d.m. wills associates limited - peterborough...the trent university tributaries (aecom, 2012). the...
TRANSCRIPT
-
Regulatory Floodplain
Assessment Report
City of Peterborough Recreation
Centre at Trent University
2330 University Road
Peterborough, Ontario
D.M. Wills Project No. 15-10706
D.M. Wills Associates Limited PARTNERS IN ENGINEERING
Peterborough
North Bay
June 2016
Prepared for:
City of Peterborough
-
Table of Contents
1.0 Introduction ................................................................................................................... 1
2.0 Site Description .............................................................................................................. 1
3.0 Topographic Information .............................................................................................. 2
4.0 Background Information ............................................................................................... 2
5.0 Hydrologic Analysis ...................................................................................................... 4
5.1 Watershed Delineation and Characterization .......................................................... 4
5.2 Hydrologic Analysis Methodologies ............................................................................ 6
5.2.1 Rational Method ..................................................................................................... 6
5.2.2 Hydrologic Model ................................................................................................... 6
5.3 Hydrologic Analysis Results ........................................................................................... 6
6.0 Hydraulic Analysis ......................................................................................................... 8
6.1 Hydraulic Model Development ................................................................................... 8
6.2 Model Results .................................................................................................................. 8
7.0 Conclusion ................................................................................................................... 10
List of Figures
Figure 1 - Location Plan ............................................................................................................... 3
Figure 2 - Drainage Area Plan .................................................................................................... 5
List of Tables
Table 1 - Catchment Parameters ............................................................................................... 6
Table 2 - Estimated Peak Flows ................................................................................................... 7
Table 3 - Estimated Regional Storm Peak Flows for Hydraulic Model ................................... 7
Table 4 - Hydraulic Model Results ............................................................................................... 9
List of Appendices
Appendix A - Hydrologic Analysis
Appendix B - Hydraulic Analysis
Appendix C - Drawings
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 1 Project Number 15-10706
1.0 Introduction
D.M. Wills Associates Limited (Wills) has been retained by the City of Peterborough as
part of an architecture/engineering design team led by architect Perkins+Will to
complete the planning and detailed design of a new City of Peterborough Recreation
Centre at Trent University. As part of the scope of work for the project, Wills is
responsible for the preparation of a Regulatory Floodplain Assessment for the tributaries
that cross the site, which is located at 2330 University Road in Peterborough, Ontario.
The tributaries, which generally flow northeast to southwest across the site, drain to the
Trent Severn Waterway canal; however they were formerly part of Thompson Creek,
which was split into two (2) segments when the canal was built through Peterborough.
The lower part of the watershed continues to be called Thompson Creek while the
upper part of the watershed, of which the project site is a part, has been referred to as
the Trent University Tributaries (AECOM, 2012). The Trent University Tributaries appear to
be of an ephemeral nature, only having flow during periods of snowmelt and rainfall.
The purpose of this study is to provide an updated Regulatory Floodplain Assessment for
the Trent University Tributaries that can be used as the basis for future planning and
development decisions for the Peterborough Recreation Centre at Trent University
Project. To achieve the stated purpose, Wills undertook the following activities:
1. Coordination of a topographic survey within and around the study area.
2. A site inspection to measure existing culverts and estimate the Manning’s
roughness coefficients for the main channel and overbank areas.
3. An assessment of future development conditions within the watershed based on
the Trent Lands Plan and knowledge of proposed developments in the area.
4. A hydrology study that considered the future development conditions and
included an assessment of multiple methodologies for the determination of peak
flows.
5. Development of a hydraulic model for the Trent University Tributaries.
6. Mapping of the Regulatory Floodline on the topographic survey.
The above noted activities and the results of the various investigations are described in
detail in the sections below and supporting materials (calculations, documentation,
etc.) are provided in the appendices. All work was undertaken in accordance with the
Technical Guide - River and Stream Systems: Flooding Hazard Limit (MNR, 2002).
2.0 Site Description
The subject property is located southeast of the intersections of Nassau Mills Road and
University Road and Nassau Mills Road and Pioneer Road and is legally described as
Part of Lots 5 and 6, Concession 10 and Part of Lots 5 and 6, Concession 11 in the
Geographic Township of Douro, County of Peterborough, City of Peterborough. The
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 2 Project Number 15-10706
surrounding land uses include agricultural and wooded areas as well as institutional
lands (Trent University). The location of the site is shown in Figure 1.
The Trent University Tributaries generally flow from northeast to southwest across the
subject property from south of Pioneer Road to east of University Road, a distance of
approximately 840 m. Two (2) tributaries cross the subject property, one (1) on the
eastern boundary of the property and one (1) on the west side of the property. Each
tributary conveys runoff from a small drainage area upstream of Pioneer Road and
from the subject property itself. The tributaries are divided by a ridge / plateau, where
the proposed Peterborough Recreation Centre development will be located. The
tributaries are generally flat having longitudinal slopes ranging from 0.3% to 1.1%. The
area immediately upstream of University Road is extremely flat and is mostly inundated
during runoff events (rainfall and snowmelt).
3.0 Topographic Information
Multiple sources of topographic information were used as part of this project. The City
of Peterborough 0.5 m contours were the primary source of topographic information for
the hydrology study, however, the data did not extend far enough beyond Douro 9th
Line; therefore, the Ontario Base Map (OBM) 5.0 m contours were used to supplement
the City of Peterborough contours. Topographic survey for the subject property and
surroundings was used to define the cross-sections within the hydraulic model. The
topographic survey was completed by Beninger Surveying Ltd., dated April 13, 2016.
The survey is geodetic and the elevations were based on the City of Peterborough
Control Monument 099940006, having an elevation of 213.717 m.
4.0 Background Information
The Trent University Tributaries were studied, on a high level, by AECOM as part of their
Un-named City Tributaries Flood Reduction Study Master Plan completed in March 2012.
AECOM completed a hydrology study for the Trent University Tributaries by delineating
the catchment area upstream of University Road and calculating peak flows using a
SWMHYMO hydrologic model. The catchment area delineated by AECOM at University
Road had an area of approximately 300 ha, a 100-year peak flow of approximately
4.9 m3/s and a Timmins Storm peak flow of approximately 12.8 m3/s.
AECOM completed a hydraulic analysis for the University Road crossing and the major
tributary located east of the subject property. The Timmins Storm Floodline defined by
AECOM is provided in Appendix B. The AECOM plan shows a portion of the floodline on
the subject property.
Based on our review of the AECOM data, we understand that the high-level analysis
was not as detailed as the analysis being carried out under this assignment; therefore,
the hydrology and floodplain delineation defined as part of this study will supersede the
hydrology and floodplain delineation provided in the AECOM study.
-
5TH LINE
7TH LINE
DO
UR
O 8TH
LINE
3RD L
INE
NASSAU
ROAD
COUN
TY R
OAD
4
COUN
TY R
OAD
32
CENTRE
ROAD
MANIECE
AVENUE
BRADFIELD ROAD
UN
IVERSITY R
OAD
DO
UR
O 9TH
LINE
WES
T BA
NK D
RIVE
BUR
NH
AM LIN
E
DR
UM
MO
ND
LINE
DO
UR
O 7TH
LINE
CHAM
PLAI
N DR
IVE
TELEVISION
RO
AD
CA
NA
L R
OA
D
CEN
TRE LIN
E
LANGTON
STREET
6TH LINE
HIGHWAY
7
PIONEER
ROAD
NAS
SAU
MILLS
RO
AD
ME
DIC
AL
DR
IVE
TOWE
RHILL
ROAD
HILLIARD STREET
MIL
ROY
DRIV
E
WOODLA
ND DRIVE
WAT
ER S
TREE
T
LAKE
FIEL
D R
OAD
CHEMONG ROAD
OLD NORWOOD ROAD
DR
UM
MO
ND
LINE
CEN
TRE LIN
EC
ENTR
E LINE
5TH LINE
HIGHWAY
7
6TH LINE DO
UR
O 8TH
LINE
BUR
NH
AM LIN
E
6TH LINE
DO
UR
O 9TH
LINE
NASSAU
ROAD
LAKE
FIEL
D R
OAD
Figure 1 - Location Plan
o
0 650 1,300 1,950325 m
NAD83 UTM Zone 17 North
LegendHighwayRampArterialLocalWetlandLakesWatercourseWoods
D.M. Wills Associates Limited150 Jameson DrivePeterborough, OntarioK9J 0B9
P. 705.742.2297F. 705.741.3568E. [email protected]
Drawn by:CH
Checked by:DG
Engineer:DG
Project No.:10706
Map File No.:10706 - Flood
Scale (Horz.):
Map Date:06/09/16
1:50,000
Peterborough
SITE
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 4 Project Number 15-10706
5.0 Hydrologic Analysis
5.1 Watershed Delineation and Characterization
The drainage area for the Trent University Tributaries was delineated in ArcGIS 10.3.1 for
Desktop using the OBM stream network, City of Peterborough contours (0.5 m interval),
OBM contours (5.0 m interval) and aerial photography. The Trent University Tributaries
generally drain from northeast to southwest and are generally flat with a main channel
slope ranging from 0.3% to 1.1%. The contributing areas are predominantly agricultural
with pockets of wetlands as well as wooded areas throughout the drainage area. The
drainage area plan is provided in Figure 2.
Hydrologic parameters such as soil infiltration properties and runoff response were
determined based on literature review. The Soils Map of Peterborough County (Soil
Survey Report No. 45) shows that the site soils consist primarily of Otonabee Loam and
Foxboro Silt Loam. According to the SCS method of classifying soils, and knowledge of
local soil conditions, these types of surficial soils correspond to Hydrologic Soils Groups B
and AB, respectively. The land cover data is based on the Ontario Land Cover
Compilation (MNRF), which combines the Provincial Land Cover Database, Far North
Land Cover and Southern Ontario Land Resource Information System. Rainfall data was
obtained from the City of Peterborough IDF curves. The Timmins Storm is the Regional
Storm within the Otonabee Region Conservation Authority jurisdiction. The Regulatory
Storm is the greater of the 100-year storm and the Regional Storm.
According to the Technical Guide - River and Stream Systems: Flooding Hazard Limit
(MNR, 2002), the Regulatory Floodplain should be based on the future development
conditions within the drainage area. The future development conditions should be
based on official municipal land use planning documents and the planning horizon
should preferably extend 20 years into the future. The City of Peterborough Official Plan
(Schedule A - Land Use) identifies the subject property as Major Open Space and the
remainder of the drainage area as Major Institution. The Trent Lands Plan (Land Use
Framework Plan) provides additional details regarding the proposed development on
the Trent University Lands. Copies of the City of Peterborough Official Plan Schedule A
and Trent Lands Plan Land Use Plan Framework Plan are provided in Appendix A. This
study assumes that stormwater controls will be implemented for all future
developments; therefore, future peak flows will be the same as existing peak flows.
For the purposes of entering flows into the hydraulic model, the drainage area was
broken down into six (6) sub-catchments. A summary of the catchment parameters is
provided in Table 1 and additional details are included in Appendix A.
-
!(101
!(102
!(103
!(105
!(104!(106
225
245
250
255
220
260
215
210
230
235
265
270
275
205
240
200
280
285
235
205
215
235
220
235
235
230
260
230
215
215
225
235
225
205
270
220
230
275 220
205
225
235
245
245
210
280
255
210
235
235
220
230
210
240
215
230
220
235
215
225
265
225
225
225
210
220
275
220
225
235
235
220
225
265
205
245
235
220
230
250
235
240
245
240
235
230
240
230
210
220
210 2
10
225
230
210
240
230
260
250
205
230
235
225
235
240
245
230
280
230
225
240
215
235
235
225
250
240
225
240
240
210
235
220
250
210
210
235
210
205
225
220
215
230
210
265
220
220
230
215
210
245
240
5TH LINE
UN
IVERSITY R
OAD
DO
UR
O 9TH
LINEW
ATER
STR
EET
CHAM
PLAI
N DR
IVE
DO
UR
O 8TH
LINE
NASSAU
ROAD
ARM
OUR
ROAD
EA
ST
BA
NK
DR
I VE
NAS
SAU M
ILLS RO
AD
COUN
TY R
OAD
4
WOODLA
ND DRIVE
LAK
EFI
ELD
RO
AD
CAR
NEG
IE AVENU
E
ARM
OU
R R
OAD
5TH LIN
E
DO
UR
O 8TH
LINE
DO
UR
O 9TH
LINE
Figure 2 - Drainage Area Plan
o
0 300 600 900150 m
NAD83 UTM Zone 17 North
LegendCatchmentArterialLocalOBM ContourWatercourseWetlandLakesWoods
D.M. Wills Associates Limited150 Jameson DrivePeterborough, OntarioK9J 0B9
P. 705.742.2297F. 705.741.3568E. [email protected]
Drawn by:CH
Checked by:DG
Engineer:DG
Project No.:10706
Map File No.:10706 - Flood
Scale (Horz.):
Map Date:06/09/16
1:25,000
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 6 Project Number 15-10706
Table 1 - Catchment Parameters
Catchment
ID
Area
(ha)
Length
(m)
Slope
(%)
Imperv.
(%) CN*
Initial Abstraction
(mm)
Time to Peak
(hr)
WS 101 163.91 3900 0.6 1.4 72.5 6.7 2.32
WS 102 91.79 2500 1.1 5.1 73.0 6.4 1.52
WS 103 39.45 1780 1.3 2.5 71.9 7.0 1.76
WS 104 7.47 500 0.6 4.4 64.8 7.9 0.89
WS 105 9.59 600 0.3 6.7 68.7 7.2 1.13
WS 106 2.52 355 1.1 20.4 54.2 8.9 0.55
Note: For WS106, the hydrologic model uses CN* for the pervious area only.
5.2 Hydrologic Analysis Methodologies
The hydrologic analysis was completed using two (2) methodologies, the Rational
Method and hydrologic modelling. The methodologies are outlined below in more
detail.
5.2.1 Rational Method
The Rational Method is one of the earlier developed methods of calculating peak flows.
In spite of the availability of advanced computational techniques, it remains a valid
approach to peak flow estimation for small drainage areas. The applications of this
method are typically limited to watersheds less than 100 ha in size. The Rational Method
estimates peak flows using the drainage area, rainfall intensity (based on local IDF
values) and the runoff coefficient (determined based on land use). The Rational
Method will only be used as a check for the hydraulic model results for this study.
5.2.2 Hydrologic Model
The hydrologic modelling software Visual OTTHYMO Version 3.0 (VO3) was used to
model the Trent University Tributaries. VO3 is a single event hydrologic model used to
simulate hydrographs by modeling rainfall, infiltration, runoff and routing through the
watershed. The drainage areas were modelled as individual catchments using the
parameters described in Section 5.1. The model layout is provided in Appendix A. A
number of AddHyd commands were used to estimate the peak flows at key locations
required for input into the hydraulic model. Various distributions for the 100-year storm
were tested within the model including the 12-hour and 24-hour SCS Type II storm
distributions and 6-hour and 12-hour AES storm distributions. The Regional Storm within
the Otonabee Region Conservation Authority jurisdiction is the 12-hour 193 mm Timmins
Storm distribution. The results of the hydrologic model are provided in Section 5.3.
5.3 Hydrologic Analysis Results
The 100-year and Regional Storm peak flows for the Trent University Tributaries,
calculated using the hydrologic model, are provided in Table 2. The detailed output
from the hydrologic model is included in Appendix A.
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 7 Project Number 15-10706
Table 2 - Estimated Peak Flows
Design
Storm
Peak Flows(m3/s)
WS 101 WS 102 WS 103 WS 104 WS 105 WS 106
100-Year 3.09 2.46 0.91 0.22 0.28 0.07
Regional 7.36 4.80 1.94 0.40 0.50 0.12
Note: The 100-year results shown are for the 6-hour AES storm distribution.
In the Otonabee Region Conservation Authority jurisdiction, the Regulatory Flow is
defined as the 100-year peak flow or the Regional Strom peak flow, whichever is
greater. Based on the data presented in Table 2, the Regulatory Flow will be the peak
flow generated by the Regional (Timmins) Storm.
The peak flows from the hydrologic model will be used within the hydraulic model to
estimate the Regulatory water surface elevations. There are multiple tributaries that
intersect to form the Trent University Tributaries. This is represented in the hydraulic
model by changing / adding flows at the locations where those tributaries intersect the
tributaries being modelled. AddHyd commands were used within the hydrologic model
to estimate the peak flows at these key locations. The peak flows at the key locations
to be used in the hydraulic model are provided in Table 3.
Table 3 - Estimated Regional Storm Peak Flows for Hydraulic Model
Model Node Location Drainage Areas
Included (WS)
Model Node ID
(NHYD)
Peak Flow
(m3/s)
Outlet of WS 102 102 102 4.80
Confluence of WS 101, 102, 103 and 104 101, 102, 103, 104 8 14.20
Outlet of WS 105 105 105 0.50
University Road Crossing 101, 102, 103,
104, 105, 106 11 14.75
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 8 Project Number 15-10706
6.0 Hydraulic Analysis
6.1 Hydraulic Model Development
The one dimensional, steady-state HEC-RAS Version 4.1 hydraulic model, developed by
the U.S. Army Corps of Engineers, was used for the hydraulic analysis of the Trent
University Tributaries to determine the location of the existing Regulatory Floodline. The
existing topography upstream and downstream of the development, is inserted into the
model as cross-sections. The cross-sections are based on detailed topographic
information collected by Beninger Surveying Ltd. in April 2016. Roughness coefficients
for the channel and overbank areas were estimated from field inspection and literature
review and are reflective of a clean, winding channel with scattered brush (0.05) and
heavy stand of timber, with few down trees, little undergrowth and flow below
branches (0.10).
The HEC-RAS model was created using three (3) separate reaches, representing the
different tributaries that cross the subject property. Reach 3 begins just downstream of
University Road (Reach 3, Cross-Section 0+010) and extends to just upstream of
University Road at the confluence of Reach 1 and Reach 2 (Reach 3, Cross-Section
0+202), a distance of approximately 190 m. The intersection of Reach 1 and Reach 2 is
represented in the model as a junction (Junction A). Reach 1 begins at Junction A and
extends to just downstream of Pioneer Road (Reach 1, Cross-Section 0+751), a distance
of 751 m. Reach 2 begins at Junction A and extends to just downstream of Pioneer
Road (Reach 2, Cross-Section 0+525), a distance of 525 m. The model includes twenty-
four (24) cross-sections that represent both the main channel and overbank (floodplain)
areas. Survey data was the primary source for the cross-section stations and elevations;
however, contour data from the City of Peterborough was used to supplement the
survey in some areas.
The HEC-RAS model requires a downstream starting water surface elevation, which can
be based on critical depth, normal depth, a rating curve or a known hydraulic control.
In this case, the downstream water surface elevation is based on normal depth at a
channel slope of 1.0%. The results of the HEC-RAS model are discussed in Section 6.2
and the detailed output is included in Appendix B.
6.2 Model Results
The HEC-RAS model sections and the Regulatory Floodplain are shown on Drawing
10706-FP01, included in Appendix C. The hydraulic model results are shown in Table 3
and the detailed model output is included in Appendix B.
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 9 Project Number 15-10706
Table 4 - Hydraulic Model Results
Reach Station
Peak
Flow
(m3/s)
Regulatory
Water Surface
Elevation (m)
Channel
Velocity
(m/s)
Top
Width
(m)
Comments
1 751 4.80 217.71 1.25 25.3 Upstream End Reach 1 - Pioneer Road
1 734 4.80 217.60 0.79 33.2
1 668 4.80 216.82 1.77 27.9
1 587 4.80 216.58 0.52 35.6
1 513 4.80 216.22 1.76 29.7
1 437 4.80 215.89 0.20 120.3
1 361 4.80 215.89 0.14 89.3
1 296 4.80 215.88 0.12 104.4
1 252 4.80 215.88 0.10 114.2
1 203 4.80 215.88 0.12 128.2
1 155 4.80 215.87 0.23 74.4
1 088 14.20 215.60 1.55 76.7
1 021 14.20 215.44 0.42 121.1 Downstream End Reach 1 - Junction A
2 525 0.50 216.20 0.39 6.2 Upstream End Reach 2 - Pioneer Road
2 505 0.50 216.00 0.77 10.6
2 443 0.50 215.45 0.04 23.6
2 383 0.50 215.45 0.03 28.6
2 306 0.50 215.45 0.01 70.5
2 230 0.50 215.45 0.01 100.0 Downstream End Reach 2 - Junction A
3 202 14.75 215.44 0.13 414.8 Upstream End Reach 3 - Junction A
3 182 14.75 215.44 0.13 417.1
University Road Culvert
C03 - 700 mm CSP, Main Channel
C01 - 300 mm CSP, Secondary Pipe
C02 - 500 mm CSP, Secondary Pipe
C04 - 500 mm HDPE, Secondary Pipe
3 154 14.75 214.81 0.43 316.5
3 113 14.75 214.76 0.61 262.6
3 010 14.75 214.46 1.22 61.1 Downstream end of Model
A review of the HEC-RAS model results shows that the majority of the site is affected by
the headwater elevation of the University Road culvert. The maximum flood depth on
University Road was estimated as 0.22 m; therefore, there is safe access across this
route.
-
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Associates Limited Page 11 Project Number 15-10706
Statement of Limitations
This report has been prepared by D.M. Wills Associates Limited on behalf of the City of
Peterborough to provide a Regulatory Floodplain Assessment Report for City of
Peterborough Recreation Centre at Trent University, which is located at 2330 University
Road in Peterborough, Ontario.
The conclusions and recommendations in this report are based on available
background documentation and discussions with applicable agencies at the time of
preparation.
The report is intended to define the Regulatory Floodplain Elevations in the area of the
proposed City of Peterborough Recreation Centre. The report is applicable only to the
project described in the text, constructed substantially in accordance with the
approved plans and details accompanying this report.
Any use which a third party makes of this report other than that of a Regulatory
Floodplain Assessment Report for City of Peterborough Recreation Centre at Trent
University is the responsibility of such third parties. D.M. Wills Associates Limited accepts
no responsibility for damages, if any, suffered by a third party as a result of decisions
made or actions taken based on using this report for purposes other than a Regulatory
Floodplain Assessment Report.
-
Appendix A
Hydrologic Analysis
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
111.03 18.20 ha Gauging Station = Peterborough0.00 0.00 ha 100 Yr Rainfall depth = 90.4 mm0.00 0.00 ha4.31 2.05 ha
11.70 14.35 ha Drainage Area 163.91 ha0.00 0.00 ha Impervious Area 2.27 ha2.00 0.27 ha Percent Impervious 1.4 %
129.04 34.86Pervious
B AB Length 3900 mUS Elev 240.0 mDS Elev 215.5 m
0.24 0.15 Slope 0.6 %CN (Nashyd) 71.7 60.5 Flat
Incl. Not Incl.Agriculture Range Grass Woods Wetland Imperv. Imperv. Imperv.
Nashyd StandhydB 0.26 0.14 0.08 0.08 0.05 0.76 0.90 0.24
AB 0.22 0.12 0.07 0.07 0.05 0.67 0.90 0.15
B 74 65 61 58 50 91 98 71.7 71.2AB 70 51 50 44 50 89 98 60.5 60.2
3900 mAverage Slope 0.6 % Drainage Area 163.91 ha
Airport 207.9 min. Runoff Coefficient Bransby - Williams 146.5 min. SCS Curve No. 69.3 68.9
Uplands - min. 72.5 72.4139.3 min. 6.7 6.82.32 hr.
Notes:1. Hydrologic Soil Group obtained from Design Chart H2-6A, M.T.O. Drainage Manual, 1980.2. Runoff coefficient obtained from M.T.O. Design Chart 1.07, M.T.O. Drainage Management Manual, 1997, Hydrologic Analysis and Design, McCuen 2004 and New Jersey Technical Manual for Stream Encroachment, 1984.3. SCS Curve No. obtained from M.T.O. Design Chart 1.09, M.T.O. Drainage Management Manual, 1997, and Table 2-2a, TR-55, page 2-5.4. The modified curve number is adjusted as per Paul Wisner & Associates (1982) and represents anticedent moisture conditions Type II5. Initial Abstraction values taken from the Environmental and Engineering Services Department, The Corporation of the City of London, Dec 20056. Use Airport Equation to calculate time of concentration for C 0.4.5. Minimum Time to Peak for use in the Rational Method and Hydrologic Model is 10 minutes
0.22
5 106 8
Land Use
Time to Peak7
SUM
Modified Curve No.4, CN*
Bare Earth (>70% Rock)
Parameter
Initial Abstraction5, mm
Runoff Coefficient2, C
SCS Curve No.3, CN
C
Foxboro Silt Loam
Total Length
Initial Abstraction.
22.510
Sheet 1 of 4
n.a.
Time of Concentration6 Composite Parameters
Land Use Weighted Value
WetlandBare Earth (>70% Rock)
Impervious
Hydrologic Soil Group1
Soil Type Otonabee Loam
AgricultureRangeGrass
Woods
Hydrologic Parameters for WS 101
Rainfall Data
6.86.7
Flat: 0-2% SlopesRolling: 2-6% SlopesHilly: >6% Slopes
Hydrology Calculations WS 101
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
Drainage Area A = 163.91 haPercent Impervious % Imp = 1.4 %Slope S = 0.6 %
Peterborough IDF Parameters2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
a = 662 1098 1560 2010 2200 2507b = 7.5 10.1 13.0 14.0 14.6 14.8c = 0.79 0.83 0.86 0.88 0.87 0.88
Development Area C-value Tc Int. FlowCondition (ha) (min) (mm/hr) (m3/s)
25 mm Storm 163.91 0.22 208 6.94 0.712 Year 163.91 0.22 208 9.50 0.975 Year 163.91 0.22 208 12.58 1.2810 Year 163.91 0.22 208 15.03 1.5325 Year 163.91 0.25 208 17.32 1.9450 Year 163.91 0.27 208 19.96 2.44
100 Year 163.91 0.28 208 21.53 2.75
Notes :
1. Rainfall intensity rainfall data obtained for Peterborough2. For storms having return period of more than 10 years the runoff coefficient was increased as follows to a maximum value of 0.95.
25 yr: add 10%50 yr: add 20%
100 yr: add 25%
3. IDF parameters for the 25 mm storm: a: 405b: 3.0c: 0.76
Rational Method for WS 101 Sheet 2 of 4
Hydrology Calculations WS 101
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.695 1.19
10 1.6425 2.1050 2.73100 3.09 3.11 3.12 3.10
Regional 7.36
Notes:
1. Storm used to determine peak flow values 6hr AES
Visual Otthymo Model for WS 101
24hr SCS TimminsDesign Storm (yr) 1hr AES 6hr AES 12hr AES 12hr SCS
Sheet 3 of 4
Hydrology Calculations WS 101
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.97 0.695 1.28 1.1910 1.53 1.6425 1.94 2.1050 2.44 2.73
100 2.75 3.09Check 2.75 3.09
Regional 7.36
Notes:
1. Method used to determine the peak flows values Visual Otthymo
Sheet 4 of 4Peak Flow Comparison for WS 101
Rational Method Visual OtthymoDesign Storm (yr)
Hydrology Calculations WS 101
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
48.48 23.97 ha Gauging Station = Peterborough0.00 0.00 ha 100 Yr Rainfall depth = 90.4 mm0.00 0.00 ha3.31 1.67 ha2.37 7.35 ha Drainage Area 91.79 ha0.00 0.00 ha Impervious Area 4.65 ha3.20 1.44 ha Percent Impervious 5.1 %
57.35 34.44Pervious
B AB Length 2500 mUS Elev 242.0 mDS Elev 215.5 m
0.28 0.20 Slope 1.1 %CN (Nashyd) 73.4 65.6 Flat
Incl. Not Incl.Agriculture Range Grass Woods Wetland Imperv. Imperv. Imperv.
Nashyd StandhydB 0.26 0.14 0.08 0.08 0.05 0.76 0.90 0.28
AB 0.22 0.12 0.07 0.07 0.05 0.67 0.90 0.20
B 74 65 61 58 50 91 98 73.4 72.0AB 70 51 50 44 50 89 98 65.6 64.2
2500 mAverage Slope 1.1 % Drainage Area 91.79 ha
Airport 136.0 min. Runoff Coefficient Bransby - Williams 89.6 min. SCS Curve No. 70.5 69.1
Uplands - min. 73.0 72.491.1 min. 6.4 6.71.52 hr.
Notes:1. Hydrologic Soil Group obtained from Design Chart H2-6A, M.T.O. Drainage Manual, 1980.2. Runoff coefficient obtained from M.T.O. Design Chart 1.07, M.T.O. Drainage Management Manual, 1997, Hydrologic Analysis and Design, McCuen 2004 and New Jersey Technical Manual for Stream Encroachment, 1984.3. SCS Curve No. obtained from M.T.O. Design Chart 1.09, M.T.O. Drainage Management Manual, 1997, and Table 2-2a, TR-55, page 2-5.4. The modified curve number is adjusted as per Paul Wisner & Associates (1982) and represents anticedent moisture conditions Type II5. Initial Abstraction values taken from the Environmental and Engineering Services Department, The Corporation of the City of London, Dec 20056. Use Airport Equation to calculate time of concentration for C 0.4.5. Minimum Time to Peak for use in the Rational Method and Hydrologic Model is 10 minutes
Hydrologic Parameters for WS 102 Sheet 1 of 4
Agriculture
Land Use Rainfall Data
Range
Bare Earth (>70% Rock)Impervious
SUM
Hydrologic Soil Group1
Soil Type Otonabee LoamFoxboro Silt
Loam
GrassWoods
Wetland
Runoff Coefficient2, C n.a.
SCS Curve No.3, CN
C
Parameter
Land Use Weighted Value
Bare Earth (>70% Rock)
2.5 2 6.4 6.7
Time of Concentration6 Composite Parameters
Initial Abstraction5, mm 6 8 5 10 10
Total Length
0.25
Modified Curve No.4, CN*
Time to Peak7Initial Abstraction.
Flat: 0-2% SlopesRolling: 2-6% SlopesHilly: >6% Slopes
Hydrology Calculations WS 102
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
Drainage Area A = 91.79 haPercent Impervious % Imp = 5.1 %Slope S = 1.1 %
Peterborough IDF Parameters2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
a = 662 1098 1560 2010 2200 2507b = 7.5 10.1 13.0 14.0 14.6 14.8c = 0.79 0.83 0.86 0.88 0.87 0.88
Development Area C-value Tc Int. FlowCondition (ha) (min) (mm/hr) (m3/s)
25 mm Storm 91.79 0.25 136 9.52 0.612 Year 91.79 0.25 136 13.09 0.835 Year 91.79 0.25 136 17.54 1.1210 Year 91.79 0.25 136 21.10 1.3425 Year 91.79 0.27 136 24.45 1.7150 Year 91.79 0.30 136 28.04 2.14
100 Year 91.79 0.31 136 30.36 2.42
Notes :
1. Rainfall intensity rainfall data obtained for Peterborough2. For storms having return period of more than 10 years the runoff coefficient was increased as follows to a maximum value of 0.95.
25 yr: add 10%50 yr: add 20%
100 yr: add 25%
3. IDF parameters for the 25 mm storm: a: 405b: 3.0c: 0.76
Rational Method for WS 102 Sheet 2 of 4
Hydrology Calculations WS 102
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.565 0.95
10 1.3125 1.6850 2.18100 2.46 2.36 2.47 2.42
Regional 4.80
Notes:
1. Storm used to determine peak flow values 6hr AES
Visual Otthymo Model for WS 102 Sheet 3 of 4
Design Storm (yr) 1hr AES 6hr AES 12hr Aes 12hr SCS 24hr SCS Timmins
Hydrology Calculations WS 102
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.83 0.565 1.12 0.9510 1.34 1.3125 1.71 1.6850 2.14 2.18
100 2.42 2.46Check 2.42 2.46
Regional 4.80
Notes:
1. Method used to determine the peak flows values Visual Otthymo
Sheet 4 of 4Peak Flow Comparison for WS 102
Design Storm (yr) Rational Method Visual Otthymo
Hydrology Calculations WS 102
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
24.29 3.37 ha Gauging Station = Peterborough0.00 0.00 ha 100 Yr Rainfall depth = 90.4 mm0.00 0.00 ha1.80 0.20 ha7.98 0.84 ha Drainage Area 39.45 ha0.00 0.00 ha Impervious Area 0.97 ha0.97 0.00 ha Percent Impervious 2.5 %
35.04 4.41Pervious
B AB Length 1780 mUS Elev 239.0 mDS Elev 215.5 m
0.22 0.18 Slope 1.3 %CN (Nashyd) 68.4 65.0 Flat
Incl. Not Incl.Agriculture Range Grass Woods Wetland Imperv. Imperv. Imperv.
Nashyd StandhydB 0.26 0.14 0.08 0.08 0.05 0.76 0.90 0.22
AB 0.22 0.12 0.07 0.07 0.05 0.67 0.90 0.18
B 74 65 61 58 50 91 98 68.4 67.5AB 70 51 50 44 50 89 98 65.0 65.0
1780 mAverage Slope 1.3 % Drainage Area 39.45 ha
Airport 110.9 min. Runoff Coefficient Bransby - Williams 66.5 min. SCS Curve No. 68.0 67.3
Uplands 157.3 min. 71.9 70.4105.4 min. 7.0 7.11.76 hr.
Notes:1. Hydrologic Soil Group obtained from Design Chart H2-6A, M.T.O. Drainage Manual, 1980.2. Runoff coefficient obtained from M.T.O. Design Chart 1.07, M.T.O. Drainage Management Manual, 1997, Hydrologic Analysis and Design, McCuen 2004 and New Jersey Technical Manual for Stream Encroachment, 1984.3. SCS Curve No. obtained from M.T.O. Design Chart 1.09, M.T.O. Drainage Management Manual, 1997, and Table 2-2a, TR-55, page 2-5.4. The modified curve number is adjusted as per Paul Wisner & Associates (1982) and represents anticedent moisture conditions Type II5. Initial Abstraction values taken from the Environmental and Engineering Services Department, The Corporation of the City of London, Dec 20056. Based on the results of the Uplands Method5. Minimum Time to Peak for use in the Rational Method and Hydrologic Model is 10 minutes
Hydrologic Parameters for WS 103 Sheet 1 of 4
Agriculture
Land Use Rainfall Data
Range
Bare Earth (>70% Rock)Impervious
SUM
Hydrologic Soil Group1
Soil Type Otonabee LoamFoxboro Silt
Loam
GrassWoods
Wetland
Runoff Coefficient2, C n.a.
SCS Curve No.3, CN
C
Parameter
Land Use Weighted Value
Bare Earth (>70% Rock)
2.5 2 7.0 7.1
Time of Concentration6 Composite Parameters
Initial Abstraction5, mm 6 8 5 10 10
Total Length
0.22
Modified Curve No.4, CN*
Time to Peak7Initial Abstraction.
Flat: 0-2% SlopesRolling: 2-6% SlopesHilly: >6% Slopes
Hydrology Calculations WS 103
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
Drainage Area A = 39.45 haPercent Impervious % Imp = 2.5 %Slope S = 1.3 %
Peterborough IDF Parameters2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
a = 662 1098 1560 2010 2200 2507b = 7.5 10.1 13.0 14.0 14.6 14.8c = 0.79 0.83 0.86 0.88 0.87 0.88
Development Area C-value Tc Int. FlowCondition (ha) (min) (mm/hr) (m3/s)
25 mm Storm 39.45 0.22 157 8.55 0.202 Year 39.45 0.22 157 11.74 0.285 Year 39.45 0.22 157 15.66 0.3710 Year 39.45 0.22 157 18.81 0.4525 Year 39.45 0.24 157 21.75 0.5750 Year 39.45 0.26 157 24.99 0.71
100 Year 39.45 0.27 157 27.02 0.80
Notes :
1. Rainfall intensity rainfall data obtained for Peterborough2. For storms having return period of more than 10 years the runoff coefficient was increased as follows to a maximum value of 0.95.
25 yr: add 10%50 yr: add 20%
100 yr: add 25%
3. IDF parameters for the 25 mm storm: a: 405b: 3.0c: 0.76
Rational Method for WS 103 Sheet 2 of 4
Hydrology Calculations WS 103
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.205 0.34
10 0.4825 0.6150 0.80100 0.91 0.88 0.91 0.90
Regional 1.94
Notes:
1. Storm used to determine peak flow values 6hr AES
Visual Otthymo Model for WS 103 Sheet 3 of 4
Design Storm (yr) 1hr AES 6hr AES 12hr AES 12hr SCS 24hr SCS Timmins
Hydrology Calculations WS 103
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.28 0.205 0.37 0.3410 0.45 0.4825 0.57 0.6150 0.71 0.80
100 0.80 0.91Check 0.80 0.91
Regional 1.94
Notes:
1. Method used to determine the peak flows values Visual Otthymo
Sheet 4 of 4Peak Flow Comparison for WS 103
Design Storm (yr) Rational Method Visual Otthymo
Hydrology Calculations WS 103
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2.17 1.16 ha Gauging Station = Peterborough0.00 0.00 ha 100 Yr Rainfall depth = 90.4 mm0.00 0.00 ha0.91 0.35 ha0.72 1.84 ha Drainage Area 7.47 ha0.00 0.00 ha Impervious Area 0.33 ha0.03 0.30 ha Percent Impervious 4.4 %
3.83 3.65Pervious
B AB Length 500 mUS Elev 218.0 mDS Elev 215.0 m
0.18 0.18 Slope 0.6 %CN (Nashyd) 65.8 59.7 Flat
Incl. Not Incl.Agriculture Range Grass Woods Wetland Imperv. Imperv. Imperv.
Nashyd StandhydB 0.26 0.14 0.08 0.08 0.05 0.76 0.90 0.18
AB 0.22 0.12 0.07 0.07 0.05 0.67 0.90 0.18
B 74 65 61 58 50 91 98 65.8 65.6AB 70 51 50 44 50 89 98 59.7 56.3
500 mAverage Slope 0.6 % Drainage Area 7.47 ha
Airport 79.5 min. Runoff Coefficient Bransby - Williams 25.8 min. SCS Curve No. 62.8 61.0
Uplands - min. 64.8 62.853.3 min. 7.9 8.10.89 hr.
Notes:1. Hydrologic Soil Group obtained from Design Chart H2-6A, M.T.O. Drainage Manual, 1980.2. Runoff coefficient obtained from M.T.O. Design Chart 1.07, M.T.O. Drainage Management Manual, 1997, Hydrologic Analysis and Design, McCuen 2004 and New Jersey Technical Manual for Stream Encroachment, 1984.3. SCS Curve No. obtained from M.T.O. Design Chart 1.09, M.T.O. Drainage Management Manual, 1997, and Table 2-2a, TR-55, page 2-5.4. The modified curve number is adjusted as per Paul Wisner & Associates (1982) and represents anticedent moisture conditions Type II5. Initial Abstraction values taken from the Environmental and Engineering Services Department, The Corporation of the City of London, Dec 20056. Use Airport Equation to calculate time of concentration for C 0.4.5. Minimum Time to Peak for use in the Rational Method and Hydrologic Model is 10 minutes
Hydrologic Parameters for WS 104 Sheet 1 of 4
Agriculture
Land Use Rainfall Data
Range
Bare Earth (>70% Rock)Impervious
SUM
Hydrologic Soil Group1
Soil Type Otonabee LoamFoxboro Silt
Loam
GrassWoods
Wetland
Runoff Coefficient2, C n.a.
SCS Curve No.3, CN
C
Parameter
Land Use Weighted Value
Bare Earth (>70% Rock)
2.5 2 7.9 8.1
Time of Concentration6 Composite Parameters
Initial Abstraction5, mm 6 8 5 10 10
Total Length
0.18
Modified Curve No.4, CN*
Time to Peak7Initial Abstraction.
Flat: 0-2% SlopesRolling: 2-6% SlopesHilly: >6% Slopes
Hydrology Calculations WS 104
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
Drainage Area A = 7.47 haPercent Impervious % Imp = 4.4 %Slope S = 0.6 %
Peterborough IDF Parameters2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
a = 662 1098 1560 2010 2200 2507b = 7.5 10.1 13.0 14.0 14.6 14.8c = 0.79 0.83 0.86 0.88 0.87 0.88
Development Area C-value Tc Int. FlowCondition (ha) (min) (mm/hr) (m3/s)
25 mm Storm 7.47 0.18 79 14.16 0.052 Year 7.47 0.18 79 19.44 0.075 Year 7.47 0.18 79 26.32 0.1010 Year 7.47 0.18 79 31.79 0.1225 Year 7.47 0.20 79 37.06 0.1550 Year 7.47 0.21 79 42.22 0.19
100 Year 7.47 0.22 79 45.88 0.21
Notes :
1. Rainfall intensity rainfall data obtained for Peterborough2. For storms having return period of more than 10 years the runoff coefficient was increased as follows to a maximum value of 0.95.
25 yr: add 10%50 yr: add 20%
100 yr: add 25%
3. IDF parameters for the 25 mm storm: a: 405b: 3.0c: 0.76
Rational Method for WS 104 Sheet 2 of 4
Hydrology Calculations WS 104
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.045 0.08
10 0.1125 0.1550 0.19100 0.22 0.20 0.23 0.22
Regional 0.40
Notes:
1. Storm used to determine peak flow values 6hr AES
Visual Otthymo Model for WS 104 Sheet 3 of 4
Design Storm (yr) 1hr AES 6hr AES 12hr AES 12hr SCS 24hr SCS Timmins
Hydrology Calculations WS 104
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.07 0.045 0.10 0.0810 0.12 0.1125 0.15 0.1550 0.19 0.19
100 0.21 0.22Check 0.21 0.22
Regional 0.40
Notes:
1. Method used to determine the peak flows values Visual Otthymo
Sheet 4 of 4Peak Flow Comparison for WS 104
Design Storm (yr) Rational Method Visual Otthymo
Hydrology Calculations WS 104
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
3.56 1.83 ha Gauging Station = Peterborough0.00 0.00 ha 100 Yr Rainfall depth = 90.4 mm0.00 0.00 ha0.12 0.27 ha0.00 3.17 ha Drainage Area 9.59 ha0.00 0.00 ha Impervious Area 0.64 ha0.33 0.31 ha Percent Impervious 6.7 %
4.01 5.58Pervious
B AB Length 600 mUS Elev 217.0 mDS Elev 215.0 m
0.31 0.15 Slope 0.3 %CN (Nashyd) 75.5 58.9 Flat
Incl. Not Incl.Agriculture Range Grass Woods Wetland Imperv. Imperv. Imperv.
Nashyd StandhydB 0.26 0.14 0.08 0.08 0.05 0.76 0.90 0.31
AB 0.22 0.12 0.07 0.07 0.05 0.67 0.90 0.15
B 74 65 61 58 50 91 98 75.5 73.5AB 70 51 50 44 50 89 98 58.9 56.6
600 mAverage Slope 0.3 % Drainage Area 9.59 ha
Airport 101.2 min. Runoff Coefficient Bransby - Williams 34.0 min. SCS Curve No. 65.9 63.7
Uplands - min. 68.7 66.167.8 min. 7.2 7.61.13 hr.
Notes:1. Hydrologic Soil Group obtained from Design Chart H2-6A, M.T.O. Drainage Manual, 1980.2. Runoff coefficient obtained from M.T.O. Design Chart 1.07, M.T.O. Drainage Management Manual, 1997, Hydrologic Analysis and Design, McCuen 2004 and New Jersey Technical Manual for Stream Encroachment, 1984.3. SCS Curve No. obtained from M.T.O. Design Chart 1.09, M.T.O. Drainage Management Manual, 1997, and Table 2-2a, TR-55, page 2-5.4. The modified curve number is adjusted as per Paul Wisner & Associates (1982) and represents anticedent moisture conditions Type II5. Initial Abstraction values taken from the Environmental and Engineering Services Department, The Corporation of the City of London, Dec 20056. Use Airport Equation to calculate time of concentration for C 0.4.5. Minimum Time to Peak for use in the Rational Method and Hydrologic Model is 10 minutes
Hydrologic Parameters for WS 105 Sheet 1 of 4
Agriculture
Land Use Rainfall Data
Range
Bare Earth (>70% Rock)Impervious
SUM
Hydrologic Soil Group1
Soil Type Otonabee LoamFoxboro Silt
Loam
GrassWoods
Wetland
Runoff Coefficient2, C n.a.
SCS Curve No.3, CN
C
Parameter
Land Use Weighted Value
Bare Earth (>70% Rock)
2.5 2 7.2 7.6
Time of Concentration6 Composite Parameters
Initial Abstraction5, mm 6 8 5 10 10
Total Length
0.22
Modified Curve No.4, CN*
Time to Peak7Initial Abstraction.
Flat: 0-2% SlopesRolling: 2-6% SlopesHilly: >6% Slopes
Hydrology Calculations WS 105
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
Drainage Area A = 9.59 haPercent Impervious % Imp = 6.7 %Slope S = 0.3 %
Peterborough IDF Parameters2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
a = 662 1098 1560 2010 2200 2507b = 7.5 10.1 13.0 14.0 14.6 14.8c = 0.79 0.83 0.86 0.88 0.87 0.88
Development Area C-value Tc Int. FlowCondition (ha) (min) (mm/hr) (m3/s)
25 mm Storm 9.59 0.22 101 11.85 0.072 Year 9.59 0.22 101 16.30 0.095 Year 9.59 0.22 101 21.98 0.1310 Year 9.59 0.22 101 26.51 0.1525 Year 9.59 0.24 101 30.84 0.2050 Year 9.59 0.26 101 35.23 0.25
100 Year 9.59 0.27 101 38.23 0.28
Notes :
1. Rainfall intensity rainfall data obtained for Peterborough2. For storms having return period of more than 10 years the runoff coefficient was increased as follows to a maximum value of 0.95.
25 yr: add 10%50 yr: add 20%
100 yr: add 25%
3. IDF parameters for the 25 mm storm: a: 405b: 3.0c: 0.76
Rational Method for WS 105 Sheet 2 of 4
Hydrology Calculations WS 105
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.065 0.10
10 0.1425 0.1850 0.24100 0.28 0.26 0.28 0.27
Regional 0.50
Notes:
1. Storm used to determine peak flow values 6hr AES
Visual Otthymo Model for WS 105 Sheet 3 of 4
Design Storm (yr) 1hr AES 6hr AES 12hr AES 12hr SCS 24hr SCS Timmins
Hydrology Calculations WS 105
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.09 0.065 0.13 0.1010 0.15 0.1425 0.20 0.1850 0.25 0.24
100 0.28 0.28Check 0.28 0.28
Regional 0.50
Notes:
1. Method used to determine the peak flows values Visual Otthymo
Sheet 4 of 4Peak Flow Comparison for WS 105
Design Storm (yr) Rational Method Visual Otthymo
Hydrology Calculations WS 105
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
0.12 0.44 ha Gauging Station = Peterborough0.00 0.00 ha 100 Yr Rainfall depth = 90.4 mm0.00 0.00 ha0.01 1.08 ha0.00 0.36 ha Drainage Area 2.52 ha0.00 0.00 ha Impervious Area 0.51 ha0.09 0.42 ha Percent Impervious 20.4 %
0.22 2.30Pervious Impervious
B AB Length 250 105 mUS Elev 218.0 214.5 mDS Elev 214.5 214.0 m
0.52 0.24 Slope 1.4 0.5 %CN (Standhyd) 72.5 51.2 Flat Flat
Incl. Not Incl.Agriculture Range Grass Woods Wetland Imperv. Imperv. Imperv.
Nashyd StandhydB 0.26 0.14 0.08 0.08 0.05 0.76 0.90 0.52
AB 0.22 0.12 0.07 0.07 0.05 0.67 0.90 0.24
B 74 65 61 58 50 91 98 83.3 72.5AB 70 51 50 44 50 89 98 59.8 51.2
355 mAverage Slope 1.1 % Drainage Area 2.52 ha
Airport 49.1 min. Runoff Coefficient Bransby - Williams 18.0 min. SCS Curve No. 61.8 53.1
Uplands - min. 63.3 54.232.9 min. 7.5 8.90.55 hr.
Notes:1. Hydrologic Soil Group obtained from Design Chart H2-6A, M.T.O. Drainage Manual, 1980.2. Runoff coefficient obtained from M.T.O. Design Chart 1.07, M.T.O. Drainage Management Manual, 1997, Hydrologic Analysis and Design, McCuen 2004 and New Jersey Technical Manual for Stream Encroachment, 1984.3. SCS Curve No. obtained from M.T.O. Design Chart 1.09, M.T.O. Drainage Management Manual, 1997, and Table 2-2a, TR-55, page 2-5.4. The modified curve number is adjusted as per Paul Wisner & Associates (1982) and represents anticedent moisture conditions Type II5. Initial Abstraction values taken from the Environmental and Engineering Services Department, The Corporation of the City of London, Dec 20056. Use Airport Equation to calculate time of concentration for C 0.4.5. Minimum Time to Peak for use in the Rational Method and Hydrologic Model is 10 minutes
Hydrologic Parameters for WS 106 Sheet 1 of 4
Agriculture
Land Use Rainfall Data
Range
Bare Earth (>70% Rock)Impervious
SUM
Hydrologic Soil Group1
Soil Type Otonabee LoamFoxboro Silt
Loam
GrassWoods
Wetland
Runoff Coefficient2, C n.a.
SCS Curve No.3, CN
C
Parameter
Land Use Weighted Value
Bare Earth (>70% Rock)
2.5 2 7.5 8.9
Time of Concentration6 Composite Parameters
Initial Abstraction5, mm 6 8 5 10 10
Total Length
0.27
Modified Curve No.4, CN*
Time to Peak7Initial Abstraction.
Flat: 0-2% SlopesRolling: 2-6% SlopesHilly: >6% Slopes
Hydrology Calculations WS 106
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
Drainage Area A = 2.52 haPercent Impervious % Imp = 20.4 %Slope S = 1.4 %
Peterborough IDF Parameters2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
a = 662 1098 1560 2010 2200 2507b = 7.5 10.1 13.0 14.0 14.6 14.8c = 0.79 0.83 0.86 0.88 0.87 0.88
Development Area C-value Tc Int. FlowCondition (ha) (min) (mm/hr) (m3/s)
25 mm Storm 2.52 0.27 49 20.08 0.042 Year 2.52 0.27 49 27.31 0.055 Year 2.52 0.27 49 37.13 0.0710 Year 2.52 0.27 49 44.79 0.0825 Year 2.52 0.30 49 52.40 0.1150 Year 2.52 0.32 49 59.29 0.13
100 Year 2.52 0.34 49 64.64 0.15
Notes :
1. Rainfall intensity rainfall data obtained for Peterborough2. For storms having return period of more than 10 years the runoff coefficient was increased as follows to a maximum value of 0.95.
25 yr: add 10%50 yr: add 20%
100 yr: add 25%
3. IDF parameters for the 25 mm storm: a: 405b: 3.0c: 0.76
Rational Method for WS 106 Sheet 2 of 4
Hydrology Calculations WS 106
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.025 0.03
10 0.0425 0.0550 0.06100 0.07 0.06 0.79 0.07
Regional 0.12
Notes:
1. Storm used to determine peak flow values 6hr AES
Visual Otthymo Model for WS 106 Sheet 3 of 4
Design Storm (yr) 1hr AES 6hr AES 12hr AES 12hr SCS 24hr SCS Timmins
Hydrology Calculations WS 106
-
Project No: 15-10706Project Name: Peterborough Rec Center
Designed/Checked By: CH / DGDate: 19-Feb-16
2 0.05 0.025 0.07 0.0310 0.08 0.0425 0.11 0.0550 0.13 0.06
100 0.15 0.07Check 0.15 0.07
Regional 0.12
Notes:
1. Method used to determine the peak flows values Visual Otthymo
Sheet 4 of 4Peak Flow Comparison for WS 106
Design Storm (yr) Rational Method Visual Otthymo
Hydrology Calculations WS 106
-
DE7 L¾
DE7
DE7L¾
ÝÝ
ÝÝ
ÝÝ
ÝÝ
ÝÝ
ÝÝ
ÝÝ
ÝÝ
ÝÝ
ÝÝ ÝÝ
ÝÝÝÝ
ÝÝ
ÝÝ ÝÝ
ÝÝ
ÝÝ
ÝÝ
Lansdow
ne St E
Parkhill Rd
W
Sherbroo
ke St
Charlotte
St
Parkhill R
d E
Park St S
Hunter St E
Ashburnham D
r
Reid S
t
Rubidge StP
a rkS
t N
Lansdown
e St W
Hunter St W
Sir Sandford FlemingDr
7 Hy
Chemong Rd
The
Quee
nswa
y
Bensfort Rd
George
St S
Aylmer St S
Fairbairn St
Hill ia rd
St
McDonne
l St
Carnegie Av
Cumberla
nd Av
Riv
er R
d S
Aylme r S
t N
Mar
ia St
Brealey Dr
Crawford
Dr
Towerh
ill Rd
Pioneer R
d
Airport Rd
Kennedy R
d
Lily Lake
Rd
University R
d
Monaghan R
d
Wat
erSt
George St N
Clon
silla
Av
Nassau Mills R
d
The Parkway
Television Rd
Johnston
Dr
Wallis D
r
McCle
nnan
StH
igh St
Goodfellow
Rd
Glenfo
rest B
v
Irelan
d
Dr
Weller S
t
Erskine Av
Maria St
Park St N
Westridge Bv
Sunse
t Bv
Woodglade Bv
Rogers St
Wolse
ly St
Kaw
arth
a
Heights Bv
Albert St
The
King
sway
Burnham St
McKellar
St
Dumb
le Av
S outhlawn Dr
Braidwood
Av
Hawley S
t
Romaine
St
Spillsbury Dr
McFarlan
e St
Forster A
v
Denure D
r
Wal
ker
Av
Marin
a Bv
Towerh
ill Rd
Oto
nabe
e D
r
Chamberla
in St
Stens
onBv
Bethune St
Highla
nd Rd
Heritage
Tl
Cherryhill
Rd
Old Norwo
od Rd
Neal Dr
Cameron
StRye S
t
Webber Av
McN
amara R
d
Maniece
Av
Ash
burn
ham
Dr
Barnardo Av
Lock St
Park St S
Fisher D
r
Rav
enw
ood
Dr
Guthrie D
r
Roy
alDr
Fra
nklin
Dr
Fair Av
Mar
sdale
Dr
Fairmount Bv
Frances
Stew
art R
d
Het
he
ringto
n
Dr
Milroy Dr
Harper R
d
Chan
dler Cres
Tech
nolog
y Dr
11
21
39
35
15
5
9
3
27
12 12
1819
24
2932
4
41
4
Oton
abee
Rive
rOt
onab
ee R
iver
Little Lake
Park St S
Lansdown
e St W 0 1.250.25 0.5 0.75 1
Miles
0 0.4 0.8 1.2 1.6 2Kilometres
Produced by:Geomatics/Mapping Division,City of Peterborougth 2015
Last Revised:August 31, 2015
μ
Map Accuracy and Interpretation:The information depicted on this hardcopyor digital map file is schematic in nature.Accurate interpretation of informationshown should be obtained fromappropriate City Planning staff.
The City of Peterborough Official Plan- Schedule A -
Land UseLegend
Residential
Agriculture
Commercial
Commercial (Otonabee)
Industrial
Industrial (Otonabee
Major Institution
Major Open Space
Protected Natural Area
Rural (Otonabee)
Village (Otonabee)
Hamlet (OSM*)
Urban Fringe Control Area (Smith)
Environmental Constraint (SEL**)
Environmental Protection (OSM*)
Employment Areas (OSM*)
OSM = Otonabee-South MonaghanSEL = Smith-Ennismore-LakefiledSee Section 10.9.3.2.4
******
Lily Lake
Rd
Detail A
Detail B
Details A and B not to scale
See Detail A
See Detail B
***
-
AcademicCore
AcademicCore
Water
St
Wat
er St
Water
St
Nassa
u Mills
Rd
Nassa
u Mills
Rd
East Bank Dr
West Bank Dr
Nassau Mills Rd
Pioneer Rd
HEPC
HEPC
Woodland D
r
University Rd
9th Line
Armou
r Rd
OtonabeeRiver
TrentCanal
2D
2F
2C
1C
1B
4F
4G
1E
1G
2A
2B
2E
3A
1A
4D
4E
4B
3B
4A
3D
3C
4A
1F
F
G
D
E
B
C
A
Natural Areas (as per Endowment Lands Master Plan, 2006)
Expanded Natural Areas (identified through the Trent Lands Plan, 2013)
Green Buffers and Corridors
Open Space
Existing/Potential Play Fields
Endowment Lands Parcel(as per Endowment Lands Master Plan, 2006)
Potential Special Use Area
University Function
Research Park
Employment
Mixed Use/Medium Density
Medium Density
Low Density
Other Research/Utility & Future Potential Uses
Experimental Farm
Existing Trails
Potential Trails
Existing Streets
Potential Streets
Existing Campus Buildings & Infrastructure
ORCA Development Control Area
Option for University/Cultural/Arena/Conference
University/Cultural/Conference
Cultural/Conference/Hospitality/Residence
University/Cultural/Conference
Cultural/Conference/Hospitality/Residence
Arena or Residential
Residential
Legend
0 100 200 300 400 500m
Land Use Framework PlanMay 2013
N
4A
A
A
B
C
D
E
F
G
Special Use Areas
-
Visual OTTHYMO Model Layout
Regulatory Floodplain Assessment Report
City of Peterborough Recreation Centre at Trent University
D.M. Wills Project No. 15-10706
-
===========================================================================================================
V V I SSSSS U U A L V V I SS U U A A L V V I SS U U AAAAA L V V I SS U U A A L VV I SSSSS UUUUU A A LLLLL
OOO TTTTT TTTTT H H Y Y M M OOO TM O O T T H H Y Y MM MM O O O O T T H H Y M M O O OOO T T H H Y M M OOODeveloped and Distributed by Civica InfrastructureCopyright 2007 - 2013 Civica InfrastructureAll rights reserved.
***** D E T A I L E D O U T P U T *****
Input filename: C:\Program Files (x86)\VO Suite 3.0\VO2\voin.dat Output filename: C:\Users\dgreen\Local Settings\Temp\a7a166e8-e0eb-46d1-bcf0-8d7adcf15c11\Scenario.out Summary filename: C:\Users\dgreen\Local Settings\Temp\a7a166e8-e0eb-46d1-bcf0-8d7adcf15c11\Scenario.sum
DATE: 06/16/2016 TIME: 04:50:56
USER:
COMMENTS: ____________________________________________________________
----------------------------------------------------------------------------------------------------------- **************************** ** SIMULATION NUMBER: 1 ** ****************************
--------------------| READ STORM | Filename: C:\Users\dgreen\Local | | Settings\Temp\ | | a7a166e8-e0eb-46d1-bcf0-8d7adcf15c11\bc99a22d| Ptotal= 81.73 mm | Comments: 100 Year, 6-hour AES Distribution, Peter-------------------- TIME RAIN | TIME RAIN |' TIME RAIN | TIME RAIN hrs mm/hr | hrs mm/hr |' hrs mm/hr | hrs mm/hr 0.50 1.63 | 2.00 27.79 | 3.50 11.44 | 5.00 1.63 1.00 1.63 | 2.50 75.02 | 4.00 6.54 | 5.50 1.63 1.50 9.81 | 3.00 21.25 | 4.50 3.27 | 6.00 1.80
-------------------------------------------------------------------------------
--------------------| CALIB || NASHYD (0101) | Area (ha)= 163.91 Curve Number (CN)= 72.5|ID= 1 DT= 5.0 min | Ia (mm)= 6.70 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 2.32
NOTE: RAINFALL WAS TRANSFORMED TO 5.0 MIN. TIME STEP.
---- TRANSFORMED HYETOGRAPH ---- TIME RAIN | TIME RAIN |' TIME RAIN | TIME RAIN hrs mm/hr | hrs mm/hr |' hrs mm/hr | hrs mm/hr 0.083 1.63 | 1.583 27.79 | 3.083 11.44 | 4.58 1.63 0.167 1.63 | 1.667 27.79 | 3.167 11.44 | 4.67 1.63 0.250 1.63 | 1.750 27.79 | 3.250 11.44 | 4.75 1.63 0.333 1.63 | 1.833 27.79 | 3.333 11.44 | 4.83 1.63 0.417 1.63 | 1.917 27.79 | 3.417 11.44 | 4.92 1.63 0.500 1.63 | 2.000 27.79 | 3.500 11.44 | 5.00 1.63 0.583 1.63 | 2.083 75.02 | 3.583 6.54 | 5.08 1.63 0.667 1.63 | 2.167 75.02 | 3.667 6.54 | 5.17 1.63 0.750 1.63 | 2.250 75.02 | 3.750 6.54 | 5.25 1.63 0.833 1.63 | 2.333 75.02 | 3.833 6.54 | 5.33 1.63 0.917 1.63 | 2.417 75.02 | 3.917 6.54 | 5.42 1.63 1.000 1.63 | 2.500 75.02 | 4.000 6.54 | 5.50 1.63 1.083 9.81 | 2.583 21.25 | 4.083 3.27 | 5.58 1.80 1.167 9.81 | 2.667 21.25 | 4.167 3.27 | 5.67 1.80 1.250 9.81 | 2.750 21.25 | 4.250 3.27 | 5.75 1.80 1.333 9.81 | 2.833 21.25 | 4.333 3.27 | 5.83 1.80 1.417 9.81 | 2.917 21.25 | 4.417 3.27 | 5.92 1.80 1.500 9.81 | 3.000 21.25 | 4.500 3.27 | 6.00 1.80
Unit Hyd Qpeak (cms)= 2.699
PEAK FLOW (cms)= 3.085 (i) TIME TO PEAK (hrs)= 5.083 RUNOFF VOLUME (mm)= 32.847 TOTAL RAINFALL (mm)= 81.726 RUNOFF COEFFICIENT = 0.402
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0103) | Area (ha)= 39.45 Curve Number (CN)= 71.9|ID= 1 DT= 5.0 min | Ia (mm)= 7.00 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 1.76
Unit Hyd Qpeak (cms)= 0.856
PEAK FLOW (cms)= 0.906 (i) TIME TO PEAK (hrs)= 4.500 RUNOFF VOLUME (mm)= 32.093 TOTAL RAINFALL (mm)= 81.726 RUNOFF COEFFICIENT = 0.393
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0012) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0101): 163.91 3.085 5.08 32.85 + ID2= 2 (0103): 39.45 0.906 4.50 32.09 ================================================== ID = 3 (0012): 203.36 3.944 4.92 32.70
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0102) | Area (ha)= 91.79 Curve Number (CN)= 73.0|ID= 1 DT= 5.0 min | Ia (mm)= 6.40 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 1.52
Unit Hyd Qpeak (cms)= 2.307
PEAK FLOW (cms)= 2.463 (i) TIME TO PEAK (hrs)= 4.167 RUNOFF VOLUME (mm)= 33.520 TOTAL RAINFALL (mm)= 81.726 RUNOFF COEFFICIENT = 0.410
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0104) | Area (ha)= 7.47 Curve Number (CN)= 64.8|ID= 1 DT= 5.0 min | Ia (mm)= 7.90 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 0.89
Unit Hyd Qpeak (cms)= 0.321
PEAK FLOW (cms)= 0.221 (i) TIME TO PEAK (hrs)= 3.500 RUNOFF VOLUME (mm)= 25.733 TOTAL RAINFALL (mm)= 81.726 RUNOFF COEFFICIENT = 0.315
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0008) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0102): 91.79 2.463 4.17 33.52 + ID2= 2 (0104): 7.47 0.221 3.50 25.73 ==================================================
-
ID = 3 (0008): 99.26 2.640 4.17 32.93
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0008) || 3 + 2 = 1 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 3 (0008): 99.26 2.640 4.17 32.93 + ID2= 2 (0012): 203.36 3.944 4.92 32.70 ================================================== ID = 1 (0008): 302.62 6.376 4.58 32.78
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0105) | Area (ha)= 9.59 Curve Number (CN)= 68.7|ID= 1 DT= 5.0 min | Ia (mm)= 7.20 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 1.13
Unit Hyd Qpeak (cms)= 0.324
PEAK FLOW (cms)= 0.276 (i) TIME TO PEAK (hrs)= 3.750 RUNOFF VOLUME (mm)= 29.194 TOTAL RAINFALL (mm)= 81.726 RUNOFF COEFFICIENT = 0.357
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0010) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0105): 9.59 0.276 3.75 29.19 + ID2= 2 (0008): 302.62 6.376 4.58 32.78 ================================================== ID = 3 (0010): 312.21 6.601 4.50 32.67
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || STANDHYD (0106) | Area (ha)= 2.52|ID= 1 DT= 5.0 min | Total Imp(%)= 20.40 Dir. Conn.(%)= 10.20-------------------- IMPERVIOUS PERVIOUS (i) Surface Area (ha)= 0.51 2.01 Dep. Storage (mm)= 1.00 8.90 Average Slope (%)= 0.50 1.40 Length (m)= 105.00 250.00 Mannings n = 0.013 0.250
Max.Eff.Inten.(mm/hr)= 75.02 16.81 over (min) 5.00 55.00 Storage Coeff. (min)= 3.63 (ii) 51.76 (ii) Unit Hyd. Tpeak (min)= 5.00 55.00 Unit Hyd. peak (cms)= 0.25 0.02 *TOTALS* PEAK FLOW (cms)= 0.05 0.06 0.069 (iii) TIME TO PEAK (hrs)= 2.50 3.33 2.50 RUNOFF VOLUME (mm)= 80.73 20.64 26.76 TOTAL RAINFALL (mm)= 81.73 81.73 81.73 RUNOFF COEFFICIENT = 0.99 0.25 0.33
***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP!***** WARNING:FOR AREAS WITH IMPERVIOUS RATIOS BELOW 20% YOU SHOULD CONSIDER SPLITTING THE AREA.
(i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 54.2 Ia = Dep. Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0011) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0010): 312.21 6.601 4.50 32.67 + ID2= 2 (0106): 2.52 0.069 2.50 26.76 ================================================== ID = 3 (0011): 314.73 6.637 4.50 32.62
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
------------------------------------------------------------------------------- **************************** ** SIMULATION NUMBER: 2 ** ****************************
--------------------| READ STORM | Filename: C:\Users\dgreen\Local | | Settings\Temp\ | | a7a166e8-e0eb-46d1-bcf0-8d7adcf15c11\a6d7c713| Ptotal= 90.39 mm | Comments: 100 Year, 12-hour AES Distribution, Pete-------------------- TIME RAIN | TIME RAIN |' TIME RAIN | TIME RAIN hrs mm/hr | hrs mm/hr |' hrs mm/hr | hrs mm/hr 1.00 0.90 | 4.00 15.37 | 7.00 6.33 | 10.00 0.90 2.00 0.90 | 5.00 41.58 | 8.00 3.62 | 11.00 0.90 3.00 5.42 | 6.00 11.75 | 9.00 1.81 | 12.00 0.90
-------------------------------------------------------------------------------
--------------------| CALIB || NASHYD (0101) | Area (ha)= 163.91 Curve Number (CN)= 72.5|ID= 1 DT= 5.0 min | Ia (mm)= 6.70 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 2.32
NOTE: RAINFALL WAS TRANSFORMED TO 5.0 MIN. TIME STEP.
---- TRANSFORMED HYETOGRAPH ---- TIME RAIN | TIME RAIN |' TIME RAIN | TIME RAIN hrs mm/hr | hrs mm/hr |' hrs mm/hr | hrs mm/hr 0.083 0.90 | 3.083 15.37 | 6.083 6.33 | 9.08 0.90 0.167 0.90 | 3.167 15.37 | 6.167 6.33 | 9.17 0.90 0.250 0.90 | 3.250 15.37 | 6.250 6.33 | 9.25 0.90 0.333 0.90 | 3.333 15.37 | 6.333 6.33 | 9.33 0.90 0.417 0.90 | 3.417 15.37 | 6.417 6.33 | 9.42 0.90 0.500 0.90 | 3.500 15.37 | 6.500 6.33 | 9.50 0.90 0.583 0.90 | 3.583 15.37 | 6.583 6.33 | 9.58 0.90 0.667 0.90 | 3.667 15.37 | 6.667 6.33 | 9.67 0.90 0.750 0.90 | 3.750 15.37 | 6.750 6.33 | 9.75 0.90 0.833 0.90 | 3.833 15.37 | 6.833 6.33 | 9.83 0.90 0.917 0.90 | 3.917 15.37 | 6.917 6.33 | 9.92 0.90 1.000 0.90 | 4.000 15.37 | 7.000 6.33 | 10.00 0.90 1.083 0.90 | 4.083 41.58 | 7.083 3.62 | 10.08 0.90 1.167 0.90 | 4.167 41.58 | 7.167 3.62 | 10.17 0.90 1.250 0.90 | 4.250 41.58 | 7.250 3.62 | 10.25 0.90 1.333 0.90 | 4.333 41.58 | 7.333 3.62 | 10.33 0.90 1.417 0.90 | 4.417 41.58 | 7.417 3.62 | 10.42 0.90 1.500 0.90 | 4.500 41.58 | 7.500 3.62 | 10.50 0.90 1.583 0.90 | 4.583 41.58 | 7.583 3.62 | 10.58 0.90 1.667 0.90 | 4.667 41.58 | 7.667 3.62 | 10.67 0.90 1.750 0.90 | 4.750 41.58 | 7.750 3.62 | 10.75 0.90 1.833 0.90 | 4.833 41.58 | 7.833 3.62 | 10.83 0.90 1.917 0.90 | 4.917 41.58 | 7.917 3.62 | 10.92 0.90 2.000 0.90 | 5.000 41.58 | 8.000 3.62 | 11.00 0.90 2.083 5.42 | 5.083 11.75 | 8.083 1.81 | 11.08 0.90 2.167 5.42 | 5.167 11.75 | 8.167 1.81 | 11.17 0.90 2.250 5.42 | 5.250 11.75 | 8.250 1.81 | 11.25 0.90 2.333 5.42 | 5.333 11.75 | 8.333 1.81 | 11.33 0.90 2.417 5.42 | 5.417 11.75 | 8.417 1.81 | 11.42 0.90 2.500 5.42 | 5.500 11.75 | 8.500 1.81 | 11.50 0.90 2.583 5.42 | 5.583 11.75 | 8.583 1.81 | 11.58 0.90 2.667 5.42 | 5.667 11.75 | 8.667 1.81 | 11.67 0.90 2.750 5.42 | 5.750 11.75 | 8.750 1.81 | 11.75 0.90 2.833 5.42 | 5.833 11.75 | 8.833 1.81 | 11.83 0.90 2.917 5.42 | 5.917 11.75 | 8.917 1.81 | 11.92 0.90 3.000 5.42 | 6.000 11.75 | 9.000 1.81 | 12.00 0.90
Unit Hyd Qpeak (cms)= 2.699
PEAK FLOW (cms)= 3.113 (i) TIME TO PEAK (hrs)= 7.583
-
RUNOFF VOLUME (mm)= 38.902 TOTAL RAINFALL (mm)= 90.387 RUNOFF COEFFICIENT = 0.430
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0103) | Area (ha)= 39.45 Curve Number (CN)= 71.9|ID= 1 DT= 5.0 min | Ia (mm)= 7.00 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 1.76
Unit Hyd Qpeak (cms)= 0.856
PEAK FLOW (cms)= 0.883 (i) TIME TO PEAK (hrs)= 6.833 RUNOFF VOLUME (mm)= 38.068 TOTAL RAINFALL (mm)= 90.387 RUNOFF COEFFICIENT = 0.421
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0012) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0101): 163.91 3.113 7.58 38.90 + ID2= 2 (0103): 39.45 0.883 6.83 38.07 ================================================== ID = 3 (0012): 203.36 3.952 7.42 38.74
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0102) | Area (ha)= 91.79 Curve Number (CN)= 73.0|ID= 1 DT= 5.0 min | Ia (mm)= 6.40 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 1.52
Unit Hyd Qpeak (cms)= 2.307
PEAK FLOW (cms)= 2.358 (i) TIME TO PEAK (hrs)= 6.500 RUNOFF VOLUME (mm)= 39.643 TOTAL RAINFALL (mm)= 90.387 RUNOFF COEFFICIENT = 0.439
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0104) | Area (ha)= 7.47 Curve Number (CN)= 64.8|ID= 1 DT= 5.0 min | Ia (mm)= 7.90 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 0.89
Unit Hyd Qpeak (cms)= 0.321
PEAK FLOW (cms)= 0.202 (i) TIME TO PEAK (hrs)= 5.750 RUNOFF VOLUME (mm)= 30.863 TOTAL RAINFALL (mm)= 90.387 RUNOFF COEFFICIENT = 0.341
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0008) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0102): 91.79 2.358 6.50 39.64 + ID2= 2 (0104): 7.47 0.202 5.75 30.86 ================================================== ID = 3 (0008): 99.26 2.524 6.50 38.98
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0008) || 3 + 2 = 1 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 3 (0008): 99.26 2.524 6.50 38.98 + ID2= 2 (0012): 203.36 3.952 7.42 38.74 ================================================== ID = 1 (0008): 302.62 6.271 7.00 38.82
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || NASHYD (0105) | Area (ha)= 9.59 Curve Number (CN)= 68.7|ID= 1 DT= 5.0 min | Ia (mm)= 7.20 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 1.13
Unit Hyd Qpeak (cms)= 0.324
PEAK FLOW (cms)= 0.257 (i) TIME TO PEAK (hrs)= 6.083 RUNOFF VOLUME (mm)= 34.790 TOTAL RAINFALL (mm)= 90.387 RUNOFF COEFFICIENT = 0.385
(i) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0010) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0105): 9.59 0.257 6.08 34.79 + ID2= 2 (0008): 302.62 6.271 7.00 38.82 ================================================== ID = 3 (0010): 312.21 6.481 6.92 38.70
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
---------------------------------------------------------------------------------------------------| CALIB || STANDHYD (0106) | Area (ha)= 2.52|ID= 1 DT= 5.0 min | Total Imp(%)= 20.40 Dir. Conn.(%)= 10.20-------------------- IMPERVIOUS PERVIOUS (i) Surface Area (ha)= 0.51 2.01 Dep. Storage (mm)= 1.00 8.90 Average Slope (%)= 0.50 1.40 Length (m)= 105.00 250.00 Mannings n = 0.013 0.250
Max.Eff.Inten.(mm/hr)= 41.58 13.86 over (min) 5.00 60.00 Storage Coeff. (min)= 4.60 (ii) 56.59 (ii) Unit Hyd. Tpeak (min)= 5.00 60.00 Unit Hyd. peak (cms)= 0.23 0.02 *TOTALS* PEAK FLOW (cms)= 0.03 0.05 0.057 (iii) TIME TO PEAK (hrs)= 4.92 5.75 5.00 RUNOFF VOLUME (mm)= 89.39 24.95 31.51 TOTAL RAINFALL (mm)= 90.39 90.39 90.39 RUNOFF COEFFICIENT = 0.99 0.28 0.35
***** WARNING: STORAGE COEFF. IS SMALLER THAN TIME STEP!***** WARNING:FOR AREAS WITH IMPERVIOUS RATIOS BELOW 20% YOU SHOULD CONSIDER SPLITTING THE AREA.
(i) CN PROCEDURE SELECTED FOR PERVIOUS LOSSES: CN* = 54.2 Ia = Dep. Storage (Above) (ii) TIME STEP (DT) SHOULD BE SMALLER OR EQUAL THAN THE STORAGE COEFFICIENT. (iii) PEAK FLOW DOES NOT INCLUDE BASEFLOW IF ANY.
-------------------------------------------------------------------------------
--------------------| ADD HYD (0011) || 1 + 2 = 3 | AREA QPEAK TPEAK R.V.-------------------- (ha) (cms) (hrs) (mm) ID1= 1 (0010): 312.21 6.481 6.92 38.70
-
+ ID2= 2 (0106): 2.52 0.057 5.00 31.51 ================================================== ID = 3 (0011): 314.73 6.519 6.92 38.64
NOTE: PEAK FLOWS DO NOT INCLUDE BASEFLOWS IF ANY.
------------------------------------------------------------------------------- **************************** ** SIMULATION NUMBER: 3 ** ****************************
--------------------| READ STORM | Filename: C:\Users\dgreen\Local | | Settings\Temp\ | | a7a166e8-e0eb-46d1-bcf0-8d7adcf15c11\e84704d6| Ptotal= 90.39 mm | Comments: 100 Year, 12-hour SCS Type II Distributi-------------------- TIME RAIN | TIME RAIN |' TIME RAIN | TIME RAIN hrs mm/hr | hrs mm/hr |' hrs mm/hr | hrs mm/hr 0.50 1.81 | 3.50 3.62 | 6.50 16.27 | 9.50 3.62 1.00 1.81 | 4.00 3.62 | 7.00 7.23 | 10.00 1.81 1.50 1.81 | 4.50 5.42 | 7.50 5.42 | 10.50 1.81 2.00 1.81 | 5.00 7.23 | 8.00 5.42 | 11.00 1.81 2.50 3.62 | 5.50 10.85 | 8.50 3.62 | 11.50 1.81 3.00 3.62 | 6.00 81.35 | 9.00 3.62 | 12.00 1.81
-------------------------------------------------------------------------------
--------------------| CALIB || NASHYD (0101) | Area (ha)= 163.91 Curve Number (CN)= 72.5|ID= 1 DT= 5.0 min | Ia (mm)= 6.70 # of Linear Res.(N)= 3.00-------------------- U.H. Tp(hrs)= 2.32
NOTE: RAINFALL WAS TRANSFORMED TO 5.0 MIN. TIME STEP.
---- TRANSFORMED HYETOGRAPH ---- TIME RAIN | TIME RAIN |' TIME RAIN | TIME RAIN hrs mm/hr | hrs mm/hr |' hrs mm/hr | hrs mm/hr 0.083 1.81 | 3.083 3.62 | 6.083 16.27 | 9.08 3.62 0.167 1.81 | 3.167 3.62 | 6.167 16.27 | 9.17 3.62 0.250 1.81 | 3.250 3.62 | 6.250 16.27 | 9.25 3.62 0.333 1.81 | 3.333 3.62 | 6.333 16.27 | 9.33 3.62 0.417 1.81 | 3.417 3.62 | 6.417 16.27 | 9.42 3.62 0.500 1.81 | 3.500 3.62 | 6.500 16.27 | 9.50 3.62 0.583 1.81 | 3.583 3.62 | 6.583 7.23 | 9.58 1.81 0.667 1.81 | 3.667 3.62 | 6.667 7.23 | 9.67 1.81 0.750 1.81 | 3.750 3.62 | 6.750 7.23 | 9.75 1.81 0.833 1.81 | 3.833 3.62 | 6.833 7.23 | 9.83 1.81 0.917 1.81 | 3.917 3.62 | 6.917 7.23 | 9.92 1.81 1.000 1.81 | 4.000 3.62 | 7.000 7.23 | 10.00 1.81 1.083 1.81 | 4.083 5.42 | 7.083 5.42 | 10.08 1.81 1.167 1.81 | 4.167 5.42 | 7.167 5.42 | 10.17 1.81 1.250 1.81 | 4.250 5.42 | 7.250 5.42 | 10.25 1.81 1.333 1.81 | 4.333 5.42 | 7.333 5.42 | 10.33 1.81 1.417 1.81 | 4.417 5.42 | 7.417 5.42 | 10.42 1.81 1.500 1.81 | 4.500 5.42 | 7.500 5.42 | 10.50 1.81 1.583 1.