tenure Improvement Project

A proposed project in Brazil will extend the benefits of

secure land ownership to up to 700,000 small farmers in the Northeast

region and improve the gQvernment's ability to formulate land policies

and administer land resources. The project will be implemented in ten

rural states having varied climatic and geographic features. It will

cover about one fifth of the northeast region or 1.5 million square

kilometers. The main features of the project include the following:

1. Aerial photography of some 56 million hectares of which

6.5 million hectares will be photographed at a scale of

1:60,000, about 45 million hectares at a scale of

1:30,000, and the remaining more densely occupied land at

a scale of 1:15,000 (The photographic outputs will be

negatives, diapositives and contact prints);

2. Ground control, aerial triangulation and mapping for the

production of orthophotomaps or line maps for all

photographed areas at scales of 1:5,000 and 1:10,000.

Page 44: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 40 -

Ground control will be carried out using conventional

field methods, an airborne inertial system, a Doppler

Transit satellite system or a Global positioning system.

Aerial triangulation will be carried out using automatic

coordinate recording devices and bundle block adjustment

programs;

3. Land tenure identification covering 31 million hectares

including production of microfilms of all land registry

documents, notification of governments intention to review

and regularize o-nership rights in areas selected for land

adjudication, field surveys to delimit parcels,

identification of all tenants and occupiers to evaluate

claims, and first estimate of potential and value of land;

4. Digitizing ot geographic and literal intormation for

computer storage and processing and the production of

about 600,000 to I million title documents for rural

properties;

5. Technical and economic studies to support the selection of

some 3.2 million hectares to be acquired by the government

and physical planning, temporary administration,

delimination, demarcation and titling of those areas;

6. Institutional strengthening, including buildings,

equipment, staff training, technical assistance;

7. Project administration;

8. Institutional, legal and socioeconomic studies to improve

efficiency of land operations; and the

9. Evaluation of the performance and progress of the program

by independent consultants.

Page 45: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 41 -

The total cost of this project is $250.5 million (including

pnysical and price contingencies); the unit cost is about $7.7 per

hectare. In the northeast region, the average land parcel size is 30

hectare.l/ Thus, the per parcel cost would be approximately $220.

Detailed lists of cadastre components as well as overall and unit costs

are presented below.

1/ These figures and the following cost tables are based on theappraisal costs for a World Bank loan. See the StaffAppraisal Report Brazil Northeast Region Land TenureImprovement Project February 11, 1985 for lists of requiredpersonnel.

Page 46: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 42 -

Components of the Cadastre

1. Basic Cartographic Data

- Copies of original aerial photographs;- aerial photographic maps, at different scales;- graphic planimetric line maps;- magnetic tapes containing planimetric data from line maps;- lists of coordinates of geodetic points, of stereo preparation

points, of aerial triangulation points and densification pointsof the cadastral system;

- identification charts for preceding points;- contour level maps on transparent films; and- magnetic tapes of contour lines and elevation points of all maps.

2. Craphic Data Resulting from Land Identification and Titling

- Coordinates of all cadastral grid points (lot boundaries) withtheir sequential numbers;

- cadastral grid vectors (all the straight lines made up of pointswith sequential numbers) and the codification for different typesof markers (wooden fence, wire fence, ditch, wall and so forth);

- cadastral grid parcels constituted by the preceding vectors andtheir numbers (tie to the tapes containing literal data);

- coordination of all the points of the topographic - planimetricsystem, with their sequential numbers (points that may also be onthe cadastral grid);

- topographic - planimetric system, with their sequential numbers(points that may also be on the cadastral grid);

- topographic - planimetric grid vectors, with sequential numberand codification of type of marker in the field;

- objects on topographic - planimetric system (roads, forests,fields and so forth), which may also be objects in the cadastralgrid;

- coordinates of all the points of the system for soil usepurposes; and

- the corresponding objects (zones of classes).

3. Systematically Gathered Literal Data

(To be defined by INCRA)(Names of villages, places, rivers and so forth)

4. Additional Agro-Economic Literal and Graphic -Data

(To be defined by INCRA)

Page 47: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 43 -

5. Additional Physical, Literal and Graphic Data

- Boundary points of zones (coordinates) of classes of soils and/orzo-nes of classification of water resources and/or ... , etc, withtheir sequential numbers;

- vectors of the corresponding physical grids, with theirsequential numbers (pointers);

- corresponding zones, with codification of each type.

6. Data Produced by Processing

- Descriptive memorandum of each parcel;- individual plat of each parcel;- general cadastral plat (on standard forms, by area,

municipality, and so forth), at different scales;- lists of parcels for each municipality, each area, with

sequential number for reference, its geographical location(centroid), area, soil classes, all improvements, buildings andname and code of the owner, etc;

- lists of owners in each municipality with reference number, andproperties (number, area, soil types, assessment for taxpurposes);

- various maps at different scales resulting.from combinations ofthe basic data (land grid, topography, soil classes, waterresources, assessment for tax purposes, vegetal cover and soforth); and

- lists, tables, diagrams, and maps showing the results ofstatistical surveys.

Page 48: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 44 -

BRAZIL

NORTHEAST REGION LAND TENURE IMPROVEMENT PROJECT

Total Project Costs(US$ '000)

TotalBaseline

Project Component Total Cost

Aerial Photogrammetry

Aerial photography 10,100 5Ground control, aerial 67,300 33

triangulation and mapping

Land Tenure Identification 59,300 29

Cadastre Impleientationand Titling 12,400 6

Support for LandRestructuring 19,300 9

Institutional Strengthening

Buildings 4,800 2Data processing equipment 5,700 3Other equip. and furniture 11,600 6Staff training and

technical assistance 4,200 2

Project Administration 8,700 4

Studies 1,400 1

Total Baseline Cost 204,800 100

Physical contingencies 24,600 12.0Price contingencies 21,100 10.3

Total Project Cost 250,500

Page 49: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 45 -

UNIT COSTS PER HECTARE US$ January 1985

Unit CostOperation per Hectare Details

Presignalization .05 1 point/km2

Aerial Photography .20 1:30,000

Complementary Geodetic Network .05

Ground Control .03 1:30,000 cost would beusing inertial system

Aerial Triangulation .05 1:30,000

Contour digitalization .35 1:30,000 5m intervals

Profiles Computation .05(by Data Processing)

Orthoprojection (Produiction of .05 1:10,000initial orthonegatives)

Production of Orthophotomaps .25 1:10,000

Production of Contour Maps .05 1:10,000 80% overlap

Photogrammetric Operations, Sub Total 1.40

Land Tenure Identification .30

Field Collection of Literal .15Data

Administrative Process .15

Field Investigation of Sampling and photo-Soil Classes .05 interpretation

Land Adjudication, sub total .65

Boundary Digitizing .02 1:10,000

Digitizing of Littoral Data .01

Digitizing of Topographic Features .01 1:10,000

Data Bank Processing .05

Production of Individual Titles .04

Production of Cadastral Maps .03

Production of Castral Listings .02

Data Processing, Map and TitleProduction, Sub Total .18

Page 50: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 46 -

EQUIPMENT LIST AND COSTS(US$)

1. Cars:

- light cars (berline) 80 x 4,500 360,000four wheel drive cars 450 x 8,000 3,600,000

Sub total 3,960,000rounded to 4,000,000

2. Topographic Equipment:

- theodolites (type Wild T 1 /T 2 ) with accessories(2 in each central unit, 1 in each microregionalunit) ---- 127 x 5,000 635,000

- distance meters (type Wild DI20/35) withaccessories (2 in each central unit, 1 in eachmicroregional unit) 127 x 10,000 1,270,000

- plane-tables with accessories (tripod, compass,open sight alidade etc.): 400 x 1800 720,000

- mirror stereoscope 60 x 1000 60,000- pocket stereoscope 460 x 60 27,600- pocket computer (type HP25) 460 x 50 23,000- measuring tape (50 m) 460 x 50 23,000- planimeter (4 in each central unit, 1 in each

mnicroregiional unit) 147 x 400 58,800- binoculars 6 x 30 (1 for each topographer) 400 x 400 160,000

Sub total 2,977,400rounded to 3,000,000

3. Draw:Lng Equipment

- lighting tables 80 x 400 32,000- accessories 80 x 100 8,000

Sub total 40,000rounded to 50,000

4. Microfilm Equipment

- reading/recording machine (2 in each control unit,1 in each microregional unit) 127 x 4,000 508,000

rounded to 550,000

Page 51: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 47 -

5. Data Processlng EquJpment

- mJnicomputer type VAX c/2m bytes 101,422- disk Wlnchester 160 m bytes 15,603

- pack dJsk 300 m bytes 57,21216 assynchron lines 5,852floating mark 650

- plotter (Ao) 32,507- graphic station 72,816- printing unit 12,000- 8 alphanumerical terminals 20,000

Base unit cost 318,062

- 10 basic units 3,180,620- 12 extra graphic stations 873,792

1 extra plotter 32,507- freight and insurance 70,000- additional software 30,000- maintenance and training 1,471,290

Sub total 5 5,658,209rounded to 5,700,000

6. Furniture

- 1600 sets x 2500 4,000,000

RECAPITULATION

1. Cars 4,000,0002. Topographical equipment 3,000,0003. Drawing equipment 50,0004. Microfilm equipment 550,0005. Data processing equipment 5,700,0006. Furniture 4,000,000

Total 17,300,000

Page 52: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 48 -

The following are illustrative unit cost calculations for the

aerial pilotography at different scales.l/ The estimates show that costs

increase proportionately to the increase in scale. As scale decreases,

however, the disparity in unit costs at 60 and 80 percent overlaps also

decreases.

Unit Costs for Aerial Photography at Different Scales

Patterns

1:15,00 photographs, minimum area: 5,000 km2 (90 x 55 kin)

1:30,000 photographs, minimum area: 20,000 km2 (18(jCx 110 kim)

1:60,000 photographs, minimum area: 50,000 kim2 (275 x 180 km)

or:

1,500 photographs in 22 strips with 60% overlap where photographs are onthe scale of 1:15,000 or 1:30,000.

3,000 photographs in 22 strips with 80% overlap where the scale is1:15,000 or 1:3U,000.

maximum speed corresponding to r5216 km/h where photoscale is 1:15,000432 km/h where photoscale is 1:30,000

1:15,000 photographs; mean unit cost:

OVERLAP 80Z 60i

mobilization/demobilization 24,000 24,000standby: 20 x $900 18,000 18,000flight: $22 (1920 + 2000) + $600 x 22) 99,440 99,440negatives: $7.5 x 3,000 or 1,500 22,500 11,250contact-prints '3 x 4,500 13,500 13,500diapositives $5 x 3,000 or 1,500 15,000 7,500photo-indexes $350 x 1U (sheets) 3,500 3,500

Total US$195,940 177,120

Unit cost per ha US$ 0.40 C.35

1:30,000 photographs; mean unit cost:

OVERLAP 80% bOZ

mobilization/demobilization 24,000 24,0U0standby (20 days) 18,00U 18,000tlight $22 (2,800 + 8,0UU) + $600 x 22) 250,80U 250,800negatives: $7.5 x 3,000 or 1,5UU 22,500 11,250contact-prints 13,500 13,500diapositivesa 15,000 15,000photo-indexes 3,500 3,500

Total US$347,300 328,550

Unit cost per ha US$ 0.18 0.17

1:60,000 Phocographs: mean unit cost: US$0.10/hectare

1/ The tollowing cost data were provided by Daniel Cremont,Consultant.

Page 53: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 49 -

The unit costs for alternative methods of ground control are

presented below. Using a conventional method, the mean unit cost would

be $.60 per hectare, the maximum unit cost of using inertial surveying

would be $.19, about 70 percent less.

1. Basic Patternphoto scale 1:30,000block size 180 x 110 kmarea 20,000 km2

number of strips of photographs: 22total number of photographs 1500on an average of 68 photographswithin each East-West strip.

bridging distance: 5 stereoinodels or 14 km2 traverses along main sides (total 360 km) with one pointevery 3 bases (8 km)

14 traverses, 110 km each with one point every 5.4 km (2 basesat right angLe.

total: 1900 km with 350 points

2. Conventional MethodAssuming that all points would be determined in x, y, z, using

theodolites and distance meters, costs, based on international tariff,could be established as follows:

preparation US$ 4,500mobilization/demobilization (8 teams) 18,000monumentation: $225 x 350 78,750clearing $210 x 1,900 399,000stations $2,000 x 350 700,000computation $55 x 350 19,250

Total US$1,219,500Mean unit cost per ha US$ 0.60

3. Inertial System

mobilization/demo bilization(1 year + helicopter) US$ 20,000clearing and monumentation 140,000doubie run traversing US$110 x 1,900 209,000computation: US$50 x 356 17,500

Total US$386,500MvIaximum unit cost per ha US$ 0.19

Page 54: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 50 -

The costs for the production of maps are as follows: for a

map at a scale of 1:5,000 the cost is $4.5 per hectare; For a map at a

scale of 1:10,000, the cost is $1-1.41 hectare; and for a map at a scale

of 1:20,000, the cost will be $.45 hectare. In terms of man months, 750

hectares can be mapped in one month at a scale of 1:5,000. Three

thousand hectares can be mapped in one month at a scale of 1:10,000.

The Philippines: The Land Settlement II Project

The land comrponent of a proposed Land Settlement II Project in

the Philippines aims to: develop a low-cost participatory approach to

surveying in order to correct land occupancy; complete cadastral surveys

and land sub-classification; establish a foundation for improved land

record and information system; streamline and reduce the cost of mapping

activities and develop the related institutional capacity; and

strengthen interagency cooperation. The component would include the

following elements:

1. Preparation for geodetic and aerophotogrammetric works

including the upgrading of the geodetic network for the

entire country, the aerial surveying and ground control of

5.5 million hectares, and the production of photos and

orthophoto maps covering 2.2 million hectares;

2. Inventory survey for soil and land sub-classification of

2.2 million hectares, cadastral surveys and inventory of

land occupancy, using orthophotomaps primarily;

3. Land tenure regularization;

4. Computerized land titling and issuance of stewardship

contracts in public forests;

Page 55: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 51 -

5. Establishment of land data bank to integrate the legal,

technical, fiscal and economic files; and

6. Training and technical assistance including 111 months of

foreign consultants in geodesy, photogrammetry, surveys,

and data processing.

For the geodetic network, a modern technology like Doppler Transit

Satellite Network could be used to establish 200 points with an average

50 km interval distance. Where possible, points would be located in old

geodetic points to minimize costs- Using the DTSN method would enable

the geodetic network to be upgraded in one year as opposed to at least

10 to 15 years that would otherwise be required for conventional ground

methods. The costs would also be considerably less.

The monumentation and presignalization would establish a

network of points dense enough (average 1 point per 2 Km2) to be

visualized on aerial photos and serve as a secondary control in the

photogrammetric process. The 1:15,000 scale aerial surveys would be

carried out on an area 2.5 times larger than the 2.2 million hectares

which will be covered by the cadastral surveys due to several reasons:

the photos have to be taken in a Ulock of 3,000 km2 wnich includes 4

DTSN points, the settlements are fairly scattered, and unprecise

boundaries require a large margin of security.

Ground control and aerial triangulation would be used to

densify the primary network of DTSN geodetic points in order to

determine the secondary framework necessary tor producing

orthophotomaps. The ground control would be cprried out in a nelicopter

equipped with an inertial system.

Page 56: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 52 -

Orthophotomaps would be the base map for the cadastral

surveys. They were selected because the cost of their production is

about 20 percent less than that of conventional maps. In addition,

using orthophotomaps significantly reduces the cost and time required

for cadastral surveys, and the computerized process for producing

orthophotomaps provides digitized information (i.e. lines and points)

which can be stored directly in a land data bank. The orthophotomaps

would be produced at a scale of 1:5,000 with a 0.56 x 0.56m standard

formac covering 760 hectare areas with 2m or 5m ina.erval contour lines

depending on topography. Expected productivity is estimated to be about

4 to 6 orthophotos per day covering about 4,000 hectares with three

stiifts of operators.

The land data bank would store graphic and non-graphic data

linked by a parcel identifying code. The initial outputs would include:

a) administrative maps with boundaries of regions, provinces,

municipalities, barangays and sections at different scales

in accordance with the needs, standard formats and the

size of the different zones;

b) soil, slope and land suitability maps;

c) cadastral and tax maps at large scale (1:500 to 1:5,000)

according to the density of parcels and natural features,

either in standard sheets or by sections:

d) indexes of owners classified in alphabetical order by code

number and giving the list of parcels owned by each of

them; and

Page 57: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 53 -

e) indexes of parcels classified sequentially by sections and

giving the name of owner and other various parameters

(area, value, etc.).

Another essential output would be the automatic issuance of titles and

stewardship contracts by extracting raw data from the files and

processing them into the suitable form of output (i.e. the Torrens

title). Special programs would be prepared for that purpose.

The total cost of the five-year program is an estimated $27.4

million (including physical but not price contingencies) with capital

costs representing the largest pr, -nrtion (70%) of the total. The unit

cost for the cadastral survey is -, --i<-mately $7 per hectare. The

individual unit cost estimates are presented on the following pages.

The approximate percentage breakdown of these costs are as follows:

aerial photography (22%), soil suitability surveys (18%), cadastral and

parcel surveys (15%), tgeodetic network upgrading (14%), photogrammetric

laboratory (11%), ground control (6%), building (6%), equipment for data

banL (3%), and field survey equipment, vehicles and miscellaneous

(5%). Four percent of the total project cost is allocated to training

and technical assistance; 26 percent is for operational purposes.

Page 58: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 54 -

THE PHILIPPINES

LAND SETTLEMENT II PROJECT/LAND COMPONENT

Cost Estimate for Cadastral Survey(US$/ha 1982)1/

Approx.Items Cost/ha

Geodetic Network .09

Aerial Surveys .74Ground Control .20Production of Orthophotos Equipment Authorization .25

Maintenance .31

Supplies .28

Salaries .35

Technical Assistance .17

Training .02

Total 1.38Inventory & Complementary Surveys 3.00

Land Tenure Regularization 1.60

Titling Data Bank .02

Supply .05

Maintenance .17

Salaries .06 .31Base Line (Rounded) 5.75

With Land Regularization 7.32

1/ Converted into 1982 US dollars using rate of P 9.42=$l

Page 59: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 55 -

THE PHILIPPINES

LAND SETTLEMENT II PROJECTS

TECHNICAL ASSISTANCE AND TRAINING

Detailed Cost Estimates(US$000, 1982)

I. Technical Assistance

Nb Monthly TotalMonths Cost Cost

Assistant to Component Coordinator 60 9 540

Expert in Photogrammetry 36 6 216

Expert in Cadastral Survey 12 6 72

Consultancy for Land Data Bank l/ 3 22 66

Consultancy for ICB's 3 11 33

Total 114 927

I. Training

Aerial Triangulation 6 22

Stereoplotting 6 22

Orthoprojection 6 22

Photo Processing 6 22

Data Processing 12 55

Total 143

Page 60: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 56 -

Canada: The Land Registration and Information Service LRIS Program

The LRIS program was established in 1973 to resolve a number

of problems related to land information management in the Maritime

provinces of Canada.l/ The program consisted of the following:

1. Densification of the primary geodetic framework;

2. Base mapping including 1:10,000 scale orthophoto maps and

1:1,000 line maps for cities and 1:2,000 line maps for

towns and built-up areas;

3. Property mapping consisting of map overlays (orthophotos

in rural areas and line maps elsewhere) on which all

parcel boundaries are delineated and assigned a property

identification number (PID);

4. When requested, assistance in the conversion of the

existing land registry systems in the three provinces to a

computerized guarantee of title systems, and

5. Investigation of alternative land data storage and

retrieval systems.

In the early 1980's, the extension of second order control was completed

for all developed areas of the Maritimes. Between 1973 and 1981, when

initial placement was completed, LRIS spent $9.7million (Can. 1983) for

1/ The Maritime provinces includes New Brunswick, Nova Scotia,and Prince Edward Island, covering 130,000 square kilometers.

Page 61: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 57 -

19,545 monuments or $500 per monument. The annual maintenance costs are

now abouLt $1.2 million (1985) or $26 per monument per year. The

production by LRIS of 4112 urban maps and 3913 medium-scale maps cost

p29.7 million (1983). The total investment in property mapping, when

the program is completed will be about $26 million (1983).1/

Illustrative costs for the program durina 1980/81 are

presented below:-/

1980/81 COSTS FOR T,RIS

% of1981 Canadian Total

($000)

Control 941 17Aerial Photography 141 3Base Mapping 1,592 30Propertv Mapping 1,345 25Parcel Index 145 3Legal 203 4Projects 447 8Administrative Overhead 608 11

5,422

As indicated in the above hudget, the costs for the ground control,

aerial photography and base mapping account for about 50 percent of the

project. Most of the remaining costs are associated with the property

napping, parcel index and related legal and project work.

The property mapping program begins after the control and base

mapping operations are complete. The program is implemented in four stages:

planning, preparation, initial lift, and maintenance. The following table

summarizes the activities, time, staff, and person-hours per parcel for

I/ Simpson, R.L. LRIS. The Basis Lor Land Information Systems.LRIS, Council of Maritime Premiers, New Brunswick, Canada.

2/ November 1981 Planning Document, LRIS.

Page 62: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 58 -

the first three stages of the program undertaken on a county-by-county

basis. The maintenance stage begins as soon as the initial lift is

completed in an area. Each year approximately 10% of all properties

have a change in status. Thus, the updating mechanism operates while

the initial lift activities are being completed.

An analysis of costs for the program in New Brunswick showed

that for the period 1973 to 1983, the per parcel cost ranged from 1981

Canadian $19.82 to $50.32 for the initial lift and update, including

administration costs (e.g. personnel management, financial management,

administrators and executives are included). The land parcels in New

Brunswick range in size from approximately .1 hectare in the towns to

more than 100 hectares in the rural areas; the average parcel size is

9 hectares. Thus, the average per hectare costs ranged from about

@2.20 to $5.60.

The lower costs occurred during the last three years of the

program due to a combination of factors including the efficiency of the

more experienced and competent management and staff, negligible changes

in standards and procedures, andl the impact of economic recession on the

cost of work contracted to the private sector. Costs were higher in the

early years of the program due largely to the required development work,

increased computer use and related costs, shortage of qualified staff,

low productivity while new staff were developing skills, and the

planning of contractor mapping. Based on 1981-83 figures for

Northumberland County, it took approximately two hours per parcel to

accomplish the property mapping exercise initially. After management

expertise and production skills improved, it took approximately one

hour. (See Chapter V for a discussion of the methodology used for

calculating these unit costs.)

Page 63: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 59 -

RESPONSIBILITY ACTIVITIES I ELAPSED CUMULATIVEI PERCENTAGESTAGE I TIME ELAPSED OF TOTAL

TIME PERSON-HOURS}I PER PARCEL

I I a-------------------------------------------------- ------------- -- - -- ---- ---------- --------- ------- ----- .- -

I It I- Assemble resources i

! - Identify requirements j ,

,Property -Ensure production of base amaps before initial lift a a a

a 0 Mapping begins I2 months j12 onths a 2 :'Planning : a a a a

a Advisor a--------------------- t --

a a a - Produce county property a a aa a a mapping plan a 3 months 15 mon ths

a a - -- --------- ---------- a-r- - -a- a

aanager project areas a 3 months a a onths

- -- - - -- - ---------------------------------------------------

a a I a a

§ ! ff- Organise regional office ' j

- Orent and tran stafRegional a - P a p

t t | ~- MSicrofilml anti codeM anager registry data

:Preparation: Liaise with assessmenta nd reityofcs 83 months 21 months j 6 2:

aI II

- --------------------- ------------------------ I

a a a - OPrepare local property a aSenior mapping plan r t a

Technician -Assemble resources into .preparation packages 3 months 2 4 months

,------------ ---------- - - ---------------------------- --- --------- ,--- ------- ------

X g s - Familiarize propertyaRegional mapper ith resourcesSurveyor and procedures

z t | ~------ -- -- -- -- -- -- - --- -J

j j § - ~Verify fieldl card dataa nin registry office search a

Property -Plot plan data on field mrlp |I

:Initial M tapper -Condtict fieldri nterviewsrpnd rnvesigntnon

Correct faeld mAa anda a complege field cfrdi e 18 months 42 months a

Check faeld rk and map

t 2 t - Cross-check map And cards ,

Senior j- Draft finAtl map 1 9 z

Technician - updlate computer data batse |

Check the fnal map and

' listings from data base 1'6 months 48 months

------------.--------------- 1------------------------------ ------------ ----------- 1 -----------

Page 64: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 60 -

V. Current Research on Cost Methodologies

Research on the costs of land information systems as well as

the methodologies for analyzing or estimating unit costs is an

undeveloped field. There are very few efforts directed at this issue;

two in particular are noteworthy.

Unit Cost Methodology

At the University of New Brunswick in Canada, Professor Angus

Hamilton has proposed a methodology by which the unit costs of the

production of any land information system product can be derived and

compared on an international basis. The inethod is based on four

principles:

1. For each product, two unit costs are essential, the cost

for initial production and the cost for maintenance;

2. An inflation factor must be used to convert each annual

unit cost in the currency of one clearly defined base

year;

3. To allow for wide fluctuations in exchange rates and

widely varying salary schedules, unit costs should be

converted into person-hours; and

4. All person hours should be normalized with the skill level

of the norm clearly stated.

Given the above principles, the formula for deriving the unit cost for a

product from an analyses of time per unit (UCT) can be expressed as

UCT = (NHS x OUF) x NTU, where NHS is the average hourly wage for the

Page 65: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 61 -

normalized person-hours, OHF is the overhead factor and NTU is the

normalized time per unit. Then, UCT UCF where UCF is the unit cost

derived from an analysis of financial statements.

There is no consensus on overhead figures for public agencies

comparable to that for private sector operations which may range from

1.5 to 2.5. In some cases, however, an overhead factor (OHF) of 1.7 has

been citied. Until a better figure is derived, the 1.7 figure can be

used.

The above methodology has been tested successfully on the unit

costs for the LRIS property ongoing LRIS program in New Brunswick

discussed earlier. Professor Hamilton contends that the methodology can

also be used for arnalyzing the unit costs for production and maintenance

of all LIS products.1/ In an attempt to classify these products, he has

proposed the Land Information Matrix (see Figure) in which all costs for

production and maintenance for different kinds of maps at different

states can be inserted. The products are grouped according to the

sequence that they are encountered. Starting from barren, treeless

uninhabited territory through sparse forest to productive inhabited land

and lastly, to the central business district of a megalopolis. To

define the regions in which the above products and costs can be

compared, Professor Hamilton suggests that there are three major steps

in the sequence that can serve as natural boundaries: the occurrence of

a soil/climate combination capable of supporting significant useful

vegetative growth, the existence of human settlement on bounded land

1/ Professor Hamilton and his students are currently working oncosts for topographic mapping.

Page 66: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 62 -

parcels, and the existence of underground utilities. The second figure

presents the resulting "regionalization" of land information products.

It shows the regional distinctions as well as the products which are

normally required for each type of land. This regional framework can be

superimposed over the L.I. matrix for an analysis of costs.

Page 67: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

UNIT-COS'T LAND lINFOW-1ATIOII tAThI X FAMILY

TypQ of Tcrraln Vundral Wiarginal Morcianiitabl Forcstry and flurals Vllag3s Cltics Ccntral Business

uninlhabited, forcut and foreat liglct intenaivo and touno (low-riso DisLtrct

un(oreoted rango land agriculture. a.jiculturo buildings) (higch-risc

and buildingjs)unincorporatedcoruivunitioz

vcry &mall

III 000 000 . P

1: 500 000

,1 1z u 5 ooo2 x ' /V.4

,c ;i 50 000

u~

1; 20 000 p

18 10000

II 50 ooo 1 4I

11 1 000

500

Tho unit-cost, Land Inforilation itrix fa=ily. Thero 1S A difforent unit-cost matrix

for each typu of terrain.

Page 68: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

' 1 .3

q~u

Jr

(1;1 000 UUU

1:1 UOU UJ)u ACI;o 1 UnI,hbt1d, no 1t0rt,? O&UII or oah.r .ic ultutra

~~ ~ p oduc i on.I 00 000 p.cl.

I 2 n ouu lb - lotn. AgSlon liii Aural n4 4'(1aetlonl

1: IUU OUO IC h liounCIns Soo;c for.st, poatuft of othcrctop 1l.ld. ocnt-on.l1. So OOU habItatlon. but no ltOnilcaroCJ -holdinie Icit thirn 1000hc 116 £06

I; i ouoOliII:

tilht o StICa1t... bboJn.te, dots.p.c, toi.

1: J ODO

1: 2 Uu IVA, la-na.(.n. 1

via1oa -Ith u/1 uIltto.).

I: 1 ouo Poion IV; U:bae ItVs Lsj,t -wn,. -ou11 clls a*t .ci. *ubu.tb.

1: S IVC: ivctcpolltan c1n11. buolne .h. 4 rttlc-

Regionalizatio n for laidcl info irmatio n prodticts

Page 69: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 65 -

OEEPE Cost Modelling Research Project

The OEEPE (European Organization for Experimental

Photogrammetric Research) cost modelling research project is directed at

obtaining information on the costs of photogrammetric processes in the

surveying and mapping field. As part of this project, Hans G. Jerie and

Eric W. Filland of the International Institute for Aerial Survey and

Earch Sciences (ITC) at Enschede, The Netherlands are developing cost

models tor photogrammetric operations and a system by which the density

of natural and cultural features can be classified for the evaluation of

costs tor all stages of photogrammetric processes.

Cost Models for Photogrammetric Processes

The cost models represent the functional relationships between

the cost per production unit of any of the sub-processes of a total

production process (e.g., cost per line km. of aerial photography, cost

of aerial triangulation per model, cost of stereoplotting per km2) and

to various factors that influence production. Each model is a function

of basic cost standards and production standards. The basic cost

standards depend on factors related to the executing organization, which

include personnel costs per time unit, equipment costs per time unit and

material costs per time unit. Production standards include required

personnel times per production unit, required equipment times per

production unit, and required material, per production unit. These

standards are significantly influenced by factors related to the project

area (e.g., density, area) product specifications (e.g., accuracy

requirements, details to be plotted), process parameters (e.g., scale of

photography, merhods and equipment used) and the executing

Page 70: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 66 -

organization. The density and complexity of an area, however, appears

to be the most important factors influencing costs; as the density or

complexity of an area increases, costs increase proportionately.

When completed, the cost modelling system will be able to

receive statistical cost information from public and private mapping

organizations. To deal with the tremendous amount of data that will be

generated, the mapping process has been divided into its basic phases:

stereo plotting (conventional and digital), primary data acquisition

(aerial photography and auxiliary data for mapping purposes) aerial

triangulation, field survey (ground control, including signalization,

field identification, completion and verification) photomap production

(orthophoto and conventional rectification) and cartography (including

reprographics and printing). For each phase, functional production

processes will be identitied with all cost generating sub-processes for

the various technical alternatives. At the same time, the factors which

influence production rates are identified. The latter may be classified

into three general categories:

1. According to the origin of the influencing factor and here there arefour, possibly five, sub-divisions:A. factors originating from the Product specificationB. factors originating from the Process specificationC/D environmental factors:C. appertaining to the Project AreaD. appertaining to the Executing organizationE. derived factors (originating from outside the particular

mapping system being considered)

2. According to the tunctional description of the influencing factorA factors which can be chosen and manipulatedB factors which can be predicted but not manipulatedY factors which can not be predicted nor manipulated

Page 71: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 67 -

3. According to the effect on production rates3.1 Strong direct influence, i.e. a factor which results in a

variation in production rates of greater than 100%( r max > 2 )(r min )

3.2 Medium direct influence, i.e. a factor which results in avariation in production rates of between 30% and 100%

( r max between 1.3 and 2)(r min )

3.3 Weak direct influence, i.e. a factor which results in avariation in production rates of between 10% and 30%

( r max between 1.1 and 1.3)(r min )where r max and r min are the maximum and minimum productionrates respectively.

The ITC has already prepared initial lists of production processes and

sub-processes and lists of factors which influence production rates.

Feature Density Classification System

The feature density classification system is being developed

to quantify the density of natural and cultural fractures as they appear

in the different projects used in the cost modelling analysis. The

classification is based on visual inspection using a series of

scandards. The system will ultimately consist of the following

elements:

1. Six categories of planimetric features including

buildings, communications, water features, vegetation and

area symbols, boundaries and borders, and point and symbol

features;

2. One category of height feature, contours;

3. Five density classes, including dense, medium dense,

medium, medium open and open;

4. A contour sheet having three degrees of difficulty,

(irregular, average and smooth);

Page 72: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 68 -

5. Feature density classification sheets for six mapping

scales: 1:1000, 1:2,500, 1:5,000, 1:20,000, 1:25,000 and

1:50,000; each will have two sheets containing three

planimetric features; and

6. A final document having 12 planimetric sheets and one

contour sheet.

The figures on the following page illustrate a sample layout of the

planimetric sheets and the 1:25,000 pilot sheet showing elements of

buildings, communications, and water features at different densities.

The feature density classification system and the

establishment of standards are intended to improve the cost estimating

pertormance of organizations in the mapping field. Using established

scandards would be particularly useful for investigations into the

costing of new procedures as well as the resulting publications which

describe them. The standards would also be used in scientific reports

and in contract specifications which must describe precisely the nature

of the terrain to be mapped.

Page 73: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 69 -ITC Journal 1983-2

1:25000 COMMUNICATIONSBUILDINGS

FEATURE DENSITY CLASSIFICATION WATER FEATURES

communications open medium open -_rnedium medium dense dense

buildings open medium open medium mnedium dense dense

1 r1 1 I

water features open medium open medium rredium dense dense

Planimetric feature density classification sheet

medium buildings rnedium dense dense

~'7 JI.,

F v -~~0 - - --t-z\'i

Feature d o.. .~J.

medium water features medium dense dense ___

Feature density classificaton sheet detail

Page 74: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

'11

II

N,

rv

I II

Page 75: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 71 -

References

Angus, Leppan, P.V. and Holstein, L.C. Aerophotogrammetric Techniquesfor Demarcation and Measuring of Rural Lands and Use of DataProcessing in Titling Proceedings of the International Workshop onLand Tenure Administration, Salvador, Brazil, August 20-24, 1984.

Balata, Kenard da Silva. Cadaster and Land Registries in Brazil.Proceedings of the International Workshop on Land TenureAdministration, Salvador, Brazil, August 20-24, 1984.

Dale, P.F. Cadastral Surveys within the Commonwealth. Overseas ResearchPublication Number 23 London: H.M.S.O. 1976.

Falloux, Francois and Cremont, Daniel. The Philippines Land SettlementDevelopment II Project, The Land Component liorking Paper. The WorldBank, April 1983.

Green, J.W. Reducing the Cost of Cadastral Surveys. The Development ofAfrican Lanid Rebources with Particular Reference to Central andSouthern Africa. Report of the proceedings of CASLE regional seminarheld in Harare, 5-9 September 1983, London: Commonwealth Associationof Surveying and Land Economy, 1984.

Hamilton, Angus C. Land Information Economics: A Challenge for FIGCommission 3, FIG XVIII InternationaL Congress, Sofia, Bulgaria, June19-28, 1983.

Hamilton, Angus, Palmer, David, and Gaudet, Roger. Procedures and UnitCosts ror Property Mapping. Paper prepared for the Second South EastAsia Survey Congress. Hong Kong 5-9 December, 1983.

Hamilton, Angus, Palmaer, David and Gaudet, Roger. Unit Cost Principlesand their Application to Property Mapping in New Brunswick. Paperprepared for publication in The Canadian Surveyor.

Hansen, Daniel 14. An Overview of the Organization, Costs and Benefitsof Computer Assisted Mapping and Records Activity Systems (CAMRAS),Computers, Environment and Urban Systems. Pergamon Press, Volume 9,Number 2/3, 1984.

Jerie, H.G. and holland, E.W. Cost Models for PhotogrammetricProcesses. Invited paper for Auto-Carto 5/ISPRS Commission IV.Symposium, Crystal City, Va., August 1982.

Page 76: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 72 -

Jerie, Hans G. and Holland, Eric W. Cost Model Project forPhotogrammetric Processes: A progress Report. ITC Journal 1983-2.

Jerie, H.G. and Holland E.W. Establishment of a Feature DensityClassification System. Presented paper for Auto-Carto 5/ISPRSCommission IV Symposium. Crystal City, Va., August 1982.

National Research Council. Procedures and Standards for a Multi-PurposeCadastre. Washington, D.C. National Academy Press 1983.

The University of New Brunswick Department of Surveying Engineering.Abbreviated Proceedings of Land Information Systems 1990-No. 2.February 18-19, 1981.

United Nations Department of Technical Cooperation for Development:Report of the Meeting of the Ad Hoc Group of Experts on CadastralSurveying and Land Information Systems. New York: United Nations1983.

The World Bank Staff Appraisal Report. Brazil National LandAdministration Program, Northeast Region Land Tenure ImprovementProject. Washington, D.C. The World Bank. February 11, 1985.

Page 77: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 73 -

ANNEX I: Papers Addressing Cost Aspects of Land Information Systems

Beck, W. Production of Cadastral Maps for Rural and Urban Areas. WorldCartography Volume XII. New York: United Nations, 1975.

deBruijn, Cornelis A. MASMAP, Design for a Project-Oriented Geo-Information Program Package for Urban Upgrading Schemes. ITC Journal1984, No. 2.

Forstner, Rudolf. Ideas on the Establishment of Surveying and Mappingin Developing Countries. Frankfurt: Institute for Applied Geodesy,1977.

Gonzalez, G., Jose A. Modern Cadastre in a Developing Country. InProceedings or the North American Conference on Modernization of LandData Systems (A Multi-purpose Approach) lWashington, D.C., April 1975.

Green, J.W. Reducing the Cost of Cadastral Surveys. The Development ofAfrican Land Resources with Particular Reference to Central andSouthern Africa. Report oi the Proceedings of a CASLE regionalseminar held in Harare, 5-9 Septemer 1983. London: CommonwealthAssociation of Surveying and Land Economy, 1984.

Hamilton, Angus, Palmer, David and Gaudet, Roger. Procedures and UnitCosts ror Property Mapping. Paper prepared tor the Second South EastAsia Survey Congress. Hong Kong, 5-9 December, 1983.

Hamilton, Angus, Palmer, David and Gaudet, Roger. Unit Cost Principlesand their Application to Property Mapping in New Brunswick. TheCanadian Surveyor, Volume 39, No. 1, Spring 1985.

Hodgson, A. A Report on the Participation of the Survey Department inthe Lilongwe Land Development Project.

Howells, L.J. The Cadastral Survey and Registration Project in theCaribbean. Chartered Surveyor Supplement, Volume I/1974.

Larsen, Hans and McLaughlin, John D. Economic Criteria for Multi-Purpose Cadastral Systems. XV International Congress of Surveyors,Stockolm, Sweden, June 1977.

Page 78: DISCUSSION PAPER Report - World Bankdocuments.worldbank.org/curated/en/... · survey such information as is readily available. If it stimulates further discussion and work in this

- 74 -

Lewis, Judy. The Caribbean Regional Cadastral Survey and LandRegistration Project. (Report obtained from University of CambridgeDepartment of Land Economy).

National Research Council. Procedures and Standards for a MultipurposeCadastre, Washington, D.C. National Academy Press, 1983 CaseStudies: Southeastern Wisconsin Region, Dupage County, Illinois,Jefferson County, Colorado, The Philadelphia Area.

University of New Brunswick. Abbreviated Proceedings of Land InformationSystems No. 2. Workshop Sponsored by Department of Surveying Engineering.February 18-19, 1981.

Zwart, P. Some Suggestions for Improving the Cost Structure of IntegratedSurvey Systems, Australian Journal of Geodesy, Photogrammetrv andSurveying. No. 37, December 1982, pp 79-99.