3 Appendix I District Minor Works (DMW) Projects in the Southern District 2014-2015 Proposed Works Projects discussed by Members during site visit Project Title Proponent Proposed Scope of Works Comments after site visit 1. Installation of flower pots on pavement railings at Repulse Bay Road Note 1 (Annex 1-3) Mr. FUNG Se-goun, Fergus Installing flower pots on pavement railings at three proposed locations (near No.4 Repulse Bay Road, near No.16 Repulse Bay Road and near the roundabout at Repulse Bay Road and South Bay Road ) Agree-in-principle to carry out preliminary feasibility study. While LCSDs initial comment was that it had no objection to the proposed project, the sites were narrow which might be difficult for greening maintenance. Besides, comments from TD and HyD should be sought for the project. The exact locations will be confirmed in detailed design stage after consulting the project proponent. 2. Construction of a rainshelter for bus stop near No. 11 Chung Hom Kok Road Note 2 (Annex 4) Mrs. CHAN LEE Pui-ying To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study. Attending members noted the proposed location was quite narrow and there was a more spacious site nearby. Members agreed that if preliminary study found that the proposed location was not feasible, the spacious site nearby would be considered and TD would be requested to adjust the bus stop location slightly to accommodate. 3. Construction of a rainshelter for bus stop near No. 39 Chung Hom Kok Road Note 2 (Annex 5) Mrs. CHAN LEE Pui-ying To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study. 4. Construction of a rainshelter for bus stop near No. 52 Chung Hom Kok Road Note 2 (Annex 6) Mrs. CHAN LEE Pui-ying To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study. 5. Construction of a rainshelter for bus stop near No. 53 Chung Hom Kok Road Note 2 (Annex 7) Mrs. CHAN LEE Pui-ying To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

Upload: lamanh

Post on 20-Apr-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

3

Appendix I

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Project Title Proponent Proposed Scope of Works Comments after site visit

1. Installation of flower pots on

pavement railings at Repulse

Bay Road Note 1

(Annex 1-3)

Mr. FUNG

Se-goun, Fergus

Installing flower pots on

pavement railings at three

proposed locations (near No.4

Repulse Bay Road, near

No.16 Repulse Bay Road and

near the roundabout at

Repulse Bay Road and South

Bay Road )

Agree-in-principle to carry out preliminary feasibility study.

While LCSD’s initial comment was that it had no objection to

the proposed project, the sites were narrow which might be

difficult for greening maintenance. Besides, comments from

TD and HyD should be sought for the project. The exact

locations will be confirmed in detailed design stage after

consulting the project proponent.

2. Construction of a rainshelter

for bus stop near No. 11

Chung Hom Kok Road Note 2

(Annex 4)

Mrs. CHAN LEE

Pui-ying

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

Attending members noted the proposed location was quite

narrow and there was a more spacious site nearby. Members

agreed that if preliminary study found that the proposed

location was not feasible, the spacious site nearby would be

considered and TD would be requested to adjust the bus stop

location slightly to accommodate.

3. Construction of a rainshelter

for bus stop near No. 39

Chung Hom Kok Road Note 2

(Annex 5)

Mrs. CHAN LEE

Pui-ying

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

4. Construction of a rainshelter

for bus stop near No. 52

Chung Hom Kok Road Note 2

(Annex 6)

Mrs. CHAN LEE

Pui-ying

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

5. Construction of a rainshelter

for bus stop near No. 53

Chung Hom Kok Road Note 2

(Annex 7)

Mrs. CHAN LEE

Pui-ying

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

Page 2: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

4

Project Title Proponent Proposed Scope of Works Comments after site visit

6. Construction of a rainshelter

for bus stop near No. 8 Cape

Road Note 2

(Annex 8)

Mrs. CHAN LEE

Pui-ying

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

7. Repaving the footpath next to

Stanley Post Office to Stanley

Main Street with anti-skid

materials Note 2

(Annex 9)

Mrs. CHAN LEE

Pui-ying

To repave the footpath with

anti-skid materials

Agree-in-principle to carry out preliminary fesaibility study.

8. Construction of a rainshelter

for bus stop near Regalia Bay

on Wong Ma Kok Road Note 2

(Annex 10)

Mrs. CHAN LEE

Pui-ying

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

9. Improvement works to the

staircase linking Lei Tung

Estate and Yuk Kwai Shan

Pavilion Note 3

(Annex 11)

Mr. LO Kin-hei To widen the staircase

To install handrails on the

side without them

Agree-in-principle to carry out preliminary feasibility study.

Attending members agreed that the comments from related

departments (e.g. WSD) should be sought. Also, members

agreed to also study the possibility of adding some “passing

place” at some locations as an alternative to staircase

widening.

10. Construction of a rainshelter

for bus stop on Ap Lei Chau

Bridge Road near Lee Chi

Road (South Horizons bound)

Note 3(Annex 12)

Ms. CHEUNG

Sik-yung

To construct a rainshelter Agree-in-principle to carry out preliminary feasibility study.

11. Improvement works to the

staircase leading to Wind

Tower Park near the

roundabout of Lee Chi Road

Note 3 (Annex 13)

Ms. CHEUNG

Sik-yung To repair the railings

To repave the stairs

Attending members noted that no relevant department had

taken up the maintenance responsibility of the existing railings

and agreed to repair the railings first with the funding from

“Minor improvement works 2014-15”. The Secretariat has

asked the Works Section to follow up after the site visit. On

suggestion to reconstruct the stairs, members agreed that it

should be considered after the improvement works to the steel

staircase nearby has completed.

Page 3: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

5

Project Title Proponent Proposed Scope of Works Comments after site visit

12. Improvement and extension

works to the sitting out area at

Wah Lam Path Note 4

(Annex 14)

Mr. LO Kin-hei To extend and connect the

existing sitting out area to

the adjacent site

To install benches with

cover and fitness

equipments for elderly

Greening the sitting out

area

To open an exit linking

Wah Lam Path near

minibus stop

Agree-in-principle to carry out preliminary feasibility study.

Attending members noted LCSD’s initial comments that as

there was an unregistered slope in the proposed location,

LCSD would study the implication of the slope on cost and

works scale. Besides, the connectivity between the extended

area and the existing sitting out area should also be considered.

13. Improvement works to the

fencing at the promenade of

Waterfall Bay Park Note 4

(Annex 15)

Mr. LO Kin-hei To reconstruct the fencing

with more durable

materials (e.g. stainless

steel, concrete )

Tree pruning for better

viewing

Agree-in-principle to carry out preliminary feasibility study.

Attending members agreed to replace the existing taller

fencing with railings.

LCSD would follow up with pruning the trees regularly.

14. To construct a trail along the

rocky shore at Sandy Bay

Note 5 (Annex 16)

Mr. Paul

ZIMMERMAN To construct a trail to connect

the rocky shore at Sandy Bay

to (1) the staircase linking

Victoria Road and (2) HKU

Sports Centre

Agree-in-principle to carry out preliminary feasibility study.

Attending members noted that some areas on site involved

temporary land allocation to government departments and it

would be necessary to accommodate and follow up with

relevant departments (e.g. WSD and DSD) when

implementing the project.

Note 1: Members attended this item include: Mr. AU Lap-sing, Mr. CHAI Man-hon, Ms. CHAN Judy Kapui, Ms. CHEUNG Sik-yung,

Mr. FUNG Se-goun, Ms. LAM Yuk-chun, MH, Dr. LIU Hong-fai, JP, Mr. LO Kin-hei, and Ir CHAN Lee-shing, William, JP.

Note 2: Members attended this item include: Mr. AU Lap-sing, Mr. CHAI Man-hon, Ms. CHAN Judy Kapui, Mrs. CHAN LEE Pui-ying,

Ms. CHEUNG Sik-yung, Mr. FUNG Se-goun, Ms. LAM Yuk-chun, MH, Dr. LIU Hong-fai, JP, Mr. LO Kin-hei, and

Ir CHAN Lee-shing, William, JP.

Page 4: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

6

Note 3: Members attended this item include: Mr. AU Lap-sing, Mr. CHAI Man-hon, Ms. CHAN Judy Kapui, Mrs. CHAN LEE Pui-ying,

Ms. CHEUNG Sik-yung, Ms. LAM Yuk-chun, MH, Dr. LIU Hong-fai, JP, Mr. LO Kin-hei, and Ir CHAN Lee-shing, William, JP.

Note 4: Members attended this item include: Mr. AU Lap-sing, Mr. CHAI Man-hon, Dr. LIU Hong-fai, JP, Mr. LO Kin-hei, and

Ir CHAN Lee-shing, William, JP.

Note 5: Members attended this item include: Mr. AU Lap-sing, Mr. CHAI Man-hon, Dr. LIU Hong-fai, JP, Mr. LO Kin-hei,

Mr. Paul ZIMMERMAN and Ir CHAN Lee-shing, William, JP.

Page 5: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 1

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Installation of flower pots on pavement railings at Repulse Bay Road -

near No.4 Repulse Bay Road

Approximate Location

Page 6: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 2

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Installation of flower pots on pavement railings at Repulse Bay Road -

near No.16 Repulse Bay Road

Approximate Location

Page 7: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 3

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Approximate Location

Installation of flower pots on pavement railings at Repulse Bay Road -

near the roundabout at Repulse Bay Road and South Bay Road

Page 8: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 4

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Construction of a rainshelter for bus stop near No. 11 Chung Hom Kok Road

Location

Alternative Location

Page 9: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 5

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Construction of a rainshelter for bus stop near No. 39 Chung Hom Kok Road

Page 10: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 6

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Construction of a rainshelter for bus stop near No. 52 Chung Hom Kok Road

Page 11: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 7

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Construction of a rainshelter for bus stop near No. 53 Chung Hom Kok Road

Page 12: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 8

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Construction of a rainshelter for bus stop near No. 8 Cape Road

Page 13: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 9

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Repaving the footpath next to Stanley Post Office to Stanley Main Street with anti-skid

materials

Page 14: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 10

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Construction of a rainshelter for bus stop near Regalia Bay on Wong Ma Kok Road

Location

Page 15: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 11

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Improvement works to the staircase linking Lei Tung Estate and

Yuk Kwai Shan Pavilion

Location

Page 16: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 12

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Construction of a rainshelter for bus stop on Ap Lei Chau Bridge Road

near Lee Chi Road (South Horizons bound)

Page 17: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 13

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Improvement works to the staircase leading to Wind Tower Park near the roundabout of

Lee Chi Road

Page 18: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 14

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Improvement and extension works to the sitting out area at Wah Lam Path

Location

Page 19: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 15

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

Location

Improvement works to the fencing at the promenade of Waterfall Bay Park

Page 20: District Minor Works (DMW) Projects in the Southern District … ·  · 2014-12-30District Minor Works ... Proposed Works Projects discussed by Members during site visit Construction

Annex 16

District Minor Works (DMW) Projects in the Southern District 2014-2015

Proposed Works Projects discussed by Members during site visit

To construct a trail along the rocky shore at Sandy Bay

Approximate Location