distributed generation safe work proceduresesafetyline.com/eei/conference s/2017spring... ·...

27
Distributed Generation Safe Work Procedures Griffin Reilly Section Manager Targeted Demand Management Energy Efficiency and Demand Management Consolidated Edison Company of New York, Inc.

Upload: others

Post on 17-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Distributed Generation

Safe Work Procedures

Griffin Reilly

Section Manager

Targeted Demand Management

Energy Efficiency and Demand Management

Consolidated Edison Company of New York, Inc.

Page 2: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Customers Infrastructure Service Territory

Electric 3.3 million

(2.4 Network)

One of the world’s

largest UG systems

All 5 boroughs and

Westchester County

Gas 1.1 million 4,333 miles of gas

mains and services

3 out of the 5 boroughs

and Westchester County

Steam 1,760 World’s largest

district steam system

Manhattan below 96th

Street

Con Edison System

Page 3: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Con Ed Solar Map

Solar Installations at Con Edison

Page 4: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Types of Distributed Generation

Spinning – Breaker Isolated Inverter Based

• Combined Heat and Power

• Micro-CHP

• Diesel Generators and other

Reciprocating Engines

• Microturbines

• Solar

• Wind

• Batteries

• Fuel Cells

• Flywheels

Page 5: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Safety of DG has been Standardized L

ocal

Sta

te

N

ati

on

al

T

ests

Sta

nd

ard

IEEE 1547

(No Inherent Authority)

Product and Installation

Requirements

Grid Interconnection and

Functional Requirements

UL 1741 and IEEE P1547.1

(Listing and Certification Test)

National Electric Code

(Voluntary)

State Codes/Laws

(selective adoption of NEC)

Local Municipal Codes

NERC / FERC

State / PSC Utility Laws

Utility Connection

Agreements

Page 6: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

New York State Standardized

Interconnection Requirements (SIR)

• Complete Interconnection Process

Description

• Customer and Utility

Reference

• Application Requirements

• Timeline Requirements

• Protection and Testing

Requirements

• Issued by New York State Public

Service Commission

Page 7: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Information is Critical

Page 8: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Training is Paramount

Page 9: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Grid Connected Solar Photovoltaic System

Page 10: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Photovoltaic Panel

• Inverter/Micro-Inverter

• Production Meter

• Disconnect Switch/Breaker

• Net Meter

Page 11: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Photovoltaic Panel

– 250W-350W capacity each

– 0-40V DC depending upon

sunlight exposure

– 5-10 Amps per panel

– Produce power any time

sunlight is on them

– Even with disconnect open,

Voltage is present at panel

– Wired in series to increase

DC Voltage and Amperage

Page 12: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Inverter

– Similar to vehicle inverter

– Converts DC to AC sine wave

– Sine wave created exactly

matches utility (unity PF)

– Acts like an amperage source

providing the house with kwh

– Integrated AC-DC disconnect

barrel switch on most models

– Multiple sizes and models can

be combined at one site

Page 13: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Micro-Inverter

– Inverter for each 1-2 panels

– Converts DC to AC prior to

leaving the roof

– No integrated disconnect

switch on the unit

– Separate disconnect switch or

breaker required to isolate

Page 14: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Inverter Safety Features

• All Inverters & Micro-Inverters are certified to UL-1741 and

IEEE-1547 national standards.

– Requires immediate shutdown on loss of utility reference signal.

– Inverter will not re-connect to restored grid until after 5-minute wait.

– Inverter will not produce power when one phase is lost.

– No voltage difference phase-phase, inverter will not produce power.

– Inverter has both Over-Voltage and Under-Voltage shutdown.

• MUST BE INSTALLED WITH CON EDISON APPROVAL

– Units found in the field that are not on M&S plate must be reported,

and approached with CAUTION!

– Units not certified may have been installed improperly

• Always Follow Work Procedures – Test Dead Before Work

Page 15: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Production Meter

– Measures AC kwh provided

by solar to the house panel

– Required by NYSERDA for

quality assurance

– Not read by Con Ed

– Can look similar to our

meters or be digital meters

– Often a source of confusion

for the homeowner

Page 16: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Disconnect Switch/Breaker

– Last piece of customer

equipment before load panel

– Isolates DG system from the

panel and meter

– Systems >25kw must have a

lockable disconnect switch

– Residential systems are

allowed to use a dedicated

breaker in the house panel

Page 17: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Basic Elements

• Net Meter

– Con Ed meter programmed

to record bi-directional flow

– Customer usage makes kwh

recorded go up as normal

– Solar export makes kwh

recorded go down

– Does not affect demand KW

– Multiple ways to determine

the meter is a net meter

Page 18: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Normal Operations

Customer Utility

Meter

Customer

Supply

Panel

Net Meter

Building

Load

At night, the Utility grid

provides power.

Utility and PV System

share load requirement.

PV System

provides power.

Export Import

Readings going Slowly Up

Backwards

Page 19: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Emergency Operations

Customer Utility

Meter

Customer

Supply

Panel

Building

Load

Utility fault causes loss of

power to the customer.

Utility and PV System

sharing load requirement.

PV System shuts

down without grid

reference signal.

X

Page 20: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Permanent Repair

Customer Utility

Meter

Customer

Supply

Panel

Building

Load

Permanent repairs made

to the service lateral.

PV System slowly ramps

up to full power.

PV System waits 5

minutes, then starts

generating again.

X

Page 21: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Temporary Repairs – Bridge Adapter

Customer Utility

Meter

Customer

Supply

Panel

Building

Load

Side-off repaired temporarily

with Bridge Adapter.

Customer not receiving

any benefit from their

investment in solar energy.

Without a phase-phase

voltage difference, PV

system cannot start up.

X

Page 22: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Temporary Repairs - PhazeSaver

Customer Utility

Meter

Customer

Supply

Panel

Building

Load

Side-off repaired temporarily

with PhazeSaver device.

Open PV System Breaker

or Disconnect to prevent

back feed to PhazeSaver.

A phase-phase voltage

difference now exists,

PV system will start up.

X

Page 23: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Keeping Information Up-To-Date

Page 24: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Breaker/Disconnect Location

• Must be shown on the One-Line Diagram which must be

posted near the meter to which the PV is connected.

Page 25: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Breaker/Disconnect Location

• If Breaker/Disconnect is

not within 10 feet of the

meter, the customer

must have signage

indicating their location.

Page 26: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Other Specifications Governing Solar

• EO-2115 – Handbook of General Requirements for

Electrical Service to Dispersed Generation Customers

• MEP-183 – Guidelines for Installation and Removal of

Temporary Bridging Adapters

• B-258 - Use of PhazeSavers and Servisavers at Locations

with Distributed Generation

Page 27: Distributed Generation Safe Work Proceduresesafetyline.com/eei/conference s/2017spring... · Electric 3.3 million (2.4 Network) One of the world’s largest UG systems All 5 boroughs

Distributed Generation

Safe Work Procedures

Griffin Reilly

Section Manager

Targeted Demand Management

Energy Efficiency and Demand Management

Consolidated Edison Company of New York, Inc.